KR20130023538A - Concrete composite wall construction method with inner insulation, composite shear connector and composite form-tie - Google Patents

Concrete composite wall construction method with inner insulation, composite shear connector and composite form-tie Download PDF

Info

Publication number
KR20130023538A
KR20130023538A KR1020110086374A KR20110086374A KR20130023538A KR 20130023538 A KR20130023538 A KR 20130023538A KR 1020110086374 A KR1020110086374 A KR 1020110086374A KR 20110086374 A KR20110086374 A KR 20110086374A KR 20130023538 A KR20130023538 A KR 20130023538A
Authority
KR
South Korea
Prior art keywords
composite
heat
tie
insulating material
wall
Prior art date
Application number
KR1020110086374A
Other languages
Korean (ko)
Other versions
KR101292523B1 (en
Inventor
유영찬
최기선
김준희
강재식
김호룡
최경석
Original Assignee
한국건설기술연구원
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국건설기술연구원 filed Critical 한국건설기술연구원
Priority to KR1020110086374A priority Critical patent/KR101292523B1/en
Publication of KR20130023538A publication Critical patent/KR20130023538A/en
Application granted granted Critical
Publication of KR101292523B1 publication Critical patent/KR101292523B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/842Walls made by casting, pouring, or tamping in situ by projecting or otherwise applying hardenable masses to the exterior of a form leaf
    • E04B2/847Walls made by casting, pouring, or tamping in situ by projecting or otherwise applying hardenable masses to the exterior of a form leaf the form leaf comprising an insulating foam panel
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • E04B2/8635Walls made by casting, pouring, or tamping in situ made in permanent forms with ties attached to the inner faces of the forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G9/00Forming or shuttering elements for general use
    • E04G9/10Forming or shuttering elements for general use with additional peculiarities such as surface shaping, insulating or heating, permeability to water or air

Abstract

PURPOSE: A concrete composite wall construction method is provided to hold the position of an insulator and to effectively prevent energy loss by installing a composite form tie for connecting a sandwich wall panel. CONSTITUTION: A concrete composite wall construction method comprises the following steps: pre-assembling and installing an insulator(110) and a composite connecting material between an euro form(210) and a gang form(220) for installing to the external wall of a building; interconnecting the gang form and euro form by a composite form tie and passing the composite form tie(400) through the insulator; and forming a concrete wall by pouring concrete(C) between the euro form and gang form. [Reference numerals] (AA) Cutting; (BB) Steel material

Description

합성 폼타이를 이용한 현장 중단열벽체 시공방법{CONCRETE COMPOSITE WALL CONSTRUCTION METHOD WITH INNER INSULATION, COMPOSITE SHEAR CONNECTOR AND COMPOSITE FORM-TIE}Construction method of construction site suspended thermal wall using composite form ties {CONCRETE COMPOSITE WALL CONSTRUCTION METHOD WITH INNER INSULATION, COMPOSITE SHEAR CONNECTOR AND COMPOSITE FORM-TIE}

본 발명은 합성 폼타이를 이용한 현장 중단열벽체 시공방법에 관한 것이다. 더욱 구체적으로 단열재를 현장에 세팅된 갱폼과 유로폼 사이에 설치하되, 상기 단열재를 합성 폼타이가 관통하도록 하고 갱폼과 유로폼 사이에 콘크리트를 타설하여 중단열벽체를 시공할 수 있도록 한 현장 중단열벽체 시공방법에 관한 것이다.The present invention relates to a method for constructing a site suspended hot wall using a synthetic form tie. More specifically, the insulating material is installed between the gangform and the euroform set in the field, but the construction of the site suspended heat wall to allow the composite foam tie to penetrate the insulating material and to install the suspended heating wall by placing concrete between the gangform and the euroform. It is about a method.

기존의 콘크리트벽체 구조에서는 예컨대 도 1a와 같이 건물의 외측벽체(40)의 내측에 단열재(10)를 설치하는 내단열(內斷熱) 구조를 채택하고 있어, 바닥 난방(20)이 주종을 이루고 있는 우리나라의 공동주택에서는 특히 바닥슬래브(30)를 통하여 외측벽체(40)로 유출되는 난방 에너지의 손실이 문제점으로 지적되고 있다.In the existing concrete wall structure, for example, as shown in Figure 1a adopts a heat-insulating structure that installs the heat insulator 10 inside the outer wall 40 of the building, the floor heating 20 is the dominant In the multi-family house in Korea, the loss of heating energy flowing out to the outer wall 40 through the floor slab 30 is pointed out as a problem.

이에 지구온난화 방지를 목적으로 범국가적으로 추진되고 있는 제로에너지ㆍ제로카본 빌딩구조물 구현을 위한 요소기술의 하나인 외단열(外斷熱) 구조는 도 1b와 같이 바닥슬래브(30)를 통하여 외측벽체(40)까지 전달된 난방에너지가 상기 외측벽체(40)의 외측에 설치된 단열재(10)에 의해 차단되므로 높은 에너지 절감효과를 기대할 수 있도록 하는 구조이다.Accordingly, the outer insulation structure, which is one of the element technologies for realizing zero energy and zero carbon building structures, which are being promoted nationwide for the purpose of preventing global warming, is formed through an outer wall through the floor slab 30 as shown in FIG. Since the heating energy transmitted up to 40 is blocked by the heat insulating material 10 installed on the outer side of the outer wall 40, it is a structure that can expect a high energy saving effect.

하지만, 이와 같은 외단열 구조의 경우 단열재(10)를 외측벽체의 외측에 설치하기 위해서는 외부작업을 위한 비계설치, 보호마감재(50) 추가시공 등의 시공 상의 어려움 및 외기환경에 노출된 단열재의 내구성 측면에서의 문제점으로 인하여 아직까지 본격적인 실용화 단계에는 이르지 못하고 있다.However, in the case of the external insulation structure, in order to install the heat insulating material 10 on the outside of the outer wall, construction difficulties such as scaffolding for external work, additional construction of the protective finishing material 50, and durability of the heat insulating material exposed to the outdoor environment. Due to the problems in the aspect it has not yet reached the stage of full-scale commercialization.

이와 같은 내단열구조의 단점과 외단열구조의 장ㆍ단점을 선택적으로 취합하기 위하여 도 1c와 같이 콘크리트벽체(A,B)의 중간에 단열재(10)를 삽입하는 소위 중단열(中斷熱) 구조의 벽체에 대한 개념이 소개된 바 있다.In order to selectively collect the disadvantages of the heat resistant structure and the advantages and disadvantages of the external heat insulating structure, a so-called middle heat structure for inserting the heat insulating material 10 in the middle of the concrete walls A and B as shown in FIG. 1C. The concept of the wall was introduced.

말하자면 단열재를 콘크리트벽체 사이에 형성시킨 샌드위치 패널 형태의 벽체들을 외측벽체로써 부착 시공하는 방식을 따른 것이다.In other words, the sandwich panel-type walls in which the insulation is formed between the concrete walls are attached to the outer wall.

도 1d 및 도 1e는 종래 콘크리트벽체를 갱폼(2)과 유로폼(1)을 이용하여 시공하는 일예를 사시도와 단면도로 도시한 것이다.1D and 1E show a perspective view and a cross-sectional view of an example in which a conventional concrete wall is constructed using the gang form 2 and the flow path 1.

이를 구체적으로 살펴보면, 유로폼(1, 콘크리트벽체용 내측거푸집)은 철재(강재)를 소재로 하여 일정규격으로 제작된 패널 형태의 부재이고, 상기 갱폼(2,,콘크리트벽체용 외측거푸집)은 일정 두께를 갖는 평철판(21)과 그 일면에는 각파이프로 된 복수개의 가로바(22)가 일정간격을 유지한 채 각기 하나씩 한줄상으로 용접되어 있으며, 또한 여러 줄 형성된 가로바(22)에는 두개가 서로 인접한 상태로 한쌍을 이루는 세로바(21)들이 일정간격을 두고 여러 쌍이 용접되어 있다.Specifically, the Euroform (1, the inner formwork for the concrete wall) is a member of the panel form made of steel (steel) material to a certain standard, the gangform (2, the outer formwork for the concrete wall) is a certain thickness A flat iron plate 21 having a plurality of horizontal bars (22) made of square pipes are welded one by one on each side while maintaining a constant interval, and two horizontal bars (22) formed on several lines Several pairs of vertical bars 21 in a state adjacent to each other are welded at a predetermined interval.

그리고 상기 갱폼(2)의 평철판(21)에는 도 1e와 같이 다수의 삽입공(24)이 뚫어져 있는데, 상기한 각 삽입공(24)들은 한쌍을 이루고 있는 두개의 세로바(23)들 사이에 위치하도록 형성되어 있으며, 상기한 다수의 삽입공(24)들에는 갱폼지지콘(25)이 각기 하나씩 조립되어 있다.In addition, a plurality of insertion holes 24 are drilled in the flat iron plate 21 of the gangform 2 as shown in FIG. 1E, and each of the insertion holes 24 is formed between a pair of two vertical bars 23. Is formed to be located, the gang foam support cones 25 are assembled to each of the plurality of insertion holes 24, one by one.

상기 유로폼(1)과 갱폼(2)은 체결장치에 의하여 일정간격으로 설치되는데, 상기 체결장치는, 유로폼(1)에 일단이 고정된 채 갱폼(2)을 지지하는 간격유지구(3)와, 상기 갱폼(2)에 용접되어 있는 한쌍의 세로바(23) 사이를 통해 삽입공(24)에 조립된 갱폼지지콘(25)을 관통하여 간격유지구(3)의 연결너트체(31)에 나사결합되는 나사부(41)가 형성된 체결구(4)와, 상기 체결구(4)의 타단에 형성된 채 세로바(23)의 외측으로 돌출되는 평판체결부(42)의 조립공(43)에 끼움되는 체결용 웨지핀(5)으로 구성되어 있다.The flow path (1) and the gang form (2) is installed at a predetermined interval by the fastening device, the fastening device, and the interval holding hole (3) for supporting the gang form (2) with one end fixed to the flow path (1) The connection nut body 31 of the spacing holder 3 passes through the gang form support cone 25 assembled in the insertion hole 24 through a pair of longitudinal bars 23 welded to the gang form 2. A fastener 4 having a threaded portion 41 screwed thereon and an assembly hole 43 of a flat plate fastening portion 42 protruding outward of the vertical bar 23 while being formed at the other end of the fastener 4. Consists of a fastening wedge pin (5) to be fitted.

이때 상기 갱폼(2)과는 분리된 채 독립적으로 형성되어 갱폼(2)의 외측에서 간격유지구(3)에 나사결합되어지는 체결구(4)의 평판체결부(42)를 수용하도록 조립설치되는 체결용 지지부재(6)가 설치된다.At this time, the assembly is formed so as to receive the plate fastening portion 42 of the fastener (4) which is formed separately from the gang form (2) and is screwed to the spacing holding (3) from the outside of the gang form (2) The fastening support member 6 is installed.

상기 체결용 지지부재(6)는 철판을 소재로 하여 제작되는 것이며, 한쌍으로 된 두개의 세로바(23)를 동시에 지지할 수있는 크기로 된 지지부(61)와, 상기 지지부(61)의 중심측에서 일측(도면상 갱폼의 반대측)을 향해 돌출되는 돌출보강부(62) 및 상기 돌출보강부(62)의 중심에 체결구(4)의 타단에 형성된 평판체결부(42)가 끼워질 수 있도록 일자형으로 형성된 관통공이 형성된 구조로 되어 있으며, The fastening support member 6 is made of an iron plate, and has a support 61 having a size capable of supporting two pairs of vertical bars 23 at the same time, and a center of the support 61. The protruding reinforcement part 62 protruding toward one side (the opposite side of the gangform on the drawing) from the side and the flat plate fastening part 42 formed at the other end of the fastener 4 can be fitted in the center of the protruding reinforcement part 62. It has a structure in which the through hole formed in a straight shape so that

이와 같은 체결용 지지부재(6)는 그 관통공을 통해 체결구(4)의 평판체결부(42)가 관통하여 돌출보강부(62)의 외측으로 돌출되게 한 상태에서 평판체결부(42)에 형성된 조립공(43)으로 체결용 웨지핀(5)을 끼워주게 되면 체결용 웨지핀(5)의 일면(도면상 좌측으로서 체결용 지지부재의 반대측)은 조립공(43)의 끝단에 지지되고 타면은 돌출보강부(62)에 밀착 지지되므로서 상기 체결용 웨지핀(5)은 체결구(4)에 결속된 상태에서 체결용 지지부재(6)가 두줄의 세로바(23)를 동시에 밀어주는 작용으로 갱폼(2)을 지지하게 되는 것이다.The fastening support member 6 as described above has the flat plate fastening portion 42 in a state where the flat plate fastening portion 42 of the fastener 4 penetrates through the through hole so as to protrude out of the protruding reinforcement portion 62. When the fastening wedge pin 5 is fitted into the assembly hole 43 formed in the one side of the fastening wedge pin 5 (the left side as opposed to the support member for fastening as the left side in the drawing) is supported at the end of the assembly hole 43 and the other surface Is tightly supported by the protruding reinforcement 62, so that the fastening wedge pin 5 is coupled to the fastener 4 so that the fastening support member 6 pushes the two vertical bars 23 simultaneously. It is to support the gang form (2) by the action.

이에 상기 갱폼과 유로폼를 이용하여 중단열벽체를 시공하기 위해서는 갱폼과 유로폼 사이에 단열재(10, 이점쇄선으로 표시)를 설치하고, 콘크리트(C, 일점쇄선으로 표시)를 타설하여 콘크리트가 양생되어 콘크리트벽체(A,B)가 완성되면 상기 체결용 지지부재(6)를 결속하고 있는 체결용 웨지핀(5)의 하단부를 망치 등으로 타격하여 조립공(43)에서 빼내게 된다.Accordingly, in order to construct a suspended heat wall using the gangform and the euroform, a heat insulating material (10, indicated by a double-dotted line) is installed between the gangform and the euroform, and concrete is cured by pouring concrete (C, indicated by a single-dotted line) to cure the concrete wall. When the (A, B) is completed, the lower end of the wedge pin (5) for fastening the fastening support member (6) is hit by a hammer or the like to be removed from the assembly hole (43).

이에 체결용 지지부재(6)가 세로바(23)에서 자연적으로 떨어지게 되므로서 체결용 지지부재(6)의 수거가 용이하며, 또한 체결용 지지부재(6)를 분리한 상태에서 체결구(4)를 나사풀림하게 되므로서 체결구(4)의 해체작업이 이루어지게 된다.Accordingly, the fastening support member 6 is naturally separated from the vertical bar 23, so that the fastening support member 6 can be easily collected, and the fastener 4 can be removed while the fastening support member 6 is separated. By disassembling the screw will be made dismantling of the fastener (4).

이때, 간격유지구(3)는 유로폼(1)에 연결된 부위를 역시 망치등으로 타격하여 머리부(3a)가 커팅되면서 유로폼(1)과 함께 해체하게 된다. 이에 머리부(3a)가 제거된 간격유지구(3)는 콘크리트와 단열재에 매립됨을 알 수 있다.At this time, the gap maintaining tool 3 is blown by a hammer or the like at a portion connected to the Euroform 1, so that the head 3a is cut and disassembled together with the Euroform 1. Therefore, it can be seen that the gap retaining region 3 from which the head 3a is removed is embedded in concrete and heat insulating material.

이때, 도 1e와 같이 상기 단열재(10)와 양 콘크리트벽체(A,B)와의 일체성을 확보하기 위하여 강재(철근)인 쉐어커넥터(70)를 사용하게 되는데 이럴 경우 쉐어 커넥터(70)를 통한 에너지 손실 즉, 열교 현상(heat bridge)이 발생한다는 문제점이 있었다. At this time, as shown in FIG. 1e, in order to secure the integrity of the heat insulating material 10 and both concrete walls A and B, a shear connector 70 made of steel (rebar) is used. In this case, the shear connector 70 is used. There is a problem in that energy loss, that is, a heat bridge occurs.

즉, 양 양 콘크리트벽체(A,B)를 접합하도록 설치된 쉐어 커넥터는 열교 현상에 의하여 난방 에너지 손실방지를 목적으로 제안된 중단열 구조의 벽체가 가지는 장점을 반감시키는 원인으로 작용한다는 문제점이 있었다.That is, the share connector installed to join both concrete walls (A, B) has a problem that acts as a cause of halving the advantages of the wall of the heat-recessed structure proposed for the purpose of preventing the loss of heating energy by thermal bridge phenomenon.

또한 종래 갱폼과 유로폼을 이용하여 콘크리트벽체를 시공함에 있어 도 1f와 같이 갱폼지지콘(25)과 연결너트체(31)를 사용하지 않고 간격유지구(3)와 체결구(4)를 서로 나사연결부(41)를 통해 서로 연결시키는 예도 있으나 이 경우 콘크리트 타설 시 단열재(10)의 위치가 변동되는 등의 문제가 발생할 수 있고 단열재(10)에 형성되어 있는 쉐어커넥터(70)에 의한 열교현상이 발생하는 문제는 여전히 남을 수 밖에 없었다.In addition, when constructing a concrete wall using a conventional gangform and euroform, as shown in FIG. 1F, the gap retaining holes 3 and the fasteners 4 are screwed together without using the gangform support cone 25 and the connecting nut body 31. Although there is an example of connecting to each other through the connection portion 41 in this case, problems such as the position of the heat insulating material 10 is changed when placing concrete, and the thermal bridge phenomenon by the shear connector 70 formed in the heat insulating material 10 Problems that have arisen still remain.

이에 본 발명은 건축물의 중단열벽체를 유로폼, 갱폼 및 폼타이를 이용하여 시공하되, 특히 열교현상을 효과적으로 방지할 수 있는 합성 폼타이를 이용한 현장 중단열벽체 시공방법 제공을 그 해결하고자 하는 과제로 한다.Therefore, the present invention is to construct a suspended heat wall of the building using the euro foam, gang form and form tie, in particular, to provide a construction method for the construction of on-site suspended heat wall using a synthetic form tie that can effectively prevent thermal bridge phenomenon. do.

중단열벽체는 기본적으로 콘크리트벽체 사이에 단열재를 설치하게 되며 단열재에는 양 콘크리트벽체를 서로 일체화시켜 주기 위한 연결재(전단연결재라고도 하며, 도 1e 및 도 1f의 쉐어커넥터가 이에 해당된다.)가 설치되어야 한다.Suspended thermal wall is basically to install a heat insulating material between the concrete wall and the heat insulating material to be connected to each other to integrate the concrete walls (also referred to as shear connector, the share connector of Fig. 1e and 1f) is to be installed. do.

이에 본 발명에서는 양 콘크리트벽체를 서로 이격시켜 연결시키는 연결재 역할을 갱폼과 유로폼 사이에 설치되는 폼타이가 하도록 하였다.Accordingly, in the present invention, the form tie installed between the gang form and the euro form serves as a connecting material for connecting both concrete walls to be spaced apart from each other.

이는 현장 타설방식으로 중단열벽체를 시공하기 위하여 폼타이가 단열재를 관통하도록 설치되기 때문에 상기 폼타이가 양 콘크리트벽체를 서로 일체화시켜 주기 위한 연결재의 역할을 할 수 있기 때문이다.This is because the form ties are installed so as to penetrate the heat insulating material in order to construct the suspended heat wall by the site-pouring method, so that the form ties can serve as a connecting material for integrating both concrete walls.

이때 상기 폼타이는 콘크리트벽체로 전달되는 열교현상을 최소화하기 위하여 FRP 폼타이와 강재 폼타이를 연결시켜 설치되는 합성 폼타이를 이용하게 된다.At this time, the form ties are made of synthetic form ties installed by connecting FRP form ties and steel form ties to minimize thermal bridges to be delivered to concrete walls.

또한 본 발명의 갱폼과 유로폼 사이에 설치된 단열재에 콘크리트 타설 시 충격등에 의하여 위치가 변동하는 등의 문제를 방지하기 위하여 단열재의 위치를 구속하는 구속수단(원판 등)이 단열재 전면부 및 후면부에 세팅될 수 있도록 구속수단을 합성 폼타이에 일체로 형성되도록 하여 본 발명의 합성 폼타이가 단열재의 위치를 구속하는 역할도 하도록 하였다.In addition, restraining means (circle, etc.) for restraining the position of the heat insulating material may be set in the heat insulating material front part and the rear part in order to prevent a problem such as the position fluctuation due to the impact when the concrete is placed in the heat insulating material installed between the gang form and the euro form of the present invention. The constraining means was formed integrally with the synthetic form ties so that the synthetic form ties of the present invention also constrain the position of the heat insulator.

또한 상기 단열재에는 합성 연결재가 더 설치되도록 함으로서 중단열벽체의 열교현상을 보다 효과적으로 방지할 수 있도록 하였다.In addition, the heat insulating material is to be installed to the composite connecting material to further prevent the thermal bridge phenomenon of the suspended heat wall more effectively.

즉, 단열재 측면에는 단열재의 전면부(A2) 및 후면부(B2)로부터 측방으로 돌출되도록 합성 연결재가 배치되도록 하고, 상기 합성 연결재가 측면에 부착된 단열재를 서로 접착제로 부착시켜 갱폼과 유로폼 사이에 조립 설치되도록 하였다.That is, the composite connector is arranged on the side of the heat insulating material so as to protrude laterally from the front portion (A2) and the rear portion (B2) of the heat insulating material, and the adhesive is attached between the gangform and the euroform by attaching the heat insulating material attached to the side with an adhesive. To be installed.

이러한 FRP 재질의 합성 연결재는 종래 중단열벽체에 사용되는 강재로 제작되는 연결재의 열전도율 보다 약 2/1000~1/100배 작기 때문에 기존의 중단열벽체에서 문제점으로 지적되었던 에너지 손실(열교 현상)을 최소화할 수 있는 장점이 있다.Since the composite connecting material made of FRP material is about 2/1000 to 1/100 times smaller than the thermal conductivity of the connecting material made of steel used in the conventional suspended heating wall, the energy loss (thermal bridge phenomenon) that has been pointed out as a problem in the existing suspended heating wall is reduced. There is an advantage that can be minimized.

또한 상기 합성 연결재는 그 배치방법에 있어 일측 콘크리트벽체 내부로부터 단열재를 관통하여 타측 콘크리트벽체 내부에 걸쳐지도록 배치되도록 하여 양 콘크리트벽체가 구조적으로 일체로 거동되도록 함으로써, 기존의 비 합성형 콘크리트벽체와 비교하면 상기 합성 연결재에 의하여 증가된 모멘트 팔 길이로 인하여 휨 모멘트 저항성능을 50%~70% 이상 증가시킬 수 있어 보다 향상된 휨 강도 및 강성을 구비하게 된다.In addition, in the arrangement method, the composite connecting material is arranged to penetrate the heat insulating material from the inside of one concrete wall so as to span the inside of the other concrete wall so that both concrete walls behave structurally integrally, compared with the existing non-synthetic concrete wall. When the moment arm length is increased by the composite connecting material, the bending moment resistance can be increased by 50% to 70% or more, thereby providing improved bending strength and rigidity.

본 발명에 의한 현장타설형 중단열벽체에 사용되는 합성 폼타이는 양 콘크리트벽체를 서로 일체화시키는 연결재 역할에 더 나아가 단열재를 통과하는 부위가 FRP 폼타이로 배치되기 때문에 종래 중단열벽체에서 문제점으로 지적되었던 에너지 손실(열교 현상)을 최소화 할 수 있는 장점이 있다.Synthetic form ties used in the site-type suspended heat wall according to the present invention pointed out as a problem in the conventional suspended heat wall because the portion passing through the insulation is arranged as FRP form ties, in addition to the role of the connecting material to integrate both concrete walls together. Has the advantage of minimizing the energy loss (heat bridge phenomenon).

또한 단열재에 설치되는 합성 연결재는 합성 폼타이와 함께 일측 콘크리트벽체 내부로부터 단열재를 관통하여 타측 콘크리트벽체 내부에 걸쳐지도록 배치되도록 하여 양 콘크리트벽체가 구조적으로 일체로 거동되도록 함으로써, 기존의 비 합성형 콘크리트벽체와 비교하면 상기 합성 연결재에 의하여 증가된 모멘트 팔 길이로 인하여 휨 모멘트 저항성능을 50%~70% 이상 증가시킬 수 있어 보다 향상된 휨 강도 및 강성을 구비하게 된다.In addition, the composite connecting member installed in the insulation material is arranged to penetrate the insulation material from the inside of one concrete wall with the synthetic form ties so as to cover the inside of the other concrete wall so that both concrete walls behave structurally integrally. Compared to the wall, the bending moment resistance can be increased by 50% to 70% or more due to the increased moment arm length by the composite connecting member, thereby providing more improved bending strength and rigidity.

또한 상기 합성 연결재는 FRP 재질로 제작된 것이 이용되므로 중단열벽체에 있어서 열교현상을 보다 확실하게 방지할 수 있게 된다.In addition, since the composite connecting material is made of a FRP material is used it is possible to more surely prevent the thermal bridge phenomenon in the suspended heat wall.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허 청구범위에 의하여 나타내어지며, 특허 청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is shown by the following claims rather than the detailed description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present invention. do.

도 1a는 종래 바닥 난방 구조에 있어서, 내단열 구조의 난방 에너지 손실의 개념도,
도 1b는 종래 바닥 난방 구조에 있어서, 외단열 구조에 의한 난방 에너지 손실방지의 개념도,
도 1c는 종래 바닥 난방 구조에 있어서, 중단열 구조에 의한 난방 에너지 손실방지의 개념도,
도 1d, 도 1e 및 도 1f는 종래 갱폼과 유로폼의 조립사시도 및 이를 이용한 콘크리트벽체 시공단면도,
도 2a 및 도 2b는 본 발명의 실시예 1에 의한 중단열벽체의 조립 사시도 및 결합사시도,
도 3a 및 도 3b는 본 발명의 실시예 2에 의한 중단열벽체의 조립 사시도 및 결합사시도,
도 4a 및 도 4b는 본 발명의 실시예 3에 의한 중단열벽체의 조립 사시도 및 결합사시도,
도 5는 본 발명의 현장타설형 중단열벽체의 시공개념도(실시예 1, 2 이용)이다.
도 6은 본 발명의 현장타설형 중단열벽체의 시공개념도(실시예 3 이용)이다.
1A is a conceptual diagram of heating energy loss of a heat insulating structure in a conventional floor heating structure,
1B is a conceptual diagram of preventing heating energy loss by an external insulation structure in a conventional floor heating structure,
Figure 1c is a conceptual diagram of preventing the heating energy loss by the heat dissipation structure in the conventional floor heating structure,
Figure 1d, 1e and 1f is a perspective view of the assembly of the conventional gangform and the flow path and concrete wall construction cross-sectional view using the same,
2a and 2b is an assembled perspective view and a combined perspective view of the interruption heat wall according to the first embodiment of the present invention,
Figure 3a and Figure 3b is an assembled perspective view and a perspective view of the interruption heat wall according to the second embodiment of the present invention,
4a and 4b is an assembled perspective view and a perspective view of the interruption heat wall according to the third embodiment of the present invention,
5 is a conceptual view (using Examples 1 and 2) of the field-pouring interrupted heat wall of the present invention.
6 is a conceptual view (using Example 3) of the construction of the field-pouring interrupted heat wall of the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.

[ 본 발명에 의한 조립 설치된 단열재와 합성 연결재를 이용한 중단열 벽체(실시예 1)][The interrupted heat wall using the assembled insulating material and the composite connecting material according to the present invention (Example 1)]

본 발명의 중단열벽체(100)는 도 2a와 같이 건축물 외벽체에 설치되는 유로폼(210,내측 거푸집) 및 갱폼(220,외측 거푸집)사이에 단열재(110)와 합성 연결재(120)를 미리 조립 설치한 후, 갱폼(220)과 유로폼(210)을 합성 폼타이(400)에 의하여 서로 연결시키되 상기 합성 폼타이(400)가 단열재를 관통하도록 한 후, 상기 유로폼(210) 및 갱폼(220)과 단열재(110) 사이에 콘크리트(C)를 타설(현장타설)하여 외측 및 내측 콘크리트벽체(130,140)가 형성되도록 시공된다.Suspended heating wall 100 of the present invention is pre-assembled and installed the heat insulating material 110 and the composite connecting member 120 between the flow path 210, the inner formwork and the gang form 220, the outer formwork is installed on the building outer wall as shown in Figure 2a. Afterwards, the gangform 220 and the euroform 210 are connected to each other by the synthetic form tie 400, but the composite form tie 400 passes through the insulation, and then the euroform 210 and the gangform 220 The concrete (C) is poured between the heat insulator (110) is constructed so that the outer and inner concrete walls (130, 140) are formed.

최종 상기 유로폼과 갱폼(210,220)은 해체되어 최종 완성되는 중단열벽체는 도 2b와 같이 최종 양 콘크리트벽체(130,140) 사이에 형성된 단열재(110) 및 외측 콘크리트벽체(130) 내부로부터 단열재(110)를 관통하여 내측 콘크리트벽체(140) 내부로 연장 형성된 합성 연결재(120)로 형성된다.Finally, the euroforms and the gangforms 210 and 220 are dismantled, and the finished heat dissipation wall is finally finished as shown in FIG. 2B. The insulation material 110 is formed from the inside of the outer concrete wall 130 and the heat insulating material 110 formed between the final concrete walls 130 and 140. It is formed of a composite connecting member 120 penetrating and extending into the inner concrete wall 140.

이때 상기 합성 폼타이(400)는 갱폼(220)에 설치되는 일측 강재 폼타이(420)만 해체되고 FRP 폼타이(410)는 단열재(110) 내부에 매립되며, 내측 콘크리트벽체(140)에는 타측 강재 폼타이(430)가 매립되게 된다.At this time, the composite form tie 400 is dismantled only one side steel form tie 420 is installed in the gang form 220, FRP form tie 410 is embedded in the heat insulating material 110, the other side in the inner concrete wall 140 Steel form ties 430 are buried.

또한 갱폼(220)과 단열재(110) 사이에는 외측 철근조립체(160)를 설치하게 된다.In addition, the outer reinforcement assembly 160 is installed between the gangform 220 and the heat insulator 110.

이러한 외측 철근조립체(160)와 이격되어 단열재(110)가 설치되는데 미리 합성 연결재(120)가 설치된 단열재(110) 다수를 갱폼과 유로폼의 크기에 맞추어 접착제를 이용하여 조립 설치하는 방식으로 설치된다.The outer reinforcing bar assembly 160 is spaced apart from the heat insulating material 110 is installed is installed in a manner of assembling and installing using a plurality of heat insulating material 110 is installed in accordance with the size of the gang foam and euro foam pre-synthetic connector 120 is installed.

이때 상기 단열재(110) 측면에는 홈(111)을 형성시키되 상하 방향으로 파형으로 형성되도록 하고 이러한 파형 형태의 홈에 본 발명의 합성 연결재(120)가 파형으로 배치되도록 하게 된다.At this time, the groove 111 is formed on the side surface of the heat insulator 110 so as to be formed in a waveform in the vertical direction, and the composite connecting member 120 of the present invention is disposed in a wave in the groove of the wave shape.

이때, 중요한 점은 합성 연결재(120)의 전단(A1) 및 후단(B1)이 단열재(110)의 전면부와 후면부(A2,B2)로부터 돌출되도록 배치하게 된다는 점이다.At this time, the important point is that the front end (A1) and the rear end (B1) of the synthetic connecting member 120 is arranged to protrude from the front and rear parts (A2, B2) of the heat insulating material (110).

이와 같이 합성 연결재(120)가 단열재(110)의 전면부(A)와 후면부(B)로 돌출되어 타설된 콘크리트에 매립되어 외측 및 내측 콘크리트벽체(130,140)를 서로 합성시킬 수 있게 된다.As described above, the synthetic connecting member 120 protrudes into the front portion A and the rear portion B of the heat insulator 110 and is embedded in the poured concrete to synthesize the outer and inner concrete walls 130 and 140 with each other.

이때 합성 연결재(120)는 봉 형태로 제작해도 상관은 없지만 스트립 형태로서 파형으로 형성시킨 것을 소정의 길이로 절단하여 이용할 수도 있다.In this case, the synthetic connecting material 120 may be manufactured in the form of a rod, but it may be used by cutting a predetermined length into a strip shaped wave form.

이때, 상기 합성 연결재(120)는 FRP 재질로 제작된 것을 이용하게 된다.In this case, the composite connecting member 120 is made of a FRP material.

이러한 FRP 재질의 합성 연결재(120)는 열전도율이 강재보다 매우 낮기 때문에 양 콘크리트벽체(130,140)를 연결(접합)하더라도 열교 현상을 최소화 시킬 수 있게 된다는 장점이 있게 된다.(강재로 제작되는 연결재의 열전도율 보다 약 2/1000~1/100배 작음)Since the composite connector 120 of the FRP material has a thermal conductivity much lower than that of the steel, even if the concrete walls 130 and 140 are connected (bonded), the thermal bridge phenomenon can be minimized. (The thermal conductivity of the connector manufactured from steel. 2 / 1000-1 / 100 times smaller)

또한 상기 FRP 재질의 합성 연결재는 그 자체로써도 강재와 동등 이상의 인장강도를 지니고 있어, 콘크리트벽체의 합성거동에 필요한 충분한 기계적 강도를 발휘할 수 있으며, 이에 따라 기존의 중단열벽체와 비교하여 대폭 향상된 단열성능을 유지할 수 있게 된다.In addition, the composite connecting material of the FRP material itself has a tensile strength equal to or higher than that of steel, thereby exhibiting sufficient mechanical strength necessary for the composite behavior of the concrete wall, and thus significantly improved insulation performance compared to the existing suspended heat wall. It can be maintained.

이와 같이 합성 연결재(120)가 측면에 부착된 단열재(110)의 조립 설치가 완료되면 이때 후술되는 유로폼(210)으로부터 일정한 피복두께를 확보할 수 있도록 내측 철근조립체(170)를 설치하게 된다.As such, when the assembly installation of the heat insulator 110 attached to the side of the synthetic connection member 120 is completed, the inner reinforcing bar assembly 170 is installed to secure a constant coating thickness from the flow path 210 which will be described later.

또한 상기 내측 철근조립체(170)와 이격되어 건축물에 유로폼(210)을 설치하게 된다.In addition, the inner side of the reinforcement assembly 170 is spaced apart from the euro foam 210 is installed in the building.

이러한 유로폼과 갱폼(210,220)과 단열재(110) 사이에 콘크리트를 타설(현장타설)하게 되면 최종 본 발명의 중단열 벽체 시공이 가능하게 된다.When the concrete is poured (in-situ) between the euroform and the gangform 210 and 220 and the heat insulator 110, the construction of the intermediate heat wall of the present invention is possible.

이때 본 발명에 의한 중단열벽체를 구조용으로 사용하는 경우에는 도 2a 및 도 2b에 도시된 바와 같이 내측 및 외측 철근조립체(160,170)를 사용하게 되지만, 외측 콘크리트벽체(130)를 비구조용으로 사용하는 경우에는 상기 외측 콘크리트벽체의 두께(t1) 및 외측 철근조립체(160)를 최소화하거나 외측 철근조립체(160)를 설치하지 않아도 된다.In this case, when using the interrupted heat wall according to the present invention for structural use it is to use the inner and outer reinforcement assembly (160, 170) as shown in Figures 2a and 2b, but using the outer concrete wall 130 for non-structural In this case, it is not necessary to minimize the thickness t1 of the outer concrete wall and the outer reinforcement assembly 160 or install the outer reinforcement assembly 160.

이에 최종 외측 및 내측 콘크리트벽체의 두께(t1,t2)는 조정될 수 있을 것이다.Thus, the thicknesses t1 and t2 of the final outer and inner concrete walls may be adjusted.

이러한 중단열 벽체에 있어 이용되는 갱폼(220)과 유로폼(210)을 연결하는본 발명의 합성 폼타이(400)는 단열재(110)를 관통하는 FRP 폼타이(410)와 FRP 폼타이(410) 양 단부에 연결되어 각각 갱폼(220)과 유로폼(210)에 연장 되어 설치되는 일측 및 타측 강재 폼타이(420,430)으로 구분되어 설치된다.Synthetic form tie 400 of the present invention connecting the gang form 220 and the euro form 210 used in such a heat-dissipating wall is FRP form tie 410 and FRP form tie 410 penetrating the heat insulating material 110 It is connected to both ends and is divided into one side and the other side steel form ties (420,430) are installed to extend to the gang form 220 and the flow path 210, respectively.

이러한 합성 폼타이(400)에는 단열재(110)의 전면부와 후면부에 접하도록 설치되는 구속수단(440, 일종의 간격재)이 설치되는데 이로서 상기 합성 폼타이(400)는 기본적으로 갱폼(220)과 유로폼(210)을 서로 연결시켜 주는 역할을 하게 되고, 단열재(110)를 관통하여 매립되는 FRP 폼타이(410)에 의하여 중단열벽체의 열교현상을 방지할 수 있도록 하게 되며, 설치된 구속수단(440)에 의하여 콘크리트 타설에 의한 충격에 의하여 단열재(110)의 위치가 변동되는 현상을 방지할 수 있는 일종의 간격재 역할도 하게 된다.The synthetic form tie 400 is provided with restraining means 440 (a kind of spacer) which is installed to contact the front and rear portions of the heat insulating material 110, whereby the synthetic form tie 400 is basically a gang form 220 and It serves to connect the flow path 210 to each other, and to prevent the thermal bridge phenomenon of the interrupted heat wall by the FRP form tie 410 embedded through the heat insulating material 110, restraining means 440 installed It also serves as a kind of spacer that can prevent the phenomenon that the position of the heat insulating material 110 is changed by the impact caused by the concrete pouring.

[ 본 발명에 의한 조립 설치된 단열재와 합성 연결재를 이용한 중단열 벽체(실시예 2)][Secondary heat wall using the assembled insulating material and the composite connecting material according to the present invention (Example 2)]

상기 실시예 2에 의한 현장타설형 중단열벽체(100)를 도시한 것이 도 3a 및 도 3b이며, 실시예 1과 다른 점은 합성 연결재(120)에 있어 실시예 1은 봉 형태 또는 얇은 두께의 스트립형태로 합성 연결재(120)를 이용하지만 실시예 2는 그리드 형태의 합성 연결재(120)를 이용한다는 것이다.3A and 3B illustrate the site-pouring interrupted heat wall 100 according to the second embodiment, which is different from the first embodiment in the synthetic connecting member 120, the first embodiment having a rod shape or a thin thickness. Although the composite connector 120 is used in the form of a strip, the second embodiment uses the composite connector 120 in the form of a grid.

구체적으로 살펴보면,Specifically,

즉, 도 3a와 같이 일정한 크기로 생산된 그리드(GRID) 합성 연결재를 준비하고 수직으로 절단하게 된다.That is, as shown in Figure 3a to prepare a grid (GRID) composite connecting material produced in a constant size and cut vertically.

이에 이와 같이 수직으로 절단된 다양한 그리드 합성 연결재(120)를 확보하게 됨을 알 수 있다.As such, it can be seen that various grid composite connectors 120 are vertically cut.

이에 도 3b와 같이 단열재(110) 측면에 상기 그리드 합성 연결재(120)를 수직으로 부착(접착제 사용)시켜 설치하게 된다.Accordingly, as shown in FIG. 3B, the grid composite connecting member 120 is vertically attached (using adhesive) to the insulation 110 side.

물론 이러한 그리드 합성 연결재(120)의 전면부(A1) 및 후면부(B1)는 단열재의 전면부(A2)와 후면부(B2)로부터 돌출 형성시키게 됨을 알 수 있다.Of course, it can be seen that the front portion A1 and the rear portion B1 of the grid composite connecting member 120 protrude from the front portion A2 and the rear portion B2 of the insulation.

이와 같이 실시예 2는 그리드 합성 연결재(120)를 단열재(110) 측면에 접착제로 부착하는 구성이외, 유로폼과 갱폼(210, 220), 내측 및 외측 철근조립체(160,170) 및 유로폼과 갱폼(210,220)과 단열재(110) 사이에 콘크리트(C)를 타설(현장타설)함으로서 콘크리트벽체(130,140)에는 내측 및 외측 철근조립체(160,170)가 매립 형성되도록 함은 실시예 1과 동일하다.As described above, the second embodiment, in addition to the configuration of attaching the grid composite connector 120 to the insulation 110 side with an adhesive, the euroform and gangform (210, 220), the inner and outer reinforcement assembly (160, 170) and the euroform and gangform (210,220) By placing concrete (C) between the heat insulating material and the heat insulating material 110, the inner and outer reinforcing bar assemblies 160 and 170 are embedded in the concrete walls 130 and 140 in the same manner as in Example 1.

물론 중단열벽체를 구조용으로 사용하는 경우에는 도 3b에 도시된 바와 같이 내측 및 외측 철근조립체(160,170)를 사용하게 되지만, 외측 콘크리트벽체(130)를 비구조용으로 사용하는 경우에는 상기 외측 콘크리트벽체의 두께 및 외측 철근조립체(160)를 최소화하거나 외측 철근조립체를 설치하지 않아도 된다.Of course, in the case of using the suspended heat wall for structural use as shown in Figure 3b, the inner and outer reinforcement assembly (160, 170), but when using the outer concrete wall 130 for non-structural use of the outer concrete wall It is not necessary to minimize the thickness and outer reinforcement assembly 160 or install the outer reinforcement assembly.

이에 실시예 2에 의한 중단열벽체는 특히 합성 연결재(120)의 제작 및 설치가 실시예1과 대비하여 더욱 용이하게 되므로 중단열벽체 제작공종이 매우 단순해지는 효과가 있게 된다.In this regard, the interruption heating wall according to the second embodiment is particularly easy to manufacture and install the composite connecting member 120, compared to the first embodiment has a very simple effect of manufacturing the interruption heating wall.

역시 이러한 중단열 벽체에 있어 이용되는 갱폼(220)과 유로폼(210)을 연결하는 합성 폼타이(400)도 단열재(110)를 관통하는 FRP 폼타이(410)와 상기 FRP 폼타이 양 단부에 연결되어 각각 갱폼(220)과 유로폼(210)에 연장 설치되는 강재 폼타이(420,430)들로 구분되는데 이는 실시예 1과 동일하다.Synthetic form tie 400, which connects the gang form 220 and the euro form 210, which is also used in such a heat-recessed wall is also connected to both ends of the FRP form tie 410 and the FRP form tie through the heat insulating material 110 And are divided into steel form ties 420 and 430 extending to the gang form 220 and the euro form 210, respectively, which is the same as the first embodiment.

나아가 역시 상기 합성 폼타이(400)에는 단열재(110)의 전면부와 후면부에 접하도록 설치되는 구속수단(440, 일종의 간격재)이 설치된다.Furthermore, the synthetic form tie 400 is also provided with restraining means 440 (a kind of spacer) installed to contact the front and rear portions of the heat insulating material 110.

이에 실시예 2에 의한 합성 폼타이(400)도 기본적으로 갱폼(220)과 유로폼(210)을 서로 연결시켜 주는 역할을 하게 되고, 단열재(110)를 관통하여 매립되는 FRP 폼타이(410)에 의하여 중단열벽체의 열교현상을 방지할 수 있도록 하게 되며, 설치된 구속수단(440)에 의하여 콘크리트 타설에 의한 충격에 의하여 단열재(110)의 위치가 변동되는 현상을 방지할 수 있는 일종의 간격재 역할도 하게 됨을 알 수 있다.Therefore, the synthetic form tie 400 according to the second embodiment also serves to connect the gang form 220 and the euro form 210 to each other, and to the FRP form tie 410 embedded through the heat insulating material 110. It is also possible to prevent the thermal bridge phenomenon of the interrupted heat wall, and also serves as a kind of spacer to prevent the phenomenon of the position of the heat insulating material 110 is changed by the impact of the concrete placing by the restraining means 440 installed. It can be seen that.

[ 본 발명에 의한 조립 설치된 단열재와 합성 연결재를 이용한 중단열 벽체(실시예 3)][Secondary heat wall using the assembled insulating material and the composite connecting material according to the present invention (Example 3)]

상기 실시예 3에 의한 중단열벽체(100)를 도시한 것이 도 4a 및 도 4b이며, 실시예 1,2와 다른점은 중단열벽체를 시공함에 있어 사용되는 단열재(110)에 합성 연결재(120)를 사용하지 않고 FRP 폼타이와 강재 폼타이들이 서로 연결되는 합성 폼타이(400)를 사용하는 예라 할 수 있다.4A and 4B illustrate the interruption heat wall 100 according to the third embodiment, and the difference from the first and second embodiments is that the composite connecting material 120 is connected to the heat insulating material 110 used in constructing the interruption heat wall. FRP form ties and steel form ties without using a) can be an example of using a composite form tie 400 is connected to each other.

이는 상기 단열재(110)를 관통하는 폼타이가 FRP 폼타이(410)이기 때문에 상기 FRP 폼타이가 실시예 1,2에 의한 합성 연결재(120)의 역할도 할 수 있어 합성 연결재(120)를 이용하지 않는 것이다.Since the form tie penetrating the insulation 110 is FRP form tie 410, the FRP form tie may also serve as the composite connecting member 120 according to Examples 1 and 2 to use the synthetic connecting member 120. It is not.

즉, 도 4a와 같이 단열재(110)를 갱폼(220)과 유로폼(210) 사이에 병렬로 부착하여 설치하게 되고, 유로폼과 갱폼(210, 220), 내측 및 외측 철근조립체(160,170) 및 유로폼과 갱폼(210,220)과 단열재(110) 사이에 콘크리트(C)를 타설(현장타설)함으로서 외측 및 내측 콘크리트벽체(130,140)가 형성되도록 하여 콘크리트벽체(130,140)에는 내측 및 외측 철근조립체(160,170)가 매립 형성되도록 하게 된다.That is, as shown in FIG. 4a, the heat insulating material 110 is installed in parallel between the gangform 220 and the flow path 210, and the flow path and the gangform 210 and 220, the inner and outer reinforcing assemblies 160 and 170, and the flow path are installed. By placing concrete (C) between the gangforms 210 and 220 and the heat insulator 110, the outer and inner concrete walls 130 and 140 are formed so that the inner and outer reinforcement assemblies 160 and 170 are embedded in the concrete walls 130 and 140. To form.

물론 이 경우에도 중단열벽체를 구조용으로 사용하는 경우에는 도 4b에 도시된 바와 같이 내측 및 외측 철근조립체(160,170)를 사용하게 되지만, 외측 콘크리트벽체(130)를 비구조용으로 사용하는 경우에는 상기 외측 콘크리트벽체의 두께 및 외측 철근조립체(160)를 최소화하거나 외측 철근조립체를 설치하지 않아도 된다.Of course, even in this case, when using the interruption heat wall for structural use as shown in Figure 4b, the inner and outer reinforcing bar assembly (160, 170), but when using the outer concrete wall 130 for non-structural the outer It is not necessary to minimize the thickness of the concrete wall and the outer reinforcement assembly 160 or install the outer reinforcement assembly.

이에 실시예 3에 의한 중단열벽체는 합성 연결재(!20)를 사용하지 않아 보다 경제적인 중단열 벽체 시공이 가능하게 된다.Accordingly, the interruption heat wall according to the third embodiment does not use the composite connecting material (! 20), and thus, the construction of the interruption heat wall can be more economical.

역시 이러한 중단열 벽체에 있어 이용되는 갱폼(220)과 유로폼(210)을 연결하는 합성 폼타이(400)는 실시예 1,2와 동일하다.Synthetic form ties 400 for connecting the gangform 220 and the flow path 210 used in such a heat-recessed wall are the same as the first and second embodiments.

[ 현장타설형 중단열벽체 시공방법 1(실시예 1 또는 실시예 2의 중단열벽체 이용) ] [In-Place Method of Recessed Hot Wall Construction Method 1 (Use of Recessed Hot Wall of Example 1 or 2)]

도 5를 기준으로 살펴보면 상기 시공방법 1은 조립 설치된 단열재(110)와 합성 연결재(120)는 갱폼(220)과 유로폼(210) 사이에 배치하고 갱폼(220)과 유로폼(210)에 콘크리트(C)를 타설하여 중단열벽체를 시공하는 것임을 알 수 있다.Referring to Figure 5 based on the construction method 1 is assembled between the heat insulating material 110 and the composite connecting member 120 is installed between the gang foam 220 and the euro foam 210 and the concrete (C) on the gang foam 220 and the euro foam 210 It can be seen that it is constructing the interrupted heat wall by pouring).

구체적으로 도 5와 같이 갱폼(220)과 유로폼(210)을 설치하게 되는데 이러한 갱폼(220)과 유로폼(210)은 본 발명의 합성 폼타이(400)에 의하여 서로 구속되어 있게 된다.Specifically, as shown in FIG. 5, the gangform 220 and the flow path 210 are installed. The gangform 220 and the flow path 210 are restrained from each other by the synthetic form tie 400 of the present invention.

이때 미리 준비한 조립 설치된 단열재(110)와 합성 연결재(120)는 갱폼(220)과 유로폼(210) 사이에 미리 배치되도록 하여 갱폼(220)과 유로폼(210)의 설치면적에 따라 다수를 서로 병렬 부착(접착제)시키게 된다.In this case, the pre-assembled heat insulating material 110 and the composite connector 120 are prepared in advance so as to be arranged in advance between the gang foam 220 and the euro foam 210, and a plurality of the gang foam 220 and the euro foam 210 are parallelly attached to each other according to the installation area. (Adhesive).

이에 합성 폼타이(400)에 있어 유로폼(210)에 설치되는 타측 강재 폼타이(430)는 유로폼(210)을 관통하여 단열재(110) 후면부까지 연장되도록 하되 단열재(110)의 후면부(B)에 접하도록 타측 강재 폼타이(430)에는 원판 형태의 구속수단(440)이 설치된다.Accordingly, the other steel form tie 430 installed in the euro form 210 in the synthetic form tie 400 extends through the euro form 210 to the rear portion of the heat insulating material 110, but is formed on the rear portion B of the heat insulating material 110. The other steel form ties 430 are provided with restraining means 440 in the form of a disc.

또한 폼타이(400)에 있어 갱폼(220)에 설치되는 일측 강재 폼타이(420)는 갱폼(220)을 관통하여 갱폼 후면부까지 연장되도록 하며,In addition, one side of the steel form tie 420 installed in the gang form 220 in the form tie 400 is to extend through the gang form 220 to the rear of the gang form,

폼타이(400)에 있어 FRP 폼타이(410)는 단열재(110)를 관통하여 강재 폼타이(420,430)에 서로 연결되도록 하게 되며, 상기 단열재(110)의 전면부(A)에 접하도록 FRP 폼타이(410)에는 원판 형태의 구속수단(440)이 설치되도록 함을 알 수 있다.In the form tie 400, the FRP form tie 410 is to be connected to each other to the steel form tie (420,430) through the heat insulating material 110, FRP foam to be in contact with the front portion (A) of the heat insulating material (110). It can be seen that the tie 410 is provided with a restraining means 440 in the form of a disc.

이에 갱폼(220)과 유로폼(210) 사이에 조립 설치된 단열재(110)와 합성 연결재(120)가 배치되고, FRP 폼타이(410)가 단열재(110)를 관통하도록 하고, 일측 및 타측 강재 폼타이(420,430)들이 상기 FRP 폼타이(410)의 양 단부와 연결되어 갱폼과 유로폼에 고정된 상태에서 단열재(110) 양측으로 콘크리트(C)를 타설함으로서 최종 외측 콘크리트벽체(130)와 내측 콘크리트벽체(140)를 형성시키게 된다.In this case, the insulating member 110 and the synthetic connecting member 120 are assembled between the gang form 220 and the euro form 210, and the FRP form tie 410 penetrates the insulating member 110, and the one side and the other steel form tie The final outer concrete wall 130 and the inner concrete wall (420,430) by placing the concrete (C) on both sides of the heat insulating material 110 in a state that is connected to both ends of the FRP form tie 410 is fixed to the gang form and the euro foam ( 140).

이로서 상기 외측 콘크리트벽체(130)와 내측 콘크리트벽체(140)는 기본적으로 합성 연결재(120)에 의하여 서로 일체화되도록 하고, 역시 합성 폼타이(400)에 의해서도 서로 완전히 일체화되도록 함을 알 수 있다.As a result, the outer concrete wall 130 and the inner concrete wall 140 can be seen to be basically integrated with each other by the composite connecting material 120, and also to be completely integrated with each other by the synthetic form tie 400.

이때, 상기 내측 콘크리트벽체(140)에 매립되는 타측 강재 폼타이(430)의 표면은 거칠면으로 처리하여 콘크리트와의 부착성능을 충분히 확보할 수 있도록 하는 것이 바람직하다.At this time, the surface of the other steel form tie 430 embedded in the inner concrete wall 140 is preferably treated with a rough surface to ensure sufficient adhesion performance with the concrete.

이때, 상기 외측 콘크리트벽체(130)는 비교적 두께가 얇고 외측 철근조립체를 배치하지 않아 비구조체로 기능하도록 할 수도 있으며, 와이어메쉬 또는 외측 철근조립체를 설치해도 상관은 없다.In this case, the outer concrete wall 130 may be relatively thin and may function as a non-structural structure by not disposing the outer reinforcing bar assembly, and it does not matter even if a wire mesh or an outer reinforcing bar assembly is installed.

반면에 단열재(110) 배면과 유로폼(210) 사이의 내측 콘크리트벽체(140)는 내부에 내측 철근조립체(170)가 배치되어 있음을 알 수 있으며 외측 콘크리트벽체(130)과 대비하여 두께가 좀 두껍게 형성되어 구조체로 기능하도록 함을 알 수 있다.On the other hand, the inner concrete wall 140 between the rear surface of the heat insulating material 110 and the euroform 210 can be seen that the inner reinforcing bar assembly 170 is disposed therein and a little thicker than the outer concrete wall 130. It can be seen that it is formed to function as a structure.

이에 상기 외측 및 내측 콘크리트벽체(130,140)가 양생되면, 갱폼(220)과 유로폼(210)을 해체하게 되는데, Accordingly, when the outer and inner concrete walls 130 and 140 are cured, the gang form 220 and the flow path 210 are dismantled.

상기 갱폼(220)은 일측 강재 폼타이(420)를 FRP 폼타이(410)로부터 분리하면서 갱폼(220)과 일측 강재 폼타이(420)를 한꺼번에 해체되도록 하고, The gang form 220 is to disassemble the gang form 220 and one side steel form tie 420 at the same time, while separating the one side steel form tie 420 from the FRP form tie 410,

FRP 폼타이(410)는 단열재(110)를 관통하여 매립되도록 하고, FRP form tie 410 is to be embedded through the heat insulator 110,

타측 강재 폼타이(430)는 내측 콘크리트벽체(140) 내부에 매립되면서 머리부(430a)를 타격하여 머리부와 유로폼(210)과 함께 해체되도록 하게 된다.The other steel form tie 430 is embedded in the inner concrete wall 140 while hitting the head 430a to be dismantled together with the head and the flow path (210).

또한, 최종 완성된 중단열벽체에 있어 폼타이에 의하여 형성된 홀들은 별도로 모르타르등을 이용하여 마감시켜 미관을 해치지 않도록 하게 된다.In addition, the hole formed by the form tie in the final finished heat-dissipating wall is finished by using a mortar, etc. separately so as not to damage the aesthetics.

[ 현장타설형 중단열벽체 시공방법 2: 실시예 3의 중단열벽체 이용 ] [Method 2: Construction of Suspended Hotwall]

도 6을 기준으로 살펴보면 상기 시공방법 2와 시공방법 1의 차이는 합성 연결재(120)가 설치되지 않은 단열재(110)를 이용하고 강재 폼타이들(420,430)과 FRP 폼타이(410)를 연결한 합성 폼타이(400)를 이용하는 것은 동일하다.Referring to FIG. 6, the difference between the construction method 2 and the construction method 1 is that the steel form ties 420 and 430 and the FRP form tie 410 are connected by using the insulation 110 that is not installed with the synthetic connecting member 120. The use of synthetic form tie 400 is the same.

이는 곧 상기 합성 폼타이(400)가 중단열벽체에 있어 종래 합성 연결재 역할을 할 수 있음을 고려하여 합성 연결재(120)가 설치되지 않은 단열재(110)를 이용하는 것이 보다 경제적이기 때문이다.This is because it is more economical to use the heat insulating material 110 that is not provided with the composite connector 120 in consideration of the fact that the synthetic form tie 400 may serve as a conventional synthetic connector in the suspended heat wall.

구체적으로 도 6과 같이 갱폼(220)과 유로폼(210)을 설치하게 되는데 이러한 갱폼(220)과 유로폼(210)은 본 발명의 합성 폼타이(400)에 의하여 서로 구속되어 있게 된다.Specifically, as shown in FIG. 6, the gangform 220 and the flow path 210 are installed. The gangform 220 and the flow path 210 are restrained from each other by the synthetic form tie 400 of the present invention.

이때 미리 준비한 조립 설치된 단열재(110)는 갱폼(220)과 유로폼(210) 사이에 미리 배치되도록 하여 갱폼(220)과 유로폼(210)의 설치면적에 따라 다수를 서로 병렬 부착(접착제)시키게 됨은 실시예 1과 동일하다.At this time, the pre-assembled heat insulating material 110 is pre-arranged between the gang foam 220 and the flow path 210 so that a plurality of the gang foam 220 and the flow path 210 in parallel with each other in accordance with the installation area (adhesive) is carried out. Same as Example 1.

이에 역시 합성 폼타이(400)에 있어 유로폼(210)에 설치되는 타측 강재 폼타이(430)는 유로폼(210)을 관통하여 단열재(110) 후면부까지 연장되도록 하되 단열재(110)의 후면부(B)에 접하도록 타측 강재 폼타이(430)에는 원판 형태의 구속수단(440)이 설치되며,In this case, the other steel form ties 430 installed on the euro form 210 in the synthetic form tie 400 extend through the euro form 210 to the rear portion of the heat insulator 110, but the rear portion B of the heat insulator 110. On the other side of the steel form tie 430 is provided with a restraining means 440 in the form of a disc,

폼타이(400)에 있어 갱폼(220)에 설치되는 일측 강재 폼타이(420)는 갱폼(220)을 관통하여 후면부까지 연장되도록 하며,One side steel form tie 420 installed in the gang form 220 in the form tie 400 is to extend through the gang form 220 to the rear portion,

폼타이(400)에 있어 FRP 폼타이(410)는 단열재(110)를 관통하여 강재 폼타이(420,430)들에 서로 연결되도록 하게 되며,In the form tie 400, the FRP form tie 410 is to be connected to each other to the steel form tie (420,430) through the insulation 110,

상기 단열재(110)의 전면부에 접하도록 FRP 폼타이(410)에는 원판 형태의 구속수단(440)이 역시 설치되도록 함을 알 수 있다.It can be seen that the FRP form tie 410 to be in contact with the front portion of the heat insulator 110 is provided with a restraining means 440 in the form of a disc.

이에 갱폼과 유로폼 사이에 조립 설치된 단열재(110)가 배치되고, 폼타이(400)의 FRP 폼타이(410)가 단열재(110)를 관통하도록 하고, 강재 폼타이(420,430)들이 FRP 폼타이의 양 단부와 연결되어 갱폼과 유로폼에 고정된 상태에서 단열재(110) 양측으로 콘크리트(C)를 타설하여 외측 콘크리트벽체(130)와 내측 콘크리트벽체(140)를 형성시키게 된다.Insulation 110 is installed between the gangform and the euro foam is disposed, the FRP form tie 410 of the form tie 400 to penetrate the insulation 110, the steel form ties (420, 430) the amount of FRP form tie The outer concrete wall 130 and the inner concrete wall 140 are formed by pouring concrete C to both sides of the heat insulating material 110 in a state connected to the end and fixed to the gang form and the flow path.

이에 상기 외측 및 내측 콘크리트벽체(130,140)가 양생되면, 갱폼(220)과 유로폼(210)을 해체하게 되는데, Accordingly, when the outer and inner concrete walls 130 and 140 are cured, the gang form 220 and the flow path 210 are dismantled.

갱폼(220)은 일측 강재 폼타이(420)를 FRP 폼타이(410)로부터 분리하면서 갱폼(220)과 일측 강재 폼타이(420)를 한꺼번에 해체되도록 하고, Gang form 220 is to disassemble the gang form 220 and the one side steel form tie 420 at the same time, while separating the one side steel form tie 420 from the FRP form tie 410,

FRP 폼타이(410)는 단열재(110)를 관통하여 매립되도록 하고, FRP form tie 410 is to be embedded through the heat insulator 110,

타측 강재 폼타이(430)는 내측 콘크리트벽체 내부에 매립되면서 머리부(430a)를 타격하여 머리부와 유로폼(210)과 함께 해체되도록 하게 됨도 동일하다.The other steel form tie 430 is embedded in the inner concrete wall while hitting the head 430a to be dismantled together with the head and the flow path 210 is the same.

또한, 최종 완성된 중단열벽체에 있어 폼타이에 의하여 형성된 홀들은 별도로 모르타르등을 이용하여 마감시켜 미관을 해치지 않도록 하게 된다.In addition, the hole formed by the form tie in the final finished heat-dissipating wall is finished by using a mortar, etc. separately so as not to damage the aesthetics.

100: 본 발명에 의한 중단열벽체
110: 단열재
111: 홈
120: 합성 연결재
130: 외측 콘크리트벽체
140: 내측 콘크리트벽체
210: 유로폼
220: 갱폼
400: 합성 폼타이
410: FRP 폼타이
420,430: 일측 및 타측 강재 폼타이
440: 구속수단
100: interrupted heat wall according to the present invention
110: Insulation
111: home
120: composite connecting material
130: outer concrete wall
140: inner concrete wall
210: Euroform
220: gangform
400: synthetic foam tie
410: FRP Form Tie
420,430: One side and the other steel form ties
440: means of restraint

Claims (11)

갱폼(220)과 유로폼(210)을 폼타이(400)를 이용하여 이격 설치하고, 상기 갱폼(220)과 유로폼(21) 사이에 단열재(110)를 설치하되, 상기 단열재(110)는 다수의 단열재를 서로 부착시켜 조립 설치되도록 하고, 상기 갱폼(220)과 유로폼(210) 사이에 단열재(110)가 매립되도록 콘크리트(C)를 타설하는 단계;를 포함하되,
상기 폼타이(400)는 FRP 폼타이(410)와 FRP 폼타이(410)의 양 단부에 일측 및 타측 강재 폼타이(420,430)가 서로 연결된 것을 이용하고, 상기 FRP 폼타이(410)는 단열재(110)를 관통하도록 설치하고, 상기 강재 폼타이(420,430)들은 FRP 폼타이(410) 양 단부에 연결되어 각각 갱폼(220)과 유로폼(210)에 연장되어 설치되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.
The gang foam 220 and the euro foam 210 is spaced apart using the form tie 400, and the insulation 110 is installed between the gang foam 220 and the euro foam 21, the insulation 110 is a plurality of Attaching the heat insulating material to each other so as to be assembled, and placing the concrete (C) so that the heat insulating material 110 is embedded between the gangform 220 and the flow path 210;
The form tie 400 is that the one and the other steel form ties 420, 430 are connected to each other at both ends of the FRP form tie 410 and the FRP form tie 410, the FRP form tie 410 is a heat insulating material ( 110, and the steel form ties 420 and 430 are connected to both ends of the FRP form ties 410, the composite form ties characterized in that the extension is installed in the gang form 220 and the euro form 210, respectively. Construction method of on-site suspended hotwall using
제 1항에 있어서,
상기 FRP 폼타이(410) 외주면에 설치되어 단열재(110) 전면부에 접하도록 구속수단(440)이 더 설치되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.
The method of claim 1,
Installed on the outer circumferential surface of the FRP form tie (410) constraining means (440) to be installed so as to contact the front portion of the heat insulator (110) on-site suspended hot wall construction method using a composite form tie.
제 1항 또는 제 2항에 있어서,
상기 일측 강재 폼타이(220) 외주면에 설치되어 단열재(110) 후면부에 접하도록 구속수단(440)이 더 설치되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.
3. The method according to claim 1 or 2,
The one-side steel form tie 220 is installed on the outer circumferential surface of the field suspended heat wall construction method using a composite form tie, characterized in that the restraining means 440 is further installed to contact the rear portion of the heat insulating material (110).
제 1항에 있어서, 상기 상기 단열재(110)는 측면에 단열재의 전면부(A2) 및 후면부(B2)로부터 연장 돌출되도록 합성 연결재(120)가 더 형성되도록 하되, 상기 합성 연결재(120)가 측면에 부착된 단열재(110)를 서로 부착시켜 조립 설치되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.The method of claim 1, wherein the heat insulating material 110 is to be further formed on the side so as to protrude from the front portion (A2) and the rear portion (B2) of the heat insulating material, the composite connector 120 is formed on the side On-site suspended heating wall construction method using a composite form tie, characterized in that to be installed by attaching to each other attached to the heat insulating material (110) attached to each other. 제 4항에 있어서, 상기 합성 연결재(120)는 봉 형태 또는 스트립(STRIP) 형태의 FRP 재질로서 파형으로 형성시킨 것을 단열재(110) 측면에 설치되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.The method of claim 4, wherein the composite connecting member 120 is formed in the form of a wave form as a rod or strip (STRIP) in the form of a wave shape so as to be installed on the side of the heat insulating material 110, characterized in that the interruption Heat wall construction method. 제 5항에 있어서, 상기 단열재(110) 측면에는 파형 형태의 합성 연결재(120)가 삽입되도록 파형으로 형성된 홈(111)을 형성시키고, 상기 홈에 합성 연결재(120)가 삽입되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.The method according to claim 5, wherein the insulating member 110 is formed on the side surface to form a groove 111 formed in a wave form so that the composite connector 120 in the form of a waveform, characterized in that the composite connector 120 is inserted into the groove. Method for construction of on-site suspended heat wall using synthetic form tie. 제 4항에 있어서, 상기 합성 연결재(120)는 그리드(GRID) 형태로 제작된 합성 연결재(120)를 절단하여 단열재(110) 측면에 수직으로 설치되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.According to claim 4, The synthetic connector 120 is cut to the synthetic connector 120 made in the form of a grid (GRID) by cutting the synthetic connector 120, the site using a synthetic form tie, characterized in that installed vertically on the side Construction method of suspended heat wall. 제 4항에 있어서, 상기 갱폼(220)과 단열재(110) 사이에는 외측 철근조립체(160)가 더 설치되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.5. The method of claim 4, wherein the outer reinforcing bar assembly 160 is further installed between the gangform 220 and the heat insulator 110. 제 4항에 있어서, 상기 유로폼(210)과 단열재(110) 사이에는 내측 철근조립체(170)가 더 설치되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.5. The method of claim 4, wherein the inner reinforcing bar assembly is further installed between the flow path 210 and the heat insulator 110. 제 4항에 있어서, 상기 갱폼(220)과 유로폼(210) 사이에 형성되는 내측 및 외측 콘크리트벽체는 서로 두께(t1,t2)를 달리하여 형성되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.The method of claim 4, wherein the inner and outer concrete walls formed between the gangform 220 and the flow path 210 are formed to be formed by varying the thickness (t1, t2) with each other, the site stop using a composite form tie Heat wall construction method. 제 4항에 있어서, 상기 합성 연결재(120)가 측면에 부착된 단열재(110)는 미리 공장에서 제작한 다수의 단열재(110)를 서로 현장에서 접착제로 부착시켜 갱폼과 유로폼 사이에 조립 설치되도록 하는 것을 특징으로 하는 합성 폼타이를 이용한 현장 중단열벽체 시공방법.According to claim 4, The synthetic connector 120 is attached to the side of the heat insulating material 110 to attach a plurality of heat insulators 110 made in advance in the factory by adhesive to each other in the field to be installed between the gangform and the euroform Method for constructing on-site suspended heating wall using a composite form tie, characterized in that.
KR1020110086374A 2011-08-29 2011-08-29 Concrete composite wall construction method with inner insulation, composite shear connector and composite form-tie KR101292523B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110086374A KR101292523B1 (en) 2011-08-29 2011-08-29 Concrete composite wall construction method with inner insulation, composite shear connector and composite form-tie

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110086374A KR101292523B1 (en) 2011-08-29 2011-08-29 Concrete composite wall construction method with inner insulation, composite shear connector and composite form-tie

Publications (2)

Publication Number Publication Date
KR20130023538A true KR20130023538A (en) 2013-03-08
KR101292523B1 KR101292523B1 (en) 2013-08-12

Family

ID=48175754

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110086374A KR101292523B1 (en) 2011-08-29 2011-08-29 Concrete composite wall construction method with inner insulation, composite shear connector and composite form-tie

Country Status (1)

Country Link
KR (1) KR101292523B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020169811A1 (en) 2019-02-22 2020-08-27 Mackencore Uk Limited Lost formwork
CN113482339A (en) * 2021-06-07 2021-10-08 五冶集团上海有限公司 Double-sided overlapped assembly type shear wall and floor slab joint template plugging construction method
KR102615298B1 (en) 2022-10-21 2023-12-19 한국건설기술연구원 Heat bridge prevention typed high load exterior insulation finish system of concrete wall with improved adhesion ability and the construction method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111502272A (en) * 2020-05-11 2020-08-07 中铁城建集团第三工程有限公司 Formwork support reinforcing system in narrow space

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005068763A (en) 2003-08-22 2005-03-17 Star House International:Kk Interval holding member for forming concrete placing space
NO333274B1 (en) 2005-11-03 2013-04-29 John A Simonsen Spacer bars for joining a stop railing's opposite side sections.

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020169811A1 (en) 2019-02-22 2020-08-27 Mackencore Uk Limited Lost formwork
CN113482339A (en) * 2021-06-07 2021-10-08 五冶集团上海有限公司 Double-sided overlapped assembly type shear wall and floor slab joint template plugging construction method
KR102615298B1 (en) 2022-10-21 2023-12-19 한국건설기술연구원 Heat bridge prevention typed high load exterior insulation finish system of concrete wall with improved adhesion ability and the construction method thereof

Also Published As

Publication number Publication date
KR101292523B1 (en) 2013-08-12

Similar Documents

Publication Publication Date Title
KR101214980B1 (en) Concrete composite wall construction method with inner insulation and composite shear connector
US8904731B2 (en) Laser configured hook column anchors and anchoring systems utilizing the same
KR101441399B1 (en) Composite form-tie for concrete composite wall and the construction method therewith
KR101182536B1 (en) Prefabricated double wall precast concrete pannel having surface material, reinforcing rod according to the purpose
KR102004419B1 (en) Structure for reinforcing column using V-shaped ties
JP5854320B2 (en) RC building method with adjacent stone
JP5077664B2 (en) RC building method with no external insulation and no adjacent space
KR101253253B1 (en) Concrete composite wall construction method with gangform and precast wall
KR101225661B1 (en) Concrete shear key strengthened with steel cover plate and tension member and the construction method therewith
KR101464921B1 (en) A fixing apparatus of insulation material and constructing method thereof
KR101615126B1 (en) Outer insulation system and installation method of outer wall using it
KR101292523B1 (en) Concrete composite wall construction method with inner insulation, composite shear connector and composite form-tie
KR100946940B1 (en) Joint structure for steel column and flat slab
KR101312992B1 (en) Concrete composite wall construction method with soft gangform and form-tie
KR101337325B1 (en) Concrete composite wall for improving resistance ability to wind load and the construction method therefor
KR101262565B1 (en) Device fixing insulating material on vertical aluminum molds
KR20150060107A (en) Adiabatic concrete connecting structure and constructing method
KR101366503B1 (en) Concrete composite wall for improving concrete pouring pressure resistance ability and the construction method therefor
KR101275932B1 (en) Method for installing ALC panel to concrete slab
KR101534568B1 (en) A fixing structure of heat insulating material for building and constructing method thereof
KR200480225Y1 (en) Joining members for connecting external panel improved heat-blocking ability and connecting structure of external panel using the same
KR101286016B1 (en) Concrete composite wall with inner insulation and frp eccentric wave shear connector and the construction method
JP3983491B2 (en) Method for manufacturing insulated PC concrete board
JP5281919B2 (en) Outside heat insulation foundation structure and its construction method
US8763317B2 (en) Concrete roof panel

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160701

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170704

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20180702

Year of fee payment: 6