KR20090093692A - A bucket of a excavator for sand distribution works - Google Patents

A bucket of a excavator for sand distribution works

Info

Publication number
KR20090093692A
KR20090093692A KR1020080019374A KR20080019374A KR20090093692A KR 20090093692 A KR20090093692 A KR 20090093692A KR 1020080019374 A KR1020080019374 A KR 1020080019374A KR 20080019374 A KR20080019374 A KR 20080019374A KR 20090093692 A KR20090093692 A KR 20090093692A
Authority
KR
South Korea
Prior art keywords
sand
excavator
laying
bucket
laying hole
Prior art date
Application number
KR1020080019374A
Other languages
Korean (ko)
Inventor
박삼진
Original Assignee
박삼진
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박삼진 filed Critical 박삼진
Priority to KR1020080019374A priority Critical patent/KR20090093692A/en
Publication of KR20090093692A publication Critical patent/KR20090093692A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/40Dippers; Buckets ; Grab devices, e.g. manufacturing processes for buckets, form, geometry or material of buckets
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/42Drives for dippers, buckets, dipper-arms or bucket-arms
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/30Auxiliary apparatus, e.g. for thawing, cracking, blowing-up, or other preparatory treatment of the soil
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60YINDEXING SCHEME RELATING TO ASPECTS CROSS-CUTTING VEHICLE TECHNOLOGY
    • B60Y2200/00Type of vehicle
    • B60Y2200/40Special vehicles
    • B60Y2200/41Construction vehicles, e.g. graders, excavators
    • B60Y2200/412Excavators

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Shovels (AREA)

Abstract

A bucket of an excavator for sand installation is provided to carry out the sand installation in a short time using an excavator in a foundation work for installing electric wires. A bucket of an excavator for sand installation comprises a body(20) where a boom(10) is connected to one side and allows them to turn and a sand installation hole(22) is formed in the other side, a sand conveying screw(25) which is installed inside the body and is parallel to the top of sand installation hole in order to convey the sand put into the inside of the body to the sand installation hole, and a driving motor which is installed at the side of the body in order to rotate the sand conveying screw.

Description

모래 포설용 굴삭기의 버킷{A BUCKET OF A EXCAVATOR FOR SAND DISTRIBUTION WORKS}Sand Bucket Excavator Bucket {A BUCKET OF A EXCAVATOR FOR SAND DISTRIBUTION WORKS}

본 발명은 모래 포설용 굴삭기의 버킷에 관한 것으로, 더욱 상세하게는 전선관 포설을 위한 모래포설작업시 굴삭기에 의한 포설로 균일하고 수평하게 단시간내에 포설하도록 한 모래 포설용 굴삭기의 버킷에 관한 것이다.The present invention relates to a bucket of sand excavator, and more particularly to a bucket of sand excavator to be laid uniformly and horizontally in a short time by the installation of the excavator during sand laying for conduit installation.

일반적으로 지중구조물 및 지중에 전선관을 설치하는 경우에는 지면을 일정 깊이로 파헤친 후 석분과 모래를 포설하고, 포설된 모래의 상부에 전선관을 포설하게 된다.In general, in the case of installing the conduit in the underground structure and underground, the ground is dug to a certain depth and then the stone powder and sand is laid, and the conduit is laid on the upper part of the laid sand.

이와 같은 작업은 통상 굴삭기에 의한 지면의 굴착작업 후 작업자가 삽 등을 이용하여 굴삭기에 의해 파여진 홈에 석분과 모래를 손수 투입한 다음 전선관을 포설하고 있는 실정이며, 이에 따라 포설작업시 상당한 시간이 걸리게 될 뿐만 아니라 장시간에 걸친 전선관의 포설 후 파헤져 놓은 흙을 다시 메워야 함에 따라 굴삭기의 운용을 위한 시간이 길어져 굴삭기 임대비용 등의 작업비용을 높이는 문제점이 있었다.Such a work is a situation in which an operator places a conduit after inserting stone powder and sand into a groove dug by an excavator using a shovel after excavation of the ground by an excavator. In addition to this, there was a problem in that the time for the operation of the excavator was increased due to the refilling of the excavated soil after the installation of the conduit for a long time, thereby increasing the operating cost such as the excavator rental cost.

더욱이, 모든 작업이 수작업으로 이루어짐으로써 다수의 작업인원이 투입되어야 할 뿐만 아니라 삽 등의 포설작업을 위한 다수의 도구가 필요하며, 이에 따른 인건비 상승과 작업도구의 구입비용 등 작업비용을 증가시키는 요인이 되고 있으며, 이러한 요인을 제외하고도 작업에 따른 효율이 저하되는 문제점이 있다.Moreover, all the work is done by hand, which requires not only a large number of workers but also a large number of tools for laying work, such as shovels, which increases labor costs such as labor costs and the cost of purchasing work tools. And, except for these factors there is a problem that the efficiency is reduced according to the operation.

한편, 인건비 등의 절감을 위해 굴삭기로 지면의 굴착작업과 포설작업을 모두 행하고 있으나 이 경우, 모래 등의 포설작업시 일정 간격으로 군데군데 뭉쳐져 포설됨에 따라 가지런하게 수평한 포설이 어려우며, 또한 파헤쳐 놓은 홈의 외부로 모래 등이 뿌려짐에 따라 별도로 작업자가 빗자루 등으로 쓸어야 하는 이중작업을 하여야 하는 문제점이 있었다. On the other hand, in order to reduce labor costs, both ground excavation and laying work are being carried out with an excavator, but in this case, when laying sand, etc., they are piled up at regular intervals, making it difficult to lay horizontally and digging. As the sand is sprayed to the outside of the groove, there is a problem that a separate work that the worker has to sweep with a broom, etc. has to be done.

본 발명은 상기한 문제점을 해결하기 위하여 창안된 것으로, 본 발명의 목적은 전선관 포설을 위한 기초작업시 굴삭기를 이용하여 모래의 포설작업을 단시간내에 할 수 있으며, 특히 포설되는 모래가 뭉치지 않고 균일하게 수평으로 포설됨에 따라 별도의 펼침작업을 하지 않아도 되는 모래 포설용 굴삭기의 버킷을 제공함에 있다.The present invention has been made to solve the above problems, an object of the present invention can be laid in a short time by using an excavator during the foundation work for laying the conduit, in particular, the sand to be laid uniformly without agglomeration It is to provide a bucket of sand excavator to be laid horizontally does not require a separate unfolding work.

또한, 본 발명의 다른 목적은 굴삭기에 의한 작업으로 인건비를 최대한 절감시킬 수 있으며, 삽 등과 같은 도구의 구입비용을 절약할 수 있는 모래 포설용 굴삭기의 버킷을 제공하는 데 있다.In addition, another object of the present invention is to provide a bucket of sand excavator excavator that can reduce the labor cost as much as possible by working with an excavator, can save the purchase cost of tools such as shovels.

상기의 목적을 달성하기 위한 본 발명의 구성은, 굴삭기의 붐에 연결되어 전선관 포설을 위한 기초작업시 석분과 모래를 포설하는 굴삭기의 버킷에 있어서, 상기 버킷은, 상기 붐(10)에 일측이 회동되게 연결되고 타측 중앙부에 일정 폭으로 모래포설공(22)이 형성된 통체의 몸체(20)와, 상기 몸체(20)의 내부에 상기 모래포설공(22)의 상측으로 수평하게 설치되어 상기 몸체(20)의 내부로 투입된 모래를 상기 모래포설공(22)으로 이송시키는 모래이송스크류(25)와, 상기 모래이송스크류(25)를 회전시키도록 상기 몸체(20)의 측면에 설치되는 구동모터(30)로 이루어진 것을 특징으로 한다.The configuration of the present invention for achieving the above object is, in the bucket of the excavator is connected to the boom of the excavator to install the stone powder and sand during the foundation work for laying the conduit, the bucket is one side to the boom (10) The body 20 of the tubular body is formed to be connected to the rotation and the sand laying hole 22 in a predetermined width in the other central portion, and is installed horizontally above the sand laying hole 22 in the body 20 is the body A sand transfer screw 25 for transferring the sand introduced into the sand 20 to the sand laying hole 22 and a drive motor installed on the side of the body 20 to rotate the sand transfer screw 25. It characterized by consisting of (30).

여기서, 상기 모래이송스크류(25)의 외주면에 형성된 이송편(27)은 모래의 포설시 상기 모래포설공(22)의 방향으로 모래를 이송시키도록 상기 모래포설공(22)을 기준으로 양측이 서로 대향되게 형성되고, 상기 모래포설공(22)에는 포설되는 모래의 균일한 포설을 위해 일정 간격으로 포설조절편(23)이 구비되는 것이 바람직하다.Here, the conveying piece 27 formed on the outer circumferential surface of the sand conveying screw 25 is both sides relative to the sand laying hole 22 to transport sand in the direction of the sand laying hole 22 when sand is laid. Formed to face each other, the sand laying hole 22 is preferably provided with a laying control piece 23 at regular intervals for uniform laying of the sand to be laid.

이때, 상기 모래이송스크류(25)에는 상기 모래포설공(22)의 상측을 커버함과 더불어 상기 모래포설공(22)로 모래의 원활한 유입을 위해 회전날개판(29)이 설치되는 것이 바람직하다.In this case, it is preferable that the rotary blade plate 29 is installed in the sand conveying screw 25 to cover the upper side of the sand laying hole 22 and to smoothly introduce sand into the sand laying hole 22. .

한편, 상기 모래포설공(22)의 주연부에는 상기 회전날개판(29)의 회전시 부피가 큰 알맹이가 상기 모래포설공(22)과 상기 회전날개판(29)의 사이로 끼이지 않도록 고무재의 끼임방지편(24)이 구비되는 것이 바람직하다.On the other hand, in the periphery of the sand laying hole 22, the rubber material is sandwiched between the sand laying hole 22 and the rotary blade plate 29 so that the bulky kernel during the rotation of the rotary blade plate 29 is pinched. It is preferable that the prevention piece 24 is provided.

상기와 같은 본 발명에 따르면, 전선관 포설시 석분과 모래 포설을 위한 기초작업시 굴삭기를 이용하여 단시간내에 포설작업을 마무리 할 수 있으며, 특히 포설되는 석분이나 모래가 뭉치지 않고 균일하게 수평으로 포설됨에 따라 별도로 작업자가 손수 펼침작업을 하지 않아도 된다.According to the present invention as described above, when laying the conduit in the foundation work for laying the stone powder and sand can be completed in a short time by using an excavator, in particular, as the stone powder or sand to be installed is not uniformly laid horizontally There is no need for the worker to manually unfold it.

또한, 굴삭기에 의한 작업으로 인건비를 최대한 절감시킬 수 있으며, 삽 등과 같은 도구의 구입비용도 절약할 수 있게 된다.In addition, it is possible to reduce the labor cost as much as possible by working with an excavator, it is also possible to save the cost of purchasing tools such as shovels.

도 1은 본 발명에 의한 모래 포설용 굴삭기의 버킷을 보인 상태도,1 is a state diagram showing a bucket of sand excavator according to the present invention,

도 2는 본 발명에 의한 포설조절편이 구비된 상태에서의 버킷을 보인 상태도,Figure 2 is a state diagram showing the bucket in a state provided with the installation control piece according to the present invention,

도 3은 본 발명에 의한 모래의 포설상태를 보인 단면상태도,3 is a cross-sectional state view showing the installation state of the sand according to the present invention,

도 4는 본 발명에 의한 회전날개판이 구비된 버킷을 보인 상태도,Figure 4 is a state diagram showing a bucket provided with a rotary blade plate according to the present invention,

도 5는 본 발명에 의한 회전날개판의 설치상태를 보인 단면상태도.Figure 5 is a cross-sectional view showing an installation state of the rotary blade plate according to the present invention.

< 도면의 부요 부분에 대한 부호의 설명 ><Description of the code | symbol about the essential part of drawing>

10: 붐 15: 포설홈10: Boom 15: Laying Home

20: 몸체 22: 모래포설공20: body 22: sand sprayer

23: 포설조절편 24: 끼움방지편23: installation control piece 24: fitting prevention piece

25: 모래이송스크류25: sand feed screw

27: 이송편 29: 회전날개판27: feed piece 29: rotary blade plate

30: 구동모터30: drive motor

이하, 첨부된 도면을 참조하여 본 발명의 모래 포설용 굴삭기의 버킷을 상세히 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail the bucket of the sand laying excavator of the present invention.

도 1은 본 발명에 의한 모래 포설용 굴삭기의 버킷을 보인 상태도이고, 도 2는 본 발명에 의한 포설조절편이 구비된 상태에서의 버킷을 보인 상태도이며, 도 3은 본 발명에 의한 모래의 포설상태를 보인 단면상태도이고, 도 4는 본 발명에 의한 회전날개판이 구비된 버킷을 보인 상태도이며, 도 5는 본 발명에 의한 회전날개판의 설치상태를 보인 단면상태도이다.1 is a state diagram showing a bucket of sand excavator according to the present invention, Figure 2 is a state diagram showing a bucket in a state provided with the installation control piece according to the present invention, Figure 3 is a state of laying sand according to the present invention 4 is a cross-sectional state diagram showing a bucket with a rotary blade plate according to the present invention, and FIG. 5 is a cross-sectional state diagram showing an installation state of the rotary blade plate according to the present invention.

상기 도면에 도시된 바와 같이, 본 발명에 의한 모래 포설용 굴삭기의 버킷은 굴삭기의 붐(10)에 연결되어 전선관 포설을 위한 기초작업으로 석분과 모래의 포설작업시 사용되는 것으로, 상기 붐(10)에 일측이 회동되게 연결되고 타측 중앙부에 일정 폭으로 모래포설공(22)이 형성된 통체의 몸체(20)와, 상기 몸체(20)의 내부에 상기 모래포설공(22)의 상측으로 수평하게 설치되어 상기 몸체(20)의 내부로 투입된 모래를 상기 모래포설공(22)으로 이송시키는 모래이송스크류(25)와, 상기 모래이송스크류(25)를 회전시키도록 상기 몸체(20)의 측면에 설치되는 구동모터(30)로 이루어진다.As shown in the drawings, the bucket of the sand laying excavator according to the present invention is connected to the boom 10 of the excavator is used in the installation work of stone powder and sand as a basic work for laying the conduit, the boom 10 The body 20 of the cylindrical body with one side connected to the rotating side and the sand laying hole 22 is formed in a predetermined width in the center of the other side, and horizontally upwards of the sand laying hole 22 in the body 20. Is installed on the side of the body 20 to rotate the sand feed screw 25 and the sand feed screw 25 to transfer the sand introduced into the body 20 to the sand hole (22). It consists of a drive motor 30 is installed.

상기 몸체(20)는 통상의 굴삭기에 사용되는 버킷과 같이 일측이 개구된 통체로 형성되고, 지면과 간섭되는 면에 상기 모래포설공(22)이 형성된다.The body 20 is formed of a cylindrical body having one side open like a bucket used in a conventional excavator, and the sand laying hole 22 is formed on a surface that interferes with the ground.

그리고, 상기 모래이송스크류(25)는 상기 구동모터(30)에 벨트 또는 체인연결되거나 기어방식으로 결합되어 회전되고, 외주면에 상기 몸체(20)의 내부로 투입된 모래를 상기 모래포설공(22)으로 이송시키도록 이송편(22)이 형성되며, 상기 이송편(27)은 모래의 포설시 상기 모래포설공(22)의 방향으로 모래를 이송시키도록 상기 모래포설공(22)을 기준으로 양측이 서로 대향되게 형성되는 것이 바람직하다.In addition, the sand transfer screw 25 is rotated by the belt or chain or coupled to the drive motor 30 is coupled to the drive method, the sand is injected into the sand of the body 20 into the outer peripheral surface of the sand laying hole (22) The conveying piece 22 is formed to be conveyed to the side, and the conveying piece 27 has both sides with respect to the sand laying hole 22 to convey the sand in the direction of the sand laying hole 22 when sand is laid. It is preferable that these are formed to face each other.

따라서, 상기 몸체(20)의 내부로 투입된 모래는 상기 이송편(27)이 형성된 모래이송스크류(25)에 의해 상기 모래포설공(22)으로 이송되어 상기 모래포설공(22)을 통해 지면으로 포설되어 지고, 이 경우 굴삭기를 이동시키면서 포설함에 따라 균일하게 포설되어 지는 것이다.Therefore, the sand introduced into the body 20 is transferred to the sand laying hole 22 by the sand conveying screw 25 in which the conveying piece 27 is formed to the ground through the sand laying hole 22. In this case, the installation is carried out evenly while moving the excavator.

이때, 상기 모래포설공(22)에는 포설되는 모래의 균일한 포설을 위해 일정 간격으로 포설조절편(23)이 구비되어 일시에 많은 량의 모래가 포설되지 않도록 한다.At this time, the sand laying hole 22 is provided with a laying adjustment piece 23 at regular intervals for uniform laying of the sand to be laid so that a large amount of sand is not placed at one time.

한편, 상기 모래포설공(22)은 전선관의 포설을 위해 지면에 형성되는 포설홈(15)의 폭길이보다 작은 길이를 갖도록 하여 포설홈(15)의 외부로 모래가 포설되지 않게 하는 것이 바람직하다. On the other hand, it is preferable that the sand laying hole 22 has a length smaller than the width of the laying groove 15 formed on the ground for laying the conduit so that sand is not placed outside the laying groove 15. .

그리고, 도 4와 도 5와 같이 본 발명의 상기 모래이송스크류(25)에는 상기 모래포설공(22)의 상측을 커버함과 더불어 상기 모래포설공(22)로 모래의 원활한 유출을 위해 회전날개판(29)이 설치된다. 즉 상기 모래이송스크류(25)의 미작동시 상기 모래포설공(22)을 커버하여 모래의 유출을 차단시키도록 하고, 상기 모래이송스크류(25)의 작동시에는 상기 이송편(27)에 의해 이송된 모래를 빠짐없이 상기 모래포설공(22)으로 밀어넣어 외부로 내보내게 되는 것이다.4 and 5, the sand transfer screw 25 of the present invention covers the upper side of the sand laying hole 22 and rotates the blades for smooth outflow of sand into the sand laying hole 22. Plate 29 is installed. That is, when the sand transfer screw 25 is not in operation, the sand laying hole 22 is covered to block the outflow of sand, and when the sand transfer screw 25 is operated by the transfer piece 27. The transported sand is pushed into the sand laying hole 22 without leaving out.

그리고, 본 발명의 상기 모래포설공(22)의 주연부에는 부피가 큰 알맹이가 상기 모래포설공(22)과 상기 회전날개판(29)의 사이로 끼이면서 상기 회전날개판(29)의 회전을 제어함에 따라 부하가 증가되어 상기 구동모터(30)를 파손시키는 것을 방지하도록 고무재의 끼임방지편(24)이 구비된다.In addition, a bulky grain is sandwiched between the sand laying hole 22 and the rotary blade plate 29 at the periphery of the sand laying hole 22 of the present invention to control the rotation of the rotary blade plate 29. As the load is increased to prevent damage to the drive motor 30 is provided with a pinch preventing piece 24 of rubber material.

본 발명에서는 모래를 포설하는 것으로 기재하고 있으나 기초작업을 위한 석분이나 자갈 등을 포설할 수도 있음은 자명하다.In the present invention, it is described as laying sand, but it is obvious that stone or gravel may be laid for the foundation work.

상기와 같이 구성된 본 발명의 작용효과를 살펴보면, 먼저 굴삭기에 통상의 굴착용 버킷을 장착시킨 다음 전선관의 포설을 위해 지면을 굴착하여 포설홈(15)을 형성하고, 굴착용 버킷을 분리시킨다.Looking at the operation and effect of the present invention configured as described above, first equipped with a conventional excavating bucket in the excavator, and then excavating the ground for laying the conduit to form the installation groove 15, and separate the excavating bucket.

이 후, 본 발명의 버킷을 굴삭기의 붐(10)에 장착하고, 포설홈(15)의 상부로 옮긴 다음 몸체(20)의 내부에 모래를 투입시킨 후 구동모터(30)를 동작시켜 모래이송스크류(25)를 회전시킨다.Thereafter, the bucket of the present invention is mounted on the boom 10 of the excavator, moved to the upper portion of the installation groove 15, and sand is introduced into the body 20, and then the drive motor 30 is operated to transfer sand. Rotate the screw 25.

상기 모래이송스크류(25)의 회전으로 상기 몸체(20)의 양측으로 투입된 모래는 중앙부로 이송되면서 모래포설공(22)을 통해 포설홈(15)으로 포설되어 지게 된다. 이때 굴삭기 운전자는 상기 포설홈(15)을 따라 굴삭기를 이동시키면서 모래의 포설작업을 진행하면 된다.The sand introduced into both sides of the body 20 by the rotation of the sand transfer screw 25 is transported to the center portion is installed in the installation groove 15 through the sand laying hole 22. At this time, the excavator driver may proceed with the sand installation while moving the excavator along the installation groove (15).

이와 같이, 굴삭기를 이용하여 모래를 포설함에 따라 기존의 삽 등을 이용하여 다수의 인원이 투입되어 행해지는 포설작업에 비해 단시간내에 보다 많은 량의 작업을 이룰 수 있으며, 작업능률도 월등히 향상되어 지게 되는 것이다.In this way, as sand is laid using an excavator, more work can be achieved in a shorter time than the laying work performed by using a large number of personnel using an existing shovel and the like, and work efficiency is greatly improved. Will be.

Claims (4)

굴삭기의 붐에 연결되어 전선관 포설을 위한 기초작업시 석분과 모래를 포설하는 굴삭기의 버킷에 있어서,In the bucket of the excavator connected to the boom of the excavator and laying the powder and sand during the foundation work for laying the conduit, 상기 버킷은, 상기 붐(10)에 일측이 회동되게 연결되고 타측 중앙부에 일정 폭으로 모래포설공(22)이 형성된 통체의 몸체(20)와,The bucket, the body 20 of the tubular body 20 is connected to the boom 10 to be rotated and the sand laying hole 22 is formed in a predetermined width in the other center portion, 상기 몸체(20)의 내부에 상기 모래포설공(22)의 상측으로 수평하게 설치되어 상기 몸체(20)의 내부로 투입된 모래를 상기 모래포설공(22)으로 이송시키는 모래이송스크류(25)와,Sand transfer screw 25 is installed horizontally in the upper portion of the sand laying hole 22 in the body 20 to transfer the sand introduced into the body 20 to the sand laying hole 22 and , 상기 모래이송스크류(25)를 회전시키도록 상기 몸체(20)의 측면에 설치되는 구동모터(30)로 이루어진 것을 특징으로 하는 모래 포설용 굴삭기의 버킷.Bucket of the sand installation excavator, characterized in that consisting of a drive motor 30 is installed on the side of the body 20 to rotate the sand transfer screw (25). 제1항에 있어서,The method of claim 1, 상기 모래이송스크류(25)의 외주면에 형성된 이송편(27)은 모래의 포설시 상기 모래포설공(22)의 방향으로 모래를 이송시키도록 상기 모래포설공(22)을 기준으로 양측이 서로 대향되게 형성되고,Both sides of the transfer piece 27 formed on the outer circumferential surface of the sand transfer screw 25 face each other with respect to the sand laying hole 22 so as to transfer sand in the direction of the sand laying hole 22 when sand is laid. Formed, 상기 모래포설공(22)에는 포설되는 모래의 균일한 포설을 위해 일정 간격으로 포설조절편(23)이 구비되는 것을 특징으로 하는 모래 포설용 굴삭기의 버킷.The sand laying hole 22 is a bucket of sand excavator, characterized in that the installation control piece 23 is provided at regular intervals for uniform installation of the sand to be installed. 제1항 또는 제2항에 있어서,The method according to claim 1 or 2, 상기 모래이송스크류(25)에는 상기 모래포설공(22)의 상측을 커버함과 더불어 상기 모래포설공(22)로 모래의 원활한 유입을 위해 회전날개판(29)이 설치되는 것을 특징으로 하는 모래 포설용 굴삭기의 버킷.The sand transfer screw 25 covers the upper side of the sand laying hole 22, and the rotary blade plate 29 is installed for smooth inflow of sand into the sand laying hole 22. Bucket of laying excavator. 제3항에 있어서,The method of claim 3, 상기 모래포설공(22)의 주연부에는 상기 회전날개판(29)의 회전시 부피가 큰 알맹이가 상기 모래포설공(22)과 상기 회전날개판(29)의 사이로 끼이지 않도록 고무재의 끼임방지편(24)이 구비되는 것을 특징으로 하는 모래 포설용 굴삭기의 버킷.At the periphery of the sand laying hole 22, a rubber material prevents pinching of the bulk material so as not to be caught between the sand laying hole 22 and the rotary blade plate 29 when the rotary blade plate 29 is rotated. Bucket of sand excavator, it characterized in that the provided 24.
KR1020080019374A 2008-02-29 2008-02-29 A bucket of a excavator for sand distribution works KR20090093692A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080019374A KR20090093692A (en) 2008-02-29 2008-02-29 A bucket of a excavator for sand distribution works

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080019374A KR20090093692A (en) 2008-02-29 2008-02-29 A bucket of a excavator for sand distribution works

Publications (1)

Publication Number Publication Date
KR20090093692A true KR20090093692A (en) 2009-09-02

Family

ID=41302143

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080019374A KR20090093692A (en) 2008-02-29 2008-02-29 A bucket of a excavator for sand distribution works

Country Status (1)

Country Link
KR (1) KR20090093692A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120912A (en) * 2016-08-18 2016-11-16 徐工集团工程机械股份有限公司科技分公司 A kind of turning scraper bowl
CN108385652A (en) * 2018-04-23 2018-08-10 西安建筑科技大学 A kind of automation laying apparatus and method based on greening sand prevention sand-protecting barrier
CN114000558A (en) * 2021-11-03 2022-02-01 扬州市职业大学(扬州市广播电视大学) Black and odorous river silt cleaning device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120912A (en) * 2016-08-18 2016-11-16 徐工集团工程机械股份有限公司科技分公司 A kind of turning scraper bowl
CN108385652A (en) * 2018-04-23 2018-08-10 西安建筑科技大学 A kind of automation laying apparatus and method based on greening sand prevention sand-protecting barrier
CN108385652B (en) * 2018-04-23 2024-05-03 西安建筑科技大学 Automatic laying device and method based on greening sand-preventing sand barrier
CN114000558A (en) * 2021-11-03 2022-02-01 扬州市职业大学(扬州市广播电视大学) Black and odorous river silt cleaning device

Similar Documents

Publication Publication Date Title
CN107780446A (en) A kind of safe and efficient power shovel
CN105155605A (en) Amphibious shovel loader
KR20090093692A (en) A bucket of a excavator for sand distribution works
US5379534A (en) Bucket equipped with mixing device, excavation machine having the bucket, and soil improvement method using the excavation machine
CN101824984B (en) Loader of dredging bucket for roadways of mine
CN105019489B (en) Continuous shoveling formula excavator
CN204940393U (en) A kind of amphibious shovel loader
CN201679026U (en) Bucket loading machine used for mine roadway
US5491914A (en) Bucket equipped with mixing device, excavation machine having the bucket, and soil improvement method using the excavation machine
US7921581B2 (en) Excavation device
CN205742318U (en) A kind of milling digging machine of automatic material-absorbing
KR101976948B1 (en) Excavator with detachable extension arm
CN211972094U (en) Silt place normal position solidification equipment
CN111097793A (en) Soil turning and throwing device for in-situ remediation of surface-layer contaminated soil
US20170037596A1 (en) Excavator Bucket With an Internally Deployable Breaker
CN213071971U (en) Pipe laying and paying-off device for hydraulic engineering
CN207003522U (en) A kind of two-wheeled, which loosens the soil, excavates conveyer
CN207553191U (en) A kind of earth moving equipment in Deep Excavation
CN111424635A (en) In-situ solidification device for muddy field and solidification construction method
CN211621749U (en) Chain bucket type excavator
JP2000273896A (en) Bucket with cutter
JPH04254626A (en) Bucket having mixing device
CN110106931B (en) Working method of excavating device
CN109487845A (en) A kind of multifunctional excavator front end equipment
CN213807668U (en) Electricity drives portable tunnel excavation desilting industrial robot device

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
NORF Unpaid initial registration fee