KR200304413Y1 KR20-2002-0031243U KR20020031243U KR200304413Y1 KR 200304413 Y1 KR200304413 Y1 KR 200304413Y1 KR 20020031243 U KR20020031243 U KR 20020031243U KR 200304413 Y1 KR200304413 Y1 KR 200304413Y1
Authority
KR
South Korea
Prior art keywords
plate
index plate
concrete
buffer
support plate
Prior art date
Application number
KR20-2002-0031243U
Other languages
Korean (ko)
Inventor
김병수
Original Assignee
김병수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김병수 filed Critical 김병수
Priority to KR20-2002-0031243U priority Critical patent/KR200304413Y1/en
Application granted granted Critical
Publication of KR200304413Y1 publication Critical patent/KR200304413Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

본 고안은 수로나 옹벽 등과 같은 콘크리트 구조물의 시공시 계절변화에 따른 구조물의 신축에 대응하기 위한 완충부를 일정한 간격마다 설치하되, 상기 완충부에 시공되는 지수판의 개량에 관한 것으로서, 특히 시공이 간편하고 편리하면서 시공시 변형이 없고, 또한 누수현상을 방지할 수 있도록 한 것이다.The present invention is to install a buffer unit at regular intervals to cope with the expansion and contraction of the structure according to the seasonal changes in the construction of concrete structures such as waterways or retaining walls, and relates to the improvement of the index plate to be constructed in the buffer unit, in particular easy to construct It is convenient and there is no deformation during construction, and it is to prevent leakage phenomenon.

상기 목적을 달성하기 위하여 본 고안은 콘크리트 구조물 시공시 완충부에 설치되는 지수판(20)을 구성하되, 요철부(21)가 형성된 본체(22)중앙에 타원형 중공체(23)를 구성하고, 상기 타원형 중공체(23)의 단부양측에 지지판(240을 수직방향으로 돌출구성하므로서 상기 지수판(20)의 사용시 지수판(20)에 구성된 지지판(24)을 이용하여 지수판(20)이 거푸집상에 고정되게 하고, 동시에 완충고무편(50)이 지지판(20) 일측에 접착되게 하므로서 거푸집사이에 콘크리트 타설시 지수판(20)의 위치가 변형되지 않게 한 것이다.In order to achieve the above object, the present invention constitutes an index plate 20 installed in a buffer part when constructing a concrete structure, and an elliptical hollow body 23 is formed in the center of the main body 22 on which the uneven part 21 is formed. The support plate 240 protrudes in the vertical direction on both ends of the elliptical hollow body 23, so that the water plate 20 is fixed on the formwork by using the support plate 24 formed on the water plate 20 when the water plate 20 is used. At the same time, the buffer rubber piece 50 is bonded to one side of the support plate 20 so that the position of the index plate 20 is not deformed when the concrete is placed between the formwork.

Description

콘크리트 구조물 시공을 위한 지수판{Board lceeping off water for concrete construction}Board lceeping off water for concrete construction

본 고안은 주로 수로나 옹벽 등과 같은 콘크리트 구조물을 시공함에 있어서, 일정한 간격마다 완충부를 구성하여 계절변화에 따른 콘크리트 구조물의 신축에 대한 완충기능을 하여 견고한 시공이 이루어질 수 있게 하는 콘크리트 구조물의 시공을 위한 지수판에 관한 것이다.The present invention is mainly for the construction of concrete structures, such as waterways or retaining walls, for the construction of concrete structures to make a solid construction by buffering the expansion and contraction of the concrete structure according to the seasonal change by configuring the buffer unit at regular intervals It's about the index plate.

일반적으로 수로나 옹벽 등과 같이 길게 구성된 콘크리트 구조물은 계절변화에 따른 신축현상이 일어나게 되며, 상기 신축현상에 대응하여 완충기능을 위한 완충부를 일정한 간격마다 시공하고 있다.In general, a long structure concrete structure such as a waterway or retaining wall is caused by the expansion and contraction of the seasonal change, and in response to the expansion phenomenon, the buffer unit for the buffer function is constructed at regular intervals.

다시 설명하면 일정한 간격마다 신축에 대한 완충역할이 가능한 완충부를 구성하되, 상기 완충부를 통하여 누수현상이 발생하지 않게 하기 위하여 합성수지로 구성된 지수판을 설치하여 완충부가 구성되게 하고 있다.In other words, a buffer unit capable of acting as a buffer for expansion and contraction at regular intervals is provided, but a buffer plate is formed by installing an index plate made of synthetic resin in order to prevent leakage from occurring through the buffer unit.

종래 시공되고 있는 완충부는 다음과 같이 구성된다.The buffer part conventionally constructed is comprised as follows.

즉 도13 및 도14에서와 같이 수로나 옹벽설치를 위한 벽체를 시공하기 위하여 거푸집(110)을 설치하되, 완충부(100)가 설치되는 부분에 지수판(120)을 설치하고, 상기 지수판(120)의 좌우측에 합성고무로된 완충고무편(130)을 고정하고, 상기한 상태에서 거푸집(110)내에 콘크리트 몰탈을 타설하게 된다.That is, as shown in FIGS. 13 and 14, the formwork 110 is installed in order to construct a wall for installing a waterway or a retaining wall, but the water stop plate 120 is installed at a portion where the buffer part 100 is installed, and the water stop plate 120 is provided. Fixed rubber piece 130 made of synthetic rubber on the left and right sides of the), and the concrete mortar is poured into the formwork 110 in the above state.

상기 콘크리트 몰탈 타설시 지수판(120)의 양측에 구성되는 완충고무편(130)의 고정수단이 없기때문에 못(140)으로 고정하고 있다.Since there is no fixing means of the buffer rubber piece 130 formed on both sides of the index plate 120 when the concrete mortar is poured, it is fixed by the nail 140.

다시 설명하면 완충고무편(130)을 지수판(120)에 고정하기 위하여 일측 완충고무편(130)을 지수판(120)의 중앙에 구성된 타원형 중공체(121) 일측에 위치시킨 다음 타원형 중공체(121)의 타측에서 못(140)을 박아 못(140)이 타원형 중공체(121)을 관통하여 일측에 위치한 완충고무편(130)에 박혀지게 하므로서 일측 완충고무편(130)이 고정되게 한다.In other words, in order to fix the shock absorbing rubber piece 130 to the index plate 120, one buffer rubber piece 130 is positioned at one side of the elliptical hollow body 121 formed at the center of the index plate 120, and then the elliptical hollow body 121 is provided. The nail 140 is driven from the other side of the nail so that the nail 140 penetrates the elliptical hollow body 121 and is embedded in the buffer rubber piece 130 located at one side, thereby fixing one buffer rubber piece 130.

다시 타원형 중공체(121)의 타측에 또 다른 완충고무편(130)을 위치시킨 다음 거푸집(110) 바깥쪽에서 못(140)을 박아 완충고무편(130)이 지수판(120)의 타원형 중공체(121) 양측부에 고정되게 한 다음 거푸집(110)사이에 콘크리트를 타설하여 콘크리트 구조물을 시공하고 있다.Another buffer rubber piece 130 is placed on the other side of the elliptical hollow body 121, and then the nail 140 is driven from the outside of the formwork 110 so that the buffer rubber piece 130 is the elliptical hollow body of the index plate 120. 121) and then fixed to both sides and then cast concrete between the mold (110) to construct a concrete structure.

따라서 상기한 구성의 콘크리트 구조물을 시공한 후 거푸집(110)을 제거하게 되면 콘크리트 구조물의 일정한 간격마다 지수판(120)과 완충고무편(130)이 형성된 완충부(100)가 구성되게 하므로서 계절변화에 따른 콘크리트 구조물의 신축시 지수판(120)과 완충고무편(130)이 이를 흡수하여 구조물의 손상을 방지케 하고 있다.Therefore, when the formwork 110 is removed after the construction of the concrete structure of the above configuration, the buffer plate 100 formed with the index plate 120 and the buffer rubber piece 130 is formed at regular intervals of the concrete structure to change the season When the expansion of the concrete structure according to the index plate 120 and the buffer rubber piece 130 to absorb this to prevent damage to the structure.

즉 여름철과 같이 기온이 높을 경우에는 구조물이 어느정도 확장하게 되고이때 완충부(100)에 구성된 지수판(120)의 타원형 중공체(121) 및 완충고무편(130)이 압축되면서 콘크리트 구조물의 확장을 흡수하게 되고, 반대로 겨울철과 같이 기온이 떨어지게 되면 구조물은 수축하게 되나 지수판(120)에 구성된 타원형 중공체(121) 및 완충고무편(130)이 늘어나면서 구조물의 수축에 대한 충격을 흡수하게 된다.That is, when the temperature is high, such as in summer, the structure is expanded to some extent, and at this time, the elliptical hollow body 121 and the buffer rubber piece 130 of the index plate 120 configured in the buffer part 100 are compressed to absorb the expansion of the concrete structure. On the contrary, when the temperature drops, such as in winter, the structure contracts, but the elliptical hollow body 121 and the buffer rubber piece 130 formed on the index plate 120 are stretched to absorb the impact of the contraction of the structure.

또한 상기 완충부(100)에는 지수판(120)이 길이 방향으로 길게 구성되면서 완충부 설치에 따른 누수현상을 방지케 하고 있다.In addition, the buffer plate 100 is configured to prevent the leakage phenomenon due to the installation of the buffer portion while the index plate 120 is formed in the longitudinal direction.

그러나 상기한 구성의 시공장치는 다음과 같은 문제가 있는 것이었다.However, the factory setting of the above-described configuration had the following problems.

즉 콘크리트 타설시 지수판(120)의 좌우측에 못으로 고정설치된 완충고무편(130)과 지수판(120)의 체결을 위한 별도의 수단이 제공되고 있지 않기 때문에 콘크리트 타설시 지수판(120) 및 완충고무편(130)의 위치가 틀어질 우려가 높고 상기에서와 같이 틀어진 상태에서 콘크리트가 양생, 시공이 되면 완충부로서의 역할을 기대하기가 어렵게될 뿐 아니라 지수판(120) 및 완충고무편(130)의 설치작업도 어려운 등의 단점이 있는 것이었다.That is, when concrete is placed, a separate means for fastening the buffer rubber piece 130 fixed to the left and right sides of the index plate 120 and the index plate 120 is not provided. If there is a high risk that the position of the 130 is wrong and the concrete is cured and constructed in the same state as described above, it becomes difficult to expect a role as a buffer part, as well as the installation of the index plate 120 and the buffer rubber piece 130 The work was also difficult and had the disadvantages.

또한 상기한 구성으로 구조물의 시공완료 후에도 지수판(120)과 일측 완충고무편(130)을 고정하기 위하여 타원형 중공체(121)를 관통한 못(140)은 제거하지 못하게 되고, 따라서 상기 못구멍을 통하여 누수되는 현상이 발생하게될 뿐 아니라 못으로부터 발생하는 녹물이 외벽으로 흘러내리게 되므로 외관이 미려치 못한 등의 문제점이 있는 것이었다.In addition, the nail 140 penetrating through the elliptical hollow body 121 to fix the index plate 120 and the one-side buffer rubber 130 even after the completion of the construction of the structure can not be removed, and thus the nail hole Not only will the leakage occur, but the green water generated from the nails will flow down to the outer wall, so the appearance was not beautiful.

본 고안은 이러한 종래의 제반 문제점을 시정하고자 수로나 옹벽과 같은 콘크리트 구조물을 시공함에 있어서, 일정한 간격마다 형성되는 완충부의 지수판 및 완충고무편의 설치가 못을 사용하지 않고도 견고하게 지지되게 함과 동시에 시공 후에도 완벽한 누수방지는 물론, 지수판 및 완충고무판의 틀어짐으로 인한 불량시공을 방지할 수 있게 구성한 것이다.The present invention, in order to correct the problems of the prior art in the construction of concrete structures such as waterways or retaining walls, while the installation of the water stop plate and the buffer rubber pieces formed at regular intervals to be firmly supported without using nails Even after the perfect leak prevention, it is configured to prevent poor construction due to the distortion of the index plate and the buffer rubber plate.

상기 목적을 달성하기 위하여 본 고안은 수로나 옹벽과 같은 콘크리트 구조물 시공시 완충부에 설치되는 지수판을 구성하되, 지수판 중앙 양측부에 지지판을 돌출 구성하여 거푸집 설치시 지수판 양측에 돌출 구성된 지지판이 거푸집 사이에 끼워져 고정되게 하고, 동시에 지수판 양측에 설치되는 완충 고무편은 지지판 일측에 접착고정될 수 있게 하여 완충고무편의 견고한 지지가 이루어질 수 있게 한 것이다.In order to achieve the above object, the present invention constitutes an index plate installed in a buffer part when constructing a concrete structure such as a waterway or a retaining wall, and a support plate protruding on both sides of the index plate is formed between the formwork by protruding a support plate at both sides of the center plate. To be fixed to the cushioning, and at the same time the cushioning rubber piece is installed on both sides of the index plate is to be fixed to one side of the support plate to enable a solid support of the cushioning rubber piece.

상기 본 고안에서 제공하고자 하는 지수판을 구성함에 있어서, 양측으로 돌출 구성된 지지판 이외에 별도의 보조지지판이 돌출구성되게 하여 그 사이에 삽입이부가 형성되게 하고, 상기 삽입부에 완충고무편이 끼워져 접착고정되게 할 수도 있다.In constructing the index plate to be provided in the present invention, in addition to the support plate is configured to protrude on both sides to the additional auxiliary support plate to be formed so that the insertion is formed therebetween, the cushioning rubber piece is inserted into the insert portion to be fixed It may be.

상기한 구성의 지수판은 합성수지로 압출 성형한 다음 구조물 시공시 지지판부분의 필요한 부위를 절개 또는 절단하여 사용하게 된다.The index plate of the above configuration is extruded from synthetic resin and then used to cut or cut a required portion of the support plate portion during construction of the structure.

도 1 : 본 고안의 사시도.1: a perspective view of the present invention.

도 2 : 본 고안 지수판을 수로 시공시 사용하기 위하여 지지판의 일부를 재단한 상태사시도.Figure 2 is a state perspective view of a part of the support plate cut for use in construction of the present invention index plate.

도 3 : 도2의 지수판을 절첩한 상태사시도.Figure 3 is a perspective view of the folded state plate of Figure 2.

도 4 : 본 고안 지수판을 이용하여 수로 시공을 위한 거푸집 설치상태도로서 요부구성도.4 is a main configuration diagram as a formwork installation state diagram for waterway construction using the present invention index plate.

도 5 : 도4의 확대구성도.5 is an enlarged configuration diagram of FIG. 4.

도 6 : 도5의 상태에서 콘크리트를 타설한 상태도.6 is a state diagram in which concrete is poured in the state of FIG.

도 7 : 도6의 확대상태도.7 is an enlarged state diagram of FIG. 6.

도 8 : 도6의 상태에서 거푸집을 제거한 상태도.8 is a state in which the formwork is removed in the state of FIG.

도 9 : 본 고안을 이용하여 수로 시공을 위한 거푸집 설치상태도.9 is a formwork installation state for waterway construction using the present invention.

도 10 : 도9의 상태에서 콘크리트를 타설한 상태도.10 is a state diagram poured concrete in the state of FIG.

도 11 : 본 고안 지수판의 타실시에의 사시도.11 is a perspective view of another embodiment of the present invention index plate.

도 12 : 도11의 사용상태도.12 is a state diagram used in FIG.

도 13 : 종래 지수판의 사시도.13 is a perspective view of a conventional index plate.

도 14 : 종래 지수판의 사용상태도.14 is a state diagram used in the conventional index plate.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

(10)--완충부 (20)--지수판(10)-buffer (20)-index

(21)--요철부 (22)--본체(21)-Uneven (22)-Body

(23)--타원형 중공체 (24)--지지판(23)-Elliptical Hollow Body (24)-Support Plate

(25)--절단부 (26)--절개부(25)-cuts (26)-cuts

이하 본 고안의 실시예를 첨부도면에 따라 상세히 설명하면 다음과 같다.Hereinafter, an embodiment of the present invention will be described in detail with reference to the accompanying drawings.

도1은 본 고안 장치 즉 완충부(10)에 사용되는 지수판(20)의 사시도이고,도2는 절첩부위는 절단한 상태이며, 도3은 상기 지수판(20)을 수로의 완충부(10)에 시공하기 위하여 절첩한 상태의 사시도이다.Figure 1 is a perspective view of the water stop plate 20 used in the present invention device, that is, the buffer portion 10, Figure 2 is a state in which the folded portion is cut, Figure 3 is the water stop plate 20 in the buffer portion 10 of the channel It is a perspective view of the state folded in in order to construct.

상기 지수판(20)의 구성은 요철부(21)가 형성된 본체(22)의 중앙에 타원형 중공체(23)을 구성하고, 타원형 중공체(23) 일측에 본체(22)와 수직교차되는 지지판(24)을 나란히 대향돌출되게 구성한다.The index plate 20 is composed of an elliptical hollow body 23 in the center of the body 22 is formed with an uneven portion 21, the support plate vertically intersecting with the main body 22 on one side of the elliptical hollow body (23) 24) are arranged side by side facing out.

상기한 구성의 지수판(20)을 이용하여 수로(30)를 시공하고자할 경우에는 다음과 같이 한다.When constructing the waterway 30 by using the index plate 20 of the above configuration is as follows.

도2에서와 같이 지수판(20)을 구성하는 일측 지지판(24)의 일부를 절단하여 절단부(25)를 구성하되, 이때 절단부(25)의 크기는 지수판(20)의 본체(22)로부터 돌출된 지지판(24)의 돌출 높이와 동일하게 절단하는 것이 바람직하며, 이는 지수판(20)의 시공을 위하여 "ㄷ"형으로 절첩시 내측에 위치하는 지지판(24)이 서로 중첩되지 않게 하기 위한 것이다.As shown in FIG. 2, a part of one side support plate 24 constituting the water stop plate 20 is cut to form a cut part 25, wherein the size of the cut part 25 protrudes from the main body 22 of the water stop plate 20. It is preferable to cut the same as the projecting height of the support plate 24, this is to prevent the support plate 24 located inside when folded in the "c" shape for the construction of the index plate 20 does not overlap each other.

또한 절단부(25)가 형성된 지지판(24)의 타측에 위치하는 지지판(24)에는 절단부(25)와 대응하는 위치에 절개부(26)를 형성하여 지수판(20)의 절첩에 장애가 되지 않게 하는 것이 바람직하며, 상기한 상태의 지수판(20)을 절첩하면 도3에서와 같이 된다.In addition, in the support plate 24 positioned on the other side of the support plate 24 on which the cut portions 25 are formed, the cut portions 26 are formed at positions corresponding to the cut portions 25 so that the folding of the index plate 20 is not impeded. Preferably, folding the index plate 20 in the above state is as shown in FIG.

도2에서와 같이 절첩된 지수판(20)을 이용한 수로(30)의 시공은 다음과 같이 된다.Construction of the channel 30 using the folded index plate 20 as shown in Figure 2 is as follows.

도9에서와 같이 수로(30)를 설치하고자 하는 위치에 먼저 콘크리트 몰탈로 바닥(31)을 시공하고, 상기 바닥(31)상에 수로(30) 설치를 위한 지수판(20)을 설치하고, 상기 지수판(20)을 기준으로 거푸집(40)을 설치하게 되며, 상기 거푸집(40)의 연결부부위에 지수판(20)을 이용한 완충부(10)를 시공하게 된다.As shown in FIG. 9, the floor 31 is first constructed with concrete mortar at the position where the waterway 30 is to be installed, and the water plate 20 for installing the waterway 30 is installed on the floor 31. The formwork 40 is installed based on the index plate 20, and the buffer part 10 using the index plate 20 is installed at the connection portion of the formwork 40.

좀더 상세히 설명하면 도3에서와 같이 절첩된 지수판(20)을 수로(30)설치를 위하여 시공된 바닥(31)상에 안치하고, 동시에 지수판(20)의 본체(22) 중앙에 구성된 타원형 중공체(23) 양측부에 도5에서와 같이 신축성 있는 완충고무편(50)을 위치시켜 완충고무편(50)의 단부가 타원형 중공체(23)의 외면에 위치케 하고 측부는 지지판(24)의 측면에 위치케 한다.More specifically, as shown in FIG. 3, the folded index plate 20 is placed on the bottom 31 constructed for the installation of the waterway 30, and at the same time, an elliptical hollow body configured in the center of the main body 22 of the index plate 20. (23) The elastic cushioning rubber piece 50 is placed on both sides thereof so that the end of the cushioning rubber piece 50 is located on the outer surface of the elliptical hollow body 23, and the side part of the supporting plate 24 Position it on the side.

이때 타원형 중공체(23)와 지지판(24)에 접하는 완충고무편(50) 단부와 측부에는 접착제를 도포하여 완충고무편(50)이 지수판(20) 양측에 접착 고정되게 한다.At this time, the adhesive rubber is applied to the end portion and the side of the buffer rubber piece 50 in contact with the elliptical hollow body 23 and the support plate 24 so that the buffer rubber piece 50 is adhesively fixed to both sides of the index plate 20.

상기에서와 같이 완충고무편(50)이 지수판(20)의 지지판(24) 양측에 접착고정되게 하는 것은 "ㄷ"형으로 절곡된 지수판(20)의 타원형 중공체(23) 전면에 걸쳐 완충고무편(50)이 접착고정되게 한다.As described above, the cushioning rubber piece 50 is fixed to both sides of the support plate 24 of the index plate 20 by the cushioning rubber over the entire surface of the oval hollow body 23 of the index plate 20 bent in a "c" shape. The piece 50 is adhesively fixed.

상기한 상태에서 도5에서와 같이 지수판(20)의 지지판(24)을 기점으로 양측부에 거푸집(40)을 위치시키되, 지지판(24)의 끝단부 일부가 중첩되는 거푸집(24)사이에 위치되게 하고 동시에 거푸집(40)의 양측단부에 위치하는 지지목(41)에 못(42)을 박아 고정되게 하므로서 지수판(20)의 양측에 거푸집(40)의 설치가 완료되고, 상기한 상태에서 거푸집(40)사이에 콘크리트를 타설하게 된다.In the above state, as shown in FIG. 5, the formwork 40 is positioned at both sides of the support plate 24 of the index plate 20, and the end portion of the support plate 24 is positioned between the overlapping formwork 24. And the nail 42 is fixed to the support wood 41 located at both ends of the formwork 40 at the same time, so that the formwork 40 is installed on both sides of the index plate 20, and the formwork is in the above state. Concrete will be placed between the 40.

이때 거푸집(40)사이에 콘크리트(43)를 타설하게 되더라도 지수판(20)의 양측 지지판(24)이 거푸집(40)사이에 견고히 고정되어 있어 지수판(20)의 위치가 변형되지 않고 초기 설치된 위치 그대로 형태를 유지하게 되므로 지수판(20)의 위치변형에 따른 불량현상을 방지할 수 있게 된다.At this time, even if the concrete 43 is placed between the formwork 40, both support plates 24 of the index plate 20 are firmly fixed between the formwork 40, so that the position of the index plate 20 is not deformed and is initially installed. Since the shape is maintained, it is possible to prevent the defect phenomenon caused by the position deformation of the index plate 20.

상기에서와 같은 구성으로 길게 구성된 수로(30)의 일정한 거리마다 지수판(20)이 위치되게 한 상태에서 거푸집(40)사이에 콘크리트를 타설, 양생 후 거푸집(40)을 제거하면 수로(30)가 완성되며, 상기 수로(30)에는 도8에서와 같은 완충부(10)가 등간격으로 형성된다.When the concrete is placed between the formwork 40 in a state where the index plate 20 is positioned at a predetermined distance of the channel 30 having a long configuration, the waterway 30 is removed after curing. Completion, the buffer portion 10 as shown in Figure 8 is formed in the water channel 30 at equal intervals.

상기한 상태에서 양생된 콘크리트(43)외부로 돌출된 지지판(24)은 절단날로 절단제거하면 본 고안에서 시공하고자 하는 수로(30)상에 완충부(10)가 등간격으로 형성되고, 상기 완충부(10)가 계절변화에 따라 콘크리트가 신축하더라도 이를 흡수하여 수로를 보호하게 된다.When the support plate 24 protruding out of the cured concrete 43 in the above state is cut and removed with a cutting blade, the buffer part 10 is formed at equal intervals on the channel 30 to be constructed in the present invention. The unit 10 protects the waterway by absorbing it even if the concrete is stretched according to the seasonal change.

본 고안에서 제공하고자 하는 지수판(20)을 이용하여 옹벽 등 긴 벽체로 구성되는 콘크리트 구조물에 적용 사용할 수 있다.By using the index plate 20 to be provided in the present invention can be applied to the concrete structure consisting of a long wall, such as a retaining wall.

본 고안을 실시함에 있어서, 도11에서와 같이 본체(22)의 중앙에 구성된 타원형 중공체(23)의 양측단부에 지지판(24)가 보조지지판(28)이 나란히 이중으로 돌출구성되게 하여 사용할 수도 있다.In carrying out the present invention, as shown in Figure 11, the support plate 24 at both side ends of the elliptical hollow body 23 formed in the center of the body 22 may be used so that the auxiliary support plate 28 protrudes in parallel in parallel. have.

이와 같이 구성된 본 고안은 수로(30)시공시 수로(30)의 일정한 거리마다 설치되는 지수판(20)으로 구성되는 완충부(10)를 구성함에 있어서, 지수판(20)을 구성하는 본체(22)의 중앙 양측에 지지판(24)을 돌출구성하고, 상기 지지판(24)을 이용하여 지수판(20)이 거푸집(40)사이에 견고히 고정되게 함과 동시에 완충고무편 (50)이 접착고정되게 할 수 있게 된다.The present invention configured as described above has a main body 22 constituting the water stop plate 20 in constructing the shock absorbing portion 10 composed of the water stop plate 20 installed at regular distances of the waterway 30 when the waterway 30 is constructed. Protruding structure of the support plate 24 on both sides of the center, by using the support plate 24 can be fixed firmly between the mold plate 40 and the buffer rubber piece 50 at the same time adhesive fixing Will be.

다시설명하면 지수판(20)을 "ㄷ"형으로 절곡한 다음 지수판(20)의 본체(22)양측 수직방향으로 돌출된 지지판(24)에 완충고무편(50)을 접착제로 견고히 접착고정할 수 있을 뿐 아니라 지수판(20) 양측에 거푸집(40) 설치시 거푸집(40)사이에 지지판(24)의 단부가 끼워져 결합되게 한 다음 못(42)으로 체결고정되게 하므로서 거푸집(40)사이에 콘크리트를 타설하더라도 지수판(20)의 위치가 변형되지 않게 된다.In other words, the index plate 20 may be bent into a "c" shape, and then the cushioning rubber piece 50 may be firmly adhered and fixed to the support plate 24 protruding in both vertical directions of the main body 22 of the index plate 20. In addition, when the formwork 40 is installed on both sides of the index plate 20, the end of the support plate 24 is fitted between the formwork 40, and then coupled to the nail 42, thereby fixing the concrete between the formwork 40. Even if it is poured, the position of the index plate 20 is not deformed.

즉 지수판(20)이 지지판(24)을 통하여 거푸집(40)에 견고히 고정되어 있고, 상기 지지판(24)에 완충고무편(50)이 접착되어 있기 때문이다.In other words, the index plate 20 is firmly fixed to the formwork 40 through the support plate 24, and the buffer rubber piece 50 is adhered to the support plate 24.

상기에서와 지수판(20)이 거푸집(40)에 의해 견고히 고정된 상태에서 콘크리트를 타설 양생하게 되므로 콘크리트 타설 중 지수판(20)의 위치가 변형되지 않고 정확한 위치에서 콘크리트의 양생이 이루어지게 된다.Since the index plate 20 is cured by pouring the concrete in the state fixed firmly by the formwork 40, the curing of the concrete is made at the correct position without changing the position of the index plate 20 during concrete placement.

다시 설명하면 지수판(20)을 구성하는 본체(22)는 수로(30)를 구성하는 벽체의 중앙 길이 방향으로 위치하면서 타원형 중공체(23) 및 완충고무편(50)을 기준으로 앞뒷쪽에 구성되고, 지지판(24) 및 완충고무편(50)은 앞뒷쪽 벽체를 완전히 격리시키게 된다.In other words, the main body 22 constituting the index plate 20 is located in the front and back on the basis of the oval hollow body 23 and the cushioning rubber piece 50 while being positioned in the central longitudinal direction of the wall constituting the waterway 30. The support plate 24 and the cushioning rubber piece 50 completely isolate the front and back walls.

따라서 수로(30)의 사용시 수로를 통하여 흘러내리는 물이 완충부(10)이 구성된 완충고무편(50)을 통하여 내부로 스며들더라도 벽체 중앙에 구성된 지수판(20)의 본체(22) 및 타원형 중공체(23)에 의해 차단되므로 수로(30)밖으로 물이 누수되지는 못한다.Therefore, even when the water flowing through the water channel 30 when the water flows through the buffer rubber piece 50 in which the buffer part 10 is formed, the main body 22 and the elliptical hollow of the water stop plate 20 configured in the center of the wall Since it is blocked by the sieve 23, water does not leak out of the waterway (30).

또한 계절의 변화에 따라 콘크리트 벽체가 신축하더라도 완충부(10)가 이를 흡수하게 된다.In addition, even if the concrete wall is stretched according to the change of the season, the buffer unit 10 will absorb it.

즉 여름철과 같이 외기의 온도가 높아 벽체가 신장하게 되면 지수판(20)을 구성하는 타원형 중공체(23) 및 완충고무편(50)이 압축되면서 이를 흡수하게 되고, 반대로 겨울철과 같이 외기에 온도가 떨어질 경우에는 벽체가 수축하게 되나 역시 지수판(20)을 구성하는 타원형 중공체(23) 및 완충고무편(50)이 신장하면서 이를 흡수하게 되므로 온도변화에 따른 수로의 손상을 방지할 수 있게 된다.That is, when the temperature of the outside air is high, as in the summer, the wall is stretched and the elliptical hollow body 23 and the buffer rubber piece 50 constituting the index plate 20 are compressed and absorbed. If it falls, the wall is contracted, but the elliptical hollow body 23 and the buffer rubber piece 50 constituting the index plate 20 is absorbed as it extends, thereby preventing damage to the channel due to temperature changes.

이상 설명한 바와 같이 본 고안은 수로나 옹벽과 같은 콘크리트 구조물을 시공하되, 상기 구조물에 등간격으로 형성되는 완충부의 지수판을 구성함에 있어서, 지수판을 구성하는 본체의 중앙 양측 수직방향에 지지판을 돌출 구성하고 상기 지지판을 이용하여 지수판이 거푸집상에 고정되게 하거나 완충고무편이 접착고정되게 하므로서 콘크리트 타설시 지수판의 위치변동을 방지할 수 있게 되므로 지수판의 정확한 시공이 이루어질 수 있게 되고 따라서 지수판의 기능을 완전히 수행할 수 있게 되는 등의 효과가 있는 것이다.As described above, the present invention constructs a concrete structure such as a waterway or a retaining wall, and in constructing a water discharge plate formed at equal intervals on the structure, protruding a support plate in both vertical directions of the center of the main body constituting the water discharge plate. By using the support plate, the index plate is fixed on the formwork or the cushioning rubber piece is fixed to the adhesive plate, thereby preventing the positional change of the index plate when placing concrete, so that the accurate construction of the index plate can be made, and thus the function of the index plate can be fully performed. It will be able to effect.

Claims (3)

요철부가 형성된 본체 중앙에 타원형 중공부가 형성된 콘크리트 구조물 시공을 위한 지수판을 구성함에 있어서, 상기 지수판(20)의 본체(22) 중앙에 구성된 타원형 중공체(23)의 양측에 수직방향으로 지지판(24)이 돌출구성되게 하여서 됨을 특징으로 하는 콘크리트 구조물 시공을 위한 지수판.In constructing an index plate for construction of a concrete structure in which an elliptical hollow part is formed in a center of an uneven part, the support plate 24 is perpendicular to both sides of an elliptical hollow body 23 formed in the center of the main body 22 of the index plate 20. Index plate for the construction of concrete structures, characterized in that the protrusions are configured. 제1항에 있어서, 지수판(20)을 구성하는 지지판(24) 측부에 완충고무편(50)이 접착고정되게 하여서 됨을 특징으로 하는 콘크리트 구조물 시공을 위한 지수판.The index plate for construction of a concrete structure according to claim 1, wherein the cushioning rubber piece (50) is fixed to the side of the support plate (24) constituting the index plate (20). 제1항에 있어서, 본체(22)에 수직방향으로 돌출구성되는 지지판(24) 일측에 보조지지판(28)이 나란히 대향되게 돌출구성되게 하여서 됨을 특징으로 하는 콘크리트 구조물 시공을 위한 지수판.According to claim 1, wherein the support plate (24) protruding in a direction perpendicular to the main body (22) on the side of the auxiliary support plate (28) side by side so as to be configured to protrude side by side to the concrete plate, characterized in that the construction.
KR20-2002-0031243U 2002-10-19 2002-10-19 Board lceeping off water for concrete construction KR200304413Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2002-0031243U KR200304413Y1 (en) 2002-10-19 2002-10-19 Board lceeping off water for concrete construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2002-0031243U KR200304413Y1 (en) 2002-10-19 2002-10-19 Board lceeping off water for concrete construction

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0064072A Division KR100482280B1 (en) 2002-10-19 2002-10-19 Board lceeping off water for concrete construction

Publications (1)

Publication Number Publication Date
KR200304413Y1 true KR200304413Y1 (en) 2003-02-19

Family

ID=49400970

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2002-0031243U KR200304413Y1 (en) 2002-10-19 2002-10-19 Board lceeping off water for concrete construction

Country Status (1)

Country Link
KR (1) KR200304413Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102461339B1 (en) 2021-09-29 2022-11-01 선일건설(주) A expansion joint water stopper board of concrete structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102461339B1 (en) 2021-09-29 2022-11-01 선일건설(주) A expansion joint water stopper board of concrete structure

Similar Documents

Publication Publication Date Title
KR100986300B1 (en) Water-proofing plate unit for concrete and construction method of concrete structure using that
US11124974B2 (en) Wood block module capable of level adjustment and shock absorption
KR101650365B1 (en) An Expansion Joint Filler
KR20150083431A (en) A Expansion Joint Filler
JPWO2005088022A1 (en) Insulation panel combined with formwork and outer insulation structure
KR100482280B1 (en) Board lceeping off water for concrete construction
KR200304413Y1 (en) Board lceeping off water for concrete construction
JP2009209639A (en) Antiseismic reinforcing joint structure of joint part of concrete structure and its construction method
JP4175658B2 (en) Construction method of composite panel on concrete outer wall of reinforced concrete building
TWM641295U (en) window mounting frame
KR20200025634A (en) Out side panel fixing device of building
KR20060027997A (en) A floor structure in floating form
KR200330037Y1 (en) Board keeping off water for concrete construction
KR101535515B1 (en) Adiabatic structure and constructing method
CN219262396U (en) Reinforced protection type rubber water stop
KR200172515Y1 (en) Expansion joint assembly for concrete construction
KR20190043267A (en) structure of multi composite tile panel
KR0173837B1 (en) Heat insulating elements
KR0173839B1 (en) Construction method of an insulating wall
JPH11172917A (en) Through slit forming member
KR101179928B1 (en) Finishing for drain board
KR200476254Y1 (en) Heat Insulator
KR200415591Y1 (en) The euroform for slab
KR200437474Y1 (en) Heat insulating shock absorber for covering chink
KR200374685Y1 (en) Assembly structure of board keeping off water for concrete construction

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T701 Written decision to grant on technology evaluation
G701 Publication of correction
EXTG Extinguishment