KR20020013618A - Method of Explosive Demolition on the Buildings by use of Explosives - Google Patents

Method of Explosive Demolition on the Buildings by use of Explosives Download PDF

Info

Publication number
KR20020013618A
KR20020013618A KR1020000046641A KR20000046641A KR20020013618A KR 20020013618 A KR20020013618 A KR 20020013618A KR 1020000046641 A KR1020000046641 A KR 1020000046641A KR 20000046641 A KR20000046641 A KR 20000046641A KR 20020013618 A KR20020013618 A KR 20020013618A
Authority
KR
South Korea
Prior art keywords
blasting
building
time difference
dismantling
pillars
Prior art date
Application number
KR1020000046641A
Other languages
Korean (ko)
Other versions
KR100680032B1 (en
Inventor
박근순
김광태
정윤식
손승우
Original Assignee
윤영석
두산중공업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 윤영석, 두산중공업 주식회사 filed Critical 윤영석
Priority to KR1020000046641A priority Critical patent/KR100680032B1/en
Publication of KR20020013618A publication Critical patent/KR20020013618A/en
Application granted granted Critical
Publication of KR100680032B1 publication Critical patent/KR100680032B1/en

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/02Particular applications of blasting techniques for demolition of tall structures, e.g. chimney stacks
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • F42D1/04Arrangements for ignition
    • F42D1/06Relative timing of multiple charges
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings

Abstract

PURPOSE: A destruction method using blasting powder is provided to improve work efficiency and to minimize noise and vibration by charging the blasting powder in the pillars placed in an overturning direction and blasting a building based on time difference. CONSTITUTION: A destruction method using blasting powder is to gradually blast a building by using delayed time difference. Blasting powder is charged in pillars(100,101,102) of a building based on delayed time difference. The delayed time difference is 25ms. The first delayed time difference of a first charge hole is over 400ms to prevent cut off in a non-electric detonating system. Since a building is blasted partially based on time difference, shock energy due to blasting at a time is avoided. The shock energy is dispersed. Thereby, blasting noise and vibration are minimized.

Description

화약에 의한 건물발파해체 방법{Method of Explosive Demolition on the Buildings by use of Explosives}Method of Explosive Demolition on the Buildings by use of Explosives}

본 발명은 화약을 사용하여 순간적으로 건물을 발파해체하는 것으로서, 특히 최소량의 장약으로 지연시차를 이용함으로서 작업성을 증대하고 소음, 진동을 저감시킬 수 있는 화약에 의한 건물발파해체 방법에 관한 것이다.The present invention relates to an explosive demolition of a building using explosives, and more particularly, to a method for demolition of a building by explosives capable of increasing workability and reducing noise and vibration by using delayed parallax with a minimum amount of charge.

대부분의 건축물들은 반영구적으로 활용하기 위해 건설되었지만 사회적 변화와 경제 발전에 의해 건축물의 수명이 구조적 수명보다 줄어들게 되었고, 건축물의 기능적 측면이나 설비의 보완, 지진이나 화재 등에 의한 자연재해의 발생, 도시 재개발 등 공공적인 요소들로 인해 건축물의 해체 작업의 필요성이 증가하고 있다.Most buildings were built for semi-permanent use, but due to social change and economic development, the lifespan of buildings has been shortened than their structural lifespan. Public factors are increasing the need for dismantling works.

인구의 증가에 비해 주어진 공간은 한정적일 수 밖에 없으며, 우리나라와 같이 산지가 많고 도시 인구밀도가 높은 나라는 환경의 보존을 위해서 도시공간의 고집적화가 필수적이라고 할 수 있다. 각종 건물이나 토목구조물 등은 기능상의 변화, 사회 경제적 가치의 변동 또는 내구성의 지연적 감퇴 등의 이유로 해체가 불가피해지는 경우가 많다. 건물은 내용년한 즉 수명을 다할 경우 해체하는 것이 일반적이지만 최근에는 쾌적한 환경 추구와 협소한 토지의 효율적인 활용을 위한 재개발, 재건축 사업의 일환으로 수명과 관계없이 해체하는 경우가 많다. 1990년대에 들어서면서 도심지 재개발의 확산으로 우리나라의 해체산업의 기술적 동향을 과거의 재래성에서 탈피하여 점차적으로 기계화, 고도화 경향이 짙어지고 있으나, 기존의 구조물 해체공법은 소음, 진동, 분진발생 등에 의한 민원의 소지가 많고 공사의 장기화에 따른 공사비용 증가 등의 문제점을 안고 있다.Compared to the increase in population, given space is limited, and in Korea, where there are many mountainous areas and high urban population density, high integration of urban space is essential for the preservation of the environment. The dismantling of various buildings and civil structures is inevitable due to functional changes, changes in socioeconomic values, or delayed decline in durability. Buildings are generally dismantled at the end of their useful life, i.e., at the end of their useful life, but recently they are often dismantled regardless of their lifespan as part of redevelopment and reconstruction projects for the pursuit of pleasant environment and efficient use of narrow land. In the 1990s, due to the proliferation of urban redevelopment, the technical trend of the dismantling industry in Korea has been gradually removed from the conventional ones, and the trend of mechanization and upgrading has been gradually increased. There are many complaints and there are problems such as increase of construction cost due to prolonged construction.

또한 해체 대상물의 고층화가 대두되면 현재의 기계식 해체장비에 의한 방법으로는 공사 안정성과 기간, 경제성 등에 있어서, 한계에 부딪힐 수 밖에 없다.본 발명은 고도로 제어된 화약류의 폭발력을 이용하므로 고층일수록 기계식에 비하여 공사기간이 단축되고, 공사비 절감에 있어서 절대적으로 유리하다. 대다수의 해체공사에서 소음, 진동, 분진으로 인한 민원이 발생하고 있으며 해체 대상구조물이 고층화 될수록 이러한 민원에 노출되는 공정은 절대적으로 길어지고 있으나 본 발명은 이러한 민원발생의 소지를 단시간에 제어하고 최소화 할 수 있는 방법이 된다.In addition, when the demolition object rises, the current mechanical dismantling equipment has a limitation in terms of construction stability, duration, and economic feasibility. The present invention utilizes the explosive power of highly controlled explosives, so that the higher the mechanical height, Compared with this, the construction period is shortened and it is absolutely advantageous in reducing the construction cost. In many demolition works, complaints are generated due to noise, vibration, and dust, and as the structure to be dismantled becomes higher, the process of exposure to these complaints is absolutely longer, but the present invention can control and minimize the occurrence of such complaints in a short time. It is a way to be.

종래의 해체공법은 노후건물의 해체를 위하여 기계화장비 및 인력을 동원한 해체방법으로 대형브레이커, 스틸볼, 압쇄기, 다이아몬드쏘, 워터제트 등의 각종 기계화장비를 혼합한 다양한 해체방법이 있으나 콘크리트 구조물의 해체에 일반적으로 사용하는 기계화 장비로는 대형브레이커 또는 압쇄기를 이용한 해체를 들 수 있다. 그러나 이러한 대형브레이커나 압쇄기의 경우에는 중량에 따른 안전문제로 인하여 저층에 국한하여 지상작업으로 이용함이 원칙이나, 현재 고층 건물 해체의 경우에도 압쇄기를 크레인 등을 이용하여 건물 옥상으로 인양하고 기존의 엘리베이터 홀을 이용한 해체물 처리용 낙하구를 통하여 상층부터의 파쇄물을 바닥층까지 낙하시키는 방법으로 구조물을 점차적으로 상층부에서부터 해체해 나가고 있다. 작업과정은 우선 바닥슬래브를 브레이커로 파쇄하여 그 아래층에서 낙하구로 낙하시키고 외벽과 기둥 등을 해체하게 된다. 이러한 작업과정을 거치면서 지속적인 분진, 소음 및 진동이 발생되므로 1일 작업시간이 제한되고, 견고한 바닥작업이 필요하기에 공사안정성에 대한 위험이 항시 존재하게 되며, 중장비의 낙하추락사고 내지는 철거중의 구조물이 뜻하지 않게 한꺼번에 붕괴되는 사고를 야기하게 된다.Conventional dismantling method is a dismantling method using mechanization equipment and manpower for dismantling old buildings, and there are various dismantling methods that mix various kinds of mechanization equipment such as large breakers, steel balls, crushers, diamond saws, water jets, etc. The mechanization equipment commonly used in the process includes dismantling using a large breaker or a crusher. However, in the case of such a large breaker or crusher, it is a principle to use the ground work only on the lower floors due to the safety problems according to the weight.However, even in the disassembly of a high-rise building, the crusher is lifted to the roof of the building by using a crane and the existing elevator The structure is gradually dismantled from the upper layer by dropping the debris from the upper layer to the bottom layer through the drop hole for dismantling of the dismantled object using a hole. The working process first breaks the floor slab with a breaker, falls from the lower floor to the drop opening, and dismantles the outer walls and columns. Due to the continuous dust, noise and vibration generated during this work process, daily work time is limited, and there is always a risk of construction stability due to the need for solid floor work, and there is always a fall or fall of heavy equipment. It can cause accidents that accidentally collapse the structure at once.

발파해체공법은 대상건물의 일부층 주요부재에 천공장비를 이용하여 장약을 할 수 있도록 천공을 한 후 소량의 폭약으로 부재를 순차적으로 파괴하여 건물전체를 붕괴시키는 공법으로 고층건물의 해체에 가장 각광받는 최신의 첨단공법이라고 할 수 있다. 작업과정은 장약을 위한 일부층의 비내력벽을 인력 또는 소형브레이커 장비로 제거하고 엘리베이터 홀과 계단부 등과 같은 강성이 큰 부재에 대하여 사전취약화 작업을 실시한 후 주요부재에 천공, 장약을 실시하여 발파해체하는 방식이다.Blasting and dismantling method is a method that breaks down the entire building by breaking the members sequentially with a small amount of explosive after drilling so that the main parts of the target building can be charged using drilling equipment. It is the latest high-tech method to receive. Work process is to remove non-bearing wall of some layers for charge by manpower or small breaker equipment, pre-weak work for rigid members such as elevator hall and stairway, and then blast and drill the main members. It is a way of dismantling.

종래의 발파해체공법에서는 여러개의 발파층을 선정하여 사전약화처리 및 방호공사를 시행하였고, 이에 따라서 화약류도 여러개의 발파대상층에 분산 장약되어 발파가 이루어졌다.In the conventional blasting and dismantling method, several blasting layers were selected to carry out preliminary treatment and protection work, and accordingly, the explosives were also dispersed and charged in several blasting target layers.

또한 여러개의 발파공을 한 블록단위로 동시에 기폭하여 발파진동과 발파소음이 크고, 구조체가 붕괴되거나 큰 단위로 붕괴되어 구조체의 지반 충격으로 인한 충격진동이 크게 발생하였다.In addition, the blasting vibration and the blasting noise are large by detonating several blasting holes in one block at the same time, and the shock vibration due to the ground impact of the structure is greatly generated because the structure is collapsed or collapsed in a large unit.

종래의 5층 규모 정도의 건물 발파해체에서는 장약층을 1층, 2층 4층으로 선택하고, 사전취약화층도 1층, 2층, 3층, 4층에 실시해왔고, 발파시 비석을 방지하기 위한 방호작업의 범위도 장약층과 동일하게 실시하여 건물의 규모에 비하여 상당히 많은부분을 발파해체를 위한 사전처리작업 대상으로 실시하였다. 이에 따라서 기계식해체공법보다 오히려 많은 시간과 공사비가 소요되어 발파해체의 장점을 살리지 못한 문제가 있다.In the conventional five-story building blast dismantling, the first floor, the second floor, and the fourth floor were selected as the first floor, the first floor, the second floor, the third floor, and the fourth floor. The scope of the protection work was also carried out in the same way as the building floor, and much of the construction work was carried out as pre-treatment work for blasting and dismantling. Accordingly, there is a problem in that it takes much time and construction cost rather than a mechanical dismantling method and thus fails to utilize the advantages of blast dismantling.

본 발명의 목적은 주로 5층 정도에 저층 건물을 발파해체 하기 위한 것으로 건물의 하부층인 1층과 2층 정도의 국한된 범위에서 최소한의 장약으로 건물을 붕괴시키고 소음과 진동을 최소한으로 감소시킬 수 있는 화약에 의한 건물의 전도발파해체 방법을 제공하는데 있다.The object of the present invention is to blast and dismantle a low-rise building on the 5th floor. The building can be collapsed with the minimum amount of charges and the noise and vibration can be minimized in the limited range of the 1st and 2nd floors. The present invention provides a method of dismantling conductive blasting of a building by powder.

도 1은 본 발명에 따른 발파해체 개념도1 is a conceptual diagram of blast dismantling according to the present invention

도 2는 본 발명에 따른 사전취약화도2 is a pre-weakness diagram according to the present invention

도 3은 본 발명에 따른 화약장약도3 is an explosive charge according to the present invention

도 4는 본 발명에 따른 방호도4 is a protection diagram according to the present invention

도 5는 본 발명에 따른 비전기식 기폭시스템도5 is a non-electromagnetic detonation system in accordance with the present invention

도 6은 본 발명에 따른 전기식 기폭시스템도6 is an electrical detonation system according to the present invention

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

100,101,102,103:기둥 104:장약공100, 101, 102, 103: pillar 104: pharmacy

105:화약 106:뇌관105: gunpowder 106: primer

107:각선 108:철망107: angle 108: wire mesh

109:부직포 110:간접방호109: nonwoven fabric 110: indirect protection

111:표면지연뇌관 112:보조모선111: surface delay primer 112: auxiliary bus

이하, 본 발명의 기술적 구성을 상세히 설명하면 다음과 같다.Hereinafter, the technical configuration of the present invention in detail.

본 발명의 화약에 의한 건물의 전도발파해체 방법은 발파에 의하여 건물이 전도될 때 전도되는 방향으로 전도공간을 확보할 수 있고 전도되는 방향의 기둥들에 장약공을 천공하여 건물을 발파해체하는 방법에 있어서, 최소한의 장약으로 발파해체하되 건물의 구역별로 지연시차를 이용하여 발파함을 기본적인 특징으로 한다.The method of discharging the conductive blasting of the building by the gunpowder of the present invention can secure the conductive space in the conductive direction when the building is inverted by the blasting and blast the dismantled building by drilling a hole in the pillars in the conductive direction. In the case of blasting and dismantling with a minimum amount of charge, the basic characteristics of the blasting by using the delay time for each area of the building.

화약류를 사용하여 건물의 발파해체 때에 저층 일부 구조지지 부재만을 순차적으로 파괴하고 건물 전체에 비틀림을 가하게 하여 자체 파쇄량을 증가시켜 전도시킴으로써 발파해체로 인한 소음 및 진동을 저감시키고, 발파해체후 지상에서의 중장비에 의한 소할파쇄작업을 원활하게 도모하기 위한 것으로 건물의 사전취약화와 화약장비 범위 및 화약류의 순차적 폭발을 위한 기폭시스템을 구성하는 방법을 설명한다.When exploding and dismantling of the building using explosives, only the lower part of the structural support members are sequentially destroyed, and the entire building is twisted to increase its amount of crushing, thereby reducing the noise and vibration caused by the blasting. This section describes how to construct a detonation system for the preliminary weakening of buildings, the scope of gun equipment, and the sequential explosion of gunpowder.

도 1은 본 발명에 따른 발파해체 개념도를 나타낸 것이다.1 shows a conceptual diagram of blast dismantling according to the present invention.

발파해체공법은 해체대상 구조물에 대한 구조역학적 문제와 구조물 붕괴시 진동을 발생시키는 지반에 전달되는 충격에너지의 양을 충분히 고려하여 최적의 발파위치 선정과 진동의 감소를 위한 발파시간차의 배분이 가장 중요한 요소가 된다. 정확하고 효율적인 발파해체는 화약의 사용량을 최소화 하면서 최대의 발파효과를 얻을 수 있어야 하며 적절한 장약과 방호방법으로 발파의 효과를 최대한 상승시키면서 파편의 비산을 효과적으로 제어할 수 있어야 하는 것이다. 구조물이 밀집된 도심지에서는 건물의 붕괴방향이 중요하고 건물 주위의 빈 공간을 최대한 이용해야 한다.In the blasting disassembly method, considering the structural dynamics of the structure to be dismantled and the amount of impact energy transmitted to the ground that generates vibration when the structure collapses, the most suitable blasting position and the distribution of the blasting time for reducing the vibration are the most important. To be an element. Accurate and efficient blasting disassembly should be able to achieve maximum blasting effect while minimizing the use of gunpowder, and be able to effectively control the scattering of debris while raising the blasting effect as much as possible with proper charging and protection method. In downtown areas with dense structures, the direction of collapse of the building is important and the empty space around the building should be used to the fullest.

도 1은 일반적인 5층 건물의 발파해체 개념에 따라 건물 구조를 종단면으로 도시한 것으로서 하부 2개 층의 일부 기둥을 발파하여 전도시키는 것을 나타낸다. 최하부층인 1층은 붕괴유도방향에 있는 기둥(100)으로부터 건물 단면의 중심에 위치한 기둥(101)까지를 발파대상으로 하고, 2층의 경우는 붕괴유도방향으로부터 중심부 사이의 기둥(102)을 발파대상으로 한다. 이때 건물의 붕괴유도방향으로의 여유부지공간은 붕괴유도방향측 최외각기둥(100)인 하단부 C지점으로부터(L1-W)+L2) 만큼의 이격거리가 확보되어 있어야 한다. 여기서 L1은 발파층의 종단면 대각선 길이이며, L2는 붕괴유도방향측의 비발파층의 높이이고, W는 건물의 폭이다.1 is a longitudinal cross-sectional view of a building structure in accordance with the concept of blast dismantling of a typical five-story building, which shows blasting and conducting some pillars of the lower two floors. The first floor, the lowest floor, is the blasting object from the pillar 100 in the collapse induction direction to the pillar 101 located in the center of the cross section of the building. It is targeted for blasting. At this time, the free ground space in the collapse induction direction of the building should be secured as much as (L1-W) + L2) from the bottom C point, which is the outermost column 100 on the collapse induction direction. Where L1 is the diagonal length of the longitudinal section of the blast layer, L2 is the height of the non-blast layer on the side of the collapse induction direction, and W is the width of the building.

건물하부층의 기둥(100)(101)을 발파하면, 나머지 A지점에 있는 기둥이 힌지역할을 하여 건물이 붕괴유도방향으로 전도운동을 시작하며 이때 기둥(102)을 발파하게 되면 건물이 전도에 필요한 운동거리를 확보할 수 있게 된다. 건물의 횡방향으로 배열되어 있는 기둥들(100),(101),(102)을 순차적으로 기폭하여 전도방향의 구조지지력을 없애주면 아직 파괴되지 않은 기둥과 파괴되어 전도 낙하하는 부분 사이의 구조체들이 비틀림을 일으켜 부서지게 되며 전도운동이 지속적으로 발생하게 되어 건물 전체가 발파해체되는 것이다.When blasting the pillars (100) and (101) of the lower floor of the building, the pillars at the remaining point A perform a hindrance to the building and the building starts to fall in the direction of collapse induction. You will be able to secure a range of motion. When the pillars 100, 101, and 102 arranged in the transverse direction of the building are sequentially detonated to eliminate structural support in the conduction direction, structures between the pillars that have not yet been destroyed and the falling and falling parts It causes torsion and breaks, and the evangelism movement continues to explode.

도 2는 사전파쇄의 범위와 방법에 대한 것으로 최소한의 화약으로 건물을 붕괴시키기 위하여 건물 내부의 구조체를 대상으로 완전파쇄제거 또는 일부 범위를 약화시켜 원활한 붕괴를 유도하기 위해 실시하며 사전취약화, 또는 사전 약화의 개념으로 해석할 수 있다.Figure 2 is about the extent and method of pre-crushing to destroy the building with a minimum amount of gunpowder to the structure within the building to remove the complete shredding or weakening a certain range to induce a smooth collapse pre-weakening, or It can be interpreted as a concept of prior weakening.

화약류를 이용해 건물을 붕괴시키는 발파해체공법은 단지 화약만을 사용한다고 해서 구조물이 원하는 방향으로 안전하게 붕괴되는 것은 아니다. 화약을 장약하는 부분은 건물의 주요 구조부재가 되는 기둥, 보, 전단벽 등이며, 구조적으로 보면 이들 구조체는 건물의 안정도를 확보하는데 중요한 역할을 하고 있다. 사전파쇄는 이러한 안정성을 지키는데 영향을 주지 않는 부위를 대상으로 주로 실시하고, 이들 구조체를 대상으로 건물의 붕괴에 저항하는 요소를 제거하여 붕괴를 촉진시켜 준다.Blasting and demolition, which uses gunpowder to collapse a building, does not mean that the structure will collapse safely in the desired direction by using only gunpowder. Gunpowder charge parts are pillars, beams, shear walls, etc., which are the main structural members of the building, and structurally, these structures play an important role in securing the stability of the building. Pre-crushing is mainly carried out on areas that do not affect the stability of these structures, and promotes the collapse by removing elements that resist the collapse of the building.

도 2와 같이 초기 힌지역할을 하는 A지점과 건물의 붕괴과정에서 2차적인 힌지역할을 하는 E지점을 이은 가상선 L1을 기준으로 발파구역이 되는 ACE 구역내의 발파대상구조체를 제외한 모든 벽체를 브레이커나 압쇄기를 장착한 중장비나 인력으로 사전에 철거하여 붕괴시 저항할 수 있는 요소를 사전에 제거함으로써 확실한 전도가 될 수 있도록 한다.Breaker breaks all walls except for the blasting structure in the ACE area, which is the blasting area, based on the virtual line L1 that connects the point A to the initial hinge area and the point E to the secondary hinge area during the collapse of the building, as shown in FIG. (B) remove it in advance with heavy equipment or manpower equipped with crushers and remove any elements that can resist in case of collapse so that it can be ensured.

도 3은 화약을 장약하는 것에 대한 개념으로 발파대상기둥(103) 내부에 화약을 설치할 수 있도록 천공한 후 뇌관(106)이 장착되어 있는 화약(105)을 장약공(104) 속에 설치하는 작업이다.3 is a work to install the gunpowder 105, which is equipped with a primer 106 in the charge hole 104 after drilling to install the gunpowder inside the blasting pole (103) as a concept to charge the gunpowder .

천공작업이란 발파대상 구조부재에 장약을 하기 위하여 구멍을 뚫는 작업을 말하여 대상구조물에 따라 사용장비, 천공규격 등이 다양하다. 특히 도심지내 건물 밀집지역에서 발파해체 작업시 천공의 정확도는 비산물 발생에 커다란 영향을 주므로 세심한 주의가 필요하다.Drilling work refers to the work of drilling a hole to make a blast on the structural member to be blasted, and there are various equipment used and drilling standards according to the target structure. In particular, when the blasting and dismantling work is concentrated in the downtown area, careful attention must be paid to the accuracy of perforation as it greatly affects the generation of fly-bys.

주 발파 대상층의 기둥은 건물붕괴시 최대한의 운동에너지를 유도하기 위하여 완전하게 파쇄하여야 하며 보조 발파층으로 주로 선정되는 상부층의 경우 계획된 붕괴거동에 지장이 없을 정도의 파쇄만이 필요하므로 하부층의 기둥은 천공수가 많고 상부로 갈수록 적어진다.The pillars of the main blasting layer must be completely crushed to induce maximum kinetic energy during building collapse. The upper layer, which is mainly selected as the auxiliary blasting layer, needs only crushing to the extent that the planned collapse behavior does not interfere. More perforations and less towards the top.

기둥의 천공위치는 구조체 단면의 중심부에 위치하여야 하며 철근 등이 위치하여 부득이 중심에 천공할 수 없을 경우에는 경사지게 천공하되 장약실은 중심에 오도록 하여야 한다.The drilling position of the column should be located at the center of the cross-section of the structure. If the steel bars are located and cannot be drilled in the center, the drill should be inclined and the cabinet should be in the center.

일반적으로 건축물의 발파해체에 주로 사용하는 화약(105)에는 젤라틴다이나마이트, 에멀젼화약, 정밀화약, 도폭선 등이 있으며, 장약되는 화약류의 기폭을 위해 뇌관(106)을 사용하는데 전기식뇌관과 비전기식뇌관의 두가지가 있다. 뇌관에 기폭력을 전달해주는 각선(107)은 전기식에는 비닐코팅동선이 사용되고 비전기식에는 속이 빈 플라스틱 튜브가 사용된다.In general, gunpowder 105 mainly used for blasting and dismantling of buildings includes gelatin dynamite, emulsion gunpowder, precision gunpowder, and detonation vessels. There are two ways. Each wire 107 that transmits the detonating force to the primer is a vinyl-coated copper wire for electric use and a hollow plastic tube for non-electric power.

5층 아파트의 경우 기둥별 천공수는 1층의 경우 3공 2층의 경우 1공이 기본이 된다.In the case of five-story apartments, the number of holes per column is the first hole in the third and second floors.

도 4는 방호방법에 대한 것으로 화약 폭발시 분출하는 가스의 팽창압력으로 비산되는 콘크리트 파편을 제어함과 동시에 분진을 1차적으로 제어하기 위한 목적으로 시행한다. 발파는 충격파에 의해서 균열이 발생하고, 생성되는 균열에 고온고압의 가스 팽창압이 작용하여 물체가 파괴되는 것을 이용한다. 이러한 가스압의 작용으로 콘크리트 파편은 비산하게 된다. 발파해체는 도심지역의 건축물을 대상으로 행해지므로 콘크리트 비산편과 분진을 억제하는 대책을 필히 세워야 한다. 방호는 직접방호와 간접방호의 두가지로 나눌 수 있다.4 is for the protection method to control the concrete debris scattered by the expansion pressure of the gas ejected during the explosives and to implement the purpose of controlling the dust at the same time. In blasting, cracks are generated by shock waves, and high-temperature, high-pressure gas expansion pressure acts on the generated cracks so that objects are destroyed. The action of the gas pressure causes the concrete fragments to scatter. Since blasting is carried out for buildings in urban areas, measures must be taken to suppress concrete scattering and dust. Protection can be divided into two categories: direct protection and indirect protection.

직접방호는 화약이 장약되어 발파되는 구조체를 대상으로 콘크리트 비산편을 막을 수 있는 방호막을 설치하는 것을 말한다. 화약의 폭발시 발생되는 압력에 의해 방호막이 파열되어 비산편이 발생하는 것을 방지하도록 하기 위해서는 방호막의 재질과 설치방법이 매우 중요하다.Direct protection refers to the installation of a protective film that can prevent concrete scattering on targets that are blasted by gunpowder. In order to prevent the protective film from rupturing due to the pressure generated during the explosive explosion, the material and installation method of the protective film are very important.

방호대상 부위에 방호막을 설치하였다 하더라도 일순간에 방출되는 폭발압력은 방호막의 약한 부위로 방출될 수 있기 때문에 도 4와 같이 서로 다른 재료를 사용하여 이중의 방호를 행한다.Even if a protective film is provided at the site to be protected, the explosion pressure released at one instant may be released to a weak area of the protective film, so that double protection is performed using different materials as shown in FIG. 4.

발파대상기둥(103)에 능형철망(108)를 두 번 감싸고 그 바깥으로 토목용부직포(109)를 다시 두 번 감싸게 되면 화약의 폭발로 인한 콘크리트 비산편을 대부분 제어할 수 있다.By wrapping the rhomboid wire mesh 108 twice in the blasting pole 103 and again wrapping the civil nonwoven fabric 109 again outside thereof, it is possible to control most of the concrete flying fragments due to the explosion of the gunpowder.

간접방호는 화약을 직접 장약하지 않는 부위를 대상을 방호하는 것으로 주로 창문, 출입구 등의 개구부를 대상으로 한다. 직접방호에서 빠져 나올 수 있는 작은 파편과 분진을 제어한다. 간접방호(110)는 직접방호보다 범위가 크며 화약이 장약되는 모든 층의 개구부를 도 4와 같이 실시하게 된다.Indirect protection is to protect the targets that do not directly charge gunpowder, mainly targeting openings such as windows and entrances. Controls small debris and dust that can escape from direct protection. The indirect protection 110 has a larger range than the direct protection and performs openings of all layers in which gunpowder is charged as shown in FIG. 4.

도 5는 장약된 화약을 폭발시키는 기폭시스템에 대한 것으로 발파후 건물의붕괴방향은 주위의 구조물과 거주민들에게 피해가 미치지 않도록 정확한 조절이 필요하다. 해체될 구조물이 붕괴될 방향은 우선적으로 주변환경과 해체후의 부서진 건물의 잔류물처리를 고려하여 선정되어야 한다. 그러므로 발파방법 즉 어떤 방향, 어떤 층의 기둥부터 발파할 것인가를 결정해야 한다.Figure 5 is for the explosion system to explode the charged gunpowder after the blasting the building collapse direction needs to be precisely adjusted so as not to damage the surrounding structures and residents. The direction of collapse of the structure to be dismantled should be selected first, taking into account the surrounding environment and the disposal of residues of the broken building after dismantling. Therefore, it is necessary to determine the blasting method, ie, which direction, which layer of pillar, to start from.

발파될 기둥의 결정은 무너져 내릴 건물의 크기, 모양, 방향 등에 따라 다르게 된다. 하부층의 기둥을 우선적으로 발파하게 되며 최초 발파구간은 건물이 무너져 내릴 방향과 장소를 결정하는데 중요한 역할을 하게 된다. 하부층 발파후에 상부층 발파는 해체될 건물의 전체가 한꺼번에 지상에 추락하는 것을 방지하기 위해서 기폭 순서가 부분적으로 순차적으로 이루어져야 한다.The crystals to be blasted will vary depending on the size, shape, and direction of the building to collapse. The lower blast columns will be blasted first, and the initial blast section will play an important role in determining the direction and location of the building's collapse. After the lower layer blasting, the upper layer blasting should be carried out in a sequential order of detonation in order to prevent the whole of the building to be dismantled at once.

이러한 순차적이고 부분적인 발파작업은 진동과 폭풍압 조절에 중요한 역할을 한다. 하부층의 발파는 상부층의 하중을 지지하고 있던 기둥을 확실하게 제거함으로써 해체대상 건물이 붕괴예상방향을 향하여 적절한 속도로 이동할 수 있게 한다.These sequential and partial blasting operations play an important role in controlling vibration and storm pressure. The blasting of the lower floor ensures that the column that was supporting the load on the upper floor is reliably removed so that the building to be dismantled can move at an appropriate speed toward the collapse direction.

상부층 역시 해체될 건물이 충분한 모멘트를 갖고 움직인 후에 제거되어야 한다. 확실한 모멘트를 갖기 전에 제거된다면 건물 붕괴방향의 오차를 가져올 수 있기 때문이다.The upper floor should also be removed after the building to be dismantled has moved with sufficient moment. If it is removed before it has a certain moment, it can lead to errors in the collapse direction of the building.

완전한 해체를 위해서는 모멘트를 최대한 이용하는 것이 좋으며 그러기 위해서는 붕괴방향에 접한 기둥이나 하부층의 기둥은 완전히 발파되어야 한다. 이에 반해 상부층의 기둥은 부분적인 발파만 해도 된다. 부분적인 기둥의 발파는 해체되는 동안 구조물이나 붕괴방향에 제한된 영향을 미치며 부서진 파쇄물의 크기를조절하는 역할을 한다. 그러므로 상부층을 완전히 발파할 필요는 없다.It is advisable to use the moment as much as possible for complete dismantling. To do this, the column facing the collapse direction or the column in the lower layer must be completely blasted. In contrast, the pillars on the upper layer may only need partial blasting. Partial column blasting has a limited effect on the structure or direction of collapse during dismantling and controls the size of broken debris. Therefore, it is not necessary to blast the top layer completely.

도 5는 5층건물을 지연시차를 사용하여 연속적으로 기폭시키는 방법이다. 지연시차의 특징은 건물을 부분적으로 발파함으로써 일시에 붕괴되는 것을 방지하여 충격에너지를 분산시킴으로써 충격진동의 영향을 최소화하고, 지발당 장약량이 최소화되어 발파소음 및 폭풍압이 줄어들게 된다. 본 발명은 종래의 여러개의 기둥을 한 단위로 하여 한꺼번에 기폭하던 방법을 기둥별로 세분화하여 기폭하는 방법이다. 또한 비전기식뇌관을 사용하는 기폭시스템에서는 하나의 기둥내에 여러개의 장약공이 있을 경우 각 장약공 별로 시차를 달리하여 기폭하는 방법을 사용하면 발파소음과 발파진동이 더 감소된다. 이때 각 장약공별 기폭 지연시차는 도 5의 비전기식에서의 장약공별 기폭초시에서와 같이 25ms 간격으로 배치하며 상부공이나 하부공의 구별없이 어디에서나 먼저 기폭을 시작하여도 되지만 최초 시작되는 장약공(104)의 기폭지연초시는 400ms 이상으로 선택하여야 한다. 이는 비전기식 기폭시스템에서의 cut off를 방지하는 방법이다. 각 기둥별 지연시차는 각 장약공에서 나온 비전기식뇌관의 각선(107)을 표면지연뇌관 (111)에 연결함으로써 이루어지며 표면지연뇌관은 42∼67ms로 설정한다. 기둥별 기폭순서는 도 5에서와 같이, 비전기석에서의 기둥별 기폭순서와 같다.5 is a method of continuously detonating a five-story building using a delay time difference. The characteristic of delayed parallax is to partially disintegrate the building to prevent it from being collapsed at one time, thereby distributing the impact energy to minimize the impact of the shock vibration, and to minimize the amount of charge per delay, thereby reducing the blast noise and storm pressure. The present invention is a method of detonating by subdividing by a column the method that previously detonated at a time by using several columns as a unit. In addition, in the detonation system using non-electric primers, if there are several charge holes in one pillar, the method of detonating with different parallax for each charge hole further reduces blasting noise and blasting vibration. At this time, the delay delay time for each charge hole is arranged at intervals of 25ms as in the non-explosive charge start in the non-electrical formula of Figure 5 and may start the explosion anywhere without distinguishing between the upper ball or the lower ball, but the first charge (104) Detonation delay of) should be selected over 400ms. This is a way to prevent cut off in non-electrical detonation systems. Delay lag for each column is made by connecting the wire 107 of the non-electrical primer from each charge hole to the surface delay primer 111, the surface delay primer is set to 42 ~ 67ms. The detonation order by pillar is the same as the detonation order by pillar in the non-stone as shown in FIG.

전기식 뇌관을 사용하는 기폭시스템에서는 도 6에서와 같이, 전기식에서의 장약공(104)별 기폭초시에서와 같이 동일 기둥(103)내 장약공별로 지연시차를 주지 않는다. 이는 전기식뇌관 종류의 한계가 있기 때문에 많은 단계의 지연발파를 할 수 없기 때문이다. 기둥별 시차는 20∼75ms로 하되 도 6에서의 전기식에서의 기둥별 기폭순서에서와 같이 설정하고 보조모선(112)으로 회로를 연결한다.In the detonation system using the electric primer, as shown in FIG. 6, the delay difference is not provided for each of the charge holes in the same pillar 103 as in the initial detonation of each charge hole 104. This is because many types of delayed blasting cannot be performed because of the limitations of the electric primer type. The parallax for each column is set to 20 to 75ms, but is set as in the detonation sequence for each column in FIG. 6, and the circuit is connected to the auxiliary bus 112.

이와 같은 본 발명의 건물발파해체 방법은 5층 정도의 저층 건물을 발파해체 하기 위한 것으로 발파에 의하여 건물의 넘어지는 전도방향의 기둥들에 장약하되 최소한의 장약으로 발파하며 건물의 구역별로 지연시차를 이용하여 발파함으로써 작업성이 증대되면서 소음과 진동을 최소한으로 감소시킬 수 있는 효과를 갖는다.The building blasting dismantling method of the present invention is to blast and dispose of a low-rise building of about 5 stories, and to blast the pillars in the falling direction of the building by blasting, but to blast with a minimum amount of delay and delay the time difference by the area of the building. By using the blasting to increase the workability has the effect of reducing noise and vibration to a minimum.

Claims (3)

발파에 의하여 건물이 전도될 때 전도되는 방향으로 전도공간을 확보할 수 있고 전도되는 방향의 기둥들에 장약공을 천공하여 건물을 발파해체하는 방법에 있어서, 최소한의 장약으로 발파해체하되 건물의 구역별로 지연시차를 이용하여 발파함을 특징으로 하는 화약에 의한 건물발파해체 방법.When the building is inverted by blasting, it is possible to secure the conduction space in the conducting direction and to blast and dismantle the building by drilling holes in the pillars in the conducting direction. Method for demolition of buildings by explosives, characterized by blasting by using a delay time. 제1항에 있어서, 상기 지연시차는 비전기식뇌관을 사용하되 이웃하는 기둥간에는 42∼67ms의 지연초시를 가지며 각 기둥당 최초 시작되는 장약공의 기폭지연초시는 400ms 이상으로 설정하고 기둥당 장약공 별로는 25ms의 단차로 기폭되게 함을 특징으로 하는 화약에 의한 건물발파해체 방법.The method of claim 1, wherein the delay time difference is to use a non-electric primer, but has a delay time of 42 ~ 67ms between the neighboring pillars and the delay delay time of the initial delay of the charge for each pillar is set to more than 400ms The method of demolition of buildings by explosives, characterized in that the star is detonated with a step of 25ms. 제1항에 있어서, 상기 지연시차는 전기식뇌관을 사용하되 각 기둥의 장약공 별로는 지연초시가 동일하고 이웃하는 각 기둥 별로는 20∼75ms의 지연초시로 기폭됨을 특징으로 하는 화약에 의한 건물발파해체 방법.The method of claim 1, wherein the delay time difference is determined by using an electric primer, but the delay time is the same for each of the pillars of each pillar, and each neighboring column is detonated with a delay time of 20 to 75 ms. .
KR1020000046641A 2000-08-11 2000-08-11 Method of Explosive Demolition on the Buildings by use of Explosives KR100680032B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020000046641A KR100680032B1 (en) 2000-08-11 2000-08-11 Method of Explosive Demolition on the Buildings by use of Explosives

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020000046641A KR100680032B1 (en) 2000-08-11 2000-08-11 Method of Explosive Demolition on the Buildings by use of Explosives

Publications (2)

Publication Number Publication Date
KR20020013618A true KR20020013618A (en) 2002-02-21
KR100680032B1 KR100680032B1 (en) 2007-02-07

Family

ID=19682854

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020000046641A KR100680032B1 (en) 2000-08-11 2000-08-11 Method of Explosive Demolition on the Buildings by use of Explosives

Country Status (1)

Country Link
KR (1) KR100680032B1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100460753B1 (en) * 2002-09-11 2004-12-08 주식회사 코리아카코 Blasting dissolution method of the infrastructure which uses a hydraulic pressure
KR100460752B1 (en) * 2002-09-11 2004-12-08 주식회사 코리아카코 Blasting dissolution method of wall
CN101936075A (en) * 2010-08-23 2011-01-05 重庆城建控股(集团)有限责任公司 Blasting method for dismantling frame structure building in situ
CN110553560A (en) * 2019-09-11 2019-12-10 辽宁工程技术大学 Blasting demolition method for building
KR102169475B1 (en) 2020-05-11 2020-10-23 김영호 Building safety dismantling system using sensors
CN113865453A (en) * 2021-09-27 2021-12-31 青岛宝利建设有限公司 Construction method for safe blasting demolition of building group and application
CN114754641A (en) * 2022-04-21 2022-07-15 武汉爆破有限公司 Directional dumping recoil control method for blasting demolition of large-span frame structure building
CN114777589A (en) * 2022-04-21 2022-07-22 武汉爆破有限公司 Method for designing directional collapse blasting notch for blasting demolition of high-rise building
KR20240028773A (en) 2022-08-25 2024-03-05 주식회사 가설안전구조연구 Integrated Construction Site Control System Using Scaffolding

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06323800A (en) * 1993-05-12 1994-11-25 Asahi Chem Ind Co Ltd Blasting method
KR0126994Y1 (en) * 1996-09-18 1998-10-15 김용구 Non-electric detonator blasting apparatus
KR100295320B1 (en) * 1998-10-02 2001-07-12 윤영재 Blasting method of a bench with two free sides
KR100358522B1 (en) * 1999-09-21 2002-10-30 코오롱건설주식회사 The setting method of shaped charges for the explosives demolition of a steel structure

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100460753B1 (en) * 2002-09-11 2004-12-08 주식회사 코리아카코 Blasting dissolution method of the infrastructure which uses a hydraulic pressure
KR100460752B1 (en) * 2002-09-11 2004-12-08 주식회사 코리아카코 Blasting dissolution method of wall
CN101936075A (en) * 2010-08-23 2011-01-05 重庆城建控股(集团)有限责任公司 Blasting method for dismantling frame structure building in situ
CN110553560A (en) * 2019-09-11 2019-12-10 辽宁工程技术大学 Blasting demolition method for building
KR102169475B1 (en) 2020-05-11 2020-10-23 김영호 Building safety dismantling system using sensors
CN113865453A (en) * 2021-09-27 2021-12-31 青岛宝利建设有限公司 Construction method for safe blasting demolition of building group and application
CN114754641A (en) * 2022-04-21 2022-07-15 武汉爆破有限公司 Directional dumping recoil control method for blasting demolition of large-span frame structure building
CN114777589A (en) * 2022-04-21 2022-07-22 武汉爆破有限公司 Method for designing directional collapse blasting notch for blasting demolition of high-rise building
KR20240028773A (en) 2022-08-25 2024-03-05 주식회사 가설안전구조연구 Integrated Construction Site Control System Using Scaffolding

Also Published As

Publication number Publication date
KR100680032B1 (en) 2007-02-07

Similar Documents

Publication Publication Date Title
KR20190103071A (en) Blasting Method using Liner applied to Primer, Booster and Charge in a blasthole
JP3062133B2 (en) Rock cutting method using tensile fracture
JP4201633B2 (en) Blasting and dismantling method of reinforced concrete structure
KR100680032B1 (en) Method of Explosive Demolition on the Buildings by use of Explosives
KR101995174B1 (en) structure base rock fragmentation of slight vibration
JP2005179924A (en) Method for blowing up and demolishing reinforced concrete structure
JP6461022B2 (en) Underground pile crushing method
KR100885925B1 (en) Blasting demolition method of the silo on a large cylindrical structure
JP2020063660A (en) Underground pile breaking method
CN108195242B (en) Rock blasting method
CN113154978B (en) Frame cylinder high-rise building blasting demolition method
JP6310181B2 (en) Dismantling method
JP6844082B2 (en) Underground pile crushing method
KR100460752B1 (en) Blasting dissolution method of wall
KR100312349B1 (en) V-cut blasting method with stage advanced blasting
KR100460753B1 (en) Blasting dissolution method of the infrastructure which uses a hydraulic pressure
KR20100001777A (en) Dismantle method of circular construction structure
JP6783493B2 (en) Underground pile removal method
WO2003004797A1 (en) Method for demolishing concrete structures provided with internal reinforcing
Laszlo et al. Technical and safety aspects at the demolition by blasting works of a cooling tower with a high of 72.00 m
CN116518803A (en) Blasting demolition method for cyclone furnace
CN115559560B (en) Method for dismantling profile steel concrete upright post
Dowding Ground motions and air-blast effects of explosive demolition of structures
JP6603774B1 (en) Underground pile crushing method
CN118031744A (en) Sectional blasting demolition method from top to bottom for high-rise building

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130201

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20131206

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20141230

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20151208

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20161206

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20171204

Year of fee payment: 12

LAPS Lapse due to unpaid annual fee