KR20110139443A - 3-arch tunnel construction method pre-construction center tunnel part - Google Patents
3-arch tunnel construction method pre-construction center tunnel part Download PDFInfo
- Publication number
- KR20110139443A KR20110139443A KR1020100059543A KR20100059543A KR20110139443A KR 20110139443 A KR20110139443 A KR 20110139443A KR 1020100059543 A KR1020100059543 A KR 1020100059543A KR 20100059543 A KR20100059543 A KR 20100059543A KR 20110139443 A KR20110139443 A KR 20110139443A
- Authority
- KR
- South Korea
- Prior art keywords
- tunnel
- construction
- central
- arch
- midway
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/14—Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/01—Methods or apparatus for enlarging or restoring the cross-section of tunnels, e.g. by restoring the floor to its original level
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
본 발명은 중앙터널부의 선 시공에 의한 3아치터널 시공방법에 관한 것이다. 더욱 구체적으로 대단위 터널단면으로 시공되는 3아치터널을 시공함에 있어 중도갱 시공, 락볼트 설치 및 해체 등에 의한 시공성, 작업성 및 공기관리에 매우 효과적인 중앙터널부의 선시공에 의한 3아치터널 시공방법에 관한 것이다.The present invention relates to a three-arch tunnel construction method by the line construction of the central tunnel portion. More specifically, the three-arch tunnel construction method by the pre-construction of the central tunnel, which is very effective in the construction workability, workability and air management by constructing the middle arch construction, rock bolt installation and dismantling, etc. will be.
통상 터널을 병렬로 한 쌍으로 시공할 경우에는 터널 상호 간의 시공과정에서의 영향, 굴착지반의 이완 등을 고려하여 수평방향으로 서로 일정거리 이격시켜 설치하는 것이 일반적이다.In general, when a pair of tunnels are installed in parallel, it is common to install them at a predetermined distance from each other in the horizontal direction in consideration of the effects of the construction process between the tunnels and the relaxation of the excavation ground.
하지만, 도심지 지하철의 터널식 정거장과 같이 승강장의 위치 등을 고려하여 대단위 단면 터널의 필요성이 있지만 터널을 서로 횡방향으로 이격시켜 시공하는 것이 불합리 할 때는 2아치 또는 3아치 터널시공방식을 따르게 된다.However, there is a need for a large-scale cross section tunnel considering the location of the platform such as the tunnel type of urban subway, but when it is unreasonable to install the tunnels laterally apart from each other, the two arch or three arch tunnel construction method follows.
이에 종래 3아치터널의 시공순서를 도 1a 내지 도 1g를 기준으로 살펴보면 다음과 같다.Thus, the construction order of the conventional three-arch tunnel as follows with reference to Figures 1a to 1g.
먼저, 도 1a와 같이 2개의 선진터널(10,20)을 시공하게 된다. 이러한 선진터널은 위치를 기준으로 하여 좌측 중도갱(10), 우측 중도갱(20)이라고 지칭하기도 한다.First, as shown in FIG. 1a, two
여기서 중도갱은 최종 터널 단면을 형성시키기 이전에 형성시키는 터널을 의미한다.Here, the midway shaft refers to a tunnel formed before forming the final tunnel cross section.
이와 같이 굳이 한 쌍의 중도갱(10,20)을 따로 따로 형성시키는 이유는 3아치터널은 대단위 단면 터널(터널 폭이 30m 정도)이기 때문에 굴착해야하는 터널단면의 크기가 커질 수밖에 없어, 이러한 대단위 단면 터널을 시공하기 위하여 막장을 한꺼번에 굴착하게 되면 적절한 보강수단(지보공으로써 락볼트,30)을 사용한다 할지라도 터널 단면이 매우 불안정해질 수밖에 없어 붕괴의 위험성을 항상 감안해야 하기 때문이다.The reason for forming a pair of
또한, 도심지 지하철과 같은 터널식 정거장은 터널 상부에 빌딩, 도로, 철도 등과 같은 기존 구조물이 시공된 경우가 많기 때문에 막장 굴착 시 지표면 침하 등이 우려되므로 소단위 단면의 중도갱(터널 폭이 7m 정도)을 적절한 보강수단(락볼트)을 사용하여 시공하여 자칫 대형안전사고를 발생시킬 수 있는 지표면의 침하현상을 최대한 억제하면서 대단위 단면의 3아치터널을 최종 시공할 수 있도록 하기 위함이라 할 수 있다.In addition, tunnel-type stops such as urban subways are often constructed with existing structures such as buildings, roads, and railways in the upper part of the tunnel. It can be said that it is possible to make the final construction of 3 arch tunnel of large section while minimizing the settlement of ground surface which can cause large safety accidents by constructing with proper reinforcing means (lock bolt).
이때, 좌측 중도갱의 우측면과 우측 중도갱의 좌측면 사이 공간은 필러 공간이라고 하는데 이러한 필러 공간(F)은 수평방향(횡방향)으로 거리가 크지 않기 때문에 통상 중도갱들(10,20)의 내측면에서 주위 지반쪽으로 방사형으로 설치되는 락볼트(30)가 간섭되므로 락볼트를 설치하지 못하고 필러공간에서의 락볼트는 필러 공간(F)을 관통하여 좌측 중도갱(10)의 우측면과 우측 중도갱(20)의 좌측면 내측에 양 단부가 고정되도록 하는 타이볼트(40)로 락볼트를 시공할 수밖에 없어 이를 설치하기 위한 공종이 추가될 수밖에 없기 때문에 추가 공종에 따른 자재투입, 공기 확보에 큰 노력이 요구될 수밖에 없었다.In this case, the space between the right side of the left midway shaft and the left side of the right midway shaft is called a filler space, and since the filler space F is not large in the horizontal direction (lateral direction), the center of the
나아가 중도갱의 시공을 발파 시공에 의할 경우 필러공간이 좁아 발파 시 주위 지반의 이완에 따른 터널 안정성에 영향을 줄 수 있다는 문제점이 있었다.In addition, when the construction of the midway shaft was carried out by the blasting construction, there was a problem that the filler space was narrow, which could affect the tunnel stability due to the relaxation of the surrounding ground during blasting.
다음으로는 도 1b와 같이 각각의 중도갱(10,20)에 기둥구조물을 설치하여 최종 3아치 터널의 중간기둥(50)을 시공하게 된다. 이러한 중간기둥(30)은 결국 대단위 터널 단면의 중간 상면을 하부 지반에 지지시켜 안전한 터널 단면 시공을 위한 것이라 할 수 있으며, 통상 3아치터널은 2개의 중간 기둥을 설치하게 된다.Next, as shown in FIG. 1B, pillar structures are installed in the
하지만 중도갱(10,20) 내측에서 각각의 중간기둥(30)을 설치하는 작업이 좁은 공간에서 이루어지다보니 아무래도 시공성이 떨어질 수밖에 없다는 문제점이 있었다.However, since the work for installing each of the
다음으로는 도 1c와 같이 중도갱(10,20) 사이의 필러공간(F) 상부 지반을 굴착하여 중앙터널부(60)를 시공하게 된다. Next, as shown in FIG. 1c, the upper ground of the filler space F between the
이때, 좌측 중도갱(10)과 우측 중도갱(20)의 필러공간(F)에 설치된 타이볼트는 제거해야 하고, 굴착장비 등을 동원하여 중앙터널부를 시공하고 중앙터널부 주위 지반에 방사형으로 락볼트(30)를 추가 시공하게 된다.At this time, the tie bolts installed in the filler space (F) of the
물론 필러 공간도 제거해야 하며, 필러공간과 접하고 있는 중도갱의 좌, 우 측면부도 함께 제거되는데 이러한 제거 작업이 좁은 공간에서 이루어지다보니 시공성 및 작업성이 저하될 수 밖에 없었다.Of course, the filler space has to be removed, and the left and right side portions of the midway shaft which are in contact with the filler space are also removed. As such removal work is performed in a narrow space, workability and workability are deteriorated.
나아가, 발파에 의한 중앙터널부 시공이 가능하지만 필러공간이 좁아 발파 시 파편 등 비석에 의하여 중도갱 중간기둥의 손상이 우려되는 등 시공에 제한이 많고, 별도의 방호시설을 설치해야 하는 문제점이 있게 된다.In addition, it is possible to construct the central tunnel part by blasting, but the filler space is narrow, and there are many limitations in the construction, such as fear of damaging the middle column by debris, etc. do.
다음으로는 도 1d와 같이 좌측 및 우측 중도갱(10,20)의 좌측과 우측면에 해당하는 좌측 및 우측 본선 터널부(70,80)를 추가로 시공하고 역시 좌측 및 우측 본선터널부 굴착 시 이완된 주위 지반에 대하여 방사형으로 락볼트를 역시 추가 시공하게 된다.Next, as shown in FIG. 1D, the left and right main
이때, 좌측 중도갱과 우측 중도갱의 좌측면과 우측면에 형성된 락볼트를 제거하면서 결국 좌측 중도갱과 우측 중도갱에 의한 굴착면은 모두 제거됨을 알 수 있다.At this time, it can be seen that the excavation surface by the left midway shaft and the right midway shaft is removed while removing the rock bolts formed on the left and right sides of the left midway shaft and the right midway shaft.
이로써, 3아치터널단면에 있어 중앙터널부와 좌측 및 우측 본선터널부가 최종 시공됨을 알 수 있다.As a result, it can be seen that the central tunnel portion and the left and right main tunnel portions are finally constructed in the three-arch tunnel section.
다음으로는 도 1e와 같이, 중앙터널부(60)와 좌측 및 우측 본선터널(70,80)에 라이닝 콘크리트(90)를 시공하여 3아치터널단면을 완성시키게 된다.Next, as shown in FIG. 1E, the lining concrete 90 is constructed in the
이에 3아치터널을 시공하기 위해서 2개의 중도갱, 중앙터널부 및 2개의 본선터널부와 같이 5번의 터널굴착, 지보공 공종이 소요됨을 알 수 있어 시공공종이 매우 복잡해져 이로 인한 시공비용 증가 등의 문제가 발생함을 알 수 있다.In order to construct a three-arch tunnel, five tunnel excavation and geo-engineering work are required, such as two midway tunnels, a central tunnel, and two main tunnels. Therefore, the construction work becomes very complicated, resulting in increased construction costs. It can be seen that occurs.
또한, 위에서 살펴본 것과 같이 2개의 중도갱에는 중간기둥이 설치되는데 비교적 좁은 공간에 장비를 동원하여 중간기둥을 시공해야 하기 때문에 시공성이 매우 떨어질 수밖에 없다는 문제점이 있으며, 중앙터널부를 시공하기 위한 장비 반입에 중간기둥이 간섭되는 등 효율적인 장비활용이 매우 어렵다는 문제점이 있었다.In addition, as described above, the two midway shafts are installed with intermediate pillars, and since the intermediate pillars must be constructed by mobilizing the equipment in a relatively narrow space, there is a problem that the constructability is very poor. There was a problem that the efficient utilization of the equipment, such as the middle pillar is interfered.
또한, 중도갱에 설치되는 락볼트 등은 시공 후 모두 제거되어야 하는데 이는 자재의 효율적 이용에 반하게 되어 공사비 증가요인이 될 수 밖에 없었다.In addition, rock bolts, etc. installed in the midway shaft should be removed after construction, which is against the efficient use of materials, which inevitably increased the cost of construction.
또한, 3아치터널의 라이닝 콘크리트 시공 시 대단위 단면을 한꺼번에 시공하다 보니, 라이닝 콘크리트 시공에 의하여 공기가 결정될 수 밖에 없어 공종의 효율적인 관리가 어렵다는 문제점이 있었다.In addition, when the lining concrete construction of the three-arch tunnel is constructed at a large unit at a time, there is a problem that the effective management of the construction is difficult because the air can not be determined by the lining concrete construction.
이에 본 발명은 종래 3아치터널 시공방식을 탈피하여 보다 안정적이면서도 공기를 단축할 수 있고, 시공성 및 작업성이 뛰어나 경제적인 3아치터널 시공이 가능한 시공성이 개선된 3아치터널 시공방법 제공을 해결하고자 하는 과제로 한다.Accordingly, the present invention is to solve the conventional three-arch tunnel construction method to provide a more stable three-tunnel construction method that can shorten the air more stably, excellent construction and workability and economical construction of three-arch tunnel construction We assume problem to do.
이에 본 발명은The present invention
3아치터널의 대단위 중앙터널부를 먼저 시공하고,Construct the large central tunnel part of the 3-arch tunnel first,
상기 대단위 중앙터널부의 내측에 중간기둥을 시공하고,Construct a middle pillar inside the central tunnel unit of large unit,
상기 대단위 중앙터널부의 좌측 및 우측으로 본선 터널부를 시공하는 단계를 포함하는 중앙터널부의 선시공에 의한 3아치터널 시공방법을 제공하게 된다.It provides a three-arch tunnel construction method by the pre-construction of the central tunnel portion comprising the step of installing the main line tunnel portion to the left and right of the large central tunnel portion.
즉, 종래와 같이 한 쌍의 중도갱 설치 공종을 완전히 배제하고 대단위 중앙터널부를 먼저 시공한 후, 상기 중앙터널부의 좌,우측에 본선 터널부를 직접 시공하는 방식을 채택한 것이다.That is, the conventional method is to completely remove the pair of midway shaft installation, and to install a large central tunnel first, and then to directly install the main tunnel to the left and right of the central tunnel.
또한 바람직하게는 상기 대단위 중앙터널부의 중간기둥 시공 후 대단위 중앙터널부의 내측면에 라이닝 콘크리트를 일부 선시공하고, 좌측 본선터널부와 우측 본선터널부 시공 후, 좌측 본선 터널부 및 우측 본선 터널부에 라이닝 콘크리트를 후시공하는 중앙터널부의 선시공에 의한 3아치터널 시공방법을 제공하게 된다.In addition, preferably after the construction of the middle pillar of the central unit of the large unit of lining concrete on the inner surface of the central unit of the central unit, and after the construction of the left main and right main tunnel, lining the left main tunnel and right main tunnel To provide a three-arch tunnel construction method by the pre-construction of the central tunnel portion to post-concrete concrete.
즉, 종래에는 중도갱 시공에 의하여 터널 단면의 시공 공종이 마지막에 완성되기 때문에 라이닝 콘크리트를 한꺼번에 형성시켜 콘크리트의 타설 및 양생기간이 절대적으로 필요하게 되지만, 본 발명의 경우에는 중앙터널부를 먼저 시공하여 완성시키기 때문에 라이닝 콘크리트를 중앙터널부 시공 완료 시 즉시 시공하여 적어도 중앙터널부 라이닝 시공에 의하여 공사 전체의 공사기간이 영향받지 않도록 하였다.That is, in the prior art, since the construction work of the tunnel cross section is completed at the end of the mid-pit construction, lining concrete is formed all at once, so that the concrete pouring and curing periods are absolutely necessary, but in the case of the present invention, the central tunnel is constructed first. In order to complete the construction, the lining concrete was constructed immediately upon completion of the construction of the central tunnel, so that the entire construction period was not affected by at least the construction of the lining of the central tunnel.
본 발명에 의하여By the present invention
첫째, 종래 중도갱을 설치하지 않기 때문에 중도갱 시공을 위한 공기, 장비운용, 자재의 투입을 배제할 수 있게 된다.First, it is possible to exclude the air, equipment operation, the input of materials for the construction of the midway shaft because the conventional midway shaft is not installed.
둘째, 중도갱의 시공시 설치되는 락볼트, 타이볼트 등을 제거할 필요가 없으므로 이러한 지보재 해체에 따른 공기의 지연, 해체 시 발생할 수 있는 각종 안전사고 등의 문제 발생을 최소화할 수 있게 된다.Second, there is no need to remove the lock bolts, tie bolts, etc. installed during the construction of the midway gang, it is possible to minimize the occurrence of problems such as the delay of the air due to the dismantling of the support material, various safety accidents that may occur during dismantling.
셋째, 중앙터널부 시공에 있어 종래 중도갱 사이의 필러공간에 대한 보강문제, 중도갱을 측면부를 해체하면서 발생하는 발파 비산문제 등을 해결할 수 있어 시공성 및 작업성이 크게 증진됨을 알 수 있다.Third, in the construction of the central tunnel, it is possible to solve the problem of reinforcement for the filler space between the middle shafts and the blasting scattering problem generated by dismantling the side shafts.
넷째, 라이닝 콘크리트 시공의 경우 중앙터널부 시공이 완료된 이후에 선시공하여 라이팅 콘크리트 선시공에 따른 공기관리에 매우 효율적이게 됨을 알 수 있다.Fourth, in the case of lining concrete construction it can be seen that after the construction of the central tunnel is completed by the pre-construction to be very efficient in air management according to the pre-installed concrete construction.
다섯째, 종래 3아치터널은 좌우 중도갱 굴착, 타이볼트 설치, 중앙터널 굴착, 중간기둥설치의 복잡한 시공단계를 거쳐야 하지만 본 발명의 경우에는 중앙터널 굴착, 중간기둥 설치로 시공단계를 매우 단순화시킬 수 있어 시공 싸이클타임의 대폭적인 단축에 의한 경제성이 크게 향상됨을 알 수 있다.Fifth, the conventional three-arch tunnel has to go through the complex construction stages of left and right midway pit excavation, tie bolt installation, central tunnel excavation, middle pillar installation in the case of the present invention can greatly simplify the construction step by the center tunnel excavation, intermediate pillar installation Therefore, it can be seen that the economic efficiency is greatly improved by the drastic reduction of construction cycle time.
본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is shown by the following claims rather than the above description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present invention. do.
도 1a, 도 1b, 도 1c, 도 1d 및 도 1e는 종래 3아치터널의 시공순서도,
도 2a, 도 2b 및 도 2c는 본 발명에 의한 3아치터널의 시공순서도,
도 3a 및 도 3b는 본 발명에 의한 3아치터널의 시공단면도이다.1a, 1b, 1c, 1d and 1e is a construction sequence diagram of a conventional three-arch tunnel,
2a, 2b and 2c is a construction sequence diagram of the three-arch tunnel according to the present invention,
3A and 3B are construction cross-sectional views of a three-arch tunnel according to the present invention.
아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.
도 2a 내지 도 2c는 본 발명에 의한 3아치터널의 시공방법을 순서대로 도시한 것이다.2a to 2c show the construction method of the three-arch tunnel according to the present invention in order.
먼저 도 2a와 같이 3아치터널의 중앙터널부(100)를 종래 좌측 및 중도갱의 시공없이 선 시공하게 된다.First, as shown in FIG. 2a, the
이러한 중앙터널부(100)는 발파, 기계굴착 어떠한 방법을 이용하더라도 종래 좌측 및 중도갱이 시공되지 않아 달리 주위 지반에 영향을 주지 않게 되며, 이에 본 발명의 3아치터널 시공방법은 좌측 및 중도갱의 시공공종이 배제되도록 함을 알 수 있다.The
물론, 이러한 중앙터널부(100)의 내측면에서 주위 지반에 방사형으로 락볼트(110)를 시공하여 중앙터널부(100)의 안정성을 충분히 확보할 수 있도록 하게 된다.Of course, the
다음으로는 중앙터널부(100)의 내측에 중간기둥(120)을 서로 횡방향으로 이격되도록 하여 시공하게 된다. 이러한 중간기둥(120)은 중앙터널부(100)의 상면과 하부지반 사이에 설치되어 중앙터널부의 안정성을 추가 확보할 수 있도록 하게 된다.Next, the
이에 본 발명의 경우 중간기둥(120)을 설치하되 비교적 굴착단면이 큰 중앙터널부(100)에서 중간기둥(120)의 시공이 가능하므로 종래 좁은 공간의 중도갱에서의 시공성 저하 문제를 충분히 해결할 수 있게 됨을 알 수 있다.In the case of the present invention, the
다음으로는 도 2b와 같이 중앙터널부(100)의 좌측 본선터널부(200)를 시공하게 되는데 이는 중앙터널부(100)의 좌측 측면에 설치된 락볼트(110)와 중앙터널부(100)의 좌측 측면을 제거하면서 시공하게 되며, 좌측 본선터널부(200)의 주위 지반에 방사형으로 락볼트(110)를 추가 시공하게 된다.Next, as shown in FIG. 2b, the left
따라서 본 발명은 중앙터널부(100)의 좌측 측면만 제거하기 때문에 종래와 같이 기 시공된 터널단면의 제거작업이 현저하게 감소하게 됨을 알 수 있다.Therefore, since the present invention removes only the left side of the
다음으로는 중앙터널부(100)의 우측 본선터널부(300)를 시공하게 되는데 이도 역시 중앙터널부(100)의 우측 측면에 설치된 락볼트(110)와 중앙터널부(100)의 우측 측면을 제거하면서 시공하게 되며, 우측 본선터널부(300)의 주위 지반에 방사형으로 역시 락볼트(110)를 추가 시공하게 된다.Next, the right
이에 본 발명은 중앙터널부(100)의 우측 측면만 제거하기 때문에 종래와 같이 기 시공된 터널단면의 제거작업이 현저하게 감소하게 됨을 알 수 있다.Therefore, since the present invention removes only the right side of the
다음으로는 도 2c와 같이 이에 최종 라이닝 콘크리트(130)를 3아치터널 전체 단면에 걸쳐 시공하여 최종 3아치터널의 시공이 완료될 수 있음을 알 수 있다.Next, as shown in Figure 2c it can be seen that the construction of the final three-arch tunnel by constructing the
이에 본 발명에 의한 3아치터널 시공방법은Thus, the three-arch tunnel construction method according to the present invention
종래 좌,우측 중도갱의 시공공종이 배제되고, 이에 따라 필러공간에 설치되는 타아볼트의 설치공종도 배제되어 3아치터널 터널 시공공종이 대폭 줄어들게 됨을 알 수 있게 된다.Conventionally, the construction work of the left and right midway shafts is excluded, and thus, the installation work of the taabolt installed in the filler space is also excluded, and the construction of the three-arch tunnel tunnel can be understood to be greatly reduced.
또한, 중앙터널부와 좌,우 본선부터널을 차례대로 시공하기 때문에 락볼트의 설치, 먼저 시공된 구조물의 간섭문제를 최소화 시킬 수 있어 매우 효율적이고 경제적인 3아치터널 시공이 가능하게 된다.In addition, since the tunnels are installed in order from the central tunnel and the left and right main ships in order, it is possible to minimize the interference problem of the installation of the rock bolts and to construct the first three-tunnel construction.
또한, 라이닝 콘크리트의 경우 중앙터널부 시공 시 중간기둥과 함께 일부 먼저 시공하고, 좌,우 본선부터널 시공 후 라이팅 콘크리트를 최종 완성시킬 수 있어 공기의 단축이 가능하게 된다.In addition, in the case of lining concrete, the construction of the central tunnel part along with the middle column first construction, and after finishing the construction of the building from the left and right main line to finalize the air can be shortened.
이는 종래의 경우 최종 3아치터널의 단면이 마직막에 완성되기 때문에 라이닝 콘크리트 시공공종이 맨 나중에 실시될 수 밖에 없지만, 본 발명의 경우에는 터널중앙부를 시공하여 먼서 완성시키기 때문에 터널중앙부에 대한 라이닝 콘크리트 시공을 앞당길 수 있어 시공관리에 매우 효율적이게 됨을 알 수 있다.In the conventional case, since the end of the final three-arch tunnel is completed at the end, the lining concrete construction work cannot but be carried out at the end, but in the case of the present invention, the lining concrete construction for the tunnel center part is completed by constructing the tunnel center part first. It can be seen that it becomes very efficient in construction management.
도 3a는 본 발명에 의한 상대식 3아치터널식 지하철 정거장의 최종시공단면도를 확인할 수 있는데, 좌, 우측 본선터널부(200,300)에 있어 승강장(400)이 마련되며, 중간기둥(120)을 기준으로 철로 등의 선로 또는 도로의 형성이 가능함을 알 수 있다.Figure 3a can confirm the final construction cross-sectional view of the relative three-arch tunnel-type subway station according to the present invention, the
도 3b는 본 발명에 의한 섬식 3아치터널식 지하철 정거장의 최종시공단면도를 확인할 수 있는데, 좌, 우측 본선터널부(200,300)에 있어 선로 또는 도로가 마련되며, 중간기둥(120)을 기준으로 좌, 우로 승강장(400)이 형성될 수 있도록 함을 알 수 있다.Figure 3b can confirm the final construction cross-sectional view of the island-type three-arch tunnel type subway station according to the present invention, the left or right main line tunnel portion (200,300) in the track or road is provided, based on the
100: 중앙터널부
110: 록볼트 200: 좌측 본선터널부
300: 우측 본선터널부 400: 승강장100: Central Tunnel
110: rock bolt 200: left main tunnel
300: right main tunnel 400: platform
Claims (2)
상기 대단위 중앙터널부의 내측에 중간기둥을 시공하고,
상기 대단위 중앙터널부의 좌측 및 우측으로 본선 터널부를 시공하는 단계를 포함하는 중앙터널부의 선시공에 의한 3아치터널 시공방법.Construct the large central tunnel part of the 3-arch tunnel first,
Construct a middle pillar inside the central tunnel unit of large unit,
3. A three-arch tunnel construction method by pre-construction of the central tunnel portion comprising the step of installing the main tunnel portion to the left and right of the central central tunnel portion.
상기 대단위 중앙터널부의 중간기둥 시공 후 대단위 중앙터널부의 내측면에 라이닝 콘크리트를 일부 선시공하고,
좌측 본선터널부와 우측 본선터널부 시공 후, 좌측 본선 터널부 및 우측 본선 터널부에 라이닝 콘크리트를 후시공하는 것을 특징으로 하는 중앙터널부의 선시공에 의한 3아치터널 시공방법.The method of claim 1,
After constructing the middle pillar of the central unit of the large unit, some lining concrete is pre-installed on the inner side of the central unit of the central unit,
A three-arch tunnel construction method according to the preliminary construction of the central tunnel portion, characterized in that after the construction of the left main line and the right main tunnel, the lining concrete is post-installed on the left main tunnel and the right main tunnel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100059543A KR101211689B1 (en) | 2010-06-23 | 2010-06-23 | 3-arch tunnel construction method pre-construction center tunnel part |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100059543A KR101211689B1 (en) | 2010-06-23 | 2010-06-23 | 3-arch tunnel construction method pre-construction center tunnel part |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20110139443A true KR20110139443A (en) | 2011-12-29 |
KR101211689B1 KR101211689B1 (en) | 2012-12-20 |
Family
ID=45504931
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100059543A KR101211689B1 (en) | 2010-06-23 | 2010-06-23 | 3-arch tunnel construction method pre-construction center tunnel part |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101211689B1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110094212A (en) * | 2019-04-28 | 2019-08-06 | 北京万兴建筑集团有限公司 | A kind of structure more cabins pipe gallery tunnel arranged side by side and its construction method independently of each other |
CN112012763A (en) * | 2020-07-23 | 2020-12-01 | 湖南省交通规划勘察设计院有限公司 | Construction method of double-layer primary support multi-arch tunnel structure |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200311976Y1 (en) | 2002-12-18 | 2003-05-09 | (주)현이앤씨 | Structure about center wall of three arch tunnel excavation method and steel sheeting |
KR100438795B1 (en) | 2003-07-31 | 2004-07-06 | (주)현이앤씨 | Design method about center wall of three arch tunnel the upside fixing type of lining excavation method |
KR100752285B1 (en) * | 2006-01-11 | 2007-08-29 | 주식회사 케이투기술단 | Construction method for two arches tunnel |
-
2010
- 2010-06-23 KR KR1020100059543A patent/KR101211689B1/en active IP Right Grant
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110094212A (en) * | 2019-04-28 | 2019-08-06 | 北京万兴建筑集团有限公司 | A kind of structure more cabins pipe gallery tunnel arranged side by side and its construction method independently of each other |
CN112012763A (en) * | 2020-07-23 | 2020-12-01 | 湖南省交通规划勘察设计院有限公司 | Construction method of double-layer primary support multi-arch tunnel structure |
Also Published As
Publication number | Publication date |
---|---|
KR101211689B1 (en) | 2012-12-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102094649B (en) | Method for constructing underground space by shield-shallow buried covered excavation composite method | |
KR100876546B1 (en) | Arched Steel Formwork | |
CN103032073B (en) | Urban subway mudstone stratum connected aisle and shield tunneling parallel construction method | |
CN103075163B (en) | Support change process of second liner construction of large-cross-section tunnel | |
JP6480815B2 (en) | Tunnel junction structure and tunnel construction method | |
CN111520145B (en) | Underground excavation tunnel primary support slope adjusting and arch changing construction method | |
CN109989767A (en) | The ruggedized construction and construction method of existing railway are worn under Large span tunnel | |
CN106869970A (en) | A kind of bored tunnel method for protecting support of assembled compensation deformation | |
CN107130968A (en) | A kind of tunnel construction mid-board | |
CN104632245A (en) | Method using multi-pilot-tunnel expanding excavation large-diameter shield tunnel for building subway station | |
CN110847915A (en) | Construction process for jumping-cutting demolishing and subsection back-jacking of double-side-wall temporary support of shallow-buried fine sand layer | |
JP6715667B2 (en) | Reconstruction method for lining of existing 2-lane road tunnel | |
CN105256836A (en) | Construction method for fast restoring road traffic in construction of underground project | |
KR101211689B1 (en) | 3-arch tunnel construction method pre-construction center tunnel part | |
KR102301960B1 (en) | Horizontal division simultaneous excavating method for tunnel | |
KR20130048883A (en) | Construction method for 2arch tunnel using shotcrete way | |
JP3888993B2 (en) | Tunnel widening method | |
CN202768001U (en) | Arc bridge type integral supporting structure for inclined well bell mouth construction | |
CN109594993A (en) | A kind of tunnel enlarging construction method in the case of uninterrupted traffic | |
JP5794794B2 (en) | Tunnel construction method and tunnel construction system | |
JP2013160029A (en) | Tunnel structure and method for constructing the same | |
JP4415838B2 (en) | Construction method inside tunnel | |
KR20140026076A (en) | Construction method of 2-arch tunnel using lattice girder | |
CN103075164B (en) | Double-hole and two-liner sequential isochronous propelling construction process | |
JP7451337B2 (en) | Tunnel renewal method and structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20151019 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20161122 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20171218 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20180927 Year of fee payment: 7 |