KR20010015933A KR1020000010342A KR20000010342A KR20010015933A KR 20010015933 A KR20010015933 A KR 20010015933A KR 1020000010342 A KR1020000010342 A KR 1020000010342A KR 20000010342 A KR20000010342 A KR 20000010342A KR 20010015933 A KR20010015933 A KR 20010015933A
Authority
KR
South Korea
Prior art keywords
curtain wall
glass panel
frame
fixing
glass panels
Prior art date
Application number
KR1020000010342A
Other languages
Korean (ko)
Other versions
KR100411948B1 (en
Inventor
이기용
Original Assignee
이기용
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이기용 filed Critical 이기용
Priority to KR10-2000-0010342A priority Critical patent/KR100411948B1/en
Publication of KR20010015933A publication Critical patent/KR20010015933A/en
Application granted granted Critical
Publication of KR100411948B1 publication Critical patent/KR100411948B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms
    • E04B2/962Curtain walls comprising panels attached to the structure through mullions or transoms with angles or corners in the curtain wall

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

PURPOSE: An assembly glass panel for a curtain wall and a construction method of the curtain wall using the same are provided to simplify the construction to reduce a construction term by forming assembly glass panels by using a construction sealant and mounting the assembly glass panels to curtain wall frame elements by fixing tools and fixing screws. CONSTITUTION: An assembly glass panel for a curtain wall includes quadrangle shaped glass panels processed to be mounted as an outer wall element of the curtain wall, fixing frames(20) assembled in the shape of quadrangle frame having a channel type groove(21) along outer side surfaces in every direction to be attached to edge parts of bottom surfaces of the glass panels, gap maintaining elements for maintaining a uniform distance between the glass panels and the fixing frames, and sealants filled between the glass panels and the fixing frames by a predetermined thickness to adhere the glass panels and the fixing frames together. In the construction method, fixing tools(200) are fitted in the channel type grooves of the neighboring assembly glass panels(100) and fixed in vertical and horizontal elements(300a,300b) by fixing screws(400), so that fixing frames of the assembly glass panels are fixed to the vertical and horizontal elements by pressing.

Description

커튼월용 조립유리패널 및 그것을 이용한 커튼월 시공방법{Shop Glazing System by Structural Silicone in Stick System Curtain Wall}Glass panel for curtain wall and curtain wall construction method using it {Shop Glazing System by Structural Silicone in Stick System Curtain Wall}

본발명은 스틱시스템 커튼월에서 구조용 실란트를 사용한 유리마감 외벽을 시공하기 위한 것으로, 특히 작업환경이 우수한 공장에서 숙련된 기능공에 의하여 구조용 실란트의 충진작업이 이루어진 조립유리패널을 미리 제작(shop-glazing)한 다음, 이를 현장에 설치되어 있는 커튼월 골조체에 조립하는 방식을 통하여 커튼월을 시공함으로써 시공이 간편할 뿐만 아니라, 종래 구조용 실란트를 주입하기 불량하였던 부위(기둥, 콘크리트 옹벽, 스팬드럴 부분)의 구조적인 안정성을 확보하여 완벽한 품질을 보장할 수 있는 커튼월용 조립유리패널 및 그것을 이용한 커튼월 시공방법에 관한 것이다.The present invention is for constructing a glass-finished outer wall using structural sealant in a stick system curtain wall, and in particular, pre-fabricated assembled glass panel in which a structural sealant is filled by skilled workers in a factory having excellent working environment (shop-glazing). Then, the construction of the curtain wall by assembling it to the curtain wall frame structure installed in the field is not only easy to install, but also a part (pillar, concrete retaining wall, spandral part) where the conventional structural sealant was poorly injected. The present invention relates to a glass wall assembly panel for curtain walls and a curtain wall construction method using the same.

종래, 스틱시스템 커튼월에서 구조용 실란트를 사용하여 건물 외벽에 유리만 보이게 하는 구조의 외벽을 시공함에 있어서는 도1의 도시와 같이,Conventionally, in the construction of the outer wall of the structure in which only the glass is visible on the outer wall of the building using the structural sealant in the stick system curtain wall, as shown in Figure 1,

건물구조체(1)에 수직재(2) 및 수평재(3)를 설치하여 커튼월 골조체를 형성한 다음,After installing the vertical member (2) and the horizontal member (3) to the building structure (1) to form a curtain wall frame,

커튼월 골조체를 이루는 수직재(2) 및 수평재(3)의 외표면에 접착성을 띠고 있는 간격유지재(4)를 접착시킨 후에,After adhering the adhesive gap holding member 4 to the outer surface of the vertical member 2 and the horizontal member 3 forming the curtain wall frame,

이 간격유지재(4)에 유리(5)를 부착하여 임시 고정하고,The glass 5 is attached and temporarily fixed to this gap holding material 4,

간격유지재에 의해 형성된 커튼월 골조체와 유리(5)사이의 공간에 구조용 실란트(6)를 주입하여 충진한 다음,Filling and filling the structural sealant (6) in the space between the curtain wall frame formed by the spacer and the glass (5),

구조용 실란트(6)가 경화되어 소정의 접착강도를 발휘하기 전까지 유리(5)가 탈락되는 것을 방지하기 위해 수직재(2)의 돌출편(2a)에 압박판(7)을 결속핀(8)으로 고정하여 유리(5)를 버티어 놓고,In order to prevent the glass 5 from falling off until the structural sealant 6 is cured and exhibits a predetermined adhesive strength, the pressing plate 7 is attached to the protruding piece 2a of the vertical member 2 by the binding pin 8. To hold the glass (5),

구조용 실란트(6)가 요구되는 접착강도를 가지게 되었을 때 압박판(7) 및 결속핀(8)을 제거하는 방식으로 시공하여 왔다.When the structural sealant 6 has the required adhesive strength, it has been constructed in such a way that the pressing plate 7 and the binding pin 8 are removed.

그러나, 이러한 종래기술은 커튼월 골조체와 유리(5)사이에 주입하는 구조용 실란트를 반드시 건물의 실내쪽에서 주입해야 올바른 시공이 이루어지는 작업의 특성상 수직재(2) 및 수평재(3)가 건물구조체(1)의 기둥, 콘크리트 옹벽, 스팬드럴 부분에 위치하는 경우에는 구조용 실란트(30)를 주입하는 것이 사실상 불가능해져 부실시공이 되어 왔다.However, in the related art, the vertical members 2 and the horizontal members 3 are formed in the building structure 1 due to the nature of the work in which the structural sealant injected between the curtain wall frame and the glass 5 must be injected from the interior side of the building. In the case of the column, the concrete retaining wall, and the spandral portion, the structural sealant 30 has been impossible to be injected.

특히, 유리(5)와 커튼월 골조체 사이에 주입된 구조용 실란트(6)가 요구되는 접착강도를 얻기까지는 유리(5)와 커튼월 구조체 사이에 접합된 간격유지재(4)에 의존하여 유리의 자중 및 건물 외부에 미치는 풍 하중에 견뎌야 하기 때문에, 이 과정에서 간격유지재(4)의 접합강도에 상기 하중들이 완전히 지지되지 않고 경화진행중인 구조용 실란트(6)에 나쁜 영향을 끼쳐 구조용 실란트(6) 본래의 접합강도를 충분히 발휘할 수 없게 되며, 현장기능공들의 숙련도에 따라 구조용 실란트(6)의 성능이 좌우되는 불합리성을 내재하여 부실시공의 원인이 되었다.In particular, the structural sealant 6 injected between the glass 5 and the curtain wall frame is dependent upon the gap retaining material 4 bonded between the glass 5 and the curtain wall structure until the desired adhesive strength is achieved. In order to withstand the weight of the building and the wind load on the exterior of the building, the loads on the bonding strength of the spacer 4 are not fully supported in this process and adversely affect the structural sealant 6 which is in progress. The original bond strength cannot be sufficiently exhibited, and the subsidiary work is caused due to the irrationality in which the performance of the structural sealant 6 depends on the skill of the field technicians.

또한, 작업환경이 열악한 고공에서 유리를 부착해야 하기 때문에, 건물 외벽을 유리로 마감하는 커튼월 시스템의 장점을 살리지 못하고, 마감표면이 고르지 않아 미적 효과를 떨어트리는 등 여러 문제점이 있었다.In addition, because the glass must be attached in a high altitude of poor working environment, there are various problems such as failing to take advantage of the curtain wall system that finishes the outer wall of the building with glass, and the finishing surface is uneven to reduce the aesthetic effect.

이에, 본 발명자는 스틱시스템 커튼월에 의해 유리마감 타입을 시공하는 종래기술에 있어서, 콘크리트 옹벽, 기둥, 스팬드럴 부위의 구조용 실란트를 현장에서 주입함에 따라 발생되는 제반 문제를 원천적으로 해결하기 위하여, 현장에서 구조용 실란트를 주입하는 것을 배제시킨 본발명을 안출하였다.Accordingly, the present inventors in order to solve the problems caused by injecting the structural sealant of the concrete retaining wall, column, spandral part in the field in the prior art of constructing the glass finish type by the stick system curtain wall, The present invention has been devised to exclude the injection of structural sealants in the field.

따라서, 본발명의 목적은 작업환경이 우수한 공장에서 숙련된 기능공에 의하여 구조용 실란트를 충진시키고 커튼월에서 요구되는 접합강도가 나타낼 때까지 완전히 경화시키어 품질의 우수성을 확보한 뒤, 커튼월의 설치현장에서는 조립만 하여 시공할 수 있도록 공장에서 미리 제작한 조립유리패널을 제공하는데 있다.Therefore, the object of the present invention is to fill the structural sealant by skilled workers in a factory with excellent working environment and completely harden it until the bonding strength required in the curtain wall is obtained. Is to provide prefabricated glass panels manufactured in the factory so that they can only be assembled.

본발명의 다른 목적은 상기 조립유리패널을 이용하여 시공이 간편할 뿐만 아니라, 구조적인 안정성을 보장하며, 스틱 커튼월 시스템에서 유리마감 형식에 따른 건물외관의 미감을 극대화시켜 주는 조립유리패널을 이용한 커튼월 시공방법을 제공하는데 있다.Another object of the present invention is to use the assembled glass panel, not only easy construction, but also ensure structural stability, using the assembled glass panel to maximize the aesthetics of the building appearance according to the glass finish type in the stick curtain wall system To provide a curtain wall construction method.

도1은 종래 기술에 따른 커튼월 구조체의 시공상태 평단면도1 is a plan sectional view of a construction state of a curtain wall structure according to the prior art

도2는 본 발명의 실시예에 따른 커튼월용 조립유리패널의 부분절개 사시도Figure 2 is a partial cutaway perspective view of the assembled glass panel for curtain wall according to an embodiment of the present invention

도3은 도2의 A-A선 상세단면도3 is a cross-sectional view taken along line A-A of FIG.

도4는 도2에 따른 조립유리패널의 정면발췌 단면도4 is a front excerpt sectional view of the assembled glass panel according to FIG.

도5는 본발명의 실시예에 따른 커튼월 구조체의 시공상태 정면도Figure 5 is a front view of the construction state of the curtain wall structure according to an embodiment of the present invention

도6은 도5의 B-B선 단면도FIG. 6 is a cross-sectional view taken along the line B-B of FIG. 5

도7은 도5의 C-C선 단면도7 is a cross-sectional view taken along the line C-C of FIG.

도8은 본발명의 실시예에 따른 커튼월 구조체의 시공상태 사시도8 is a perspective view of a construction state of the curtain wall structure according to an embodiment of the present invention

〈도면의 주요부분에 대한 부호의 설명〉<Explanation of symbols for main parts of drawing>

1:건물구조체 2:수직재 3:수평재1: Building structure 2: Vertical material 3: Horizontal material

4:간격유지재 5:유리 6:실란트4: Spacing material 5: Glass 6: Sealant

7:압박판 8:결속핀 10:유리패널7: pressing plate 8: binding pin 10: glass panel

20:고정틀 21:채널형홈 22:가스켓홈20: fixing frame 21: channel type groove 22: gasket groove

23:코너보강재 30:실란트 40:간격유지재23: Corner reinforcement 30: Sealant 40: Spacing maintenance material

100:조립유리패널 200:고정구 201:머리부100: assembled glass panel 200: fixture 201: head

300a:수직재 300b:수평재 301:결착홈300a: vertical material 300b: horizontal material 301: binding groove

400:고정나사 500:가스켓 S:건물구조체400: set screw 500: gasket S: building structure

상기 목적들을 달성하기 위한 본 발명은 알미늄 압출재인 수직재와 수평재를 현장의 건물구조체에 격자형으로 긴결, 설치하여 커튼월 골조체를 형성하여 두고, 이와는 별개로 공장에서 유리패널의 이면 가장자리에 고정틀을 실란트로 부착하여 조립유리패널을 제작한 다음, 이 조립유리패널을 현장으로 운반하여 현장에 설치되어 있는 커튼월 골조체의 수직재 및 수평재에 고정구 및 고정나사등을 통하여 고정설치하는 것을 기술구성상의 기본적인 특징으로 한다.The present invention for achieving the above object is to form a curtain wall frame by connecting the vertical and horizontal members of the aluminum extruded material in a lattice form on the building structure of the site, and separately from the fixing frame on the back edge of the glass panel in the factory After fabricating the assembled glass panel by attaching it with sealant, the assembled glass panel is transported to the site and fixed to the vertical and horizontal members of the curtain wall frame installed on the site through fixtures and fixing screws. It is done.

이하, 본 발명의 기술구성을 본발명의 실시예에 따른 첨부도면을 참조하여 구체적으로 설명한다.Hereinafter, the technical configuration of the present invention will be described in detail with reference to the accompanying drawings in accordance with an embodiment of the present invention.

본 발명의 실시예에 따른 조립유리패널은 도2 내지 도4의 도시와 같이, 커튼월의 외벽판재로 설치되도록 가공된 4각형태의 유리패널(10)과, 4방의 바깥쪽 옆구리면을 따라 채널형홈(21)을 갖는 4각틀체로 조립되어 상기 유리의 이면 가장자리부에 부착되는 고정틀(20)과, 상기 유리패널(10)과 고정틀(20)을 양측으로 두고 그것들의 사이에 들어가 일정 두께로 충진되어 2부재들을 상호 부착하여 주는 구조용 실란트(30)로 구성되는 것을 특징으로 한다.Assembled glass panel according to an embodiment of the present invention, as shown in Figures 2 to 4, the four-sided glass panel 10, which is processed to be installed as the outer wall plate material of the curtain wall, along the outer side of the four sides The fixed frame 20 is assembled into a rectangular frame having a channel-shaped groove 21 and attached to the rear edge of the glass, and the glass panel 10 and the fixing frame 20 are placed on both sides thereof, and enter into a predetermined thickness between them. It is characterized by consisting of a structural sealant 30 is filled with two members attached to each other.

상기에서 고정틀(20)은 상기 유리패널(10)의 4변에 각각 상응하는 길이로 절단되며 채널형강재로 조립되며, 이 채널형강재로서는 알미늄 압출재가 사용된다.The fixing frame 20 is cut into lengths corresponding to the four sides of the glass panel 10 and assembled into a channel steel, and an aluminum extrusion material is used as the channel steel.

이 채널형강재의 외측에는 채널형홈(21)이 형성되고, 내측에는 가스켓홈(22)이 형성된다.The channel-shaped groove 21 is formed on the outer side of the channel steel, and the gasket groove 22 is formed on the inner side.

고정틀(20)은 상기 홈들에 의해서, 4방의 바깥쪽 옆구리면에 채널형홈(21)이 형성되며, 안쪽 옆구리면에는 가스켓홈(22)이 형성되는 4각틀체로 완성된다.The fixing frame 20 is formed by the grooves, the channel-shaped groove 21 is formed on the four outer sides of the four sides, the inner side is completed with a four-sided frame formed with a gasket groove 22.

채널형강재들의 양측단부들은 45°각도로 절단되어서 이웃하는 것들끼리 맞대어져 조립된다.Both ends of the channel steels are cut at an angle of 45 ° so that neighboring ones are assembled to each other.

채널형강재들이 맞대어지는 4모서리부의 채널형홈(21)에는 각각 앵글형 플레이트로 제작된 코너보강재(23)가 삽입된 후 나사고정되어서 이웃하는 채널형강재를 연결하는 동시에 보강하여 준다.The four corners of the channel-shaped grooves are joined to the channel-shaped groove 21, the corner stiffener 23 is made of an angle plate is inserted and then screwed to reinforce at the same time to connect the adjacent channel-shaped steel.

상기 유리패널(10)과 고정틀(20)의 사이에는 정확한 구조계산에 의거해, 일정한 두께를 가지며 양쪽면에 접착성을 띠는 간격유지재(40)가 상기 실란트(30)가 충진되기에 앞서 내측으로 들어가 1차적으로 접착된다.Between the glass panel 10 and the fixing frame 20 based on the exact structural calculation, the gap retainer 40 having a predetermined thickness and adhesiveness on both sides before the sealant 30 is filled. It enters inside and is primarily bonded

유리패널(10)과 고정틀(20)은 상기 간격유지재(40)에 의해 일정간격이 유지된 상태에서, 그것들의 사이공간에 상기 실란트(30)가 골고루 충진되어 접합된다.The glass panel 10 and the fixing frame 20 are bonded to each other by filling the sealant 30 evenly in the spaces between them while a predetermined interval is maintained by the gap maintaining material 40.

구조용 실란트(30)가 충진되어 일체화된 유리패널(10)과 고정틀(20)은 구조용 실란트(30)가 완전히 경화되어 주어진 접착강도를 완전히 발휘할 때까지 정확한 수평을 유지토록 관리한다.The glass panel 10 and the fixing frame 20 integrated with the structural sealant 30 are maintained to maintain the correct level until the structural sealant 30 is completely cured to fully exhibit a given adhesive strength.

따라서, 본발명에 의한 조립유리패널(100)은 커튼월의 설계에 따라 모든 제품들이 일정한 품질로 규격화되어 공장제작된다.Therefore, the assembled glass panel 100 according to the present invention is manufactured in a factory in which all products are standardized to a certain quality according to the design of the curtain wall.

본 발명의 실시예에 따른 커튼월 시공방법은 도5 내지 도8의 도시와 같이, 상기 기재한 바와 같이 공장에서 커튼월용 유리패널(10)과 4방의 바깥쪽 옆구리면을 따라 채널형홈(21)을 갖는 고정틀(20)을 구조용 실란트(30)로 접합하여 조립유리패널(100)을 제작한 후, 그 조립유리패널(100)을 현장으로 운반하여 이웃하는 조립유리패널(100)의 채널형홈(21)에 고정구(200)를 일정간격으로 절반씩 끼워 넣고, 현장의 건물구조체(S)에 격자형으로 긴결설치되어 있는 커튼월 골조체의 수직재(300a) 및 수평재(300b)에 상기 고정구(200)를 고정나사(400)로 체결하여서 상기 조립유리패널(100)의 고정틀(20)을 상기 수직재(300a) 및 수평재(300b)에 압박 고정시키는 작업을 통하여, 상기 커튼월 골조체에 상기 유리패널(10)을 설치함을 특징으로 한다.Curtain wall construction method according to an embodiment of the present invention, as shown in Figures 5 to 8, the channel-shaped grooves 21 along the outer side of the glass panel for the curtain wall 10 and the four sides in the factory as described above After joining the fixing frame 20 having a structural sealant 30 to manufacture the assembled glass panel 100, the assembled glass panel 100 is transported to the site of the channel-shaped groove of the neighboring assembled glass panel 100 ( The fittings 200 are inserted in half at regular intervals 21, and the fixtures 200 are disposed on the vertical members 300a and the horizontal members 300b of the curtain wall frame which are tightly installed in a grid structure on the building structure S of the site. ) By fastening the fixing screw 400 to the fixing frame 20 of the assembled glass panel 100 to the vertical member (300a) and the horizontal member (300b) through the operation, the glass wall frame to the frame It characterized in that the installation (10).

상기에서 커튼월 골조체의 수직재(300a) 및 수평재(300b)는 알미늄 압출재가 사용된다.In the above, the vertical member 300a and the horizontal member 300b of the curtain wall frame are made of aluminum extrusion material.

이 수직재(300a) 및 수평재(300b)는 그 전면들에 길이방향을 따라 내측으로 들어간 결착홈(301)이 형성된다.The vertical member 300a and the horizontal member 300b are provided with binding grooves 301 which enter the inner side along the longitudinal direction on the front surfaces thereof.

상기 고정구(200)는 알미늄 주물제품이 사용된다.The fixture 200 is an aluminum casting product is used.

이 고정구는 상기 수직재(300a) 및 수평재(300b)에 형성된 결착홈(301)에 상응하는 폭으로 그 중앙부의 머리부(201)가 돌출되는 T형상으로 형성되고, 그 머리부(201)에는 구멍이 뚫려 있어서, 상기 결착홈(301)에 머리부(201)를 끼워서 나사 결착시키도록 한 구성으로 되어 있다.The fastener is formed in a T shape in which the head portion 201 of the center portion protrudes in a width corresponding to the binding groove 301 formed in the vertical member 300a and the horizontal member 300b, and has a hole in the head portion 201. This hole has a configuration in which the head 201 is screwed into the binding groove 301 to be screwed.

상기 고정틀(20)의 안쪽 옆구리면을 따라 형성된 가스켓홈(22)에는 상기 커튼월 골조체의 수직재(300a) 및 수평재(300b)의 외표면과 상기 유리패널(10)의 이면에 밀착되는 가스켓(500)을 설치한다.The gasket groove 22 formed along the inner side of the fixing frame 20 is in close contact with the outer surface of the vertical member 300a and the horizontal member 300b of the curtain wall frame and the rear surface of the glass panel 10. 500).

이 가스켓(500)은 상기 실란트(30)와 고정틀(20)이 접합된 부분을 밀폐하여서 외기 및 수분의 침투를 방지하여 준다.The gasket 500 seals a portion where the sealant 30 and the fixing frame 20 are joined to prevent penetration of outside air and moisture.

이상과 같이 시공되는 본발명은 스틱시스템 커튼월에서 유리마감 구조의 최대 핵심인 구조용 실란트(30)가 공장에서 미리 충진되어 완전히 경화된 상태로 제작된 후 현장에서는 간단한 조립만으로 설치가 완료되므로, 작업성이 우수한 것은 물론이고, 유리패널이 구조적으로 안정되게 고정되는 커튼월 구조체를 구현하여 준다.Since the present invention is constructed as described above, the structural sealant 30, which is the largest core of the glass finishing structure in the stick system curtain wall, is pre-filled at the factory and manufactured in a completely hardened state, and thus the installation is completed by simple assembly in the field. As well as excellent properties, it implements a curtain wall structure in which the glass panel is structurally stable fixed.

상기한 바와 같이 본발명의 커튼월용 조립유리패널 및 그것을 이용한 커튼월 시공방법에 의하면, 종래 스틱시스템 커튼월에 적용되는 유리마감구조에 있어서 유리와 커튼월 골조체를 구조적으로 접합시켜 주는 구조용 실란트의 현장접합으로 인해 접합이 불량했던 부위, 즉 콘크리트 옹벽, 기둥, 스팬드럴 부위의 구조적 결함이 야기되어 왔던 종래기술과는 달리, 구조용 실란트를 이용한 유리의 공장취부 방법을 채택하여 일체화시킨 조립유리패널을 공장제작한 후, 이 조립유리패널을 현장으로 운반하여 건물구조체에 결속된 커튼월 골조체에 고정구와 고정나사를 이용하여 설치함으로써, 시공이 간편하여 현장공기가 단축되고 경제적인 시공이 이루어질 뿐만 아니라, 공장에서 체계화된 제작 체계에 의해 품질관리가 정확히 이루어진 우수한 품질의 제품을 얻을 수 있어 구조적인 안정성이 뛰어나고, 아울러 건물 외관의 미적 효과를 최대한 살릴 수 있는 커튼월을 구현하여 주는 등 여러 효과가 있는 매우 유용한 발명이다.As described above, according to the assembled glass panel for the curtain wall of the present invention and the curtain wall construction method using the same, the structural sealant structurally joining the glass and the curtain wall frame structure in the glass finishing structure applied to the conventional stick system curtain wall Unlike the prior art in which structural defects such as concrete retaining walls, columns and spandral parts have been caused by poor bonding due to field joining, the assembled glass panel is integrated by adopting a factory mounting method of glass using structural sealant. After the factory is manufactured, the assembled glass panels are transported to the site and installed on the curtain wall frame, which is bound to the building structure, using fixtures and fixing screws. Quality with precise quality control by a systematic production system Excellent structural stability it can get the products, as well as a very useful invention that has multiple effects that the implementation of a curtain that can save as much as possible the aesthetic effect of the building facade.

Claims (6)

커튼월의 외벽판재로 설치되도록 가공된 4각형태의 유리패널(10)과, 4방의 바깥쪽 옆구리면을 따라 채널형홈(21)을 갖는 4각틀체로 조립되어 상기 유리의 이면 가장자리부에 부착되는 고정틀(20)과, 상기 유리패널(10)과 고정틀(20)을 양측으로 두고 그것들의 사이에 들어가 일정 두께로 충진되어 2부재들을 상호 부착하여 주는 구조용 실란트(30)로 구성되는 것을 특징으로 하는 커튼월용 조립유리패널.A quadrangular glass panel 10 processed to be installed as an outer wall plate of a curtain wall and a quadrangular frame body having channel grooves 21 along four outer sides are attached to the rear edge of the glass. The fixing frame 20, and the glass panel 10 and the fixing frame 20 to both sides and enters between them filled with a predetermined thickness, characterized in that consisting of the structural sealant 30 to attach the two members to each other Assembly glass panel for curtain wall. 제1항에 있어서, 상기 고정틀(20)은 상기 유리패널(10)의 4변에 각각 상응하는 길이로 절단된 4개의 채널형강재를 조립하여 형성하되, 채널형강재들의 양측단부들이 45°각도로 절단되어 이웃하는 것들끼리 맞대어져 조립되며, 그 4모서리부의 채널형홈(21)에는 각각 앵글형 플레이트로 제작된 코너보강재(23)가 삽입고정되어서 이웃하는 채널형강재를 연결하는 동시에 보강하여 줌을 특징으로 하는 커튼월용 조립유리패널.According to claim 1, wherein the fixing frame 20 is formed by assembling four channel-shaped steel cut to a length corresponding to each of the four sides of the glass panel 10, wherein both ends of the channel-shaped steel are 45 ° angle The neighboring ones are cut together to be assembled to each other, and the corner reinforcements 23 made of angle plates are inserted into the channel-shaped grooves 21 of the four corners, respectively. Assembly glass panel for curtain wall characterized in that. 제1항에 있어서, 상기 유리패널(10)과 고정틀(20)의 사이에는 양쪽면에 접착성을 띠는 간격유지재(40)가 1차적으로 접착되어 일정간격이 유지되고, 그 간격유지재(40)로 인해 일정하게 형성된 유리패널(10)과 고정틀(20)의 사이공간에 상기 실란트(30)가 충진되어 접합된 것을 특징으로 하는 커튼월용 조립유리패널.According to claim 1, wherein the gap between the glass panel 10 and the fixing frame 20 is adhered to both sides of the interval maintaining material 40 is primarily bonded to maintain a constant interval, the gap holding material Assembly glass panel for a curtain wall, characterized in that the sealant 30 is filled and bonded to the space between the glass panel 10 and the fixed frame 20 is formed constantly by the 40. 공장에서 커튼월용 유리패널(10)과 4방의 바깥쪽 옆구리면을 따라 채널형홈(21)을 갖는 고정틀(20)을 구조용 실란트(30)로 접합하여 조립유리패널 (100)을 제작한 후, 그 조립유리패널(100)을 현장으로 운반하여 이웃하는 조립유리패널(100)의 채널형홈(21)에 고정구(200)를 일정간격으로 절반씩 끼워 넣고, 현장의 건물구조체(S)에 격자형으로 긴결 설치되어 있는 커튼월 골조체의 수직재(300a) 및 수평재(300b)에 상기 고정구(200)를 고정나사(400)로 체결하여서 상기 조립유리패널(100)의 고정틀(20)을 상기 수직재(300a) 및 수평재(300b)에 압박 고정시키는 작업을 통하여, 상기 커튼월 골조체에 상기 유리패널(10)을 설치함을 특징으로 하는 조립유리패널을 이용한 커튼월 시공방법.After fabricating the assembled glass panel 100 by joining the fixing frame 20 having the channel-shaped groove 21 along the outer sides of the curtain wall glass panel 10 and the four sides in the factory with the structural sealant 30, The assembly glass panel 100 is transported to the site, and the fixture 200 is inserted into the channel-shaped groove 21 of the neighboring assembly glass panel 100 at regular intervals, and the grid structure is formed on the building structure S of the site. The fixing frame 20 of the assembled glass panel 100 is fastened to the vertical member 300a and the horizontal member 300b of the curtain wall frame body which is tightly installed by the fixing screw 400, and the vertical member 300a. And a horizontal wall (300b) through the fixing operation, the curtain wall construction method using the assembled glass panel, characterized in that the glass panel 10 is installed on the curtain wall frame. 제4항에 있어서, 상기 커튼월 골조체의 수직재(300a) 및 수평재(300b)는 그 전면에 길이방향을 따라 내측으로 들어간 결착홈(301)이 형성되고, 상기 고정구 (200)는 그 중앙부의 머리부(201)가 돌출되는 T형상으로 형성되어서, 상기 결착홈 (301)에 머리부(201)를 끼워서 결착시키도록 한 것을 특징으로 하는 조립유리패널을 이용한 커튼월 시공방법.The vertical member (300a) and the horizontal member (300b) of the curtain wall frame is formed in the front of the binding groove 301 which is inwardly in the longitudinal direction is formed, the fastener 200 is the center portion The head part 201 is formed in a T-shape protruding, and the curtain wall construction method using the assembled glass panel, characterized in that the binding by inserting the head portion 201 in the binding groove (301). 제4항에 있어서, 상기 고정틀(20)은 그 4방의 안쪽 옆구리면을 따라 가스켓홈(22)이 형성되고, 가스켓홈(22)에는 상기 커튼월 골조체의 수직재(300a) 및 수평재(300b)의 외표면과 상기 유리패널(10)의 이면에 밀착되는 가스켓(500)을 설치하여서, 상기 실란트(30)와 고정틀(20)이 접합된 부분을 밀폐하여 주는 것을 특징으로 하는 조립유리패널을 이용한 커튼월의 설치방법.The gasket groove 22 is formed along four inner side surfaces of the fixing frame 20, and the gasket groove 22 has a vertical member 300a and a horizontal member 300b of the curtain wall frame. By installing a gasket 500 in close contact with the outer surface of the glass panel 10 and the rear surface of the, the sealant 30 and using the assembly glass panel, characterized in that to seal the portion bonded to the fixing frame 20 How to install curtain wall.
KR10-2000-0010342A 2000-03-02 2000-03-02 Shop Glazing System by Structural Silicone in Stick System Curtain Wall KR100411948B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2000-0010342A KR100411948B1 (en) 2000-03-02 2000-03-02 Shop Glazing System by Structural Silicone in Stick System Curtain Wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2000-0010342A KR100411948B1 (en) 2000-03-02 2000-03-02 Shop Glazing System by Structural Silicone in Stick System Curtain Wall

Publications (2)

Publication Number Publication Date
KR20010015933A true KR20010015933A (en) 2001-03-05
KR100411948B1 KR100411948B1 (en) 2003-12-18

Family

ID=19651471

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2000-0010342A KR100411948B1 (en) 2000-03-02 2000-03-02 Shop Glazing System by Structural Silicone in Stick System Curtain Wall

Country Status (1)

Country Link
KR (1) KR100411948B1 (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100779930B1 (en) * 2007-02-14 2007-11-28 이봉재 Outer wall decoration panel of building
KR100947163B1 (en) * 2008-03-07 2010-03-12 이봉재 Outer wall decoration ceramic panel of building
CN109429820A (en) * 2019-01-11 2019-03-08 韩霄然 A kind of novel glass mounting structure for glasshouse
KR20200021876A (en) 2019-07-02 2020-03-02 정태호 An art wall assembly for building wall finishing
KR20200134505A (en) * 2019-05-22 2020-12-02 주식회사 인아웃텍 Windows frame
KR20210003617A (en) 2019-07-02 2021-01-12 정태호 An art wall system
CN112267603A (en) * 2020-11-25 2021-01-26 中国十七冶集团有限公司 Externally-hung glass curtain wall corner column and construction method
CN112459315A (en) * 2020-11-23 2021-03-09 王翊彤 Building glass curtain wall structure convenient to dismouting just has self-locking structure
CN112854566A (en) * 2021-02-25 2021-05-28 伍保国 Assembled curtain is used to building decoration with quick mounting structure
CN113250355A (en) * 2021-06-01 2021-08-13 江苏致一建设工程有限公司 Anti-falling high-sealing glass curtain wall mounting structure
EP3779083A4 (en) * 2018-03-30 2021-12-22 LIXIL Corporation Glass panel support structure
WO2022131426A1 (en) * 2020-12-18 2022-06-23 (주)거광기업 Multi-functional platform curtainwall system
CN115405120A (en) * 2022-09-28 2022-11-29 中建八局第二建设有限公司 Relief GRC curtain wall construction tool and construction method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100652129B1 (en) 2004-12-13 2006-12-01 주식회사 엘지화학 Sheath type curtain wall system having an adiabatic structure using a gasket
KR102622191B1 (en) * 2022-01-19 2024-01-09 주식회사 아키페이스 Curtain wall system With SideGasket

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4650702A (en) * 1985-10-15 1987-03-17 Kawneer Company, Inc. Structural interface and weatherseal for structurally bonded glazing
GB8829937D0 (en) * 1988-12-22 1989-02-15 Don Reynolds Limited Building system
JPH0518030A (en) * 1991-07-12 1993-01-26 Shin Nikkei Co Ltd Slippage stop construction of face member in ssg type curtain wall
JPH0765342B2 (en) * 1993-02-02 1995-07-19 株式会社玉俊工業所 Connection structure of mounting members
US5369924A (en) * 1993-04-30 1994-12-06 Neudorf; Peter Structural curtainwall system and components therefor
JPH11293796A (en) * 1998-04-13 1999-10-26 Shin Etsu Polymer Co Ltd Gasket, panel mounting structure, and panel mounting method

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100779930B1 (en) * 2007-02-14 2007-11-28 이봉재 Outer wall decoration panel of building
KR100947163B1 (en) * 2008-03-07 2010-03-12 이봉재 Outer wall decoration ceramic panel of building
EP3779083A4 (en) * 2018-03-30 2021-12-22 LIXIL Corporation Glass panel support structure
US11834894B2 (en) 2018-03-30 2023-12-05 Lixil Corporation Glass panel support structure
CN109429820A (en) * 2019-01-11 2019-03-08 韩霄然 A kind of novel glass mounting structure for glasshouse
KR20200134505A (en) * 2019-05-22 2020-12-02 주식회사 인아웃텍 Windows frame
KR20200021876A (en) 2019-07-02 2020-03-02 정태호 An art wall assembly for building wall finishing
KR20210003617A (en) 2019-07-02 2021-01-12 정태호 An art wall system
CN112459315A (en) * 2020-11-23 2021-03-09 王翊彤 Building glass curtain wall structure convenient to dismouting just has self-locking structure
CN112459315B (en) * 2020-11-23 2021-10-22 王翊彤 Building glass curtain wall structure convenient to dismouting just has self-locking structure
CN112267603A (en) * 2020-11-25 2021-01-26 中国十七冶集团有限公司 Externally-hung glass curtain wall corner column and construction method
WO2022131426A1 (en) * 2020-12-18 2022-06-23 (주)거광기업 Multi-functional platform curtainwall system
KR20220087802A (en) * 2020-12-18 2022-06-27 (주)거광기업 Multi functional platform curtain wall system
CN112854566A (en) * 2021-02-25 2021-05-28 伍保国 Assembled curtain is used to building decoration with quick mounting structure
CN113250355B (en) * 2021-06-01 2022-05-17 江苏致一建设工程有限公司 Anti-falling high-sealing glass curtain wall mounting structure
CN113250355A (en) * 2021-06-01 2021-08-13 江苏致一建设工程有限公司 Anti-falling high-sealing glass curtain wall mounting structure
CN115405120A (en) * 2022-09-28 2022-11-29 中建八局第二建设有限公司 Relief GRC curtain wall construction tool and construction method
CN115405120B (en) * 2022-09-28 2023-10-20 中建八局第二建设有限公司 Construction tool and construction method for embossed GRC curtain wall

Also Published As

Publication number Publication date
KR100411948B1 (en) 2003-12-18

Similar Documents

Publication Publication Date Title
KR100411948B1 (en) Shop Glazing System by Structural Silicone in Stick System Curtain Wall
JP2755900B2 (en) curtain wall
NZ507152A (en) Wall cladding assembly with cladding having recesses along opposite sides to engage with flanges of support members
JPH02197639A (en) Junction block for building
KR101772493B1 (en) Curtain wall system that is compatible with the structural element bars
KR880000028B1 (en) Glass unit
KR100947053B1 (en) Insulation panel structure and the form of construction work
CN110984408B (en) Sealing device between externally hung wallboards for assembled building
JPH0754015B2 (en) Insulation panel for wall in wooden building and construction method of this insulation panel for wall
JPS6049738B2 (en) How to install glass plates in curtain wall
JPH0740006Y2 (en) Curtain wall panel structure
CN211714305U (en) Combined building curtain wall
CN211647767U (en) Finished aluminum alloy door and window
CN219100598U (en) Socket-joint opposite-buckling type assembled overhead ground system
CN211229105U (en) Hollow glass module and semi-hidden frame or hidden frame glass curtain wall system
CN108266092B (en) Door and window structure
EP2395170B1 (en) Device for mounting glass bricks
JP2024049475A (en) How to assemble a glass door
KR20000024010A (en) executing method for window frame assembly
CN203546970U (en) Unit glass auxiliary frame section bar
KR101352173B1 (en) Sealing member and double skin curtain wall having the same
JPH0647050Y2 (en) Joint structure of outer wall panel
JPS59187959A (en) Corner part connecting structure of tile panel structure
CN116044113A (en) Socket-joint opposite-buckling type assembled overhead ground system
JPS6346608Y2 (en)

Legal Events

Date Code Title Description
A201 Request for examination
G15R Request for early opening
N231 Notification of change of applicant
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20111209

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20121211

Year of fee payment: 10

LAPS Lapse due to unpaid annual fee