KR20080065571A - Psc bridge pier assembled with precast concrete segments having steel duct and steel pipe, and constructing method thereof - Google Patents
Psc bridge pier assembled with precast concrete segments having steel duct and steel pipe, and constructing method thereof Download PDFInfo
- Publication number
- KR20080065571A KR20080065571A KR1020080059383A KR20080059383A KR20080065571A KR 20080065571 A KR20080065571 A KR 20080065571A KR 1020080059383 A KR1020080059383 A KR 1020080059383A KR 20080059383 A KR20080059383 A KR 20080059383A KR 20080065571 A KR20080065571 A KR 20080065571A
- Authority
- KR
- South Korea
- Prior art keywords
- steel
- segment
- psc
- precast concrete
- foundation
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
- E01D2101/285—Composite prestressed concrete-metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
본 발명은 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각 및 이의 시공 방법에 관한 것으로서, 상세하게는 교각 기초 및 세그먼트에 부분적으로 짧은 길이의 강재 덕트를 이용한 전단 연결재를 설치하고, 세그먼트 및 코핑부에 부분적으로 짧은 길이의 강재 덕트를 이용한 연결 소켓을 설치하며, 강선의 자립을 위해 강관을 쉬스관과 강선 사이에 삽입하도록 하는 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각 및 이의 시공 방법에 관한 것이다.The present invention relates to a PSC pier and a construction method thereof assembled from a precast concrete segment having a steel duct and a steel pipe, and in particular, a shear connecting member using a steel duct of a short length is installed in a pier foundation and a segment. Connection sockets using steel ducts with short lengths are installed in the segments and copings, and assembled into precast concrete segments with steel ducts and steel pipes for inserting steel pipes between sheath pipes and steel wires for the independence of steel wires. It relates to a PSC pier and its construction method.
일반적으로, 현장에서의 콘크리트 타설로 인한 교량의 시공은 공사기간이 늘어나고, 환경문제 및 이로 인한 민원문제의 발생으로 인하여 근래에는 이와 같은 시공방법이 줄어들고, 대신 미리 성형된 세그먼트를 현장에서 조립식으로 시공하는 급속 시공 방법이 많이 이용되고 있다.In general, the construction of bridges due to concrete pouring on site increases the construction period, and due to the occurrence of environmental problems and civil complaints, such a construction method is reduced in recent years, and instead, preformed segments are prefabricated on site. The rapid construction method to use is used a lot.
상기한 급속 시공 방법은 교량의 전체적인 공사 기간을 단축할 수 있을 뿐 아니라 환경문제 및 민원 문제를 최소화할 수 있는 방안이 되고 있으며, 이러한 급속시공 방법은 대형 장비를 이용하여야 함에 따라 건설환경을 기계화하는데 일조하고 있는 것이 사실이다.The rapid construction method not only shortens the overall construction period of the bridge but also minimizes environmental problems and civil complaints. The rapid construction method requires the use of large equipment to mechanize the construction environment. It is true that it helps.
이러한 세그먼트를 조립함에 있어서 세그먼트 사이에 존재하게 되는 불연속면에서의 전단연결을 위해서는 전단키를 설치하여 기계적인 맞물림에 의한 전단저항력이 발휘되도록 하여야 한다. 프리캐스트 콘트리트 세그먼트의 경우 일반적으로 이러한 전단키는 세그먼트를 제작할 때 세그먼트의 일측에 돌출부 형태로 만들게 된다. 그런데 이와 같이 세그먼트의 일측에 돌출된 형태의 전단키를 제작하는 경우, 거푸집을 탈형할 때, 사소한 부주의로 인하여 전단키가 부러지는 현상이 쉽게 발생하게 된다. 특히 전단키의 크기가 작고 그 돌출 길이가 클수록 세그먼트 제작과정에서 전단키의 부러짐 현상이 발생하기 쉽다. 그 뿐만 아니라 거푸집의 전단키 형성 부분 내에 콘크리트가 제대로 채워지지 않아 거푸집을 탈형하였을 때 세그먼트에 전단키가 원하는 형태로 형성되어 있지 아니한 경우가 종종 발생한다.In assembling these segments, the shear key is to be provided for the shear connection in the discontinuous surface existing between the segments so that the shear resistance by mechanical engagement is exerted. In the case of precast concrete segments, these shear keys are generally formed as protrusions on one side of the segment when fabricating the segment. However, in the case of manufacturing a shear key protruding to one side of the segment as described above, when demolding the formwork, the shear key is easily broken due to minor carelessness. In particular, the smaller the shear key size and the larger the protruding length, the more likely the breakage of the shear key is to occur during the segment manufacturing process. Not only that, when concrete is not properly filled in the shear key forming part of the formwork, when the mold is demolded, the shear key is often not formed in the desired shape.
한편, 이웃하는 세그먼트에 연속적으로 긴장재를 배치함에 있어서, 세그먼트 간의 불연속면을 통해서 누수가 발생할 가능성이 있다. 세그먼트간의 불연속면 즉, 세그먼트의 접합면에서 발생하는 긴장재 설치공에서의 누수는 긴장재의 부식을 유발하게 되고 이는 긴장재의 손상을 가져오게 되어 구조물의 붕괴 등과 같은 구조물 전체에 심각한 문제를 유발할 수 있게 된다. 따라서 세그먼트를 연속적으로 조립함에 있어서는 세그먼트에 연속적으로 배치되는 긴장재의 부식을 방지할 수 있도록 하기 위한 별도의 특별 조치가 필요하다.On the other hand, in arranging tension members continuously in neighboring segments, there is a possibility that water leakage occurs through discontinuous surfaces between the segments. Leakage in the tension member installation hole that occurs at the discontinuous surface between the segments, that is, the joint surface of the segment causes corrosion of the tension member, which may cause damage of the tension member and cause serious problems for the entire structure such as collapse of the structure. Therefore, in order to continuously assemble the segment, special special measures are required to prevent corrosion of the tension member disposed continuously in the segment.
이러한 문제를 해결하기 위하여 본 출원인에 의해 특허 등록 10-0738999호(강재 덕트를 이용한 조립구조를 가지는 프리캐스트 콘트리트 세그먼트 및 그 연결 조립구조)가 개발되었다.In order to solve this problem, the applicant has developed a patent registration No. 10-0738999 (precast concrete segment having an assembly structure using a steel duct and its connection assembly structure).
도 1에 도시된 바와 같이 상기 강재 덕트를 이용한 조립구조를 가지는 프리캐스트 콘크리트 세그먼트(10)(이하, "세그먼트"라고 약칭한다)의 내부에는 세그먼트(10)의 조립 방향으로 전단연결을 위한 강재 덕트가 관통된 상태로 매립되어 있다. 상기 강재 덕트는 원통형 강선 지지용 강관으로 이루어지며 세그먼트(10)에 긴장력을 도입하게 될 긴장재가 상기 강재 덕트(20)의 내부를 관통하여 배치된다.As shown in FIG. 1, a steel duct for shear connection in a prefabricated concrete segment 10 (hereinafter, abbreviated as “segment”) having an assembly structure using the steel duct in the assembling direction of the
도면에 도시된 것처럼, 상기 강재 덕트(20)는 그 하단부는 상기 세그먼트(10)의 하면에 맞추어 위치하게 되어 외부로 돌출되지 아니하지만, 상기 강재 덕트(20)의 상단부는 상기 세그먼트(10)의 상면 밖으로 돌출되어 위치하게 된다. 상기 외부로 돌출된 강재 덕트(20)의 상단부는 후술하는 것처럼, 이웃하는 세그먼트(10)끼리 조립할 때, 이웃 세그먼트(10)의 하면 즉, 이웃 세그먼트(10) 내에 매립 설치된 강재 덕트(20)의 하단부에 삽입된다. 이러한 서로 이웃하는 세그먼트(10)들 사이에서 상기 강재 덕트(20)의 용이한 삽입 결합을 위하여 상기 강재 덕트(20)의 하단부는 그 직경이 확대된 확관부(21)로 이루어지고, 또한 이러한 확관부(21)의 형성에 더하여 상기 강재 덕트(20)의 상단부는 점점 그 직경이 줄어들도록 테이퍼진 축관부(23)로 형성된다. As shown in the figure, the lower end of the
그러나, 강재 덕트의 일단에 축관부를 형성하고, 타단에 확관부를 형성하기 때문에 세그먼트의 길이가 길어지는 경우 이와 함께 강재 덕트의 길이도 길어져 공 사비 상승을 초래하는 문제점이 있다.However, since the shaft portion is formed at one end of the steel duct, and the expansion tube is formed at the other end, when the length of the segment is longer, the length of the steel duct is also increased, resulting in an increase in the cost of air.
또한, 교각 총길이와 동일한 강선이 삽입된 쉬스관을 교각 기초에 설치후 세그먼트를 적층시 강선에서 휨이 발생하고, 이로 인해 세그먼트의 적층이 어려운 다른 문제점이 있다.In addition, when the sheath pipe with the same steel wire length is inserted into the piling base, bending occurs in the steel wire when the segments are stacked, which causes another problem that is difficult to stack the segments.
또, 교각 구체에 사용되는 세그먼트를 교각 기초와 연결시키는 경우 교각 기초에 별도로 세그먼트와 연결되는 전단부가 형성되지 않기 때문에 세그먼트와 교각 기초와의 연결이 용이하지 않고, 이로 인해 접합부의 전단 파괴 우려의 소지를 안고 있는 문제점이 있다.In addition, when the segment used in the pier sphere is connected to the pier foundation, since the shear section is not formed on the pier foundation separately, the connection between the segment and the pier foundation is not easy, which may cause shear failure of the joint. There is a problem with.
본 발명은 상기와 같은 문제점을 해결하기 위한 것으로, 교각 기초 및 세그먼트에 부분적으로 짧은 길이의 강재 덕트를 이용한 전단 연결재를 설치하고, 세그먼트 및 코핑부에 부분적으로 짧은 길이의 강재 덕트를 이용한 연결 소켓을 설치함으로써 공사비 상승을 미연에 방지하고, 세그먼트와 교각 기초와의 연결을 용이하도록 하며, 접합부의 전단 파괴를 미연에 방지하도록 하는 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각 및 이의 시공 방법을 제공하는데 그 목적이 있다.The present invention is to solve the above problems, and to install a connecting connector using a steel duct of a short length part in the pier foundation and the segment, the connection socket using a steel duct of a short length part in the segment and the coping part PSC piers assembled from precast concrete segments with steel ducts and steel pipes that prevent cost increases, facilitate connection between segments and piers, and prevent shear failure of joints. The purpose is to provide a construction method.
또한, 본 발명은 강선과 쉬스관 사이에 강선의 자립을 위한 강선 지지용 강관을 삽입함으로써 세그먼트 적층시에 강선 지지용 강관에 의해 강선이 직립하도록 하여 시공성을 향상시키도록 하는 강재 덕트 및 강관을 구비하는 프리캐스트 콘트 리트 세그먼트로 조립된 PSC 교각 및 이의 시공 방법을 제공하는데 다른 목적이 있다.In addition, the present invention is provided with a steel duct and a steel pipe to improve the workability by allowing the steel wire to stand up by the steel wire support steel pipe at the time of segment stacking by inserting the steel wire support steel pipe for the independence of the steel wire between the steel wire and the sheath pipe. Another object is to provide a PSC piers and a construction method thereof assembled from precast concrete segments.
또, 본 발명은 교각 기초 및 세그먼트의 모서리를 모따기하고, 이에 실링재를 부착함으로써 세그먼트 사이를 방수함과 동시에 실링재에 색상을 부가하여 심미감을 줄 수 있도록 하는 데 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각 및 이의 시공 방법을 제공하는 데 또 다른 목적이 있다.In addition, the present invention is to chamfer the corners of the pier foundation and the segment, and by attaching a sealing material to the waterproofing between the segments and at the same time to add a color to the sealing material to give the aesthetic, precast concrete having a steel duct and steel pipe Another object is to provide a PSC piers assembled into segments and construction methods thereof.
상기와 같은 목적을 달성하기 위한 본 발명의 특징은,Features of the present invention for achieving the above object,
PSC 교각 시공 방법에 있어서, 복수의 기초용 쉬스관과, 교각 길이만큼 연장 형성되어 상기 기초용 쉬스관에 삽입되는 강선과, 상기 강선이 관통되며, 전단 연결을 위한 복수의 전단 연결재가 상면으로 돌출 형성되도록 교각 기초를 시공하는 교각 기초 시공 공정과; 상기 교각 기초에 삽입 설치된 상기 기초용 쉬스관과 강선 사이에 상기 강선과 동일 길이를 가지는 강선 지지용 강관을 삽입하는 강선 지지용 강관 삽입 공정과; 상면에 복수의 전단 연결재와, 이와 대응되는 저면에 복수의 연결 소켓을 구비하도록 기제작된 프리캐스트 콘크리트 세그먼트의 각각의 연결 소켓을 상기 교각 기초의 상면에 구비된 각각의 전단 연결재와 1:1 상호 결합시켜 상기 세그먼트를 상기 교각 기초의 상면에 적층하는 제 1적층 공정과; 상기 세그먼트의 각각의 전단 연결재에 이웃하는 세그먼트의 각각의 연결 소켓을 1:1 상호 결합시켜 세그먼트를 다단으로 적층하는 제 2적층 공정과; 최상단의 세그먼트의 상면에 코핑부를 형성하는 코핑부 형성 공정; 및 상기 강선 지지용 강관을 제거한 후 상기 강 선을 긴장시켜 정착시키는 정착 공정으로 이루어지는 것을 특징으로 한다.In the PSC bridge construction method, a plurality of foundation sheath pipe, a steel wire extending by the length of the pier is inserted into the foundation sheath pipe, and the steel wire is penetrated, a plurality of shear connecting members for the shear connection protrudes to the upper surface A pier foundation construction step of constructing a pier foundation to be formed; A steel wire supporting steel pipe insertion step of inserting a steel wire supporting steel pipe having the same length as the steel wire between the foundation sheath pipe and the steel wire inserted into the piling foundation; Each of the connecting sockets of the precast concrete segment prefabricated to have a plurality of shear connecting members on the upper surface and a plurality of connecting sockets on the bottom thereof is 1: 1 interconnected with each of the shear connecting members provided on the upper surface of the pier foundation. A first lamination step of joining and laminating the segment on the upper surface of the pier foundation; A second lamination process of laminating segments in multiple stages by mutually coupling each connecting socket of a segment neighboring each shear connecting member of the segment to each other; A coping portion forming step of forming a coping portion on an upper surface of the uppermost segment; And a fixing step of tensioning and fixing the steel wire after removing the steel wire supporting steel pipe.
여기에서, 상기 교각 기초는 상면에 세그먼트용 요홈이 형성되고, 상기 요홈에 수평 유지 및 무수축 몰탈 충진을 위한 고무 패드가 더 삽입 설치된다.Here, the pier base is formed with a segment groove on the upper surface, the rubber pad for horizontal maintenance and non-shrink mortar filling is further inserted into the groove.
여기에서 또한, 상기 요홈은 무수축 몰탈의 부착이 용이하도록 칩핑(Chipping)된다.Here, the groove is also chipped to facilitate attachment of the non-shrink mortar.
여기에서 또, 상기 세그먼트는 상기 강선 및 강선 지지용 강관이 관통되도록 상기 기초용 쉬스관과 1:1 대응되고, 상기 전단 연결재의 하단에서 및 연결 소켓의 상단까지 연장되는 세그먼트용 쉬스관을 더 구비한다.Here, the segment is further provided with a segment sheath tube for a one-to-one correspondence with the base sheath tube so that the steel wire and the steel support steel pipe penetrates, and extends from the lower end of the shear connecting member to the upper end of the connecting socket. do.
여기에서 또, 상기 세그먼트는 최상단의 세그먼트의 저면 모서리와, 최하단의 세그먼트와 최상단의 세그먼트에 이웃하는 세그먼트의 상하면 모서리에 각각 모따기부가 형성되고, 상기 모따기부에 실링재가 결합된다.Here, the segment is formed with a chamfer at the bottom edge of the uppermost segment, and the upper and lower edges of the segment adjacent to the lowermost segment and the uppermost segment, and the sealing material is bonded to the chamfer.
여기에서 또, 상기 세그먼트는 상기 전단 연결재의 외측면에서 일정 거리 이격되어 링 형태의 실링홈이 형성되고, 상기 실링홈에 실링용 고무 패드가 설치된다.Here, the segment is spaced apart from the outer surface of the shear connector by a predetermined distance to form a sealing groove in the form of a ring, the sealing rubber pad is provided in the sealing groove.
여기에서 또, 상기 실링용 고무 패드는 상면에 상기 연결 소켓의 저면이 면접된다.Here, the bottom surface of the connection socket is interviewed on the upper surface of the sealing rubber pad.
여기에서 또, 상기 강선 지지용 강관은 상기 교각 기초에서 강관 지지용 철근에 의해 고정되고, 상기 세그먼트의 적층시 제거된다.Here, the steel wire support steel pipe is fixed by the steel pipe support reinforcement at the pier foundation, and is removed during the stacking of the segments.
여기에서 또, 상기 코핑부는 최상단의 세그먼트 상면에서 현장 타설되거나 또는 프리캐스트로 기제작되어 최상단의 세그먼트의 상면에 적층된다.Herein, the coping portion is cast in situ on the uppermost segment upper surface or precast and laminated on the uppermost segment.
여기에서 또, 상기 코핑부는 상기 세그먼트의 전단 연결재와 1:1 대응되는 위치인 저면에 연결 소켓을 삽입하여 형성된다.Here, the coping portion is formed by inserting a connection socket on the bottom surface of the corresponding position 1: 1 with the shear connector of the segment.
여기에서 또, 상기 코핑부는 상기 강선 및 강선 지지용 강관이 관통되도록 상기 세그먼트용 쉬스관과 1:1 대응되고, 상기 전단 연결재의 하단에서 및 연결 소켓의 상단까지 연장되는 코핑용 쉬스관을 더 구비한다.Here, the coping portion is further provided with a coping sheath pipe that corresponds 1: 1 with the sheath pipe for the segment so that the steel wire and the steel wire for supporting the steel line passes, and extends from the lower end of the shear connector and to the upper end of the connection socket. do.
여기에서 또, 상기 전단 연결재는 상하면이 개방된 원통형 또는 상하면이 개방되되 상단이 좁고 하단으로 갈수록 넓어지는 테이퍼형으로 형성된다.Here, the shear connection member is formed in a cylindrical shape having an upper and lower surfaces opened or a tapered shape in which the upper and lower surfaces are opened but the upper end is narrower and wider toward the lower end.
여기에서 또, 상기 연결 소켓은 상면이 폐쇄되고, 하면이 개방된 원통형으로 형성되되, 상면 중앙부에 상기 기초용 쉬스관 또는 세그먼트용 쉬스관이 관통되는 관통홀을 구비한다.Here, the connection socket is formed in a cylindrical shape of the upper surface is closed, the lower surface is open, the upper surface has a through hole through which the base sheath pipe or the segment sheath pipe through.
여기에서 또, 상기 전단 연결재와, 연결 소켓은 상호 결합시 갭(Gap)을 유지하고, 갭 및 전단 연결재 및 연결 소켓 내부에 무수축 몰탈이 충진된다.Here, the shear connector and the connection socket maintain a gap when mutually coupled, and the non-shrink mortar is filled in the gap and the shear connector and the connection socket.
여기에서 또, 상기 제 2적층 공정은 상기 세그먼트의 상면에 접착제를 도포한 후 이웃하는 세그먼트를 적층한다.Here, in the second lamination step, the adhesive is applied to the upper surface of the segment, and then the neighboring segments are laminated.
본 발명의 다른 특징은,Another feature of the invention,
상기의 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각의 시공 방법에 의해 시공된 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각을 특징으로 한다.It is characterized in that the PSC pier assembled from the precast concrete segment having the steel duct and the steel pipe constructed by the construction method of the PSC pier assembled from the precast concrete segment provided with the steel duct and the steel pipe.
상기와 같이 구성되는 본 발명인 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각 및 이의 시공 방법에 따르면, 교각 기초 및 세그먼트에 부분적으로 짧은 길이의 강재 덕트를 이용한 전단 연결재를 설치함으로써 공사비 상승을 미연에 방지하고, 세그먼트와 교각 기초와의 연결을 용이하도록 하며, 접합부의 전단 파괴를 미연에 방지할 수 있다.According to the PSC pier and the construction method thereof assembled from the precast concrete segment having the steel duct and the steel pipe of the present invention configured as described above, the construction cost by installing a shear connection material using a steel duct of short length in the pier foundation and segment The rise can be prevented in advance, the connection between the segment and the pier foundation can be facilitated, and the shear failure of the joint can be prevented.
또한, 본 발명에 따르면 강선과 쉬스관 사이에 강선의 자립을 위한 강선 지지용 강관을 삽입함으로써 세그먼트 적층시에 강선 지지용 강관에 의해 강선이 직립하도록 하여 시공성을 향상시켜 시공 기간을 단축시킬 수 있다.In addition, according to the present invention by inserting a steel support steel pipe for the independence of the steel wire between the steel wire and the sheath pipe to allow the steel wire to be upright by the steel wire support steel pipe at the time of stacking the segment to improve the workability to shorten the construction period. .
또, 본 발명에 따르면 교각 기초 및 세그먼트의 모서리를 모따기하고, 이에 실링재를 부착함으로써 세그먼트 사이를 방수함과 동시에 실링재에 색상을 부가하여 심미감을 줄 수 있다.In addition, according to the present invention, by chamfering the corners of the pier foundation and the segment, and attaching a sealing material thereto, it is possible to provide aesthetics by waterproofing the segments and adding color to the sealing material.
이하, 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각의 구성을 첨부된 도면을 참조하여 상세하게 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings the configuration of the PSC piers assembled with precast concrete segments having a steel duct and a steel pipe according to the present invention will be described in detail.
하기에서 본 발명을 설명함에 있어, 관련된 공지 기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략할 것이다. 그리고 후술되는 용어들은 본 발명에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례 등에 따라 달라질 수 있다. 그러므로 그 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것이다.In the following description of the present invention, if it is determined that a detailed description of a related known function or configuration may unnecessarily obscure the subject matter of the present invention, the detailed description thereof will be omitted. Terms to be described later are terms defined in consideration of functions in the present invention, and may be changed according to intentions or customs of users or operators. Therefore, the definition should be made based on the contents throughout the specification.
도 2는 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 교각 기초의 구성을 나타낸 사시도이고, 도 3은 도 2의 A-A 단면도이며, 도 4는 도 2의 평면도이고, 도 5는 본 발명에 따른 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 세그먼트의 구성을 나타낸 사시도이고, 도 6은 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 세그먼트의 구성을 나타낸 저면 사시도이며, 도 7은 도 6의 B-B 단면도이고, 도 8은 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 코핑부의 구성을 나타낸 측단면도이며, 도 9a 및 도 9b는 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 전단 연결재의 구성을 나타낸 사시도이고, 도 10은 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 연결 소켓의 구성을 나타낸 사시도이며, 도 11은 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각을 나타낸 단면도이다.Figure 2 is a perspective view showing the configuration of the pier foundation of the PSC pier assembled with precast concrete segment having a steel duct and steel pipe according to the present invention, Figure 3 is a cross-sectional view of Figure 2 AA, Figure 4 is a plan view of Figure 2 5 is a perspective view showing the configuration of the segment of the PSC pier assembled with precast concrete segments having the steel duct and steel pipe according to the present invention, Figure 6 is a steel duct and steel pipe according to the present invention Fig. 7 is a sectional view taken along the line BB of Fig. 6, and Fig. 8 is a precast concrete segment having a steel duct and a steel pipe according to the present invention. Side cross-sectional view showing the configuration of the coping portion of the assembled PSC bridge piers, Figures 9a and
도 2 내지 도 11에 도시된 바와 같이 교각 기초(110)는 현장에서 타설되는 데, 상단부에 전단 연결을 위한 복수의 전단 연결재(203)가 삽입되어 전단 연결재(203)가 상면으로 돌출 형성된다.As shown in FIGS. 2 to 11, the
그리고, 교각 기초(110)는 복수의 기초용 쉬스관(111)과, 교각 길이만큼 연장 형성되어 기초용 쉬스관(111)에 삽입되는 강선(201)을 구비하며, 전단 연결재(203)의 내외측으로 상면에 세그먼트용 요홈(113)이 형성되는 데, 요홈(113)은 그 면이 무수축 몰탈의 부착이 용이하도록 칩핑(Chipping)되고, 요홈(113)에 수평 유지 및 무수축 몰탈 충진의 누수 방지를 위한 고무 패드(115)가 더 삽입 설치된다. 이때, 기초용 쉬스관(111)의 일끝단에는 강선(201)을 정착시키기 위한 정착구(202)가 연결 설치된다.The
또한, 교각 기초(110)의 상면 모서리는 다짐 장비 등에 의한 파손을 차단하기 위하여 모따기부(117)가 형성되는 것이 바람직하다.In addition, the upper edge of the
한편, 교각 기초(110)는 양생이 완료되면 기초용 쉬스관(111)과 강선(201) 사이에 강선(201)과 동일 길이를 가지는 강선 지지용 강관(207)을 삽입하고, 강선 지지용 강관(207)을 지지용 철근(119)에 의해 고정시킨다.On the other hand, when the
도 5 내지 도 7에 도시된 바와 같이 세그먼트(120)는 직육면체 또는 원통형으로 충실(充實) 또는 중공(中空)으로 형성되어 상면에 복수의 전단 연결재(203)와, 이와 대응되는 저면에 복수의 연결 소켓(205)을 구비한다.As shown in FIGS. 5 to 7, the
그리고, 세그먼트(120)는 강선(201) 및 강선 지지용 강관(207)이 관통되도록 기초용 쉬스관(111)과 1:1 대응되고, 전단 연결재(203)의 하단에서 및 연결 소켓(205)의 상단까지 연장되는 세그먼트용 쉬스관(121)을 더 구비한다.In addition, the
또한, 세그먼트(120)는 모서리에 모따기부(123)가 형성되고, 모따기부(123)에 실링재(125)가 결합되고, 전단 연결재(203)의 외측면에서 일정 거리 이격되어 링 형태의 실링홈(127)이 형성되고, 실링홈(127)에 실링용 고무 패드(129)가 설치되는 데, 실링용 고무 패드(129)는 상면에 연결 소켓(205)의 저면이 면접된다. 이때, 실링재(125)를 대신하여 몰탈이 타설될 수도 있다.In addition, the
도 8 및 도 11에 도시된 바와 같이 코핑부(130)는 최상단의 세그먼트 상면에서 현장 타설되거나 또는 프리캐스트로 기제작되어 최상단의 세그먼트의 상면에 적층된다.As illustrated in FIGS. 8 and 11, the coping
그리고, 코핑부(130)는 세그먼트(120)의 전단 연결재(203)와 1:1 대응되는 위치인 저면에 연결 소켓(205)을 삽입하여 형성되고, 강선(201) 및 강선 지지용 강관(207)이 관통되도록 세그먼트용 쉬스관(121)과 1:1 대응되고, 전단 연결재(203)의 하단에서 및 연결 소켓(205)의 상단까지 연장되는 코핑용 쉬스관(131)을 구비한다.In addition, the coping
한편, 본 발명의 교각 기초(110) 및 세그먼트(120)에 형성된 전단 연결재(203)는 도 9a에 도시된 바와 같이 스틸 재질로 상하면이 개방된 원통형으로 형성된다. 여기에서, 전단 연결재(203)는 도 9b에 도시된 바와 같이 상하면이 개방되되 상단이 좁고 하단으로 갈수록 넓어지는 테이퍼형으로 형성될 수도 있다.Meanwhile, the
그리고, 세그먼트(120) 및 코핑부(130)에 형성된 연결 소켓(205)은 도 10에 도시된 바와 같이 상면이 폐쇄되고, 하면이 개방된 원통형으로 형성되되, 상면 중앙부에 기초용 쉬스관(111) 또는 세그먼트용 쉬스관(121)이 관통되는 관통홀(206)을 구비한다.In addition, the connecting
한편, 전단 연결재(203)와, 연결 소켓(205)은 상호 결합시 갭(G)을 유지하고, 갭(G) 및 전단 연결재(203) 및 연결 소켓(205)내부에 무수축 몰탈이 충진된다.Meanwhile, the
또한, 기초용 쉬스관(111)과 세그먼트용 쉬스관(121) 및 코핑용 쉬스관(131) 내부에는 무수축 몰탈이 충진되어 내부에 위치한 강선(201)의 긴장력을 유지시킨 다.In addition, the
이하, 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각의 시공 방법을 첨부된 도면을 참조하여 상세하게 설명하면 다음과 같다.Hereinafter, a construction method of a PSC piers assembled with precast concrete segments having steel ducts and steel pipes according to the present invention will be described in detail with reference to the accompanying drawings.
도 12는 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각의 시공 방법을 간략화시킨 공정도이고, 도 13a 내지 도 13g는 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각의 시공 방법을 설명하기 위한 공정도이다.12 is a simplified process diagram of a construction method of a PSC pier assembled from precast concrete segments having steel ducts and steel pipes according to the present invention, and FIGS. 13A to 13G are free having steel ducts and steel pipes according to the present invention. It is a process chart for demonstrating the construction method of the PSC piers assembled by the cast concrete segment.
먼저, 도 13a에 도시된 바와 같이 복수의 기초용 쉬스관(111)과, 교각 길이만큼 연장 형성되어 기초용 쉬스관(111)에 삽입되는 강선(201)과, 강선(201)이 관통되며, 전단 연결을 위한 복수의 전단 연결재(203)가 상면으로 돌출 형성되도록 교각 기초(110)를 지표면에 시공한다(S110). 이때, 교각 기초(110)는 다짐 장비에 의해 지표면에서 다짐 공정을 수행한다.First, as shown in FIG. 13A, a plurality of
그리고, 도 13b에 도시된 바와 같이 교각 기초(110)에 삽입 설치된 기초용 쉬스관(111)과 강선(201) 사이에 강선(201)과 동일 길이를 가지는 강선 지지용 강관(207)을 삽입한다(S120). 이때, 강선 지지용 강관(207)을 지지용 철근(119)에 의해 고정시키는 것이 바람직하다.And, as shown in Figure 13b is inserted between the
그런 다음, 도 13c에 도시된 바와 같이 기제작된 세그먼트(120)를 교각 기초(110)의 상면에 적층하는 데, 교각 기초(110)의 세그먼트용 요홈(113)에 수평 유지를 위해 고무 패드(115)를 올려놓은 상태에서 세그먼트(120)의 연결 소켓(205)을 교각 기초(110)의 전단 연결재(203)와 1:1 상호 결합시킨다(S130). 이때, 강선(201) 및 강선 지지용 강관(207)은 세그먼트(120)의 세그먼트용 쉬스관(121)을 통해 세그먼트(120)를 관통한다. 또한, 고무 패드(115) 사이의 공간을 통해 세그먼트용 요홈(113)에 무수축 몰탈 충진한다.Then, as shown in FIG. 13C, the
도 13d에 도시된 바와 같이 이러한 상태에서 다시 설계 높이까지 기제작된 세그먼트(120)를 교각 기초(110)의 상면에 적층된 세그먼트(120)의 상면에 순차적으로 적층하는 데, 연결 소켓(205)과 전단 연결재(203)를 1:1 상호 결합시킨다(S140). 이때, 지지용 철근(119)을 강선 지지용 강관(207)에서 제거하여 세그먼트(120)를 적층시킨다. 또한, 세그먼트(120)의 상면과 이웃하는 세그먼트(120)의 저면에는 에폭시가 도포되어 이들을 상호 결합시킨다.In this state, as shown in FIG. 13D, the
그리고, 도 13e에 도시된 바와 같이 최상단의 세그먼트 상면에 코핑부(130)를 현장 타설하거나 또는 프리캐스트로 기제작된 것을 최상단의 세그먼트의 상면에 적층하는 데, 전단 연결재(203)와 연결 소켓(205)을 상호 결합시킨다(S150). 이때, 코핑용 쉬스관(131)을 통해 강선(201) 및 강선 지지용 강관(207)이 배출된다.And, as shown in FIG. 13E, the coping
그런 다음, 도 13f에 도시된 바와 같이 강선 지지용 강관(207)을 빼낸 다음, 강선(201)을 긴장시켜 정착시킨다(S160). 강선(201)의 정착은 통상의 방법으로 그 상단에 정착구(202)를 결합시켜 긴장시키고, 교각 기초(110)의 정착구(202)를 통해 기초용 쉬스관(111) 내부로 몰탈을 충진하여 세그먼트용 쉬스관(121) 및 코핑용 쉬스관(131)의 전길이 방향으로 몰탈을 충진한다.Then, the steel wire
그리고, 전단 연결재(203)와, 연결 소켓(205) 내부에 무수축 몰탈을 충진한 다. 이때, 연결 소켓(205)의 저면이 면접한 실링용 고무 패드(129)에 의해 무수축 몰탈이 외부로 미배출된다.In addition, the
한편, 도 13g에 도시된 바와 같이 교각 시공이 완료되면 세그먼트(120)와 이웃하는 세그먼트(120) 사이, 즉 모따기부(123)에 콘크리트와 다른 색상이 부여된 실링재(125)를 접착시켜 이들 사이를 실링시킨다. 이때, 실링재(125)를 대신하여 몰탈을 타설할 수도 있으며, 실링재(125)는 세그먼트(120)의 적층 과정에서 부착될 수도 있다.Meanwhile, as shown in FIG. 13G, when the pier construction is completed, the sealing
본 발명은 다양하게 변형될 수 있고 여러 가지 형태를 취할 수 있으며 상기 발명의 상세한 설명에서는 그에 따른 특별한 실시 예에 대해서만 기술하였다. 하지만 본 발명은 상세한 설명에서 언급되는 특별한 형태로 한정되는 것이 아닌 것으로 이해되어야 하며, 오히려 첨부된 청구범위에 의해 정의되는 본 발명의 정신과 범위 내에 있는 모든 변형물과 균등물 및 대체물을 포함하는 것으로 이해되어야 한다.As those skilled in the art would realize, the described embodiments may be modified in various ways, all without departing from the spirit or scope of the present invention. It is to be understood, however, that the present invention is not limited to the specific forms referred to in the description, but rather includes all modifications, equivalents, and substitutions within the spirit and scope of the invention as defined by the appended claims. Should be.
도 1은 종래의 강재 덕트를 이용한 조립구조를 가지는 세그먼트의 구성을 나타낸 사시도,1 is a perspective view showing the configuration of a segment having an assembly structure using a conventional steel duct,
도 2는 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 교각 기초의 구성을 나타낸 사시도,Figure 2 is a perspective view showing the configuration of the pier foundation of the PSC pier assembled with precast concrete segment having a steel duct and steel pipe according to the present invention,
도 3은 도 2의 A-A 단면도이며, 도 4는 도 2의 평면도,3 is a cross-sectional view taken along line A-A of FIG. 2, and FIG. 4 is a plan view of FIG. 2;
도 5는 본 발명에 따른 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 세그먼트의 구성을 나타낸 사시도,Figure 5 is a perspective view showing the configuration of the segment of the PSC piers assembled with precast concrete segment having a steel duct and steel pipe according to the present invention,
도 6은 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 세그먼트의 구성을 나타낸 저면 사시도,Figure 6 is a bottom perspective view showing the configuration of the segment of the PSC piers assembled with precast concrete segment having a steel duct and steel pipe according to the present invention,
도 7은 도 6의 B-B 단면도,7 is a cross-sectional view taken along line B-B of FIG.
도 8은 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 코핑부의 구성을 나타낸 측단면도,Figure 8 is a side cross-sectional view showing the configuration of the coping portion of the PSC pier assembled with precast concrete segment having a steel duct and steel pipe according to the present invention,
도 9a 및 도 9b는 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 전단 연결재의 구성을 나타낸 사시도,9a and 9b are perspective views showing the configuration of the shear connector in the PSC piers assembled with precast concrete segments having a steel duct and steel pipe according to the present invention,
도 10은 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각중 연결 소켓의 구성을 나타낸 사시도,10 is a perspective view showing the configuration of the connection socket of the PSC piers assembled with precast concrete segments having a steel duct and a steel pipe according to the present invention,
도 11은 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각을 나타낸 단면도,11 is a cross-sectional view showing a PSC pier assembled from precast concrete segments having steel ducts and steel pipes according to the present invention;
도 12는 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각의 시공 방법을 간략화시킨 공정도,12 is a process diagram simplifying the construction method of PSC piers assembled from precast concrete segments having steel ducts and steel pipes according to the present invention;
도 13a 내지 도 13g는 본 발명에 따른 강재 덕트 및 강관을 구비하는 프리캐스트 콘트리트 세그먼트로 조립된 PSC 교각의 시공 방법을 설명하기 위한 공정도.13A to 13G are process drawings for explaining a construction method of PSC piers assembled from precast concrete segments having steel ducts and steel pipes according to the present invention.
<도면의 주요 부분에 관한 부호의 설명><Explanation of symbols on main parts of the drawings>
110 : 교각 기초 120 : 세그먼트110: pier foundation 120: segment
130 : 코핑부 201 : 강선130: coping part 201: steel wire
203 : 전단 연결재 205 : 연결 소켓203: shear connector 205: connection socket
207 : 강선 지지용 강관207: steel pipe for supporting steel wire
Claims (16)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020080059383A KR101039656B1 (en) | 2008-06-24 | 2008-06-24 | Psc bridge pier assembled with precast concrete segments having steel duct and steel pipe, and constructing method thereof |
CN2008101444273A CN101613995B (en) | 2008-06-24 | 2008-07-31 | Psc bridge pier assembled with precast concrete segments having steel duct and steel pipe, and constructing method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020080059383A KR101039656B1 (en) | 2008-06-24 | 2008-06-24 | Psc bridge pier assembled with precast concrete segments having steel duct and steel pipe, and constructing method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20080065571A true KR20080065571A (en) | 2008-07-14 |
KR101039656B1 KR101039656B1 (en) | 2011-06-08 |
Family
ID=39816384
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020080059383A KR101039656B1 (en) | 2008-06-24 | 2008-06-24 | Psc bridge pier assembled with precast concrete segments having steel duct and steel pipe, and constructing method thereof |
Country Status (2)
Country | Link |
---|---|
KR (1) | KR101039656B1 (en) |
CN (1) | CN101613995B (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100924746B1 (en) * | 2009-03-26 | 2009-11-05 | (주)대우건설 | Method for constructing precast coping by using multi-step tensioning |
KR100971001B1 (en) * | 2009-05-28 | 2010-07-20 | (주)대우건설 | Prefabricated precast bridge pier for having shear connection fixing plate |
KR101010540B1 (en) * | 2008-07-21 | 2011-01-25 | 지에스건설 주식회사 | Half-precast coping construction method |
KR101017292B1 (en) * | 2008-12-10 | 2011-03-02 | 지에스건설 주식회사 | Precasr pier unit for footing level control and pier construction method therewith |
KR101029042B1 (en) * | 2008-07-21 | 2011-04-15 | 지에스건설 주식회사 | Precasr pier unit using sheath and pier construction method therewith |
CN105970803A (en) * | 2016-06-03 | 2016-09-28 | 南京工业大学 | Shearing resisting energy consumption device and construction method of prefabricated pier |
CN107938499A (en) * | 2018-01-11 | 2018-04-20 | 西南科技大学 | A kind of prefabricated assembled bridge pier |
CN112176886A (en) * | 2020-11-16 | 2021-01-05 | 山东高速建设管理集团有限公司 | Double-steel sleeve socket connection structure of prefabricated bridge pier and construction method thereof |
CN112267680A (en) * | 2020-11-05 | 2021-01-26 | 山东省建筑科学研究院有限公司 | Pouring system and method for prefabricated concrete structure |
WO2021237102A1 (en) * | 2020-05-21 | 2021-11-25 | Blaine Miller | Bridge support system |
CN113699876A (en) * | 2021-09-24 | 2021-11-26 | 江苏瑞沃建设集团有限公司 | Pier is assembled in prefabricated of segment of vertical continuous band tenon fourth of twelve earthly branches structure |
KR20230081880A (en) * | 2021-11-30 | 2023-06-08 | 한국철도기술연구원 | Bridge lower structure of assembly type having elastic duct coupler of socket type, and construction method for the same |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101831875A (en) * | 2010-06-09 | 2010-09-15 | 中交第一公路勘察设计研究院有限公司 | Precast assembly process of prestressed concrete cylindrical hollow pier |
KR100981982B1 (en) * | 2010-06-11 | 2010-09-13 | (주)대우건설 | Precast coping lifting system |
CN102864744B (en) * | 2012-08-31 | 2014-12-10 | 中交第二航务工程局有限公司 | Precast concrete construction element transporting system and method |
CN103758031B (en) * | 2014-01-26 | 2015-09-23 | 招商局重庆交通科研设计院有限公司 | A kind of method utilizing Steel Fiber Reinforced Self-compacting Concrete to prepare assembling bridge pier stud |
CN104088230B (en) * | 2014-07-29 | 2016-03-16 | 中国石油集团川庆钻探工程有限公司 | The method of attachment of prefabricated reinforced concrete block packaged type bridges pier |
CN110820545B (en) * | 2019-11-08 | 2021-06-08 | 济南金诺公路工程监理有限公司 | Assembled concrete pier |
CN110886204B (en) * | 2019-11-29 | 2021-03-16 | 重庆交通大学 | Prefabricated segment pier of assembled |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN85202839U (en) * | 1985-07-12 | 1986-05-28 | 铁道部第三勘测设计公司职工铁道工程学院 | Assembled prefabricated components made of reinforced concrete |
JPH08312854A (en) * | 1995-05-18 | 1996-11-26 | Ushio Kogyo Kk | Connecting structure of steel pipe and construction method for connecting and inserting of steel pipe |
CN100494597C (en) * | 2005-08-16 | 2009-06-03 | 株式会社大宇建设 | Prefabricated segmental concrete filled tube member, and fabrication structure and method using the same |
KR100704737B1 (en) * | 2005-10-27 | 2007-04-06 | 김태균 | Precast-underwater prefabricated pier structure |
KR100704874B1 (en) * | 2005-12-15 | 2007-04-09 | 주식회사 포스코건설 | Structures of prefabricated concrete pier strengthened in shear by steel pipe |
KR20080000243A (en) * | 2006-06-27 | 2008-01-02 | 한국건설기술연구원 | Reinforced soil pier and the bridge construction method therewith |
KR100653283B1 (en) * | 2006-07-11 | 2006-12-04 | 영도건설산업주식회사 | Method for connecting reinforced concrete structures |
JP5057223B2 (en) | 2007-09-11 | 2012-10-24 | 東洋建設株式会社 | Temporary wall construction method using steel segments |
-
2008
- 2008-06-24 KR KR1020080059383A patent/KR101039656B1/en active IP Right Grant
- 2008-07-31 CN CN2008101444273A patent/CN101613995B/en not_active Expired - Fee Related
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101010540B1 (en) * | 2008-07-21 | 2011-01-25 | 지에스건설 주식회사 | Half-precast coping construction method |
KR101029042B1 (en) * | 2008-07-21 | 2011-04-15 | 지에스건설 주식회사 | Precasr pier unit using sheath and pier construction method therewith |
KR101017292B1 (en) * | 2008-12-10 | 2011-03-02 | 지에스건설 주식회사 | Precasr pier unit for footing level control and pier construction method therewith |
KR100924746B1 (en) * | 2009-03-26 | 2009-11-05 | (주)대우건설 | Method for constructing precast coping by using multi-step tensioning |
KR100971001B1 (en) * | 2009-05-28 | 2010-07-20 | (주)대우건설 | Prefabricated precast bridge pier for having shear connection fixing plate |
CN105970803A (en) * | 2016-06-03 | 2016-09-28 | 南京工业大学 | Shearing resisting energy consumption device and construction method of prefabricated pier |
CN107938499A (en) * | 2018-01-11 | 2018-04-20 | 西南科技大学 | A kind of prefabricated assembled bridge pier |
WO2021237102A1 (en) * | 2020-05-21 | 2021-11-25 | Blaine Miller | Bridge support system |
CN112267680A (en) * | 2020-11-05 | 2021-01-26 | 山东省建筑科学研究院有限公司 | Pouring system and method for prefabricated concrete structure |
CN112176886A (en) * | 2020-11-16 | 2021-01-05 | 山东高速建设管理集团有限公司 | Double-steel sleeve socket connection structure of prefabricated bridge pier and construction method thereof |
CN112176886B (en) * | 2020-11-16 | 2022-03-22 | 山东高速建设管理集团有限公司 | Double-steel sleeve socket connection structure of prefabricated bridge pier and construction method thereof |
CN113699876A (en) * | 2021-09-24 | 2021-11-26 | 江苏瑞沃建设集团有限公司 | Pier is assembled in prefabricated of segment of vertical continuous band tenon fourth of twelve earthly branches structure |
KR20230081880A (en) * | 2021-11-30 | 2023-06-08 | 한국철도기술연구원 | Bridge lower structure of assembly type having elastic duct coupler of socket type, and construction method for the same |
Also Published As
Publication number | Publication date |
---|---|
CN101613995A (en) | 2009-12-30 |
KR101039656B1 (en) | 2011-06-08 |
CN101613995B (en) | 2011-07-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101039656B1 (en) | Psc bridge pier assembled with precast concrete segments having steel duct and steel pipe, and constructing method thereof | |
KR101036852B1 (en) | Psc bridge pier assembled with precast concrete segments having steel duct and steel pipe and reinforcing bar, and constructing method thereof | |
CN105696706B (en) | A kind of plug-in type assembled house | |
KR101143310B1 (en) | Precast concrete segments for constructing bridge piers with elongated round holes surrounding reinforcing bars and the method using the same | |
KR100920204B1 (en) | Constructing method of precast pier footing for bridge | |
JP4698491B2 (en) | Temporary closing method and structure of underwater structure | |
KR101708760B1 (en) | Construction method for precast concrete wall | |
KR100909277B1 (en) | Pier foundation with steel pipe and assembly structure | |
KR101713284B1 (en) | Seismic retrofit PC wall panel for RC frame, Seismic retrofit structure of RC frame using PC wall panel and construction method thereof | |
CN204112525U (en) | Band perps precast shear wall structure in strong concrete precast frame | |
KR100738999B1 (en) | Precast concrete segment having connecting structure using steel duct, and connecting structure thereof | |
KR100817685B1 (en) | New RC Plate Slab - to - CFT Column Connection, and Top-down Method for Constructing Underground Floors of Building | |
JP5509380B1 (en) | Seismic reinforcement method and structure for existing buildings | |
CN111827091A (en) | Prefabricated assembled hollow pier connected through prestress and construction method | |
CN111074767A (en) | Double-block type prefabricated assembled anti-collision guardrail and construction method | |
KR102580530B1 (en) | Bridge lower structure of assembly type having elastic duct coupler of socket type, and construction method for the same | |
JP4924967B2 (en) | Tower structure | |
KR100880022B1 (en) | Prefabricated precast concrete pumping plant manhole | |
CN212561130U (en) | Prefabricated assembled hollow pier connected through prestress | |
CN211341214U (en) | Connecting joint of caisson | |
KR20120134677A (en) | The precast concrete closed conduit that is reinforced by the shear connector and constructing method of it | |
KR100823348B1 (en) | Installation method of a retaining wall | |
JP3117906U (en) | Tower structure | |
KR20110103087A (en) | Power transmission manhole | |
KR200370627Y1 (en) | Frame to draw out beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20140624 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20150616 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20160525 Year of fee payment: 6 |