KR200240967Y1 - build-on inspection equipment for fixity of bridge - Google Patents

build-on inspection equipment for fixity of bridge Download PDF

Info

Publication number
KR200240967Y1
KR200240967Y1 KR2019990000429U KR19990000429U KR200240967Y1 KR 200240967 Y1 KR200240967 Y1 KR 200240967Y1 KR 2019990000429 U KR2019990000429 U KR 2019990000429U KR 19990000429 U KR19990000429 U KR 19990000429U KR 200240967 Y1 KR200240967 Y1 KR 200240967Y1
Authority
KR
South Korea
Prior art keywords
fixed
fixing
pedestal
support
construction
Prior art date
Application number
KR2019990000429U
Other languages
Korean (ko)
Other versions
KR19990017520U (en
Inventor
이성희
천영덕
Original Assignee
정진문
주식회사 용마엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 정진문, 주식회사 용마엔지니어링 filed Critical 정진문
Priority to KR2019990000429U priority Critical patent/KR200240967Y1/en
Publication of KR19990017520U publication Critical patent/KR19990017520U/en
Application granted granted Critical
Publication of KR200240967Y1 publication Critical patent/KR200240967Y1/en

Links

Abstract

본 고안은 교량점검시설중에서 특히 조립형 고정식 교량점검시설에 관한 것으로, 종래의 현장맞춤 용접고정식의 고정식 점검시설의 제반 단점을 제거하여, 구성요소들을 단순화하면서 그 부재들과 시공작업을 규격화하고 조립형으로 구성하여서, 원자재비의 절감과 시공 표준화에 의한 설비비의 절감과 공기단축 및 공사발,수주의 품질관리 및 시공상의 품질관리, 점검작업상의 작업효율을 높일 수 있는 조립형 고정식 교량점검시설을 제공함에 목적이 있는 것으로, 교각의 상단 둘레에 일정간격으로 매입식 보울트에 의해 고정되는 수개의 고정브라켓들과, 이 고정브라켓들에 고정되는 3가지 형태의 받침대들 및 일측 받침대의 중간에 설치되는 모서리받침대들을 규격화하고 상호간에 조립식으로 고정시키는 조립형으로 형성하며, 상기 받침대들과 모서리받침대들 간에 형성하는 발판의 구성을 규격품의 플로어데크를 조립식으로 고정하여 형성하며, 받침대들의 외측단에는 규격품의 핸드레일을 조립식으로 고정하여 형성하며, 받침대들의 외단측에는 조립식으로 마감재를 설치함에 특징이 있는 것이다.The present invention relates to a fixed bridge inspection facility, which is an assembly type, among the bridge inspection facilities, and to eliminating all the disadvantages of the conventional fixed inspection facility of the field-fitting welding, standardizing and assembling the members and the construction work while simplifying the components. It is composed of molds, and it provides a fixed fixed bridge inspection facility that can reduce the cost of raw materials by reducing raw material costs and standardize construction, and improve the efficiency of work by reducing the air and construction, quality control of construction orders and construction quality. It is intended to have several fixing brackets fixed by an embedded bolt at regular intervals around the top of the piers, three types of pedestals fixed to the fixing brackets, and corners installed in the middle of one side pedestal. Standardize the pedestals and form a prefabricated assembly to be mutually fixed to each other, and It is formed by fixing the floor deck of the standard product in a prefabricated manner, and the outer end of the pedestal is formed by prefabricating the handrail of the standard product, and installs the finishing material on the outer end of the pedestal. Is there.

Description

조립형 고정식 교량점검시설{build-on inspection equipment for fixity of bridge}Build-on inspection equipment for fixity of bridge

본 고안은 교량점검시설에 관한 것으로 특히 고정식 교량점검시설을 조립형으로 구성함에 특징이 있는 것이다.The present invention relates to a bridge inspection facility, and in particular, the fixed bridge inspection facility is characterized by the assembly type.

종래의 교량의 하부면이나 교좌장치의 점검을 위하여 제공된 교량점검시설에는, 교각의 주위에 일체형으로 고정한 고정식 점검시설과, 교량의 하단에서 교량과 교량사이를 이동하도록 자주식 이동수단을 갖는 이동식 점검시설이 있다.The bridge inspection facility provided for the inspection of the lower surface or bridge device of a conventional bridge includes a stationary inspection facility fixed integrally around the bridge, and a mobile inspection facility having self-propelled means for moving between the bridge and the bridge at the bottom of the bridge. There is this.

상기 구성중에서 고정식 점검시설의 구성과 설치방법은, 교각의 상단 둘레에 임의의 간격으로 수개의 고정브라켓을 매입식 보울트로 고정한 후, 이 수개의 고정브라켓들에 각각 수평받침대들을 용접으로 고정 부착하며, 수평받침대들 간의 내단측과 외단측에 각각 횡열받침대들을 용접고정하고, 일부 측면 받침대들에는 중간외측면에 모서리받침대들을 용접으로 고정 부착하여 교각의 둘레 전체에 장방형의 받침틀을 형성하여서, 이 받침틀의 상면에는 강판, 다공판 및 타공망등을 깔아 용접으로 부착하여 발판을 형성하고, 외단측 둘레에는 받침대들의 외단 상면에 수직의 지지봉을 용접으로 고정한 후 지지봉들의 사이에는 가로레일대나 안전망등을 다시 용접으로 고정시켜 핸드레일로 형성하는 구성이었다.In the above configuration, the configuration and installation method of the fixed inspection facility is to fix several fixing brackets at a predetermined interval around the top of the pier with an embedded bowl, and then fix the horizontal feet to each of the several fixing brackets by welding. , Weld fixing the horizontal row support on the inner end and the outer end side between the horizontal support, and welding the edge support on the middle outer side to some side pedestals by welding to form a rectangular support frame all around the piers. Steel plate, perforated plate, and perforated net are applied to the upper surface to form a scaffold, and the outer end is fixed by welding a vertical support rod to the upper end of the pedestal by welding, and then the horizontal rail or safety net is welded between the support rods. It was fixed by the structure and formed into a handrail.

이와같은 고정식 교량점검시설은 그 구성요소와 설치방법에 있어서, 교각의 상단 외측면에 매입 보울트에 의해 조립식으로 고정설치하는 고정브라켓과, 수평받침대들의 외단 상측에 고정되는 핸드레일의 지지봉을 제외한 나머지 모든 부재들을, 첫 공정인 고정브라켓들간의 설치규격이나 수평받침대들 간의 설치규격에 맞추어 시공현장에서 원자재를 절단 가공하여서, 고정브라켓을 설치한 후에 수평받침대, 횡열받침대, 모서리받침대, 발판, 핸드레일등을 연차적으로 용접작업에 의하여 일체로 고정시키는 현장맞춤시공으로 설치되는 구성이어서, 발주 및 시공시에는 물론 시공후의 보수유지에 여러 가지 문제점이 있었다.Such a fixed bridge inspection facility, except for the components and the installation method, except for a fixed bracket which is fixedly installed by a buried bolt on the upper outer surface of the pier, and a support rod of a handrail fixed to the upper end of the horizontal supports. All members are cut and processed at the construction site in accordance with the installation process between the fixed brackets or the horizontal supporters, which is the first process, and then the horizontal supporters, the horizontal supporters, the corner supporters, the footrests and the handrails are installed after the fixing brackets are installed. It is a configuration that is installed by the site-fitting construction to be fixed integrally by the welding work annually, there were a number of problems in the maintenance and maintenance after construction as well as during ordering and construction.

첫 번째 문제점은, 대부분의 교량용 교각의 규격은 몇가지의 유형으로 규격화되어 있음에도 불구하고 기존의 고정식 교량점검시설은 상술한 바와같이 현장맞춤식과 용접고정식으로 시공되고 구성되어 있으므로, 교량점검시설부재의 규격과 시공사양 및 시공작업의 표준화가 어려운 점이다.The first problem is that although most bridge pier standards are standardized in several types, the existing fixed bridge inspection facilities are constructed and configured as on-site and welded fixed as described above. Standardization, construction quantity and standardization of construction work are difficult.

교량점검시설부재의 규격과 시공사양 및 시공작업이 비표준화되면, 공사발주처는 공사발주시마다 매건별로 점검시설의 규격과 시공사양 및 시공작업에 소요되는 공기 및 시공단가등의 발주사양을 새롭게 작성하여야 하는 점에서 매우 비능률적이고,If the standard, construction quantity and construction work of the bridge inspection facility member are de-standardized, the construction orderer shall newly prepare the ordering specification of the inspection facility, construction quantity and construction cost and construction cost for each construction order. Very inefficient in terms of

시공업체도 해당공사의 수주전에는 자재의 소요량이나 공사기간등의 예측이 어려워 시공자재의 구입, 공사인원의 관리 및 수주공사의 배분등이 매우 어려웠으며, 수주가 되어도 수주후에서 공사시작하기전까지의 공사준비기간을 많이 소요하게되고, 시공작업시에도 많은 공정이 현장 맞춤식이므로 모든 부품의 원자재를 현장으로 운반한 후에 현장에서 공정에 맞추어 단계적으로 절단 및 가공을 하여 용접고정식으로 시공하여야 하므로, 운반비의 상승, 원자재의 낭비, 과대한 현장시공시설의 소요, 단계적시공에 의한 공기지연 등의 문제점들이 있었던 것이다.The contractor also had difficulty in predicting the requirements of the materials and the construction period before the contract was received. Therefore, it was very difficult to purchase construction materials, manage the construction personnel, and distribute the construction work. It takes a lot of time to prepare for the construction, and many processes are custom-made even during the construction work. Therefore, the raw materials of all parts must be transported to the site and then cut and processed step by step according to the process at the site to be fixed by welding. There were problems such as rise, waste of raw materials, excessive site construction facilities, and air delay due to phased construction.

상기한 문제점들은 발주처는 물론 시공업체의 품질관리와 공사시의 감리를 어렵게 하므로, 생산원가 및 설비비용을 상승시키게 된다.The above problems make it difficult to control the quality management and construction of the contractor as well as the client, thereby increasing the production cost and equipment cost.

두 번째 문제점은, 점검시설의 구성이 모든 구성부재들간을 용접으로 고정하는 구성이므로, 이들 용접부위에 방청도료를 도색함에 따른 상당한 도료비와 공정이 소요되어 공사단가가 높아지고, 시공후에도 지속적으로 주기적인 도색작업을 실시하여야 하는 점과 미관이 불량한 단점이 있었고, 시설을 사용중에 점검시설의 부분적인 파손이나 일부부재의 기능저하에 의하여 부재의 교체, 수리등의 보수, 유지작업에 있어서 각부재들의 연결이 용접고정식으로 형성되어 부분적인 보수작업이 어렵고 작업비도 상당히 소요되는 문제점이 있었으며,The second problem is that the inspection facility is configured to fix all the components by welding, which requires considerable paint cost and process by coating the rust-preventive paint on these welded parts, resulting in high construction cost and continuous maintenance after construction. There was a disadvantage that the painting work should be performed and the aesthetics were poor, and the connection of each member in repair, maintenance, etc. Formed by this welding fixed type, there is a problem that the partial repair work is difficult and the work cost is also considerably high.

세 번째 문제점은, 상기 기존의 고정식 점검시설은 구성요소가 많은 점에서도 원자재비의 상승과 이로 인한 공사비의 상승요인이 있었고, 모든 부재들이 각 공사별로 용접식 단품으로 제작되어야 하므로 대량생산이 어려워 안정적인 자재수급과 품질관리가 어려웠던 것이다.The third problem is that the existing fixed inspection facility had a lot of components, and there was a factor of increase in raw material cost and construction cost due to this, and it was difficult for mass production because all members had to be manufactured by welding separately for each construction. Supply and quality control was difficult.

본 고안은 상기와 같은 기존의 고정식 점검시설의 문제점들을 해결하고져 제공되는 것으로서, 고정식 교량점검시설을 형성함에 있어서 구성요소들을 단순화하면서 그 부재들과 시공작업을 규격화하고 조립형으로 구성하여서, 원자재비의 절감과 시공 표준화에 의한 설비비의 절감과 공기단축 및 공사발,수주의 품질관리 및 시공상의 품질관리, 점검작업상의 작업효율을 높일 수 있는 조립형 고정식 교량점검시설을 제공함에 목적이 있는 것이다.The present invention is provided to solve the problems of the existing fixed inspection facilities as described above, by simplifying the components in forming the fixed bridge inspection facilities, standardizing the members and construction work, and composed of assembled materials, The purpose is to reduce the cost of equipment by standardization of construction and standardization, and to provide an assembly-type fixed bridge inspection facility that can improve the work efficiency of air shortening, construction start-up, order quality control and construction quality, and inspection work.

도 1은 본 고안에 의한 일실시예 조립형 고정식 교량점검시설의 사시도1 is a perspective view of an embodiment assembled fixed bridge inspection facility according to the present invention

도 2는 본 고안에 의한 일실시예 조립형 고정식 교량점검시설의 설치상태측면도Figure 2 is a side view of the installation state of one embodiment assembled fixed bridge inspection facility according to the present invention

도 3은 본 고안에 의한 일실시예 조립형 고정식 교량점검시설의 설치상태평면도Figure 3 is an installation state plan view of one embodiment assembled fixed bridge inspection facility according to the present invention

도 4는 도3의 구성중 A-A선 단면 확대도4 is an enlarged cross-sectional view of the A-A line in the configuration of FIG.

도 5는 본 고안에 의한 일실시예 조립형 고정식 교량점검시설의 받침틀 평면도Figure 5 is a plan view of the support frame of an embodiment assembled fixed bridge inspection facility according to the present invention

도 6은 본 고안에 의한 일실시의 조립형 고정식 교량점검시설의 구성중 기본형 받침대의 조립사시도6 is a perspective view of the assembly of the basic stand of the configuration of the fixed bridge inspection facility of one embodiment according to the present invention

도 7은 본 고안에 의한 일실시예 조립형 교량점검시설의 구성중 기본형 받침대의 조립상태 측면도Figure 7 is a side view of the assembled state of the base pedestal of the embodiment of the assembled bridge inspection facility according to the present invention

도 8은 본 고안에 의한 일실시예 조립형 고정식 교량점검시설의 구성중 우측면 받침대의 조립사시도Figure 8 is an assembly perspective view of the right side pedestal of the embodiment of the assembled fixed bridge inspection facility according to the present invention

도 9는 본 고안에 의한 일실시예 조립형 고정식 교량점검시설의 구성중 우측면 받침대의 조립상태 평면도9 is a plan view of the assembled state of the right side pedestal of the embodiment of the assembled fixed bridge inspection facility according to the present invention

도10은 본 고안에 의한 일실시예 조립형 고정식 교량점검시설의 구성중 좌측면 받침대와 모서리받침대의 조립사시도Figure 10 is an assembly perspective view of the left side pedestal and the corner support of the embodiment of the assembled fixed bridge inspection facility according to the present invention

도11은 본 고안에 의한 일실시예 조립형 고정식 교량점검시설의 구성중 좌측면 받침대와 모서리 받침대의 조립부 확대 단면도Figure 11 is an enlarged cross-sectional view of the assembly of the left side pedestal and the corner pedestal of the embodiment of the assembled fixed bridge inspection facility according to the present invention

도12는 본 고안의 일실시예 조립형 고정식 교량점검시설에 사용되는 플로어데크의 단면도Figure 12 is a cross-sectional view of the floor deck used in the embodiment fixed bridge inspection facility of the present invention

도13은 본 고안의 일실시예 조립형 고정식 교량점검시설의 구성중 플로어데크의 조립구조 및 핸드레일, 마감판의 조립구조 단면도Figure 13 is a cross-sectional view of the assembly structure of the floor deck and the assembly structure of the handrail, the closing plate of the assembled bridge fixed inspection system of an embodiment of the present invention

도14는 본 고안의 다른실시예 조립형 고정식 교량점검시설의 사시도14 is a perspective view of another embodiment of the assembled fixed bridge inspection facility of the present invention

도15는 본 고안의 다른실시예 조립형 고정식 교량점검시설의 평면도15 is a plan view of another embodiment of the assembled fixed bridge inspection facility of the present invention

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

100:일실시예 조립형 고정식 교량점검시설100: one embodiment assembly type fixed bridge inspection facility

100a:다른실시예의 조립형 고정식 교량점검시설100a: Prefabricated fixed bridge inspection facility in another embodiment

20:고정브라켓 22:교각 고정홀 21:고정판재20: fixing bracket 22: piercing fixing hole 21: fixing plate

23,24:받침대 고정판 26:받침대 고정홀 27:보강부재23, 24: Base fixing plate 26: Base fixing hole 27: Reinforcing member

30:기본형 받침대 31,32;받침대들의 찬넬부재 33:받침대들의 연결대30: standard pedestal 31, 32; channel member of the pedestal 33: connection of the pedestal

34:브라켓 고정홀 35,35a,45:지지봉 고정홀34: Bracket fixing hole 35, 35a, 45: Support rod fixing hole

37:모서리받침대 고정홀 39,49:마감판 고정홀37: Corner stand fixing hole 39, 49: Finishing plate fixing hole

30a,30b,30c,30d:좌우측면 받침대 36a,36b:모서리받침대용 측면연결구30a, 30b, 30c, 30d: Left and Right Side Stands 36a, 36b: Side Connectors for Corner Supports

40:모서리받침대 41,42:모서리받침대 찬넬부재40: corner stand 41, 42: corner stand channel member

43:모서리받침대 연결대 46:측면연결구 47:측면연결구 고정홀43: corner support connecting rod 46: side connector 47: side connector fixing hole

50:플로어데크 51:상판 52,53:전,후면세로대50: floor deck 51: tops 52, 53: front, rear, vertical

52a,53a:전후면 절곡단 60:클립보울트52a, 53a: front and rear bending end 60: clip bolt

70:핸드레일 71:핸드레일 지지봉 72:고정홀70: handrail 71: handrail support rod 72: fixing hole

73,74:가로레일고정홀 76,77:상하 가로레일대 78:세로레일대73,74: horizontal rail fixing hole 76, 77: upper and lower horizontal rail 78: vertical rail

80:마감판 81:마감판 고정홀80: finish plate 81: finish plate fixing hole

Ba:매입보울트 B1~B4:보울트 Na:너트 N1~N4:너트Ba: Embedded bolt B1-B4: Bolt Na: Nut N1-N4: Nut

B5:고정피스B5: fixed piece

상기 목적을 달성하고져 본 고안의 구성은, 교각의 상단 둘레에 일정간격으로 매입식 보울트에 의해 고정되는 수개의 고정브라켓들과, 이 고정브라켓들에 고정되는 3가지 형태의 받침대들 및 일측 받침대의 중간에 설치되는 모서리받침대들을 규격화하고 상호간에 조립식으로 고정시키는 조립형으로 형성하며, 상기 받침대들과 모서리받침대들 간에 형성하는 발판의 구성을 규격품의 플로어데크를 조립식으로 고정하여 형성하며, 받침대들의 외측단에는 규격품의 핸드레일을 조립식으로 고정하여 형성하며, 받침대들의 외단측에는 조립식으로 마감재를 설치함에 특징이 있는 것이다.In order to achieve the above object, the construction of the present invention is made up of several fixing brackets fixed by a buried bolt at a predetermined interval around the upper end of the piers, three types of pedestals and one side pedestal fixed to the fixing brackets. Formed in the form of assembly to standardize the corner brackets installed in the middle and prefabricated between each other, and to form the configuration of the scaffold formed between the pedestal and the corner support to form a fixed floor deck of the standard product, the outside of the pedestal End is formed by prefabricating the fixed handrail of the standard product, and the outer end side of the pedestal is characterized by installing the finishing material in the prefabricated.

이하 본 고안을 첨부된 일실시예들의 도면과 함께 설명하면 다음과 같다.Hereinafter, the present invention will be described with reference to the accompanying drawings.

도1 내지 도13에 도시한 본 고안의 일실시예 조립형 고정식 교량점검시설 (100)의 구성은 철도교량중 전철주 없는 교각에 설치되는 형으로서, 교각(P)의 상단 둘레에 일정간격으로 매입식 보울트에 의해 고정되는 수개의 고정브라켓(20)과, 이 수개의 고정브라켓(20)에 조립식으로 고정되는 받침대들을 기본형 받침대(30)들, 좌우측면 받침대(30a)(30b)(30c)(30d)들 및 상기 좌우측면 받침대(30a)(30b)(30c)(30d)들의 중간부 외측면에 조립고정되는 모서리받침대(40)들의 3가지 형태를 사용하여, 상기 받침대들의 상면에 플로어데크(50)를 조립하여 발판을 형성하고, 받침대들의 외단측에 규격품의 핸드레일(70)과 규격품의 마감판(80)을 조립식으로 고정설치한 구성이다.1 to 13, the assembly type fixed bridge inspection facility 100 according to an embodiment of the present invention is a type installed in a pier without a train pole of a railway bridge, and at regular intervals around the upper end of the bridge P. Several fixing brackets 20 fixed by the buried bolts and the pedestals fixedly assembled to the several fixing brackets 20 are provided with the basic pedestals 30 and the left and right pedestals 30a, 30b, 30c. Floor decks on the upper surfaces of the pedestals, using three types of corner pedestals 40 which are assembled and fixed to the outer sides of the middle portions of the 30d and the left and right side pedestals 30a, 30b, 30c and 30d. (50) is assembled to form a footrest, and is a configuration in which the handrail 70 of the standard product and the finishing plate 80 of the standard product are fixedly installed on the outer ends of the pedestals.

고정브라켓(20)은 교각(P)의 상단 외측면에 일정 간격으로 매입보울트(Ba)에 의해 고정설치되어 점검시설 전체를 교각에 지지시키는 구성으로서, 매입보울트(Ba)들이 끼워지는 수개의 교각 고정홀(22)들을 사변 모서리측에 구비하여 교각(P)의 외측면에 부착되는 고정판재(21)와, 상기 고정판재(21)의 중앙측에서 판면과 직교방향이면서 서로간에 일정간격을 갖고 수직으로 고정되며 수개의 받침대 고정홀(26)들을 갖는 2개의 받침대고정판(23)(24)과, 이들 2개의 받침대고정판(23)(24)의 상단일부에서 각각 고정판재(21)와 일체로 용접된 보강부재(27)들을 구비한 구성이다(도4,6,7 참조).The fixing bracket 20 is fixed to the upper outer surface of the pier P at fixed intervals by a buried bolt Ba to support the entire inspection facility on the pier, where several pier to which the buried bolts Ba are fitted. Fixing plate 22 is provided on the side of the corner of the fixing hole 22 is attached to the outer surface of the pier (P), and at the center side of the fixing plate member 21 in a direction perpendicular to the plate surface and have a predetermined distance from each other Two pedestal fixing plates 23 and 24 which are vertically fixed and have several pedestal fixing holes 26, and at the upper end portions of these two pedestal fixing plates 23 and 24, respectively, integrally with the fixing plate 21. The configuration is provided with welded reinforcing members 27 (see FIGS. 4, 6 and 7).

상기 고정브라켓(20)에 조립식으로 설치되어 교각면과 직교방향으로 설치되는 받침대의 구성은 교각(P)의 정배면에 설치되는 기본형 받침대(30)와, 교각(P)의좌우측면에 설치되는 좌우측면 받침대(30a)(30b)(30c)(30d)들로 구성된다.The assembly of the pedestal is installed on the fixing bracket 20 and installed in a direction perpendicular to the pier surface is installed on the left and right sides of the base type pedestal 30 and the pier P, which is installed on the front surface of the pier (P) It consists of the left-right side pedestals 30a, 30b, 30c, and 30d.

기본형 받침대(30)의 구성은, 두개의 [ 자형 찬넬부재(31)(32)들을 상기 고정브라켓(20)의 2개의 받침대고정판(23)(24)에 외접상태로 밀접하게 끼워지는 정도의 폭을 갖고 수개의 연결대(33)로 용접 고정한 구성으로서, 상기 2개의 받침대고정판(23)(24)에 끼워지는 찬넬부재(31)(32)들의 내단측 웨브에는 상기 연결판재의 받침대 고정홀(26)들과 동축상으로 관통하는 수개의 브라켓 고정홀(34)들을 형성하고, 외단측 웨브에는 후술하는 마감판(80)의 조립 내단측에 핸드레일 지지봉(71)이 맞닿아 조립될수 있을 정도의 일정간격을 두고 지지봉 고정홀(35)들을 상하로 형성하며, 외단측 상단플랜지에는 끝단부에 마감판 고정홀(39)을 형성한 구성이다(도4,6,7 참조).The basic pedestal 30 has a width such that the two [shaped channel members 31, 32 are closely fitted to the two pedestal fixing plates 23, 24 of the fixing bracket 20 in an external state. In the inner end side webs of the channel members 31 and 32 to be fitted to the two pedestal fixing plates 23 and 24, the pedestal fixing hole 26 of the connecting plate material ) And several bracket fixing holes 34 penetrating coaxially with each other, and the handrail support rod 71 is assembled to the inner end side of the closing plate 80 to be described later on the outer side web. The support rod fixing holes 35 are formed at a predetermined interval up and down, and the closing plate fixing hole 39 is formed at the end of the outer flange side upper flange (see FIGS. 4, 6 and 7).

측면형 받침대의 구성은 좌측형과 우측형으로 구성되어 좌,우측형 각각에서 2개가 대칭형으로 형성되는 좌측면 받침대(30a)(30b)와 우측면 받침대(30c)(30d)로 구성된다.The side of the pedestal is composed of the left and right sides are composed of left and right pedestals 30a, 30b and right side pedestals 30c and 30d, respectively, two of which are formed symmetrically.

2개의 우측면받침대(30c)(30d)는, 상기 기본형받침대(30)와 기본적인 골격이 동일하게 두개의 [ 자형 찬넬부재(31)(32)들을 상기 고정브라켓(20)의 2개의 받침대고정판(23)(24)에 외접상태로 밀접하게 끼워지는 정도의 폭을 갖고 수개의 연결대(33)로 용접 고정한 구성이고, 각각의 외단측 웨브에는 후술하는 마감판(80)의 조립 내단측에 핸드레일 지지봉(71)이 맞닿아 조립될수 있을 정도의 일정간격을 두고 지지봉 고정홀(35)들을 상하로 형성하며, 외단측 상단플랜지에는 끝단부에 마감판 고정홀(39)을 형성한 구성으로서, 이들 각각의 외단측 외측면에는 각각 2장의판재로 되어 웨브의 외단측 선단에서 후술하는 모서리받침대(40)가 받침대의 외단과 일렬로 조립되는 정도의 폭을 두고, 외측면에서부터 상하 플랜지들에 함께 고정되어 외측방으로 일정길이 돌출되며 모서리받침대 고정홀(37)들을 갖는 측면 연결구(36b)들을 형성한 구성이다(도8,9 참조).The two right side support (30c) (30d), the basic support base 30 and the same basic skeleton has two [shaped channel members 31, 32] two pedestal fixed plate 23 of the fixing bracket (20) ) Is a structure that is welded and fixed with several connecting rods 33, having a width that is closely fitted in a circumferential state, and each of the outer end webs has a handrail support rod on the inner end side of the assembling plate 80 to be described later. The support rod fixing holes 35 are formed up and down with a predetermined interval such that 71 can be assembled in contact with each other, and a closing plate fixing hole 39 is formed at the end of each of the outer flanges. The outer side of the outer side of each of the two pieces of plate material, the width of the corner support 40, which will be described later at the outer end of the web to be assembled in line with the outer end of the pedestal, and is fixed to the upper and lower flanges together from the outer side It protrudes a certain length to the outside The side connector 36b which has the corner stand fixing holes 37 is formed (refer FIG. 8, 9).

2개의 좌측면받침대(30a)(30b)는, 상기 우측면받침대(30c)(30d)와 기본적인 골격이 동일하되, 각각의 찬넬 웨브의 외단측과 상단플랜지에는 상기 우측면받침대와 동일한 구성의 지지봉 고정홀(35)들과 마감판 고정홀(39)들이 형성되며, 전체 길이가 우측면받침대보다 일정길이 길게 형성된 구성으로서, 상이하게는 이들 각각의 중간부 외면측에는 각각 2장의 판재로 되어 웨브와 상하 플랜지들에 함께 고정되어 외측방으로 일정길이 돌출되고 모서리받침대 고정홀(37)들을 갖는 측면연결구(36a)들이 형성되고, 상기 2장의 측면연결구(36a)들의 판재 사이에는 양측 찬넬들을 관통하는 핸드레일의 지지봉 고정홀(35a)을 형성한 구성이다(도10,11 참조).The two left side supporters 30a and 30b have the same basic structure as the right side supporters 30c and 30d, but the support rod fixing holes having the same configuration as the right side supporters on the outer side and the upper flange of each channel web. (35) and the closing plate fixing holes 39 are formed, the overall length is formed a certain length longer than the right side support, differently, each of these intermediate portion of the outer surface side is made of two sheets of web and upper and lower flanges Side connectors 36a are formed to be fixed together at a predetermined length to protrude outward and have corner support fixing holes 37, and the support rods of the handrails penetrate both channels between the plates of the two side connectors 36a. The fixing hole 35a is formed (refer to FIG. 10, 11).

상기 좌우측면받침대(30a)(30b)(30c)(30d)들의 중간부에 직교방향으로 조립되는 모서리받침대(40)의 구성은 4개가 동일한 구성으로서, 두개의 [ 자형 찬넬부재(41)(42)들을 상기 좌우측면받침대(30a)(30b)(30c)(30d)들의 측면연결구(36a) (36b)들에 외접상태로 밀접하게 끼워지는 정도의 폭을 갖고 수개의 연결대(43)로 용접 고정되고, 각각의 외단측 웨브에는 상기 기본형받침대 및 좌우측면받침대들에 형성한 지지봉 고정홀(35)들과 동일한 지지봉 고정홀(45)들이 상하로 형성되며, 각각의 외단측 상단플랜지에도 마감판 고정홀(39)과 동일한 구성의 마감판고정홀(49)을 형성한 구성은 동일하되, 각각의 내단측에는 웨브를 연장하여 상기 측면 연결구(36a)(36b)들에 외접하는 측면연결구(46)들을 형성하여서 상기 측면연결구(36a)(36b)들의 모서리받침대 고정홀(37)들과 대응하는 위치에 수개의 측면연결구 고정홀(47)들을 형성한 구성이다(도10,11 참조).The left and right side supporters 30a, 30b, 30c, 30d, the corner support 40 is assembled in the orthogonal direction to the middle portion of the configuration of the same configuration, the four configuration, two [-shaped channel member 41, 42 ) Are welded and secured with several connecting members 43 having a width that is close enough to be externally fitted to the side connectors 36a and 36b of the left and right side rests 30a, 30b, 30c and 30d. Each outer end web has support rod fixing holes 45 which are the same as the support rod fixing holes 35 formed in the basic support base and the left and right side supporters, and is formed up and down. The end plate fixing hole 49 having the same configuration as that of the hole 39 has the same configuration, but each inner end side of the side connectors 46 external to the side connectors 36a and 36b by extending a web. And corresponding to the corner support fixing holes 37 of the side connectors 36a and 36b. A block forming a number of side connector mounting holes 47 in the value (see Fig. 10, 11).

점검통로를 형성하는 일 부재인 발판의 구성은, 다공판으로 형성되어 좌우로 긴 상판(51)과, 이 상판(51)에서 전후단을 하향으로 일정높이 절곡하여 형성한 전,후면세로대(52)(53)와, 상기 전면세로대(52)의 끝단을 형으로 절곡한 전면절곡단(52a)과, 상기 후면세로대(53)의 끝단을 상기 전면절곡단(52a)이 상단내부로 감싸지게 형으로 절곡한 후면절곡단(53a)이 형성된 기성품의 다공판형 플로어데크(50)를 사용하여, 수개의 플로어데크(50)들을 상기 기본형 받침대(30)들 및 좌우측면 받침대(30a)(30b)(30c)(30d)들의 상단에 얹어 받침대들의 길이에 맞추어 수개를 폭방향으로 조립한 후, 상기 받침대들에 얹어진 전면절곡단(52a) 및 후면절곡단(53a)들을 두개의 [ 자형 찬넬부재(31)(32)(41)(42)들 중에서 일측 찬넬의 상단플랜지에 클립보울트(clip bolt)(60)로 고정시키는 구성이다(도2,12,13 참조).The structure of the scaffold which is a member which forms the inspection passage is formed by the perforated plate, which is formed on the left and right sides of the upper plate 51, and the front and rear vertical stands 52 formed by bending the front and rear ends downwardly at a predetermined height from the upper plate 51. 53, the front bent end 52a bent to form an end of the front vertical band 52, and the front end of the rear vertical band 53 so that the front end 52a is wrapped inside the upper end. Using the ready-made porous plate-shaped floor deck 50 having the rear bent end 53a formed thereon, several floor decks 50 are mounted on the basic pedestals 30 and the left and right side pedestals 30a and 30b ( 30c) and assembled several pieces in the width direction in accordance with the length of the pedestal on the top of the (30d), and then the front bent end 52a and the rear bent end (53a) placed on the pedestal two [-shaped channel member ( Among the 31, 32, 41, and 42, it is fixed to the upper flange of one side channel with a clip bolt 60 (See Fig. 2,12,13).

점검통로의 안전장치인 핸드레일(70)의 구성은, 상기 기본형 받침대(30)들의 외단측에서 두개의 [ 자형 찬넬부재(31)(32) 사이와, 상기 좌우측면 받침대(30a) (30b)(30c)(30d)들의 두개의 [ 자형 찬넬부재(31)(32) 사이 및 상기 모서리받침대(40)들의 외단측 두개의 [ 자형 찬넬부재(41)(42) 사이에 수직으로 끼워지는 관으로 형성되어, 하단 일측에는 상기 지지봉 고정홀(35)(45)들에 대응하여 관통된 고정홀(72)들이 형성되며, 상단측에는 상하로 일정 간격을 갖고 좌우로 관통된 가로레일고정홀(73)(74)이 형성된 수개의 핸드레일 지지봉(71)들과,The configuration of the handrail 70, which is a safety device for the inspection passage, is provided between two [-shaped channel members 31, 32] at the outer ends of the basic pedestals 30, and the left and right side pedestals 30a, 30b. (30c) between the two [-shaped channel members 31, 32 of the 30d) and the two [-shaped channel members (41, 42) on the outer side of the corner support 40 vertically It is formed, the fixing hole 72 penetrating corresponding to the support rod fixing holes 35, 45 is formed on one side of the lower side, and the horizontal rail fixing hole 73 penetrated to the left and right at regular intervals on the upper side Several handrail supporting rods 71 formed with 74,

이들 핸드레일 지지봉(71)들 사이에서 상기 가로레일 고정홀(73)(74)들에 가로방향으로 끼워져 고정되는 상하 가로레일대(76)(77)들과, 상기 상하 가로레일대(76)(77)들 간에 수직방향으로 일정간격의 지그재그형으로 고정 부착된 세로레일대(78)로 구성된다(도1,4,6 참조).Vertical rail rails 76, 77 and vertical rail rails 76 and 77 that are inserted into and fixed to the horizontal rail fixing holes 73 and 74 between the handrail supporting rods 71 and the horizontal rail rails 76. It consists of longitudinal rails 78 fixedly attached in a zigzag shape at regular intervals in the vertical direction between the 77 (see Figs. 1, 4 and 6).

마감판(80)은 구성은, 받침대들의 외측단에서 상하단플랜지폭을 감싸는 정도의 폭으로 아연도 강판이나 스테인레스판을 ]형 단면으로 절곡하여 형성하되, 상하단 플랜지에는 상기 받침대들의 외측단 상하단 플랜지에 형성한 마감판 고정홀(39)들과 대응하는 위치에 마감판 고정홀(81)을 형성한 구성이다(도4,13 참조).The closing plate 80 is formed by bending a galvanized steel sheet or a stainless steel plate in a cross-section with a width that covers the upper and lower flange widths at the outer ends of the pedestals, and the upper and lower flanges are formed on the upper and lower flanges of the outer ends of the pedestals. The finishing plate fixing hole 81 is formed at a position corresponding to the formed closing plate fixing holes 39 (see FIGS. 4 and 13).

도면중 미설명 부호 B1~B4, N1~N4 들은 고정브라켓(20) 및 받침대들을 조립하는 보울트 및 너트들이며, 부호 B5은 받침대들에 마감판(80)들을 조립하는 고정피스를 표시한 것이다.In the drawings, reference numerals B1 to B4 and N1 to N4 are bolts and nuts for assembling the fixing bracket 20 and pedestals, and B5 denotes a fixing piece for assembling the closing plate 80 to the pedestals.

이와같은 구성의 일실시예 조립식 점검시설은 다음과 같은 조립방법에 의하여 시공된다.One embodiment of such a configuration prefabricated inspection facility is constructed by the following assembly method.

고정브라켓(20)의 교각(P) 외측면에의 고정시공은 공지한 고정식 점검시설의 고정브라켓 시공방법과 동일하게, 기본형 받침대(30)들 및 좌우측면 받침대(30a)(30b)(30c)(30d)들을 일정간격으로 설치할 수 있도록, 교각(P)의 외측면에 각조의 매입보울트(Ba)들을 매입고정 한 후, 고정판재(21)를 매입보울트(Ba)들에 교각 고정홀(22)을 맞추어 끼우고 외측면에서 너트(Na)를 조여 고정한다.The fixed construction of the fixing bracket 20 on the outer side of the piers P is the same as the method of installing the fixed bracket of the fixed inspection facility, and the basic pedestals 30 and the left and right side pedestals 30a, 30b, 30c. After fixing the purchase bolts of each set on the outer surface of the pier P so that the 30ds can be installed at regular intervals, the fixing plate 21 is piercing fixing holes 22 to the buying bolts Ba. ) And fix it by tightening nut (Na) at the outer side.

상기와 같이 교각(P)의 외측면 둘레에 고정브라켓(20)들이 임의의 간격으로 고정 설치되면, 상기 고정브라켓(20)의 받침대고정판(23)(24)들에 대하여 도6 및 도8와 같이, 조립할 기본형받침대(30)들 및 좌우측면받침대(30a)(30b)(30c)(30d)들의 내단측을 외접상태로 끼워서 받침대 고정홀(26)에 브라켓 고정홀(34)을 맞추어 보울트(B1) 및 너트(N1)를 조여 조립 고정한다.6 and 8 with respect to the pedestal fixing plates 23 and 24 of the fixing bracket 20 when the fixing brackets 20 are fixedly installed at random intervals around the outer surface of the piers P as described above. Likewise, by fitting the inner end side of the basic support base 30 and the left and right side support (30a) (30b) (30c) (30d) to be assembled in a circumferential state to align the bracket fixing hole (34) to the pedestal fixing hole 26 bolt ( B1) and the nut (N1) are tightened to secure the assembly.

상기와 같이 고정브라켓(20)들에 기본형받침대(30)들 및 좌우측면받침대(30a)(30b)(30c)(30d)들이 조립 고정되면,When the basic type support 30 and the left and right side support (30a) (30b) 30c (30d) is assembled and fixed to the fixing brackets 20,

좌측면받침대(30a)(30b)들의 중간부 외측면의 측면연결구(36a)(36b)에는 각각 도8,9 와 같이 모서리받침대(40)들을, 상기 측면연결구(36a)(36b)에는 측면연결구(46)를 외접상태로 끼워 모서리받침대 고정홀(37)들과 측면연결구 고정홀(47)들을 맞추어 보울트(B2), 너트(N2)를 조여 직교방향으로 조립하고,The side connectors 36a and 36b on the outer side of the middle portion of the left side support 30a and 30b are provided with the corner supports 40 as shown in FIGS. 8 and 9, respectively, and the side connectors 36a and 36b are connected to the side connectors. Assemble (46) in an external state to assemble the orthogonal direction by tightening the bolt (B2) and nut (N2) by aligning the corner support fixing holes (37) and the side connector fixing holes (47).

우측면받침대(30c)(30d)들의 외단측 외측면의 측면연결구(36b)에는 각각 도10,11과 같이 모서리받침대(40)들을, 상기 측면연결구(36a)에는 측면연결구(46)를 외접상태로 끼워 모서리받침대 고정홀(37)들과 측면연결구 고정홀(47)들을 맞추어 보울트(B3), 너트(N3)를 조여 직교방향으로 조립한다.In the side connector (36b) of the outer side of the outer side of the right side support (30c) (30d), as shown in Figs. 10 and 11, respectively, the corner support 40, the side connector (36a) to the side connector 46 in an external state Insert the corner support fixing holes 37 and the side connector fixing holes 47 to tighten the bolts B3 and nuts N3 to assemble in the orthogonal direction.

상기와 같이 기본형받침대(30)들 및 좌우측면받침대(30a)(30b)(30c)(30d)들에 모서리받침대(40)들이 조립되면 도5와 같이 점검대의 받침틀이 완성되는 바, 그 상면에 플로어데크(50)를 얹어 발판을 조립 고정한다.When the corner support 40 is assembled to the basic type support 30 and the left and right side support (30a) (30b) (30c) (30d) as described above, the support frame of the support stand is completed as shown in Figure 5, the upper surface Put the floor deck 50 to assemble and secure the footrest.

플로어데크(50)의 조립 고정은 교각(P)의 정배면 및 좌우측면에서 각각 독립적인 규격으로 시공된다.Assembly fixing of the floor deck 50 is constructed in independent standards on the front and rear and left and right sides of the piers (P), respectively.

정배면에서의 플로어데크(50)의 조립 고정은, 도1,3과 같이 교각(P)의 정배면에 설치된 기본형받침대(30)들의 상면과 좌우 양끝의 모서리받침대(40)들의 일부면에 대하여 플로어데크(50)를 가로방향으로 설치하는 바, 정배면의 전체길이를 2등분한 길이의 플로어데크(50)들을 중앙측 기본형받침대(30)를 중심으로 좌우 양쪽에서 기본형받침대(30)들의 길이에서 외단측에 설치되는 핸드레일 지지봉(71)의 내측단까지 폭방향으로 3장을 연속적으로 조립하여 얹은 후, 도13과 같이 플로어데크(50)들간의 후면절곡단(53a)에 전면절곡단(52a)이 겹쳐 감싸진 폭 방향 조립부분을 각각의 받침대들을 형성하는 부재인 찬넬부재(31)(32)(41)(42)들 중에서 일측 찬넬의 상단플랜지에 클립보울트(60)를 사용하여 조립식으로 고정한다.Assembly and fixation of the floor deck 50 on the front surface, as shown in Figures 1 and 3 with respect to the upper surface of the basic support base 30 installed on the rear surface of the piers (P) and a part of the surface of the left and right corner butts 40 Since the floor deck 50 is installed in the horizontal direction, the lengths of the base decks 30 on the left and right sides of the floor decks 50 having a length equal to two of the total length of the front surface are centered on the base support base 30 at the center. After assembling and mounting three pieces in the width direction to the inner end of the handrail support rod 71 is installed on the outer end side in the front side, the front bending end to the rear bending end 53a between the floor deck 50 as shown in FIG. Using the clip bolt 60 on the upper flange of one channel among the channel members 31, 32, 41, and 42, which are members forming the respective pedestals, in which the widthwise assembled portion 52a is overlapped. Fix it assembling.

좌측면에서의 플로어데크(50)의 조립 고정은, 도1,3,10,11과 같이 교각(P)의 좌측면에 설치된 좌측면받침대(30a)(30b)들의 상면에 대하여 플로어데크(50)를 가로방향으로 설치하는 바, 좌측면받침대(30a)(30b)들의 길이에서 중간부 측면연결구(36a)까지는 정배면에 조립된 플로어데크(50)들 간의 내측공간폭으로 길이를 맞추어 폭방향으로 3장을 연속적으로 조립하여 얹고, 중간부 측면연결구(36a) 이후에서 좌측면받침대(30a)(30b)들의 외단측까지는 각각의 내측 찬넬부재간의 폭으로 좌우 길이를 맞추어 폭방향으로 3장을 연속적으로 조립하여 얹은 후, 정배면에서의 플로어데크의 조립 고정방법과 동일하게 클립보울트(60)를 사용하여 조립식으로 고정한다.Assembling and fixing of the floor deck 50 on the left side, the floor deck 50 with respect to the upper surface of the left side support (30a, 30b) installed on the left side of the bridge P as shown in Figs. ) Is installed in the horizontal direction, the length of the left side support (30a) (30b) to the middle side connector (36a) to the width of the inner space between the floor space 50 between the floor deck 50 assembled on the back Assemble three pieces in succession and put them on, and from the middle side connector (36a) to the outer end side of the left side support (30a, 30b) to match the left and right length by the width between each inner channel member three pieces in the width direction After assembling and placing it continuously, it is fixed by assembly using the clip bolt 60 in the same manner as the assembly method of assembling the floor deck on the rear surface.

우측면에서의 플로어데크(50)의 조립 고정은, 도1,3,8,9와 같이 교각(P)의 우측면에 설치된 우측면받침대(30c)(30d)들의 상면에 대하여 플로어데크(50)를 가로방향으로 설치하는 바, 우측면받침대(30c)(30d)들의 상면에 대하여 정배면에 조립된 플로어데크(50)들 간의 내측공간폭으로 길이를 맞추어 폭방향으로 3장을 연속적으로 조립하여 얹은 후, 정배면이나 좌측면에서의 플로어데크의 조립 고정방법과 동일하게 클립보울트(60)를 사용하여 조립식으로 고정한다.Assembling and fixing of the floor deck 50 on the right side transverses the floor deck 50 with respect to the top surface of the right side rests 30c and 30d provided on the right side of the piers P as shown in FIGS. 1, 3, 8 and 9. After the installation in the direction, the length of the inner space between the floor decks 50 assembled on the rear surface with respect to the upper surface of the right side support (30c) (30d) to assemble the three pieces in the width direction continuously, In the same manner as in the assembly and fixing method of the floor deck on the front or the left side is fixed by the assembly using the clip bolt (60).

상기와 같이 기본형받침대(30)들과 좌우측면받침대(30a)(30b)(30c)(30d)들 및 모서리받침대(40)들에 플로어데크(50)를 얹어 교각(P)의 둘레 전체에 발판이 조립 고정되면 점검통로 안전장치인 핸드레일(70)을 조립 고정한다.Floor deck 50 is placed on the basic support 30, left and right side support (30a) (30b) (30c) (30d) and the corner support 40 as described above scaffolding around the pier (P) When the assembly is fixed, the handrail 70, which is an inspection passage safety device, is assembled and fixed.

핸드레일(70)의 설치는 먼저 각각의 기본형받침대(30), 좌우측면받침대(30a) (30b)(30c)(30d)들 및 모서리받침대(40)들의 외단측에서 두 개의 찬넬부재들 사이에 핸드레일 지지봉(71)을, 찬넬의 지지봉 고정홀(35)에 지지봉의 고정홀(72)들을 맞추어 수직으로 끼운 후 각각의 고정홀에 보울트(B4) 및 너트(N4)를 채워 조립 고정한다(도12,13 참조).The installation of the handrail 70 is first carried out between two channel members at the outer end of each basic support 30, left and right side support 30a, 30b, 30c and 30d and the corner support 40. The handrail supporting rod 71 is vertically fitted by fitting the fixing holes 72 of the supporting rods to the supporting rod fixing holes 35 of the channel, and then filling and fixing the bolts B4 and nuts N4 in the respective fixing holes ( 12, 13).

이어서 좌측면받침대(30a)(30b)들의 중간부에서 두 개의 찬넬부재들 사이에도 각각 핸드레일 지지봉(71)을, 찬넬의 지지봉 고정홀(35a)에 지지봉의 고정홀(72)들을 맞추어 수직으로 끼운 후 각각의 고정홀에 보울트(B4) 및 너트(N4)를 채워 조립 고정한다.Subsequently, the handrail support bar 71 is also aligned between the two channel members in the middle of the left side support 30a and 30b, respectively, and the fixing bar 72 of the support bar is vertically aligned with the support bar fixing hole 35a of the channel. Insert and fix the bolts (B4) and nuts (N4) in each of the fixing holes.

상기와 같이 각각의 받침대들에 핸드레일 지지봉(71)들이 수직으로 고정되면 각각의 지지봉들사이에는, 각각의 받침대들간의 폭에 맞추어 적정의 길이로 규격화 하여 제작된 가로레일대(76)(77)들을 지지봉의 가로레일 고정홀(73)(74)들에 끼워 조립 고정하여 전체적인 핸드레일의 조립을 완성한다.When the handrail support rods 71 are vertically fixed to the respective pedestals as described above, between the support rods, the horizontal rail stands 76 and 77 manufactured by standardizing the proper lengths according to the widths of the pedestals. ) By fitting the horizontal rail fixing holes (73) (74) of the support rod to complete the assembly of the overall handrail.

상기와 같이 핸드레일의 조립 시공이 완료되면 점검통로 마감재인 마감판(80)을 도13과 같이, 교각(P)의 정배면 및 좌우측면에서 각각의 받침대들의 외단측에서 상하단플랜지를 감싸게 끼운 후, 각각의 받침대들 외단측 상하단 플랜지들에 형성한 마감판 고정홀(39)들에 마감판의 고정홀(81)들을 맞춘 후 고정피스(B5)를 조여 조립 시공한다.When the assembly of the handrail is completed as described above, as shown in Figure 13, the closing plate 80, which is a check passage finishing material, to wrap the upper and lower flanges at the outer end side of each pedestal on the front and left and right sides of the piers (P). After fitting the fixing holes 81 of the closing plate to the closing plate fixing holes 39 formed on the upper and lower end flanges of the respective pedestals, tighten the fixing piece B5 to assemble and construct.

도14~15에는 본 고안에 의한 다른실시예의 조립형 고정식 교량점검시설 (100a)의 구성이 도시되어 있다.14 to 15 show the structure of the assembled stationary bridge inspection facility 100a according to another embodiment of the present invention.

이 구성은 철도교량중 전철주 있는 교각에 설치되는 형으로서, 모든 구성요소 및 이들의 조립식 기술적구성이 상기 일실시예의 조립형 고정식 교량점검시설 (100)과 동일하나, 단지 전철주 있는 교각이 전철주 없는 교각에 비하여 좌우 길이가 다소 길게 형성되어, 교각상단의 좌측면에 돌출된 통로를 형성하지 못하는 점에 기인하여, 좌측면 받침대들의 구성을 상기 일실시예 우측면받침대(30c)(30d)들의 구성과 동일하게 형성한 구성이 상이하고, 이에따라 교각의 정배면에 설치되는 플로어데크(50)의 길이방향 규격이 늘어나고 좌측면에 설치되는 플로어데크(50)의 수량은 줄어드는 구성에서만 상이하다.This configuration is a type that is installed in the pontoon pier of the railway bridge, all components and their prefabricated technical configuration is the same as the prefabricated fixed bridge inspection facility 100 of the above embodiment, but only the pontoon pier is train Due to the fact that the left and right lengths are slightly longer than those of the main piers, it is not possible to form a protruding passage on the left side of the top of the piers, and thus the configuration of the left pedestals of the right side pedestals 30c and 30d of the embodiment is described. The configuration formed in the same way as the configuration is different, and accordingly, the longitudinal dimension of the floor deck 50 provided on the back of the pier increases, and the quantity of the floor deck 50 provided on the left side is different only in the configuration of decreasing.

상기와 같은 본 고안의 일실시예들은 철도 교량용 교각중에서 일 형태에 적용되는 구성인 바, 본 고안의 구성은 반드시 상기 일실시예들에 국한되는 것은 아니다. 예를 들어 철도 교량중에서도 그 평면형태가 상이한 타 종류에 적용할 때에나, 또는 도로용 교각 등에 적용할 때에도 동일한 구성요소들을 사용하되 그 규격에 있어서만 변경시켜서 동일한 조립구조로 실시할 수 있는 것이며, 점검통로의 폭방향을 특정 규격으로 증감할 경우에는 규격화된 한판의 플로어데크 폭 규격의 배수로 형성되는 규격에 맞추어 받침대들의 길이를 규격화하여 변경실시할 수 있는 것이고, 마감판의 조립은 상단을 고정피스를 고정하는 수단외에 하단에도 고정피스를 사용하거나, 또는 보울트,너트로 고정시킬수도 있는 것이다.One embodiment of the present invention as described above is a configuration applied to one form of the bridge for railroad bridge, the configuration of the present invention is not necessarily limited to the one embodiment. For example, in the case of railway bridges, the same components may be used in different types of planes or road piers. In the case of increasing or decreasing the width direction of the inspection passage to a specific standard, the length of the pedestals can be standardized according to the standard formed in multiples of the floor deck width standard of the standardized bout. In addition to the means for fixing the fixing piece at the bottom, or bolts, nuts can also be fixed.

상기와 같이 본 고안의 조립형 고정식 교량점검시설은 그 구성요소들이, 고정브라켓들과 기본형 받침대들과, 좌우측면 받침대들과 모서리받침대들 및 기성품의 플로어데크, 핸드레일등으로 구성요소가 단순화되고, 고정브라켓에 연차적으로 보울트, 너트에 의하여 조립식으로 시공하는 구성인 바 종래의 현장맞춤 용접고정식 점검시설에 비하여 다음과 같은 효과를 갖는다.As described above, the assembled fixed bridge inspection facility of the present invention has a simplified component, with fixed brackets and basic pedestals, left and right side pedestals, corner rests, and ready-made floor decks, handrails, and the like. In comparison with the conventional field-fitting welding fixed inspection facility, it is constructed to be prefabricated by bolts and nuts annually to the fixing bracket.

중요한 효과는 점검시설을 구성하는 부자재와 시공사양을 교각의 유형에 맞추어 몇가지로 규격화함에 있다.An important effect is to standardize the subsidiary materials and construction amount that make up the inspection facility in several ways according to the type of piers.

점검시설부재와 시공사양이 규격화되면, 공사발주처는 공사발주시마다 매건별로 시설설계와 발주사양을 작성함에 따른 제반 비능률적인 요소들을 제거하여 발주업무를 능률화 할 수 있고,When the inspection facility member and the construction quantity are standardized, the construction orderer can streamline the ordering work by eliminating all the inefficient elements of the facility design and ordering specification for each construction order.

시공업체는 부자재의 대량생산이 가능하여 생산원가를 낮추며, 원자재 및 시공자재의 수급이 용이해지며, 시공작업도 표준화할 수가 있다.The contractor can mass-produce the subsidiary materials, lower the production cost, facilitate the supply and demand of raw materials and construction materials, and standardize the construction work.

또한 시공업체에서 해당공사의 수주전에도 부재에 대하여 소요량과 공사기간등의 예측이 가능하여 시공자재의 구입, 공사인원의 관리 및 수주공사의 배분등이매우 용이해지며, 수주후에는 즉시 재고부재에 의하여 겅사에 착수할 수 있으며, 시공작업시에도 선공정으로 공장에서 규격화된 상기 점검시설부재들을 현장으로 운반하여 단순한 보울트,너트 조립공정만으로 시공을 완료시킬 수 있으므로, 대폭적인 공기단축효과와 함께, 운반비와 인건비의 절감, 공사설비의 단순화를 통한 공사비절감등의 효과를 얻을 수 있고,In addition, the construction company can predict the required amount and construction period before the order is received. Therefore, it is very easy to purchase the construction materials, manage the construction personnel, and distribute the construction work. It can be started by this company, and even during the construction work, the inspection facility members standardized in the factory can be transported to the site to complete the construction by simple bolt and nut assembling process. It can reduce the transportation cost and labor cost, and reduce the construction cost by simplifying the construction equipment.

공사내역이 단순화되므로서 발주처에서는 공사중의 감리 및 시공상의 품질관리가 매우 용이해지는 효과를 얻는다.As the construction details are simplified, the client can easily manage supervision during construction and quality control in construction.

또 다른 효과는 점검시설의 구성이 모든 구성부재들간을 현장용접이 아닌 현장에서 조립식으로 시공하므로, 종래의 시공시 용접부위에 방청도료를 도색하여야 하고 시공후에도 유지보수를 위하여 주기적으로 도색하여야 함에 따른 상당한 도료비와 공정을 제거하여 공사단가 및 유지보수비를 현저히 낮추며,Another effect is that the construction of the inspection facility is prefabricated in the field rather than on-site welding, so that the rust-preventive paint should be painted on the welded area in the conventional construction and periodically painted for maintenance after construction. Significantly lowers construction and maintenance costs by eliminating paint and process costs.

시공후에 점검시설의 부분적인 파손이나 일부부재의 기능저하에 의하여 부재의 교체, 수리등의 보수, 유지작업에 있어서도 각부재들의 연결부위에서만 해당 보울트,너트를 풀러 간편하고 신속하게 규격화된 해당부재의 보수, 교체작업을 실시할 수 있으므로 이부분에서도 상당한 보수작업비를 절감할 수 있는 효과를 갖는 것이다.After repairing, the bolts and nuts can be loosened only at the connection part of each member to repair or maintain the member due to partial damage of the inspection facility or deterioration of some members. Since repair and replacement work can be carried out, this part also has the effect of saving considerable maintenance work costs.

또한 점검시설의 외측면에 대하여 마감판에 의하여 마감시키므로서 종래의 구성에 비하여 외관을 미려하게 할수 있는 효과도 갖는다.In addition, the outer surface of the inspection facility by the closing plate has the effect of making the appearance beautiful compared to the conventional configuration.

Claims (4)

교량용 고정식 점검시설을 형성함에 있어서, 교각의 상단 둘레에 일정간격으로 매입식 보울트에 의해 고정되는 것으로 받침대 연결판재를 갖는 수개의 고정브라켓들과, 이 고정브라켓들의 연결판재에 조립 고정되는 것으로 교각의 정배면측에 설치되는 기본형 받침대들과, 교각의 좌우측면에 설치되는 좌우측면받침대들과, 상기 좌우측면받침대의 외단측과 중간부 외측면에 조립수단에 의하여 설치되는 모서리받침대들을 구비하며, 상기 받침대들과 모서리받침대들에 의하여 형성된 받침틀의 상단에는 플로어데크를 클립보울트에 의하여 조립식으로 고정하며, 받침대들의 외측단에는 규격품의 핸드레일을 핸드레일지지봉들을 상기 받침대들의 찬넬부재들 사이에 끼워 조립수단에 의하여 고정하며, 받침대들의 외단측에는 전둘레에 걸쳐서 마감판을 조립식으로 고정시켜 형성함을 특징으로 한 조립형 고정식 교량점검시설.In forming a fixed inspection facility for a bridge, several fixed brackets having a pedestal connecting plate are fixed by a buried bolt at a predetermined interval around the upper end of the bridge, and the bridges are assembled and fixed to the connecting plate of the fixing brackets. Basic type pedestals are installed on the rear side of the, and the left and right side rests are installed on the left and right sides of the piers, and the corner rests are installed by the assembly means on the outer side and the middle side of the left and right side rests, On the top of the support frame formed by the pedestals and the corner supporters, the floor deck is prefabricated and fixed by a clip bolt, and on the outer end of the pedestals, a handrail of standard parts is fitted between the channel members of the pedestals. Fixed by means, on the outer side of the pedestal the closing plate over the entire circumference A built-up static bridge inspection facilities, characterized in that formed by fixing the prefabricated. 제1항에 있어서 고정브라켓의 구성은, 교각(P)에 설치되는 매입보울트(Ba)들이 끼워지는 수개의 교각 고정홀(22)들을 사변 모서리측에 구비하여 교각(P)의 외측면에 부착되는 고정판재(21)와, 상기 고정판재(21)의 중앙측에서 판면과 직교방향이면서 서로간에 일정간격을 갖고 수직으로 고정되며 수개의 받침대 고정홀(26)들을 갖는 2개의 받침대고정판(23)(24)과, 이들 2개의 받침대고정판(23)(24)의 상단일부에서 각각 고정판재(21)와 일체로 용접된 보강부재(27)들을 구비한 고정브라켓(20)으로 형성함을 특징으로 한 조립형 고정식 교량점검시설.The structure of claim 1, wherein the fixing bracket includes a plurality of piercing fixing holes 22 into which the buried bolts Ba installed in the pier P are fitted on the side of the quadrilateral, and attached to the outer side of the pier P. The fixed plate member 21 and two pedestal fixing plates 23 which are vertically fixed with a predetermined interval therebetween and perpendicular to the plate surface at a central side of the fixed plate member 21 and having several pedestal fixing holes 26. (24) and a fixing bracket (20) having reinforcing members (27) integrally welded to the fixing plate (21) at each of the upper ends of these two pedestal fixing plates (23) and (24). One prefabricated fixed bridge inspection facility. 제1항에 있어서 기본형 받침대의 구성은, 두개의 [ 자형 찬넬부재(31)(32)들을 고정브라켓(20)의 2개의 받침대고정판(23)(24)에 외접상태로 밀접하게 끼워지는 정도의 폭을 갖고 수개의 연결대(33)로 용접 고정하고, 상기 2개의 받침대고정판 (23)(24)에 끼워지는 찬넬부재(31)(32)들의 내단측 웨브에는 상기 연결판재의 받침대 고정홀(26)들과 동축상으로 관통하는 수개의 브라켓 고정홀(34)들을 형성하며, 외단측 웨브에는 마감판(80)의 조립 내단측에 핸드레일 지지봉(71)이 맞닿아 조립될수 있을 정도의 일정간격을 두고 지지봉 고정홀(35)들을 상하로 형성하며, 외단측 상단플랜지에는 끝단부에 마감판 고정홀(39)을 구비한 기본형 받침대(30)로 형성함을 특징으로 한 조립형 고정식 교량점검시설.The structure of the base pedestal according to claim 1 is such that the two [shaped channel members 31 and 32 are closely fitted to the two pedestal fixing plates 23 and 24 of the fixing bracket 20 in an external state. The inner side of the channel members 31 and 32 fitted with the width and welded with several connecting rods 33 and fitted into the two pedestal fixing plates 23 and 24 is a pedestal fixing hole 26 of the connecting plate material. ) And a plurality of bracket fixing holes 34 penetrating coaxially with each other, and the outer end web has a predetermined interval such that the handrail support rod 71 can be assembled to the inner end side of the closing plate 80. Assembled fixed bridge inspection facility, characterized in that the support rod fixing holes 35 are formed up and down, and the outer end side flange is formed as a basic pedestal 30 having a closing plate fixing hole 39 at the end. . 제1항에 있어서 좌우측면받침대의 구성은, 교각(P)의 좌우측면에 서 각각 2개씩의 좌우측면 받침대(30a)(30b)(30c)(30d)들로 구성하되,According to claim 1, the configuration of the left and right side rests, each of the two left and right side pedestals 30a, 30b, 30c, 30d on the left and right sides of the piers (P), 우측면받침대(30c)(30d)는, 두개의 [ 자형 찬넬부재(31)(32)들을 고정브라켓 (20)의 2개의 받침대고정판(23)(24)에 외접상태로 밀접하게 끼워지는 정도의 폭을 갖고 수개의 연결대(33)로 용접 고정하고, 각각의 외단측 웨브에는 마감판(80)의 조립 내단측에 핸드레일 지지봉(71)이 맞닿아 조립될수 있을 정도의 일정간격을 두고 지지봉 고정홀(35)들을 상하로 형성하며, 외단측 상하플랜지에는 끝단부에 마감판 고정홀(39)을 형성하며, 이들 각각의 외단측 외측면에는 각각 2장의 판재로 되어 웨브의 외단측 선단에서 후술하는 모서리받침대(40)가 받침대의 외단과 일렬로 조립되는 정도의 폭을 두고, 외측면에서부터 상하 플랜지들에 함께 고정되어 외측방으로 일정길이 돌출되며 모서리받침대 고정홀(37)들을 갖는 측면 연결구(36b)들을 구비하고,The right side support 30c, 30d has a width such that the two [shaped channel members 31, 32] are closely fitted to the two pedestal fixing plates 23, 24 of the fixing bracket 20 in an external state. And fixed by welding with several connecting rods 33, and each of the outer end side webs has a fixed interval such that the handrail support rods 71 abut on the inner end side of the closing plate 80 so that they can be assembled. (35) are formed up and down, the outer end side flange is formed in the end of the end plate fixing hole 39, each of these outer end side is formed of two pieces of plate each to be described later in the outer end side of the web Side joints 36b having a width such that the corner support 40 is assembled in line with the outer end of the pedestal, fixed together with the upper and lower flanges from the outer side to protrude a predetermined length toward the outside, and having the corner support fixing holes 37. ), 좌측면받침대(30a)(30b)는, 상기 우측면받침대(30c)(30d)와 기본적인 골격이 동일하되, 각각의 찬넬 웨브의 외단측과 상단플랜지에는 상기 우측면받침대와 동일한 구성의 지지봉 고정홀(35)들과 마감판 고정홀(39)들이 형성되며, 전체 길이가 우측면받침대보다 일정길이 길게 형성하면서, 이들 각각의 중간부 외면측에는 각각 2장의 판재로 되어 웨브와 상하 플랜지들에 함께 고정되어 외측방으로 일정길이 돌출되고 모서리받침대 고정홀(37)들을 갖는 측면연결구(36a)들을 구비하고, 상기 2장의 측면연결구(36a)들의 판재 사이에는 양측 찬넬들을 관통하는 핸드레일의 지지봉 고정홀(35a)을 구비하여 구성함을 특징으로 한 조립형 고정식 교량점검시설.The left side support 30a, 30b has the same basic skeleton as the right side support 30c, 30d, but the support rod fixing hole 35 having the same configuration as the right side support in the outer end side and the upper flange of each channel web. ) And closing plate fixing holes 39 are formed, and the overall length is formed to be longer than the right side support, while each of the middle portion of the outer surface side is formed of two sheets, respectively fixed to the web and the upper and lower flanges together to the outside And a side connector 36a having protruding lengths and corner support fixing holes 37, and the support rod fixing hole 35a of the handrail penetrating both channels between the plate members of the two side connectors 36a. Prefabricated fixed bridge inspection facility characterized in that the configuration.
KR2019990000429U 1999-01-16 1999-01-16 build-on inspection equipment for fixity of bridge KR200240967Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2019990000429U KR200240967Y1 (en) 1999-01-16 1999-01-16 build-on inspection equipment for fixity of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2019990000429U KR200240967Y1 (en) 1999-01-16 1999-01-16 build-on inspection equipment for fixity of bridge

Publications (2)

Publication Number Publication Date
KR19990017520U KR19990017520U (en) 1999-05-25
KR200240967Y1 true KR200240967Y1 (en) 2001-10-27

Family

ID=54754882

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2019990000429U KR200240967Y1 (en) 1999-01-16 1999-01-16 build-on inspection equipment for fixity of bridge

Country Status (1)

Country Link
KR (1) KR200240967Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102219006B1 (en) * 2020-07-09 2021-02-23 김진희 Bicycle road structure for bridge

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101460710B1 (en) * 2012-08-23 2014-11-11 서울메트로 Inspection equipment of bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102219006B1 (en) * 2020-07-09 2021-02-23 김진희 Bicycle road structure for bridge

Also Published As

Publication number Publication date
KR19990017520U (en) 1999-05-25

Similar Documents

Publication Publication Date Title
HU221798B1 (en) Prefabricated building systems
US8959849B1 (en) Light steel frame structure for deck
CN114482375B (en) Construction method of integral joint type reinforced concrete superimposed sheet
CN108915140B (en) Method for installing full glass curtain wall with arc exceeding 10m Gao Wan
KR200240967Y1 (en) build-on inspection equipment for fixity of bridge
KR100381724B1 (en) Inspection plate for a pier
CN113636361B (en) Multilayer overhead closed type steel pipe truss combined system for conveying gallery
KR200404035Y1 (en) A fixed frame for food- plate, and a fixed inspection equipment for bridges
CN211421945U (en) Container building structure convenient to assemble
KR100526996B1 (en) Fabricated inspecting support of bridge using steel bar and installing method thereof
KR200191454Y1 (en) A fixed inspection equipment for bridges
CN113464170A (en) Template structure for tunnel special-shaped section lining and assembling method thereof
CN112900624A (en) Assembly type building structure
CN113123513A (en) Lapping type bottom-wrapping connecting assembly and steel bar truss floor bearing plate
CN112227733A (en) Installation method of three-way pipe truss
KR200191453Y1 (en) A inspection plate for inspection equipment of bridge
CN220285017U (en) Steel frame with stiffening nodes of box column root raw floor slab
KR20000036274A (en) A build-on inspection equipment for bridges and a process for mounting there of
CN219908581U (en) Supporting frame
CN108842916A (en) Curved-surface structure adjustable curvature truss and method
CN211058110U (en) Heat-insulation floor layer
JP2006118191A (en) Construction method of concrete floor slab of composite floor slab bridge, and form structure
KR20000024671A (en) A inspection plate for inspection equipment of bridge
CN115045421B (en) Outdoor glass curtain wall structure and construction method
KR20000024672A (en) A fixed inspection equipment for bridges

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
REGI Registration of establishment
LAPS Lapse due to unpaid annual fee