KR20140005447A - Controlling method using a dangerousness work permission managing system of the drillship - Google Patents

Controlling method using a dangerousness work permission managing system of the drillship Download PDF

Info

Publication number
KR20140005447A
KR20140005447A KR1020120072625A KR20120072625A KR20140005447A KR 20140005447 A KR20140005447 A KR 20140005447A KR 1020120072625 A KR1020120072625 A KR 1020120072625A KR 20120072625 A KR20120072625 A KR 20120072625A KR 20140005447 A KR20140005447 A KR 20140005447A
Authority
KR
South Korea
Prior art keywords
work
risk
dangerous
permission
menu
Prior art date
Application number
KR1020120072625A
Other languages
Korean (ko)
Inventor
정종헌
한승현
박현민
윤용준
Original Assignee
현대중공업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현대중공업 주식회사 filed Critical 현대중공업 주식회사
Priority to KR1020120072625A priority Critical patent/KR20140005447A/en
Publication of KR20140005447A publication Critical patent/KR20140005447A/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/26Government or public services
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Development Economics (AREA)
  • Primary Health Care (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a control method using a dangerous work permission management system of the drill ship, the present invention as described above is to drill down the drilling ship construction work according to the risk level according to the risk work permission management procedure subdivided the license and safety management DB of the management server After putting it in the container, the operator can use the terminal equipped with the dangerous work permission management procedure to acquire a plurality of permits and safety management of a specific work, and then perform the work. Each time the work is carried out, the work permit and safety management are acquired according to the risk work permission management procedure of the server. Therefore, the work risk of the entire construction of the drilling ship is systematically managed and minimized. It is effective to maximize safety.

Description

CONTROLLING METHOD USING A DANGEROUSNESS WORK PERMISSION MANAGING SYSTEM OF THE DRILLSHIP}

The present invention relates to a control method using a dangerous work permit management system of a drillship, and in particular, the drill ship construction work according to the risk work permitting subdivision and safety management according to the degree of risk and put it into the DB of the management server By using the terminal equipped with the dangerous work permission management procedure, a plurality of specific work permits and safety managements can be obtained, and then the work can be performed to control the drill ship's dangerous work permit management system to maximize the safety of the drilling ship construction work. It is about a method.

In general, in shipyards that build ships, especially drilling ships (hereinafter referred to as drill ships), when a production plan for an ordered drill ship is established, a small schedule for the production is established by department and by type, and the purchase material is received accordingly. Will run production. In this case, the drillship production plan is to establish a schedule according to the time of each division, such as assembly, painting, design, mounting, etc. by department and leading, trailing, cabin, specialty, captain, captain, battlefield.

And when entering the production work in accordance with the drillship production plan as described above, the work in the hazardous area, such as double fire, paint, and enclosed area, the worker is put into the work that has been approved by the work approval rights. At this time, in the dangerous workplace as described above, the licensed work permit is provided and work safety and security personnel are also arranged to prevent possible risk factors in advance.

Here, the prior art related to the risk management method of the conventional drillship construction as described in Korea Patent Publication No. 10-0846829 (registered name: industrial safety accident monitoring system of the manufacturing industry) filed by Hyundai Heavy Industries Co., Ltd. registered date: 10 July 2008).

     Then, the risk management method of the conventional drillship drying as described above with reference to Figure 1, first, by department, such as assembly, painting, design, mounting, and the like, preceding, trailing, cabin, special degree using the designed drillship drying design drawings A first step (S100) of setting a workplace for each type of work, such as a captain, a captain, a battlefield, and a batch worker thereof;

      A second step (S110) of drying the drillship according to the drillship drying design drawing by the operator of the set workshop after the first step (S100);

In the case of the dangerous workplace during the second step (S110), before the start of the work, a request for approval of the dangerous work is requested to the work approval right holder, and the work approval right person grasps the state of the work place and its input by visual or wired and issues a work permit book. A third step (S120) for giving or returning a dangerous work approval request;

If the dangerous work is approved after the third step (S120) and the fourth step (S130) for the workers of the dangerous worker to attach the approved work permit site around the workplace and then execute the dangerous work;

After the fourth step (S130), the safety officer is put into the corresponding dangerous workplace to check the work safety matters, and further comprising a fifth step (S140) for the manager to check the status of the workplace.

On the other hand, the risk management method of the conventional drillship drying as described above in more detail, by using the designed drillship drying design drawings by department, such as assembly, painting, design, mounting, leading, trailing, cabin, special fare, millet, Set workshops for each type of work such as captain and battlefield, and their arrangement workers. Then, when the design work is completed as described above, the worker of the set workshop is input and the drill ship is dried according to the drill ship drying design drawings. In the case of a dangerous workplace during this process, a request for approval of a dangerous work is requested to the work approval right before the work starts, and the work approval right may visually identify the work place and its inputs by wire or wire and issue a work permit or approve the dangerous work. Return the request. At this time, if the dangerous work is approved during the above process, the workers of the dangerous worker attach the licensed work permit to the periphery of the workplace and execute the dangerous work. In addition, when a worker is put into the dangerous workplace as described above, the safety personnel are put into the dangerous workplace to check the safety of the work, and the manager checks the status of the workplace and leaves a record. .

However, the risk management method of the conventional drill ship construction as described above, the management cost is greatly increased because the safety management of the work space and the worker is not effectively implemented to correspond to the size of the drill ship, especially fire in dangerous work space There is a problem that rapid response or management is not implemented for risk management such as an explosion, and therefore, damage to human and physical property can be increased accordingly.

Therefore, the present invention was invented to solve the above-mentioned problems of the prior art, and according to the risk work permission management procedure of the server each time to separate the entire drying work of the drill ship according to the degree of risk and proceed with the divided work The purpose of this study is to provide a control method using the dangerous work permit management system of the drill ship which can systematically manage the work risk of the entire construction work of the drill ship since the work permit and safety management are carried out.

Another object of the present invention is to process the work permit for the drillship construction work after obtaining the permission by the approval authority designated by the grade according to the work risk, so that if the work permit request is duplicated or the reason for the nonconformity of the work occurs, this is effective. The present invention provides a control method using a dangerous work permit management system of drill ships, which can improve the work quality of drill ship construction work.

The present invention for achieving the above object is to classify the entire dry operation of the drill ship according to the degree of risk grade initial screen of the dangerous work permission management menu displayed on the dangerous work permission management system equipped with the risk work permission management procedure A risk task permission menu configuration process in which, when a user clicks any one of the largely classified menu icons, detailed items of the clicked dangerous task are displayed in a detailed menu screen;

If the worker who wants to work on the dangerous work enters the dangerous work application information including the work date, working time, number of people and detailed work place on the dangerous work permission request menu screen, which is a detailed menu of the dangerous work permission management menu after the menu configuration process, A risk work permission request process that the work permission management system executes;

After the risk work permission request process, the risk work permission management system sets an item on the risk work approval menu screen, which is a detailed menu of the risk work permission management menu, that sets the items for which the approver designated by each risk work checks, approves, or rejects the work request. The risk work permit approval process implemented;

After the dangerous work permit approval process is approved, the dangerous work approval information is checked to check whether the currently approved dangerous work is performed in parallel on the safety inspection menu screen of the risk work permission management menu. Marking dangerous work parallels;

During the parallel check process of the dangerous work, if the safety officer checks the permit output item on the safety check menu screen, the risk work permit management system changes the menu screen to the approver check waiter. An on-site inspection request process for sending a on-site inspection request text message or voice guidance message to the on-site inspection request;

After the site inspection request process, if the approver authorized to approve the dangerous work on the risk work approval menu screen confirms the risk work site and enters the result information on the site inspection menu screen, the risk work permission management system registers it. It provides a control method using the dangerous work permission management system of the drill ship including the completion process.

According to the present invention as described above, according to the risk work permission management procedure, the drillship drying operation according to the degree of risk subdivided the permission and safety management into the DB of the management server, the operator uses the terminal equipped with the risk work permission management procedure By acquiring a plurality of permits and safety management of a specific work, and then performing the work, the whole construction of the drillship is classified according to the degree of risk, and whenever the classified work is carried out, according to the risk work permission management procedure of the server. Since it proceeds after obtaining work permit and safety management, it minimizes and systematically manages the work risk of the entire drying work of the drillship, thereby maximizing the safety of the drilling ship drying work.

As described above, the present invention processes the work permit for the drillship construction work after acquiring the permission by the approver designated by the class according to the work risk, so that the work permit request is duplicated or the reason for the nonconformity of the work is efficiently generated. Since it can be excluded and managed, there is also an effect that can significantly improve the work quality of the drillship drying operation.

1 is an explanatory diagram illustrating a risk management method of conventional drillship drying;
2 is an explanatory diagram illustrating a dangerous work permission management system to which the present invention is applied.
3 is a flowchart illustrating the method of the present invention.

Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

The risk work permission management system 1 to which the method of the present invention is applied is equipped with a risk work permission management procedure or a risk work permission management program as shown in FIG. It classifies and manages the dangerous work permission management menu screen for approval of the dangerous work and transmits the dangerous work permission request signal transmitted through the terminal 2 to the approver for the risk work. The grant unit is configured to receive and process the risk work permission management menu screen.

On the other hand, the control method of the present invention having the above configuration will be described.

According to the method of the present invention, as shown in FIG. 3, the initial screen of the dangerous work permission management menu displayed in the dangerous work permission management system equipped with the dangerous work permission management procedure is carried out in the initial state S1. A risk task permission menu configuration process (S2) of classifying and organizing according to the degree of risk and clicking on any one of the largely classified menu icons to display detailed items of the clicked risk task on a detailed menu screen;

After the menu configuration process (S2), in the dangerous work permission request menu screen, which is a detailed menu of the dangerous work permission management menu, a worker who wants to perform a dangerous work inputs information on a dangerous work request including a work date, a working time, a working person, and a detailed work place. A risk work permission request process (S3) for the risk work permission management system to execute the risk work;

After the dangerous work permission request process (S3), if the approver designated by each risk job sets items for confirming and approving or rejecting the job application on the dangerous work approval menu screen, which is a detailed menu of the dangerous work permission management menu, the dangerous work permission management is performed. A risk work permit approval process (S4) in which the system executes it;

After the dangerous work permit approval process (S4), if the permission of the dangerous work requested by the approver is approved, the dangerous work is checked to check whether the currently approved dangerous work is performed on the safety inspection menu screen of the risk work permission management menu. A risk work parallel check process (S5) for displaying the approval information;

During the risk task parallel check process (S5), when the safety officer checks the permit output item on the safety inspection menu screen, the risk task permission management system changes the menu screen to the approvers check wait when the task manager outputs the risk task permit. In addition, the on-site inspection request process (S6) for transmitting the on-site inspection request text message or voice guidance message to the approving authority;

If the approver who approves the dangerous work on the dangerous work approval menu screen after the site inspection request process (S6) confirms the dangerous work site and enters the result information on the site inspection menu screen, the risk work permission management system registers it. It consists of a site inspection completion process (S7).

After the site inspection completion process (S7), if a request for searching the dangerous work statuses based on the work department, safety department, and work place is requested from the risk work permission management menu, the dangerous work permission management system searches for the corresponding information and outputs it on the display. It further includes a dangerous job status search process to output or output through the output device.

Here, the dangerous work permission menu configuration process (S2) in the initial screen of the risk work permission management menu, fire work, painting work, electrical work, heavy load, enclosed space (fire / paint, etc.), chief work, test, non-routine work The information on items such as diving, oil supply, and common work is largely classified, or classified into work management forms such as work area and performance management.

In the dangerous work permission menu configuration process (S2), since the standardized work place for the dangerous work is displayed on the dangerous work permission management menu, the detailed work place information of the dangerous place is checked so that the dangerous work is not performed in parallel. It may be configured to further include a dangerous place management menu.

After the menu configuration process (S2), on the detailed menu screen of the risk task permission management menu, the risk task permission request menu screen requesting the approvers for approval of the risk task and the risk task approval for processing the approval of the approver for the risk task The menu screen further includes.

Here, during the dangerous work permission request process (S3), when the work applicant clicks on the dangerous work permission request menu screen, including the work request information, the work route, work process, work contents, zone classification, work zone and detailed zone It further includes a strike window display step for jumping the strike window to select the information.

Here, the risk work permission approval process (S4) configures an item item for checking whether the work in parallel in the risk work approval menu screen, if the item item is selected for the parallel work requesting parallel work to the safety department personnel A parallel work request text sending step of automatically sending a text message further includes a step.

In the dangerous work parallel check process (S5), if it is checked that the dangerous work is being performed by the safety officer set in the safety check menu screen, the safety officer with authority can click the safety parallel tuning menu screen according to the work priority. A parallel work change request step of requesting a worker to change a work schedule and place is further included.

In the dangerous work parallel check process (S5), the safety officer checks the item requesting to change the parallel work schedule and location on the safety parallel tuning menu screen, or checks the permission output item on the safety check menu screen. The system further includes a safety coordination alarm step in which the dangerous work permission management system transmits the change request or the permit output to the worker by text message or voice guidance message.

Here, the method of the present invention as described above in more detail, the drillship risk permission management system 1 of the present invention, first, the operator to execute the dangerous work from his terminal (2) to the risk work permission management menu When the connected icon is clicked, the dangerous work permission management system 1 transmits the dangerous work permission management menu on the corresponding terminal 2 to be displayed. Then, in the dangerous work permission management menu as described above, the operator enters the dangerous work permission request menu screen, which is a detailed menu, and inputs the dangerous work application information including a work date, a working time, a working person, and a detailed work place. Then, the dangerous work permission management system 1 jumps the strike window on the terminal 2, so that the job applicant uses the strike window, including the work application information, the work route, the work process, the work contents, the zone classification, Allows you to select information about work and detail areas.

In addition, after requesting the dangerous work permit as described above, the designated approver for each risk task confirms the work application on the dangerous work approval menu screen, which is a detailed menu of the risk work permit management menu, and approves or rejects the requested dangerous work. Will set.

Then, the dangerous work permission management system 1 automatically sends a text message requesting parallel work to the safety department manager when an item item for the work parallel is selected by the approver.

On the other hand, when the risk work permit as described above is approved by the approver, the risk work permit management system 1 checks whether the risk work currently approved is performed on the safety inspection menu screen of the risk work permit management menu in parallel. Display the approval information. At this time, when the safety officer sees the safety inspection menu screen, the safety officer can check the parallel of dangerous work after referring to various situations, and in this process, checking that the dangerous work is being performed in parallel. In this case, the safety officer clicks the safety parallel tuning menu screen on his terminal 2 and requests the worker to change the work schedule and place according to the work priority.

On the other hand, if the safety officer checks the item requesting to change the parallel work schedule and location on the safety parallel coordination menu screen or checks the permission output item on the safety inspection menu screen, the request or permission to change the parallel work is checked. The dangerous work permission management system 1 transmits the output to the worker in a text message.

As described above, when the safety officer checks the permission output item on the safety inspection menu screen, when the work manager outputs the dangerous work permit through the display 3, the dangerous work permission management system 1 waits for the approver to check the menu screen. In addition, the system sends a site check request text message to the approver.

Then, if the approver authorized to approve the dangerous work as above confirms the dangerous work site and inputs the result information on the site inspection menu screen, the risk work permission management system 1 registers it and manages the risk permission of the drillship. Terminate the procedure.

Therefore, according to the present invention as described above, after the drillship drying operation according to the risk task permission management procedure subdivided the permission and safety management into the DB of the management server, the worker is equipped with the risk task permission management procedure By obtaining a plurality of permits and safety management of a specific task using a terminal, and then performing the task, the entire construction of the drillship is classified according to the degree of risk, and the risk task permission management of the server is performed whenever the classified tasks are performed. As the procedure is carried out after acquiring the work permit and safety management according to the procedure, it is possible to systematically manage the work risk of the entire construction of the drillship.

In addition, the present invention as described above processes the work permit for the drillship construction work after obtaining the permission by the approval authority specified for each grade according to the work risk, so if the work permission request is duplicated or the reason for the nonconformity of the work occurs Since it can be effectively excluded and managed, the work quality of the drillship's drying operation can be significantly improved.

1: Dangerous work permission management system 2: Terminal
3: Display

Claims (9)

The initial screen of the Hazard Work Permit Management menu displayed on the Hazard Work Permit Management System equipped with the Hazard Work Permit Management System is configured to classify the entire construction of the drillship according to the degree of risk level. A risk task permission menu configuration process in which, when clicked, detailed items of the risk task clicked are displayed in a detailed menu screen;
If the worker who wants to work on the dangerous work enters the dangerous work application information including the work date, working time, number of people and detailed work place on the dangerous work permission request menu screen, which is a detailed menu of the dangerous work permission management menu after the menu configuration process, A risk work permission request process that the work permission management system executes;
After the risk work permission request process, the risk work permission management system sets an item on the risk work approval menu screen, which is a detailed menu of the risk work permission management menu, that sets the items for which the approver designated by each risk work checks, approves, or rejects the work request. The risk work permit approval process implemented;
After the dangerous work permit approval process is approved, the dangerous work approval information is checked to check whether the currently approved dangerous work is performed in parallel on the safety inspection menu screen of the risk work permission management menu. Marking dangerous work parallels;
During the parallel check process of the dangerous work, if the safety officer checks the permit output item on the safety check menu screen, the risk work permit management system changes the menu screen to the approver check waiter. An on-site inspection request process for sending a on-site inspection request text message or voice guidance message to the on-site inspection request;
After the site inspection request process, if the approver authorized to approve the dangerous work on the risk work approval menu screen confirms the risk work site and enters the result information on the site inspection menu screen, the risk work permission management system registers it. A control method using a dangerous work permit management system of a drill ship including a completion process.
According to claim 1, wherein the risk work permission menu configuration process is carried out on the initial screen of the risk work permission management menu, fire work, painting work, electrical work, heavy load, enclosed space (fire / coating, etc.), chief work, test, unusual Control using the dangerous work permission management system of the drill ship, characterized in that the item information such as work, diving work, oil supply and common work is largely classified or classified into work management forms such as work area and performance management. Way.
According to claim 1, wherein the dangerous work permission menu configuration process in the dangerous work permission management menu is displayed after standardizing on the place where the dangerous work is performed, the detailed work place for the dangerous place so that the risk work is not parallel A control method using a dangerous work permission management system of a drill ship, characterized in that further comprises a menu of dangerous work place management to confirm the information.
According to claim 1, After the menu configuration process to handle the risk task permission request menu screen for requesting approval authority for the risk task on the detailed menu screen of the risk task permission management menu and the approval authority for the risk task A control method using a dangerous work permission management system of a drill ship, characterized by further comprising a dangerous work approval menu screen.
According to claim 1, wherein during the risk work permission request process, when the work applicant clicks on the risk work permission request menu screen, the work route, work process, work contents, zone classification, work zone and detailed zone including work application information are included. A control method using a drillship dangerous work permission management system, characterized in that it further comprises a strike window display step of jumping the strike window to select information about.
According to claim 1, The risk work permission approval process configures the item item to confirm whether the work parallel in the dangerous work approval menu screen, if the item item is selected for the parallel work request to the safety department personnel parallel work A control method using a dangerous work permission management system of a drill ship, characterized in that it further comprises a parallel work request text sending step of automatically sending a text message.
According to claim 1, When the risk task parallel check process checks that dangerous work is being performed by the safety officer set on the safety inspection menu screen, the safety officer with authority by clicking the safety parallel tuning menu screen priority According to the control method using a dangerous work permission management system of the drill ship, characterized in that it further comprises a parallel work change request step for requesting workers to change the work schedule and location.
The method of claim 1, wherein during the parallel check operation of the dangerous work, the safety officer checks an item requesting to change the parallel work schedule and location on the safety parallel tuning menu screen, or checks the permission output item on the safety check menu screen. If the risk work permission management system of the drillship, characterized in that it further comprises a safety coordination alarm step that the risk work permission management system transmits the request for the parallel work change request or permission output to the worker as a text message or voice guidance message. Control method used.
According to claim 1, After the completion of the site inspection process in the dangerous work permission management menu when the request for searching the dangerous work status created on the basis of the work department, safety department and work site, the dangerous work permission management system searches for the corresponding information on the display The control method using the dangerous work permission management system of the drill ship, characterized in that it further comprises a dangerous job status search process to output to or through the output device.
KR1020120072625A 2012-07-04 2012-07-04 Controlling method using a dangerousness work permission managing system of the drillship KR20140005447A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120072625A KR20140005447A (en) 2012-07-04 2012-07-04 Controlling method using a dangerousness work permission managing system of the drillship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120072625A KR20140005447A (en) 2012-07-04 2012-07-04 Controlling method using a dangerousness work permission managing system of the drillship

Publications (1)

Publication Number Publication Date
KR20140005447A true KR20140005447A (en) 2014-01-15

Family

ID=50140839

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120072625A KR20140005447A (en) 2012-07-04 2012-07-04 Controlling method using a dangerousness work permission managing system of the drillship

Country Status (1)

Country Link
KR (1) KR20140005447A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200043306A (en) * 2018-10-17 2020-04-27 주식회사 넥스트코어테크놀로지 Apparatus and method for intergrating management of safety in the workplace
CN112116118A (en) * 2019-06-19 2020-12-22 中国石油化工股份有限公司 Operation reduction early warning system based on data mining

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200043306A (en) * 2018-10-17 2020-04-27 주식회사 넥스트코어테크놀로지 Apparatus and method for intergrating management of safety in the workplace
CN112116118A (en) * 2019-06-19 2020-12-22 中国石油化工股份有限公司 Operation reduction early warning system based on data mining

Similar Documents

Publication Publication Date Title
JP7232539B2 (en) Methods and systems for providing and receiving information for field risk management
JP7473985B2 (en) Method and system for providing and receiving information for on-site risk management - Patents.com
Ebrahemzadih et al. Assessment and risk management of potential hazards by failure modes and effect analysis (FMEA) method in Yazd Steel Complex
US20190088069A1 (en) Device for real time equipment tracking at a construction site
Rodrigues et al. Correlation of causal factors that influence construction safety performance: A model
KR102481223B1 (en) A smart integrated safety management system that can support various safety management, including safety inspection and education, using digital technology
KR102391197B1 (en) Digital Safety Work Management System and Method
James et al. Development of methodology for the disassemblability index of automobile systems using a structural approach
Pouya et al. The comparative study of evaluating human error assessment and reduction technique and cognitive reliability and error analysis method techniques in the control room of the cement industry
TWI469068B (en) Quality control system, specification and task management system, device, application program and storage medium thereof
KR20140005447A (en) Controlling method using a dangerousness work permission managing system of the drillship
Shokria et al. A cognitive human error analysis with CREAM in control room of petrochemical industry
KR20140005446A (en) System for managing a dangerousness work permission of the drillship using a mobile device
KR20140005448A (en) Method for controlling a dangerousness work permission managing system of the drillship using a mobile device
KR20130082628A (en) Work permittion managemnt system, method thereof, and recordable medium storing the same
KR20160049232A (en) Modeling Method of Healthy, Safety and Environment Management Processes on Nuclear Power plant Construction Project
Teizer et al. BIM for construction safety and health
KR20130134650A (en) Dangerousness work permission managing system of the drillship
Zimmerman et al. Process safety management best practice: safe work permit management system
Stout et al. From strategy to reality: 25 years of planning and progress in occupational injury research
Chhillar et al. Safety Management with Application of Internet of Things, Artificial Intelligence, and Machine Learning for Industry 4.0 Environment
KR20120067468A (en) System for preventing industrial accident in shipbuilding
Szabó The characteristics of industrial safety risk management
JP6940362B2 (en) Assembly procedure display system
Courtway Wearables, augmented and virtual reality, integrated project delivery, and artificial intelligence

Legal Events

Date Code Title Description
WITN Withdrawal due to no request for examination