이승영
나공열
Original Assignee
이승영
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이승영 filed Critical 이승영
Priority to KR2020010030167U priority Critical patent/KR200274808Y1/en
Application granted granted Critical
Publication of KR200274808Y1 publication Critical patent/KR200274808Y1/en

Links

Abstract

본 고안은 교각에 올려진 일,타측 교량빔을 동시에 인상할 수 있는 교량빔 인상 장치에 관한 것으로서, 그 구성을 설명하면 다음과 같다.The present invention relates to a bridge beam lifting device capable of simultaneously lifting one and the other bridge beam mounted on the bridge, the configuration thereof is as follows.

일,타측 상부구조의 교량빔을 각각 받혀주는 양측 교좌장치가 교각의 상면에 설치되어 있는 교량에 있어서; 상기 양측 교량빔의 전방에 장착되어 있으며, 중앙에는 하나 이상의 잭이 장착되는 잭 장착부가 형성되어 있고, 그 양측에는 전면 지지부가 구비되어 있고, 이 전면 지지부의 후방에는 상기 교좌장치가 삽입되는 교좌장치 삽입부가 구비되어 있는 전방 브라켓과; 상기 양측 교량빔의 후방에 상기 전방브라켓과 대칭되게 장착되어 있으며, 중앙에는 하나 이상의 잭이 장착되는 잭 장착부가 형성되어 있고, 그 양측에는 후면 지지부가 구비되어 있고, 이 후면 지지부의 전방에 상기 교좌장치가 삽입되는 교좌장치 삽입부가 구비되어 있는 후방 브라켓; 및 상기 전,후면 브라켓 간의 폭을 조정하면서 교좌장치 삽입부를 서로 연결하는 다수의 하부 연결대로 구성됨을 특징으로 하는 것이다.In the bridge is provided on the upper surface of the bridge, both bridge devices for receiving the bridge beam of the one, the other superstructure; It is mounted in front of the bridge beams on both sides, the center is provided with a jack mounting portion for mounting one or more jacks, both sides are provided with a front support portion, the rear of the front support portion, the bridge device is inserted A front bracket having an insertion portion; It is mounted symmetrically with the front bracket at the rear of the two bridge beams, the center is provided with a jack mounting portion for mounting at least one jack, both sides are provided with a rear support portion, the bridge in front of the rear support portion A rear bracket having a seat device insert into which the device is inserted; And it is characterized in that it is composed of a plurality of lower connecting rods connecting the teaching device inserts to each other while adjusting the width between the front and rear brackets.

Description

교량빔 인상 장치{Lifting apparatus of the bridge beam}Lifting apparatus of the bridge beam

본 고안은 교량의 상부구조를 지지하는 교좌장치를 교체할 수 있도록 교량빔을 인상하는 장치에 관한 것으로서, 더욱 상세하게는, 교각에 올려진 일,타측 교량빔을 동시에 인상할 수 있는 교량빔 인상 장치에 관한 것이다.The present invention relates to a device for raising a bridge beam to replace the bridge device supporting the upper structure of the bridge, and more specifically, to raise the bridge beam that can simultaneously raise the one and the other bridge beam on the bridge Relates to a device.

일반적으로 교량(橋梁)이라 함은, 하천, 계곡, 움푹 꺼진 땅 등을 넘기 위하여 만들어지는 각종 구조물을 총칭하는 것이다.Generally, a bridge is a general term for various structures that are made to cross rivers, valleys, and pit grounds.

이에 교량은, 수직으로 세워지는 다수의 교각으로 이루어진 하부구조와, 상기 교각들의 상부에 설치되는 상부구조로 구성되며, 상기 상부구조는, 상판과 상판의 하부에 다수로 장착되어 상기 교각들의 상단에 거치되는 보강빔으로 구성된다.The bridge is composed of a lower structure consisting of a plurality of bridges erected vertically, and an upper structure that is installed on top of the bridges, the upper structure, a plurality of upper and lower parts of the upper plate is mounted on the top of the bridges It consists of a reinforcing beam mounted.

한편 상기 하부구조의 교각들 상단에는, 상부구조로부터 발생되는 하중을 하부구조로 전달하기 위하여 교량빔을 지지하는 교좌장치가 설치되는데, 이 교좌장치는, 상부구조에 발생하는 충격을 최소화하고 온도변화에 따른 상부구조의 신축작용을 상쇄시키는 역할을 수행하며, 대표적으로 금속재 또는 고무재로 나누어 진다.On the other hand, on the top of the bridges of the substructure, a bridge device for supporting the bridge beam is installed to transfer the load generated from the superstructure to the substructure, the bridge device is to minimize the impact occurring on the superstructure and change the temperature To counteract the expansion and contraction of the superstructure according to, typically divided into metal or rubber materials.

그러나 상기 교좌장치로 빗물 또는 오염물질이 침투되게 됨으로서, 금속재의 교좌장치는 부식을 일으키게 되고 고무재의 교좌장치는 손상을 입게 됨에 따라서, 교좌장치의 제 기능을 수행 할 수 없게 된다.However, as rainwater or contaminants penetrate into the teaching device, the teaching device made of metal causes corrosion and the teaching device made of rubber becomes damaged, so that the function of the teaching device becomes impossible.

따라서 상기와 같이 손상된 교좌장치를 교체할 경우에는 상부구조의 인상이 선행되어야 한다. 그러므로 상부구조를 인상할 경우에는, 교좌장치가 올려진 교각의 상단에 잭을 설치하여 교량빔과 상판으로 구성된 상부구조를 전체적으로 인상하는 것이다.Therefore, when replacing the damaged device as described above, the impression of the superstructure must be preceded. Therefore, in the case of raising the upper structure, by installing a jack on the top of the bridge where the bridge device is raised to raise the overall structure consisting of the bridge beam and the top plate as a whole.

그러나, 상기와 같이 상부구조를 인상함에 있어서, 교좌장치 또는 교각의 종류에 따라 교각 상면의 공간이 협소할 경우에는 잭의 설치가 곤란함으로서, 상부구조의 인상에 많은 어려움이 따르는 문제점을 가지고 있었다.However, in raising the upper structure as described above, when the space on the upper surface of the pier is narrow according to the type of bridge device or bridge, it is difficult to install the jack, there was a problem that a lot of difficulties in raising the upper structure.

또한 잭을 통해 상부구조를 인상함에 있어서, 단일의 교량빔 만을 인상함에 따라 단부에 과도한 인상력이 작용함으로서, 교량빔의 단부가 직접적으로 파손되는 문제점을 가지고 있었다.In addition, in raising the upper structure through the jack, excessive pulling force acts on the end portion by pulling only a single bridge beam, so that the end portion of the bridge beam was directly damaged.

이에, 본 고안은 상기의 문제점을 해결하기 위하여 고안된 것으로서, 교각 상면 양측에 거치되는 일,타측 교량빔의 단부를 서로 연결하여 하나 이상의 잭을 통해 일,타측 교량빔을 동시에 인상함으로서, 교좌장치 또는 교각의 종류에 따라 잭의 장착공간이 협소하더라도 잭의 장착을 가능하게 하여 교량빔을 용이하게 인상할 수 있는 교량빔 인상 장치를 제공함을 목적으로 한다.Accordingly, the present invention is designed to solve the above problems, by connecting the ends of one bridge beam mounted on both sides of the upper surface of the bridge, the other bridge beam through the one or more jacks at the same time, the bridge device or It is an object of the present invention to provide a bridge beam raising apparatus that enables the jack to be mounted even if the mounting space of the jack is narrow according to the type of the bridge.

또한 일,타측 교량빔을 동시에 인상함으로서, 잭의 인상력을 일,타측 교량빔으로 균일 분배시켜 과도한 인상력으로 인하여 발생되는 교량빔의 단부 파손을 방지할 수 있는 목적도 있는 것이다.In addition, by simultaneously pulling the one and the other bridge beam, there is also an object to uniformly distribute the pulling force of the jack to the one and the other bridge beam to prevent the end of the bridge beam caused by excessive pulling force.

또 전,후방 브라켓의 폭을 조정 가능하게, 전,후방 브라켓의 양측에 구비된전,후면 지지부를 구성하는 상,하 수평대 및 좌,우 수직대의 길이를 조정 가능하게 함으로서, 교량빔의 크기와 관계없이 인상장치를 호환적으로 사용할 수 있는 목적도 가지는 것이다.In addition, it is possible to adjust the width of the front and rear brackets, and to adjust the lengths of the upper and lower horizontal and left and right vertical bands that constitute the front and rear support portions provided on both sides of the front and rear brackets. Regardless of the purpose, the impression device can be used interchangeably.

상기와 같은 목적을 달성하기 위한 본 고안, 일,타측 상부구조의 교량빔을 각각 받혀주는 양측 교좌장치가 교각의 상면에 설치되어 있는 교량에 있어서; 상기 양측 교량빔의 전방에 장착되어 있으며, 중앙에는 하나 이상의 잭이 장착되는 잭 장착부가 형성되어 있고, 그 양측에는 전면 지지부가 구비되어 있고, 이 전면 지지부의 후방에는 상기 교좌장치가 삽입되는 교좌장치 삽입부가 구비되어 있는 전방 브라켓과; 상기 양측 교량빔의 후방에 상기 전방브라켓과 대칭되게 장착되어 있으며, 중앙에는 하나 이상의 잭이 장착되는 잭 장착부가 형성되어 있고, 그 양측에는 후면 지지부가 구비되어 있고, 이 후면 지지부의 전방에 상기 교좌장치가 삽입되는 교좌장치 삽입부가 구비되어 있는 후방 브라켓; 및 상기 전,후면 브라켓 간의 폭을 조정하면서 교좌장치 삽입부를 서로 연결하는 다수의 하부 연결대로 구성됨을 특징으로 하는 것이다.In the present invention for achieving the above object, in the bridge, which is provided on the upper surface of the bridge both side bridge device for receiving the bridge beam of the one, the other superstructure; It is mounted in front of the bridge beams on both sides, the center is provided with a jack mounting portion for mounting one or more jacks, both sides are provided with a front support portion, the rear of the front support portion, the bridge device is inserted A front bracket having an insertion portion; It is mounted symmetrically with the front bracket at the rear of the two bridge beams, the center is provided with a jack mounting portion for mounting at least one jack, both sides are provided with a rear support portion, the bridge in front of the rear support portion A rear bracket having a seat device insert into which the device is inserted; And it is characterized in that it is composed of a plurality of lower connecting rods connecting the teaching device inserts to each other while adjusting the width between the front and rear brackets.

도 1은 본 고안에 따른 교량빔 인상장치의 설치상태를 나타낸 개략도.1 is a schematic view showing the installation state of the bridge beam lifting apparatus according to the present invention.

도 2는 본 고안의 교량빔 인상장치를 확대 도시한 사시도.Figure 2 is an enlarged perspective view of the bridge beam lifting device of the present invention.

도 3,4는 본 고안에 따른 교량빔 인상장치의 일부 분해 사시도.3 and 4 is a partially exploded perspective view of the bridge beam lifting apparatus according to the present invention.

도면의 주요부분에 대한 부호의 설명Explanation of symbols for main parts of the drawings

1 : 교각1: pier

11 : 상면11: upper surface

2 : 상부구조2: superstructure

21 : 교량빔21: bridge beam

22 : 교좌장치22: teaching device

3 : 전방 브라켓3: front bracket

31 : 잭 장착부31: jack mounting

32 : 전면 지지부32: front support

33 : 교좌장치 삽입부33: insertion unit insertion unit

4 : 후방 브라켓4 rear bracket

41 : 잭 장착부41: jack mounting

42 : 전면 지지부42: front support

43 : 교좌장치 삽입부43: insertion unit insertion unit

6 : 잭6: jack

이하 본 고안의 구성 및 작용을 첨부도면을 참조하여 상세히 설명한다.Hereinafter, the configuration and operation of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 고안에 따른 교량빔 인상장치의 설치상태를 나타낸 개략도이며, 도 2는 본 고안의 교량빔 인상장치를 확대 도시한 사시도로서, 먼저, 그 구성을 설명하면 다음과 같다.1 is a schematic view showing the installation state of the bridge beam raising apparatus according to the present invention, Figure 2 is an enlarged perspective view of the bridge beam raising apparatus of the present invention, first, the configuration will be described as follows.

일,타측 상부구조(2)의 교량빔(21)을 각각 받혀주는 양측 교좌장치(22)가 교각(1)의 상면(11)에 설치되어 있는 교량에 있어서;In the bridge, which is provided on the upper surface 11 of the bridge (1), both bridge devices (22) for supporting the bridge beam (21) of the other side superstructure (2);

상기 양측 교량빔(21)의 전방에 장착되어 있으며, 중앙에는 하나 이상의 잭(6)이 장착되는 잭 장착부(31)가 형성되어 있고, 그 양측에는 전면 지지부(32)가 구비되어 있고, 이 전면 지지부(32)의 후방에는 상기 교좌장치(22)가 삽입되는 교좌장치 삽입부(33)가 구비되어 있는 전방 브라켓(3)과; 상기 양측 교량빔(2)의 후방에 상기 전방브라켓(3)과 대칭되게 장착되어 있으며, 중앙에는 하나 이상의 잭(6)이 장착되는 잭 장착부(41)가 형성되어 있고, 그 양측에는 후면 지지부(42)가 구비되어 있고, 이 후면 지지부(42)의 전방에 상기 교좌장치(22)가 삽입되는 교좌장치 삽입부(43)가 구비되어 있는 후방 브라켓(4); 및 상기 전,후면 브라켓(3,4) 간의 폭을 조정하면서 교좌장치 삽입부(33,43)를 서로 연결하는 다수의 하부 연결대(s1)로 구성되는 것이다.It is mounted in front of the both side beam beams 21, the center is provided with a jack mounting portion 31 in which at least one jack (6) is mounted, the front support portion 32 is provided on both sides thereof, the front A front bracket (3) provided at the rear of the support part (32) having a seat device insert (33) into which the seat device (22) is inserted; The rear side of the bridge beam (2) is mounted symmetrically with the front bracket (3), the center is provided with a jack mounting portion 41 is mounted at least one jack (6), both sides of the rear support ( A rear bracket (4) provided with a rear seat support (42) and a front seat support (42) having a seat device insertion portion (43) into which the seat device (22) is inserted; And it is composed of a plurality of lower connecting rods (s1) connecting the teaching device inserting portions (33, 43) to each other while adjusting the width between the front, rear brackets (3, 4).

특히 상기 전,후방 브라켓(3,4)에 장착되는 잭(6)은 별도의 유압장치(도시않됨)를 통해 작동되며, 상기 잭(6)은 실린더형이 사용될 수 있으며, 또한 신축성을 가지는 챔버형이 사용될 수 도 있는 것이다.In particular, the jacks 6 mounted to the front and rear brackets 3 and 4 are operated through a separate hydraulic device (not shown), and the jacks 6 may be cylindrical, and the chamber may have elasticity. The type may be used.

상기 구성을 좀더 구체적으로 설명하면 다음과 같다.The configuration is described in more detail as follows.

도 3은 본 고안에 따른 교량빔 인상장치의 일부 분해 사시도로서, 상기 전,후방 브라켓(3,4)의 잭 장착부(31)는, 다수로 굴곡된 파이프 골조(311,411)와, 이 파이프 골조(311,411)의 중간에 돌출 형성된 중간 잭 장착판(312,412), 및 이 중간 잭 장착판(312)의 양측에 중간 지지판 보다 상대적으로 높은 위치에 돌출 형성되어 있는 양측 잭 장착판(313,413)으로 구성되는 것이다.Figure 3 is a partially exploded perspective view of the bridge beam lifting apparatus according to the present invention, the jack mounting portion 31 of the front and rear brackets (3, 4), a plurality of pipe skeletons (311, 411) and the pipe frame ( Intermediate jack mounting plates 312 and 412 protruding in the middle of the 311, 411, and both jack mounting plates 313, 413 protruding at a position higher than the intermediate supporting plate on both sides of the intermediate jack mounting plate 312. .

따라서 상기 교각(1)의 상면 공간에 따라서, 2개소의 잭(6)을 상기 전,후방 브라켓(3,4)의 중간 잭 장착판(312)에 설치하거나, 4개소의 잭(6)을 상기 전,후방 브라켓(3,4)의 양측 잭 장착판(313,413)에 선택적으로 설치할 수 있는 것이다.Accordingly, two jacks 6 are provided in the middle jack mounting plate 312 of the front and rear brackets 3 and 4, or four jacks 6 are provided according to the upper surface space of the piers 1. The front and rear brackets (3, 4) can be selectively installed on both side jack mounting plate (313,413).

즉 교량빔(21)의 하면과 교각의 상면 사이의 거리가 좁을 경우에는 하중분담 지지부(3)의 하면중앙에 일정한 높이를 가지는 잭(4)을 장착할 수 없음에 따라서, 상기 전,후방 지지부(33,43)의 상단에 구비되어 있는 잭 장착판(312,412)들의 하부에 중앙 전후방의 2개소 또는 모서리 부분의 4개소의 잭(6)을 선택적으로 장착하여 일,타측 교량빔(21)을 동시에 인상시킬 수 도 있는 것이다.That is, when the distance between the lower surface of the bridge beam 21 and the upper surface of the bridge is narrow, the front and rear support portions cannot be mounted to the jack 4 having a constant height in the center of the lower surface of the load sharing support portion 3. The one and the other bridge beams 21 are selectively mounted by mounting two jacks 6 at the front and rear or at four corners at the bottom of the jack mounting plates 312 and 412 provided at the upper ends of the 33 and 43. You can raise it at the same time.

도 4는 본 고안에 따른 교량빔 인상장치의 일부 분해 사시도로서, 상기 전,후방 브라켓(3,4)의 양측에 형성된 전,후면 지지부(32,42)는, 상기 잭 장착부(31,41)의 양측에 연결되어 있으며, 연결대(s2)를 통해 신축되며 볼트(b)로 고정되는 상,하 수평대와 좌,우 수직대로 구성되는 것이다.4 is a partially exploded perspective view of the bridge beam lifting apparatus according to the present invention, wherein the front and rear support portions 32 and 42 formed on both sides of the front and rear brackets 3 and 4 are the jack mounting portions 31 and 41. It is connected to both sides of the, and stretched through the connecting rod (s2) is to be composed of the upper, lower horizontal and the left, right vertical fixed to the bolt (b).

그리고 상기 상,하 수평대와 좌,우 수직대는, 하나 이상의 관통홀(h1)이 각기 형성된 파이프가 직각을 이루는 다수의 연결 파이프와, 상기 파이프에 삽입되고 다수의 간격유지홀(h2)이 형성되어 있는 다수의 연결대(s2), 및 상기 관통홀(h1)과 간격유지홀(h2)을 관통하여 체결되는 다수의 볼트(b)의 조립체로 구성되는 것이다.The upper and lower horizontal bands and the left and right vertical bands each include a plurality of connecting pipes each having a right angle to a pipe on which at least one through hole h1 is formed, and a plurality of gap maintaining holes h2 inserted into the pipe. It is composed of a plurality of connecting table (s2) and the assembly of a plurality of bolts (b) fastened through the through hole (h1) and the space maintaining hole (h2).

따라서 상기 전,후면 지지부(32,42)를 통해 상기 일,타측 교량빔(21)의 단부의 전,후면을 잡아줌으로서, 교량빔의 인상시 인상장치의 흔들림을 방지함은 물론, 인상장치가 교량빔의 하면에서 이탈되는 것을 방지할 수 있는 것이다.Accordingly, by holding the front and rear surfaces of the ends of the one and the other bridge beam 21 through the front and rear support portions 32 and 42, the lifting device is prevented from shaking when the bridge beam is raised, as well as the pulling device. It is possible to prevent the deviation from the lower surface of the bridge beam.

또한 상기 전,후면 지지부(32,42)를 구성하는 상,하 수평대와 좌,우 수직대가 신축가능함으로서, 교량빔의 크기와 관계없이 인상장치를 호환적으로 사용할 수 있는 것이다.In addition, since the upper and lower horizontal and left and right vertical bars constituting the front and rear support parts 32 and 42 can be stretched, the pulling device can be used interchangeably regardless of the size of the bridge beam.

한편, 도 3에 도시된 바와같이, 상기 전,후방 브라켓(3,4)의 하부 양측에 형성되어 있는 교좌장치 삽입부(33,43)는 상기 전,후면 지지부(32,42)의 하부 좌,우에서 돌출된 2개소의 종형 파이프(p1)로 구성된다. 그리고 상기 종형 파이프(p1)들에는 전,후방 브라켓(3,4)간의 폭을 조정할 수 있도록 상기 다수의 하부 연결대(s1)가 삽입되어 신축 고정되는 것이다.On the other hand, as shown in Figure 3, the insertion device 33, 43 formed on both sides of the lower front and rear brackets (3, 4) of the lower left of the front and rear support portions (32, 42) It consists of two vertical pipes p1 protruding from the right side. In addition, the plurality of lower connecting rods s1 are inserted into the vertical pipes p1 so as to adjust the widths between the front and rear brackets 3 and 4 and are fixed and stretched.

그리고 상기 종형 파이프(p1)에는 하나 이상의 관통홀(h1)이 형성되고 상기 하부 연결대(s1)에는 다수의 간격 유지홀(h2)이 형성되어 상기 관통홀(h1)과 간격 유지홀(h2)에는 볼트(b)가 관통 체결되는 것이다.In addition, at least one through hole h1 is formed in the vertical pipe p1, and a plurality of gap maintaining holes h2 are formed in the lower connecting rod s1, so that the through hole h1 and the gap maintaining hole h2 are formed in the vertical pipe p1. The bolt (b) is to be fastened through.

특히 상기 교좌장치 삽입부(33,43)를 구성하는 종형 파이프(p1)의 상측에는 신축패드(7)가 추가로 장착됨으로서, 상기 종형 파이프(p1)와 교량빔(21) 사이의 밀착력을 향상시킴에 따라, 교량빔의 인상시 인상장치의 요동을 방지 할 수 있는 것이다.In particular, the expansion pad 7 is further mounted on the upper side of the vertical pipe p1 constituting the bridge device insertion parts 33 and 43, thereby improving the adhesion between the vertical pipe p1 and the bridge beam 21. By doing so, it is possible to prevent rocking of the pulling device when the bridge beam is raised.

따라서 상기 전,후방 브라켓(3,4)의 폭을 자유로이 조정할 수 있음에 따라서, 교량빔의 폭과 관계없이 본 고안의 교량빔 인상장치를 호환되게 사용할 수 있는 것이다.Therefore, as the width of the front and rear brackets (3, 4) can be adjusted freely, the bridge beam lifting device of the present invention can be used interchangeably regardless of the width of the bridge beam.

이하 상기와 같이 구성된 인상장치를 통해 교량빔을 인상하는 방법을 설명하면 다음과 같다.Hereinafter, a method of raising the bridge beam through the pulling device configured as described above will be described.

도 1 내지 도 4에 도시된 바와같이, 일,타측 상부구조의 교량빔을 각각 받혀주는 일,타측 교좌장치(22)가 교각(1)의 상면에 설치된 상태에서 상기 교량빔을 인상함에 있어서, 먼저, 상기 양측 교좌장치(22)를 통과되는 전방 브라켓(3)을 교량빔(21)의 전방에 장착한 후, 상기 전방 브라켓(3)의 후방인 교량빔(21)의 후방에 교량빔(21)을 장착한다.As shown in Figures 1 to 4, one, the one to receive the bridge beam of the other upper structure, respectively, in raising the bridge beam in the state in which the other bridge device 22 is installed on the upper surface of the bridge (1), First, the front bracket (3) passing through the both sides of the bridge device 22 is mounted in front of the bridge beam 21, then the bridge beam (behind the bridge beam 21, which is the rear of the front bracket 3) 21).

다음 상기 전,후방 브라켓(3)의 형성된 잭 장착부(3)의 하면과 교각(1)의 상면 사이에 2개소 이상의 잭(6)을 장착한다.Next, two or more jacks 6 are mounted between the lower surface of the jack mounting portion 3 formed on the front and rear brackets 3 and the upper surface of the piers 1.

그리고 최종적으로, 유압장치(도시않됨)를 통해 상기 잭(6)을 신장시켜 일,타측 상부구조(2)의 교량빔(21)을 동시에 인상함으로서, 교좌장치의 교체를 가능하게 할 수 있는 것이다.And finally, by extending the jack 6 through a hydraulic device (not shown) to simultaneously pull up the bridge beam 21 of one, the other superstructure 2, it is possible to replace the bridge device. .

그리고 교좌장치를 교체한 후에는 상기 순서와 역순으로 교량빔을 하강시키는 것이다. 즉, 잭(6)의 작동을 통해 교량빔을 하강시킨 다음, 하중분담 지지부(3)의 하부에 장착되어 있는 잭(4)을 이탈시킨 후, 전,후방 브라켓(3)을 서로 분리하여 전,후방 브라켓(3,4)을 교량빔(21)의 하부로부터 이탈시키는 것이다.After replacing the bridge device, the bridge beam is lowered in the reverse order. That is, the bridge beam is lowered by the operation of the jack 6, and then the jack 4 mounted on the lower portion of the load sharing support part 3 is separated, and then the front and rear brackets 3 are separated from each other. The rear brackets 3 and 4 are separated from the lower part of the bridge beam 21.

따라서 잭(6)의 인상력을 일,타측 교량빔으로 균일 분배시켜 과도한 인상력으로 인하여 발생되는 교량빔의 단부 파손을 방지할 수 있는 것이다.Therefore, it is possible to uniformly distribute the pulling force of the jack 6 to one, the other bridge beam to prevent the end of the bridge beam caused by the excessive pulling force.

한편, 상기와 같이 잭 설치함에 있어서, 잭(6)을 전,후방 브라켓(3,4)의 중앙 전,후방인 교각(1) 상면(11)의 중앙 전후방에 설치함으로서, 2개소의 잭(6)을 통해 일,타측의 교량빔을 동시에 인상할 수 도 있는 것이다.On the other hand, in the jack installation as described above, by installing the jack (6) in the center front and rear of the upper surface 11 of the piers (1), which is the front, rear, front and rear of the center of the front and rear brackets (3, 4), two jacks ( 6) it is possible to simultaneously raise the beam beams of one side and the other.

또한 잭(6)을 전,후방 브라켓(3,4)의 양측 전,후방인 교각(1) 상면(11)의 양측 전후방에 설치함으로서, 4개소의 잭(4)을 통해 일,타측의 교량빔을 동시에 인상할 수 도 있는 것이다.In addition, the jack 6 is installed in both front and rear sides of the upper surface 11 of the piers 1, which are the front and rear sides of the front and rear brackets 3 and 4, so that the bridges on the one side and the other side through the four jacks 4 are provided. You can also raise the beam at the same time.

상술한 바와 같이 본 고안은, 교좌장치 또는 교각의 종류에 따라 잭의 장착공간이 협소하더라도 잭의 장착을 가능하게 함에 따라 교량빔을 용이하게 인상함으로서, 교좌장치를 신속히 교체할 수 있는 효과를 가지는 것이다.As described above, the present invention has an effect of quickly replacing the bridge device by easily raising the bridge beam by allowing the jack to be mounted even if the mounting space of the jack is narrow according to the type of bridge device or bridge. will be.

또한 잭의 인상력을 일,타측 교량빔으로 균일 분배시켜 과도한 인상력으로 인하여 발생되는 교량빔의 단부 파손을 방지함으로서, 교량의 파손없이 교좌장치를 신속히 교체할 수 있는 효과도 있다.In addition, by uniformly distributing the jack's pulling force to the one and the other bridge beam to prevent the end of the bridge beam caused by excessive pulling force, there is also an effect that can quickly replace the bridge device without breaking the bridge.

또 교량빔의 크기와 관계없이 인상장치를 호환적으로 사용할 수 있도록 하는 효과도 있다.In addition, regardless of the size of the bridge beam, there is an effect that allows the use of the impression device compatible.

본 고안은 도면에 도시된 일실시예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 당해 기술분야에 통상의 지식을 지닌자라면 이로부터 다양한 변형 및 균등한 타실시예가 가능하다는 점을 이해할 것이다.Although the present invention has been described with reference to one embodiment shown in the drawings, this is merely exemplary, and it will be understood by those skilled in the art that various modifications and equivalent other embodiments are possible.

Claims (7)

일,타측 상부구조(2)의 교량빔(21)을 각각 받혀주는 양측 교좌장치(22)가 교각(1)의 상면(11)에 설치되어 있는 교량에 있어서;In the bridge, which is provided on the upper surface 11 of the bridge (1), both bridge devices (22) for supporting the bridge beam (21) of the other side superstructure (2); 상기 양측 교량빔(21)의 전방에 장착되어 있으며, 중앙에는 하나 이상의 잭(6)이 장착되는 잭 장착부(31)가 형성되어 있고, 그 양측에는 전면 지지부(32)가 구비되어 있고, 이 전면 지지부(32)의 후방에는 상기 교좌장치가 삽입되는 교좌장치 삽입부(33)가 구비되어 있는 전방 브라켓(3)과;It is mounted in front of the both side beam beams 21, the center is provided with a jack mounting portion 31 in which at least one jack (6) is mounted, the front support portion 32 is provided on both sides thereof, the front A front bracket (3) provided at the rear of the support part (32) having a seat device insert (33) into which the seat device is inserted; 상기 양측 교량빔의 후방에 상기 전방브라켓(3)과 대칭되게 장착되어 있으며, 중앙에는 하나 이상의 잭이 장착되는 잭 장착부(41)가 형성되어 있고, 그 양측에는 후면 지지부(42)가 구비되어 있고, 이 후면 지지부(42)의 전방에 상기 교좌장치(22)가 삽입되는 교좌장치 삽입부(43)가 구비되어 있는 후방 브라켓(4); 및It is mounted symmetrically with the front bracket (3) in the rear of the bridge beams on both sides, the center is provided with a jack mounting portion 41 for mounting one or more jacks, the rear support portion 42 is provided on both sides A rear bracket (4) having a seat device insertion portion (43) into which the seat device (22) is inserted in front of the rear support (42); And 상기 전,후면 브라켓(3,4) 간의 폭을 조정하면서 교좌장치 삽입부(33,43)를 서로 연결하는 다수의 하부 연결대(s1)로 구성됨을 특징으로 하는 교량빔 인상장치.Bridge beam raising device, characterized in that consisting of a plurality of lower connecting rods (s1) connecting the bridge device insertion portion (33,43) to each other while adjusting the width between the front and rear brackets (3,4). 제 1항에 있어서, 상기 전,후방 브라켓(3,4)의 잭 장착부(31,41)는, 다수로 굴곡된 파이프 골조(311,411)와, 파이프 골조(311,411)의 중간에 돌출 형성된 중간 잭 장착판(312,412), 및 이 중간 잭 지지판(312,412)의 양측에 중간 지지판 보다 상대적으로 높은 위치에 돌출 형성되어 있는 양측 잭 장착판(313,413)으로 구성됨을 특징으로 하는 교량빔 인상장치.According to claim 1, The jack mounting portion (31, 41) of the front and rear brackets (3, 4), a plurality of curved pipe frame (311, 411), the intermediate jack mounting formed in the middle of the pipe frame (311, 411) A bridge beam raising apparatus comprising: a plate (312, 412), and both jack mounting plates (313, 413) protruding on both sides of the intermediate jack support plate (312, 412) at a position higher than the intermediate support plate. 제 1항에 있어서, 상기 전,후방 브라켓(3,4)의 양측에 형성된 전,후면 지지부(32,42)는, 상기 잭 장착부(31,41)의 양측에 연결되어 있으며, 연결대(s2)를 통해 신축되며 볼트(b)로 고정되는 상,하 수평대와 좌,우 수직대로 구성됨을 특징으로 하는 교량빔 인상장치.The front and rear support portions 32 and 42 formed on both sides of the front and rear brackets 3 and 4 are connected to both sides of the jack mounting portions 31 and 41, respectively, and the connecting table s2. Bridge beam lifting device, characterized in that it is configured to be stretched through and fixed to the bolt (b) up, down horizontal and left and right vertical. 제 3항에 있어서, 상기 상,하 수평대와 좌,우 수직대는, 하나 이상의 관통홀(h1)이 각기 형성된 파이프가 직각을 이루는 다수의 연결 파이프와, 상기 파이프에 삽입되고 다수의 간격유지홀(h2)이 형성되어 있는 다수의 연결대(s2), 및 상기 관통홀(h1)과 간격유지홀(h2)을 관통하여 체결되는 다수의 볼트(b)의 조립체로 구성됨을 특징으로 하는 교량빔 인상장치.According to claim 3, wherein the upper and lower horizontal and left and right vertical bands, a plurality of connecting pipes formed at right angles to the pipe, each formed with one or more through-holes (h1), and a plurality of spacing holes inserted into the pipe (h2) is a bridge beam lifting, characterized in that composed of a plurality of connecting rods (s2) and the assembly of a plurality of bolts (b) fastened through the through-hole (h1) and the interval maintaining hole (h2) Device. 제 1항에 있어서, 상기 전,후방 브라켓(3,4)의 하부 양측에 형성되어 있는 교좌장치 삽입부(33,43)는 상기 전,후면 지지부(32,42)의 하부 좌,우에서 돌출된 2개소의 종형 파이프(p1)로 구성되며, 이 종형 파이프(p1)에는 전,후방 브라켓(3,4)간의 폭을 조정할 수 있도록 상기 다수의 하부 연결대(s1)가 삽입되어 신축 고정됨을 특징으로 하는 교량빔 인상장치.The method of claim 1, wherein the insertion device insertion portion (33, 43) formed on both sides of the lower front and rear brackets (3, 4) protrude from the lower left and right of the front and rear support (32, 42). It consists of two vertical pipes (p1), characterized in that the plurality of lower connecting rods (s1) is inserted and fixed to the vertical pipe (p1) to adjust the width between the front and rear brackets (3,4). Bridge beam raising device. 제 5항에 있어서, 상기 종형 파이프(p1)에는 하나 이상의 관통홀(h1)이 형성되고 상기 하부 연결대(s1)에는 다수의 간격 유지홀(h2)이 형성되어 상기 관통홀(h1)과 간격유지홀(h2)에는 볼트(b)가 관통 체결됨을 특징으로 하는 교량빔 인상장치.The at least one through hole h1 is formed in the vertical pipe p1, and a plurality of gap maintaining holes h2 are formed in the lower connecting rod s1 to maintain the gap with the through hole h1. The bridge beam lifting device, characterized in that the bolt (b) is penetrated through the hole (h2). 제 5항에 있어서, 상기 교좌장치 삽입부(33,43)를 구성하는 종형 파이프(p1)의 상측에는 종형 파이프(p1)와 교량빔(21)사이의 밀착력을 향상시킬 수 있도록 신축패드(7)가 추가로 장착됨을 특징으로 하는 교량빔 인상장치.The expansion pad (7) according to claim 5, wherein the upper side of the vertical pipe (p1) constituting the stabilization device insertion portion (33, 43) to improve the adhesion between the vertical pipe (p1) and the bridge beam (21) Bridge beam raising device, characterized in that it is additionally mounted.
KR2020010030167U 2001-09-29 2001-09-29 Lifting apparatus of the bridge beam KR200274808Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020010030167U KR200274808Y1 (en) 2001-09-29 2001-09-29 Lifting apparatus of the bridge beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020010030167U KR200274808Y1 (en) 2001-09-29 2001-09-29 Lifting apparatus of the bridge beam

Publications (1)

Publication Number Publication Date
KR200274808Y1 true KR200274808Y1 (en) 2002-05-11

Family

ID=73109892

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020010030167U KR200274808Y1 (en) 2001-09-29 2001-09-29 Lifting apparatus of the bridge beam

Country Status (1)

Country Link
KR (1) KR200274808Y1 (en)

Similar Documents

Publication Publication Date Title
KR100683621B1 (en) Bracket for jacking-up upper structure having angle and lengch control-function
KR100931317B1 (en) Bridge using strut and tie member and construction method
KR100579597B1 (en) Temporary construction system and the construction method using the same
KR200274808Y1 (en) Lifting apparatus of the bridge beam
KR20200085573A (en) Gravity type leveling method for precast members including expansion joint
KR100489626B1 (en) Lifting method and apparatus of the bridge beam
KR100529517B1 (en) Method for pulling up equally the upper structure of a bridge using a raising bracket supporting load dispersedly, having a displacement measuring instrument
KR100418833B1 (en) Lifting method and apparatus of the bridge beam
KR19990001957A (en) Jack restraint device to raise superstructure of bridge
KR100450863B1 (en) Method and apparatus for pulling up an upper structure of bridge
KR200263287Y1 (en) Lifting apparatus of the bridge beam
KR102132338B1 (en) Steel Composite PSC Girder Including Arched Reinforcement
KR100402030B1 (en) Concrete form for src slim floor
KR20040076348A (en) Apparatus and method for pulling up and prevention of falling down of bridge beam
KR200286097Y1 (en) Lifting apparatus of the bridge beam
KR20090025748A (en) Closed conduit using corbel slab
KR102619855B1 (en) Construction method for continuous bridge using single supporter
KR20040038522A (en) Apparatus for pulling up bridge composed of inside and outside bracket unit using steel plate, and constructing method for repairing and reinforcing bridge using the apparatus
KR200333841Y1 (en) Temporary bridge structure using steel
KR20100003462A (en) Transporting device for girder beam
KR200406524Y1 (en) Temporary Construction System
KR100559441B1 (en) Method for raising a bridge and the raising structure
KR100538410B1 (en) The connecting device for pre-cast girder and installation method applied the connecting device
KR100580224B1 (en) Method for lifting and lowering structures using a fabricated bracket having easy attachment and detachment, and increased safety
KR200322332Y1 (en) Apparatus for pulling up bridge composed of inside and outside bracket unit using steel plate

Legal Events

Date Code Title Description
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T701 Written decision to grant on technology evaluation
FPAY Annual fee payment

Payment date: 20090420

Year of fee payment: 8