KR20160000364U - Fixing Structure Between Distribution Box and RC Beams During Foam Construction - Google Patents
Fixing Structure Between Distribution Box and RC Beams During Foam Construction Download PDFInfo
- Publication number
- KR20160000364U KR20160000364U KR2020140005477U KR20140005477U KR20160000364U KR 20160000364 U KR20160000364 U KR 20160000364U KR 2020140005477 U KR2020140005477 U KR 2020140005477U KR 20140005477 U KR20140005477 U KR 20140005477U KR 20160000364 U KR20160000364 U KR 20160000364U
- Authority
- KR
- South Korea
- Prior art keywords
- reinforcing bars
- reinforcing
- circumferential surfaces
- present
- wiring box
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G15/00—Forms or shutterings for making openings, cavities, slits, or channels
- E04G15/06—Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/04—Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Distribution Board (AREA)
Abstract
In the present invention, the horizontal reinforcement and the longitudinal reinforcement are fixed to each other so that the transverse reinforcement and the longitudinal reinforcement can be smoothly coupled without separate cutting and welding operations. Structure.
In order to achieve the above object, the present invention proposes a transverse fastening hole having a vertical fastening hole having a recessed groove on the upper and lower surfaces of the outer circumferential surface of the wiring box body and a horizontal fastening hole having recessed grooves on the upper and lower surfaces of the outer circumferential surface of the wiring box body, And the center of the sphere forms an interval equal to the diameter of the reinforcing bars.
In this way, it is possible to remarkably improve the efficiency of the construction work because the construction is completed simply by inserting the wiring box into the reinforcing bars in spite of the difference in position between the transverse reinforcement and the longitudinal reinforcement. It is possible to provide a high quality of construction without being deformed during concrete pouring and curing.
Description
The present invention relates to a fixing structure between a wiring box and a reinforcing bar during a formwork construction process, and particularly relates to a fixing structure between a wiring box and a reinforcing bar in a formwork construction process for easily fixing a wiring box to a reinforcing bar, To a fixed structure between the plates.
As it is known, since the main power line or communication cable of the building is installed inside the retaining wall or wall, it is distributed inside the building in order to install the overcurrent breaker, earth leakage breaker, connector, etc. connected to the power line or cable inside the retaining wall or wall. And a communication box are embedded in a retaining wall or a wall. In order to install such a wiring box, a reinforcing bar is fixed, a peripheral surface of the wiring box is fixed to the wiring box, and a mold is placed on the wiring box so that only the inside of the wiring box is exposed.
When the concrete was laid in this state, the concrete was filled in the peripheral surface except for the reinforcing bars and the front surface of the wiring box inside the formwork, so that the concrete was cured and completed in a solid state.
Therefore, such a junction box is inevitably subjected to pressure during the filling and curing process of the concrete, and it is necessary to be firmly fixed to the reinforcing bar so that the installation state is not deformed.
The conventional method of distributing panel boards includes a process of reinforcing steel frame construction, reinforcing bars and wires, fixing of panel boards, formwork installation process, wiring process, reinforcing plate installation process, concrete pouring and curing process, die removing process, .
1, a certain space is allocated for the installation of the
In the process of fixing the panel board, the
In the process of fixing the panel board, the
Further, in the process of fixing the panel, another reinforcing
On the other hand, after concrete pouring and curing process, the form is removed by the mold removal process. Therefore, the
As described above, in the conventional method of installing a distribution panel, a
In order to install the
In order to overcome such conventional problems, a Korean Registered Utility Model No. 0293405 (design name: reinforcing bar of a distribution board base; hereinafter referred to as a "citation design") has been proposed.
According to this cited design, the reinforcing bars fixing means are formed on the upper side and the lower side of the rear surface of the
As can be seen from the above, the citation design is a structure in which the reinforcing rods arranged in a longitudinal direction and the transverse direction are fixed by the
2, since the
The object of the present invention is to solve such a problem by making the positions of the transverse reinforcing bars and the longitudinal reinforcing bars different from each other in view of the fact that the respective vertical surfaces formed by the transverse reinforcing bars and the longitudinal reinforcing bars are different in accordance with the thickness of the reinforcing bars The present invention provides a fixed structure between a junction box and a reinforcing bar during a molding process in which a transverse reinforcing bar and a longitudinal reinforcing bar are smoothly joined without cutting and welding.
In order to achieve the above object, the present invention provides a well-known structure in which a reinforcing bar fixing means is formed on the upper and lower sides of the back surface of a wiring box so as to be fixed to a reinforcing bar on the inside of a mold, And a transverse fastening hole having recesses on the upper and lower surfaces of the outer circumferential surface of the wiring box body so as to form an interval equal to the diameter of the reinforcing bars.
In this way, despite the difference in position between the transverse reinforcement and the longitudinal reinforcement, the construction is completed simply by inserting the wiring box into the reinforcing bars. Therefore, the efficiency of the construction work can be greatly improved, So that it is possible to provide a high quality of construction without being deformed during the concrete pouring and curing process.
1 is an explanatory view of a fixed state between a wire and a reinforcing frame using a general banding reinforcement.
2 is a perspective view showing a reinforcing bar of the distribution board base according to the present invention.
3 is a front perspective view showing a wiring box provided with a fixing structure of a reinforcing frame to which the present invention is applied.
4 is a rear perspective view showing a wiring box provided with a fixing structure of a reinforced concrete frame to which the present invention is applied.
5 is a front view of a wiring box to which the present invention is applied.
6 is a rear perspective view showing a state in which a wiring box is fixed to a reinforcing frame in the present invention;
7 is a plan view showing a state in which a wiring box is fixed to a reinforcing frame in the present invention.
8 is a side view showing a state in which a wiring box is fixed to a reinforcing frame in the present invention.
FIG. 9 is a plan view showing a state in which a reinforcing frame is fixed to another position of a wiring box in the present invention shown in FIG. 7; FIG.
FIG. 10 is a side view showing a state in which a reinforcing frame is fixed to another position of a wiring box in the present invention shown in FIG. 8; FIG.
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art can easily carry out the present invention with reference to the accompanying drawings.
3 and 4 show the wiring box to which the present invention is applied. As can be seen from this figure, the present invention includes a
A semicircular recessed
The positional difference between the positions of the center positions of the
3 to 6 show specific embodiments of the present invention.
As can be seen from the above, the present invention is provided with a recessed portion (2). In order to allow the housing (1) to be embedded in a structure of a building such as a wall or a pillar, When the mold is removed by curing the concrete after the concrete is put on the mold to cover only the
The present invention is characterized in that a
Particularly, the positions of the
In the present invention, if necessary, a through hole is formed in the upper end of the
In addition, the present invention is characterized in that the fasteners (3) located at the optimum position among the three transverse fasteners (3) and the longitudinal fasteners (3) according to the positions of the transverse reinforcing bars (501) 9 and 10 at the positions shown in Figs. 7 and 8 so as to be engaged with the guide grooves.
Even in such a case, the number and position of the lateral and longitudinal reinforcing bars fastened by the plurality of
As shown in FIG. 5, the
This is illustrative of the best mode embodiment of the present invention and not limitation of the present invention.
Accordingly, it is a matter of course that many modifications and variations of the present invention can be made without departing from the spirit and scope of the present invention, And falls within the scope of the technical idea of the present invention.
1: Enclosure 2: Inlet portion 3: Fastener
201: specification display section 301: concave groove 302:
w: diameter of the rebar 5: reinforcing frame 501: transverse reinforcing bar
502: longitudinal reinforcement 601: fixing protrusion 602: wiring
Claims (3)
Wherein a semicircular recessed portion and a retaining piece for retaining the reinforcing bars are formed on upper and lower circumferential surfaces and both circumferential surfaces of the enclosure,
And a position difference between a position of the concave groove center of the upper and lower circumferential surfaces and a concave groove center position of the fastener formed on both side circumferential surfaces is different by a diameter w of the reinforcing bars Fixed structure between junction box and reinforcing bar during formwork construction.
Wherein the upper and lower circumferential surface fasteners and the two side circumferential surface fasteners are the same in number and have a plurality of fastener openings.
Wherein the upper and lower circumferential surfaces are provided with the same number of fasteners on both circumferential surfaces and a plurality of fasteners on both circumferential surfaces so that the difference in position between the grooved center positions is different by the diameter w of the steel bar. Fixing structure between junction box and reinforcing bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR2020140005477U KR20160000364U (en) | 2014-07-22 | 2014-07-22 | Fixing Structure Between Distribution Box and RC Beams During Foam Construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR2020140005477U KR20160000364U (en) | 2014-07-22 | 2014-07-22 | Fixing Structure Between Distribution Box and RC Beams During Foam Construction |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20160000364U true KR20160000364U (en) | 2016-02-02 |
Family
ID=55351907
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR2020140005477U KR20160000364U (en) | 2014-07-22 | 2014-07-22 | Fixing Structure Between Distribution Box and RC Beams During Foam Construction |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20160000364U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110397268A (en) * | 2019-07-20 | 2019-11-01 | 山东金城建设有限公司 | Ring beam template and board support integrated design and construction method are poured after fabricated shear wall |
KR102129941B1 (en) | 2020-02-10 | 2020-08-05 | 한국토지주택공사 | Box assembly for constructing case integrated with wall of building |
-
2014
- 2014-07-22 KR KR2020140005477U patent/KR20160000364U/en not_active Application Discontinuation
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110397268A (en) * | 2019-07-20 | 2019-11-01 | 山东金城建设有限公司 | Ring beam template and board support integrated design and construction method are poured after fabricated shear wall |
KR102129941B1 (en) | 2020-02-10 | 2020-08-05 | 한국토지주택공사 | Box assembly for constructing case integrated with wall of building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101258188B1 (en) | Building a concrete wall insulation connected devices | |
KR101585942B1 (en) | Closing device for concrete | |
KR101270556B1 (en) | Switchgear with enclosing structure reinforced by multi-bending | |
KR101893218B1 (en) | translate online | |
KR20150005300A (en) | Permanent form preventing interference of reinforcing bar and construction method for coping | |
KR101314066B1 (en) | Integral cable-tray sleeve to penetrate the slab | |
KR20160000364U (en) | Fixing Structure Between Distribution Box and RC Beams During Foam Construction | |
KR20110040493A (en) | Permanent formwork for reinforced concrete | |
KR200255166Y1 (en) | a wall buried socket box | |
CN205355726U (en) | Pre -buried subassembly of wiring magazine | |
KR101648698B1 (en) | Plumbing supporters and its construction methods | |
KR101234813B1 (en) | Fixing device of power distributing box of apartment house | |
CN204826618U (en) | After water board template structure | |
KR102129941B1 (en) | Box assembly for constructing case integrated with wall of building | |
KR101311706B1 (en) | Corner bar and method for constructing concrete forms using the same | |
KR20090128076A (en) | Terminal box | |
KR200476569Y1 (en) | conduit support holder | |
KR101526200B1 (en) | Cd pipe supporting apparatus and weight fixing method and wall installing method | |
KR200460713Y1 (en) | Fixing apparatus for terminal block | |
KR101038353B1 (en) | A type reclamation communication device box | |
KR101402443B1 (en) | Insert for support of cd conduit and conduit construction method using the same | |
KR102022064B1 (en) | Distribution Panel for Easy Wall Distance Adjustment | |
KR20160120828A (en) | A supporter fixing unit for waterprof sill | |
KR20150003251U (en) | Connector for vertical type cable tray | |
KR20170013507A (en) | Sleeve Joint connecter for Cable-Tray |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E601 | Decision to refuse application |