KR20040000698A - Installing method of a prefabricated batcher plant - Google Patents
Installing method of a prefabricated batcher plant Download PDFInfo
- Publication number
- KR20040000698A KR20040000698A KR1020020035615A KR20020035615A KR20040000698A KR 20040000698 A KR20040000698 A KR 20040000698A KR 1020020035615 A KR1020020035615 A KR 1020020035615A KR 20020035615 A KR20020035615 A KR 20020035615A KR 20040000698 A KR20040000698 A KR 20040000698A
- Authority
- KR
- South Korea
- Prior art keywords
- unit
- meter
- sand
- belt conveyor
- cement
- Prior art date
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28C—PREPARING CLAY; PRODUCING MIXTURES CONTAINING CLAY OR CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28C9/00—General arrangement or layout of plant
- B28C9/002—Mixing systems, i.e. flow charts or diagrams; Making slurries; Involving methodical aspects; Involving pretreatment of ingredients; Involving packaging
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28C—PREPARING CLAY; PRODUCING MIXTURES CONTAINING CLAY OR CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28C7/00—Controlling the operation of apparatus for producing mixtures of clay or cement with other substances; Supplying or proportioning the ingredients for mixing clay or cement with other substances; Discharging the mixture
- B28C7/04—Supplying or proportioning the ingredients
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28C—PREPARING CLAY; PRODUCING MIXTURES CONTAINING CLAY OR CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28C9/00—General arrangement or layout of plant
- B28C9/02—General arrangement or layout of plant for producing mixtures of clay or cement with other materials
Landscapes
- Chemical & Material Sciences (AREA)
- Dispersion Chemistry (AREA)
- Preparation Of Clay, And Manufacture Of Mixtures Containing Clay Or Cement (AREA)
Abstract
Description
본 발명은 조립식 배처 플렌트의 설치방법에 관한 것으로, 보다 상세하게는 배처 플랜트의 각 구성요소들을 제1 유닛과 제2 유닛으로 모듈화하여 배처 플랜트를 조립식으로 설치하고, 또한 분리하여 운반할 수 있도록 한 조립식 배처 플랜트 설비에 관한 것이다.The present invention relates to a method for installing a prefabricated batcher plant, and more particularly, to modularize each component of the batcher plant into a first unit and a second unit so that the batcher plant can be prefabricated and also separated and transported. A prefabricated batcher plant facility.
배처 플랜트는 재료의 저장장치, 계량장치, 믹서, 및 혼합한 콘크리트의 배출장치 등의 기능을 결합 구성하여 레미콘을 제조하는 설비를 말하는 것이다. 여기에서 생산된 레미콘은 믹서 트럭에 담겨져서 공사현장으로 공급된다. 도 1에는 종래의 일반적인 배처 플랜트의 구조가 도시되어 있다.The batcher plant refers to a facility for manufacturing ready-mixed concrete by combining functions such as a material storage device, a metering device, a mixer, and a discharge device of mixed concrete. The ready-mixed concrete is then supplied to the construction site in a mixer truck. 1 shows the structure of a conventional general batcher plant.
도 1에서와 같이, 모래 및 자갈 등의 골재는 골재 호퍼(110)에 투입되어 골재 계량기(120)에 의해 적정량으로 계량되어 벨트 컨베이어(130)를 통해 혼합믹서(140)로 투입된다. 또한, 시멘트는 시멘트 사일로(150)에 저장되며 시멘트 계량기(160)를 통하여 혼합믹서(140)로 투입된다. 혼화제 및 물 계량기(170)를 통해서 혼합믹서(140)에 혼화제 및 물이 투입되도록 한다. 이와 같이 혼합믹서(140)에 투입된 시멘트, 골재, 혼화제 및 물 등은 서로 혼합되어 하부에 대기중인 레이콘 트럭(180)에 담겨져서 공사현장으로 이송된다.As shown in FIG. 1, aggregate such as sand and gravel is input to the aggregate hopper 110, and weighed in an appropriate amount by the aggregate meter 120, and is introduced into the mixing mixer 140 through the belt conveyor 130. In addition, the cement is stored in the cement silo 150 and introduced into the mixing mixer 140 through the cement meter 160. Admixtures and water are added to the mixing mixer 140 through the admixture and the water meter 170. In this way, the cement, aggregate, admixture, water, and the like introduced into the mixing mixer 140 are mixed with each other and are contained in the Racon truck 180 waiting at the bottom and transported to the construction site.
배처 플랜트는 큰 규모에서부터 비교적 소형 까지 다양한 형태를 갖고, 특히 비교적 소형의 것은 터널 공사등의 용도로 사용된다. 터널 공사 후 다른 터널 공사에 사용하기 위해 배처 플랜트를 작업 현장 가까이로 옮겨서 설치해야하는데, 종래의 배처 플랜트(100)는 각각의 구성 장치들이 모듈화되어 있지 않아서 해체 작업이 매우 불편하게 된다. 특히 해체 작업시에 산소 절단기를 사용하여야 하는 등 여러 불편이 있으며, 재 설치 시에도 작업시간이 많이 걸리고, 조정작업이 필요하게 된다. 또한, 전기배선은 해체시 분리한 후 재설치할 때 다시 결선하여야 하며, 대부분의 경우 흔히 사용중에 튀어나온 레미콘이 굳어서 전선을 재사용할 수 없게 되며, 이러한 경우는 전선을 새로 구입해서 배선하여야 한다. 특히 불규칙한 부피의 여러 부품들 때문에 운반상의 문제도 발생하게 된다. 따라서, 조립식으로 설치와 분해가 용이하고, 적정한 크기의 모듈타입으로 되어 있어서 운반이 또한 용이한 조립식 배처 플랜트가 요구되어 왔다.Batcher plants come in a variety of forms, from large to relatively small, especially for smaller constructions. After the tunnel construction, the batcher plant has to be moved to and installed near the work site for use in another tunnel construction. In the conventional batcher plant 100, each component is not modularized, which makes dismantling work very inconvenient. In particular, there are various inconveniences such as the use of the oxygen cutter during the dismantling operation, it takes a lot of work time even when re-installation, and adjustment work is required. In addition, electrical wiring should be reconnected when re-installed after disassembly and disassembly. In most cases, the ready-mixed concrete ready to be used cannot be reused, and in this case, a new wire must be purchased and wired. In particular, problems with transport due to various parts of irregular volume. Therefore, there has been a demand for a prefabricated batcher plant that is easy to install and disassemble in a prefabricated manner, and has a module type of an appropriate size.
또한, 조립식 배처 플랜트는 상하 2개의 직육면체형의 프레임구조물 내에 믹서, 계량기 등을 적절한 위치에 배열하고 고정하며, 프레임 구조물을 정위치시키면 믹서와 계량기 등의 위치가 자동으로 들어맞도록 구성되여야 한다. 그러나, 이러한 조립식 배처 플랜트에서 벨트 컨베이어는 상당한 길이로 형성되며, 이러한 벨트는 중간부분을 분리하거나 접어서 운반하기가 힘들기 때문에 조립식 배처 플랜트 모듈을 구성하는데 있어서 문제가 되는 것이다.In addition, the prefabricated batcher plant arranges and fixes the mixer and the meter in the proper position in the upper and lower two-sided frame structures, and when the frame structure is correctly positioned, the mixer and the meter should be configured to automatically fit. . However, in such a prefabricated batcher plant, the belt conveyor is formed to a considerable length, and such a belt is a problem in constructing a prefabricated batcher plant module because it is difficult to separate or fold and transport the middle part.
또한, 도 2에서와 같이, 종래의 배처 플랜트의 벨트 컨베이어(130)는 모래 및 자갈을 운반하는 벨트 컨베이어가 각각 구성되며, 따라서 긴 벨트 구조물이 적어도 2개 필요한 구성을 갖는다. 이러한 구조의 벨트 컨베이어를 사용하면 전체적인 배처 플랜트 설비의 모듈화가 불가능하며, 운반 및 재설치가 어렵게 되는 문제가 있다. 따라서, 벨트 컨베이어의 구성을 개선한 새로운 벨트 컨베이어를 사용한 배처 플랜트가 연구된 것이다.In addition, as shown in Figure 2, the belt conveyor 130 of the conventional batcher plant is composed of a belt conveyor for transporting sand and gravel, respectively, and thus has a configuration that requires at least two long belt structure. Using a belt conveyor of such a structure is impossible to modularize the overall batcher plant equipment, there is a problem that difficult to transport and reinstall. Therefore, the batcher plant using the new belt conveyor which improved the structure of the belt conveyor was studied.
본 발명은 상기와 같은 문제점을 해결하기 위한 것으로, 배처 플랜트에 사용되는 각종 구성요소들을 제1 유닛과 제2 유닛으로 모듈화하여 배처 플랜트 설비의 분해, 운반 및 재조립이 용이하게 될 수 있는 조립식 배처 플랜트 설비의 설치방법을 제공하는 것을 목적으로 한다.The present invention is to solve the problems as described above, by modularizing the various components used in the batcher plant into a first unit and a second unit prefabricated batcher that can be easily disassembled, transported and reassembled the batcher plant equipment It is an object to provide a method for installing plant equipment.
또한, 본 발명은 각 구성요소들을 구동시키거나 정지 및 제어신호를 인가하는 터미널 박스를 제1 유닛에 포함하여 배처 플랜트의 분해 후 재조립시에 전기배선을 간단히 할 수 있도록 하는 조립식 배처 플랜트 설치방법을 제공하는 것을 목적으로 한다.In addition, the present invention includes a terminal box for driving each component or applying a stop and control signal to the first unit, the prefabricated batcher plant installation method for simplifying the electrical wiring when disassembly and reassembly of the batcher plant The purpose is to provide.
또한 본 발명은 조립식 배처 플랜트에 사용되는 벨트 컨베이어를 제1 및 제2 벨트 컨베이어로 구분하여 사용하고 배열함으로써, 배처 플랜트 설비의 분해, 운반 및 재조립이 용이하게 되도록 하는 벨트 컨베이어를 사용하는 조립식 배처 플랜트 설치방법을 제공하는 것을 목적으로 한다.In addition, the present invention is a prefabricated batcher using a belt conveyor to facilitate the disassembly, transportation and reassembly of the batcher plant equipment by using and arranging the belt conveyor used in the prefabricated batcher plant as the first and second belt conveyor. The purpose is to provide a plant installation method.
도 1은 종래의 배처 플랜트 설비를 도시한 설치상태도이다.1 is an installation state diagram showing a conventional batcher plant equipment.
도 2는 도 1의 배처 플랜트 설비에 사용되는 벨트 컨베이어의 배열 상태를 도시한 평면도이다.2 is a plan view showing the arrangement of the belt conveyor used in the batcher plant of FIG.
도 3은 본 발명에 의한 조립식 배처 플랜트 설비를 도시한 정면도이다.3 is a front view showing a prefabricated batcher plant facility according to the present invention.
도 4는 도 3의 설비의 평면도이다.4 is a plan view of the installation of FIG. 3.
도 5는 도 3의 설비의 사시도이다.5 is a perspective view of the installation of FIG. 3.
도 6은 본 발명에 의한 제1 및 제2 유닛의 사시도이다.6 is a perspective view of the first and second units according to the present invention.
도 7은 도 6의 제1 유닛의 터미널 박스에 사용되는 분리형 전기 컨넥터의 사시도이다.FIG. 7 is a perspective view of a detachable electrical connector for use in the terminal box of the first unit of FIG. 6.
도 8은 도 6의 제2 유닛의 시멘트 계량장치에 사용되는 조인트 박스의 사시도이다.8 is a perspective view of a joint box used in the cement metering device of the second unit of FIG. 6.
도 9는 도 6의 제1 및 제2 유닛 사이에 사용되는 분리형 배관의 개념도이다.FIG. 9 is a conceptual diagram of a separate pipe used between the first and second units of FIG. 6.
도 10은 본 발명에 의한 벨트 컨베이어의 사시도이다.10 is a perspective view of a belt conveyor according to the present invention.
도 11(a) 및 도 11(b)는 본 발명에 의한 벨트 컨베이어와 프레임의 결합상태를 도시한 것이다.11 (a) and 11 (b) show the coupling state of the belt conveyor and the frame according to the present invention.
도 12는 운반트럭에 본 발명에 의한 벨트 컨베이어와 모듈화된 유닛 들이 적재된 상태를 도시한 것이다.12 illustrates a state in which a belt conveyor and modular units according to the present invention are loaded in a transport truck.
* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings
1: 조립식 배처 플랜트3: 제2 벨트 컨베이어1: prefabricated batcher plant 3: second belt conveyor
5: 제1 벨트 컨베이어7: 제1 유닛5: first belt conveyor 7: first unit
9: 제2 유닛10: 모래 및 자갈 저장호퍼9: second unit 10: sand and gravel storage hopper
20: 모래 및 자갈 계량기40: 배합믹서20: sand and gravel meter 40: mixing mixer
50: 시멘트 사일로60: 시멘트 계량기50: cement silo 60: cement gauge
70: 물 및 혼화제 계량기200: 터미널 박스70: water and admixture meter 200: terminal box
93,94: 배관220,221: 배선93, 94: pipe 220, 221: wiring
상기와 같은 목적을 달성하기 위한 구성수단으로서, 본 발명은 직육면체 형상의 프레임구조를 갖고, 배합믹서, 제1 벨트 컨베이어, 모래 및 자갈 계량기 및 이들에 전기적인 제어 및 구동신호를 보내는 터미널 박스를 포함하는 제1 유닛을 설치 위치에 고정시키는 단계; 상기 제1 유닛과 같은 크기의 직육면체 형상의 프레임구조를 갖고, 물 및 혼화제 펌프, 물 및 혼화제 계량장치, 시멘트 계량장치, 및 에어 컴프레샤를 포함하는 제2 유닛을 상기 제1 유닛 상부에 쌓는 단계; 상기 제1 유닛 및 상기 제2 유닛을 서로 볼트결합시키는 단계; 상기 제2 유닛의 전기적인 배선을 상기 제1 유닛의 터미널 박스에 연결시키고, 상기 스크류 컨베이어는 상기 시멘트 계량장치에 부착된 조인트 박스를 통하여 상기 제1 유닛의 터미널 박스와 전기적으로 연결시키며, 상기 물 및 혼화제 계량장치로 부터의 배관을 플렉시블 조인트를 통하여 제1 유닛의 배합믹서에 연결시키는 단계; 시멘트를 운송하는 스크류컨베이어를 포함하는 시멘트 사일로를 상기 제1 및 제2 유닛과 별도로 장착시키고 상기 스크류 컨베이어를 상기 제2 유닛의 시멘트 계량장치 상부에 위치시키는 단계; 및 상기 모래 및 자갈 계량기에 모래 및 자갈을 각각 공급하는 적어도 2개의 제2 벨트 컨베이어를 상기 제1 유닛의 모래 및 자갈 계량기 상부와 연결시키는 단계;를 포함하는 조립식 배처 플랜트의 설치방법을 제공한다.As a construction means for achieving the above object, the present invention has a rectangular parallelepiped frame structure, and includes a mixing mixer, a first belt conveyor, a sand and gravel meter and a terminal box for transmitting electrical control and driving signals thereto. Fixing the first unit to the installation position; Stacking a second unit having a rectangular parallelepiped frame structure having the same size as the first unit and including a water and admixture pump, a water and admixture metering device, a cement metering device, and an air compressor; Bolting the first unit and the second unit together; The electrical wiring of the second unit is connected to the terminal box of the first unit, the screw conveyor is electrically connected to the terminal box of the first unit via a joint box attached to the cement metering device, and the water And connecting the piping from the admixture metering device to the blending mixer of the first unit via a flexible joint; Mounting a cement silo comprising a screw conveyor for transporting cement separately from said first and second units and placing said screw conveyor on top of a cement metering device of said second unit; And connecting at least two second belt conveyors respectively supplying sand and gravel to the sand and gravel meter with the sand and gravel meter top of the first unit.
이하 본 발명에 대하여 첨부된 도면에 따라서 보다 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.
도 3은 본 발명에 의한 조립식 배처 플랜트 설비를 도시한 단면도이고, 도 4는 도 3의 설비의 평면도, 도 5는 도 3의 설비의 사시도이다.Figure 3 is a cross-sectional view showing a prefabricated batcher plant equipment according to the present invention, Figure 4 is a plan view of the equipment of Figure 3, Figure 5 is a perspective view of the equipment of FIG.
상기 도 3 내지 도 5에서와 같이, 직육면체 형상의 프레임(72)구조를 갖고, 프레임(72)이 또한 내측으로 설치되는 제1 유닛(7)에는 상기 프레임에 고정되며 콘크리트를 배합하는 배합믹서(40)와, 상기 배합믹서(40)에 모래 및 자갈 혼합물을 공급하는 제1 벨트 컨베이어(5)가 장착되고, 또한 상기 제1 벨트 컨베이어(5)에 모래 및 자갈을 계량 및 혼합하여 공급하는 모래 및 자갈 계량기(20)가 장착된다. 제1 유닛(7)에는 내부에 프레임(72)이 형성되어 상기 프레임(72)에 배합믹서(40)가 볼트결합에 의해 고정된다. 배합믹서(40)의 투입구 상부에는 제1 벨트 컨베이어(5)가 위치하게 된다. 상기 제1 벨트 컨베이어(5)는 일측이 상기 배합믹서(40)의 상부에 위치하며, 타측은 상기 제1 유닛(7)의 하부면 쪽으로 경사져서 위치하게 된다. 또한 상기 제1 벨트 컨베이어(5)의 타측의 상부에는 모래 및 자갈 계량기(20)가 위치하게 된다. 제1 벨트 컨베이어(5)는 보조프레임(71)들과 볼트 결합에 의해 고정되며, 상기 계량기(20)는 제1 유닛(7)의 프레임(72)에 고정된다.3 to 5, a compound mixer having a structure of a rectangular parallelepiped frame 72 and fixed to the frame and compounding concrete in the first unit 7 in which the frame 72 is also installed inwardly ( 40 and a first belt conveyor 5 for supplying a mixture of sand and gravel to the blending mixer 40, and sand for measuring and mixing sand and gravel for the first belt conveyor 5. And the gravel meter 20 is mounted. A frame 72 is formed in the first unit 7 so that the mixing mixer 40 is fixed to the frame 72 by bolting. The first belt conveyor 5 is positioned above the inlet of the mixing mixer 40. One side of the first belt conveyor 5 is positioned above the mixing mixer 40, and the other side of the first belt conveyor 5 is inclined toward the lower surface of the first unit 7. In addition, the sand and gravel meter 20 is located on the other side of the first belt conveyor (5). The first belt conveyor 5 is fixed to the auxiliary frames 71 by bolt coupling, and the meter 20 is fixed to the frame 72 of the first unit 7.
상기 제1 유닛(7)의 상부에는 상기 제1 유닛과 같은 크기의 직육면체 형상의 프레임(92) 구조를 갖고 프레임(92)이 내측으로 설치되는 제2 유닛(9)이 적층된다. 상기 제2유닛은 프레임(92)에 장착되는 시멘트 계량장치(60), 혼화제 및 물 계량장치(70)를 포함하며, 이들은 모두 상기 제1 유닛(7)에서와 마찬가지로 프레임(92)에 장착되어 있다. 상기 계량장치(60,70)로부터 계량된 물질들을 배합믹서(40)로 이송하는 통로를 이루는 이송기구(93)는 상기 제1 유닛(7)과 제2 유닛(9)의 결합후에 각각 제위치에 결합된다.On the upper part of the first unit 7, a second unit 9 having a structure of a frame 92 having a rectangular parallelepiped shape having the same size as the first unit and having the frame 92 installed therein is stacked. The second unit includes a cement metering device 60, admixture and water metering device 70 mounted to the frame 92, all of which are mounted to the frame 92 as in the first unit 7. have. The transfer mechanism 93, which forms a passage for transferring the substances metered from the metering devices 60 and 70 to the blending mixer 40, is in place after the first unit 7 and the second unit 9 are combined. Is coupled to.
상기 제1 및 제2 유닛과 별도로 시멘트를 저장 및 운송하는 시멘트 사일로(50)가 제1 및 제2 유닛과 일정거리 떨어진 위치에 설치되며, 시멘트를 운송하는 스크류 컨베이어(52)가 조립되어 시멘트 계량장치(60)로 시멘트를 이송하게 된다.A cement silo 50 for storing and transporting cement separately from the first and second units is installed at a predetermined distance from the first and second units, and a screw conveyor 52 for transporting cement is assembled to measure cement. The cement is transferred to the device 60.
상기 제1 유닛(7)의 모래 및 자갈 계량기(20)에는 적어도 2개의 제2 벨트 컨베이어(3)의 일측이 위치하게 된다. 상기 제2 벨트 컨베이어(3)는 일측이 상기와 같이 모래 및 자갈 계량기(20)의 상측에 위치하며, 타측이 하부로 경사져서 위치하고, 다시 상기 제2 벨트 컨베이어(3)의 타측 상부에는 모래 및 자갈 저장호퍼(10)가 위치하게 된다. 상기 제2 벨트 컨베이어(3)의 길이는 상기 제1 유닛(7)의 긴 방향으로의 길이보다 길지 않게 된다. 이는 벨트를 이동시킬 때 상기 제1 및 제2 유닛과 더불어 함께 운송을 할 수 있도록 하기 위함이며, 비록 제2 벨트 컨베이어(3)의 길이가 종래와 비교하여 볼 때 짧게 되나, 본 발명에서는 제1 벨트 컨베이어(5)를 상기 제1 유닛(7)에 장착함으로써 짧아진 길이를 보상하게 된다.One side of at least two second belt conveyors 3 is positioned in the sand and gravel meter 20 of the first unit 7. One side of the second belt conveyor 3 is located above the sand and gravel meter 20 as described above, and the other side is inclined downward, and again, sand and the upper portion of the second belt conveyor 3 are located on the other side of the second belt conveyor 3. Gravel storage hopper 10 is located. The length of the second belt conveyor 3 is no longer than the length of the first unit 7 in the longitudinal direction. This is to allow transport together with the first and second units when the belt is moved, although the length of the second belt conveyor 3 becomes short compared with the prior art, in the present invention the first By mounting the belt conveyor 5 to the first unit 7, the shortened length is compensated.
도 6는 본 발명에 의한 제1 및 제2 유닛의 사시도이다. 상술한 바와 같이, 본 발명에 의한 조립식 배처 플랜트의 제1 유닛(7)에는 배합 믹서(40)가 장착되며, 상기 배합믹서(40)의 상부에는 제1 벨트 컨베이어(5)가 장착되고, 또한 측부에는 모래 및 자갈 계량기(20)가 장착되어 있다. 제1 유닛(7)에는 터미널 박스(200)가 상기 모래 및 자갈 계량장치(20)의 반대쪽 측부에 장착되어 있으며, 상기 터미널 박스(200)는 전원의 공급 및 차단 기능을 수행하며, 모터 컨트롤 센터로써의 역할도 한다. 상기 터미널 박스(200)의 배선(220)은 프레임(72) 내측으로 이어져 있으며 각 구성 요소들에 연결된다. 따라서 상기와 같이 프레임 구조를 채택하고 프레임 내측으로 전기배선들이 연결되도록 하여 운반중에 전선이 결손되는 것을 방지할 수 있다.6 is a perspective view of the first and second units according to the present invention. As described above, the mixing unit 40 is mounted on the first unit 7 of the assembled batcher plant according to the present invention, and the first belt conveyor 5 is mounted on the mixing mixer 40 above. The side is equipped with a sand and gravel meter 20. In the first unit 7, a terminal box 200 is mounted on the opposite side of the sand and gravel meter 20, and the terminal box 200 performs a function of supplying and shutting off power, and a motor control center. It also plays a role. The wiring 220 of the terminal box 200 extends into the frame 72 and is connected to each component. Therefore, by adopting a frame structure as described above and by allowing electrical wires to be connected to the inside of the frame, it is possible to prevent the wires from being broken during transportation.
상기 제1 유닛(7)의 터미널 박스(200)는 조종석(도시하지 않음)과 전기적으로 연결되는데, 이는 단지 터미널 박스(200)에 관련된 전선을 연결하는 것에의해 용이하게 연결된다. 또한, 상기 제2 유닛(9)의 각 구성요소들과 연결되는 배선(221)은 도시한 바와 같이 터미널 박스 위치에 근접하도록 인출된다. 상기 제2 유닛의 배선(221)은 터미널 박스(200)의 컨넥터(210)에 연결된다. 도 7에 도시한 바와 같이 컨넥터(210)는 양측의 전선(250)이 볼트에 의해 연결고정되는 구조를 갖는다. 컨넥터(210)의 내부는 도체로 연결되어 있다. 이와 같은 컨넥터의 구조를 사용하여 터미널 박스(200)와 상기 제2 유닛의 배선(221)을 연결한다.The terminal box 200 of the first unit 7 is electrically connected to a cockpit (not shown), which is easily connected only by connecting a wire associated with the terminal box 200. In addition, the wirings 221 connected to the components of the second unit 9 are drawn to be close to the terminal box positions as shown. The wiring 221 of the second unit is connected to the connector 210 of the terminal box 200. As shown in FIG. 7, the connector 210 has a structure in which wires 250 on both sides are connected and fixed by bolts. The inside of the connector 210 is connected by a conductor. The terminal box 200 and the wiring 221 of the second unit are connected using the structure of the connector.
도 8에는 시멘트 사일로(50)의 스크류 컨베이어(52)로부터의 전선을 연결하는 조인트 박스(202)를 도시하고 있다. 조인트 박스(202)는 시멘트 계량장치(60)의일측에 부착되어 있다. 조인트 박스(202)는 시멘트의 침투로 인하여 추후에 배선을 분리하는 것이 불가능하게 될 경우를 대비하여 전체가 밀폐된 박스구조를 채택하고 있다. 상기 조인트 박스(202)의 내부는 앞서본 컨넥터(210)의 구조와 유사하다.8 shows a joint box 202 connecting wires from a screw conveyor 52 of a cement silo 50. The joint box 202 is attached to one side of the cement meter 60. The joint box 202 adopts a hermetically sealed box structure in case the cement becomes impossible to separate the wiring later. The inside of the joint box 202 is similar to the structure of the connector 210 described above.
또한, 이송기구(93)는 상기 제1 유닛(7)과 제2 유닛(9)을 통하여 서로 분리되어 있는 배관(93,94)으로 구성되며, 도 9에 도시한 바와 같은 플렉시블 조인트(270)를 사용하여 연결된다. 제2 유닛의 배관(94)은 물탱크(75) 및 혼화제탱크(76)와 연결된 물 및 혼화제 계량장치(70)에 각각 연결된 것이다. 또한 제1 유닛의 배관(93)은 배합믹서(40)와 연결되어 있으며, 이러한 배관들은 각 유닛의 결합시에 플렉시블 조인트(270)를 통하여 연결된다. 플렉시블 조인트(270)는 유연한 관과 양끝단에 플렌지를 갖는 구조이다.In addition, the transfer mechanism 93 is composed of pipes 93 and 94 separated from each other through the first unit 7 and the second unit 9, and the flexible joint 270 as shown in FIG. Is connected using. The pipe 94 of the second unit is connected to the water and admixture metering device 70 connected to the water tank 75 and the admixture tank 76, respectively. In addition, the pipe 93 of the first unit is connected to the mixing mixer 40, these pipes are connected through the flexible joint 270 at the time of coupling of each unit. The flexible joint 270 has a flexible pipe and a flange at both ends.
도 10은 본 발명에 의한 벨트 컨베이어의 사시도이고, 도 11(a) 및 도 11(b)는 본 발명에 의한 벨트 컨베이어와 프레임의 결합상태를 도시한 것이다. 도 10에서, 벨트(33)는 모터(32)의 구동에 의해 운동한다. 모터(32)는 벨트의 상부에 장착되어 있으며, 모터(32)로부터의 구동력은 벨트-풀리조합(34)에 의해 하부의 구동축(36)으로 전달되어 벨트(33)를 움직이게 된다. 이러한 구조는 상기 제1 벨트 컨베이어(5) 및 제2 벨트 컨베이어(3)에 모두 적용된다. 또한, 상기 제2 벨트 컨베이어(3)는 적어도 2개이상이다. 이는 모래 및 자갈을 각각 운송하기 위함이며, 모래 및 자갈은 제2 벨트 컨베이어(3)의 끝단에서 계량기(20)로 들어가서 합쳐지게 되며, 하나의 제1 벨트 컨베이어(5)를 통해서 배합믹서(40)에 전달된다.Figure 10 is a perspective view of the belt conveyor according to the present invention, Figure 11 (a) and Figure 11 (b) shows a coupled state of the belt conveyor and the frame according to the present invention. In FIG. 10, the belt 33 moves by driving the motor 32. The motor 32 is mounted on the upper part of the belt, and the driving force from the motor 32 is transmitted to the lower drive shaft 36 by the belt-pull combination 34 to move the belt 33. This structure applies to both the first belt conveyor 5 and the second belt conveyor 3. The second belt conveyor 3 is at least two in number. This is to transport sand and gravel, respectively, sand and gravel enters the meter 20 at the end of the second belt conveyor (3) and is combined, and through the first belt conveyor (5) mixing mixer (40) Is delivered).
도 11(a)는 결합수단(42)을 사용하여 제2 벨트 컨베이어(3)와 제1 유닛(7)의 프레임(72)을 연결한 상태를 도시하고 있다. 결합수단(42)은 프레임(72)과 밀착되고 볼트(41)가 결합되는 관통홀이 형성되어 있는 부분과 상기 제2 벨트 컨베이어(3)와 밀착되고 또한 다수개의 볼트구멍이 형성되어 벨트 컨베이어 프레임과 결합되는 부분으로 구성된다. 상기 결합수단(42)은 소정의 각도로 절곡되어 있으며, 상기 각도는 제2 벨트 컨베이어(3)가 형성하는 각도와 일치하게 된다.FIG. 11 (a) shows a state in which the second belt conveyor 3 and the frame 72 of the first unit 7 are connected by using the coupling means 42. Coupling means 42 is in close contact with the frame 72, the through-hole is formed in which the bolt 41 is coupled and the second belt conveyor 3 in close contact with the plurality of bolt holes are formed to form a belt conveyor frame It is composed of a part combined with. The coupling means 42 is bent at a predetermined angle, the angle of which coincides with the angle formed by the second belt conveyor 3.
도 11(b)는 지지프레임(43)에 의해 제2 벨트 컨베이어(3)가 장착된 상태를 도시하고 있다. 상기 지지프레임(43)은 제1 유닛(7)의 프레임(72)과 일체로 또는 별도로 형성될 수 있으며, 소정의 각도로 상향 절곡되어 있다. 상기 각도는 제2 벨트 컨베이어(3)가 형성하는 각도와 일치하며, 볼트로 상호 결합하거나 또는 다른 보조 결합부재(45)를 사용하여 결합될 수 있다.FIG. 11 (b) shows a state in which the second belt conveyor 3 is mounted by the support frame 43. The support frame 43 may be formed integrally with or separately from the frame 72 of the first unit 7 and is bent upward at a predetermined angle. The angle coincides with the angle formed by the second belt conveyor 3 and may be coupled to each other by bolts or by using another auxiliary coupling member 45.
도 11(c)는 다른 결합수단(47)을 사용하여 제2 벨트 컨베이어(3)와 제1 유닛의 프레임(72)를 연결한 상태를 도시하고 있다. 결합수단(47)은 프레임(72)의 모서리에 일체로 형성되거나 또는 별개로 형성되어 부착되고, 벨트 컨베이어(3)를 지지하는 플레이트 또는 지지부재를 포함하게 된다. 상기 결합수단(47)은 가운데가 핀결합을 이루게 되어 벨트 컨베이어의 설치각도에 따라서 같은 각도로 지지할 수 있도록 되어 있다.FIG. 11 (c) shows a state in which the second belt conveyor 3 is connected to the frame 72 of the first unit by using another coupling means 47. The coupling means 47 is integrally formed at the edge of the frame 72 or separately formed and attached, and includes a plate or a supporting member for supporting the belt conveyor 3. The coupling means 47 is to form a pin coupling in the middle to support the same angle according to the installation angle of the belt conveyor.
도 12는 운반트럭에 본 발명에 의한 벨트 컨베이어와 모듈화된 유닛 들이 적재된 상태를 도시한 것이다. 본 발명에 의한 제1 벨트 컨베이어는 제1 유닛(7) 내에 장착되고, 또한 제2 벨트 컨베이어(3)는 그 길이가 제1 유닛(7)의 길이보다 길지 않기 때문에 트럭 등의 운송수단을 통해 동시에 운반이 가능하게 된다.12 illustrates a state in which a belt conveyor and modular units according to the present invention are loaded in a transport truck. The first belt conveyor according to the invention is mounted in the first unit 7, and also because the length of the second belt conveyor 3 is not longer than that of the first unit 7. At the same time transport is possible.
상술한 바와 같은 조립식 배처 플랜트의 설치방법에 대하여 설명하면 다음과 같다. 먼저, 직육면체 형상의 프레임구조를 갖고, 배합믹서, 제1 벨트 컨베이어, 모래 및 자갈 계량기 및 이들에 전기적인 제어 및 구동신호를 보내는 터미널 박스를 포함하는 제1 유닛을 설치 위치에 고정시킨다. 그후, 상기 제1 유닛과 같은 크기의 직육면체 형상의 프레임구조를 갖고, 물 및 혼화제 탱크, 시멘트 계량장치, 혼화제 계량장치, 및 물 계량장치를 포함하는 제2 유닛을 상기 제1 유닛 상부에 쌓게 된다.Referring to the installation method of the prefabricated batcher plant as described above is as follows. First, a first unit having a rectangular parallelepiped frame structure and including a compounding mixer, a first belt conveyor, a sand and gravel meter, and a terminal box for transmitting electrical control and driving signals thereto is fixed at an installation position. Thereafter, a second unit having a rectangular parallelepiped frame structure of the same size as the first unit and including a water and admixture tank, a cement metering device, a admixture metering device, and a water metering device is stacked on top of the first unit. .
다음은, 상기 제1 유닛 및 상기 제2 유닛을 서로 볼트결합시키고, 상기 제2 유닛의 전기적인 배선을 상기 제1 유닛의 터미널 박스에 연결시키며, 상기 스크류 컨베이어는 상기 시멘트 계량장치에 부착된 조인트 박스를 통하여 상기 제1 유닛의 터미널 박스와 전기적으로 연결시키고, 상기 물 및 혼화제 계량장치로 부터의 배관을 플렉시블 조인트를 통하여 제1 유닛의 배합믹서에 연결시키게 된다.Next, the first unit and the second unit are bolted together, and the electrical wiring of the second unit is connected to the terminal box of the first unit, and the screw conveyor is a joint attached to the cement metering device. The box is electrically connected to the terminal box of the first unit, and the pipe from the water and admixture metering device is connected to the blending mixer of the first unit through a flexible joint.
그 후 시멘트를 운송하는 스크류 컨베이어를 포함하는 시멘트 사일로를 상기 제1 및 제2 유닛과 별도로 장착시키고 상기 스크류 컨베이어를 상기 제2 유닛의 시멘트 계량장치 상부에 위치시키며, 상기 모래 및 자갈 계량기에 모래 및 자갈을 각각 공급하는 적어도 2개의 제2 벨트 컨베이어를 상기 제1 유닛의 모래 및 자갈 계량기 상부와 연결시켜서 배처 플랜트를 설치하게 된다.A cement silo comprising a screw conveyor for transporting cement is then mounted separately from the first and second units and the screw conveyor is placed on top of the cement metering device of the second unit, and sand and At least two second belt conveyors, each supplying gravel, are connected to the sand and gravel meter top of the first unit to install the batcher plant.
상기와 같은 조립식의 배처 플랜트의 분해는 상기 순서의 역순으로 행하게되면 가능하게 된다.The disassembly of the prefabricated batcher plant can be performed by performing the reverse order.
상술한 바와 같은 본 발명에 따른 조립식 배처 플렌트의 작동을 도면을 참조하여 설명하면 다음과 같다.The operation of the prefabricated batcher plant according to the present invention as described above with reference to the drawings as follows.
모래 및 자갈 호퍼(10)에서 투입된 모래 및 자갈들은 각각 제2 벨트 컨베이어(3)를 통해 모래 및 자갈 계량기(20)로 이동하게 된다. 상기 계량기(20)에서 모래 및 자갈은 합쳐져서 제1 벨트 컨베이어(5)에 옮겨지게 되며, 제1 벨트 컨베이어(5)는 상기 모래 및 자갈 혼합물을 배합믹서(40)로 운송하게 된다. 또한, 시멘트 사일로(50)를 통해 시멘트가 시멘트 계량기(60)로 운송되며, 상기 계량기(60)를 통해 배합믹서(40)로 시멘트가 투입되며, 물 및 혼화제 역시 상기와 같은 방법으로 계량기(70)를 통해 배합믹서(40)에 투입된다. 배합믹서(40)는 각 투입물질을 배합하여 레미콘 트럭에 전달하게 된다.Sand and gravel introduced from the sand and gravel hopper 10 are respectively moved to the sand and gravel meter 20 through the second belt conveyor (3). In the meter 20, sand and gravel are combined and transferred to the first belt conveyor 5, and the first belt conveyor 5 transports the sand and gravel mixture to the blending mixer 40. In addition, the cement is transported to the cement meter 60 through the cement silo 50, the cement is introduced into the blending mixer 40 through the meter 60, and the water and the admixture are also metered in the same manner as described above. Into the blending mixer 40 through). The mixing mixer 40 mixes each input material and delivers the mixed material to the ready-mixed truck.
상기와 같은 작동을 위하여, 제1 유닛(7)과 제2 유닛(9) 및 제2 벨트 컨베이어(3)와 시멘트 사일로(50)가 서로 전기적으로 뿐만아니라 그 상호간 위치 역시 정확하게 연결되어야 한다. 이를 위하여 제1 유닛과 제2 유닛의 전기배선은 터미널 박스(200)에 연결되며, 제1 유닛과 제2 유닛은 통상적인 결합방식인 볼트 결합을 통하여 서로 결합된다. 또한 시멘트 사일로(50)는 상기 유닛들과 별도로 설치되며, 스크류 컨베이어를 제2 유닛과 저장호퍼(50) 사이에 서로 연결하게 된다. 제2 벨트 컨베이어(3)는 제1 유닛(5)의 일측면, 즉 모래 및 자갈 계량장치(20)의 상부에 일 끝단이 위치하도록 장착된다.For this operation, the first unit 7 and the second unit 9 and the second belt conveyor 3 and the cement silo 50 must not only be electrically connected to each other, but also their mutual positions must be correctly connected. To this end, the electrical wiring of the first unit and the second unit is connected to the terminal box 200, and the first unit and the second unit are coupled to each other through bolt coupling, which is a conventional coupling method. In addition, the cement silo 50 is installed separately from the units, and connects the screw conveyor between the second unit and the storage hopper 50. The second belt conveyor 3 is mounted such that one end is positioned on one side of the first unit 5, that is, the top of the sand and gravel meter 20.
이상과 같이 본 발명의 조립식 배처 플랜트에 의하면, 배처 플랜트에 사용되는 각종 구성요소들을 제1 유닛과 제2 유닛으로 모듈화하여 배처 플랜트 설비의 분해, 운반 및 재조립이 용이하게 될 수 있는 조립식 배처 플랜트 설비를 제공할 수 있다.As described above, according to the prefabricated batcher plant of the present invention, the prefabricated batcher plant which can be easily disassembled, transported and reassembled in the batcher plant by modularizing various components used in the batcher plant into the first unit and the second unit. Facilities can be provided.
또한 본 발명에 의하면 각 구성요소들을 구동시키거나 정지 및 제어신호를 인가하는 터미널 박스를 제1 유닛에 포함하여 배처 플랜트의 분해 후 재조립시에 전기배선을 간단히 할 수 있게 되며, 배선이 시멘트 등의 다른 물질에 의하여 오염되거나 굳게 되는 현상을 줄일 수 있으며, 운반을 위한 분해작업시 전선을 절단하지 않고도 운반을 할 수 있는 효과가 있다.In addition, according to the present invention includes a terminal box for driving each component or applying a stop and control signal to the first unit to simplify the electrical wiring during disassembly and reassembly of the batcher plant, the wiring is cement, etc. It is possible to reduce the phenomenon of contamination or hardening by other materials, and the transport can be carried out without cutting the wires during disassembly for transport.
본 발명은 특정한 실시예에 관련하여 도시하고 설명하였지만, 이하의 특허청구범위에 의해 마련되는 본 발명의 정신이나 분야를 벗어나지 않는 한도 내에서 본 발명이 다양하게 개조 및 변화될 수 있다는 것을 당업계에서 통상의 지식을 가진 자는 용이하게 알 수 있음을 밝혀두고자 한다.While the invention has been shown and described with respect to particular embodiments, it will be understood that various changes and modifications can be made in the art without departing from the spirit or scope of the invention as set forth in the claims below. It will be appreciated that those skilled in the art can easily know.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020020035615A KR20040000698A (en) | 2002-06-25 | 2002-06-25 | Installing method of a prefabricated batcher plant |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020020035615A KR20040000698A (en) | 2002-06-25 | 2002-06-25 | Installing method of a prefabricated batcher plant |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20040000698A true KR20040000698A (en) | 2004-01-07 |
Family
ID=37312521
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020020035615A KR20040000698A (en) | 2002-06-25 | 2002-06-25 | Installing method of a prefabricated batcher plant |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20040000698A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101220163B1 (en) * | 2010-06-18 | 2013-01-11 | 미래이엔씨주식회사 | Mixing device for lightweight concrete and concrete construction device comprising it |
KR101583522B1 (en) * | 2014-09-04 | 2016-01-19 | 최은주 | System of investigation watching ratio in IPTV using WiFi and smartphone |
CN109676798A (en) * | 2019-01-03 | 2019-04-26 | 中联重科股份有限公司 | Control method and control system for concrete PC mixing station |
CN110744707A (en) * | 2019-10-30 | 2020-02-04 | 黑龙江兰德超声科技股份有限公司 | Material system is failed in compound cast material coupling stirring |
-
2002
- 2002-06-25 KR KR1020020035615A patent/KR20040000698A/en not_active Application Discontinuation
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101220163B1 (en) * | 2010-06-18 | 2013-01-11 | 미래이엔씨주식회사 | Mixing device for lightweight concrete and concrete construction device comprising it |
KR101583522B1 (en) * | 2014-09-04 | 2016-01-19 | 최은주 | System of investigation watching ratio in IPTV using WiFi and smartphone |
CN109676798A (en) * | 2019-01-03 | 2019-04-26 | 中联重科股份有限公司 | Control method and control system for concrete PC mixing station |
CN110744707A (en) * | 2019-10-30 | 2020-02-04 | 黑龙江兰德超声科技股份有限公司 | Material system is failed in compound cast material coupling stirring |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212096940U (en) | Integrated folding foundation-free concrete mixing station and frame thereof | |
CN101391459A (en) | Detachable mobile mixing station capable of loading in container | |
KR20040000698A (en) | Installing method of a prefabricated batcher plant | |
KR20120010663A (en) | Concrete batch plant | |
KR200292640Y1 (en) | A prefabricated batcher plant | |
KR200292639Y1 (en) | A belt conveyor of a prefabricated batcher plant | |
CN111975989A (en) | Concrete processingequipment for construction | |
KR100744193B1 (en) | Portable concrete manufacturing apparatus | |
CN107150414B (en) | Traction type commercial concrete mixing station | |
CN201604215U (en) | Movable mixing plant capable of being detached and loaded in container | |
KR200345507Y1 (en) | Portable concrete batch plant | |
CN113246300A (en) | Integrated concrete mixing plant convenient to assemble and carry | |
CN206170350U (en) | Compact stabilized soil stirring station | |
CN107225690A (en) | A kind of concrete mixing plant batching plant | |
KR101162239B1 (en) | concrete mix apparatus reducing cost of plant, install and drive | |
CN210791538U (en) | Complete production equipment for desulfurized gypsum dry-mixed mortar | |
CN219114413U (en) | Quick assembly disassembly modularization concrete mixing plant | |
CN216941302U (en) | Concrete mixing plant system | |
JP2001225319A (en) | Manufacturing device for civil engineering work material containing coal ash as main raw material | |
CN1079316C (en) | Mobile batching plant | |
JP6550430B2 (en) | Concrete mixing unit | |
CN111283879B (en) | Exempt from basis multi-direction and put bayonet oblique belt stirring station | |
KR200432529Y1 (en) | Batcher plant | |
CN208343172U (en) | Mixing plant and prefabricated components production line | |
JP3246884B2 (en) | silo |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
WITN | Withdrawal due to no request for examination |