R-H Structure and Method and Mold for Constructing the Same Download PDFInfo
- Publication number
- KR20150041462A KR20150041462A KR20130120010A KR20130120010A KR20150041462A KR 20150041462 A KR20150041462 A KR 20150041462A KR 20130120010 A KR20130120010 A KR 20130120010A KR 20130120010 A KR20130120010 A KR 20130120010A KR 20150041462 A KR20150041462 A KR 20150041462A
- Authority
- KR
- South Korea
- Prior art keywords
- slab
- plywood
- support
- reinforcing
- concrete
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
[0001] The present invention relates to a RH structure, its form, and a construction method. More particularly, the present invention relates to a RH structure for applying an underground parking lot complex construction method (hereinafter referred to as RH construction method) And a molding method and a construction method thereof.
In the construction method of the underground parking lot, the quality and economical efficiency of the RC (Reinforced Concrete) group is remarkably lowered due to the decrease of skillful skilled workers and the increase of the cost of the temporary materials. Therefore, the PC (Precast Concrete) It has been applied in Korea since the early 2000s, reflecting the change of the parking module.
Slabs such as Multi Ribbed Slab (MRS) and Hollow Core Slab (HCS) were used as the span became shorter and the beam and column were also PC members.
As a result, the bottom support is no longer required at the time of construction, and safe quality can be ensured through factory production.
This PC method has advantages of less manpower and installation cost and quick construction, but it is difficult to apply it to the irregular section due to the characteristics of the PC produced through the mold, and even if applied, it is not economical.
In other words, in the conventional PC method, the system is composed of PC slab [MRS (roof layer), HCS (basement layer)], PC beam and PC column. The application efficiency is decreased according to site conditions (site condition, design plan).
In the construction method using the PC method, the 'construction method using the centrifugal forming hollow PC column and the cast-in-place concrete or steel column together with the centrifugal forming hollow PC column' of Korean Patent No. 0932468 (registered on Dec. 09, 2009) In the construction of the underground building structure, the centrifugally formed hollow PC column preliminarily manufactured at the factory is used as the column of the building structure, or the centrifugally formed hollow PC column reinforced with the cast concrete or the small size steel column is used, Provide structurally stable building construction methods without the need to use large size and heavy steel columns.
In addition, in the hollow-type beam using U-shaped PC box, its construction method and its joining structure of Korean Patent No. 0806821 (registered on Feb. 18, 2008), hollow is formed in the inside to reduce the weight A hollow beam that can be easily completed by using a U-shaped PC box and a rod-shaped lightweight molding material, a method of constructing a hollow beam that simplifies the field work, and A joint structure of the hollow beam and the slab is provided.
However, this PC method is applied as the main construction method of underground parking lot construction, but it was confirmed that the efficiency of field application of PC products is low due to various design conditions due to the nature of construction work and the field conditions.
For example, when the length of the PC beam is varied, the cost of the construction is more than necessary because each mold needs to be manufactured at the plant according to the length of the beam.
Also, in case of 1 ~ 2 span where the main house and the underground parking lot are in contact with each other, RC beams should be generated due to the construction conditions, and the slab is also constructed by RC slab, resulting in a decrease in the PC slab use area.
Therefore, RC has a merit that it is not affected greatly by module and it is comparatively easy to modify. However, it depends on manpower, and it is affected by quality according to skill of skilled workers.
Therefore, an object of the present invention is to provide an R-H structure for replacing a PC beam with an RC beam and applying a slab to a hollow PC slab.
It is also an object of the present invention to provide a form of an R-H structure for assembling RC beams to replace RC beams in the basement and roof layers.
Another object of the present invention is to provide a method of constructing a RH structure in which a dam is provided in a hollow portion of the HCS and a hole is formed in the hollow portion of the HCS to pour concrete into a shear frictional reinforcing bar disposed in the hollow portion.
SUMMARY OF THE INVENTION The object of the present invention is to provide a pillar having a rectangular top surface; A beam connecting the upper ends of the adjacent columns to each other, the beam being perpendicular to the columns and being formed to be parallel to the ground; A slab orthogonal to the column and perpendicular to the beam, the slab orthogonal to the horizontal plane, the opposite ends of which connect adjacent beams, and a plurality of adjacent slabs are arranged to form an upper floor; A concrete surface forming a plane on the slab and the beam; And a reinforcement embedded in the slab, beam, and concrete to increase the shear strength of both ends of the slab located on both sides of the beam.
Also, according to the present invention, it is preferable that both ends of the slab are embedded in the beam.
According to the present invention, it is preferable that the slab further includes a dam positioned on both sides of the hollow portion so as to block concrete flowing from both sides of the slab hollow portion.
Also, according to the present invention, the reinforcing bar may include: a shearing friction reinforcing bar disposed at the center of the hollow portion so as to connect both ends of the adjacent slabs between the beams through the beam; And a basic reinforcing bar disposed along the longitudinal direction of the slab.
It is also an object of the present invention to provide a pillar having a rectangular top surface; A beam connecting the upper ends of the adjacent columns to each other, the beam being perpendicular to the columns and being formed to be parallel to the ground; A slab orthogonal to the column and perpendicular to the beam, the slab orthogonal to the horizontal plane and having opposite ends connected to each other and adjacent to each other to form a roof surface; A concrete surface forming a plane on the slab and the beam; And reinforcing bars embedded in slabs, beams, and concrete to increase the shear strength of both ends of the slabs located on both sides of the beams and beams.
Also, according to the present invention, it is preferable that both ends of the slab are embedded in the beam.
According to the present invention, it is preferable that the slab further includes a dam positioned on both sides of the hollow portion so as to block concrete flowing from both sides of the slab hollow portion.
According to the present invention, it is preferable that the holes are formed so that the reinforcing bars penetrate from the hollow portion of the slab upward to the dam positions along the longitudinal direction from both ends of the upper end of the slab.
According to another aspect of the present invention, the reinforcing bars include: a shearing friction reinforcing bar located inside the hollow portion to connect adjacent slab edges along the longitudinal direction of the hollow portion; A moment reinforcing steel reinforcing bar located above and outside the hole parallel to the shear friction reinforcing bars; And a horizontal shear reinforcement which is disposed perpendicular to the shear friction reinforcement and the momentum reinforcing steel and passes through the hole.
Also, an object of the present invention is to provide a slab supporting apparatus comprising: a slab support portion vertically erected so as to support both ends of a slab forming an upper floor bottom; A plywood formed of a lower plywood forming a bottom surface of the beam and a side plywood vertically erected from both sides of the plywood to form a side surface of the plywood and supporting a slab end; And a resilient supporting structure which is erected on the slab support part or the ground to support the plywood.
According to the present invention, it is preferable that the side plywood further includes a horizontal member which connects the side plywoods to each other so as to be vertical and parallel to each other when the concrete is poured.
According to the present invention, it is preferable that the resilient supporting portion is in the form of a rectilinear type which is erected vertically from the ground and a thrust type which is erected from the side portion of the slab support.
According to another aspect of the present invention, there is provided a method of manufacturing an electronic component, comprising the steps of: And a plurality of pipes arranged between the bottom plate and the bottom plate in the longitudinal direction of the bottom plate.
It is also an object of the present invention to provide a slab support structure comprising: a slab support portion vertically erected to support both ends of a slab forming a roof surface; A plywood formed of a lower plywood forming a bottom surface of the beam and a side plywood vertically erected from both sides of the plywood to form a side surface of the plywood and supporting a slab end; And a resilient supporting structure which is erected on the slab support part or the ground to support the plywood.
According to the present invention, it is preferable that the side plywood further includes a horizontal member which connects the side plywoods to each other so as to be vertical and parallel to each other when the concrete is poured.
According to the present invention, it is preferable that the resilient supporting portion is in the form of a rectilinear type which is erected vertically from the ground and a thrust type which is erected from the side portion of the slab support.
According to another aspect of the present invention, there is provided a method of manufacturing an electronic component, comprising the steps of: And a plurality of pipes arranged between the bottom plate and the bottom plate in the longitudinal direction of the bottom plate.
The object of the present invention can also be achieved by a method of manufacturing a column, comprising: a column-mounting step for mounting a column vertically from a ground; A step of assembling the mold so as to form a beam orthogonal to the columns at the upper surface of the columns; A bottom slab arranging step of positioning both ends of the plurality of slabs along the upper ends of the respective side plywoods of adjacent brackets, with the ends of the slabs being embedded in the beams; A reinforcing steel reinforcing step for reinforcing the reinforcing steel including the shear friction reinforcing steel reinforced by the slab hollow portion; Placing a topping concrete on the slab, forming a beam by the concrete introduced into the mold, and forming a concrete surface of a predetermined thickness on the slab to form an upper floor bottom surface. Lt; / RTI >
According to another aspect of the present invention, there is provided a method of manufacturing a floor slab, comprising the steps of: erecting a slab support vertically from the ground to support a slab; Assembling the side plywood vertically on both sides of the lower plywood to form the beam; and a step of erecting a pivot support for transmitting the load to one side or the ground of the slab support so as to support the lower plywood Do.
According to another aspect of the present invention, there is provided a method of manufacturing a reinforced concrete structure, comprising the steps of: installing a dam at a predetermined depth in a hollow portion of a slab disposed on a side plywood to allow concrete to flow only to a dam; A shear frictional reinforcement step in which shear frictional reinforcing bars connecting both ends of a hollow portion of adjacent slabs are disposed; It is preferable to include a basic reinforcing step of laying a basic reinforcing steel along the longitudinal direction of the slab on the slab.
The object of the present invention can also be achieved by a method of manufacturing a column, comprising: a column-mounting step for mounting a column vertically from a ground; A step of assembling the mold so as to form a beam orthogonal to the columns at the upper surface of the columns; A roof slab disposing step of disposing both ends of the plurality of slabs along the upper ends of the respective side plywoods of adjacent brackets, with the ends of the slabs being embedded in the beams; A reinforcing bar laying step of forming a hole in the slab hollow part to dispose a horizontal shear reinforcement rod penetrating through the hole and a reinforcing bar including a shear friction reinforcing bar; Placing a topping concrete on a slab, forming a beam by concrete introduced into a mold, and forming a concrete surface of a predetermined thickness on the slab to form a roof surface. .
According to another aspect of the present invention, there is provided a method of manufacturing a roof structure, comprising the steps of: erecting a slab support vertically from the ground to support a slab; Assembling the side plywoods vertically on both sides of the lower plywood to form beams; And a step of raising a bolt receiving portion for transmitting a load to one side or the ground of the slab receiving portion so as to support the plywood.
According to another aspect of the present invention, there is provided a method of manufacturing a reinforced concrete structure, comprising the steps of: installing a dam at a predetermined depth in a hollow portion of a slab disposed on a side plywood to allow concrete to flow only to a dam; A hole forming step of forming holes to be ruptured from both side ends of the upper end of the slab hollow portion to the dam position along the longitudinal direction; A reinforcing steel shear reinforcement located in the hollow portion, a reinforcing steel reinforcing bar located at the upper portion of the hole, and a horizontal shear reinforcing bar connecting the shearing friction reinforcing bar and the moment reinforcing steel through the hole, A shear frictional reinforcement step connecting both ends of adjacent slabs between beams; A basic reinforcing step of laying a basic reinforcing steel along the longitudinal direction of the slab on the slab; And a reinforcing bar laying step of laying the upper end reinforcing bars at both ends of the slabs adjacent to each other between the beams and the beams.
Therefore, the RH structure of the present invention, the construction method thereof and the formwork of the present invention by the above-mentioned problem solving means can be applied to a PC without forming additional molds in an irregular section which is constructed by a conventional RC, have.
In addition, the integrity of the structure can be improved by simultaneously placing the topping concrete and the RC column / beam.
In addition, it is possible to reduce the input of construction materials by eliminating the slab formwork operation compared to the RC structure, and it is possible to reduce the input of the hypothetical equipment by making the columns and beams relatively heavy compared to the PC structure RC. Especially, HCS is relatively lightweight Tower cranes can be used for both construction and construction.
Therefore, it is possible to reduce the variability of quality, which is influenced by skill of skilled worker, by using uniform quality PC. It is possible to reduce the floor height by applying RC wide beam, The cost of construction can be reduced.
1 is a bottom plan view of a RH structure according to a first embodiment of the present invention,
FIG. 2 is a cross-sectional view of AA, BB, CC, and DD portions in FIG. 1,
3 is a roof top view of a RH structure according to a second embodiment of the present invention,
FIG. 4 is a cross-sectional view of each of AA, BB, CC, and DD portions in FIG. 3,
5 is a schematic sectional view for constructing the floor of the RH structure according to the first embodiment of the present invention,
6 is a schematic sectional view for constructing a roof of a RH structure according to a second embodiment of the present invention;
FIG. 7 is a bottom construction flowchart of a method of constructing a RH structure according to a first embodiment of the present invention;
8 is a detailed flowchart of the reinforcement step of FIG. 7,
9 is a flowchart showing a roof construction process of a method of constructing a RH structure according to a second embodiment of the present invention;
10 is a detailed flowchart of the reinforcing step of FIG. 9;
The terms and words used in the present specification and claims should not be construed as limited to ordinary or dictionary terms and the inventor may appropriately define the concept of the term in order to best describe its invention It should be construed as meaning and concept consistent with the technical idea of the present invention.
Therefore, the embodiments described in this specification and the configurations shown in the drawings are merely the most preferred embodiments of the present invention and do not represent all the technical ideas of the present invention. Therefore, It is to be understood that equivalents and modifications are possible.
Hereinafter, embodiments of the R-H structure of the present invention and its form and construction method will be described in more detail with reference to the accompanying drawings.
BRIEF DESCRIPTION OF THE DRAWINGS Figure 1 shows an overall cross-sectional view according to a first embodiment of the R-H structure of the present invention.
As shown in FIG. 2, which is a partial sectional view of FIG. 1 and FIG. 1, the first embodiment of the present invention relates to an interlayer bottom structure of an underground parking lot.
For this purpose, the horizontal width of the beam is narrower than the horizontal width of the beam of the second embodiment described later but larger than the column width, and the shear friction reinforcement is applied to the inside of the slab.
To this end, the RH structure of the present invention comprises a
As shown in FIG. 2A, which is a cross-sectional view taken along the line A-A of FIG. 1, the
At this time, the beam 40 is vertically crossed to the top of the
As shown in FIG. 2B, which is a cross-sectional view taken along the line B-B of FIG. 1, the beam 40 vertically connects the
As shown in FIG. 2 (C), which is a cross-sectional view taken along the line C-C of FIG. 1, the
The
At this time, the end of the
The
At this time, a dam (24) serving as a partition is inserted into the hollow part (21) at the end of the slab (20) so that the concrete flows into the hollow part (21) only up to the position of the dam (24).
Further, the
2 (d), which is a sectional view taken along the line DD of FIG. 1, a shear friction reinforcing bar 76 (see FIG. 2) connecting the both ends of the
As shown in FIG. 2 (b), the reinforcing bars may be constructed of basic reinforcing bars 77 arranged along the longitudinal direction of the
Figure 3 shows an overall cross-sectional view according to a second embodiment of the R-H structure of the present invention.
4, a second embodiment of the present invention relates to a roof structure of a ceiling of an underground parking lot. To this end, And the horizontal shear reinforcement is penetrated through the inside and outside of the slab with the shear friction reinforcement.
To this end, the RH structure of the present invention comprises a
As shown in FIG. 4A, which is a sectional view taken along the line A-A of FIG. 3, the
At this time, the
As shown in FIG. 4B, which is a cross-sectional view taken along the line B-B of FIG. 3, the
As shown in FIG. 4 (C), which is a cross-sectional view taken along the line C-C of FIG. 3, the
The
At this time, the end of the
The
At this time, a dam (34) serving as a partition is inserted into the hollow part (31) at the end of the slab (30) so that the concrete flows into the hollow part (31) only up to the position of the dam (34).
Also, the
4 (d), the
The
Further, the horizontal
Also, the mandrel reinforcement bars 71 are arranged along the hollow slab on the hollow slab so as to resist the moment generated at the joint.
4 (b), the reinforcing bars are formed by an upper
Figure 5 shows a cross-sectional view of a R-H structure form according to a first embodiment of the present invention.
As shown in FIG. 5, the first embodiment of the present invention relates to a bottom surface formwork between basements of an underground parking lot. For this purpose, the horizontal width of the beam is narrower than the horizontal width of the beam of the second embodiment And is formed so as not to be smaller than the column width.
To this end, the RH structure formwork of the present invention comprises a
The
The
The
The plywood is a flat plate assembled to form a bottom surface and a side surface of the beam, and is constituted of a
At this time, the side plywood of the beam is supported on the end of the slab (20) so that the slab end located on the plywood is embedded in the inside of the beam by concrete pouring.
The side plywood is also horizontal and is made to attach a
At this time, the length of the
Figure 6 shows a cross-sectional view of an R-H structure form according to a second embodiment of the present invention.
As shown in FIG. 6, the second embodiment of the present invention relates to a roof surface formwork of a roof layer of an underground parking lot, wherein a horizontally extended width from left to right is formed from a horizontal width of a column .
To this end, the RH structure formwork of the present invention comprises a
The
The resilient supporting
In this case, the
At this time, the
The plywood is a flat plate assembled to form a bottom surface and a side surface of the beam, and is constituted of a
At this time, the lateral plywood of the beam is supported on the end of the slab (30) so that the slab end located on the plywood is embedded in the inside of the beam by concrete pouring.
The side plywood is also horizontal and is made to attach a
In this case, the length of the
FIG. 7 shows a flowchart according to the first embodiment of the R-H structure construction method of the present invention.
A first embodiment of the present invention relates to a floor structure between basements in an underground parking lot, and is a construction method in which a shear friction reinforcement connecting adjacent two-stage slabs is applied.
As shown in FIG. 7, first, a column installing step (S10) is performed in which pillars are vertically installed at equal intervals on the ground.
In the column mounting step (S10), the column is formed as a rectangular columnar RC structure vertically installed at regular intervals from the ground so as to support the bottom floor of the upper layer.
At this time, the beam is vertically intersected at the top face of the column.
After the column installation step (S10), a step S20 is performed to form a beam orthogonal to the column.
In the step S20 of installing the slab, the slab support portion for supporting the slab is vertically erected, the support portion for supporting the slab support portion to be formed by the concrete slab is installed between the slab support portions on both sides, A plywood to be formed on the lower surface and the side surface of the plywood board is assembled and stood on the pivot board.
At this time, a support plate is disposed at the upper end of the support portion to stably support the plywood, and a plurality of pipes are placed between the support plate and the bottom plywood in a longitudinal direction so that a uniform load is applied to the support portion.
In addition, to make the side and bottom of the beam, the plywood is set up vertically on the side of the plywood on both sides of the plywood and fixed with the horizontal material.
After the step S20 is performed, a bottom slab placing step S30 is performed in which both ends of the plurality of slabs are positioned along the upper ends of the respective side plywoods of neighboring brackets.
In the bottom slab placement step (S30), the side plywood of the beam supports the end of the slab so that the end of the slab located on the plywood is embedded in the inside of the beam by concrete pouring.
After performing the bottom slab arranging step S30, a reinforcing barging step S40 is performed in which a hole is formed in the slab hollow portion to reinforce the reinforcing bar including the shearing friction reinforcing bar.
More specifically, as shown in FIG. 8, first, a dam is installed at a certain depth in the hollow portion of the hollow portion of the slab disposed on the side plywood, and a dam installation step (S41) is performed to allow the concrete to flow only to the dam position .
After the dam installation step (S41) is performed, a shear friction reinforcement step (S43) is performed in which the shear friction reinforcement connecting the both ends of the hollow portions of the slabs on both sides is disposed.
That is, the shear friction reinforcement which connects both ends of the adjacent slabs between the beams passing through the beam is disposed at the center of the hollow portion.
After performing the shearing friction reinforcing step S43, a basic reinforcing steel reinforcing step S44 is performed to lay the basic reinforcing bars along the longitudinal direction of the slab on the slabs to perform all of the reinforcing steel reinforcing step S40.
When the reinforcing bars are laid out in the reinforcing steel laying step (S40), the topping concrete is laid on the slab, the beams are formed by the concrete introduced into the formwork, the concrete surface is formed on the slab, and the concrete is hardened A
FIG. 9 shows a flowchart according to a second embodiment of the R-H structure construction method of the present invention.
The second embodiment of the present invention relates to a roof layer structure of an underground parking lot, which forms a horizontal width expanded to both sides of a horizontal width of a column to be viewed and forms a horizontal shear along the inner and outer portions of the open hole of the slab together with the shear friction reinforcement And the reinforcing bars are applied.
As shown in FIG. 9, a column installation step (S110) is performed in which columns are installed perpendicularly at equal intervals on the ground.
In the column installation step (S110), the column is formed as a rectangular columnar RC structure vertically installed at regular intervals from the ground so as to support the bottom surface of the upper layer.
At this time, the beam is made orthogonal at the top surface of the column.
After the post installation step S110, the roof post form installation step S120 is performed to form orthogonal beams having a vertical width extended to both sides of the column.
In the step S120, the slab supporting part for supporting the slab is vertically erected, and the supporting part for supporting the beam part to be formed by the concrete is installed in a trust or straight shape between the slab supporting parts on both sides, A plywood to be formed on the lower surface and the side surface of the plywood board is assembled and stands on the pivot board.
At this time, a support plate is disposed at the upper end of the support portion to stably support the plywood, and a plurality of pipes are placed between the support plate and the bottom plywood in a longitudinal direction so that a uniform load is applied to the support portion.
In addition, to make the side and bottom of the beam, the plywood is set up vertically on the side of the plywood on both sides of the plywood and fixed with the horizontal material.
After performing the step S120, a roof slab disposing step S130 is performed in which both ends of the plurality of slabs are positioned along the upper ends of the respective side plywoods of adjacent brackets.
In the roof slab arranging step (S130), the side plywood of the beam is supported on the end of the slab so that the slab end located on the plywood is embedded in the inside of the beam by concrete casting.
After performing the roof slab arranging step (S130), a reinforcement step (S140) is performed to reinforce the reinforcing bars including the shear friction reinforcing bars in the slab hollow portion.
More specifically, as shown in FIG. 10, first, a dam is installed at a certain depth in the hollow portion of the hollow portion of the slab disposed on the side plywood, and a dam installation step (S141) is performed to allow the concrete to flow only to the dam position .
After performing the dam installation step (S141), a hole forming step (S142) for forming an open-type hole so as to be ripped from both ends of the slab hollow part along the longitudinal direction is performed, and the hole forming step (S142) Shear friction reinforcement step (S143) in which the open-type hollow shear friction reinforcing bars and the reinforcing bars are joined to each other.
In this case, the horizontal shear reinforcement penetrates vertically through the open hole, and the normal moment reinforcement and the shear friction reinforcement penetrate the beam horizontally, so as to connect both ends of the neighboring slabs between beams.
A step S144 of performing a basic reinforcing steel reinforcement step S144 in which the reinforcing steel reinforcing step S143 is performed and the basic reinforcing bars are arranged along the longitudinal direction of the slab on the slab, The reinforcing bar reinforcement step (S145) for reinforcing the upper end reinforcing bars located on both ends is performed to perform all of the reinforcing bar reinforcement step (S140).
When the reinforcing bars are laid in the reinforcing steel laying step (S140), the topping concrete is laid on the slab, the beams are formed by the concrete introduced into the formwork, and the concrete surface of the predetermined thickness is formed on the slab. The concrete installation step 150 in which the form is removed is performed to thereby perform the second embodiment of the RH construction method of the present invention.
While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is clearly understood that the same is by way of illustration and example only and is not to be taken by way of illustration, It will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.
10:
21, 31: hollow part 24, 34: dam
32: hole 40, 50: beam
71; Reinforced
73: horizontal shear reinforcement 77: primary reinforcing bar
Claims (23)
A beam connecting the upper ends of the adjacent columns to each other, the beam being perpendicular to the columns and being formed to be parallel to the ground;
A slab orthogonal to the column and perpendicular to the beam, the slab orthogonal to the horizontal plane, the opposite ends of which connect adjacent beams, and a plurality of adjacent slabs are arranged to form an upper floor;
A concrete surface forming a plane on the slab and the beam;
And reinforcing bars embedded in slabs, beams, and concrete so as to increase the shear strength of both ends of the slabs located on both sides of the beams and beams.
And both ends of the slab are embedded in the beam.
Wherein the slab further comprises a dam located inside the hollow portion to block concrete entering from both sides of the slab hollow portion.
The reinforcing bars,
A shear friction reinforcing bar disposed at the center of the hollow portion to connect both ends of adjacent slabs between the beams through the beams;
And a basic reinforcing steel reinforced along the longitudinal direction of the slab.
A beam connecting the upper ends of the adjacent columns to each other, the beam being perpendicular to the columns and being formed to be parallel to the ground;
A slab orthogonal to the column and perpendicular to the beam, the slab orthogonal to the horizontal plane and having opposite ends connected to each other and adjacent to each other to form a roof surface;
A concrete surface forming a plane on the slab and the beam;
And reinforcing bars embedded in slabs, beams, and concrete so as to increase the shear strength of both ends of the slabs located on both sides of the beams and beams.
And both ends of the slab are embedded in the beam.
Wherein the slab further comprises a dam located inside the hollow portion to block concrete entering from both sides of the slab hollow portion.
Wherein the holes are formed so as to be ruptured from both ends of the upper end of the slab to the dam position along the longitudinal direction so that the reinforcing bars pass through the hollow portion of the slab upwardly.
The reinforcing bars,
A shear frictional reinforcing bar positioned so as to connect opposite ends of the slab adjacent to each other in the longitudinal direction of the hollow portion in the hollow portion;
A moment reinforcing steel reinforcing bar located above and outside the hole parallel to the shear friction reinforcing bars;
And a horizontal shear reinforcement rope disposed perpendicularly to the shear friction reinforcement and the momentum reinforcing bars and passing through the holes.
A plywood formed of a lower plywood forming a bottom surface of the beam and a side plywood vertically erected from both sides of the plywood to form a side surface of the plywood and supporting a slab end;
And a pivot support portion which is erected on the slab support portion or the ground to support the plywood.
Wherein the side plywood further comprises a horizontal member connecting the side plywood to each other so as to be vertical from the bottom plywood and to be parallel to each other when the concrete is poured.
Wherein the resilient supporting portion is in the form of a straight type which is erected vertically from the ground and a thrust type which is erected from a side portion of the slab support.
Wherein,
A support plate formed in the lengthwise direction of the beam at an upper end of the beam receiving portion;
Further comprising a plurality of pipes arranged in the longitudinal direction of the support plate between the support plate and the bottom plywood.
A plywood formed of a lower plywood forming a bottom surface of the beam and a side plywood vertically erected from both sides of the plywood to form a side surface of the plywood and supporting a slab end;
And a pivot support portion which is erected on the slab support portion or the ground to support the plywood.
Wherein the side plywood further comprises a horizontal member connecting the side plywood to each other so as to be vertical from the bottom plywood and to be parallel to each other when the concrete is poured.
Wherein the resilient supporting portion is in the form of a straight type which is erected vertically from the ground and a thrust type which is erected from a side portion of the slab support.
Wherein,
A support plate formed in the lengthwise direction of the beam at an upper end of the beam receiving portion;
Further comprising a plurality of pipes arranged in the longitudinal direction of the support plate between the support plate and the bottom plywood.
A step of assembling the mold so as to form a beam orthogonal to the columns at the upper surface of the columns;
A bottom slab arranging step of positioning both ends of the plurality of slabs along the upper ends of the respective side plywoods of adjacent brackets, with the ends of the slabs being embedded in the beams;
A reinforcing steel reinforcing step for reinforcing the reinforcing steel including the shear friction reinforcing steel reinforced by the slab hollow portion;
Placing a topping concrete on the slab, forming a beam by the concrete introduced into the mold, and forming a concrete surface of a predetermined thickness on the slab to form an upper floor bottom surface. .
In the step of installing the bottom support,
Erecting the slab support vertically from the ground to support the slab;
Assembling the side plywoods vertically on both sides of the lower plywood to form beams;
The method as claimed in claim 1, further comprising the step of erecting a bolt receiving part for supporting a load on one side or the ground of the slab receiving part to support the plywood.
The reinforcing steel reinforcing step comprises:
A dam installation step in which a dam is installed at a certain depth in the inside of the hollow part of the slab disposed on the side plywood to allow the concrete to flow only to the dam position;
A shear frictional reinforcement step in which shear frictional reinforcing bars connecting both ends of a hollow portion of adjacent slabs are disposed;
And a basic reinforcing step of laying a basic reinforcing steel along the longitudinal direction of the slab on the slab.
A step of assembling the mold so as to form a beam orthogonal to the columns at the upper surface of the columns;
A roof slab disposing step of disposing both ends of the plurality of slabs along the upper ends of the respective side plywoods of adjacent brackets, with the ends of the slabs being embedded in the beams;
A reinforcing bar laying step of forming a hole in the slab hollow part to dispose a horizontal shear reinforcement rod penetrating through the hole and a reinforcing bar including a shear friction reinforcing bar;
Placing a topping concrete on the slab, forming a beam by the concrete introduced into the mold, and forming a concrete surface of a predetermined thickness on the slab to form a roof surface.
The step of installing the roof-
Erecting the slab support vertically from the ground to support the slab;
Assembling the side plywoods vertically on both sides of the lower plywood to form beams;
The method as claimed in claim 1, further comprising the step of erecting a bolt receiving part for supporting a load on one side or the ground of the slab receiving part to support the plywood.
The reinforcing steel reinforcing step comprises:
A dam installation step in which a dam is installed at a certain depth in the inside of the hollow part of the slab disposed on the side plywood to allow the concrete to flow only to the dam position;
A hole forming step of forming holes to be ruptured from both side ends of the upper end of the slab hollow portion to the dam position along the longitudinal direction;
A reinforcing steel shear reinforcement located in the hollow portion, a reinforcing steel reinforcing bar located at the upper portion of the hole, and a horizontal shear reinforcing bar connecting the shearing friction reinforcing bar and the moment reinforcing steel through the hole, A shear frictional reinforcement step connecting both ends of adjacent slabs between beams;
A basic reinforcing step of laying a basic reinforcing steel along the longitudinal direction of the slab on the slab;
And a reinforcing bar laying step of laying the upper end reinforcing bars at both ends of the adjacent slabs between the beams and the beams.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR20130120010A KR20150041462A (en) | 2013-10-08 | 2013-10-08 | R-H Structure and Method and Mold for Constructing the Same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR20130120010A KR20150041462A (en) | 2013-10-08 | 2013-10-08 | R-H Structure and Method and Mold for Constructing the Same |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20150041462A true KR20150041462A (en) | 2015-04-16 |
Family
ID=53034949
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR20130120010A KR20150041462A (en) | 2013-10-08 | 2013-10-08 | R-H Structure and Method and Mold for Constructing the Same |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20150041462A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113530011A (en) * | 2021-08-09 | 2021-10-22 | 成都魔筑科技有限公司 | Stable piece, keel, supporting structure, pouring system and mounting process for wall |
-
2013
- 2013-10-08 KR KR20130120010A patent/KR20150041462A/en not_active Application Discontinuation
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113530011A (en) * | 2021-08-09 | 2021-10-22 | 成都魔筑科技有限公司 | Stable piece, keel, supporting structure, pouring system and mounting process for wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107989227B (en) | Assembled steel reinforced concrete shear wall structure and preparation and installation methods thereof | |
KR101030419B1 (en) | Joint structure of vertical member and horizontal member | |
US20160340855A1 (en) | Modular construction mold apparatus and method for constructing concrete buildings and structures | |
CN105649360A (en) | Integral assembling type building system and installing method | |
KR101809687B1 (en) | Joining Members of Steel Concrete Column and Steel Beam and Construction Method Thereof | |
KR101658648B1 (en) | Beam-column joint and simultaneous construction method of upper and lower part of building using thereof | |
KR101663132B1 (en) | Self-supporting type column structure | |
WO2012096639A1 (en) | Modular construction mold apparatus and method for constructing concrete buildings and structures | |
CN107859206A (en) | Pre-manufactured steel structure overlapped shear wall and its construction method | |
CN111364681A (en) | Prefabricated section steel concrete end column-beam node prestressed tendon staggered tensioning anchoring structure for assembly building and construction method | |
CN207812741U (en) | Pre-manufactured steel structure overlapped shear wall | |
CN112681511B (en) | Reinforced concrete structure construction method using section steel to replace part of reinforcing steel bars | |
CN107447873B (en) | Device for connecting prefabricated laminated connecting beam and prefabricated shear wall and installation method | |
CN113718753A (en) | Anchorage underground diaphragm wall foundation assembled type mid-partition wall and construction method | |
KR101521946B1 (en) | Enlarged capital of steel framed reinforced concrete column | |
KR20130040652A (en) | Precast concrete frame and its construction method for buildings using precast concrete slab continued by post tensioning | |
JP5869717B1 (en) | Existing concrete structure reinforcement structure | |
JP5750246B2 (en) | Composite beam, building, and composite beam construction method | |
KR101534641B1 (en) | The method for constructing the basement | |
KR20150041462A (en) | R-H Structure and Method and Mold for Constructing the Same | |
KR101324884B1 (en) | Hybrid building construction method combining dry type and wet type | |
KR20190052638A (en) | Beam-reinforced deck plate and construction method using the same | |
KR101311207B1 (en) | Column of steel framed reinforced precast concrete structure, manufacturing methods for the same, and construction methods for the same | |
CN111335485B (en) | Prefabricated section steel concrete intermediate column beam node prestressed tendon staggered tensioning anchoring structure for assembly building and construction method | |
KR101880813B1 (en) | A sandwitch pc pannel structure and construction method of structure using thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E90F | Notification of reason for final refusal | ||
N231 | Notification of change of applicant | ||
E90F | Notification of reason for final refusal | ||
E601 | Decision to refuse application |