KR200400109Y1 - Arch-shaped precast panel for building arch-type slab - Google Patents

Arch-shaped precast panel for building arch-type slab Download PDF

Info

Publication number
KR200400109Y1
KR200400109Y1 KR20-2005-0018084U KR20050018084U KR200400109Y1 KR 200400109 Y1 KR200400109 Y1 KR 200400109Y1 KR 20050018084 U KR20050018084 U KR 20050018084U KR 200400109 Y1 KR200400109 Y1 KR 200400109Y1
Authority
KR
South Korea
Prior art keywords
slab
precast panel
arch
arched
concrete
Prior art date
Application number
KR20-2005-0018084U
Other languages
Korean (ko)
Inventor
김회준
김성일
Original Assignee
(주)스틸엔콘크리트
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)스틸엔콘크리트 filed Critical (주)스틸엔콘크리트
Priority to KR20-2005-0018084U priority Critical patent/KR200400109Y1/en
Application granted granted Critical
Publication of KR200400109Y1 publication Critical patent/KR200400109Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 고안은 아치형 프리캐스트판넬을 이용하여 아치형으로 슬래브를 설치하여 인장력이 발생하지 않고 압축력만 발생하도록 함과 동시에 교량설치시 별도의 거푸집을 사용하지 않고 상기 아치형 프리캐스트판넬을 설치하고 콘크리트를 타설하여 슬래브와 일체가되도록 한 아치형슬래브교량설치방법이다.        The present invention uses the arched precast panel to install the slab in the arch shape so that the tensile force does not occur and only the compressive force is generated, and the arched precast panel is installed without the use of additional formwork when installing the bridge and the concrete is poured. Arched slab bridge installation method to be integrated with the slab.

Description

아치형슬래브설치를 위한 아치형프리캐스트판넬{Arch-shaped precast panel for building arch-type slab}Arch-shaped precast panel for building arch-type slab}

본 고안은 교각의 상부에 교량의 폭을 형성하도록 다수개의 프리스트레싱 합성빔을 설치하고 상기 양측에 설치된 프리스트레싱 합성빔의 하부케이싱 콘크리트의 상부에 단위 아치형 프리캐스트판넬을 거치하여 슬래브의 중앙에서 전단키와 강선에 의한 연결부를 형성하도록 하여 아치형으로 슬래브를 설치할 수 있는 아치형 프리캐스트판넬을 설치한 후에 상기 아치형 프리케스트판넬의 수직부와 프리스트레싱 합성빔의 복부와의 사이에 콘크리트 몰탈을 타설한 타설부를 형성한 후에 전체적으로 슬래브를 형성할 수 있도록 콘크리트를 타설하여 아치형 프리캐스트 판넬과 슬래브가 일체형으로 설치된 아치형슬래브교량의 설치방법이다.        The present invention installs a plurality of prestressing composite beams to form the width of the bridge in the upper part of the pier, and the shear key and steel wire in the center of the slab by mounting a unit arched precast panel on the upper casing concrete of the prestressing composite beams installed on both sides After installing the arched precast panel that can install the slab in the arch shape by forming the connection part by the concrete, and after forming the casting part in which the concrete mortar is poured between the vertical part of the arched precast panel and the abdomen of the prestressing composite beam It is a method of installing the arched slab bridge in which the arched precast panel and the slab are integrally installed by pouring concrete to form the slab as a whole.

상기 단위 아치형 프리캐스트 판넬은 일측에 수직부를 형성하고, 상기 수직부의 상부에서 일정한 간격을 두고 돌출부와 홈부를 다수개 교차형성한 아치부를 설치하되, 설치하고자 하는 교량의 아치부의 중간길이에 해당하는 길이만큼 아치부를 설치하고, 아치부가 끝나는 부분의 면에는 돌출부 및 홈부 또는 홈부 및 돌출부를 각각 형성하여 상기 단위 아치형프리캐스트판넬을 중앙에서 서로 연결할 때 상호 맞물려 연결되도록 하는 전단키를 형성하고, 연결부의 판넬몸체에 강선을 관통하여 강선을 이용하여 상호 연결할 수 있도록 하는 연결부를 형성하도록 한 것이다.        The unit arcuate precast panel has a vertical portion formed on one side, and installs an arch portion formed by crossing a plurality of protrusions and groove portions at regular intervals from the upper portion of the vertical portion, and has a length corresponding to the intermediate length of the arch portion of the bridge to be installed. The arch portion is provided as much as possible, and on the surface of the end portion of the arch portion, protrusions and grooves or grooves and protrusions are respectively formed to form shear keys for interlocking with each other when the unit arc-shaped precast panels are connected to each other at the center, and the panel body of the connection portion. Through the wires to form a connection to be connected to each other using a steel wire.

본 고안은 슬래브의 하부를 아치형으로 설치하기 위하여 거푸집 대용으로 아치형 프리캐스트판넬을 사전에 공장제작하여 이를 현장에 거치하도록 한 후에 콘크리트를 타설하여 아치형 슬래브교량을 시공하도록 한 것이다.        In order to install the lower part of the slab in arch shape, the present invention manufactures the arch precast panel in advance as a substitute for the formwork and mounts it on the site, and then installs the arch to form the arched slab bridge.

본 고안의 합성빔은 프리스트레싱이 도입된 합성빔을 이용하는 것으로서 통상적으로 시용하고 있는 프리플렉스 합성빔 및 기타 모든 합성빔을 지칭하는 것이다.        The synthesized beam of the present invention refers to a preplex synthesized beam and all other synthesized beams which are commonly used as using a synthetic beam having prestressing introduced therein.

상기와 같은 아치형 슬래브교량의 설치목적은 아치형으로 슬래브를 설치하므로서, 아치형 프리캐스트 판넬에 별도의 압축력을 도입할 필요가 없고, 아치형 슬래브에는 압축력이 작용하도록 된 아치이론(σ=P/A)에 의하여 설계가 가능하므로 슬래브의 전단면이 유효한 단면으로 구조적으로 매우안정적이며 별도의 압축력을 도입할 필요가 없는 설치가 간단한 방법이며, 상기와 같이 아치형 프리캐스트 판넬을 이용하여 슬래브를 헌치부가 없는 곡선형의 아치형으로 설치가 가능하도록 거푸집 대용으로 공장제작된 아치형 프리캐스트판넬을 이용하도록 하도록 하여 슬래브설치를 위하여 콘크리트타설시 상기 아치형 프리캐스트판넬과 일체형으로 설치가 가능하도록 한 것이다.        The purpose of the installation of the arched slab bridge as described above is to install the slab in an arch shape, so that it is not necessary to introduce a separate compressive force to the arched precast panel, and to the arch theory (σ = P / A) that the compressive force acts on the arched slab. As the design is possible, the shear surface of the slab is an effective cross-section, which is structurally very stable, and it is simple to install without the need for introducing a separate compressive force. In order to enable the installation of the arch to use the factory-made arched precast panel as a substitute for the form of the slab to be installed in the concrete when the slab is to be installed integrally with the arched precast panel.

종래에는 도 1의 (가)(나)(다)(라)에서보는바와 같이 (가) 교각(11)위에 프리플렉스 합성빔(18)을 교량의 폭에 해당하도록 다수개 설치한 후에, (나)상기 합성빔(18)의 하부케이싱 콘크리트(23) 상부에 헌치부(17)가 설치된 프리캐스트(15)를 설치한 후에, (다)상기 프리캐스트(15)에 압축력을 도입할 수 있도록 프리캐스트를 강선으로 긴장연결하면서 콘크리트를 타설양생한 후에 상기 강선을 릴리스하면 압축력이 상기 프리캐스트에 도입되도록 하는 압축력도입부(16)를 설치하고, 슬래브콘크리트(14)를 타설양생하도록 한 다음, (라)헌치부(17)가 설치된 슬래브(12)를 형성하고 그 위에 연석(13)등의 교량에 필요한 시설을 하여 교량(10)을 설치하도록 한 것이며,        Conventionally, as shown in (a), (b) and (d) of FIG. 1, (a) after a plurality of preplex composite beams 18 are installed on the bridge 11 to correspond to the width of the bridge, B) After the precast 15 having the haunches 17 is installed on the lower casing concrete 23 of the composite beam 18, (c) to introduce a compressive force into the precast 15. After the concrete is poured while tensioning the precast with a steel wire, when the steel wire is released, a compression force introduction part 16 is installed to allow the compressive force to be introduced into the precast, and the slab concrete 14 is poured into D) forming the slab 12 in which the hunt portion 17 is installed and installing the bridge 10 by installing the necessary facilities for bridges such as curbs 13 thereon,

또 다른 종래의 방법에는 도 2의 (가)(나)(다)(라)에서 보는바와 같이 (가) 교각(11)위에 프리플렉스 합성빔(18)을 교량의 폭에 해당하도록 다수개 설치한 후에, (나)상기 합성빔(18)의 하부케이싱 콘크리트(23) 상부에 헌치부(17)가 설치된 거푸집(32)을 동바리(31)를 이용하여 설치한 후에, (다) 슬래브콘크리트(14)를 타설양생하도록 한 다음, (라)헌치부(17)가 설치된 슬래브(12)를 형성하고 그 위에 연석(13)등의 교량에 필요한 시설을 하여 교량을 설치하도록 한 것이다.          In another conventional method, as shown in (a) (b) and (d) of FIG. 2, (a) a plurality of preflex composite beams 18 are installed on the bridge 11 to correspond to the width of the bridge. Afterwards, (b) after installing the formwork 32 having the haunches 17 installed on the lower casing concrete 23 of the composite beam 18 by using the copper club 31, (c) the slab concrete ( 14) after the casting, and (d) to form the slab (12) on which the hunt unit (17) is installed and the necessary facilities for bridges, such as curb (13), to install the bridge.

상기 종래기술인 도 1과 2의 슬래브(12)에는 헌치부(17)가 설치된 프리캐스트(15)를 이용하여 슬래브(12)를 설치하거나 거푸집(32)에 헌치부(17)가 설치될 수 있도록 제작하여 헌치부(17)가 있는 슬래브(12)를 설치한 것으로서, 헌치부(17)가 있는 슬래브(12)에는 판이론(σ=±M/Z)에 의하여 중립축 상부에 타설한 콘크리트만 유효한 단면으로 하고 중립축의 하부에 타설된 콘크리트는 유효단면으로 인정하지 않고, 이를 보완하기 위하여 철근을 배근하도록 하여 중립축 하부의 인장력을 철근에 의하여 부담하도록 한 구조계산에 의한 것으로서, 상기 도 1과 같이 프리캐스트(15)를 이용하여 슬래브(12)를 설치하더라도 헌치부(17)가 있을 경우 프리캐스트(15)에 압축력을 도입하도록 하는 단계를 별도로 반드시 거쳐야 하는 번거로움과 도 2에서보는바와 같이 중립축 하부의 단면도 인장력을 받도록 하기 위하여는 인장철근을 설치하도록 하는 과다설계의 문제점이 제기되어 왔다.        1 and 2 of the prior art, so that the slab 12 is installed using the precast 15 having the haunches 17 installed thereon, or the haunches 17 may be installed in the form 32. The slab 12 with the haunch 17 is manufactured and only the concrete placed on the neutral shaft by plate theory (σ = ± M / Z) is effective for the slab 12 with the haunch 17. The concrete placed in the cross section and placed in the lower part of the neutral shaft is not recognized as an effective cross section, and it is by structural calculation to reinforce the rebar to compensate for this and to bear the tensile force in the lower part of the neutral shaft by the rebar, as shown in FIG. Even if the slab 12 is installed using the cast 15, if there is a haunting unit 17, it is necessary to separately go through the step of introducing a compressive force to the precast 15, and as shown in FIG. Of over-design to install the tensile reinforcement to receive a cross-sectional view tension problems have been raised.

본 고안은 상기와 같은 문제점을 개선하기 위하여 제안된 것으로서, 아치형으로 슬래브를 설치하므로서, 아치형 프리캐스트 판넬에 별도의 압축력을 도입하지 않고도 아치형 슬래브에 압축력이 도입되도록 하여 슬래브의 전단면이 유효한 단면으로 구조적으로 매우안정적이며 설치가 간단한 방법이며 별도의 인장철근이 필요없어 경제적인 시공이 가능하며,         The present invention has been proposed to improve the above problems, by installing the slab in the arch shape, so that the compressive force is introduced into the arched slab without introducing a separate compressive force to the arched precast panel to the effective cross section of the slab It is structurally very stable and simple to install and economical construction is possible because there is no need for additional tensile rebar.

상기와 같이 아치형 프리캐스트 판넬을 이용하여 슬래브를 헌치부가 없는 곡선형의 아치형으로 설치가 가능하도록 공장제작된 아치형 프리캐스트판넬을 거푸집 대용으로 이용하여 슬래브콘크리트 타설시 슬래브와 일체가 되도록 한 아치형 슬래브교량설치방법을 제공하는데 있다.       Arch type slab which is integrated with slab when slab concrete is poured by using the factory-made arch type precast panel as a substitute for the formwork so that the slab can be installed in a curved arch shape without the haunch part using the arch type precast panel as described above. To provide a bridge installation method.

본 고안은 교각(11)의 상부에 교량의 폭을 형성하도록 다수개의 프리스트레싱 합성빔(20)을 설치하고 상기 양측에 설치된 프리스트레싱 합성빔(20)의 하부케이싱 콘크리트(23)의 상부에 단위 아치형 프리캐스트판넬(60)을 거치하여 슬래브(12)의 중앙에서 전단키(71)와 강선(73)에 의한 연결부(70)를 형성하도록 하여 아치형으로 슬래브(12)를 설치할 수 있는 아치형 프리캐스트판넬(50)을 설치한 후에 상기 아치형 프리캐스트판넬(50)의 수직부(54)와 프리스트레싱 합성빔(20)의 복부(22)와의 사이에 콘크리트 몰탈을 타설한 타설부(42)를 형성한 후에 전체적으로 슬래브(12)를 형성할 수 있도록 콘크리트(14)를 타설하여 아치형 프리캐스트 판넬(50)과 슬래브(12)가 일체형으로 설치된 아치형슬래브교량(40)의 설치방법이다.        The present invention provides a plurality of pre-stressing composite beam 20 to form a width of the bridge on the top of the pier 11 and unit arch-shaped free on top of the lower casing concrete 23 of the pre-stressing composite beam 20 installed on both sides An arched precast panel 50 through which the slab 12 can be installed in an arch shape by forming the connection portion 70 by the shear key 71 and the steel wire 73 in the center of the slab 12 by passing through the cast panel 60. After installing the slab, the slab part in which concrete mortar is poured is formed between the vertical part 54 of the arcuate precast panel 50 and the abdomen 22 of the prestressing composite beam 20. It is a method of installing the arched slab bridge 40 in which the concrete 14 is cast so as to form 12, and the arcuate precast panel 50 and the slab 12 are integrally installed.

상기 단위 아치형 프리캐스트 판넬(60)은 일측에 수직부(54)를 형성하고, 상기 수직부(54)의 상부에서 일정한 간격을 두고 돌출부(58)와 홈부(57)를 다수개 교차형성한 아치부(51)를 설치하되, 설치하고자 하는 교량의 아치형 슬래브의 중간길이에 해당하는 길이만큼 아치부(51)를 설치하고, 아치부(51)가 끝나는 부분의 면에는 돌출부(58) 및 홈부(57) 또는 홈부(57) 및 돌출부(58)를 각각 형성하여 상기 단위 아치형프리캐스트판넬(60)을 중앙에서 서로 연결할 때 상호 맞물려 연결되도록 하는 전단키(71)를 형성하고, 상기 단위아치형프리캐스트판넬(60)이 상호 연결되는 부분의 판넬(60)몸체에 강선(73)을 관통하도록 하여 인접한 판넬과 강선으로 상호 연결하도록 하는 연결부(70)를 형성한 것에 특징이 있다.        The unit arcuate precast panel 60 forms a vertical portion 54 on one side and cross-produces a plurality of protrusions 58 and grooves 57 at regular intervals from the upper portion of the vertical portion 54. To install the tooth 51, the arch portion 51 is installed to the length corresponding to the middle length of the arched slab of the bridge to be installed, and the projections 58 and the groove ( 57 or the grooves 57 and the protrusions 58, respectively, to form a shear key 71 to be engaged with each other when the unit arcuate precast panel 60 is connected to each other at the center, and the unit arch type precast panel It is characterized in that the connection portion 70 is formed so as to penetrate the steel wire 73 to the panel 60 body of the portion where the 60 is connected to each other to interconnect with the adjacent panel and the steel wire.

이하, 첨부된 도면에 의하여 본 고안의 구성 및 작용을 상세히 설명하면 다음과 같다.        Hereinafter, the configuration and operation of the present invention in detail by the accompanying drawings as follows.

도 3(가)(나)(다)(라)는 본 고안의 아치형프리캐스트판넬을 이용하여 아치형슬래브를 설치한 아치형슬래브교량의 설치과정을 보여주는 도면으로서, (가)는 교각(11)의 상부에 교량의 폭을 형성하도록 다수개의 프리스트레싱 합성빔(20)을 설치하고, (나)는 상기 양측에 설치된 프리스트레싱 합성빔(20)의 하부케이싱 콘크리트(23)의 상부에 단위 아치형 프리캐스트판넬(60)을 각각 거치하여 아치형 슬래브의 중앙에서 전단키(71)와 강선(73)에 의한 연결부(70)를 형성하도록 하여 아치형으로 슬래브(12)를 설치할 수 있는 아치형 프리캐스트판넬(50)을 설치한 후에,         Figure 3 (a) (b) (c) (d) is a view showing the installation process of the arched slab bridge in which the arched slab is installed using the arched precast panel of the present invention, (a) is the A plurality of prestressing composite beams 20 are installed to form the width of the bridge on the upper part, and (b) unit arc-shaped precast panels (top) of the lower casing concrete 23 of the prestressing composite beams 20 installed on both sides. 60) to form the connection portion 70 by the shear key 71 and the steel wire 73 in the center of the arched slab to install the arcuate precast panel 50 that can install the slab 12 in the arch after,

(다)는 상기 아치형 프리캐스트판넬(50)의 수직부(54)와 프리스트레싱 합성빔(20)의 복부(22)와의 사이에 콘크리트 몰탈을 타설한 타설부(42)를 형성한 후에 전체적으로 슬래브(12)를 형성할 수 있도록 콘크리트(14)를 타설하고, (라)는 상기 슬래브(12)를 아치형 프리캐스트판넬(50)과 일체형으로 설치하고, 슬래브(12) 상부에는 교량의 양쪽폭의 단부에 연석(13)을 설치한 아치형슬래브교량(40)이다.(C) The slab (the entirety of the arcuate precast panel 50 and the vertical part 54 and the abdomen 22 of the prestressing composite beam 20) is formed as a whole, The concrete 14 is poured to form 12, and (d) the slab 12 is integrally installed with the arcuate precast panel 50, and the slabs 12 are formed at both ends of both widths of the bridge. It is an arched slab bridge 40 provided with a curb 13.

상기 (다)의 그림에서 아치형 프리캐스트판넬(50)의 수직부(54)와 프리스트레싱 합성빔(20)의 복부(22)와의 사이에 1차적으로 콘크리트 몰탈을 타설한 타설부(42)를 형성하도록 하는 것은 복부(22)와 수직부(54) 사이에 몰탈을 타설하므로서 수직부(54)가 내측 즉, 교량의 지간내부로 향하도록 하면서 향후에 타설되는 슬래브콘크리트에 의하여 아치부인 슬래브(12)에 압축력이 자동적으로 도입되도록 하여 아치부에는 압축력만 작용될 수 있게 하여 슬래브 전체단면이 유효한 단면이 되도록 하여 단면력증대와 인장철근사용량을 감소시키도록 하면서 수직부(54)가 정확하게 하부케이싱콘크리트(23)위에 설치되도록 위치를 고정하도록 하기 위함이다.        In the figure (c), a casting part 42 in which concrete mortar is poured is formed between the vertical part 54 of the arcuate precast panel 50 and the abdomen 22 of the prestressing composite beam 20. The slab 12, which is arched by the slab concrete, which is poured in the future while placing the mortar between the abdomen 22 and the vertical portion 54 while directing the vertical portion 54 to the inner side, that is, the interior of the bridge. The compressive force is automatically introduced into the arch so that only the compressive force can be applied to the arch so that the entire section of the slab becomes an effective cross section, thereby increasing the cross-sectional force and reducing the amount of tensile rebar, while the vertical portion 54 accurately lowers the concrete (23). This is to fix the position so that it is installed above.

상기 프리스트레싱 합성빔의 하부케이싱 콘크리트 상부에 아치형 프리캐스트 판넬을 사용하지 않고 거푸집을 아치형으로 제작설치한 다음 슬래브콘크리트를 타설하여 아치형슬래브교량을 설치하는 방법을 이용할 수도 있는데 이경우에도 아치형의 슬래브에는 압축력이 도입된 상태인 것이다.        It is also possible to use a method of fabricating the formwork in an arch form without using an arch precast panel on the upper casing concrete of the prestressing composite beam, and then installing slab concrete to install an arch slab bridge. Introduced.

도 4는 본 고안의 단위아치형프리캐스트판넬을 조립한 아치형프리캐스트판넬을 보여주는 도면으로서, 아치형 슬래브(12)를 설치하기 위하여 단위아치형 프리캐스트판넬(60)을 상호 연결한 것으로서 일정한 폭을 갖는 단위 아치형 프리캐스트판넬(60)을 교량의 길이방향으로 설치하고 콘크리트를 타설하여 아치형 슬래브(12)를 설치하기 위한 것이다.         4 is a view showing an arched precast panel in which the unit arch type precast panel of the present invention is assembled. The unit having a predetermined width as interconnecting the unit arch type precast panel 60 to install the arcuate slab 12 is shown in FIG. The arcuate precast panel 60 is installed in the longitudinal direction of the bridge and is to install the arcuate slab 12 by pouring concrete.

상기 단위 아치형 프리캐스트 판넬(60)은 일측에 수직부(54)를 형성하고, 상기 수직부(54)의 상부에서 일정길이 연장된 연장부의 상면에는 일정한 간격을 두고 돌출부(58)와 홈부(57)를 다수개 교차형성한 아치부(51)를 설치하되, 설치하고자 하는 교량의 아치형 슬라브(12)를 이등분하는 길이만큼 아치부(51)를 설치하고, 아치부(51)가 끝나는 부분의 면에는 돌출부(58) 및 홈부(57) 또는 홈부(57) 및 돌출부(58)가 각각 형성된 전단키(71)를 형성하도록 하여 상기 단위 아치형프리캐스트판넬(60)을 중앙에서 서로 연결할 때 상기 전단키(71)의 돌출부(58) 및 홈부(57)가 상호 맞물려 연결되도록 하고, 상기 단위아치형프리캐스트판넬(60)이 상호 연결되는 부분의 판넬몸체에 강선(73)을 관통하도록 하여 인접하여 상호 연결된 상기 판넬(60)을 강선(73)으로 상호 연결하도록 하는 연결부(70)를 형성하도록 한 것이다.상기 연장부의 상면에 형성된 홈부(57)와 돌출부(58)는 도 6에서 보는 바와 같이 슬래브 콘크리트(14)를 타설하여 슬래브를 설치할 때 긴밀하게 결합되어 일체적으로 외부하중에 대하여 거동할 수 있도록 하기 위한 전단연 결재역할을 하도록 한 것으로서, 상기와 같이 홈부와 돌출부를 순차적으로 형성하는 방법이외에, 상기 연장부 상면에 철근을 디긋자형태로 돌출설치하는 것과 전단볼트를 다수개 설치하는 등, 타설되는 콘크리트와의 부착력을 향상시키기 위한 모든 전단연결재를 포함하도록 한다.         The unit arcuate precast panel 60 forms a vertical portion 54 on one side, and the protrusions 58 and the groove portion 57 at regular intervals on the upper surface of the extension portion extending from the upper portion of the vertical portion 54 by a predetermined length. ) Install a plurality of cross-sections of the arch portion 51, the arch portion 51 is installed to a length equal to the length of the arch-shaped slab 12 of the bridge to be installed, the surface of the portion where the arch portion 51 ends In order to form a shear key 71 formed with a protrusion 58 and a groove 57 or a groove 57 and a protrusion 58, respectively, the shear key 71 when the unit arcuate precast panel 60 is connected to each other in the center thereof. The protrusions 58 and the grooves 57 of the) are engaged with each other, and the unit arch type precast panel 60 penetrates the steel wire 73 through the panel body of the interconnected portion so as to be adjacent to each other. (60) to interconnect with steel wire (73) As shown in FIG. 6, the groove portion 57 and the protrusion 58 formed on the upper surface of the extension portion are closely coupled and integrally formed when the slab is installed by pouring the slab concrete 14 as shown in FIG. 6. As a shear connecting role to be able to behave with respect to the external load in addition to the method of sequentially forming the groove portion and the protrusion as described above, protruding rebar in the form of a deflector on the upper surface of the extension portion and shear Include all shear connectors to improve adhesion to the concrete being poured, such as installing multiple bolts.

상기 단위아치형 프리캐스트 판넬(60)을 형성하는 철골은 수직부(54)의 하단에 철근(55)을 설치하고, 수직부(54)와 아치부(51)에는 와이어메쉬(56)를 설치한 다음 콘크리트를 타설양생하도록 한 공장제작품이거나 현장제작품으로 사전에 제작하여 설치하여 아치형슬래브를 형성하도록 한 것이다.         The steel frame forming the unit arch type precast panel 60 is provided with reinforcing bar 55 at the lower end of the vertical part 54, and wire mesh 56 is installed at the vertical part 54 and the arch part 51. Next, it is to make arch type slab by manufacturing and installing in advance as factory production or site production to cast concrete.

도 5는 본 고안의 단위 아치형프리캐스트판넬과 연결부를 상세히 보여주는 도면으로서, 설치하고자 하는 교량의 슬래브길이의 1/2에 해당하는 길이로 제작한 것으로서, 추후에 아치를 형성하기 위하여 상기 단위 아치형프리캐스트판넬(60)을 설치하여 교량의 아치부분의 슬래브 중앙에서 상기 단위아치형 프리캐스트판넬(60)이 상호 연결되도록 하여 아치형의 슬래브(12)를 설치하도록 하기 위한 것이다.        Figure 5 is a view showing in detail the unit arch-shaped precast panel and the connection of the present invention, which is made of a length corresponding to half the slab length of the bridge to be installed, the unit arched free to form an arch later The cast panel 60 is installed to allow the unit arch type precast panel 60 to be interconnected at the center of the slab of the arch portion of the bridge to install the arcuate slab 12.

상기 단위 아치형 프리캐스트 판넬(60)은 일측에 수직부(54)를 형성하고, 상기 수직부(54)의 상부에서 일정길이 연장된 연장부의 상면에는 일정한 간격을 두고 돌출부(58)와 홈부(57)를 다수개 교차형성한 아치부(51)를 설치하되, 설치하고자 하는 교량의 아치형 슬래브(12)를 이등분하는 길이만큼 아치부(51)를 설치하고, 아치부(51)가 끝나는 부분의 면에는 돌출부(58) 및 홈부(57) 또는 홈부(57) 및 돌출부(58)가 각각 형성된 전단키(71)를 형성하도록 하여 상기 단위 아치형프리캐스트판넬(60)을 중앙에서 서로 연결할 때 상기 전단키(71)의 돌출부(58) 및 홈부(57)가 상호 맞물려 연결되도록 하고, 상기 단위아치형프리캐스트판넬(60)이 상호 연결되는 부분의 판넬몸체에 강선을 관통하도록 하여 인접하여 상호 연결된 상기 판넬을 강선으로 상호 연결하도록 하는 연결부를 형성하도록 한 것이다.The unit arcuate precast panel 60 forms a vertical portion 54 on one side, and the protrusions 58 and the groove portion 57 at regular intervals on the upper surface of the extension portion extending from the upper portion of the vertical portion 54 by a predetermined length. ) Install a plurality of cross-sectioned arch portion 51, but installs the arch portion 51 to the length equal to the length of the arch-shaped slab 12 of the bridge to be installed, the surface of the portion where the arch portion 51 ends In order to form a shear key 71 formed with a protrusion 58 and a groove 57 or a groove 57 and a protrusion 58, respectively, the shear key 71 when the unit arcuate precast panel 60 is connected to each other in the center thereof. The protrusions 58 and the grooves 57 of the () are meshed with each other and the unit arch type precast panel 60 is connected to the panel body of the interconnected portion by a steel wire so that the adjacent interconnected panels are steel wires. Connections to Interconnect To form.

상기 단위아치형 프리캐스트 판넬(60)을 형성하는 철골은 수직부(54)의 하단에 철근(55)을 설치하고, 수직부(54)와 아치부(51)에는 와이어메쉬(56)를 설치한 다음 콘크리트를 타설양생하도록 한 공장제작품이거나 현장제작품으로 사전에 제작하여 설치하여 아치형슬래브를 형성하도록 한 것이다.         The steel frame forming the unit arch type precast panel 60 is provided with reinforcing bar 55 at the lower end of the vertical part 54, and wire mesh 56 is installed at the vertical part 54 and the arch part 51. Next, it is to make arch type slab by manufacturing and installing in advance as factory production or site production to cast concrete.

도 6은 본 고안의 단위아치형 프리캐스트판넬을 조립하여 아치형프리캐스트판넬을 프리스트레싱 합성빔에 설치하고 콘크리트를 타설하여 아치형슬래브교량을 설치한 것을 상세히 보여주는 도면으로서, 도 3의 설치과정에 의하여 설치된 교량을 전체적으로 보여주는 것이다.         6 is a view showing in detail the installation of the arch arch slab bridge by installing the arch arch precast panel to the pre-stressing composite beam by assembling the unit arch type precast panel of the present invention, the concrete is installed, the bridge installed by the installation process of FIG. Shows the whole.

교각(11)의 상부에 교량의 폭을 형성하도록 다수개의 프리스트레싱 합성빔(20)을 설치하고, 상기 양측에 설치된 프리스트레싱 합성빔(20)의 하부케이싱 콘크리트(23)의 상부에 단위 아치형 프리캐스트판넬(60)을 각각 거치하여 슬래브의 중앙에서 아치부(51)가 전단키(71)와 강선(73)에 의한 연결부(70)를 형성하도록 하여 아치형으로 슬래브(12)를 설치할 수 있는 아치형 프리캐스트판넬(50)을 설치한 후에, 상기 아치형 프리캐스트판넬(50)의 수직부(54)와 프리스트레싱 합성빔(20)의 복부(22)와의 사이에 콘크리트 몰탈을 타설한 타설부(42)를 형성한 후에 전체적으로 슬래브를 형성할 수 있도록 콘크리트를 타설하고, 상기 슬래브를 아치형 프리캐스트판넬(50)과 일체형으로 설치하고, 슬래브(12) 상부에는 교량의 양쪽폭의 단부에 연석(13)을 설치한 아치형슬래브교량(40)이다.        A plurality of prestressing composite beams 20 are provided on the top of the bridge 11 to form the width of the bridge, and the unit arcuate precast panel is provided on the upper casing concrete 23 of the prestressing composite beams 20 provided on both sides. Arching precast panel that can install the slab 12 in an arch shape by mounting the respective 60 so that the arch 51 in the center of the slab to form a connecting portion 70 by the shear key 71 and the steel wire 73. After installing 50, a casting part 42 in which concrete mortar is poured is formed between the vertical part 54 of the arcuate precast panel 50 and the abdomen 22 of the prestressing composite beam 20. Later, concrete is formed so that the slab can be formed as a whole, the slab is integrally installed with the arcuate precast panel 50, and the slab 12 has an arch shape in which the curbstones 13 are installed at the ends of both widths of the bridge. Slab Bridge 40.

상기 아치형 프리캐스트판넬(50)의 수직부(54)와 프리스트레싱 합성빔(20)의 복부(22)와의 사이에 1차적으로 콘크리트 몰탈을 타설한 타설부(42)를 형성하도록 하는 것은 복부와 수직부 사이에 몰탈을 타설하므로서 수직부가 내측 즉, 교량의 지간내부로 향하도록 하면서 향후에 타설되는 슬래브콘크리트에 의하여 아치부에 자동적으로 압축력이 도입되면서 상기 아치부와 일체로 형성된 슬래브(12)에도 압축력이 자동적으로 도입되도록 하여 아치부를 포함한 슬래브 전체에는 압축력만 작용될 수 있게 하면서 수직부(54)가 정확하게 하부케이싱콘크리트(23)위에 설치되도록 위치를 고정하도록 하기 위함이다.          Forming a casting part 42 in which concrete mortar is poured between the vertical part 54 of the arcuate precast panel 50 and the abdomen 22 of the prestressing composite beam 20 is perpendicular to the abdomen. While placing the mortar between the parts, the vertical part is directed to the inside, that is, the interior of the bridge, and the compressive force is automatically introduced into the arch by the slab concrete, which is poured in the future, and the slab 12 formed integrally with the arch part also has the compressive force. This is to ensure that the vertical portion 54 is accurately installed on the lower casing concrete 23 while allowing only the compressive force to be applied to the entire slab including the arch portion to be automatically introduced.

본 고안은 상기와 같은 문제점을 개선하기 위하여 제안된 것으로서, 아치형의 아치형 프리캐스트 판넬을 설치하고 그 위에 슬래브콘크리트를 타설양생하여 압축력이 도입되도록 한 상기 판넬과 슬래브가 일체형으로 설치된 아치형 슬래브로서, 상기 아치형 프리캐스트 판넬에 별도의 압축력을 도입할 필요가 없는 아치형 슬래브의 전단면이 압축력이 작용하게되므로서 슬래브전단면이 유효한 단면으로서 인장철근량을 감소시키면서 구조적으로 매우안정적이며 설치가 간단한 방법이며, 상기와 같이 아치형 프리캐스트 판넬을 이용하여 슬래브를 헌치부가 없는 곡선형의 아치형으로 설치가 가능하도록 공장제작된 아치형 프리캐스트판넬을 거푸집 대용으로 이용하면서 슬래브콘크리트 타설시 슬래브와 일체가 되도록 한 경제적이며 시공이 간편한 아치형 슬래브교량설치방법인 것이다.           The present invention has been proposed to improve the above problems, an arcuate slab in which the panel and the slab are integrally installed so that the compression force is introduced by installing an arcuate arched precast panel and pouring slab concrete thereon. As the shear surface of the arched slab does not need to introduce a separate compressive force to the arcuate precast panel, the compressive force acts, so the cross section of the slab is effective and the structure is very stable and simple to install while reducing the amount of tensile rebar. It is economical and construction to be integrated with the slab when slab concrete is laid while using the factory-made arch precast panel as a substitute for formwork so that the slab can be installed in a curved arch form without a haunch using the arch precast panel. This handy Tooth slab will bridge the installation.

도 1(가)(나)(다)(라)는 종래에 헌치부가 있는 프리캐스트를 이용하여 헌치형 슬래브를 설치한 교량의 설치과정을 보여주는 도면.        Figure 1 (a) (b) (c) is a diagram showing the installation process of the bridge to install the haunting slab using a precast conventional haunch.

도 2(가)(나)(다)(라)는 종래에 헌치부가 있는 거푸집을 이용하여 헌치형 슬래브를 설치한 교량의 설치과정을 보여주는 도면.        Figure 2 (a) (b) (c) (d) is a view showing the installation process of the bridge to install the haunting slab using the formwork with the haunch conventionally.

도 3(가)(나)(다)(라)는 본 고안의 아치형 프리캐스트판넬을 이용하여 아치형 슬래브를 설치한 아치형슬래브교량의 설치과정을 보여주는 도면.        Figure 3 (a) (b) (c) (d) is a view showing the installation process of the arched slab bridge installed the arched slab using the arched precast panel of the present invention.

도 4는 본 고안의 단위아치형프리캐스트판넬을 조립한 아치형프리캐스트판넬을 보여주는 도면.        Figure 4 is a view showing an arched precast panel assembled with the unit arch type precast panel of the present invention.

도 5는 본 고안의 단위 아치형프리캐스트판넬의 연결부를 상세히 보여주는 도면.        Figure 5 is a view showing in detail the connection of the unit arcuate precast panel of the present invention.

도 6은 본 고안의 단위아치형 프리캐스트판넬을 조립하여 아치형프리캐스트판넬을 프리스트레싱 합성빔에 설치하고 콘크리트를 타설하여 아치형슬래브교량을 설치한 것을 상세히 보여주는 도면.        6 is a view showing in detail the installation of the arch arch slab bridge by assembling the unit arch type precast panel of the present invention to install the arch type precast panel to the prestressing composite beam and cast concrete.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10 : 교량 11 : 교각         10 bridge 11 bridge

12 : 슬래브 13 : 연석         12: slab 13: curb

14 : 슬래브콘크리트 15 : 프리캐스트         14: Slab Concrete 15: Precast

16 : 압축력도입부 17 : 헌치부         16: compressive force introduction portion 17: haunting portion

18 : 프리플렉스 합성빔         18: preplex composite beam

20 : 프리스트레싱 합성빔 21 : H형빔         20: prestressing composite beam 21: H-beam

22 : 복부 23 : 하부케이싱콘크리트         22: abdomen 23: lower casing concrete

30 : 교량 31 : 동바리         30: bridge 31: dongbari

32 : 거푸집          32: formwork

40 : 아치형슬래브교량 41 : 아치형슬래브         40: arched slab bridge 41: arched slab

42 : 콘크리트몰탈타설부         42: mortar of concrete mortar

50 : 아치형프리캐스트판넬 51 : 아치부         50: arch type precast panel 51: arch portion

52 : 하면 53 : 상면         52: When 53: When

54 : 수직부 55 : 철근         54: vertical part 55: reinforcing bar

56 : 와이어메쉬 57 : 홈부         56: wire mesh 57: groove

58 : 돌출부          58: protrusion

60 : 단위아치형프리캐스트판넬         60: unit arch type precast panel

70 : 연결부 71 : 전단키         70: connection portion 71: shear key

72 : 관통부 73 : 강선         72: penetrating portion 73: steel wire

Claims (7)

교각의 상부에 교량의 폭을 형성하도록 다수개의 프리스트레싱 합성빔을 설치하고, 상기 양측에 설치된 프리스트레싱 합성빔의 하부케이싱 콘크리트의 상부에 단위 아치형 프리캐스트판넬을 거치하여 슬래브의 중앙에서 전단키와 강선에 의한 연결부에 의하여 연결된 아치형 프리캐스트판넬을 설치하고, 상기 아치형 프리캐스트판넬과 프리스트레싱 합성빔의 사이에 콘크리트 몰탈 타설부를 형성하고, 슬래브를 형성할 수 있도록 전체적으로 콘크리트를 타설하여 아치형 프리캐스트 판넬과 슬래브가 일체형으로 설치되어 아치형으로 슬래브가 형성된 것에 특징이 있는 아치형슬래브설치를 위한 아치형프리캐스트판넬.        A plurality of prestressing composite beams are installed to form the width of the bridge on the upper part of the pier, and a unit arch-shaped precast panel is mounted on the lower casing concrete of the prestressing composite beams installed on both sides by a shear key and steel wire at the center of the slab. An arcuate precast panel connected by a connection part is installed, and a concrete mortar casting part is formed between the arcuate precast panel and the prestressing composite beam, and the concrete is poured to form a slab. Arched precast panel for arched slab installation characterized in that the slab is formed in the form of an arch. 제 1항에 있어서,        The method of claim 1, 상기 단위 아치형 프리캐스트판넬은 일측에 수직부를 형성하고, 상기 수직부의 상부에서 일정길이 연장된 연장부의 상면에는 일정한 간격을 두고 돌출부와 홈부를 다수개 교차형성한 아치부를 설치하되, 설치하고자 하는 교량의 아치형 슬라브를 이등분하는 길이만큼 아치부를 설치하고, 아치부가 끝나는 부분의 면에는 돌출부 및 홈부 또는 홈부 및 돌출부가 각각 형성된 전단키를 형성하고, 상기 단위아치형프리캐스트판넬이 상호 연결되는 부분의 판넬몸체에 강선을 관통하도록 한 것에 특징이 있는 아치형슬래브설치를 위한 아치형프리캐스트판넬.        The unit arc-shaped precast panel has a vertical portion formed on one side, and on the upper surface of the extended portion extending a certain length from the upper portion of the vertical portion at regular intervals, a plurality of arch portions formed by cross-protruding portions and grooves are installed, The arch part is provided in bisecting lengths of the arcuate slabs, and the front end of the arch part is formed with a shear key formed with a projection part and a groove part or a groove part and a projection part respectively, and the steel wire is formed on the panel body of the part where the unit arch type precast panel is interconnected. Arched precast panel for installation of arched slabs characterized by passing through them. 제 1항에 있어서,        The method of claim 1, 상기 콘크리트 몰탈타설부는 프리스트레싱 합성빔의 하부케이싱콘크리트 상부에 설치된 아치형프리캐스프판넬의 수직부와 상기 프리스트레싱 합성빔의 복부와의 사이에 콘크리트 몰탈을 타설한 것으로서, 아치형의 슬래브에 압축력을 도입하도록 하는 것에 특징이 있는 아치형슬래브설치를 위한 아치형프리캐스트판넬.        The concrete mortar casting part is to cast concrete mortar between the vertical part of the arch-shaped precast panel installed on the upper casing concrete of the prestressing composite beam and the abdomen of the prestressing composite beam, to introduce a compressive force to the arcuate slab. Arched precast panel for arched slab installation characterized by 제 1항에 있어서,        The method of claim 1, 상기 연결부에는 전단키와 강선에 의한 연결이 이루어지도록 한 것에 특징이 있는 아치형슬래브설치를 위한 아치형프리캐스트판넬.        The connection portion is an arched precast panel for the arched slab installation characterized in that the connection by the shear key and the steel wire is made. 제 1항에 있어서,        The method of claim 1, 상기 전단키는 좌우에서 상호 마주연결되는 아치형프리캐스트판넬의 연결부분에 형성된 것으로서, 좌우측의 단면에 돌출부 및 홈부 또는 홈부 및 돌출부가 각각 형성되도록 하여 서로 연결할 때 상기 전단키의 돌출부 및 홈부가 상호 맞물려 연결되도록 한 것에 특징이 있는 아치형슬래브설치를 위한 아치형프리캐스트판넬.        The shear key is formed in the connecting portion of the arcuate precast panel that is mutually connected from the left and right, so that the projection and the groove or the groove and the projection is formed in the left and right cross-section respectively so that the projection and the groove of the shear key are connected to each other when connected to each other. Arched precast panel for arched slab installation characterized by one. 제 1항에 있어서,        The method of claim 1, 상기 단위아치형 프리캐스트 판넬은 수직부의 하단에 철근을 설치하고, 수직부와 아치부에는 와이어메쉬를 설치한 다음 콘크리트를 타설양생하여 제작한 것에 특징이 있는 아치형슬래브설치를 위한 아치형프리캐스트판넬.        The unit arch type precast panel is installed in the reinforcing bar at the bottom of the vertical portion, the arched precast panel for the installation of the arched slab characterized in that the concrete is made by pouring concrete after installing the wire mesh on the vertical portion and the arch portion. 제 1항에 있어서,       The method of claim 1, 상기 프리스트레싱 합성빔의 하부케이싱 콘크리트 상부에 아치형 프리캐스트 판넬을 사용하는 대신에 거푸집을 아치형으로 제작설치하고, 슬래브콘크리트를 타설양생한 것에 특징이 있는 아치형슬래브설치를 위한 아치형프리캐스트판넬.        Instead of using an arched precast panel on the upper casing concrete of the pre-stressing composite beam, the arched precast panel for the installation of arched slabs characterized in that the formwork is made in the form of arches, cast slab concrete.
KR20-2005-0018084U 2005-06-23 2005-06-23 Arch-shaped precast panel for building arch-type slab KR200400109Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2005-0018084U KR200400109Y1 (en) 2005-06-23 2005-06-23 Arch-shaped precast panel for building arch-type slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2005-0018084U KR200400109Y1 (en) 2005-06-23 2005-06-23 Arch-shaped precast panel for building arch-type slab

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020050054234 Division 2005-06-23 2005-06-23

Publications (1)

Publication Number Publication Date
KR200400109Y1 true KR200400109Y1 (en) 2005-11-02

Family

ID=43701145

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2005-0018084U KR200400109Y1 (en) 2005-06-23 2005-06-23 Arch-shaped precast panel for building arch-type slab

Country Status (1)

Country Link
KR (1) KR200400109Y1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101241400B1 (en) * 2010-01-04 2013-03-12 리다산업 주식회사 Arch structure
CN110528382A (en) * 2019-09-27 2019-12-03 广州揽睿路桥设计有限公司 A kind of prestressed high-strength regenerative mixed Continuous Rigid-Frame Bridge system and construction technology

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101241400B1 (en) * 2010-01-04 2013-03-12 리다산업 주식회사 Arch structure
CN110528382A (en) * 2019-09-27 2019-12-03 广州揽睿路桥设计有限公司 A kind of prestressed high-strength regenerative mixed Continuous Rigid-Frame Bridge system and construction technology
CN110528382B (en) * 2019-09-27 2024-03-29 广州揽睿路桥设计有限公司 Prestressed high-strength regenerated mixed continuous rigid frame bridge system and construction process

Similar Documents

Publication Publication Date Title
KR100986207B1 (en) Precast psc t-type girder bridge and its construction method
KR100682794B1 (en) Manufacturing method for prestressed steel composite girder
KR101117497B1 (en) Bridge having continuous arch hybrid girders and the bridge construction method using the same
KR101329443B1 (en) Precast concrete frame and its construction method for buildings using precast concrete slab continued by post tensioning
KR200400109Y1 (en) Arch-shaped precast panel for building arch-type slab
KR100707136B1 (en) Construction method of arch-shaped slab bridge using arch-shaped precast panel for building arch-type slab
KR100544318B1 (en) Corrugated Board Type Deck Plate
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
KR100522298B1 (en) Improved prestressed steel reinforced concrete beam and bridge construction method using the same beam
KR101075756B1 (en) A manufacturing process for the Truss Half Precast Prestressed Concrete Panel
KR101216722B1 (en) Prestressed assembly block structure applying external PS force to strongly connected assembly block and construction method thereof
KR101181160B1 (en) Prestressed precast concrete beam having efficient prestressing anchorage structure
KR102325276B1 (en) Half Precast Concrete continuous slab and construction method of the same
KR101640921B1 (en) Precast Concrete Underground Box Structures for Underground Roads and Construction Method of Such Structures
JP7334948B2 (en) Culvert structure and its construction method
KR20060028828A (en) Precast concrete girder having integrated slab
KR100596072B1 (en) Composite Beam Stiffened with Prestressed Concrete Panel Having Embedded Lower Flange and Constructing Method thereof
KR100480471B1 (en) Connecting Structure and Connecting Method of Honeycomb Type Composite Beam Stiffened with Prestressed Concrete Panel
KR100580327B1 (en) PSC beam with tensioned lower flange and construction method
KR20100074741A (en) Bridge and its construction method using tide arch hybrid girders having precast slabs
KR100960386B1 (en) Girder-panel composite section type panel deck
JP2001049616A (en) Precast pc web for use in concrete bridge and prestressed concrete bridge having the pc web
JP2004270382A (en) Bridge having low girder height
JP2004011300A (en) Pc composite structure, pc bridge and prestressing method
KR200371104Y1 (en) Precast Concrete Girder Having Integrated Slab

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20081002

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20111006

Year of fee payment: 9

EXPY Expiration of term