KR20130034535A - Electric power computation system - Google Patents

Electric power computation system Download PDF

Info

Publication number
KR20130034535A
KR20130034535A KR1020110098595A KR20110098595A KR20130034535A KR 20130034535 A KR20130034535 A KR 20130034535A KR 1020110098595 A KR1020110098595 A KR 1020110098595A KR 20110098595 A KR20110098595 A KR 20110098595A KR 20130034535 A KR20130034535 A KR 20130034535A
Authority
KR
South Korea
Prior art keywords
unit
inlet temperature
data
electric power
power generation
Prior art date
Application number
KR1020110098595A
Other languages
Korean (ko)
Inventor
황광원
장철호
안영모
Original Assignee
한국전력공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국전력공사 filed Critical 한국전력공사
Priority to KR1020110098595A priority Critical patent/KR20130034535A/en
Publication of KR20130034535A publication Critical patent/KR20130034535A/en

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R21/00Arrangements for measuring electric power or power factor
    • G01R21/14Compensating for temperature change
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R22/00Arrangements for measuring time integral of electric power or current, e.g. electricity meters
    • G01R22/06Arrangements for measuring time integral of electric power or current, e.g. electricity meters by electronic methods
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Power Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Control Of Eletrric Generators (AREA)

Abstract

PURPOSE: An electric power computation system is provided to track the electric output amount and compute an exact electric power amount by using exact compressor inlet temperature prediction data and corrected compressor inlet temperature data of a complex electric power generating facility. CONSTITUTION: An electric power computation system(100) comprises following: an inlet temperature estimating unit(110) which tracks the atmosphere temperature for each time slot on a following day by using weather information of a certain location and reliably estimating a compressor inlet temperature; a corrected data acquisition unit(120) which acquires corrected inlet temperature of the compressor which is provided by a power plant supplier; a data gathering unit(130) which the corrected data obtained by acquiring the data indicated from a gas turbine output and a steam turbine output power generating system; an electrical output amount change detection unit(140) which calculates the amount of change of the electrical output by using the data gathered from the data gathering unit; and an electric power computing unit(150) which computes the electric power depending on the amount of change of the electrical output. [Reference numerals] (110) Inlet temperature estimating unit; (120) Corrected data acquisition unit; (130) Data gathering unit; (140) Electrical output amount change detection unit; (150) Electric power computing unit; (160) Abnormality inspection unit; (170) Display unit; (200) Bidding system;

Description

발전량 산정 시스템{ELECTRIC POWER COMPUTATION SYSTEM}Power Generation Calculation System {ELECTRIC POWER COMPUTATION SYSTEM}

본 발명은 발전량 산정 시스템에 관한 것이다.
The present invention relates to a power generation calculation system.

국가 전체의 전력수요에 맞춰 빈틈없는 전력수급계획 수립과 경제급전 도모, 발전설비의 효율적 운용과 발전사업의 수익성 증대를 달성하기 위해서 발전사업자는 정확한 발전량을 입찰해야 한다. 또한 국내외 전력산업 환경이 크게 변화되어 전력시장의 기능이 강화되면서 발전설비와 전력시장 운영 측면에서 정확한 발전량 입찰이 강조되고 있으며, 입찰한 발전량 준수에 대한 규제도 점차 강화되고 있는 한편 압축기 입구온도 변화에 따라 복합발전설비의 전기출력이 크게 변하기 때문에 이러한 압축기 입구온도 변화에 따른 전기출력 변화량을 파악하고 정확한 발전량을 산정하는 것이 필요하다.In order to achieve a seamless power supply and demand plan, promote economic power supply, efficiently operate power generation facilities, and increase profitability of power generation projects, power generation companies must bid the exact amount of power generation. In addition, as the environment of the domestic and overseas power industry has changed drastically, the function of the power market has been strengthened, and the bidding for accurate power generation is emphasized in terms of power generation facilities and operation of the power market. Accordingly, since the electrical output of the combined cycle installation is greatly changed, it is necessary to grasp the change in electrical output according to the change of the compressor inlet temperature and to calculate the exact amount of power generation.

기존에는 부정확한 발전량 추정으로 정확한 발전량 입찰이 미흡할 뿐만 아니라 복합발전설비의 전기출력 변화에 큰 영향을 주는 압축기 입구온도를 객관적으로 반영하지 못하고, 과거 운전실적, 경험치 등의 경험 자료에 의존하여 발전량을 추정하기 때문에 정확한 발전량을 산정하는데 어려움이 있었다.
Previously, accurate power generation bidding was insufficient due to inaccurate power generation, and it did not objectively reflect the compressor inlet temperature, which greatly affects the change in the electric output of the combined cycle power plant. It is difficult to estimate the exact amount of power generation because of

한국공개특허 제10-2008-0123456호Korean Patent Publication No. 10-2008-0123456

상술한 종래 기술의 문제점을 해결하기 위해, 본 발명은 정확한 압축기 입구온도 예측자료와 발전설비 공급자가 제공한 해당 복합발전설비의 압축기 입구온도 보정자료를 이용하여 전기출력 변화량을 파악하고 정확한 발전량을 산정하는 발전량 산정 시스템을 제공한다.In order to solve the above problems of the prior art, the present invention uses the accurate compressor inlet temperature prediction data and the compressor inlet temperature correction data of the corresponding complex power generation equipment provided by the power generation equipment supplier to determine the change in electric output and calculate the exact power generation amount. It provides a power generation calculation system.

본 발명의 목적들은 이상에서 언급한 목적들로 제한되지 않으며, 언급되지 않은 또 다른 목적들은 아래의 기재로부터 명확하게 이해될 수 있을 것이다.
The objects of the present invention are not limited to the above-mentioned objects, and other objects not mentioned can be clearly understood from the following description.

상기 목적을 달성하기 위하여, 본 발명의 일 측면에 따른 발전량 산정 시스템은 발전기 소재 지역의 기상 정보를 이용하여 익일 시간대별 대기온도를 파악하고 신뢰성 있는 압축기 입구온도를 예측하는 입구온도 예측부, 발전설비 공급자가 제공한 압축기의 입구온도에 대한 보정자료를 취득하는 보정자료 취득부, 가스터빈출력, 증기터빈출력을 발전소에서 지시되는 데이터를 취득하여 확보된 보정자료를 취합하는 자료 취합부, 상기 자료 취합부에서 취합된 데이터를 이용하여 전기출력 변화량을 계산하는 전기출력 변화량 검출부 및 상기 전기출력 변화량에 따른 발전량을 산정하는 발전량 산정부를 포함한다.In order to achieve the above object, the power generation amount estimation system according to an aspect of the present invention using the weather information of the region of the generator, the inlet temperature predicting unit for grasping the air temperature for each hour of the next day and predicting the reliable compressor inlet temperature, power generation equipment Compensation data acquisition unit for acquiring correction data for the inlet temperature of the compressor provided by the supplier, data collection unit for acquiring the data instructed by the power plant for gas turbine output, steam turbine output, and collecting the data An electric output change detection unit for calculating an electric output change amount using the data collected by the unit and a power generation calculation unit for calculating the electric power generation amount according to the electric output change amount.

본 발명의 일 측면에서, 발전량 산정 시스템은 산정된 발전량과 생상된 발전량을 비교 분석하여 이상 유무를 점검하는 이상 점검부를 더 포함할 수 있다.In one aspect of the present invention, the power generation amount calculation system may further include an abnormality check unit for checking the presence or absence by comparing and analyzing the calculated power generation amount and the generated power generation amount.

상기 목적을 달성하기 위한 구체적인 사항들은 첨부된 도면과 함께 상세하게 후술된 실시예들을 참조하면 명확해질 것이다.BRIEF DESCRIPTION OF THE DRAWINGS The above and other objects, features and advantages of the present invention will be more apparent from the following detailed description taken in conjunction with the accompanying drawings, in which: FIG.

그러나 본 발명은 이하에서 개시되는 실시예들에 한정되는 것이 아니라, 서로 다른 다양한 형태로 구성될 수 있으며, 본 실시예들은 본 발명의 개시가 완전하도록 하고 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공되는 것이다.
The present invention may, however, be embodied in many different forms and should not be construed as being limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the invention to those skilled in the art. It is provided to fully inform the owner of the scope of the invention.

본 발명의 일 실시 예에 따른 발전량 산정 시스템은 복합발전소에서 압축기 입구온도에 변화에 따라 전기출력이 크게 변화되는(500 MW설비의 압축기 입구온도 20℃ 변화에 약 35MW 변화) 특성을 반영하여 전기출력 변화량을 정확하게 산정 후 전력거래입찰을 할 수 있다. 이러한 발전량 산정 시스템은 입찰한 발전량 준수에 대한 규제가 강화되고 있는 상황에서 복합발전설비의 전기출력 변화에 큰 영향을 주는 압축기 입구온도의 신뢰성 있는 자료를 예측하고 발전설비 공급자가 제공한 압축기 입구온도 보정자료를 이용하여 전기출력 변화량을 파악한다. 그리고 발전량 산정 시스템은 정확한 발전량을 산정하여 입찰함으로써 국가 전체의 전력수요에 맞춰 빈틈없는 전력수급계획 수립과 경제급전으로 전력시장의 안정적 운영과 전력거래의 신뢰성을 향상시킬 수 있다. 또한, 발전량 산정 시스템은 발전설비의 효율적 운용과 발전사업의 수익성을 증대시킬 뿐만 아니라 입찰 발전량을 준수해야 하는 전력시장 규제에 대해서도 적극적으로 대처해나갈 수 있다.
The power generation calculation system according to an embodiment of the present invention reflects the characteristics of the electric power greatly changing according to the change of the compressor inlet temperature in the complex power plant (about 35MW change in the compressor inlet temperature of 20 M in 500 MW equipment). After accurately calculating the amount of change, you can bid for electricity trade. This generation calculation system predicts the reliable data of the compressor inlet temperature, which greatly affects the change in the electrical output of the combined cycle power plant under the tightening regulations on the bid generation, and corrects the compressor inlet temperature provided by the power plant supplier. Use the data to identify changes in electrical output. In addition, the power generation calculation system calculates and bids the correct amount of power generation so that the stable operation of the power market and the reliability of power transactions can be improved by establishing a power supply and demand plan and an economic power supply in accordance with the nation's electric power demand. In addition, the power generation calculation system not only increases the efficient operation of the power generation facilities and increases the profitability of the power generation business, but also can actively cope with the regulation of the power market, which must comply with the bidding generation amount.

도 1은 본 발명의 일 실시예에 따른 발전량 산정 시스템을 나타내는 블록도이다.
도 2는 본 발명의 일 실시 예에 따른 발전량 산정 시스템에서 사용되는 복합 전기출력 보정곡선을 나타내는 도면이다.
도 3은 본 발명의 일 실시 예에 따른 발전량 산정 시스템의 정보를 나타내는 도면이다.
1 is a block diagram showing a power generation calculation system according to an embodiment of the present invention.
2 is a view showing a complex electric power output correction curve used in the power generation calculation system according to an embodiment of the present invention.
3 is a view showing information of the power generation amount calculation system according to an embodiment of the present invention.

본 발명은 다양한 변경을 가할 수 있고 여러 가지 실시예를 가질 수 있는 바, 특정 실시예들을 도면에 예시하고 이를 상세한 설명을 통해 상세히 설명하고자 한다.The present invention may be variously modified and have various embodiments, and specific embodiments will be illustrated in the drawings and described in detail with reference to the accompanying drawings.

그러나, 이는 본 발명을 특정한 실시 형태에 대해 한정하려는 것이 아니며, 본 발명의 사상 및 기술 범위에 포함되는 모든 변경, 균등물 내지 대체물을 포함하는 것으로 이해되어야 한다.It should be understood, however, that the invention is not intended to be limited to the particular embodiments, but includes all modifications, equivalents, and alternatives falling within the spirit and scope of the invention.

본 발명을 설명함에 있어서, 관련된 공지 기술에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우 그 상세한 설명을 생략한다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.

이하, 첨부된 도면들을 참조하여 본 발명의 실시를 위한 구체적인 내용을 설명하도록 한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명의 일 실시예에 따른 발전량 산정 시스템을 나타내는 블록도이다.1 is a block diagram showing a power generation calculation system according to an embodiment of the present invention.

도 1을 참조하면, 본 발명의 일 실시 예에 따른 발전량 산정 시스템은 입구온도 예측부(110), 보정자료 취득부(120), 자료 취합부(130), 전기출력 변화량 검출부(140), 발전량 산정부(150), 이상 점검부(160) 및 표시부(170)를 포함한다.Referring to FIG. 1, the power generation amount estimating system according to an exemplary embodiment of the present invention includes an inlet temperature predicting unit 110, a correction data acquiring unit 120, a data collecting unit 130, and an electric output change detecting unit 140. The calculation unit 150, the abnormality check unit 160 and the display unit 170 is included.

우선, 전력거래소에 전력 거래를 위한 입찰용 발전량 결정은 입찰마감 시한(예컨대 1일전 10시까지) 전까지 익일 예상 발전량을 결정하여 입찰해야 한다.First, in order to determine the amount of power generation for bidding for power trading on the power exchange, the bidding should be made by determining the expected amount of power generation the next day before the bid deadline (for example, until 10 o'clock one day before).

입구온도 예측부(110)는 발전기 소재 지역의 기상 정보를 이용하여 익일 시간대별 대기온도를 파악하여 신뢰성 있는 압축기 입구온도를 예측한다. 여기서 입구온도 예측부(110)는 아래의 표 1과 같은 기상 정보를 취득할 수 있다.The inlet temperature predictor 110 predicts a reliable compressor inlet temperature by grasping the air temperature according to the next day's time zone using weather information of the region where the generator is located. Here, the inlet temperature predictor 110 may acquire weather information as shown in Table 1 below.

익일시간대Next day 00 33 66 99 1212 1515 1818 2121 2424 대기온도(℃)Atmospheric temperature (℃) 1212 1313 1515 1616 2424 2727 2323 1717 1414

보정자료 취득부(120)는 발전설비 공급자가 제공한 압축기 입구온도 보정자료를 취득하여 확보한다. 여기서 보정자료 취득부(120)는 도 2에 도시된 발전소별 대기온도에 따른 복합 전기출력 보정곡선(300)을 이용하여 입구온도 예측부(110)에서 예측된 익일 대기온도에 해당되는 출력보정 팩터(factor)(Ck)를 매 시간대별로 계산할 수 있다.The correction data acquisition unit 120 acquires and secures the compressor inlet temperature correction data provided by the power supplier. Here, the correction data acquisition unit 120 outputs a power correction factor corresponding to the next-day air temperature predicted by the inlet temperature predictor 110 using the complex electric output correction curve 300 according to the air temperature of each power plant shown in FIG. 2. The factor (Ck) can be calculated for each time zone.

도 2는 본 발명의 일 실시 예에 따른 발전량 산정 시스템에서 사용되는 복합 전기출력 보정곡선을 나타내는 도면이다.2 is a view showing a complex electric power output correction curve used in the power generation calculation system according to an embodiment of the present invention.

자료 취합부(130)는 확보된 보정 자료를 취합한다. 여기서 자료 취합부(130)는 가스터빈 출력 및 증기터빈 출력 등의 발전소에서 지시하는 데이터를 취득할 수 있다. 그리고 자료 취합부(130)는 발전소에서 지시하는 데이터를 취합할 수 있다.The data collecting unit 130 collects the obtained correction data. Here, the data collection unit 130 may acquire data instructed by a power plant, such as a gas turbine output and a steam turbine output. The data collection unit 130 may collect data instructed by the power plant.

전기출력 변화량 검출부(140)는 전기출력 변화량을 계산한다. 여기서 전기출력 변화량 검출부(140)는 전기출력 변화량으로 복합전기출력 정격치를 계산할 수 있다. 이때, 전기출력 변화량 검출부(140)는 자료 취합부(130)에서 취합된 데이터를 이용하여 아래의 수학식 1을 통해 복합전기출력 정격치를 계산할 수 있다.The electrical output variation detecting unit 140 calculates the electrical output variation. Herein, the electrical output variation detecting unit 140 may calculate the composite electrical output rated value as the electrical output variation. In this case, the electrical output variation detection unit 140 may calculate the composite electrical output rating value through Equation 1 below using the data collected by the data collection unit 130.

[수학식 1][Equation 1]

ΣPOBASE = POGT1 + POGT2 + POST ΣPO BASE = PO GT1 + PO GT2 + PO ST

수학식 1에서 ΣPOBASE는 복합전기출력 정격치(kW)이고, POGT1는 1호기 가스터빈출력 정격치(kW)이고, POGT2는 2호기 가스터빈출력 정격치(kW)이며, POST는 증기터빈출력 정격치(kW)이다.In Equation 1, ΣPO BASE is the combined electric output rated value (kW), PO GT1 is the unit 1 gas turbine output rated value (kW), PO GT2 is the unit 2 gas turbine output rated value (kW), and PO ST is the steam turbine output. Rated value (kW).

발전량 산정부(150)는 전기출력 변화량에 따른 발전량을 산정한다. 여기서 발전량 산정부(150)는 전기출력 변화량 검출부(140)에서 계산된 복합전기출력 정격치와 대기온도에 해당되는 출려보정 팩터(Ck)를 이용하여 아래의 수학식 2를 통해 대기온도에 따라 보정된 복합전기출력을 계산할 수 있다.The generation amount calculation unit 150 calculates the generation amount according to the change amount of electric output. Here, the generation amount calculation unit 150 is corrected according to the atmospheric temperature through the following equation 2 using the output correction factor (Ck) corresponding to the combined electric output rated value calculated by the electrical output change detection unit 140 and the atmospheric temperature. The complex electrical output can be calculated.

[수학식 2]&Quot; (2) "

POCORRECTED = ΣPOBASE ㅧ CkPO CORRECTED = ΣPO BASE ㅧ Ck

수학식 2에서 POCORRECTED는 대기온도에 따라 보정된 복합전기출력(kW)이고, ΣPOBASE는 복합전기출력 정격치(kW)이며, Ck는 대기온도에 해당되는 출력보정 팩터이다.In Equation 2, PO CORRECTED is a composite electrical output (kW) corrected according to the ambient temperature, ΣPO BASE is a composite electrical output rated value (kW), and Ck is an output correction factor corresponding to the ambient temperature.

이러한 발전량 산정부(150)는 산정된 발전량을 입찰 시스템(200)에 제공할 수 있다.The generation amount calculation unit 150 may provide the calculated generation amount to the bidding system 200.

이상 점검부(160)는 산정된 발전량과 생산된 발전량을 비교하고 분석하여 이상 유무를 점검한다. 여기서 이상 점검부(160)는 발전량 산정값과 발전량 생산값의 비교를 통해 계산의 적정성을 점검할 수 있다.The abnormality checker 160 checks the abnormality by comparing and analyzing the calculated power generation amount and the generated power generation amount. Here, the abnormality checking unit 160 may check the adequacy of the calculation by comparing the generation amount calculation value and the generation amount production value.

표시부(170)는 입구온도 예측부(110), 보정자료 취득부(120), 자료 취합부(130), 전기출력 변화량 검출부(140), 발전량 산정부(150) 또는 이상 점검부(160) 각각에서 출력되는 정보를 표시한다. 여기서 표시부(170)는 도 3에 도시된 바와 같이 각종 정보를 표시할 수 있다.The display unit 170 includes an inlet temperature predicting unit 110, a correction data obtaining unit 120, a data collecting unit 130, an electric output change detection unit 140, a power generation calculation unit 150, or an abnormality checking unit 160. Display information output from. The display unit 170 may display various types of information as shown in FIG. 3.

도 3은 본 발명의 일 실시 예에 따른 발전량 산정 시스템의 정보를 나타내는 도면이다.3 is a view showing information of the power generation amount calculation system according to an embodiment of the present invention.

상술한 바와 같이 본 발명의 일 실시 예에 따른 발전량 산정 시스템은 복합발전소에서 압축기 입구온도에 변화에 따라 전기출력이 크게 변화되는(500 MW설비의 압축기 입구온도 20℃ 변화에 약 35MW 변화) 특성을 반영하여 전기출력 변화량을 정확하게 산정 후 전력거래입찰을 할 수 있다. 이러한 발전량 산정 시스템은 입찰한 발전량 준수에 대한 규제가 강화되고 있는 상황에서 복합발전설비의 전기출력 변화에 큰 영향을 주는 압축기 입구온도의 신뢰성 있는 자료를 예측하고 발전설비 공급자가 제공한 압축기 입구온도 보정자료를 이용하여 전기출력 변화량을 파악한다. 그리고 발전량 산정 시스템은 정확한 발전량을 산정하여 입찰함으로써 국가 전체의 전력수요에 맞춰 빈틈없는 전력수급계획 수립과 경제급전으로 전력시장의 안정적 운영과 전력거래의 신뢰성을 향상시킬 수 있다. 또한, 발전량 산정 시스템은 발전설비의 효율적 운용과 발전사업의 수익성을 증대시킬 뿐만 아니라 입찰 발전량을 준수해야 하는 전력시장 규제에 대해서도 적극적으로 대처해나갈 수 있는 효과가 있다.As described above, the power generation amount estimating system according to an embodiment of the present invention has a characteristic in which the electric output is greatly changed according to the change in the compressor inlet temperature in the combined cycle power plant (about 35MW change in the 20 ℃ change in the compressor inlet temperature of the 500 MW facility). After reflecting the exact amount of electricity output change, it is possible to make a bid for electricity trade. This generation calculation system predicts the reliable data of the compressor inlet temperature, which greatly affects the change in the electrical output of the combined cycle power plant under the tightening regulations on the bid generation, and corrects the compressor inlet temperature provided by the power plant supplier. Use the data to identify changes in electrical output. In addition, the power generation calculation system calculates and bids the correct amount of power generation so that the stable operation of the power market and the reliability of power transactions can be improved by establishing a power supply and demand plan and an economic power supply in accordance with the nation's electric power demand. In addition, the power generation calculation system not only increases the efficient operation of the power generation facilities and increases the profitability of the power generation business, but also has the effect of actively coping with power market regulations that must comply with the bidding generation amount.

이상의 설명은 본 발명의 기술 사상을 예시적으로 설명한 것에 불과한 것으로서, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자라면 본 발명의 본질적인 특성에서 벗어나지 않는 범위에서 다양한 수정 및 변형이 가능할 것이다.The foregoing description is merely illustrative of the technical idea of the present invention, and various changes and modifications may be made by those skilled in the art without departing from the essential characteristics of the present invention.

따라서, 본 발명에 개시된 실시 예들은 본 발명의 기술 사상을 한정하기 위한 것이 아니라 설명하기 위한 것이고, 이러한 실시 예에 의하여 본 발명의 기술 사상의 범위가 한정되는 것은 아니다.Therefore, the embodiments disclosed in the present invention are intended to illustrate rather than limit the scope of the present invention, and the scope of the technical idea of the present invention is not limited by these embodiments.

본 발명의 보호 범위는 아래의 청구범위에 의하여 해석되어야 하며, 그와 동등한 범위 내에 있는 모든 기술 사상은 본 발명의 권리범위에 포함되는 것으로 해석되어야 할 것이다.
The scope of protection of the present invention should be construed according to the following claims, and all technical ideas falling within the scope of the same shall be construed as falling within the scope of the present invention.

100: 발전량 산정 시스템
110: 입구온도 예측부
120: 보정자료 취득부
130: 자료 취합부
140: 전기출력 변화량 검출부
150: 발전량 산정부
160: 이상 점검부
170: 표시부
200: 입찰 시스템
100: power generation calculation system
110: inlet temperature predictor
120: correction data acquisition unit
130: data collector
140: electrical output change detection unit
150: power generation
160: abnormal inspection unit
170:
200: bidding system

Claims (2)

발전기 소재 지역의 기상 정보를 이용하여 익일 시간대별 대기온도를 파악하고 신뢰성 있는 압축기 입구온도를 예측하는 입구온도 예측부;
발전설비 공급자가 제공한 압축기의 입구온도에 대한 보정자료를 취득하는 보정자료 취득부;
가스터빈출력, 증기터빈출력을 발전소에서 지시되는 데이터를 취득하여 확보된 보정자료를 취합하는 자료 취합부;
상기 자료 취합부에서 취합된 데이터를 이용하여 전기출력 변화량을 계산하는 전기출력 변화량 검출부; 및
상기 전기출력 변화량에 따른 발전량을 산정하는 발전량 산정부를 포함하는 발전량 산정 시스템.
An inlet temperature predicting unit for estimating the air temperature by the next day's time zone and predicting a reliable compressor inlet temperature by using weather information of a generator region;
A correction data acquisition unit for acquiring correction data for the inlet temperature of the compressor provided by the power generation equipment supplier;
A data collecting unit which collects correction data obtained by acquiring data indicative of gas turbine output and steam turbine output from the power plant;
An electrical output variation detection unit configured to calculate an electrical output variation using the data collected by the data collection unit; And
A generation amount calculation system comprising a generation amount calculation unit for calculating a generation amount according to the change amount of the electric output.
제1 항에 있어서,
산정된 발전량과 생상된 발전량을 비교 분석하여 이상 유무를 점검하는 이상 점검부를 더 포함하는 발전량 산정 시스템.
The method according to claim 1,
A generation amount calculation system further comprising an abnormality checker for checking whether there is an abnormality by comparing and analyzing the calculated power generation amount and the generated power generation amount.
KR1020110098595A 2011-09-28 2011-09-28 Electric power computation system KR20130034535A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110098595A KR20130034535A (en) 2011-09-28 2011-09-28 Electric power computation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110098595A KR20130034535A (en) 2011-09-28 2011-09-28 Electric power computation system

Publications (1)

Publication Number Publication Date
KR20130034535A true KR20130034535A (en) 2013-04-05

Family

ID=48436645

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110098595A KR20130034535A (en) 2011-09-28 2011-09-28 Electric power computation system

Country Status (1)

Country Link
KR (1) KR20130034535A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107918822A (en) * 2017-10-09 2018-04-17 广东核电合营有限公司 A kind of method assessed in fortune nuclear power plant steam turbine output hoisting power
KR20210022910A (en) 2019-08-21 2021-03-04 한국남동발전 주식회사 Solar Energy Business Development Business Platform and its Operating Methods

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107918822A (en) * 2017-10-09 2018-04-17 广东核电合营有限公司 A kind of method assessed in fortune nuclear power plant steam turbine output hoisting power
CN107918822B (en) * 2017-10-09 2021-09-24 广东核电合营有限公司 Method for evaluating output lifting capacity of steam turbine in nuclear power plant
KR20210022910A (en) 2019-08-21 2021-03-04 한국남동발전 주식회사 Solar Energy Business Development Business Platform and its Operating Methods

Similar Documents

Publication Publication Date Title
Schmidt et al. Implementing key performance indicators for energy efficiency in manufacturing
Bastidas-Rodríguez et al. Model-based degradation analysis of photovoltaic modules through series resistance estimation
US8290745B2 (en) Systems and methods for identifying faulty sensors within a power generation system
KR101300101B1 (en) Device for verifying electric energy data, system for verifying electric energy data including the same, and method of verifying electric energy data
US20160356859A1 (en) Fault detection in energy generation arrangements
US20200191854A1 (en) Accurate detection and correction of technical and non-technical losses using smart metering
US20180252753A1 (en) Distributed-Generator Power-Generation-Amount Estimation Apparatus and Method
CN111999691B (en) Error calibration method and error calibration device for metering sensor device
KR20130034535A (en) Electric power computation system
CN104158489B (en) The monitoring method of photovoltaic plant and power station monitoring system
JPH11229820A (en) Thermal efficiency diagnosis and device of thermal power plant
CN117314257A (en) Single ship construction carbon footprint accounting method, system and electronic equipment
Golub et al. Climate Change and the Vulnerability of Germany’s Power Sector to Heat and Drought
Coroiu et al. Energy efficiency indicators and methodology for evaluation of energy performance and retained savings
JP5892892B2 (en) Indicator for photovoltaic power generation
US8738326B2 (en) Performance characteristic calculation and comparison
KR101115163B1 (en) Billing data creation system and method
CN113095532A (en) Photovoltaic power station power generation real-time power prediction system and implementation method thereof
Keatley Cost modelling of coal power plant start-up in cyclical operation
JP2016197948A (en) Power estimation device and power estimation method
Galvão et al. Sustainable energy for plastic industry plant
JP6190438B2 (en) Power generation data collection system and solar power generation device
Zhu et al. The effects analysis of measurement anomaly in electricity settlement of provincial generation power market
US11573098B1 (en) Method and system to detect non-technical losses in an electrical power system
CN117471366B (en) Metering device neutral line contact failure studying and judging method based on least square method

Legal Events

Date Code Title Description
WITN Application deemed withdrawn, e.g. because no request for examination was filed or no examination fee was paid