KR20120138569A - Method for leg assembly of jack-up rig - Google Patents

Method for leg assembly of jack-up rig Download PDF

Info

Publication number
KR20120138569A
KR20120138569A KR1020110058138A KR20110058138A KR20120138569A KR 20120138569 A KR20120138569 A KR 20120138569A KR 1020110058138 A KR1020110058138 A KR 1020110058138A KR 20110058138 A KR20110058138 A KR 20110058138A KR 20120138569 A KR20120138569 A KR 20120138569A
Authority
KR
South Korea
Prior art keywords
jack
league
vessel
rig
sea
Prior art date
Application number
KR1020110058138A
Other languages
Korean (ko)
Other versions
KR101221550B1 (en
Inventor
윤도윤
신장용
김영관
Original Assignee
대우조선해양 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대우조선해양 주식회사 filed Critical 대우조선해양 주식회사
Priority to KR1020110058138A priority Critical patent/KR101221550B1/en
Publication of KR20120138569A publication Critical patent/KR20120138569A/en
Application granted granted Critical
Publication of KR101221550B1 publication Critical patent/KR101221550B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/04Equipment specially adapted for raising, lowering, or immobilising the working platform relative to the supporting construction
    • E02B17/08Equipment specially adapted for raising, lowering, or immobilising the working platform relative to the supporting construction for raising or lowering
    • E02B17/0836Equipment specially adapted for raising, lowering, or immobilising the working platform relative to the supporting construction for raising or lowering with climbing jacks
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • E02B2017/0047Methods for placing the offshore structure using a barge
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0073Details of sea bottom engaging footing
    • E02B2017/0082Spudcans, skirts or extended feet

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Wind Motors (AREA)

Abstract

PURPOSE: A method for assembling columns of a jack-up rig is provided to transport and install a jack-up rig on the sea in different regions regardless of the soil condition at the bottom of the sea. CONSTITUTION: A method for assembling columns of a jack-up rig comprises the steps of: keeping a vessel and a jack-up rig on standby on the sea(S1), submerging the vessel in the sea and moving the jack-up rig above the vessel(S2), regulating the jack-up rig to the right position above the vessel and floating the vessel on the sea(S3), attaching or detaching supporting members to the bottom of columns of the jack-up rig being placed on the top of the deck of the vessel(S4), submerging the vessel(S5), moving the jack-up rig to a predetermined installation position on the sea(S6), and floating the vessel on the sea(S7). [Reference numerals] (S1) First step for standby; (S2) Second step for submerging a vessel and moving a jack-up rig; (S3) Third step for floating the vessel to the moved jack-up rig; (S4) Fourth step for attaching or detaching a support member to a column of the jack-up rig; (S5) Fifth step for submerging the vessel; (S6) Sixth step for moving the jack-up rig; (S7) Seventh step for floating the vessel

Description

잭업리그의 기둥 조립 방법{METHOD FOR LEG ASSEMBLY OF JACK-UP RIG}How to assemble pillars of jack up league {METHOD FOR LEG ASSEMBLY OF JACK-UP RIG}

본 발명은 잭업리그의 기둥 조립 방법에 관한 것으로서, 더욱 상세하게는 수면 위에서 잭업리그의 기둥에 받침부재를 탈착하고 다시 진수할 수 있게 하는 잭업리그의 기둥 조립 방법에 관한 것이다.The present invention relates to a method for assembling a jack up league, and more particularly, to a method for assembling a jack up league, which allows the support member to be detached and launched again on a pole of the jack up league on the water surface.

국제적으로 급격하게 산업 및 공업이 발전함에 따라 석유와 같은 지구 자원의 사용량은 점차 증가하고 있으며, 이에 따라 원유의 안정적인 생산과 공급이 전지구적인 차원에서 대단히 중요한 문제로 떠오르고 있다.With the rapid development of industries and industries internationally, the use of global resources such as petroleum is gradually increasing, so that stable production and supply of crude oil is becoming a very important problem at the global level.

이와 같은 이유로 인해서, 최근에는 지금까지 경제성이 없어 무시되어 왔던 군소의 한계 유전(marginal field)이나 심해 유전의 개발이 경제성을 가지게 되었으며, 해저 채굴 기술의 발달과 더불어 이런 유전의 개발에 적합한 시추설비를 구비한 리그(rig)가 개발되어 있다.For this reason, the development of marginal or deep sea oil fields, which have been neglected in recent years because of their lack of economic viability, has become economically viable. A provided rig has been developed.

일반적으로, 리그(rig)는 바지(barge)에 설치한 3 ~ 6개 정도의 각주를 해저에 내려 세워 바지를 해상에 설치하는 잭업형(jack-up rig)과 수중의 하부선각에 세워진 각주로서 해상의 갑판을 지탱하는 반잠수형과 선각과 같은 모양의 선형과 토사를 매립하여 인공섬으로 만든 매립식 인공섬형과 잠함 등을 해저에 침설 하여 중량으로 파력이나 지진력을 견디게 하는 중력형과 원반형상의 부유식 구조체를 이루는 원반 부체형 등이 있다.Generally, a rig is a jack-up rig that puts three to six footnotes placed on a barge on the sea floor and puts the pants on the sea, and footnotes erected at the bottom of the water. A semi-submersible supporting the deck of the sea, and a buried artificial island and submarine made of artificial islands by embedding the linear and earth-shape like the hull, and submerged in the sea floor by gravity and discoid floating to endure wave or seismic force by weight. Disc shaped discs, etc. that make up the structure.

이러한 리그 중 잭업형 리그는 암반지역, 연약지반 등에 설치될 수 있는데 암반지역 같은 경우는 리그의 각주가 지반침투를 하기 힘들지만 연약지반 같은 경우에는 리그의 각주가 지반침투를 하기 쉬워서 리그가 해상에 정상적으로 설치되기 어렵다는 문제점이 있다. 따라서, 이러한 문제점을 해결하기 위한 연구 개발이 필요하였다.Among these leagues, jack-up leagues can be installed in rocky areas and soft grounds. In the case of rocky areas, league footnotes are difficult to penetrate into the ground. There is a problem that it is difficult to install. Therefore, research and development were needed to solve this problem.

잭업형 리그의 각주가 연약지반에서 지반을 침투하는 것을 방지하기 위해 각주의 끝단에 스퍼드캔(spudcan)과 같은 받침부재를 설치할 수 있다. To prevent footnotes from jack-up rigs from penetrating the ground in soft ground, support members such as spudcans may be installed at the ends of the footnotes.

하지만, 각주의 끝단에 스퍼드캔을 일체형으로 설치할 경우 스퍼드캔이 필요없는 암반지역에서도 스퍼드캔은 강도 상에 문제가 없어야 하므로 크기를 크게 하고 중량을 무겁게 해야한다. 따라서 중량이 무겁기 때문에 잭업형 리그를 이송할 시 이송속도가 느리게 된다는 문제점이 있다.However, when the spud cans are integrally installed at the end of the footnotes, even in the rock area where the spud cans are not needed, the spud cans should be large in size and heavy in weight because they have no problem in strength. Therefore, since the weight is heavy, there is a problem that the feeding speed is slow when transferring the jack-up rig.

본 발명은 상기한 바와 같은 종래의 문제점을 해결하기 위한 것으로서, 수면 위에서 잭업형 리그의 기둥에서 받침부재를 탈착하여 다시 진수할 수 있게 한 잭업리그의 기둥 조립 방법을 제공하는데 그 목적이 있다.The present invention is to solve the conventional problems as described above, it is an object of the present invention to provide a method for assembling the jack up league that can be released again by removing the support member from the pole of the jack-up type on the water surface.

상기 목적을 달성하기 위한 본 발명의 일 측면에 따르면, 받침부재가 설치되는 잭업리그(jack-up rig)의 기둥 조립 방법에 있어서, 해상에 선박 및 잭업리그를 대기하는 제1단계; 상기 선박을 해저로 잠수시키고 상기 잭업리그를 상기 선박의 상측으로 이동시키는 제2단계; 상기 잭업리그가 상기 선박의 상측 정위치에 위치하도록 조정한 후 상기 선박을 해상으로 부양시키는 제3단계; 및 상기 잭업리그가 상기 선박의 데크 위에 놓인 상태에서, 상기 잭업리그의 기둥 하단에 받침부재를 부착하거나 또는 상기 잭업리그의 기둥 하단으로부터 받침부재를 분리하는 제4단계를 포함하는 것을 특징으로 한다.According to an aspect of the present invention for achieving the above object, a method for assembling a jack-up rig (jack-up rig) pillars supporting member is provided, the first step of waiting for the ship and jack-up league at sea; A second step of submerging the vessel to the seabed and moving the jackup league to an upper side of the vessel; A third step of adjusting the jack up league to be positioned at an upper side of the ship and then supporting the ship at sea; And a fourth step of attaching a supporting member to a lower end of the pole of the jack up league or separating the supporting member from the lower end of the pole of the jack up league while the jack up league is placed on the deck of the ship.

상기 선박의 데크 위에는 상기 잭업리그를 지지하는 그릴리지(grillage)가 구비되는 것을 특징으로 한다.On the deck of the ship is characterized in that the grille (grillage) for supporting the jack-up league is provided.

상기 선박은 잠수가 가능한 바지선 또는 반잠수정인 것을 특징으로 한다.The vessel is characterized in that the submersible barge or semi-submersible.

상기 제4단계 이후에 상기 선박을 잠수시키는 제5단계와 상기 잭업리그를 해상에 설치할 위치로 이동시키는 제6단계 및 상기 선박을 해상으로 부양시키는 제7단계를 더 포함하는 것을 특징으로 한다.And a fifth step of submerging the ship after the fourth step, a sixth step of moving the jack up league to a position to be installed at sea, and a seventh step of supporting the ship at sea.

상기 목적을 달성하기 위한 본 발명의 다른 측면에 따르면, 받침부재가 설치되는 잭업리그(jack-up rig)의 기둥 조립 방법에 있어서, 상기 받침부재와 그릴리지가 데크 위에 적재된 선박을 잠수시킨 상태에서 상기 잭업리그를 상기 선박의 상측으로 이동시키고 상기 선박을 해상으로 부유하게 함에 따라 상기 잭업리그의 중앙을 상기 그릴리지가 지지하게 하여 상기 잭업리그의 각 기둥에 상기 받침부재를 탈착하는 것을 특징으로 한다.According to another aspect of the present invention for achieving the above object, in the method of assembling the jack-up rig (jack-up rig) pillar supporting member is installed, the supporting member and the grille is submerged the ship loaded on the deck As the jack up league moves to the upper side of the vessel and the vessel is floating in the sea as the support of the grillage to the center of the jack up league characterized in that the support member is detached to each pillar of the jack up league do.

이상과 같은 본 발명에 따르면, 수면 위에서 잭업리그의 기둥에 받침부재를 탈착하여 다시 진수할 수 있게 함에 따라 해저의 토질 상태에 상관없이 잭업리그를 각기 다른 지역의 해상에 이동하여 설치할 수 있게 하는 효과가 있다.According to the present invention as described above, by removing the support member on the pole of the jack up league on the water surface to be launched again, the effect of allowing the jack up league to be moved and installed on the sea in different regions regardless of the soil state of the seabed There is.

또한, 잭업리그의 각 기둥에 동시에 받침부재를 탈착할 수 있어 작업 시간을 단축하는 효과가 있다.In addition, the support member can be detached to each pillar of the jack up league at the same time, thereby reducing the work time.

도 1은 본 발명의 일 실시예에 따른 잭업리그의 기둥 조립 방법을 나타낸 흐름도이다.
도 2는 도 1의 제1단계를 개략적으로 도시한 구성도이다.
도 3은 도 1의 제2단계를 개략적으로 도시한 구성도이다.
도 4는 도 1의 제3단계를 개략적으로 도시한 구성도이다.
도 5는 도 1의 제4단계를 개략적으로 도시한 구성도이다.
1 is a flowchart illustrating a method of assembling a pillar of a jack up league according to an exemplary embodiment of the present invention.
FIG. 2 is a diagram schematically illustrating a first step of FIG. 1.
3 is a configuration diagram schematically illustrating a second step of FIG. 1.
4 is a configuration diagram schematically illustrating a third step of FIG. 1.
5 is a configuration diagram schematically illustrating a fourth step of FIG. 1.

이하 첨부한 도면을 참조하여 본 발명의 바람직한 실시예에 대한 구성 및 작용을 상세히 설명하면 다음과 같다. 또한, 하기 실시예는 여러 가지 다른 형태로 변형될 수 있으며, 본 발명의 범위가 하기 실시예에 한정되는 것은 아니다. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. In addition, the following examples may be modified in many different forms, and the scope of the present invention is not limited to the following examples.

도 1은 본 발명의 일 실시예에 따른 잭업리그의 기둥 조립 방법을 나타낸 흐름도이고, 도 2는 도 1의 제1단계를 개략적으로 도시한 구성도이다.1 is a flowchart illustrating a method of assembling a pillar of a jack up league according to an exemplary embodiment of the present invention, and FIG. 2 is a configuration diagram schematically illustrating a first step of FIG. 1.

도 1 및 도 2에 도시된 바와 같이, 본 발명에 따른 잭업리그의 기둥 조립 방법은 해상에 선박(30) 및 잭업리그(10)를 대기하는 제1단계(S1)를 포함한다. 상기 제1단계(S1)에서 상기 잭업리그(10)는 대륙으로부터 해상으로 이동한 잭업리그(10) 또는 해상에 설치된 잭업리그(10) 일 수 있다. 그리고 상기 선박(30)은 상기 잭업리그(10)의 인근 또는 상기 잭업리그(10)를 설치할 해상의 인근에서 대기하는데, 이러한 상기 선박(30)은 데크(deck) 위에 장치 또는 부품 등을 적재한 상태로 운송 및 잠수를 할 수 있는 바지(barge)선 또는 반잠수정일 수 있다. 한편, 상기 선박(30)의 데크 위 특히 중앙에 그릴리지(grillage, 50)가 설치될 수 있다. 1 and 2, the method of assembling the pillar of the jack up league according to the present invention includes a first step (S1) of waiting for the ship 30 and jack up league 10 on the sea. In the first step (S1), the jack up league 10 may be a jack up league 10 moving from the continent to the sea or a jack up league 10 installed at sea. The vessel 30 stands by near the jack up league 10 or near the sea where the jack up league 10 is to be installed, and the ship 30 loads a device or parts on a deck. It may be a barge or semi-submersible, capable of transporting and diving in the state. On the other hand, a grille (grillage) 50 may be installed on the deck of the vessel 30, in particular in the center.

도 3은 도 1의 제2단계를 개략적으로 도시한 구성도이다.3 is a configuration diagram schematically illustrating a second step of FIG. 1.

도 3에 도시된 바와 같이, 본 발명에 따른 잭업리그의 기둥 조립 방법은 상기 선박(30)을 해저로 잠수시키고 상기 잭업리그(10)가 상기 선박(30)의 상측에 올 수 있도록 이동시키는 제2단계(S2)를 포함한다.As shown in Figure 3, the pillar assembly method of the jack up league according to the present invention is to submerge the vessel 30 to the sea floor and to move the jack up league 10 to come to the upper side of the vessel 30 It includes two steps (S2).

도 4는 도 1의 제3단계를 개략적으로 도시한 구성도이다.4 is a configuration diagram schematically illustrating a third step of FIG. 1.

도 4에 도시된 바와 같이, 본 발명에 따른 잭업리그의 기둥 조립 방법은 상기 잭업리그(10)가 상기 선박(30)의 상측 정위치에 위치하도록 조정한 후 상기 선박(30)을 해상으로 부양시켜 상기 잭업리그(10)가 상기 선박(30)의 데크 위에 놓일 수 있도록 하는 제3단계(S3)를 포함한다. 이때, 상기 그릴리지(50)는 상기 잭업리그(10)의 중앙을 하측에서 지지하여 상기 잭업리그(10)가 상기 선박(30)의 데크 위에 상기 그릴리지(50)의 높이만큼 떠있도록 할 수 있다.As shown in FIG. 4, the pillar assembly method of the jack up league according to the present invention adjusts the jack up league 10 to be positioned at an upper side of the ship 30 and then floats the vessel 30 at sea. And a third step S3 for allowing the jackup league 10 to be placed on the deck of the ship 30. In this case, the grille 50 may support the center of the jack up league 10 from the lower side so that the jack up league 10 floats on the deck of the ship 30 by the height of the grille 50. have.

도 5는 도 1의 제4단계를 개략적으로 도시한 구성도이다.5 is a configuration diagram schematically illustrating a fourth step of FIG. 1.

도 5에 도시된 바와 같이, 본 발명에 따른 잭업리그의 기둥 조립 방법은 상기 잭업리그(10)가 상기 선박(30)의 데크 위에 특히, 상기 그릴리지(50)에 의해 중앙이 지지되어 소정 높이만큼 떠 있는 상태에서 상기 잭업리그(10)의 기둥(11) 하단에 받침부재(40)를 부착하거나 또는 상기 잭업리그(10)의 기둥(11) 하단에 부착된 받침부재(40)를 분리하는 제4단계(S4)를 포함한다. 여기서 상기 잭업리그(10)의 기둥(11) 하단에 받침부재(40)를 부착할 경우에는 상기 제1단계(S1)에서 상기 선박(30)의 데크 위에 상기 받침부재(40)를 적재한 상태로 대기할 수 있다. 그리고 상기 잭업리그(10)의 기둥(11) 하단에서 받침부재(40)를 분리할 경우에는 상기 선박(30)에 분리된 상기 받침부재(40)를 적재할 수 있다. 상기 제4단계(S4)에서 잭업리그(10)의 기둥(11) 하단에 받침부재(40)를 탈착하는 작업은 복수로 형성되는 상기 잭업리그(10)의 기둥(11)에서 동시에 수행할 수 있다. 또한, 수면 위에서 받침부재(40)의 탈착작업을 수행하기 때문에 작업시간이 빠르고 쉽게 할 수 있다.As shown in FIG. 5, the pillar assembly method of the jack up league according to the present invention has the jack up league 10 being supported on the deck of the ship 30, in particular, by the grille 50, and having a predetermined height. Attaching the support member 40 to the lower end of the pillar 11 of the jack up league 10 in the floating state or to separate the support member 40 attached to the lower end of the pillar 11 of the jack up league 10 A fourth step S4 is included. In this case, when the supporting member 40 is attached to the lower end of the pillar 11 of the jack up league 10, the supporting member 40 is loaded on the deck of the vessel 30 in the first step S1. Can wait. When the supporting member 40 is separated from the lower end of the pillar 11 of the jack up league 10, the supporting member 40 separated from the ship 30 may be loaded. In the fourth step S4, the detaching of the support member 40 at the lower end of the pillar 11 of the jack up league 10 may be simultaneously performed by the pillars 11 of the jack up league 10. have. In addition, since the desorption operation of the support member 40 on the water surface, the working time can be quickly and easily.

상기 받침부재(40)는 상기 잭업리그(10)가 연약지반의 해상에 설치될 시 상기 연약지반에 세워지는 상기 잭업리그(10)의 복수의 기둥(11)이 연약지반을 침투하지 못하도록 상기 잭업리그(10)의 각 기둥(11) 하단에 부착되는 것이다. 이러한 상기 받침부재(40)는 일명 스퍼드캔(SPUDCAN)이라 할 수 있다.The support member 40 is the jack-up so that the plurality of pillars 11 of the jack up league 10, which is built on the soft ground when the jack up league 10 is installed on the soft ground, does not penetrate the soft ground. Will be attached to the bottom of each pillar (11) of the rig (10). The support member 40 may be referred to as a spud can (SPUDCAN).

본 발명에 따른 잭업리그의 기둥 조립 방법은 상기 제4단계(S4)에서 상기 잭업리그(10)의 각 기둥(11)에 받침부재(40)를 탈착한 후 상기 잭업리그(10)를 해상에 설치하기 위해서 상기 선박(30)을 잠수하는 제5단계(S5)를 더 포함한다.In the method of assembling the pillar of the jack up league according to the present invention, the jack up league 10 is detached to the sea after detaching the supporting members 40 from each of the pillars 11 of the jack up league 10 in the fourth step S4. It further includes a fifth step (S5) for submerging the vessel 30 to install.

본 발명에 따른 잭업리그의 기둥 조립 방법은 상기 선박(30)이 잠수하여 해상에 부유한 상기 잭업리그(10)를 설치할 해상의 장소로 이동시키는 제6단계(S6)를 더 포함한다. 이때, 받침부재(40)를 부착한 상기 잭업리그(10)는 연약지반의 해상에 설치되고, 받침부재(40)가 분리된 상기 잭업리그(10)는 암반지역의 해상에 설치된다.The pillar assembly method of the jack up league according to the present invention further includes a sixth step (S6) in which the vessel 30 is submerged and moved to a place where the jack up league 10 floating on the sea is to be installed. At this time, the jack up league 10 to which the support member 40 is attached is installed on the sea of the soft ground, and the jack up league 10 from which the support member 40 is separated is installed on the sea of the rock area.

본 발명에 따른 잭업리그의 기둥 조립 방법은 잠수한 상기 선박(30)을 해상으로 부유시키는 제7단계(S7)를 포함한다.The pillar assembly method of the jack up league according to the present invention includes a seventh step (S7) to float the submerged vessel 30 to the sea.

본 발명은 상기 실시 예에 한정되지 않고 본 발명의 기술적 요지를 벗어나지 아니하는 범위 내에서 다양하게 수정 또는 변형되어 실시될 수 있음은 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에 있어서 자명한 것이다.It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit and scope of the invention will be.

10: 잭업리그
11: 기둥
30: 선박
40: 받침부재
50: 그릴리지
10: Jack Up League
11: pillar
30: ship
40: support member
50: grillage

Claims (5)

받침부재가 설치되는 잭업리그(jack-up rig)의 기둥 조립 방법에 있어서,
해상에 선박 및 잭업리그를 대기하는 제1단계;
상기 선박을 해저로 잠수시키고 상기 잭업리그를 상기 선박의 상측으로 이동시키는 제2단계;
상기 잭업리그가 상기 선박의 상측 정위치에 위치하도록 조정한 후 상기 선박을 해상으로 부양시키는 제3단계; 및
상기 잭업리그가 상기 선박의 데크 위에 놓인 상태에서, 상기 잭업리그의 기둥 하단에 받침부재를 부착하거나 또는 상기 잭업리그의 기둥 하단으로부터 받침부재를 분리하는 제4단계를 포함하는 것을 특징으로 하는 잭업리그의 기둥 조립 방법.
In the pillar assembly method of the jack-up rig (jack-up rig) is installed,
A first step of waiting for the ship and the jack-up league at sea;
A second step of submerging the vessel to the seabed and moving the jackup league to an upper side of the vessel;
A third step of adjusting the jack up league to be positioned at an upper side of the ship and then supporting the ship at sea; And
And a fourth step of attaching a supporting member to a lower end of the pillar of the jack up league or separating the supporting member from the lower end of the pillar of the jack up league while the jack up league is placed on the deck of the ship. How to assemble the pillars.
청구항 1에 있어서,
상기 선박의 데크 위에는 상기 잭업리그를 지지하는 그릴리지(grillage)가 구비되는 것을 특징으로 하는 잭업리그의 기둥 조립 방법.
The method according to claim 1,
Method of assembling the jack up league on the deck of the ship characterized in that the grille (grillage) for supporting the jack up league is provided.
청구항 1에 있어서,
상기 선박은 잠수가 가능한 바지선 또는 반잠수정인 것을 특징으로 하는 잭업리그의 기둥 조립 방법.
The method according to claim 1,
The vessel is a jack-up league pillar assembly method characterized in that the submersible barge or semi-submersible.
청구항 1에 있어서,
상기 제4단계 이후에 상기 선박을 잠수시키는 제5단계와
상기 잭업리그를 해상에 설치할 위치로 이동시키는 제6단계 및
상기 선박을 해상으로 부양시키는 제7단계를 더 포함하는 것을 특징으로 하는 잭업리그의 기둥 조립 방법.
The method according to claim 1,
A fifth step of submerging the vessel after the fourth step;
A sixth step of moving the jack up league to a position to be installed at sea; and
And a seventh step of supporting the vessel at sea.
받침부재가 설치되는 잭업리그(jack-up rig)의 기둥 조립 방법에 있어서,
상기 받침부재와 그릴리지가 데크 위에 적재된 선박을 잠수시킨 상태에서 상기 잭업리그를 상기 선박의 상측으로 이동시키고 상기 선박을 해상으로 부유하게 함에 따라 상기 잭업리그의 중앙을 상기 그릴리지가 지지하게 하여 상기 잭업리그의 각 기둥에 상기 받침부재를 탈착하는 것을 특징으로 하는 잭업리그의 기둥 조립 방법.
In the pillar assembly method of the jack-up rig (jack-up rig) is installed,
In the state where the supporting member and the grillage are submerged in the ship loaded on the deck, the jackup league is moved to the upper side of the vessel and the vessel floats at sea so that the grille supports the center of the jackup league. Method of assembling the jack up league, characterized in that for removing the support member on each pole of the jack up league.
KR1020110058138A 2011-06-15 2011-06-15 Method for leg assembly of jack-up rig KR101221550B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110058138A KR101221550B1 (en) 2011-06-15 2011-06-15 Method for leg assembly of jack-up rig

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110058138A KR101221550B1 (en) 2011-06-15 2011-06-15 Method for leg assembly of jack-up rig

Publications (2)

Publication Number Publication Date
KR20120138569A true KR20120138569A (en) 2012-12-26
KR101221550B1 KR101221550B1 (en) 2013-01-14

Family

ID=47905347

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110058138A KR101221550B1 (en) 2011-06-15 2011-06-15 Method for leg assembly of jack-up rig

Country Status (1)

Country Link
KR (1) KR101221550B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101461998B1 (en) * 2013-11-14 2014-11-19 대우조선해양 주식회사 Spudcan and jack-up rig with the same

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102037740B1 (en) 2013-11-08 2019-10-29 대우조선해양 주식회사 Jack up rig having a retractable platform of escape chute

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0237934U (en) * 1988-08-31 1990-03-13
KR950008473Y1 (en) * 1992-04-04 1995-10-11 김이남 A post for fences

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101461998B1 (en) * 2013-11-14 2014-11-19 대우조선해양 주식회사 Spudcan and jack-up rig with the same

Also Published As

Publication number Publication date
KR101221550B1 (en) 2013-01-14

Similar Documents

Publication Publication Date Title
CN100999247B (en) Truss semi-submersible offshore floating structure
RU2571049C2 (en) Truss system of slab against vertical rocking for marine foundation
CN102227349A (en) Semi-submersible offshore structure
TWI624406B (en) Semi-submersible support platform and positioning method thereof
KR20210042504A (en) Fixed type offshore structure and method for installation of Fixed type offshore structure
KR101221550B1 (en) Method for leg assembly of jack-up rig
JP2020522429A (en) Launch method
CN201816730U (en) Low-heaving semi-submersible type platform hull
US8899879B2 (en) Structure-supported jackup system
KR20140035658A (en) Leg system for offshore vessel
CN203890991U (en) Multifunctional well drilling boat for ocean oil filed
KR20120138568A (en) Structure for leg of jack-up rig
US9604708B2 (en) Multi-column tension leg platform
JP2606799B2 (en) Installation method of marine platform
US20170002534A1 (en) System and Method for Improving A Jack Up Platform with Asymmetric Cleats
US11634197B2 (en) Offshore steel structure with integral anti-scour and foundation skirts
CN103879524B (en) A kind of tension leg platform (TLP)
US9022693B1 (en) Rapid deployable floating production system
KR20120138909A (en) Structure for leg of jack-up rig
WO2015126237A1 (en) Offshore support structure and methods of installation
KR101370525B1 (en) Gravity Based Offshore Structure Using Neutral Buoyancy and Construction Method of the Same
TWI691646B (en) Common undertaking platform for underwater base assembly and transportation
US20040265069A1 (en) Mat supported offshore structure
KR101669260B1 (en) Structure and method for leg structure installation of self-elevating unit using float over
KR102060681B1 (en) Marine structure

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170109

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee