KR20100027434A - Post pile and sheet pile combination - Google Patents
Post pile and sheet pile combination Download PDFInfo
- Publication number
- KR20100027434A KR20100027434A KR1020080086351A KR20080086351A KR20100027434A KR 20100027434 A KR20100027434 A KR 20100027434A KR 1020080086351 A KR1020080086351 A KR 1020080086351A KR 20080086351 A KR20080086351 A KR 20080086351A KR 20100027434 A KR20100027434 A KR 20100027434A
- Authority
- KR
- South Korea
- Prior art keywords
- pile
- sheet
- sheet pile
- file
- shaped
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
- E02D5/06—Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
- E02D5/08—Locking forms; Edge joints; Pile crossings; Branch pieces
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/24—Placing by using fluid jets
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
- E02D2300/0032—Steel; Iron in sheet form, i.e. bent or deformed plate-material
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
The present invention relates to a deformed sheet pile and a method of installing the same, and more particularly, when an underground excavation work is performed in the basic construction for various buildings, inserting an H type pile into the ground, and the H type pile Insert the seat pile with seat pile connection hook adjacent to the ground, install temporary block structure inside the ground, and proceed with underground excavation to make the ground stable. Soil and groundwater to collapse and ground due to instability of ground It relates to a deformed sheet pile and its installation method to prevent the inflow of water.
In general, excavation work is carried out with a certain depth to the lower side of the ground in order to build the underground structure of the building, and during such excavation work, temporary earthquake structures to prevent the earth wall from collapsing due to earth pressure or water pressure by the excavation. The installation work is being done in parallel.
In the construction of temporary cladding structure, there were problems of ordering, settlement, lack of free space at the border of adjacent land, construction period and material loss in the existing construction method (H-Pile + earth plate). The method was used.
The sheet pile method is not a plate concept when constructing a wall of a wall, but a method of creating a wall structure by a continuous construction method of engaging a plate of a small pile concept. That is, this is by the continuous type of the sheet pile (Sheet Pile) of the same width as compared to the earth plate method has the advantage that the order effect is improved and settlement problems can be solved. However, in this method, since the construction of the sheet pile is continuous type, the construction speed is very slow, and the sheet pile is inevitably cut in the middle of the construction by the one-way continuous construction. The problem of air delay and material cost was enormous, as it had to be calibrated. In addition, the existing sheet piles have a very small allowable bending stress in the direction of the shaft, so that all of them must be inserted to a certain depth to cope with the main earth pressure. Therefore, there are problems such as air delay and material cost increase.
In addition, the sheet pile used in the sheet pile construction method has a curved shape, not a plate shape, with connecting rings at both ends. In theory, steel sheet can be used for recycling, but in practice, it can be used only once or twice. The curved part is unfolded or the ring is deformed, which makes it difficult to recycle.
The present invention has been devised to solve the above problems, the present invention relates to a modified sheet pile and its installation method, and more particularly, when the underground excavation work in the base construction for the construction of various buildings, Insert the H-shaped thumb pile, insert the sheet pile with seat pile connection hook adjacent to the H-shaped thumb pile, install the temporary block structure inside the ground, and proceed with the underground excavation to make the ground stable. This is to prevent the inundation and excavation of soil and groundwater due to instability.
When the present invention is used, the ground is excavated after the deformation sheet pile is installed, so it may be effective for stabilization of the ground, and the sheet pile inserted between the H-shaped piles may be used by connecting one or two or more grounds. Depending on the state of use, the utilization varies. In addition, since the degree of function is increased, the problem of the conventional earth plate method can be solved. In addition, compared to the existing sheet pile method, semi-permanent materials can be recycled, thereby reducing the waste of resources as well as recycling the materials used in the existing sheet pile method. In addition, the existing sheet pile method requires the incorporation of individual sheet piles up to a certain depth, which reduces the economic efficiency. Economical in time and cost.
The present invention provides a connection guide sheet attaching step of attaching a
As a temporary soil structure to prevent the stability of the ground and the inflow of groundwater, a pair of H-
When using the present invention,
First, the air is shorter and the ordering effect is superior to that of the earth plate method.
Second, compared with the CIP method, the upper head concrete pouring that integrates piles is not required at all and the verticality can be improved by using a separate guide frame.
Third, it is excellent in close construction at adjacent land boundary lines and is drawn after construction of underground walls, so it does not exist as a permanent object in the ground, so it is eco-friendly and the construction of underground structures can be made by making the best use of the site.
Fourth, the excavation back ground loosening, underground buried ground escape, damage and ground subsidence are relatively small compared with the earth plate method.
Fifth, the construction speed is very fast compared to the existing sheet pile method or CIP method, so the economy is excellent.
The present invention relates to a modified sheet pile and its installation method,
The present invention provides a connection guide sheet attaching step of attaching a
As a temporary soil structure to prevent the stability of the ground and the inflow of groundwater, a pair of H-
Here, the
In the sheet pile insertion step, the
In the additional sheet file inserting step, the
In addition, a
In addition, the H-type thumb pile insertion step or finishing H-type thumb pile insertion step in the direction in which the H-
In addition, the sheet file inserting step or the additional sheet file inserting step includes a
In addition, after the finishing H-type thumb pile insertion step, the installation of the belt strip to install the
And, the groove filling 400, the
Hereinafter, the present invention will be described in more detail with reference to the accompanying drawings.
Figure 2 is a perspective view showing a modified seat pile installed in accordance with the present invention, Figure 3 is an exploded perspective view of the H-shaped pile and the seat pile of the present invention, Figure 4 is a component H of the present invention 5 is a cross-sectional view of a thumb pile and a sheet pile, and FIG. 5 is a perspective view of a sheet pile which is a component of the present invention having a tip shoe, and FIG. Is a perspective view (a) mounted on an H-shaped thumb pile, (b) mounted on a sheet pile, showing a state in which a conduit and an injection nozzle are provided on a component of a deformation sheet pile according to the present invention. 8 is a perspective view showing an example of an induction frame having an induction groove used in the present invention, Figure 9 is a cross-sectional view showing a state in which the groove filling machine used in the present invention is installed in the first space portion, Figure 10 is a view of the present invention Component An exploded perspective view of the fill.
As shown in FIG. 2, the present invention, unlike the conventional sheet pile method, further includes an H-
Figure 3 is an exploded perspective view of the H-shaped thumb pile and the seat pile of the present invention. As shown in FIG. 3, the H-
H-
In addition, the H-shaped
Figure 4 is a cross-sectional view of the H-shaped thumb pile and sheet pile which is a component of the present invention.
As shown in Figure 4 (a) H-shaped
The H-shaped
5 is a perspective view of a sheet pile that is a component of the present invention having a tip shoe. As shown in FIG. 5, the
6 is a cross-sectional view showing a state in which the modified sheet pile according to the present invention is installed.
As shown in FIG. 6, the
Figure 7 is a perspective view (a) mounted on the H-shaped thumb pile, (b) seat mounted on the sheet pile of the deformed sheet pile according to the present invention with the conduit and the injection nozzle in the component.
Figure 7 (a) shows the
Since the H-
8 is a perspective view showing an example of an induction frame having an induction groove used in the present invention.
9 is a cross-sectional view showing a state in which the groove filling machine used in the present invention is installed in the first space portion, and FIG. 10 is an exploded perspective view of the groove filling machine which is a component of the present invention.
In general, after installing the earthquake structure to increase the bearing capacity by installing a belt to increase the resistance of earth pressure and water pressure. As shown in FIG. 9, after installing the deformation sheet pile according to the present invention, the
When the
The groove filling 400 is mounted on the
That is, the groove filling 400 is composed of a
1 is a perspective view of a sheet pile installed using a conventional sheet pile method.
Figure 2 is a perspective view showing a state in which the modified sheet pile according to the present invention is installed.
Figure 3 is an exploded perspective view of the H-shaped thumb pile and the seat pile of the present invention.
Figure 4 is a cross-sectional view of the H-shaped thumb pile and the sheet pile which is a component of the present invention.
Figure 5 is a perspective view of the tip pile of the sheet pile which is a component of the present invention.
Figure 6 is a cross-sectional view showing a state in which the modified sheet pile is installed in accordance with the present invention.
Figure 7 is a perspective view (a) mounted on the H-shaped thumb pile, (b) seat mounted on the sheet pile of the deformed sheet pile according to the present invention with the conduit and the injection nozzle in the component.
Figure 8 is a perspective view showing an example of an induction frame having an induction groove used in the present invention.
9 is a cross-sectional view showing a groove filling machine used in the present invention is installed in the first space.
Figure 10 is an exploded perspective view of the groove filling the components of the present invention.
11 is a block process diagram step by step of the present method.
<Description of the symbols for the main parts of the drawings>
1: ground 2: conventional sheet pile
10: guide frame 11: guide groove
100: H-shaped thumb pile 110: Web
111: water jet conduit 112: jet nozzle
120: Flange 150: Connection guide sheet
151: guide hanger 160: fixed part
200: sheet file 210: sheet file connection hanger
220: tip shoe 250: hook portion
300: strip 350: first space part
360: second space 400: home filling
410: clasp 420: clamp
421: fixing bolt 430: fixing nut
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020080086351A KR20100027434A (en) | 2008-09-02 | 2008-09-02 | Post pile and sheet pile combination |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020080086351A KR20100027434A (en) | 2008-09-02 | 2008-09-02 | Post pile and sheet pile combination |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20100027434A true KR20100027434A (en) | 2010-03-11 |
Family
ID=42178399
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020080086351A KR20100027434A (en) | 2008-09-02 | 2008-09-02 | Post pile and sheet pile combination |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20100027434A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100978468B1 (en) * | 2009-06-12 | 2010-08-26 | 박강호 | Reinforced massive soil body making use of arching effect and method constructing by it |
KR200452946Y1 (en) * | 2010-08-05 | 2011-03-29 | 황현만 | Welded H type steel sheet pile and integrated composite order wall |
KR200453408Y1 (en) * | 2010-08-05 | 2011-05-03 | 황현만 | Integral Order Wall by Continuous Coupling of Welded H Type Steel Sheet Piles |
-
2008
- 2008-09-02 KR KR1020080086351A patent/KR20100027434A/en not_active Application Discontinuation
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100978468B1 (en) * | 2009-06-12 | 2010-08-26 | 박강호 | Reinforced massive soil body making use of arching effect and method constructing by it |
KR200452946Y1 (en) * | 2010-08-05 | 2011-03-29 | 황현만 | Welded H type steel sheet pile and integrated composite order wall |
KR200453408Y1 (en) * | 2010-08-05 | 2011-05-03 | 황현만 | Integral Order Wall by Continuous Coupling of Welded H Type Steel Sheet Piles |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100882831B1 (en) | Reformed sheet plate and the method of installation of the same | |
KR100846229B1 (en) | Establishment Method of Soil Guard Structure | |
CN108291377A (en) | Temporary facility water-proof type soil-baffling structure body and its construction method | |
KR100968048B1 (en) | A retaining panel structure and construction method | |
KR20120089665A (en) | Earth retaining wall and method of constructing same | |
KR20100027434A (en) | Post pile and sheet pile combination | |
KR101103909B1 (en) | A wale system for supporting earth retaining wall | |
KR101474338B1 (en) | Furlable earth retaining structure for provisional facilities and construction method thereof | |
KR20090101993A (en) | Soil guard structure and establishment method | |
KR101266112B1 (en) | Non-open cut excavation construction method for underground structure using wire saw apparatus | |
KR101287739B1 (en) | Sheet pile combined modular bridge abutment and construction method of the same | |
KR100903508B1 (en) | '?' Shape Waling Method Separated from the Basement Wall | |
KR200247053Y1 (en) | wale for construction method for defending earth using prestress | |
KR101221084B1 (en) | Temporary pile using bending restoring force and temporary structure construction method therewith | |
KR102497458B1 (en) | Cip Retaining Reinforcing Structure and Method Constructing the Same | |
KR20180112453A (en) | Soil Retaining Wall using PHC Pile and Construction Method | |
KR200399769Y1 (en) | Steel frame revetment using earth anchor | |
KR101744378B1 (en) | Method for Constructing Retaining Wall | |
KR101534058B1 (en) | Soil retaining wall for load support and constructing method thereof | |
KR101039341B1 (en) | Pile structure and construction method for foundation using the same | |
KR200463615Y1 (en) | Height control way guide beam | |
KR100969352B1 (en) | Geogrid fixing structure for retaining wall block | |
KR100479500B1 (en) | The slope tree-planting structure using socket type steel pipe, and his construction method | |
KR100401330B1 (en) | A method of construction for earth-protection walls of building | |
KR101557462B1 (en) | A freestanding temporary retaining and it's construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E601 | Decision to refuse application |