KR102156971B1 - Gang form lifting device and outdoor wall construction method of building using the same - Google Patents

Gang form lifting device and outdoor wall construction method of building using the same Download PDF

Info

Publication number
KR102156971B1
KR102156971B1 KR1020180063716A KR20180063716A KR102156971B1 KR 102156971 B1 KR102156971 B1 KR 102156971B1 KR 1020180063716 A KR1020180063716 A KR 1020180063716A KR 20180063716 A KR20180063716 A KR 20180063716A KR 102156971 B1 KR102156971 B1 KR 102156971B1
Authority
KR
South Korea
Prior art keywords
gang form
building
wall
support structure
lifting device
Prior art date
Application number
KR1020180063716A
Other languages
Korean (ko)
Other versions
KR20190137485A (en
Inventor
김형근
Original Assignee
김형근
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김형근 filed Critical 김형근
Priority to KR1020180063716A priority Critical patent/KR102156971B1/en
Publication of KR20190137485A publication Critical patent/KR20190137485A/en
Application granted granted Critical
Publication of KR102156971B1 publication Critical patent/KR102156971B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/28Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

갱폼 인상장치가 개시된다. 상기 갱폼 인상장치는, 건물의 외벽을 시공하기 위해 건물 외벽에 설치되는 갱폼을 인상하기 위한 갱폼 인상장치에 있어서, 일측이 건물의 외벽에 지지되고, 타측 상부에 수직 배열되는 톱니가 형성된 지지구조체; 상기 지지구조체와 결합되는 상기 갱폼을 레일 결합하기 위해 갱폼 일측에 복수 개가 설치되는 갱폼 연결 가이드레일; 상기 갱폼의 일측에 설치되고, 상기 지지구조체 및 상기 갱폼을 상승 동작시키기 위한 톱니기어가 구비된 감속모터; 및 상기 감속모터의 구동을 제어하고, 갱폼 인상장치 동작 전반을 제어하는 제어부;를 포함할 수 있다.A gang form lifting device is disclosed. The gang form lifting device is a gang form lifting device for lifting a gang form installed on an outer wall of a building to construct an outer wall of a building, the support structure having one side supported on the outer wall of the building and vertically arranged on the other side; A gangform connection guide rail having a plurality of gangforms installed on one side of the gangform to rail-couple the gangforms coupled with the support structure; A reduction motor installed on one side of the gang form and provided with a toothed gear for lifting the support structure and the gang form; And a control unit for controlling the driving of the reduction motor and controlling the overall operation of the gang form lifting device.

Description

갱폼 인상장치 및 이를 이용한 건물의 외벽 시공방법{Gang form lifting device and outdoor wall construction method of building using the same}Gang form lifting device and outdoor wall construction method of building using the same}

본 발명은 갱폼 인상장치 및 이를 이용한 건물의 외벽 시공방법에 관한 것으로, 더욱 구체적으로 설명하면, 갱폼 설치단계, 갱폼 인상단계 및 건물의 외벽을 증설 시공을 위한 콘크리트 타설단계를 손쉽게 연속적으로 수행하여 건물의 외벽 시공시간을 단축시킬 수 있는 갱폼 인상장치 및 이를 이용한 건물의 외벽 시공방법에 관한 것이다.The present invention relates to a gang form lifting device and a method of constructing an outer wall of a building using the same, and more specifically, a gang form installation step, a gang form lifting step, and a concrete pouring step for expanding the outer wall of the building are easily and continuously performed to a building. It relates to a gang form lifting device that can shorten the construction time of the outer wall of a building and a method of constructing the outer wall of a building using the same.

일반적으로, 건물의 외벽은 갱폼과 같은 거푸집을 이용하여 시공되어 지는데, 상기 거푸집은 그 크기와 무게에 따라 건물의 외벽 전체를 덮을 수 없기 때문에 통상적으로 하나의 층마다 설치하여 외벽을 시공한 후, 상기 거푸집을 인상시켜 그 윗 층의 외벽을 시공하고 있다.In general, the outer wall of a building is constructed using a form such as gangfoam, but the formwork cannot cover the entire outer wall of the building depending on its size and weight, so it is usually installed for each floor to construct the outer wall, The above formwork is raised to construct the outer wall of the upper layer.

이때, 상기 거푸집의 인상하기 위해 종래에는 타워크레인을 이용하고 있다. 타워크레인은 주로 고층 건축에 사용하는 고양정의 기중기로 초고층 빌딩이나 아파트 건설현장에서 많이 사용된다. 인력을 사용할 경우 많은 인력과 시간이 소요됨에 따라 아파트 건물을 짓는데 필요한 외벽 거푸집 및 철근, 설비 및 전기 등각종자재 와 물자를 수직타워 상부 필요한 곳까지 손쉽게 운반할 수 있어 주로 타워크레인을 이용하고 있다.At this time, conventionally, a tower crane is used to raise the formwork. Tower cranes are mainly used in high-rise construction, and are widely used in high-rise buildings and apartment construction sites. In case of using manpower, it takes a lot of manpower and time, so it is possible to easily transport the exterior wall formwork and reinforcement, equipment and electricity, etc., necessary for building an apartment building to the upper part of the vertical tower, and therefore, a tower crane is mainly used.

하지만 이와 같은 타워크레인을 이용할 경우 타워크레인으로 인한 중대 재해가 많이 발생하는 등 타워크레인을 설치·해체·인상하는 작업과 관련된 사고가 전체의 약 절반 정도를 차지하고 있고, 또한, 크레인 사용에 따른 많은 비용이 발생하는 문제가 있어, 최근에는 건물을 시공하기 위한 갱폼 등의 거푸집을 인상하기 위해 타워크레인을 대체하는 갱폼 인상장치가 개발되고 있는 추세이다.However, when using such a tower crane, accidents related to the installation, dismantling, and raising of the tower crane account for about half of the total, such as a lot of serious disasters caused by the tower crane. There is a problem that occurs, and in recent years, there is a trend of developing a gang form lifting device that replaces a tower crane to raise a form such as a gang form for constructing a building.

이와 같이 타워크레인을 대체하는 거푸집 인상장치로는 종래에 "등록실용신안 20-0241872"을 통해 제안된 바 있다.As such, a formwork raising device that replaces the tower crane has been previously proposed through "Registered Utility Model 20-0241872".

도 1은 종래의 거푸집 인상 장치를 도시한 단면도이다.1 is a cross-sectional view showing a conventional formwork raising device.

종래의 거푸집 인상 장치(200)는 유압을 이용하는 것으로, 유압잭을 이용한 거푸집 인상 장치(200)는 유압잭 본체(201)와, 유압잭 본체(201)의 축중심에 삽입, 고정된 작업 로드(202)와, 유압잭 본체(201)의 상하부 작업 로드(202) 상에 각각 설치되며, 그 내부에 죠 클램프(204)(204') 및 죠 클램프(204)(204')를 지지하는 스프링(205)(205')을 각각 갖는 상,하부 죠 하우징(203)(203')을 기본적으로 구비하도록 구성된다.The conventional formwork lifting device 200 uses hydraulic pressure, and the formwork lifting device 200 using a hydraulic jack includes a hydraulic jack body 201, a work rod 202 inserted and fixed in the axial center of the hydraulic jack body 201 , Springs 205 and 205 which are respectively installed on the upper and lower work rods 202 of the hydraulic jack main body 201, and support the jaw clamps 204 and 204' and the jaw clamps 204 and 204' therein. It is configured to basically have upper and lower jaw housings 203 and 203' each having').

상기와 같은 종래의 거푸집 인상 장치(200)는 거푸집 인상 장치(200)를 설치하고 해체하는 작업이 복잡하고 작업시간이 많이 소요되는 문제가 있다. 즉, 전반적인 외벽 시공작업이 연속적으로 이루어지지 못하고, 상기 거푸집 인상 장치(200)를 설치하고, 거푸집을 인상하는 작업 및 콘크리트 타설작업이 별도로 이루어짐에 따라 작업시간이 많이 소요되고, 이에 따른 작업 비용도 많이 소요되는 문제가 있다.The conventional formwork lifting device 200 as described above has a problem in that the work of installing and dismantling the formwork lifting device 200 is complicated and takes a lot of work time. That is, the overall exterior wall construction work is not performed continuously, and as the formwork raising device 200 is installed, the work of raising the formwork and the concrete pouring work are performed separately, it takes a lot of work time, and thus the work cost is also There is a problem that takes a lot.

대한민국 등록실용신안 20-0241872Republic of Korea Utility Model Registration 20-0241872

본 발명의 목적은, 이러한 문제점을 해결하기 위한 것으로, 타워크레인을 이용하지 않고도 갱폼을 인상하는 작업을 수행할 수 있고, 갱폼 설치단계, 갱폼 인상단계 및 건물의 외벽을 증설 시공을 위한 콘크리트 타설단계를 손쉽게 연속적으로 수행하여 건물의 외벽 시공시간을 단축시킬 수 있고, 작업비용 절감 및 작업의 위험도를 낮출 수 있는 갱폼 인상장치 및 이를 이용한 건물의 외벽 시공방법을 제공하는데 있다.An object of the present invention is to solve this problem, and it is possible to perform a work of raising the gang form without using a tower crane, the gang form installation step, the gang form raising step, and the concrete pouring step for the extension construction of the outer wall of the building It is to provide a gang form lifting device that can reduce the construction time of the exterior wall of a building by easily and continuously perform the construction of the exterior wall of the building, reduce the work cost and lower the risk of work, and a method of constructing the exterior wall of a building using the same.

상기 과제를 달성하기 위한 본 발명의 기술적 사상의 일 실시예에 따른 갱폼 인상장치는, 건물의 외벽을 시공하기 위해 건물 외벽에 설치되는 갱폼을 인상하기 위한 갱폼 인상장치에 있어서, 일측이 건물의 외벽에 지지되고, 타측 상부에 수직 배열되는 톱니가 형성된 지지구조체; 상기 지지구조체와 결합되는 상기 갱폼을 레일 결합하기 위해 갱폼 일측에 복수 개가 설치되는 갱폼 연결 가이드레일; 상기 갱폼의 일측에 설치되고, 상기 지지구조체 및 상기 갱폼을 상승 동작시키기 위한 톱니기어가 구비된 감속모터; 및 상기 감속모터의 구동을 제어하고, 갱폼 인상장치 동작 전반을 제어하는 제어부;를 포함할 수 있다.In the gang form lifting device according to an embodiment of the technical idea of the present invention for achieving the above object, in the gang form lifting device for raising the gang form installed on the outer wall of the building to construct the outer wall of the building, one side is the outer wall of the building A support structure that is supported on and vertically arranged on the other side; A gangform connection guide rail having a plurality of gangforms installed on one side of the gangform to rail-couple the gangforms coupled with the support structure; A reduction motor installed on one side of the gang form and provided with a toothed gear for lifting the support structure and the gang form; And a control unit for controlling the driving of the reduction motor and controlling the overall operation of the gang form lifting device.

또한, 상기 갱폼 인상장치는, 상기 지지구조체를 건물의 외벽에 지지된 상태로 고정하기 위한 고정레버를 포함할 수 있다.In addition, the gang form lifting device may include a fixing lever for fixing the support structure in a state supported by the outer wall of the building.

또한, 상기 갱폼 연결 가이드레일은, 상기 갱폼에 설치되고, 돌출 형성된 레일; 및 상기 레일에 대응되도록 지지구조체에 설치되고, 상기 레일이 삽입될 수 있는 홈부가 마련되어 돌출된 레일 일부를 감싸 듯 레일에 슬라이딩 결합되는 레일 결합부;를 포함할 수 있다.In addition, the gang form connection guide rail, a rail installed on the gang form and formed protruding; And a rail coupling portion installed on the support structure to correspond to the rail, and provided with a groove portion into which the rail can be inserted, and slidably coupled to the rail as if surrounding a portion of the protruding rail.

또한, 상기 갱폼 인상장치는, 상기 갱폼이 시공중인 건물의 외벽에 밀착 고정되거나 이격되어 분리되도록 하기 위해 상기 갱폼의 일측에 설치되는 이격부를 포함할 수 있다.In addition, the gangfoam lifting device may include a spacer installed on one side of the gangfoam to allow the gangfoam to be closely fixed or separated from the outer wall of the building under construction.

또한, 상기 이격부는, 상기 갱폼이 건물의 외벽으로부터 이격되도록 반반력을 발생시키기 위한 이격스프링; 및 상기 갱폼을 건물의 외벽에 밀착 고정된 상태로 유지시키기 위한 이격레버;를 포함할 수 있다.In addition, the spacing part, a spacing spring for generating an anti-reaction force so that the gang form is separated from the outer wall of the building; And a separation lever for maintaining the gang form in a tightly fixed state on the outer wall of the building.

또한, 상기 감속모터는, 상기 제어부의 제어에 의해 정방향 또는 역방향으로 구동될 수 있다.In addition, the reduction motor may be driven in a forward or reverse direction under the control of the controller.

또한, 상기 갱폼 인상장치는, 상기 갱폼의 레벨 및 수평을 측정하기 위한 레벨기 및 수평기를 포함할 수 있다.In addition, the gangfoam lifting device may include a leveler and a leveler for measuring the level and horizontality of the gangform.

또한, 상기 제어부는, 상기 감속모터 등 전기적인 장치를 제어하여 상기 지지구조체 및 상기 갱폼의 동작을 제어하고, 원격으로도 제어할 수 있다.In addition, the controller may control an electric device such as the reduction motor to control the operation of the support structure and the gang form, and remotely control the support structure.

상기 과제를 달성하기 위한 본 발명의 기술적 사상의 일 실시예에 따른 인상장치를 이용한 건물의 외벽 시공방법은, 상기 제1항 내지 제8항의 갱폼 인상장치 및 건물의 외벽을 시공하기 위한 갱폼을 설치하기 위한 설치단계(S10); 상기 갱폼 인상장치를 이용하여 상기 갱폼을 인상하는 인상단계(S20); 상기 인상단계 이후 건물 외벽을 추가로 증설 시공하기 위해 콘크리트를 타설하는 타설단계(S30); 및 상기 설치단계(S10), 상기 인상단계(S20) 및 상기 타설단계(S30)를 순차적으로 반복하는 반복단계(S40);를 포함할 수 있다.A method of constructing an outer wall of a building using an impression device according to an embodiment of the inventive concept for achieving the above object, is to install the gang form lifting device of paragraphs 1 to 8 and the gang form for constructing the outer wall of the building. The installation step (S10) for; A lifting step (S20) of raising the gang form using the gang form lifting device; A pouring step (S30) of pouring concrete to further expand the exterior wall of the building after the raising step; And a repeating step (S40) of sequentially repeating the installation step (S10), the raising step (S20), and the pouring step (S30).

또한, 상기 설치단계(S10)는, 상기 지지구조체를 건물의 외벽에 고정하기 위한 고정레버를 설치하기 위한 고정레버 설치단계(S11)를 더 포함할 수 있다.In addition, the installation step (S10) may further include a fixing lever installation step (S11) for installing a fixing lever for fixing the support structure to the outer wall of the building.

또한, 상기 설치단계(S10)는, 상기 갱폼이 시공중인 건물의 외벽에 밀착 고정되거나 이격되어 분리되도록 하기 위해 상기 갱폼의 일측에 설치되는 이격부를 설치하기 위한 이격부 설치단계(S12)를 더 포함할 수 있다.In addition, the installation step (S10) further includes a spacer installation step (S12) for installing a spacer installed on one side of the gangform so that the gangform is closely fixed or spaced apart from the outer wall of the building under construction. can do.

또한, 상기 설치단계(S10)는, 상기 갱폼에 레벨기 및 수평기를 설치하고, 갱폼의 설치된 상태의 레벨 및 수평을 측정하는 레벨기 및 수평기 설치단계(S13)를 더 포함할 수 있다.In addition, the installation step (S10) may further include a leveler and a leveler installation step (S13) of installing a leveler and a leveler on the gangform, and measuring the level and level of the installed state of the gangform.

또한, 상기 인상단계(S20)는, 감속모터를 정방향으로 구동하여 갱폼을 인상하는 갱폼 인상단계(S21); 및 상기 감속모터를 역방향으로 구동하여 지지구조체를 인상하는 지지구조체 인상단계(S22);를 포함할 수 있다.In addition, the raising step (S20), a gang form lifting step (S21) of lifting the gang form by driving the reduction motor in the forward direction; And a support structure lifting step (S22) of lifting the support structure by driving the reduction motor in a reverse direction.

또한, 상기 타설단계(S30)는, 추가적으로 건물의 외벽을 증설 시공을 위한 거푸집을 설치하는 거푸집 설치단계(S31); 및 상기 설치된 거푸집에 콘크리트를 타설하는 콘크리트 타설단계(S32);를 포함할 수 있다.In addition, the pouring step (S30), a formwork installation step (S31) of installing a formwork for additionally expanding the exterior wall of the building; And a concrete pouring step (S32) of pouring concrete into the installed formwork.

본 발명에 따른 갱폼 인상장치는, 용이하게 갱폼을 설치하고 갱폼을 인상하는 작업이 전기적인 제어에 의해 연속적으로 이루어질 수 있어, 타워크레인을 이용하지 않고도 안전하고 신속하게 갱폼을 인상하는 작업을 수행할 수 있는 효과가 있다. 또한, 상기 갱폼 인상장치를 이용한 건물의 외벽 시공방법은, 타워크레인을 이용하지 않고 갱폼을 설치하는 과정부터 갱폼을 인상하는 과정 및 건물의 외벽을 증설 시공을 위한 콘크리트 타설단계를 손쉽게 연속적으로 수행할 수 있어 건물의 외벽 시공시간을 단축시킬 수 있고, 작업비용 절감 및 작업의 위험도를 낮출 수 있는 효과가 있다.In the gang form lifting device according to the present invention, since the work of easily installing the gang form and lifting the gang form can be continuously performed by electric control, it is possible to safely and quickly perform the work of lifting the gang form without using a tower crane. It can have an effect. In addition, in the method of constructing the outer wall of a building using the gang form lifting device, from the process of installing the gang form without using a tower crane, the process of raising the gang form and the step of placing concrete for extension construction of the building's outer wall can be easily and continuously performed. It is possible to shorten the construction time of the exterior wall of the building, reduce the work cost and lower the risk of work.

도 1은 종래의 거푸집 인상 장치를 도시한 단면도.
도 2는 건물의 외벽에 본 발명의 일 실시예에 따른 갱폼 인상장치가 설치된 모습을 나타낸 도면.
도 3은 본 발명의 일 실시예에 따른 갱폼 인상장치를 이용한 건물의 외벽 시공방법을 나타낸 흐름도.
도 4는 본 발명의 일 실시예에 따른 갱폼 인상장치가 설치되기 전 건물의 외벽을 나타낸 도면.
도 5는 건물의 외벽에 본 발명의 일 실시예에 따른 갱폼 인상장치가 설치되는 과정에 있어 고정레버가 설치되기 전 모습을 나타낸 도면.
도 6은 도 5의 갱폼 인상장치가 설치된 상태에서 고정레버가 설치된 모습을 나타낸 도면.
도 7은 도 6의 상태에서 갱폼이 상승된 상태를 나타낸 도면.
도 8은 도 7의 상태에서 거푸집이 상부로 이동한 모습을 나타낸 도면.
도 9는 도 8의 상태에서 거푸집과 갱폼 사이에 매립앙카가 설치된 모습을 나타낸 도면.
도 10은 도 9의 상태에서 지지구조체로부터 고정레버가 제거된 상태의 도면.
도 11은 도 10의 상태에서 지지구조체가 상승한 상태를 나타낸 도면.
1 is a cross-sectional view showing a conventional formwork raising device.
Figure 2 is a view showing a state in which the gang form raising device according to an embodiment of the present invention is installed on an outer wall of a building.
3 is a flow chart showing a method of constructing an exterior wall of a building using a gang form impression device according to an embodiment of the present invention.
Figure 4 is a view showing the outer wall of the building before the gang form lifting device according to an embodiment of the present invention is installed.
5 is a view showing a state before the fixing lever is installed in the process of installing the gangform raising device according to an embodiment of the present invention on an outer wall of a building.
6 is a view showing a state in which the fixing lever is installed in the state where the gang form lifting device of FIG. 5 is installed.
7 is a view showing a state in which the gang form is raised in the state of FIG. 6.
Figure 8 is a view showing a state in which the formwork has moved upward in the state of Figure 7;
9 is a view showing a state where a buried anchor is installed between a formwork and a gang form in the state of FIG. 8;
10 is a view showing a state in which the fixing lever is removed from the support structure in the state of FIG. 9;
11 is a view showing a state in which the support structure is raised in the state of FIG. 10;

본 발명과 본 발명의 동작상의 이점 및 본 발명의 실시에 의하여 달성되는 목적을 충분히 이해하기 위해서는 본 발명의 바람직한 실시예를 예시하는 첨부 도면 및 도면에 기재된 내용을 참조하여야 한다.In order to fully understand the present invention, the operational advantages of the present invention, and the objects achieved by the implementation of the present invention, reference should be made to the accompanying drawings illustrating preferred embodiments of the present invention and the contents described in the drawings.

이하, 첨부한 도면을 참조하여 본 발명의 바람직한 실시예를 설명함으로써, 본 발명을 상세히 설명한다. 각 도면에 제시된 동일한 참조부호는 동일한 부재를 나타낸다.Hereinafter, the present invention will be described in detail by describing a preferred embodiment of the present invention with reference to the accompanying drawings. The same reference numerals in each drawing indicate the same member.

본 발명의 기술적 사상의 일 실시예에 따른 갱폼 인상장치는, 종래의 타워크레인을 이용하지 않고도 갱폼을 인상하는 작업을 수행할 수 있는 것으로, 설치가 간편하고 전기적인 제어에 의해 자동으로 갱폼을 상승시킬 수 있도록 한 것이다.The gang form lifting device according to an embodiment of the technical idea of the present invention is capable of performing the work of lifting the gang form without using a conventional tower crane, and is easy to install and automatically increases the gang form by electrical control. I made it possible to do it.

갱폼(10)은 대형화된 외부벽체용 거푸집으로서, 주로 고층 아파트와 같이 평면상 상ㆍ하부가 동일한 단면 구조물에서 외부 벽체 거푸집과 작업용 발판(11)을 일체로 하여 제작한 대형 거푸집을 말하는 것으로, 본 발명은 건물의 외벽(1)을 시공하는 과정에서 상기 갱폼(10)을 상부로 인상시키기 위한 갱폼 인상장치(100)에 관한 것이다.Gangform (10) is a large-sized external wall formwork, mainly refers to a large formwork manufactured by integrating the exterior wall formwork and the working scaffolding (11) in a cross-sectional structure with the same upper and lower part on the plane like a high-rise apartment. The invention relates to a gang form lifting device 100 for lifting the gang form 10 upward in the process of constructing the outer wall 1 of a building.

도 2는 건물의 외벽에 본 발명의 일 실시예에 따른 갱폼 인상장치가 설치된 모습을 나타낸 도면이다.2 is a view showing a state in which a gang form raising device according to an embodiment of the present invention is installed on an outer wall of a building.

도 2를 참조하면, 갱폼 인상장치(100)은 크게 지지구조체(110), 갱폼 연결 가이드레일(120), 감속모터(130) 및 제어부(140)를 포함할 수 있다.Referring to FIG. 2, the gang form lifting device 100 may largely include a support structure 110, a gang form connection guide rail 120, a reduction motor 130, and a control unit 140.

상기 지지구조체(110)는 용이하게 구조를 변경할 수 있고 조립이 가능하며, 지형물에 밀착 설치할 수 있도록 한 앵글 형태의 구조물로서, 일측이 건물의 외벽(1)에 지지될 수 있다. 즉, 지지구조체(110)는 외벽(1)에 지지되는 부분인 외벽 고정부(111)와 갱폼(10)과 연결되는 갱폼 연결부(112)를 포함할 수 있으며, 상기 갱폼 연결부(112)는 외벽 고정부(111)의 끝단의 높이보다 더 높이 연장되도록 형성될 수 있다.The support structure 110 is an angle-shaped structure that can be easily changed and assembled, and can be installed in close contact with the terrain, and one side may be supported on the outer wall 1 of the building. That is, the support structure 110 may include an outer wall fixing part 111 which is a part supported by the outer wall 1 and a gang form connection part 112 connected to the gang form 10, and the gang form connection part 112 is an outer wall It may be formed to extend higher than the height of the end of the fixing portion 111.

또한, 지지구조체(110)에 있어 갱폼(10)과 연결되는 부분에는 상부에 수직 배열되는 톱니가 형성된 톱니 레일(113)이 형성될 수 있다. 상기 톱니 레일(113)은 상기 외벽 고정부(111) 반대 측 부분의 갱폼 연결부(112) 구조물 상부에 형성되며, 외벽 고정부(111) 상부 끝단과 비슷한 높이에서부터 상부 일부분에 형성될 수 있다.In addition, in the support structure 110, a toothed rail 113 may be formed at a portion connected to the gang form 10 with teeth vertically arranged thereon. The toothed rail 113 is formed on the upper part of the gangform connection part 112 structure opposite the outer wall fixing part 111, and may be formed on the upper part from a height similar to the upper end of the outer wall fixing part 111.

이러한 지지구조체(110)는 일측이 외벽(1)에 지지되고, 타측이 갱폼(1)과 연결되도록 구성되며, 외벽 고정부(111)와 갱폼 연결부(112) 사이는 가로상으로 배치되는 구조물에 의해 외벽 고정부(111)와 갱폼 연결부(112)는 소정의 간격을 가지고 이격되도록 구성될 수 있으며, 상기 외벽 고정부(111)와 갱폼 연결부(112)는 수직방향으로 연장되도록 구성될 수 있다. 예를 들어, 지지구조체(110)를 도면에 도시된 바와 같이, 측면에서 봤을 때에는 사다리 구조의 형태로 구성될 수 있다.This support structure 110 is configured such that one side is supported by the outer wall 1 and the other side is connected to the gang form 1, and the outer wall fixing part 111 and the gang form connection part 112 are arranged in a horizontal direction. Accordingly, the outer wall fixing part 111 and the gang form connection part 112 may be configured to be spaced apart at a predetermined interval, and the outer wall fixing part 111 and the gang form connection part 112 may be configured to extend in a vertical direction. For example, as shown in the drawing, the support structure 110 may be configured in the form of a ladder structure when viewed from the side.

한편, 도면에 도시된 구조 및 형태로 한정하는 것은 아니고, 구조물의 형태에 대해서는 특정하지 않으며, 일측이 외벽(1)에 지지할 수 있고, 갱폼(10)과 연결되는 구조라면 변형된 형상이라도 포함될 수 있음은 물론이다.On the other hand, it is not limited to the structure and shape shown in the drawings, and the shape of the structure is not specified, and if one side can be supported on the outer wall 1 and connected to the gang form 10, even a modified shape may be included. Of course you can.

또한, 상기 갱폼 인상장치(100)는, 상기 지지구조체(110)를 건물의 외벽(1)에 지지된 상태로 고정하기 위한 고정레버(150)를 포함할 수 있다.In addition, the gang form lifting device 100 may include a fixing lever 150 for fixing the support structure 110 in a state supported by the outer wall 1 of the building.

상기 고정레버(150)는, 상기 지지구조체(110)를 외벽(1), 특히, 외벽(1)의 창틀이 설치되는 개방된 공간에 설치되어 지지구조체(110)를 외벽(1)에 지지 고정시키기 위한 것이다. 즉, 고정레버(150)를 외벽(1)의 창틀이 설치되는 개방된 공간의 테두리 부분에 걸림되도록 설치함으로써 지지구조체(110)가 외벽(1)에 지지 고정될 수 있게 된다. 따라서, 지지구조체(110)를 쉽게 고정하고 분리할 수 있도록 원터치 레버 동작에 의해 걸림되거나 분리될 수 있는 구조로 구성될 수 있다.The fixing lever 150 is installed in an open space where the support structure 110 is installed on the outer wall 1, in particular, the window frame of the outer wall 1 to support and fix the support structure 110 to the outer wall 1 It is to let. That is, the support structure 110 can be supported and fixed to the outer wall 1 by installing the fixing lever 150 so as to be engaged with the edge of the open space where the window frame of the outer wall 1 is installed. Therefore, the support structure 110 may be configured in a structure that can be locked or separated by a one-touch lever operation so that the support structure 110 can be easily fixed and separated.

다음으로, 상기 갱폼 연결 가이드레일(120)은, 갱폼(10)에 설치되는 레일(121)과 상기 지지구조체(110)에 설치되고 상기 레일(121)과 결합되는 레일 결합부(122)로 구성될 수 있다.Next, the gang form connection guide rail 120 is composed of a rail 121 installed on the gang form 10 and a rail coupling portion 122 installed on the support structure 110 and coupled to the rail 121 Can be.

갱폼 연결 가이드레일(120)은 지지구조체(110)와 갱폼(10)을 연결하되, 상호간 수직 방향으로 슬라이딩 동작이 이루어질 수 있도록 구성되는 것으로, 상기 레일(121)은 갱폼(10)의 일측에 설치되고, 돌출 형성될 수 있다. 또한, 상기 레일 결합부(122)는 레일(121)이 삽입될 수 있도록 레일(121)의 돌출된 형상과 대응되도록 홈부가 마련될 수 있다. 즉, 레일 결합부(122)는 돌출된 레일(121) 일부를 감싸 듯 레일 결합부(122)의 홈부에 레일(121)이 결합되는 구조로서 상호간 슬라이딩 결합될 수 있다. 이때, 레일 결합부(122)의 양 끝단은 안쪽으로 폭이 좁혀지도록 모아진 형태로 구성됨으로써, 레일 결합부(122)로부터 레일(121)이 쉽게 분리 이탈되지 못하도록 할 수 있다. 또한, 갱폼 연결 가이드레일(120)은 경우에 따라 복수 개가 설치될 수도 있다.The gang form connection guide rail 120 connects the support structure 110 and the gang form 10, but is configured to allow sliding motion in a vertical direction, and the rail 121 is installed on one side of the gang form 10 And can be formed to protrude. In addition, the rail coupling portion 122 may be provided with a groove to correspond to the protruding shape of the rail 121 so that the rail 121 can be inserted. That is, the rail coupling portion 122 has a structure in which the rail 121 is coupled to the groove portion of the rail coupling portion 122 as if surrounding a portion of the protruding rail 121 and may be slidably coupled to each other. At this time, both ends of the rail coupling portion 122 are configured in a gathered shape so as to narrow the width inward, so that the rail 121 cannot be easily separated and separated from the rail coupling portion 122. In addition, a plurality of gangform connection guide rails 120 may be installed in some cases.

다음으로, 상기 감속모터(130)는, 지지구조체(110) 및 갱폼(10)을 상승 동작 시키기 위한 것으로, 모터(131) 및 모터(131)의 회전축과 연결되도록 구성되는 톱니기어(132)를 포함할 수 있다.Next, the reduction motor 130 is for lifting the support structure 110 and the gang form 10, and a toothed gear 132 configured to be connected to the rotation shaft of the motor 131 and the motor 131 Can include.

감속모터(130)는 갱폼(10)의 일측에 설치되고, 베벨기어 등과 같이 직각 방향으로 방향을 전환시킬 수 있는 구조로 이루어질 수 있고, 경우에 따라 모터(131)의 회전속도를 제어하기 위해 감속기(미도시)를 포함할 수 있다. 그리고, 상기 톱니기어(132)는 상기 지지구조체(110)의 톱니레일(113)과 맞물림 되면서 모터(121)의 회전 동작에 의해 갱폼(10) 또는 지지구조체(110)를 상승시킬 수 있게 된다.The reduction motor 130 is installed on one side of the gang form 10, and may be formed in a structure capable of changing the direction in a right angle direction, such as a bevel gear, and in some cases, a speed reducer to control the rotational speed of the motor 131 (Not shown) may be included. In addition, the toothed gear 132 is engaged with the toothed rail 113 of the support structure 110, and the gangform 10 or the support structure 110 can be raised by the rotational operation of the motor 121.

또한, 감속모터(130)는 후술하는 제어부(140)의 제어에 의해 정방향 또는 역방향으로 구동될 수 있다. 예를 들어, 감속모터(130)를 정방향으로 회전시키면 갱폼(10)이 상승동작이 이루어지고, 감속모터(130)를 역방향을 회전시키면 지지구조체(110)가 상승동작이 이루어질 수 있다. 이에 대해 모터(131)의 정방향 및 역방향은 특정 동작에 대해 특정하지 않으며, 설정에 따라 변경될 수 있다.In addition, the reduction motor 130 may be driven in a forward direction or a reverse direction under the control of the controller 140 to be described later. For example, when the reduction motor 130 is rotated in the forward direction, the gangfoam 10 may rise, and when the reduction motor 130 is rotated in the reverse direction, the support structure 110 may rise. In contrast, the forward and reverse directions of the motor 131 are not specified for a specific operation and may be changed according to settings.

감속모터(130)의 회전에 의해 갱폼(10) 및 지지구조체(110)의 상승하는 동작에 대해서는 후술하는 갱폼 인상장치를 이용한 건물의 외벽 시공방법을 설명하면서 구체적으로 설명한다.The ascending operation of the gang form 10 and the support structure 110 by rotation of the reduction motor 130 will be described in detail while explaining a method of constructing an outer wall of a building using a gang form lifting device to be described later.

다음으로, 상기 제어부(140)는, 전반적인 전기적인 장치의 구동을 제어하고, 특히, 상기 감속모터(130)의 동작을 제어하며, 갱폼 인상장치(100)의 동작 전반을 제어하는 부분이다.Next, the control unit 140 controls the overall driving of the electrical device, in particular, controls the operation of the reduction motor 130, and controls the overall operation of the gangform lifting device 100.

또한, 제어부(140)는 후술하는 레벨기(170) 및 수평기(180)를 제어하고 측정된 데이터를 관리하며, 동작의 오류 등을 체크할 수 있으며, 원격으로 갱폼 인상장치(100)를 제어할 수 있다.In addition, the controller 140 controls the leveler 170 and the leveler 180 to be described later, manages the measured data, checks for errors in operation, etc., and remotely controls the gangform raising device 100. I can.

한편, 상기 갱폼 인상장치(100)는, 도 2에 도시된 바와 같이, 상기 갱폼(10)이 시공중인 건물의 외벽(1)에 밀착 고정되거나 이격되어 분리되도록 하기 위해 상기 갱폼(10)의 일측에 설치되는 이격부(160)를 포함할 수 있다.On the other hand, the gang form lifting device 100, as shown in Figure 2, one side of the gang form 10 in order to ensure that the gang form 10 is in close contact with or separated from the outer wall 1 of the building under construction. It may include a spacer 160 installed on.

도 2를 참조하면, 상기 이격부(160)는, 갱폼(10)이 건물의 외벽(1)으로부터 이격되도록 반반력을 발생시키기 위한 이격스프링(161) 및 상기 갱폼(10)을 건물의 외벽(1)에 밀착 고정된 상태로 유지시키기 위한 이격레버(162)를 포함할 수 있다.Referring to FIG. 2, the spacing part 160 includes a spacing spring 161 and the gang form 10 for generating an anti-reaction force so that the gang form 10 is separated from the outer wall 1 of the building. It may include a separation lever 162 for maintaining in a tightly fixed state to 1).

즉, 갱폼(10)에 있어 외벽(1)측 방향은 2중 구조의 구조물로 구성되고 일측의 구조물에는 이격스프링(161) 및 이격레버(162)가 설치되고 타측의 구조물은 상기 이격레버(162)에 의해 걸림될 수 있는 구조로 구성되는데, 이때, 타측 구조물이 일측 구조물과 유격이 좁혀지면서 이격스프링(161)이 압축된 상태로 이격레버(162)에 의해 갱폼(10)이 건물의 외벽(1)에 밀착 고정될 수 있게 된다.That is, in the gang form 10, the outer wall (1) side direction is composed of a structure of a double structure, a separation spring 161 and a separation lever 162 are installed in the structure on one side, and the separation lever 162 is installed on the structure on the other side. ), and the gap between the other structure and the structure on the other side is narrowed and the separation spring 161 is compressed, and the gangform 10 is formed by the separation lever 162 on the outer wall of the building ( 1) can be tightly fixed.

한편, 상기 갱폼 인상장치(100)는, 상기 갱폼(10)의 레벨 및 수평을 측정하기 위한 레벨기(170) 및 수평기(180)를 포함할 수 있다.On the other hand, the gangform raising device 100 may include a leveler 170 and a leveler 180 for measuring the level and horizontality of the gangform 10.

상기 레벨기(170) 및 수평기(180)는 건물의 외벽을 시공하는 과정에서 갱폼(10)을 설치할 때 레벨 및 수평을 측정하고 측정된 레벨 및 수평 데이터는 상기 제어부(140)와 통신하여 설치된 갱폼(10)의 정확한 설치상태를 파악하고 조절하기 위한 것이다.The leveler 170 and the leveler 180 measure the level and level when installing the gangfoam 10 in the process of constructing the outer wall of the building, and the measured level and horizontal data are gangform installed in communication with the control unit 140. It is to check and adjust the exact installation condition of (10).

이하에서는 상기 설명한 갱폼 인상장치(100)를 이용한 건물의 외벽 시공방법에 대하여 구체적으로 설명한다.Hereinafter, a method of constructing an outer wall of a building using the above-described gang form raising device 100 will be described in detail.

도 3은 본 발명의 일 실시예에 따른 갱폼 인상장치를 이용한 건물의 외벽 시공방법을 나타낸 흐름도이다.3 is a flow chart showing a method of constructing an exterior wall of a building using a gang form impression device according to an embodiment of the present invention.

도 3을 참조하면, 상기 인상장치(100)를 이용한 건물의 외벽 시공방법은, 크게 설치단계(S10), 갱폼인상단계(S20), 타설단계(S30), 지지구조체 인상단계(S40) 및 반복단계(S50)를 포함할 수 있다.3, the method of constructing an outer wall of a building using the lifting device 100 is largely an installation step (S10), a gang form lifting step (S20), a pouring step (S30), a support structure lifting step (S40) and repetition. It may include a step (S50).

상기 설치단계(S10)는 갱폼 인상장치(100) 및 건물의 외벽(1)을 시공하기 위한 갱폼(10)을 설치하기 위한 단계이고, 상기 갱폼인상단계(S20)는 갱폼 인상장치(100)를 이용하여 갱폼(10)를 상부로 인상하는 단계이며, 상기 타설단계(S30)는 상기 갱폼인상단계(S20) 이후 건물 외벽(1)을 추가로 증설 시공하기 위해 콘크리트를 타설하는 단계이고, 상기 지지구조체 인상단계(S40)는 갱폼 인상장치(100)를 이용하여 지지구조체(110)를 상부로 인상하는 단계이며, 상기 반복단계(S50)는 건물의 외벽 시공이 완료될 때까지 건물 외벽(1)을 추가로 증설하기 위해 상기 설치단계(S10), 상기 갱폼인상단계(S20), 상기 타설단계(S30) 및 상기 지지구조체 인상단계(S40)를 순차적으로 반복하는 단계이다.The installation step (S10) is a step for installing the gang form lifting device 100 and the gang form 10 for constructing the outer wall 1 of the building, and the gang form lifting step (S20) is the gang form lifting device 100 It is a step of raising the gang form 10 to the top by using, and the pouring step (S30) is a step of pouring concrete to additionally expand the building outer wall 1 after the gang form lifting step (S20), and the support The structure raising step (S40) is a step of raising the support structure 110 to the top using the gangfoam lifting device 100, and the repeating step (S50) is the outer wall of the building (1) until the construction of the outer wall of the building is completed. The installation step (S10), the gang form raising step (S20), the pouring step (S30), and the support structure raising step (S40) are sequentially repeated in order to further expand.

이하에서는 상기 설명한 갱폼 인상장치(100)를 이용하여 건물의 외벽 시공하는 과정에 있어, 상기 설치단계(S10), 상기 갱폼인상단계(S20), 상기 타설단계(S30), 상기 지지구조체인상단계(S40) 및 상기 반복단계(S50)가 이루어지는 건물의 외벽 시공방법에 대하여 구체적으로 설명한다.Hereinafter, in the process of constructing the outer wall of a building using the gang form lifting device 100 described above, the installation step (S10), the gang form lifting step (S20), the pouring step (S30), the supporting structure chain lifting step ( It will be described in detail with respect to the outer wall construction method of the building in which S40) and the repeating step (S50) are performed.

도 4는 본 발명의 일 실시예에 따른 갱폼 인상장치가 설치되기 전 건물의 외벽을 나타낸 도면이고, 도 5는 건물의 외벽에 본 발명의 일 실시예에 따른 갱폼 인상장치가 설치되는 과정에 있어 고정레버가 설치되기 전 모습을 나타낸 도면이며, 도 6은 도 5의 갱폼 인상장치가 설치된 상태에서 고정레버가 설치된 모습을 나타낸 도면이고, 도 7은 도 6의 상태에서 갱폼이 상승된 상태를 나타낸 도면이며, 도 8은 도 7의 상태에서 거푸집이 상부로 이동한 모습을 나타낸 도면이고, 도 9는 도 8의 상태에서 거푸집과 갱폼 사이에 매립앙카가 설치된 모습을 나타낸 도면이며, 도 10은 도 9의 상태에서 지지구조체로부터 고정레버가 제거된 상태의 도면이고, 도 11은 도 10의 상태에서 지지구조체가 상승한 상태를 나타낸 도면이다.4 is a view showing the exterior wall of a building before the gang form lifting device according to an embodiment of the present invention is installed, and FIG. 5 is a process in which the gang form lifting device according to an embodiment of the present invention is installed on the exterior wall of the building. It is a view showing the state before the fixing lever is installed, FIG. 6 is a view showing the state in which the fixing lever is installed in the state in which the gang form lifting device of FIG. 5 is installed, and FIG. 7 is a view showing the state in which the gang form is raised in the state of FIG. FIG. 8 is a view showing a state that the formwork has moved upward in the state of FIG. 7, FIG. 9 is a view illustrating a state where a buried anchor is installed between the formwork and the gang form in the state of FIG. 8, and FIG. 10 is In the state of 9, the fixing lever is removed from the support structure, and FIG. 11 is a view showing a state in which the support structure is raised in the state of FIG.

상기 도 4 내지 도 6을 참조하면, 상기 설치단계(S10)는 기본적으로, 건물의 외벽 시공작업을 하는데 있어, 상기 지지구조체(110), 갱폼 연결 가이드레일(120), 감속모터(130), 제어부(140) 등을 포함하는 갱폼 인상장치(100)를 설치하고, 상기 갱폼 인상장치(100)와 연동하여 동작하는 갱폼(10)을 설치하는 기초 단계이다.4 to 6, the installation step (S10) is basically, in the construction of the exterior wall of the building, the support structure 110, the gang form connection guide rail 120, the reduction motor 130, This is a basic step of installing the gang form lifting device 100 including the control unit 140 and the like, and installing the gang form 10 operating in conjunction with the gang form lifting device 100.

이 과정에서, 설치단계(S10)는 지지구조체(110)를 외벽(1)에 고정하기 위한 고정레버 설치단계(S11), 외벽(1)에 갱폼(10)을 이격되도록 고정하는 이격부 설치단계(S12), 레벨기(170) 및 수평기(180)를 설치하는 레벨기 및 수평기 설치단계(S13)를 포함할 수 있다.In this process, the installation step (S10) includes a fixing lever installation step (S11) for fixing the support structure 110 to the outer wall 1, and a spacer installation step of fixing the gang form 10 to the outer wall 1 so as to be spaced apart. (S12), it may include a leveler and leveler installation step (S13) of installing the leveler 170 and the leveler 180.

상기 고정레버 설치단계(S11)는, 도 6에 도시된 바와 같이, 지지구조체(110)의 외벽 고정부(111)를 외벽(1)의 창틀 설치공간에 고정시키기 위해 고정레버(150)를 설치하는 과정으로, 상기 고정레버(150)를 통해 지지구조체(110)가 외벽(1)에 고정될 수 있다.In the fixing lever installation step (S11), as shown in FIG. 6, the fixing lever 150 is installed to fix the outer wall fixing portion 111 of the support structure 110 to the window frame installation space of the outer wall 1 As a process, the support structure 110 may be fixed to the outer wall 1 through the fixing lever 150.

상기 이격부 설치단계(S12)는, 도 2에 도시된 바와 같이, 갱폼(10)을 건물의 외벽(1)에 밀착 고정되거나 이격되어 분리되도록 하기 위해 갱폼(10)의 일측에 이격부(160)를 설치하는 과정으로, 상기 이격부(160)를 통해 갱폼(10)이 외벽(1)으로부터 소정의 간격만큼 이격된 상태로 유지될 수 있다.The spacer installation step (S12), as shown in Figure 2, the spacer 160 on one side of the gangform 10 in order to be fixed in close contact with or separated from the outer wall 1 of the building. ), the gangfoam 10 may be maintained in a state spaced apart from the outer wall 1 by a predetermined distance through the spacer 160.

상기 레벨기 및 수평기 설치단계(S13)는, 상기 레벨기(170) 및 수평기(180)를 갱폼(10)에 설치하여 설치된 갱폼(10)의 레벨 및 수평을 측정하기 위한 과정으로, 갱폼(10)을 설치하는 과정에서 갱폼(10)의 레벨 및 수평이 정상의 범위를 벗어날 경우 갱폼(10)의 레벨 및 수평을 측정하고 재조정하기 위해 갱폼(10)에 설치하는 단계이다.The level and leveler installation step (S13) is a process for measuring the level and level of the installed gangform 10 by installing the leveler 170 and the leveler 180 on the gang form 10, and the gang form 10 In the process of installing ), if the level and the horizontal of the gang form 10 are out of the normal range, it is a step of installing on the gang form 10 to measure and readjust the level and level of the gang form 10.

도 7 내지 도 11을 참조하면,7 to 11,

갱폼(10)을 인상하는 갱폼 인상단계(S20) 및 지지구조체(110)를 인상하는 지지구조체 인상단계(S40)를 포함한다.It includes a gang form raising step (S20) of raising the gang form 10 and a support structure raising step (S40) of raising the support structure 110.

상기 갱폼 인상단계(S20)는, 상기 감속모터(130)의 구동에 의해 갱폼(10)을 상부로 이동시키는 과정이다. 이때, 감속모터(130)를 정방향으로 구동시키면 갱폼(10)이 상부로 이동될 수 있다. 도 7에 도시된 바와 같이, 도 7은 감속모터(130)를 정방향으로 구동시켰을 경우 갱폼(10)이 상부로 이동된 경우를 나타낸 것으로, 감속모터(130)의 톱니 기어(132)가 지지구조체의 톱니 레일(113)과 맞물려진 상태에서 모터(131)가 구동하면 톱니 기어(132)가 톱니 레일(113) 상부 위치까지 회전하고, 고정된 지지구조체(110)에 의해 결국 갱폼(10)이 상부로 이동할 수 있게 된다.The gang form raising step (S20) is a process of moving the gang form 10 upward by driving the reduction motor 130. At this time, when the reduction motor 130 is driven in the forward direction, the gang form 10 may be moved upward. As shown in FIG. 7, FIG. 7 shows a case where the gangform 10 is moved upward when the reduction motor 130 is driven in the forward direction, and the toothed gear 132 of the reduction motor 130 is a support structure When the motor 131 is driven in a state engaged with the toothed rail 113 of the toothed gear 132, the toothed gear 132 rotates to the upper position of the toothed rail 113, and the gangform 10 is eventually formed by the fixed support structure 110. You can move to the top.

지지구조체 인상단계(S40)는, 상기 감속모터(130)의 구동에 의해 지지구조체(110)를 상부로 이동시키는 과정이다. 이때, 감속모터(130)를 역방향으로 구동시키면 지지구조체(110)가 상부로 이동될 수 있다. 도 11에 도시된 바와 같이, 도 11은 감속모터(130)를 역방향으로 구동시켰을 경우 지지구조체(110)가 상부로 이동된 경우를 나타낸 것으로, 감속모터(130)의 톱니 기어(132)가 지지구조체의 톱니 레일(113)과 맞물려진 상태에서 모터(131)가 구동하면 톱니 기어(132)가 톱니 레일(113) 하부 위치까지 회전하고, 매립앙카(5)에 의해 갱폼(10)이 고정된 상태이고 지지구조체(110)는 고정이 해제된 상태가 됨으로써, 결국 지지구조체(110)가 상부로 이동할 수 있게 된다.The step of raising the support structure (S40) is a process of moving the support structure 110 upward by driving the reduction motor 130. At this time, when the reduction motor 130 is driven in the reverse direction, the support structure 110 may be moved upward. As shown in FIG. 11, FIG. 11 shows a case where the support structure 110 is moved upward when the reduction motor 130 is driven in the reverse direction, and the toothed gear 132 of the reduction motor 130 is supported. When the motor 131 is driven in a state engaged with the toothed rail 113 of the structure, the toothed gear 132 rotates to the lower position of the toothed rail 113, and the gang form 10 is fixed by the buried anchor 5. In this state, the support structure 110 is in a state in which the fixing is released, so that the support structure 110 can move upward.

상기 갱폼(10) 및 지지구조체(110)가 상부로 구동되기 위해 구동하는 감속모터(130)의 정방향 및 역방향에 대한 회전 방향은 감속모터(130)의 설치 위치 등에 따라 그 방향은 변경될 수도 있다.The direction of rotation of the reduction motor 130, which is driven to drive the gangform 10 and the support structure 110 upward, with respect to the forward and reverse directions may be changed according to the installation position of the reduction motor 130, etc. .

도 8 내지 도 11을 참조하면, 상기 타설단계(S30)는 기본적으로, 상기 갱폼인상단계(S20) 이후 건물 외벽(1)을 추가로 증설 시공하기 위해 콘크리트를 타설하는 단계이다.Referring to FIGS. 8 to 11, the pouring step (S30) is basically a step of pouring concrete in order to further expand the building outer wall 1 after the gang form raising step (S20).

상기 타설단계(S30)는, 추가적으로 건물의 외벽(1)을 증설 시공을 위한 거푸집을 설치하는 거푸집 설치단계(S31) 및 상기 설치된 거푸집에 콘크리트를 타설하는 콘크리트 타설단계(S32)를 포함할 수 있다.The pouring step (S30) may include a formwork installation step (S31) of installing a formwork for additionally expanding the outer wall 1 of the building and a concrete pouring step (S32) of pouring concrete into the installed formwork. .

상기 거푸집 설치단계(S31)는, 건물의 외벽(1)을 추가 증설할 경우 이미 설치된 거푸집에 타설된 콘크리트가 고착화된 이후 연속해서 상부로 위치를 이동하면서 추가로 건물의 외벽(1)을 증설하기 위해 거푸집(4)을 해체 및 설치하는 과정이다.In the formwork installation step (S31), when additionally extending the outer wall 1 of the building, after the concrete poured in the already installed formwork is fixed, it is continuously moved to the upper part and additionally expands the outer wall 1 of the building. This is the process of dismantling and installing the formwork (4).

도 8 내지 도 9에 도시된 바와 같이, 거푸집(4)을 슬라브(2)의 상부 공간으로 위치시켜 설치하고, 거푸집(4)과 갱폼(10)을 연결 고정하기 위해 매립앙카(5)를 설치한다.8 to 9, the formwork 4 is placed in the upper space of the slab 2 and installed, and a buried anchor 5 is installed to connect and fix the formwork 4 and the gang form 10 do.

상기 매립앙카(5)는 기본적으로 볼트 및 와셔 등으로 구성되는 고정장치를 이용하여 이미 콘크리트 외벽(1)의 타설 및 양생이 끝난 하부층의 외벽(1) 및 슬라브(2)와 고정하기 위해 하부층 외벽(1)에 매립된 매립앙카(5)와 고정장치를 체결하고, 거푸집(4)을 고정 설치한 후 하부층 상부에 새로운 층의 벽체를 콘크리트 타설하고, 새로운 벽체의 콘크리트 양생이 완료되면, 하부층의 매립앙카(5)와 체결된 고정장치를 분리한 후, 갱폼(10)을 인상하는 작업이 이루어진다.The buried anchor 5 basically uses a fixing device composed of bolts and washers to fix it with the outer wall 1 and the slab 2 of the lower layer after the concrete outer wall 1 has been cast and cured. After fastening the fixing device with the buried anchor (5) buried in (1), the formwork (4) is fixedly installed, the wall of the new layer is poured into concrete on the upper part of the lower layer, and when the concrete curing of the new wall is completed, the lower layer is After separating the fixing device fastened with the buried anchor 5, the gang form 10 is lifted.

상기 콘크리트 타설단계(S32)는, 상기 상부 층으로 설치된 거푸집(4)에 콘크리트를 타설하여 새로운 층의 벽체를 완성하기 위해 콘크리트를 타설하는 단계이다. 즉, 상부 층에 거푸집(4) 설치를 하고, 상기 거푸집(4)과 갱폼(10)을 고정하는 매립앙카(5)의 설치가 완료되면 거푸집(4)과 갱폼(10) 사이의 공간, 즉, 외벽(1)을 구성하기 위한 공간으로 콘크리트를 타설하게 된다.The concrete pouring step (S32) is a step of pouring concrete to complete the wall of a new layer by pouring concrete into the formwork 4 installed as the upper layer. That is, when the formwork 4 is installed on the upper layer and the installation of the buried anchor 5 fixing the formwork 4 and the gang form 10 is completed, the space between the formwork 4 and the gang form 10, that is, , Concrete is poured as a space for constructing the outer wall (1).

또한, 상기 인상장치(100)를 이용한 건물의 외벽(1) 시공방법은 시공이 완료될 때까지 상기 설치단계(S10), 상기 갱폼인상단계(S20), 상기 타설단계(S30), 상기 지지구조체 인상단계(S40)를 순차적으로 반복하는 반복단계(S50)를 거치면서 연속해서 외벽(1)을 추가로 증설하는 과정이 이루어질 수 있다.In addition, the construction method of the outer wall (1) of the building using the lifting device 100 is the installation step (S10), the gang form lifting step (S20), the pouring step (S30), the support structure until the construction is completed. A process of additionally expanding the outer wall 1 may be performed continuously while going through the repeating step S50 of sequentially repeating the raising step S40.

이하에서는 상기 설명한 갱폼 인상장치(100)를 이용하여 건물의 외벽 시공하는 과정에 있어, 갱폼 인상장치(100)의 동작에 대한 설명을 도 4 내지 도 11을 참조하여 설명한다.Hereinafter, in the process of constructing the outer wall of a building using the gang form lifting device 100 described above, a description of the operation of the gang form lifting device 100 will be described with reference to FIGS. 4 to 11.

최초 건물의 외벽(1)을 시공하는 과정에서 외벽(1)에 매립앙카(5)를 이용하여 갱폼(10)을 설치하고, 지지구조체(110)가 갱폼(10)의 갱폼 연결 가이드레일(120)에 의해 결합된 상태로 외벽(1) 일측에 지지되도록 한다.In the process of first constructing the outer wall (1) of the building, the gang form (10) is installed on the outer wall (1) using a buried anchor (5), and the support structure (110) connects the gang form to the gang form (10). ) To be supported on one side of the outer wall (1) in a coupled state.

그 다음, 고정레버(150)를 통해 외벽(1)의 창틀이 설치되는 공간에 지지구조체(110)를 고정 설치하여 설치단계(S10)를 수행한다. Then, the support structure 110 is fixedly installed in the space where the window frame of the outer wall 1 is installed through the fixing lever 150 to perform the installation step (S10).

그 다음, 감속모터(130)의 구동에 의해 모터(131)가 정방향으로 회전하면 톱니 기어(132)가 회전하여 갱폼(10)이 상부로 인상하여 갱폼인상단계(S20)을 수행한다.
그 다음, 최 상단에 설치된 거푸집(4)과 이동된 갱폼(10)이 상호 고정될 수 있도록 매립앙카(5)를 설치 후 거푸집(4)과 갱폼(10)의 사이공간에 콘크리트를 타설하고 양생하는 과정을 거치면서 타설단계(S30)가 이루어진다.
그 다음, 외벽(1)에 고정되어 있던 고정레버(150)를 제거하여 지지구조체(110)가 외벽(1)으로부터 분리될 수 있도록 하고, 감속모터(130)의 구동에 의해 모터(131)가 역방향으로 회전하면 톱니 기어(132)가 회전하여 지지구조체(110)가 상부로 인상되며 지지구조체 인상단계(S40)가 이루어진다.
그 다음, 건물의 외벽(1) 시공이 완료될 때까지 상기 설치단계(S10)와, 갱폼 인상단계(S20)와, 타설단계(S30) 및 지지구조체 인상단계(S40)가 반복됨으로써 반복단계(S50)가 이루어지고 건물의 외벽(1) 시공이 완료된다.
Then, when the motor 131 is rotated in the forward direction by the driving of the reduction motor 130, the toothed gear 132 is rotated and the gang form 10 is lifted upward to perform the gang form lifting step (S20).
Then, after installing the buried anchor 5 so that the formwork 4 installed at the top and the moved gang form 10 can be fixed to each other, concrete is poured into the space between the formwork 4 and the gang form 10 and cured. While going through the process, the pouring step (S30) is performed.
Then, by removing the fixing lever 150 fixed to the outer wall (1) so that the support structure 110 can be separated from the outer wall (1), and the motor 131 is driven by the reduction motor 130 When rotated in the reverse direction, the toothed gear 132 rotates, the support structure 110 is raised to the top, and the support structure raising step (S40) is made.
Then, the installation step (S10), the gang form raising step (S20), the pouring step (S30), and the support structure raising step (S40) are repeated until the construction of the outer wall (1) of the building is completed. S50) is made and the construction of the exterior wall (1) of the building is completed.

삭제delete

삭제delete

삭제delete

삭제delete

이러한 상기 본 발명의 기술적 사상에 의한 일 실시예에 따른 본 발명에 따른 갱폼 인상장치(100)는, 용이하게 갱폼(10)을 설치하고 갱폼(10)을 인상하는 작업이 전기적인 제어에 의해 연속적으로 이루어질 수 있어, 종래와 같이 타워크레인을 이용하지 않고도 안전하고 신속하게 갱폼(10)을 인상하는 작업을 수행할 수 있는 효과가 있다. 또한, 상기 갱폼 인상장치(100)를 이용한 건물의 외벽 시공방법은, 종래와 같이 타워크레인을 이용하지 않고 갱폼(10)을 설치하는 과정부터 갱폼(10)을 인상하는 과정 및 건물의 외벽(1)을 증설 시공을 위한 콘크리트 타설단계를 손쉽게 연속적으로 수행할 수 있어 건물의 외벽(1) 시공시간을 단축시킬 수 있고, 작업비용 절감 및 작업의 위험도를 낮출 수 있는 효과가 있는 것이다.In the gang form lifting device 100 according to the present invention according to an embodiment of the technical idea of the present invention, the operation of easily installing the gang form 10 and raising the gang form 10 is continuously performed by electrical control. It can be made of, there is an effect that can perform the work of safely and quickly raising the gang form 10 without using a tower crane as in the prior art. In addition, the method of constructing the outer wall of a building using the gang form lifting device 100 is, from the process of installing the gang form 10 without using a tower crane as in the prior art, the process of raising the gang form 10 and the outer wall of the building (1). ), it is possible to easily and continuously perform the concrete pouring step for the extension construction, thereby reducing the construction time of the outer wall (1) of the building, reducing work cost and lowering the risk of work.

이상 설명한 바와 같이 도면과 명세서에서 최적 실시예가 개시되었다. 여기서 특정한 용어들이 사용되었으나, 이는 단지 본 발명을 설명하기 위한 목적에서 사용된 것이지 의미를 한정하거나 특허청구범위에 기재된 본 발명의 범위를 제한하기 위하여 사용된 것은 아니다. 그러므로 본 기술분야의 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 타 실시예가 가능하다는 점을 이해할 것이다. 따라서, 본 발명의 진정한 기술적 보호범위는 첨부된 특허청구범위의 기술적 사상에 의해 정해져야 할 것이다.As described above, an optimal embodiment has been disclosed in the drawings and specification. Although specific terms have been used herein, these are only used for the purpose of describing the present invention and are not used to limit the meaning or the scope of the present invention described in the claims. Therefore, those of ordinary skill in the art will understand that various modifications and equivalent other embodiments are possible therefrom. Accordingly, the true technical scope of the present invention should be determined by the technical spirit of the appended claims.

100: 갱폼 인상장치 110: 지지구조체
111: 외벽 고정부 112: 갱폼 연결부
113: 톱니 레일 120: 갱폼 연결 가이드레일
121: 레일 122: 레일 결합부
130: 감속모터 131: 모터
132: 톱니 기어 140: 제어부
150: 고정레버 160: 이격부
161: 이격스프링 162: 이격레버
170: 레벨기 180: 수평기
100: gang form lifting device 110: support structure
111: outer wall fixing part 112: gang form connection
113: toothed rail 120: gangform connection guide rail
121: rail 122: rail coupling portion
130: reduction motor 131: motor
132: toothed gear 140: control unit
150: fixing lever 160: separation part
161: separation spring 162: separation lever
170: level 180: level

Claims (14)

건물의 외벽을 시공하기 위해 건물 외벽에 설치되는 갱폼을 인상하기 위한 갱폼 인상장치에 있어서,
일측이 건물의 외벽에 지지되고, 타측 상부에 수직 배열되는 톱니가 형성된 지지구조체;
상기 지지구조체와 결합되는 상기 갱폼을 레일 결합하기 위해 갱폼 일측에 복수 개가 설치되는 갱폼 연결 가이드레일;
상기 갱폼의 일측에 설치되고, 상기 지지구조체 및 상기 갱폼을 상승 동작시키기 위한 톱니기어가 구비된 감속모터; 및
상기 감속모터의 구동을 제어하고, 갱폼 인상장치 동작 전반을 제어하는 제어부;를 포함하는 것을 특징으로 하는 갱폼 인상장치.
In the gang form lifting device for raising the gang form installed on the outer wall of the building to construct the outer wall of the building,
A support structure in which one side is supported on the outer wall of the building and vertically arranged on the other side;
A gangform connection guide rail having a plurality of gangforms installed on one side of the gangform to rail-couple the gangforms coupled with the support structure;
A reduction motor installed on one side of the gang form and provided with a toothed gear for lifting the support structure and the gang form; And
And a control unit that controls the driving of the reduction motor and controls the overall operation of the gang form pulling device.
제1항에 있어서,
상기 갱폼 인상장치는,
상기 지지구조체를 건물의 외벽에 지지된 상태로 고정하기 위한 고정레버를 포함하는 것을 특징으로 하는 갱폼 인상장치.
The method of claim 1,
The gang form lifting device,
A gang form lifting device comprising a fixing lever for fixing the support structure in a state supported by an outer wall of a building.
제1항에 있어서,
상기 갱폼 연결 가이드레일은,
상기 갱폼에 설치되고, 돌출 형성된 레일; 및
상기 레일에 대응되도록 지지구조체에 설치되고, 상기 레일이 삽입될 수 있는 홈부가 마련되어 돌출된 레일 일부를 감싸 듯 레일에 슬라이딩 결합되는 레일 결합부;를 포함하는 것을 특징으로 하는 갱폼 인상장치.
The method of claim 1,
The gang form connection guide rail,
A rail installed on the gang form and protruding; And
And a rail coupling portion installed on the support structure to correspond to the rail, provided with a groove portion into which the rail can be inserted, and slidably coupled to the rail as if surrounding a portion of the protruding rail.
제1항에 있어서,
상기 갱폼 인상장치는,
상기 갱폼이 시공중인 건물의 외벽에 밀착 고정되거나 이격되어 분리되도록 하기 위해 상기 갱폼의 일측에 설치되는 이격부를 포함하는 것을 특징으로 하는 갱폼 인상장치.
The method of claim 1,
The gang form lifting device,
The gang form lifting device, characterized in that it comprises a spacer installed on one side of the gang form to be closely fixed or separated from the outer wall of the building under construction.
제4항에 있어서,
상기 이격부는,
상기 갱폼이 건물의 외벽으로부터 이격되도록 반발력을 발생시키기 위한 이격스프링; 및
상기 갱폼을 건물의 외벽에 밀착 고정된 상태로 유지시키기 위한 이격레버;를 포함하는 것을 특징으로 하는 갱폼 인상장치.
The method of claim 4,
The spacing part,
A spacing spring for generating a repulsive force so that the gang form is separated from the outer wall of the building; And
And a separation lever for maintaining the gang form in a tightly fixed state on the outer wall of the building.
제1항에 있어서,
상기 감속모터는,
상기 제어부의 제어에 의해 정방향 또는 역방향으로 구동될 수 있는 것을 특징으로 하는 갱폼 인상장치.
The method of claim 1,
The reduction motor,
Gang form lifting device, characterized in that it can be driven in a forward or reverse direction under the control of the control unit.
제1항에 있어서,
상기 갱폼 인상장치는,
상기 갱폼의 레벨 및 수평을 측정하기 위한 레벨기 및 수평기를 포함하는 것을 특징으로 하는 갱폼 인상장치.
The method of claim 1,
The gang form lifting device,
A gang form lifting device comprising a level and a level for measuring the level and horizontal of the gang form.
제1항에 있어서,
상기 제어부는,
감속모터를 포함하는 전기적인 장치를 제어하여 지지구조체 및 갱폼의 동작을 제어하고, 원격으로도 제어할 수 있는 것을 특징으로 하는 갱폼 인상장치.
The method of claim 1,
The control unit,
A gang form lifting device, characterized in that it is possible to control an electrical device including a reduction motor to control the operation of the support structure and the gang form, and to remotely control it.
제1항의 갱폼 인상장치와 건물의 외벽을 시공하기 위한 갱폼을 설치하기 위한 설치단계(S10);
갱폼 인상장치를 이용하여 갱폼을 인상하는 갱폼인상단계(S20);
상기 갱폼인상단계 이후 건물 외벽을 추가로 증설 시공하기 위하여 거푸집을 설치하는 거푸집 설치단계(S31)와, 상기 설치된 거푸집에 콘크리트를 타설하는 콘크리트 타설단계(S32)로 이루어지는 타설단계(S30);
상기 갱폼 인상장치를 이용하여 지지구조체를 인상하는 지지구조체인상단계(S40);
상기 설치단계(S10), 상기 갱폼인상단계(S20), 상기 타설단계(S30) 및 지지구조체 인상단계(S40)를 순차적으로 반복하는 반복단계(S50);를 포함하는 인상장치를 이용한 건물의 외벽 시공방법.
An installation step (S10) for installing the gang form raising device of claim 1 and the gang form for constructing the outer wall of the building;
The gang form raising step of raising the gang form using the gang form lifting device (S20);
A pouring step (S30) consisting of a formwork installation step (S31) of installing a formwork in order to further expand the building exterior wall after the gang form raising step, and a concrete pouring step (S32) of pouring concrete into the installed formwork;
A support structure chain upper step (S40) of raising the support structure by using the gang form lifting device;
The installation step (S10), the gang form lifting step (S20), the pouring step (S30), and a repeating step (S50) of sequentially repeating the support structure lifting step (S40); the outer wall of the building using an impression device including Construction method.
제9항에 있어서,
상기 설치단계(S10)는,
상기 지지구조체를 건물의 외벽에 고정하기 위한 고정레버를 설치하기 위한 고정레버 설치단계(S11)를 더 포함하는 것을 특징으로 하는 인상장치를 이용한 건물의 외벽 시공방법.
The method of claim 9,
The installation step (S10),
A method of constructing an outer wall of a building using an impression device, further comprising: a fixing lever installation step (S11) for installing a fixing lever for fixing the support structure to the outer wall of the building.
제9항에 있어서,
상기 설치단계(S10)는,
상기 갱폼이 시공중인 건물의 외벽에 밀착 고정되거나 이격되어 분리되도록 하기 위해 상기 갱폼의 일측에 설치되는 이격부를 설치하기 위한 이격부 설치단계(S12)를 더 포함하는 것을 특징으로 하는 인상장치를 이용한 건물의 외벽 시공방법.
The method of claim 9,
The installation step (S10),
Building using an impression device, characterized in that it further comprises a spacer installation step (S12) for installing a spacer installed on one side of the gangform so that the gangform is closely fixed or separated from the outer wall of the building under construction Exterior wall construction method.
제9항에 있어서,
상기 설치단계(S10)는,
상기 갱폼에 레벨기 및 수평기를 설치하고, 갱폼의 설치된 상태의 레벨 및 수평을 측정하는 레벨기 및 수평기 설치단계(S13)를 더 포함하는 것을 특징으로 하는 인상장치를 이용한 건물의 외벽 시공방법.
The method of claim 9,
The installation step (S10),
A method for constructing an exterior wall of a building using an impression device, further comprising: installing a leveler and a leveler on the gangform, and measuring the level and level of the installed state of the gangform (S13).
제9항에 있어서,
상기 갱폼인상단계(S20)는, 감속모터를 정방향으로 구동하여 갱폼을 인상하고, 지지구조체인상단계(S40)는, 감속모터를 역방향으로 구동하여 지지구조체를 인상함을 특징으로 하는 인상장치를 이용한 건물의 외벽 시공방법.
The method of claim 9,
In the gang form lifting step (S20), the reduction motor is driven in a forward direction to raise the gang form, and the support structure chain lifting step (S40) is performed using a lifting device, characterized in that the reduction motor is driven in the reverse direction to raise the support structure. Building exterior wall construction method.
삭제delete
KR1020180063716A 2018-06-01 2018-06-01 Gang form lifting device and outdoor wall construction method of building using the same KR102156971B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180063716A KR102156971B1 (en) 2018-06-01 2018-06-01 Gang form lifting device and outdoor wall construction method of building using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180063716A KR102156971B1 (en) 2018-06-01 2018-06-01 Gang form lifting device and outdoor wall construction method of building using the same

Publications (2)

Publication Number Publication Date
KR20190137485A KR20190137485A (en) 2019-12-11
KR102156971B1 true KR102156971B1 (en) 2020-09-16

Family

ID=69003528

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180063716A KR102156971B1 (en) 2018-06-01 2018-06-01 Gang form lifting device and outdoor wall construction method of building using the same

Country Status (1)

Country Link
KR (1) KR102156971B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114892966B (en) * 2022-06-27 2024-07-26 中交二公局第七工程有限公司 Integral casting concrete supporting component and supporting method for inverted cone-shell water tower water tank

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200241872Y1 (en) 2001-05-26 2001-10-29 지종연 Apparatus for pulling up a form using a hydraulic jack
KR101008359B1 (en) * 2008-06-30 2011-01-13 서보산업 주식회사 A concrete mold lifter

Also Published As

Publication number Publication date
KR20190137485A (en) 2019-12-11

Similar Documents

Publication Publication Date Title
KR101151866B1 (en) A Lifting method of formwork working Foothold
JP7193151B2 (en) Self-climbing device and method of operation for vertical and near-vertical concrete surfaces
JP5280445B2 (en) Method for forming multiple horizontal structural members
KR102115380B1 (en) Hydraulic slipform safety locking device and virtical structure and slab construction method using the same
US3302749A (en) Derrick scaffold structure
JP5660569B2 (en) Building lifting equipment
KR20100001123U (en) Self-standing auto climbing apparatus and system using the same
KR200417331Y1 (en) Gangform Lift
KR102156971B1 (en) Gang form lifting device and outdoor wall construction method of building using the same
KR20090020246A (en) Self-standing auto climbing system, apparatus and method using the same
JP6622504B2 (en) Chimney demolition scaffold and chimney demolition method
JP5990427B2 (en) Wind resistance reinforcement method for elevating formwork
KR100475544B1 (en) Wall form climbing system for constructing concrete wall of high-rise buldings
KR100934376B1 (en) Elevating and lowering platform and method of movement
CN114197860B (en) Double-layer climbing formwork system for rapid construction and climbing formwork construction method
JP3531111B2 (en) Apparatus and method for constructing tower-like structure
JP6059176B2 (en) Mobile lifting scaffold for assembling temporary elevated jetty
KR200366291Y1 (en) Wall form climbing system for constructing concrete wall of high-rise buldings
CN104453217A (en) Elevator shaft whole formwork lifting construction method
WO2005042876A1 (en) A lifting assembly for a shutter to allow continuous casting
KR101030795B1 (en) Salvare unit with constructing care
KR100293687B1 (en) Concrete delivery device and its installation method
JP4027170B2 (en) External scaffold device and construction method of external scaffold device
KR200256771Y1 (en) Automatic system for low pier construction
JP4876817B2 (en) Construction method of tower structure, tower structure

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant