KR20000053938A - Form Work Device Of Concrete Structure - Google Patents

Form Work Device Of Concrete Structure Download PDF

Info

Publication number
KR20000053938A
KR20000053938A KR1020000025131A KR20000025131A KR20000053938A KR 20000053938 A KR20000053938 A KR 20000053938A KR 1020000025131 A KR1020000025131 A KR 1020000025131A KR 20000025131 A KR20000025131 A KR 20000025131A KR 20000053938 A KR20000053938 A KR 20000053938A
Authority
KR
South Korea
Prior art keywords
formwork
support
corner
reinforcement
fixing
Prior art date
Application number
KR1020000025131A
Other languages
Korean (ko)
Other versions
KR100381681B1 (en
Inventor
이봉수
Original Assignee
이봉수
서용건설 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이봉수, 서용건설 주식회사 filed Critical 이봉수
Priority to KR10-2000-0025131A priority Critical patent/KR100381681B1/en
Priority to KR2020000014934U priority patent/KR200200945Y1/en
Publication of KR20000053938A publication Critical patent/KR20000053938A/en
Application granted granted Critical
Publication of KR100381681B1 publication Critical patent/KR100381681B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/04Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements
    • E04G17/042Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements being tensioned by threaded elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/04Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements
    • E04G17/045Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements being tensioned by wedge-shaped elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PURPOSE: A mold apparatus of a concrete structure is provided to form the surface of a concrete structure smoothly and to assemble a mold apparatus easily by reinforcement of a mold. CONSTITUTION: To form a four-cornered pillar, a corner support(50) is positioned on the corner between two molds(10). Then, a pin support unit is placed between a frame member and the corner support(50). A plurality of fixing pins is inserted into each hole of the pin support unit and the frame member. A support body(30) is pulled and a side reinforcement(20) is pushed by fixing a screw shaft(34) by a bolt(36). Therefore, the different two molds(10) are fixed firmly.

Description

콘크리트 구조물의 거푸집 장치{ Form Work Device Of Concrete Structure }Form work device of concrete structure

본 발명은 콘크리트를 지지하는 거푸집장치에 관한 것으로, 특히, 콘크리트 구조물을 형성하기 위하여 사용하는 거푸집을 "ㄱ" 자 형상으로 두 개를 서로 겹친 상태에서 모서리부분에 면귀부재를 대고서 고정핀으로 고정시키고, 거푸집에 수평으로 덧대진 측면보강부재에 모서리보강수단으로 체결하여 고정시킨 후, 측면가압수단 및 보조모서리 보강수단을 설치하여서 거푸집을 보강하므로 조립이 용이하고 콘크리트 구조물의 표면이 매끄럽게 형성하도록 하는 콘크리트 구조물의 거푸집장치에 관한 것이다.The present invention relates to a formwork for supporting concrete, and in particular, the formwork used to form a concrete structure "a" in the shape of the two overlapping each other in the state overlapping the edge of the face member and fixed with a fixing pin After fastening by means of corner reinforcing means to the side reinforcement member horizontally padded to the formwork, the side reinforcing means and the auxiliary edge reinforcing means are installed to reinforce the formwork so that the assembly is easy and the surface of the concrete structure is formed smoothly. It relates to a formwork for concrete structures.

일반적으로, 거푸집이라는 건축기구물은 콘크리트를 사용하여 벽체 혹은 내력기둥 등을 형성할 때, 콘크리트의 외곽면을 지지하여 평면을 형성하여 주는 콘크리전용 보강체이다.In general, a building structure called a formwork is a concrete reinforcement for forming a plane by supporting the outer surface of the concrete when forming walls or bearing columns using concrete.

상기한 거푸집은 초기에는 나무, 특히, 합판을 사용하여 판재로 이용하고 목재빔등을 사용하여 지지대로 사용하여서 거푸집으로서 역할을 수행하다가 최근에는 금속판재를 사용하고 그 이외의 보강재를 덧대어서 거푸집으로 사용하는 추세에 있다.The formwork is initially used as a plate using wood, especially plywood, and as a support using wood beams, etc. Recently, the formwork is used as a formwork by using a metal plate and reinforcing other materials. There is a trend to use.

그런데, 상기 목재빔을 사용하여 거푸집으로 사용하는 경우에는 목재 거푸집을 고정하여 눌러주는 별도의 보강수단이 많이 필요할 뿐 만아니라 목재의 경우에는 가격이 비싸고 반복적으로 사용하는 경우 내구성이 약하여서 전체적인 공정에 분리한 절감하지 못하는 문제점을 지닌다.However, in the case of using the wood beam as a formwork, not only a lot of separate reinforcement means for fixing and pressing the wood formwork, but also in the case of wood is expensive and repeated use is weak in durability and the overall process There is a problem that can not be separated.

이와 같이, 최근에는 목재 대신에 금속재질을 사용하여 공사를 진행하는 추세가 이루어지고 있으며, 금속재를 사용한 경우에는 거푸집이 연결되는 부분과 모서리부분 및 측면부분을 적절하게 보강하지 못하여 정밀한 콘크리트구조물에는 제대로 적용하지 못하는 문제점을 지닌다.As such, in recent years, a trend is being made to use metal materials instead of wood, and in the case of using metal materials, it is difficult to properly reinforce the part, the corner part and the side part to which the formwork is connected, so that it can be properly applied to the precise concrete structure. There is a problem that cannot be applied.

본 발명은 이러한 점을 감안하여 안출한 것으로서, 콘크리트 구조물을 형성하기 위하여 사용하는 거푸집을 "ㄱ" 자 형상으로 두 개를 서로 겹친 상태에서 모서리부분에 면귀부재를 대고서 고정핀으로 고정시키고, 거푸집에 수평으로 덧대진 측면보강부재에 모서리보강수단으로 체결하여 고정시킨 후, 측면가압수단 및 보조모서리 보강수단을 설치하여서 거푸집을 보강하므로 조립이 용이하고 콘크리트 구조물의 표면이 매끄럽게 형성하는 것이 목적이다.The present invention has been made in view of this point, the formwork used to form a concrete structure "a" in the form of the two overlapping each other in the state overlapping each other in the corner portion to fix the fixing pin, the formwork After fastening by means of edge reinforcing means to the side reinforcement member horizontally padded on the side reinforcement means, by installing the side pressure means and the auxiliary edge reinforcement means to reinforce the formwork is easy to assemble and smooth surface of the concrete structure.

도 1은 본 발명에 따른 거푸집장치의 구조를 보인 도면이고,1 is a view showing the structure of the formwork apparatus according to the present invention,

도 2는 본 발명에 따른 거푸집장치에서 분리되는 부분을 보인 도면이며,Figure 2 is a view showing a part separated from the formwork apparatus according to the present invention,

도 3은 본 발명에 따른 거푸집장치의 측면보강수단을 보인 분해 사시도 이고,Figure 3 is an exploded perspective view showing the side reinforcing means of the formwork apparatus according to the present invention,

도 4는 본 발명에 따른 측면보강수단의 조립 상태를 보인 도면이며,4 is a view showing an assembled state of the side reinforcing means according to the present invention,

도 5는 본 발명에 따른 보조 모서리보강수단의 조립 상태를 보인 도면이며,5 is a view showing an assembled state of the auxiliary edge reinforcing means according to the present invention,

도 6은 본 발명에 따른 거푸집장치의 사용 상태를 보인 평면도이다.Figure 6 is a plan view showing a state of use of the formwork apparatus according to the present invention.

-도면의 주요부분에 대한 부호의 설명-Explanation of symbols on the main parts of the drawing

10 : 거푸집 12 : 지지패널10 formwork 12 support panel

14 : 수직 보강재 20 : 측면 보강재14: vertical reinforcement 20: side reinforcement

22 : 요홈부 24 : 코너 커넥터22: groove 24: corner connector

30 : 모서리 보강수단 32 : 지지체30: corner reinforcement means 32: support

34 : 고정나사축 36 : 고정볼트34: fixing screw shaft 36: fixing bolt

37 : 끼움공 40 : 면귀부재37: fitting hole 40: face ear member

42 : 고정핀 지지부 50 : 모서리 지지대42: fixing pin support 50: corner support

60 : 측면 보강부재 62 : 지지부재60: side reinforcement member 62: support member

65 : 가압보강재 67 : 고정볼트65: pressure reinforcement 67: fixing bolt

70 : 보조 모서리 보강수단70: secondary corner reinforcement means

이러한 목적은 프레임부재의 내측면에 콘크리트에 접촉되는 지지패널을 형성하고, 수직으로 수직보강재를 보강하여 콘크리트구조물을 형성하는 거푸집 장치에 있어서, 상기 거푸집의 수직보강재에 수평으로 고정되어 일정한 상,하간격으로 요홈부를 갖도록 형성된 측면보강재와; 상기 각각의 거푸집의 프레임부재에 접촉되어서 90도 각도로 절곡되어 다수의 통공이 형성된 모서리지지대와; 상기 두 개의 거푸집의 모서리 부분에 일정 각도로 절곡된 고정핀지지부가 돌출되어서 프레임부재에 접촉되어지고, 모서리지지대의 통공, 고정핀지지부의 끼움공 및 프레임부재의 통공으로 끼워진 고정핀에 의하여 콘크리트구조물의 모서리 부분을 경사지게 형상하는 면귀부재와; 상기 각각의 거푸집의 모서리 부분에 위치한 측면보강재의 요홈부에 삽입되어서 거푸집의 모서리 부분을 가압하여 고정하는 모서리보강수단과; 상기 각각의 거푸집의 측면부분에 측면보강재를 가압하여 거푸집의 연결부위를 가압하여 보강하는 측면보강부재와; 상기 모서리보강수단이 설치된 거푸집의 다른 모서리부분 보강을 위하여 측면보강재의 요홈부에 고정 설치되는 보조모서리보강수단으로 구성된 콘크리트구조물의 거푸집장치를 제공함으로써 달성된다.The object is to form a support panel in contact with the concrete on the inner surface of the frame member, and to form a concrete structure by reinforcing the vertical reinforcement vertically, the horizontal reinforcement to the vertical reinforcement of the formwork fixed up, down A side reinforcing material formed to have a recessed portion at intervals; An edge support contacting the frame member of each formwork and being bent at an angle of 90 degrees to form a plurality of through holes; The fixed pin support part bent at an angle to the corners of the two formwork protrudes to contact the frame member, and the concrete structure by the fixing pin inserted into the hole of the corner support, the fitting hole of the fixing pin support and the hole of the frame member. Face ear member and the edge portion of the inclined shape; A corner reinforcing means inserted into the recess of the side reinforcement located at the corner of each formwork to press and fix the corner portion of the formwork; A side reinforcing member for pressing the side reinforcing member to the side portions of each formwork to pressurize and reinforce the connecting portion of the formwork; It is achieved by providing a formwork for the concrete structure consisting of secondary edge reinforcing means fixedly installed in the groove portion of the side reinforcement for reinforcing the other corner portion of the formwork with the corner reinforcement means is installed.

이하, 첨부한 도면에 의거하여 본 발명의 구성에 대하여 상세히 설명한다.EMBODIMENT OF THE INVENTION Hereinafter, the structure of this invention is demonstrated in detail based on an accompanying drawing.

우선, 도 1은 본 발명에 따른 거푸집장치의 구조를 보인 도면이고, 도 2는 본 발명에 따른 거푸집장치에서 분리되는 부분을 보인 도면이며, 도 3은 본 발명에 따른 거푸집장치의 측면보강수단을 보인 분해 사시도이고, 도 4는 본 발명에 따른 측면보강수단의 조립 상태를 보인 도면이며, 도 5는 본 발명에 따른 보조 모서리보강수단의 조립 상태를 보인 도면이며, 도 6은 본 발명에 따른 거푸집장치의 사용 상태를 보인 평면도이다.First, Figure 1 is a view showing the structure of the formwork apparatus according to the present invention, Figure 2 is a view showing a portion separated from the formwork apparatus according to the invention, Figure 3 is a side reinforcing means of the formwork apparatus according to the invention 4 is an exploded perspective view illustrating an assembly state of the side reinforcing means according to the present invention, FIG. 5 is a view illustrating an assembling state of the auxiliary edge reinforcing means according to the present invention, and FIG. 6 is a formwork according to the present invention. A plan view showing the state of use of the device.

본 발명의 구성은, 프레임부재(16)의 내측면에 콘크리트에 접촉되는 지지패널(12)을 형성하고, 수직으로 수직보강재(14)를 보강하여 콘크리트구조물(80)을 형성하는 거푸집(10) 장치에 있어서, 상기 거푸집(10)의 수직보강재(14)에 수평으로 고정되어 일정한 상,하간격으로 요홈부(22)를 갖도록 형성된 측면보강재(20)와; 상기 각각의 거푸집(10)의 프레임부재(16)에 접촉되어서 90도 각도로 절곡되어 다수의 통공(18)이 형성된 모서리지지대(50)와; 상기 두 개의 거푸집(10)의 모서리 부분에 일정 각도로 절곡된 고정핀지지부(42)가 돌출되어서 프레임부재(16)에 접촉되어지고, 모서리지지대(50)의 통공(52), 고정핀지지부(42)의 끼움공(44) 및 프레임부재(16)의 통공(18)으로 끼워진 고정핀(19)에 의하여 콘크리트구조물(80)의 모서리 부분을 경사지게 형상하는 면귀부재(40)와; 상기 각각의 거푸집(10)의 모서리 부분에 위치한 측면보강재(20)의 요홈부(22)에 삽입되어서 거푸집(10)의 모서리 부분을 가압하여 고정하는 모서리보강수단(30)과; 상기 각각의 거푸집(10)의 측면부분에 측면보강재(20)를 가압하여 거푸집(10)의 연결부위(17)를 가압하여 보강하는 측면보강부재(60)와; 상기 모서리보강수단(30)이 설치된 거푸집(10)의 다른 모서리부분에 보강을 위하여 측면보강재(20)의 요홈부(22)에 고정 설치되는 보조모서리보강수단(70)으로 구성된다.In the configuration of the present invention, the formwork 10 for forming the concrete structure 80 by forming a support panel 12 in contact with the concrete on the inner surface of the frame member 16, and vertically reinforce the vertical reinforcement (14) In the apparatus, the side reinforcement (20) formed horizontally fixed to the vertical reinforcement (14) of the formwork (10) to have a groove portion 22 at a constant upper and lower intervals; A corner support 50 which is contacted with the frame member 16 of each formwork 10 and bent at an angle of 90 degrees to form a plurality of through holes 18; Fixing pin support part 42 bent at an angle to the corner of the two formwork 10 is projected to contact the frame member 16, the through hole 52 of the corner support 50, the fixing pin support ( A faceting member 40 which inclined a corner portion of the concrete structure 80 by the fixing pin 19 fitted into the fitting hole 44 of the 42 and the through hole 18 of the frame member 16; Corner reinforcing means 30 is inserted into the groove portion 22 of the side reinforcement (20) located in the corner portion of each formwork 10 to press and fix the corner portion of the formwork (10); A side reinforcing member 60 for pressing the side reinforcing member 20 to the side portions of each formwork 10 to pressurize and reinforce the connecting portion 17 of the formwork 10; The edge reinforcing means 30 is composed of a secondary edge reinforcing means 70 is fixed to the groove portion 22 of the side reinforcing material 20 for reinforcement in the other corner portion of the formwork 10 is installed.

그리고, 상기 모서리보강수단(30)은, 상기 각각의 측면보강재(20)의 요홈부 (22)에 대칭 방향으로 삽입되어 측면보강재(20)의 삽입공(27)으로 삽입되어 관통공(38)으로 삽입된 고정핀(38)으로 고정되고, 수평으로 관통된 끼움공(37)을 형성하는 지지체(32)와; 상기 대응된 각각의 지지체(70)의 끼움공(37)에 삽입되는 고정나사축(34)과; 상기 고정나사축(34)에 각각 체결되어 각각의 지지체(32)를 서로 당겨주어서 서로 다른 두 개의 거푸집(10)의 모서리부분을 고정 시켜주는 고정볼트(36)로 구성된다.The corner reinforcing means 30 is inserted into the recess 22 of each side reinforcing material 20 in a symmetrical direction and inserted into the insertion hole 27 of the side reinforcing material 20 to pass through the hole 38. A support 32 which is fixed by a fixing pin 38 inserted into and formed in a horizontally fitted fitting hole 37; A fixed screw shaft (34) inserted into the fitting hole (37) of the corresponding support body (70); The fixing screw shaft 34 is fastened to each support 32 is composed of a fixing bolt 36 for fixing the corners of the two different formwork 10 by pulling each other.

또한, 상기 측면보강수단(60)은, 거푸집(10) 연결부위(17)의 측면보강재(20)의 요홈부(22)에 삽입되어 측면보강재(20)의 끼움공(26)으로 끼워진 고정핀(38)에 의하여 고정되고 일측으로 숫나사부(63)가 형성된 지지부재(62)와; 상기 지지부재(62)의 숫나사부(63)가 삽입장공(66)으로 돌출되어서 숫나사부(63)에 체결된 고정볼트(67)에 의하여 측면보강재(20)의 측면부를 가압하여 고정하는 가압보강재(65)로 구성된다.In addition, the side reinforcement means 60, the pin 10 is inserted into the groove portion 22 of the side reinforcing material 20 of the connection portion 17 of the mold 10 is fitted into the fitting hole 26 of the side reinforcing material (20). A support member 62 fixed by 38 and having a male screw portion 63 formed at one side thereof; The pressurized stiffener which presses the side part of the side reinforcement 20 by the fixing bolt 67 fastened to the male thread part 63 by protruding the male thread part 63 of the support member 62 into the insertion hole 66. It consists of 65.

그리고, 상기 보조 모서리 보강수단(70)은, 상기 각각의 측면보강재(20)의 요홈부(22)에 대칭 방향으로 삽입되어 측면보강재(20)로 삽입되는 고정핀(72)에 의해 고정되고, 걸림턱부(76)에 의하여 회전이 방지된 상태로 고정되는 보조지지체(74)와; 상기 대응된 각각의 보조지지체(70)에 삽입되는 고정나사축(77)과; 상기 고정나사축(34)에 각각 체결되어 각각의 보조지지체(32)를 서로 당겨주어 서로 다른 두 개의 거푸집(10)의 모서리부분을 고정 시켜주는 고정볼트(78)로 구성된다.And, the auxiliary edge reinforcing means 70 is fixed by a fixing pin 72 is inserted into the side reinforcing material 20 is inserted in the symmetrical direction to the groove portion 22 of each side reinforcing material 20, An auxiliary support 74 fixed in a state in which rotation is prevented by the locking jaw portion 76; A fixing screw shaft 77 inserted into the corresponding subsidiary support 70; Each of the fixing screw shaft 34 is fastened to each of the auxiliary support 32 is composed of a fixing bolt 78 for fixing the corners of the two different formwork (10).

이하, 본 발명의 작용을 상세하게 살펴보도록 한다.Hereinafter, the operation of the present invention will be described in detail.

먼저, 본 발명에 따른 거푸집장치의 사용 상태를 살펴 보게 되면, 도 2에 도시된 바와 같이, 사각기둥을 형성하기 위하여 두 개의 거푸집(10)을 서로 겹쳐서 모서리 부분에 모서리 지지대(50)를 위치 시키도록 한다.First, looking at the state of use of the formwork apparatus according to the present invention, as shown in Figure 2, to place the corner support 50 in the corner portion by overlapping the two formwork 10 to form a square pillar To do that.

그리고, 상기 두 개의 거푸집(10)에 위치를 맞춘 후에 모서리부분 내측면에 면귀부재(40)를 설치하여서 고정핀지지부(42)가 프레임부재(16)와 모서리지지대 (50) 사이에 위치하도록 한다.Then, after adjusting the position of the two formwork (10) by installing the face ear member 40 on the inner side of the corner portion so that the fixing pin support portion 42 is located between the frame member 16 and the corner support (50). .

이와 같은 상태에서 고정핀(19)을 모서리지지대(50)의 통공(52), 고정핀지지부(42)의 끼움공(44) 및 프레임부재(16)의 통공(18)으로 끼워서 고정시키도록 한다.In this state, the fixing pin 19 is inserted into the through hole 52 of the edge support 50, the fitting hole 44 of the fixing pin support 42, and the through hole 18 of the frame member 16 to be fixed. .

그런 후에 상기 거푸집(10)의 측면보강재(20)의 요홈부(22)에 모서리보강수단(30)인 지지체(32)를 삽입하고, 상부로부터 고정핀(38)을 삽입하여 관통공(38)으로 끼워서 서로 다른 두 개의 지지체(32)를 대응하도록 설치한다.Thereafter, the support 32, which is the edge reinforcing means 30, is inserted into the recess 22 of the side reinforcing material 20 of the formwork 10, and the fixing pin 38 is inserted from the upper portion of the through hole 38. It is installed so as to correspond to the two different support (32).

이와 같은 상태에서. 고정나사축(34)을 지지체(32)의 끼움공(37)을 통하여 삽입하여 끼운 후에 반대측 끝단 부분에서 삽입하여서 고정볼트(36)로 강한 힘을 가하여 체결하면, 지지체(30)가 당겨지면서 측면보강재(20)를 밀어주어서 서로 다른 두 개의 거푸집(10)을 견고하게 고정시켜 주게 된다.In such a state. When the fixing screw shaft 34 is inserted and inserted through the fitting hole 37 of the support 32 and then inserted from the opposite end portion and fastened by applying a strong force to the fixing bolt 36, the support 30 is pulled to the side By pushing the reinforcing material 20 is fixed to two different formwork (10) firmly.

그리고, 도 3에 도시된 바와 같이, 거푸집(10)의 공간부내에 콘크리트를 주입하여 타설하게 되면, 그 압력이 매우 크므로 상기 거푸집(10)의 연결부위(17)가 약간 볼록하게 외측으로 벌려지는 것을 방지할 필요성이 있다.And, as shown in Figure 3, when the concrete is poured into the space portion of the formwork 10, the pressure is very large, so that the connection portion 17 of the formwork 10 is slightly convex outwardly spread outwards. There is a need to prevent losing.

그러므로, 상기 측면보강재(20)의 요홈부(22) 내에 지지부재(64)를 삽입하여 측면보강재(20)의 끼움공(26)에 고정핀(38)을 삽입하여 지지부재(64)의 삽입공(64)으로 끼워서 위치를 고정시키도록 한다,Therefore, the support member 64 is inserted into the recess 22 of the side reinforcement 20 to insert the fixing pin 38 into the fitting hole 26 of the side reinforcement 20 to insert the support member 64. Insert into the ball 64 to fix the position,

그리고, 상기 지지부재(62)의 숫나사부(63)를 통하여 가압보강재(65)의 삽입장공(66)을 끼워서 고정시킨 후에 고정볼트(67)를 나사로 조여 주면, 가압보강재(65)가 당겨지면서 측면보강재(20)를 밀어주어서 거푸집(12)의 연결부위 (17)가 미세한 량이나마 밀려나오는 것을 방지하게 된다.Then, after fixing the insertion hole 66 of the pressure reinforcing material 65 through the male screw portion 63 of the support member 62 and tightening the fixing bolt 67 with a screw, the pressure reinforcing material 65 is pulled out. By pushing the side reinforcing material 20 to prevent the connection portion 17 of the formwork 12 is pushed out of the minute amount.

한편, 상기 보조모서리보강수단(70)이 설치되는 거푸집(10)의 모서리에는 측면보강재(20)의 요홈부(22)에 별도의 코너커넥터(24)를 삽입하여 위치를 보강하도록 한다.On the other hand, at the corners of the formwork 10 in which the auxiliary edge reinforcing means 70 is installed, a separate corner connector 24 is inserted into the recess 22 of the side reinforcement 20 to reinforce the position.

이와 같이, 상기 코너커넥터(24) 만으로 충분하게 거푸집(10)의 모서리부분을 보강하지 못하는 경우, 상기 보조 모서리 보강수단(70)중에서 보조지지체(74)를 코너커넥터(24)의 홈부에 삽입하여 위치를 잡은 후에 고정핀(72)을 측면보강재(20)와 지지체(32)에 삽입하여 각각의 보조지지체(74)의 위치를 고정하도록 한다.As such, when the corner connector 24 alone does not sufficiently reinforce the corner portion of the formwork 10, the auxiliary support 74 is inserted into the groove of the corner connector 24 in the auxiliary corner reinforcing means 70. After positioning, the fixing pin 72 is inserted into the side reinforcement 20 and the support 32 to fix the position of each auxiliary support 74.

그리고, 상기 고정나사축(77)을 보조지지체(74)에 삽입하여 끼운후에 양측 끝탄부에서 고정볼트(78)를 체결하여 보조지지체(74)를 당겨주어서 거푸집(10)의 모서리부분을 보조적으로 보강하도록 한다.Then, after the fixing screw shaft 77 is inserted into the auxiliary support 74, the fixing bolt 78 is fastened by fastening the fixing bolts 78 at both ends of the auxiliary support 74 to assist the edges of the formwork 10 in an auxiliary manner. Enhance.

따라서, 상기한 바와 같이, 본 발명에 따른 콘크리트의 거푸집장치를 사용하게 되면, 콘크리트 구조물을 형성하기 위하여 사용하는 거푸집을 "??" 자 형상으로 두 개를 서로 겹친 상태에서 모서리부분에 면귀부재를 대고서 고정핀으로 고정시키고, 거푸집에 수평으로 덧대진 측면보강부재에 모서리보강수단으로 체결하여 고정시킨 후, 측면가압수단 및 보조모서리 보강수단을 설치하여서 거푸집을 보강하므로 조립이 용이하고 콘크리트 구조물의 표면이 매끄럽게 형성하도록 하는 매우 유용하고 효과적인 발명이다.Therefore, as described above, when using the formwork of the concrete according to the invention, the formwork used to form the concrete structure "??" In the state where the two overlap each other, put the face ear member on the corner and fix it with the fixing pin, and fasten it by fastening the edge reinforcement means to the side reinforcement member horizontally padded on the formwork, and then press the side pressure means and the auxiliary edge. By reinforcing the formwork by installing the reinforcing means is a very useful and effective invention that is easy to assemble and form a smooth surface of the concrete structure.

Claims (4)

프레임부재(16)의 내측면에 콘크리트에 접촉되는 지지패널(12)을 형성하고, 수직으로 수직보강재(14)를 보강하여 콘크리트구조물(80)을 형성하는 거푸집(10) 장치에 있어서,In the formwork (10) apparatus for forming a concrete structure 80 by forming a support panel 12 in contact with the concrete on the inner surface of the frame member 16, and vertically reinforce the vertical reinforcement (14), 상기 거푸집(10)의 수직보강재(14)에 수평으로 고정되어 일정한 상,하간격으로 요홈부(22)를 갖도록 형성된 측면보강재(20)와;A side stiffener 20 fixed horizontally to the vertical stiffener 14 of the formwork 10 so as to have a recess 22 at a predetermined upper and lower intervals; 상기 각각의 거푸집(10)의 프레임부재(16)에 접촉되어서 90도 각도로 절곡되어 다수의 통공(18)이 형성된 모서리지지대(50)와;A corner support 50 which is contacted with the frame member 16 of each formwork 10 and bent at an angle of 90 degrees to form a plurality of through holes 18; 상기 두 개의 거푸집(10)의 모서리 부분에 일정 각도로 절곡된 고정핀지지부(42)가 돌출되어서 프레임부재(16)에 접촉되어지고, 모서리지지대(50)의 통공(52), 고정핀지지부(42)의 끼움공(44) 및 프레임부재(16)의 통공(18)으로 끼워진 고정핀(19)에 의하여 콘크리트구조물(80)의 모서리 부분을 경사지게 형상하는 면귀부재(40)와;Fixing pin support part 42 bent at an angle to the corner of the two formwork 10 is projected to contact the frame member 16, the through hole 52 of the corner support 50, the fixing pin support ( A faceting member 40 which inclined a corner portion of the concrete structure 80 by the fixing pin 19 fitted into the fitting hole 44 of the 42 and the through hole 18 of the frame member 16; 상기 각각의 거푸집(10)의 모서리 부분에 위치한 측면보강재(20)의 요홈부 (22)에 삽입되어서 거푸집(10)의 모서리 부분을 가압하여 고정하는 모서리보강수단 (30)과;A corner reinforcing means 30 inserted into the recess 22 of the side reinforcement 20 positioned at the corner portion of each formwork 10 to press and fix the corner portion of the formwork 10; 상기 각각의 거푸집(10)의 측면부분에 측면보강재(20)를 가압하여 거푸집(10)의 연결부위(17)를 가압하여 보강하는 측면보강부재(60)와;A side reinforcing member 60 for pressing the side reinforcing member 20 to the side portions of each formwork 10 to pressurize and reinforce the connecting portion 17 of the formwork 10; 상기 모서리보강수단(30)이 설치된 거푸집(10)의 다른 모서리부분에 보강을 위하여 측면보강재(20)의 요홈부(22)에 고정 설치되는 보조모서리보강수단(70)으로 구성된 것을 특징으로 하는 콘크리트구조물의 거푸집장치.Concrete, characterized in that consisting of the secondary edge reinforcing means 70 is fixed to the groove portion 22 of the side reinforcement 20 for reinforcement in the other corner portion of the formwork 10 is installed the corner reinforcement means (30) Formwork of structure. 제 1 항에 있어서, 상기 모서리보강수단(30)은, 상기 거푸집(10)으로 접촉되는 부위에서 각각의 측면보강재(20)의 요홈부(22)에 대칭 방향으로 삽입되어 측면보강재(20)의 삽입공(27)으로 삽입되어 관통공(38)으로 삽입된 고정핀(38)으로 고정되고, 수평으로 관통된 끼움공(37)을 형성하는 지지체(32)와; 상기 대응된 각각의 지지체(70)의 끼움공(37)에 삽입되는 고정나사축(34)과; 상기 고정나사축(34)에 각각 체결되어 각각의 지지체(32)를 서로 당겨주어서 서로 다른 두 개의 거푸집(10)의 모서리부분을 고정 시켜주는 고정볼트(36)로 구성된 것을 특징으로 하는 콘크리트 구조물의 거푸집장치.According to claim 1, wherein the edge reinforcing means 30 is inserted in the symmetrical direction of the groove portion 22 of each side reinforcing material 20 at the site of contact with the formwork 10 of the side reinforcing material 20 A support 32 inserted into the insertion hole 27 and fixed to the fixing pin 38 inserted into the through hole 38 to form a horizontally fitted fitting hole 37; A fixed screw shaft (34) inserted into the fitting hole (37) of the corresponding support body (70); The concrete structure, characterized in that consisting of a fixing bolt 36 is fastened to each of the fixing screw shaft 34 to pull each support 32 to fix the corners of the two different formwork (10) Formwork. 제 1 항에 있어서, 상기 측면보강수단(60)은, 거푸집(10) 연결부위(17)의 측면보강재(20)의 요홈부(22)에 삽입되어 측면보강재(20)의 끼움공(26)으로 끼워진 고정핀(38)에 의하여 고정되고 일측으로 숫나사부(63)가 형성된 지지부재(62)와; 상기 지지부재(62)의 숫나사부(63)가 삽입장공(66)으로 돌출되어서 숫나사부(63)에 체결된 고정볼트(67)에 의하여 측면보강재(20)의 측면부를 가압하여 고정하는 가압보강재(65)로 구성된 것을 특징으로 하는 콘크리트의 거푸집장치.According to claim 1, The side reinforcing means 60 is inserted into the recess 22 of the side reinforcing material 20 of the formwork 10, the connection portion 17, the fitting hole 26 of the side reinforcing material (20) A support member 62 which is fixed by a fixing pin 38 inserted into the male member 63 and has a male screw portion 63 formed at one side thereof; The pressurized stiffener which presses the side part of the side reinforcement 20 by the fixing bolt 67 fastened to the male thread part 63 by protruding the male thread part 63 of the support member 62 into the insertion hole 66. Formwork of concrete, characterized in that consisting of (65). 제 1항에 있어서, 상기 보조 모서리 보강수단(70)은, 상기 측면보강재(20)의 요홈부(22)에 대칭 방향으로 삽입되어 측면보강재(20)로 삽입되는 고정핀(72)에 의해 고정되고, 걸림턱부(76)에 의하여 회전이 방지된 상태로 고정되는 보조지지체 (74)와; 상기 대응된 각각의 보조지지체(70)에 삽입되는 고정나사축(77)과; 상기 고정나사축(34)에 각각 체결되어 각각의 보조지지체(32)를 서로 당겨주어 서로 다른 두 개의 거푸집(10)의 모서리부분을 고정 시켜주는 고정볼트(78)로 구성된 것을 특징으로 하는 콘크리트 구조물의 거푸집장치.According to claim 1, wherein the auxiliary edge reinforcing means 70 is fixed by the fixing pin 72 is inserted into the side reinforcing material 20 is inserted in the symmetrical direction to the groove portion 22 of the side reinforcing material (20). And, the auxiliary support member 74 is fixed in a state where the rotation is prevented by the locking jaw portion 76; A fixing screw shaft 77 inserted into the corresponding subsidiary support 70; Concrete structure, characterized in that consisting of a fixing bolt 78 is fastened to each of the fixing screw shaft 34 to pull each auxiliary support 32 to fix the corner portions of the two different formwork (10) Of formwork.
KR10-2000-0025131A 2000-05-10 2000-05-10 Form Work Device Of Concrete Structure KR100381681B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR10-2000-0025131A KR100381681B1 (en) 2000-05-10 2000-05-10 Form Work Device Of Concrete Structure
KR2020000014934U KR200200945Y1 (en) 2000-05-10 2000-05-26 Form work device of concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2000-0025131A KR100381681B1 (en) 2000-05-10 2000-05-10 Form Work Device Of Concrete Structure

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020000014934U Division KR200200945Y1 (en) 2000-05-10 2000-05-26 Form work device of concrete structure

Publications (2)

Publication Number Publication Date
KR20000053938A true KR20000053938A (en) 2000-09-05
KR100381681B1 KR100381681B1 (en) 2003-04-26

Family

ID=19668390

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2000-0025131A KR100381681B1 (en) 2000-05-10 2000-05-10 Form Work Device Of Concrete Structure

Country Status (1)

Country Link
KR (1) KR100381681B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030052872A (en) * 2001-12-21 2003-06-27 재단법인 포항산업과학연구원 Steel mold for bridge scaffolding and steel housing using the steel mold
CN113279568A (en) * 2021-06-24 2021-08-20 中建海峡建设发展有限公司 Novel light steel plastic spraying template and supporting structure and construction method thereof
CN113279563A (en) * 2021-03-25 2021-08-20 张娟 Integral type building aluminum mould board and welding equipment thereof

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100583772B1 (en) * 2003-06-24 2006-05-30 서보가설산업 주식회사 fixing structure of form for concrete
CN106193601B (en) * 2016-07-04 2019-03-22 浙江谊科建筑技术发展有限公司 A kind of recycling technique of aluminum alloy pattern plate
WO2018143534A1 (en) * 2017-01-31 2018-08-09 유대식 Mold assembly

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06272374A (en) * 1993-03-22 1994-09-27 Shimizu Corp Force-fit placing method of concrete
KR950014492U (en) * 1993-11-08 1995-06-16 Formwork for building concrete structures
JP2649322B2 (en) * 1994-02-02 1997-09-03 日本仮設株式会社 Opening and closing device for working form made of square concrete block
KR100249661B1 (en) * 1997-12-30 2000-03-15 정순착 Formwork system for wall corners
KR200251518Y1 (en) * 1998-12-30 2001-12-13 김종열 Formwork Fixture_

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030052872A (en) * 2001-12-21 2003-06-27 재단법인 포항산업과학연구원 Steel mold for bridge scaffolding and steel housing using the steel mold
CN113279563A (en) * 2021-03-25 2021-08-20 张娟 Integral type building aluminum mould board and welding equipment thereof
CN113279568A (en) * 2021-06-24 2021-08-20 中建海峡建设发展有限公司 Novel light steel plastic spraying template and supporting structure and construction method thereof

Also Published As

Publication number Publication date
KR100381681B1 (en) 2003-04-26

Similar Documents

Publication Publication Date Title
KR200200945Y1 (en) Form work device of concrete structure
KR100381681B1 (en) Form Work Device Of Concrete Structure
KR200403876Y1 (en) Quadrangle type Manhole mold
JP7515312B2 (en) Fixtures and wall construction
KR101070585B1 (en) Fixing device for grating panel
KR100662815B1 (en) A pillars form for as a vertical struc-tural body
KR100641887B1 (en) Joint Apparatus jointed at Slab Panel for mold that can join directly Slab Panel for mold with Wall Panel for mold AND Using Method thereof
KR20190129269A (en) Pannel Structure for Mold
CN212613719U (en) Keel connecting assembly for corner part and building template system
JPS6132014Y2 (en)
JPH04176927A (en) Body utilizing form plate and fixing assembly method
JP2542714Y2 (en) Fixing structure of double-floor support leg and double-floor support
JPH071445Y2 (en) Formwork Reinforcement Clamp
JP2560900B2 (en) Movable partition wall
JPH071455Y2 (en) Panel holder
JP2005351068A (en) Structure for reinforcing reentrant part of existing wooden building
KR200182866Y1 (en) A clamping apparatus for formwork assembling
JPS6112387Y2 (en)
JPH0618982Y2 (en) Concrete formwork assembly fittings
JPS5922177Y2 (en) Side flap fixing device
JP3307550B2 (en) Structure for attaching members to the base of a wooden building
JPH0625533Y2 (en) Entrance porch structure
JP3014646U (en) Panel connection device for metal foam formwork for construction
JP2552104Y2 (en) Floor structure of assembled houses
JPH0740012Y2 (en) Ceiling board joint structure

Legal Events

Date Code Title Description
A201 Request for examination
G15R Request for early opening
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130412

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20140414

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20160412

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20170410

Year of fee payment: 15

FPAY Annual fee payment

Payment date: 20180410

Year of fee payment: 16

FPAY Annual fee payment

Payment date: 20190603

Year of fee payment: 17

FPAY Annual fee payment

Payment date: 20200303

Year of fee payment: 18