KR102051331B1 - Method, apparatus and computer readable recording medium for selecting construction method of earth retaining wall - Google Patents

Method, apparatus and computer readable recording medium for selecting construction method of earth retaining wall Download PDF

Info

Publication number
KR102051331B1
KR102051331B1 KR1020190076936A KR20190076936A KR102051331B1 KR 102051331 B1 KR102051331 B1 KR 102051331B1 KR 1020190076936 A KR1020190076936 A KR 1020190076936A KR 20190076936 A KR20190076936 A KR 20190076936A KR 102051331 B1 KR102051331 B1 KR 102051331B1
Authority
KR
South Korea
Prior art keywords
construction
temporary
earthquake
construction site
ground
Prior art date
Application number
KR1020190076936A
Other languages
Korean (ko)
Inventor
안재형
Original Assignee
안재형
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 안재형 filed Critical 안재형
Priority to KR1020190076936A priority Critical patent/KR102051331B1/en
Application granted granted Critical
Publication of KR102051331B1 publication Critical patent/KR102051331B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/10Miscellaneous comprising sensor means

Abstract

The present invention relates to a method for selecting a construction method for a temporary facility for earth retaining. More particularly, the method comprises: a ground data collection step of collecting ground data related to the geological characteristics of a construction site by conducting a ground survey on the construction site where a temporary facility for earth retaining is installed; a step of selecting a construction method for a temporary facility for earth retaining, more specifically, selecting a construction method for a temporary facility for earth retaining corresponding to ground data conditions collected from a database which stores one or more construction methods for temporary facilities for earth retaining; a monitoring step of performing monitoring by measuring the displacement of the temporary facility for earth retaining from one or more sensor modules in a state where installation construction of the temporary facility for earth retaining is performed at a construction site based on the selected construction method for the temporary facility for earth retaining, and the one or more sensor modules are installed in one area of the temporary facility for earth retaining; and a reinforcing work information providing step of providing, to a site manager terminal, reinforcing work information required for the temporary facility for earth retaining when it is determined that the measured displacement of the temporary facility for earth retaining is out of a preset maximum allowable displacement amount as a result of the monitoring step. The method can prevent various accidents which may occur when ground works are performed.

Description

흙막이 가시설 공법의 선정 방법, 장치 및 컴퓨터 판독가능 기록 매체{METHOD, APPARATUS AND COMPUTER READABLE RECORDING MEDIUM FOR SELECTING CONSTRUCTION METHOD OF EARTH RETAINING WALL}METHOOD, APPARATUS AND COMPUTER READABLE RECORDING MEDIUM FOR SELECTING CONSTRUCTION METHOD OF EARTH RETAINING WALL}

본 발명은 흙막이 가시설 공법의 선정 방법에 관한 것으로서, 구체적으로는, 시공 현장의 지질 특성과 관련한 지반 데이터와 건축물의 설계 조건을 고려하여 시공 현장에 매칭되는 흙막이 가시설 공법을 선정하고, 설치된 흙막이 가시설을 관제하여 안전 사고를 미연에 방지할 수 있도록 하는 기술과 관련된 것이다.The present invention relates to a method of selecting a temporary tent construction method, specifically, in consideration of the ground data related to the geological characteristics of the construction site and the design conditions of the building, selecting a temporary tent construction method matching the construction site, and installing the installed temporary tent facility It is related to the technology to control and prevent safety accidents in advance.

일반적으로 흙막이 가시설의 설치 공사는 건설 공사에 있어서 가장 기본이 되는 작업으로서, 지지 구조물을 설치하여 굴착 작업 시에 시공 현장 내로 주변 흙이나 물의 유입을 방지하면서 주변 지반 붕괴를 방지하고, 토압 및 수압의 측압에 저항하도록 설치되는 가설공사를 말한다.In general, the installation work of the earthenware temporary installation is the most basic work in the construction work, by installing the supporting structure to prevent the surrounding ground collapse while preventing the inflow of the surrounding soil or water into the construction site during the excavation work, and prevents earth pressure and water pressure Temporary construction installed to resist side pressure.

이러한 흙막이 가시설 설치 공사는, 최근 구조물의 대형화, 고층화, 지하공간 활용의 필요성 증대에 따른 수요로 인하여 대규모 지반 굴착 및 흙막이 공사가 증대되고 있다.In recent years, such construction of temporary wall installations has been increasing due to the demand for larger structures, higher floors, and increased use of underground spaces.

그러나, 이러한 수요 증대에도 불구하고, 흙막이 가시설 공사는 공사 후 제거되는 임시 가시설이라는 이유로 지반 굴착 공사에서 발생하는 붕괴 사고 중 48%가 흙막이 가시설의 부실 시공에 의한 사고임에도 불구하고 명확한 흙막이 가시설 설계 가이드 라인을 제공하거나, 설치된 흙막이 가시설의 관리를 수행하기 위한 기술 개발이 소홀히 되는 문제가 있었다.However, despite the increasing demand, the clearing block design guidelines are clear despite the fact that 48% of the breakdowns in the ground excavation work are due to the inadequate construction of the earth block construction because the temporary block construction is a temporary unit that is removed after construction. There has been a problem of neglecting the development of technology to provide or to perform the management of the installed earthquake temporary installation.

한편, 종래 기술로서 한국 등록 특허 제10-1191131호(흙막이 가시설 구조물의 변위 계측 장치)에서는 가시설 구조물 자체의 변위를 측정하여 원격지에서도 가시설의 관리가 수행될 수 있도록 하는 기술이 개시되어 있다.On the other hand, in the prior art Korean Patent No. 10-1191131 (displacement measuring device of the temporary construction structure) discloses a technique for measuring the displacement of the temporary structure itself so that the management of the temporary facility can be performed at a remote location.

그러나, 상술한 종래 기술은, 설치된 가시설의 변위 측정에 의하여 가시설의 모니터링을 수행할 수 있다는 장점은 있으나, 흙막이 가시설의 설치를 수행함에 있어서, 지질 조사를 수행하여 측정된 측정값을 기반으로 사람이 직접 데이터를 분석하여, 흙막이 가시설의 설치 공법을 선정하여야 하는 문제가 존재하였다.However, the above-described prior art has the advantage that the monitoring of the temporary facility can be performed by measuring the displacement of the installed temporary facility. However, in the installation of the earthquake temporary facility, a person based on the measured value measured by performing a geological survey There was a problem of selecting the installation method of the temporary block installation by analyzing the data directly.

게다가 이러한 문제는 지질 조사 수행 시점의 지질 상태에 대한 흙막이 가시설의 설치 공법을 결정하게 됨에 따라서, 지질 조사 시점 이후 기상 상황이 악화되어, 단기간에 강수량이 늘어날 경우, 토사 유실 및 토양 하중 증가로 인한 붕괴 사고를 대응할 수 없는 문제가 있었다.In addition, this problem is determined by the construction method of the seismic temporary installation for the geological state at the time of geological survey, the weather situation worsened after the geological survey, if the rainfall increased in a short time, the loss due to soil loss and soil load increase There was a problem that could not respond to the accident.

이에 본 발명에서는, 시공 현장의 지질 특성과 관련한 지반 데이터와 건축물의 설계 조건을 고려하여 시공 현장에 매칭되는 흙막이 가시설 공법을 선정하되, 시공 현장에 대응되는 지역의 기상 데이터를 이용하여 기상 요소가 고려된 흙막이 가시설 공법의 선정 방법을 제공하는 것에 제1 목적이 있다.Therefore, in the present invention, while selecting the earthquake temporary construction method matching the construction site in consideration of the ground data related to the geological characteristics of the construction site and the design conditions of the building, the weather elements are considered using the weather data of the area corresponding to the construction site It is a 1st objective to provide the selection method of the temporary block temporary construction method.

또한, 본 발명에서는, 시공 현장에 설치된 흙막이 가시설을, 센서 모듈을 통해 모니터링을 수행하고, 실시간으로 변위를 계측하여 현장 관리자 단말 측에 보강이 필요한 영역의 보강 작업 정보를 제공하여줄 수 있는 흙막이 가시설 공법의 선정 방법을 제공하는 것에 제2 목적이 있다. In addition, in the present invention, the earthquake temporary installation installed in the construction site, monitoring the sensor through the sensor module, measuring the displacement in real time to provide the reinforcement work information of the area that needs to be reinforced on the site manager terminal side A second object is to provide a method for selecting a public method.

상기 목적을 달성하기 위한 하나 이상의 프로세서 및 프로세서에서 수행 가능한 명령들을 저장하는 하나 이상의 메모리를 포함하는 컴퓨팅 장치에서 구현되는 흙막이 가시설 공법의 선정 방법은, 흙막이 가시설이 설치되는 시공 현장에 대한 지반 조사를 수행하여 시공 현장의 지질 특성과 관련한 지반 데이터를 수집하는 지반 데이터 수집 단계; 하나 이상의 흙막이 가시설 공법이 저장되어 있는 데이터베이스에서 수집된 지반 데이터 조건에 대응되는 흙막이 가시설 공법을 선정하는 흙막이 가시설 공법 선정 단계; 선정된 흙막이 가시설 공법을 기초로 시공 현장에 흙막이 가시설의 설치 시공을 수행하되, 흙막이 가시설의 일 영역에는 하나 이상의 센서 모듈이 설치되도록 하여, 센서 모듈로부터 흙막이 가시설의 변위를 계측하여 모니터링을 수행하는 모니터링 단계; 및 모니터링 단계의 수행 결과, 계측된 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단될 경우, 현장 관리자 단말에 흙막이 가시설에 요구되는 보강 작업 정보를 제공하는 보강 작업 정보 제공 단계;를 포함하는 것을 특징으로 한다.In order to achieve the above object, a method of selecting a clogging construction method implemented in a computing device including at least one processor and at least one memory storing instructions that can be executed by the processor, the ground survey for the construction site where the clogging construction is installed A ground data collection step of collecting ground data relating to geological characteristics of the construction site; Selecting a clogging construction method for selecting a clogging construction method corresponding to the ground data conditions collected from a database in which at least one clogging construction method is stored; Based on the selected earthquake temporary construction method, the installation of the earthquake temporary facility at the construction site is carried out, but one or more sensor modules are installed in one area of the earthquake temporary facility, and the monitoring is performed by measuring the displacement of the earthquake temporary facility from the sensor module. step; And reinforcing job information providing step of providing reinforcement work information required for the earthquake temporary facility to the site manager terminal when it is determined that the measured displacement of the temporary fence is out of the preset maximum allowable displacement amount. It is characterized by.

상술한 흙막이 가시설 공법 선정 단계는, 지반 데이터로부터, 시공 현장에 요구되는 흙막이 가시설의 최소 내하력을 산출하고, 산출된 최소 내하력을 만족하는 흙막이 가시설 공법이 선정되도록 하는 것이 바람직하다. In the above-described selection method of the temporary wall construction method, it is preferable to calculate the minimum load capacity of the temporary wall temporary facility required for the construction site from the ground data and to select the temporary wall temporary construction method that satisfies the calculated minimum load capacity.

상술한 흙막이 가시설 공법 선정 단계는, 시공 현장에 대한 기상 데이터를 더 수집하여 흙막이 가시설 공법의 선정 기준 중 하나로 이용하되, 기상 데이터는 기상 관측 서버를 통해 수집된, 시공 현장에 대한 미래의 예측된 기상 데이터이고, 예측된 기상 데이터로부터 흙막이 가시설의 설치가 예정된 시공 기간에 우천이 예상되는 경우, 흙막이 가시설의 선정 기준을 상향 조정하여 상대적으로 큰 내하력을 갖는 흙막이 가시설이 선정될 수 있도록 하는 것이 바람직하다.In the above-described selection process of the temporary block construction method, the weather data for the construction site is collected and used as one of the selection criteria of the temporary block construction method, but the weather data is collected through the weather observation server. If the weather is expected and the weather is expected during the construction period when the installation of the temporary fence facility is scheduled, it is desirable to adjust the selection criteria of the temporary fence facility to select the temporary fence facility having a relatively large load capacity.

상술한 흙막이 가시설 공법 선정 단계는, 시공 현장에 대한 기상 데이터를 더 수집하여 흙막이 가시설 공법의 선정 기준 중 하나로 이용하되, 기상 데이터는, 시공 현장에 대한 과거의 누적된 기상 데이터를 통계적으로 분석하여 도출된 우천 발생 기간에 대한 기상 데이터이고, 우천 발생 기간과 흙막이 가시설의 설치가 예정된 시공 기간이 중복되는 경우, 흙막이 가시설의 선정 기준을 상향 조정하여 상대적으로 큰 내하력을 갖는 흙막이 가시설이 선정될 수 있도록 하는 것이 바람직하다.In the above-described selection process of the temporary block construction method, the weather data for the construction site is collected and used as one of the selection criteria of the temporary block construction method, but the weather data is derived by statistically analyzing the accumulated weather data of the construction site in the past. It is the weather data on the period of rainy weather, and when the rainy season is overlapped with the scheduled construction period, it is possible to raise the selection criteria of the temporary fence facility so that the temporary fence facility with a relatively large load capacity can be selected. It is preferable.

상술한 센서 모듈은, 흙막이 가시설이 설치되는 시공 현장을 기준으로 기 설정된 반경 내에 존재하는 주변 현장에 더 설치되도록 하여, 모니터링 단계의 수행 시, 시공 현장의 지반 및 인접 구조물의 지반 중 적어도 어느 하나를 포함하는 지반의 변위 계측을 통한 모니터링이 가능해지도록 하는 것이 바람직하다.The sensor module described above may be installed at a surrounding site existing within a predetermined radius based on the construction site where the earthquake temporary installation is installed, and thus, at least one of the ground of the construction site and the ground of the adjacent structure during the monitoring step. It is desirable to be able to monitor through the displacement measurement of the containing ground.

상술한 흙막이 가시설의 시공 인력 단말에는, 선정된 흙막이 가시설 공법에 요구되는 자재 정보, 시공 순서 및 시공 유의사항 정보 중 적어도 어느 하나를 포함하는 시공 안내 콘텐츠가 제공되고, 시공 안내 콘텐츠는, 시공 인력 단말의 출력 수단에서 출력 가능한 텍스트 이미지 및 영상 중 적어도 어느 하나를 포함하는 형태로서 출력 제공되는 것이 바람직하다.The construction maneuver terminal of the above-mentioned mud temporary facility is provided with a construction guide content including at least one of material information, a construction order, and construction precaution information required for the selected mud temporary facility construction method. It is preferable that the output is provided as a form including at least one of a text image and an image which can be output by the output means.

상술한 센서 모듈은, 지중 경사계, 침하계, 하중계, 지하 수위계, 변형률계, 수압계 및 토압계 중 적어도 어느 하나를 포함하는 것이 바람직하다.The sensor module described above preferably includes at least one of an underground inclinometer, a settlement meter, a load gauge, an underground water gauge, a strain gauge, a hydraulic pressure gauge, and a earth pressure gauge.

한편, 하나 이상의 프로세서 및 프로세서에서 수행 가능한 명령들을 저장하는 하나 이상의 메모리를 포함하는 컴퓨팅 장치로 구현되는 흙막이 가시설 공법의 선정 장치는, 흙막이 가시설이 설치되는 시공 현장에 대한 지반 조사를 수행하여 시공 현장의 지질 특성과 관련한 지반 데이터를 수집하는 지반 데이터 수집부; 하나 이상의 흙막이 가시설 공법이 저장되어 있는 데이터베이스에서 수집된 지반 데이터 조건에 대응되는 흙막이 가시설 공법을 선정하는 흙막이 가시설 공법 선정부; 선정된 흙막이 가시설 공법을 기초로 시공 현장에 흙막이 가시설의 설치 시공을 수행하되, 흙막이 가시설의 일 영역에는 하나 이상의 센서 모듈이 설치되도록 하여, 센서 모듈로부터 흙막이 가시설의 변위를 계측하여 모니터링을 수행하는 모니터링부; 및 모니터링부의 기능 수행 결과, 계측된 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단될 경우, 현장 관리자 단말에 흙막이 가시설에 요구되는 보강 작업 정보를 제공하는 보강 작업 정보 제공부;를 포함하는 것을 특징으로 한다.Meanwhile, the apparatus for selecting a clogging construction method implemented as a computing device including at least one processor and at least one memory storing instructions that can be executed by the processor may be performed by performing a ground survey on a construction site where the clogging construction is installed. A ground data collector for collecting ground data related to geological characteristics; A clogging construction method selection unit for selecting a clogging construction method corresponding to the ground data conditions collected from a database in which at least one clogging construction method is stored; Based on the selected earthquake temporary construction method, the installation of the earthquake temporary facility at the construction site is carried out, but one or more sensor modules are installed in one area of the earthquake temporary facility, and the monitoring is performed by measuring the displacement of the earthquake temporary facility from the sensor module. part; And a reinforcement job information providing unit for providing reinforcement work information required for the earthquake temporary facility to the site manager terminal when it is determined that the measured displacement of the temporary facility is out of the maximum allowable displacement amount as a result of performing the function of the monitoring unit. It is characterized by.

또 다른 한편, 컴퓨터 판독가능 기록 매체로서, 컴퓨터 판독가능 기록 매체는, 컴퓨팅 장치로 하여금 이하의 단계들을 수행하도록 하는 명령들을 저장하며, 상술한 단계들은: 흙막이 가시설이 설치되는 시공 현장에 대한 지반 조사를 수행하여 시공 현장의 지질 특성과 관련한 지반 데이터를 수집하는 지반 데이터 수집 단계; 하나 이상의 흙막이 가시설 공법이 저장되어 있는 데이터베이스에서 수집된 지반 데이터 조건에 대응되는 흙막이 가시설 공법을 선정하는 흙막이 가시설 공법 선정 단계; 선정된 흙막이 가시설 공법을 기초로 시공 현장에 흙막이 가시설의 설치 시공을 수행하되, 흙막이 가시설의 일 영역에는 하나 이상의 센서 모듈이 설치되도록 하여, 센서 모듈로부터 흙막이 가시설의 변위를 계측하여 모니터링을 수행하는 모니터링 단계; 및 모니터링 단계의 수행 결과, 계측된 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단될 경우, 현장 관리자 단말에 흙막이 가시설에 요구되는 보강 작업 정보를 제공하는 보강 작업 정보 제공 단계;를 포함하는 것을 특징으로 한다.On the other hand, as a computer readable recording medium, the computer readable recording medium stores instructions for causing a computing device to perform the following steps, wherein the steps described above are: a ground survey for the construction site where the masonry is installed; A ground data collection step of collecting ground data related to the geological characteristics of the construction site by performing a; Selecting a clogging construction method for selecting a clogging construction method corresponding to the ground data conditions collected from a database in which at least one clogging construction method is stored; Based on the selected earthquake temporary construction method, the installation of the earthquake temporary facility at the construction site is carried out, but one or more sensor modules are installed in one area of the earthquake temporary facility, and the monitoring is performed by measuring the displacement of the earthquake temporary facility from the sensor module. step; And reinforcing job information providing step of providing reinforcement work information required for the earthquake temporary facility to the site manager terminal when it is determined that the measured displacement of the temporary fence is out of the preset maximum allowable displacement amount. It is characterized by.

본 발명의 일 실시 예에 따르면, 시공 현장에 대한 과거 및 예측된 기상데이터를 이용하여 흙막이 가시설 공법을 선정하게 됨에 따라서, 지반 조사 시점 이후, 단기간에 강우량이 많아져 토압 및 수압이 증대되더라도 증대된 토압 및 수압의 측압에 저항할 수 있는 흙막이 가시설을 제공할 수 있게 되는 효과가 있다.According to an embodiment of the present invention, as the soil barrier construction method is selected by using the past and predicted weather data on the construction site, the rainfall increases in a short period of time after the soil survey, and thus the earth pressure and water pressure are increased. There is an effect that it is possible to provide an earthquake-proof facility that can resist the earth pressure and the side pressure of the hydraulic pressure.

또한, 본 발명의 일 실시 예에 따르면, 시공 현장에 설치된 흙막이 가시설을, 센서 모듈을 통해 모니터링을 수행하여 원격지에서도 흙막이 가시설의 관리가 가능해지는 효과가 있으며, 실시간으로 변위를 계측하여 현장 관리자 단말 측에 보강이 필요한 영역의 보강 작업 정보를 제공하여 줌에 따라서 흙막이 가시설의 설치 안정성이 극대화되는 효과가 있다.In addition, according to an embodiment of the present invention, by monitoring through the sensor module module installed in the construction site, through the sensor module has the effect that it is possible to manage the construction of the temporary block from a remote location, by measuring the displacement in real time on the site manager terminal side By providing information on the reinforcement work in the area where reinforcement is required, the installation stability of the earthenware temporary facility is maximized.

또한, 본 발명의 일 실시 예에 따르면, 시공 현장은 물론이고, 시공 현장에 인접한 인접 구조물의 변위 계측을 통한 모니터링을 수행하여, 지반 공사 수행 시 발생할 수 있는 각종 안전 사고를 미연에 방지할 수 있게 되는 효과가 있다.In addition, according to an embodiment of the present invention, as well as the construction site, by performing the monitoring by measuring the displacement of the adjacent structure adjacent to the construction site, it is possible to prevent various safety accidents that may occur when performing the ground work in advance. It is effective.

또한, 본 발명의 일 실시 예에 따르면, 선정된 흙막이 가시설 공법에 대한 시공 안내 콘텐츠를 시공 인력 단말에 제공하여, 체계적인 시공이 수행되도록 하며, 시공 유의사항을 상기 시켜 시공 인력의 시공 실수를 최소화할 수 있게 되어 시공 품질 저하를 미연에 방지할 수 있는 효과가 있다.In addition, according to an embodiment of the present invention, by providing the construction guide content for the selected earth block temporary construction method to the construction manpower terminal, so that systematic construction is carried out, by reminding the construction notes to minimize the construction mistakes of construction personnel It is possible to prevent the deterioration in construction quality in advance.

도 1은 본 발명의 일 실시 예에 따른 흙막이 가시설 공법의 선정 방법의 흐름도.
도 2는 본 발명의 일 실시 예에 따라 수집된 지반 데이터를 기초로 흙막이 가시설 공법이 선정되어 제공되는 일 예.
도 3은 본 발명의 일 실시 예에 따라 수집된 기상 데이터에 따라 흙막이 가시설의 선정 기준이 상향 조정되는 일 예.
도 4는 본 발명의 일 실시 예에 따라 흙막이 가시설에 설치된 센서 모듈에 의하여 흙막이 가시설의 변위가 모니터링 되는 일 예.
도 5는 본 발명의 일 실시 예에 따라 현장 관리자 단말에 보강 작업 정보가 제공되는 일 예.
도 6은 본 발명의 일 실시 예에 따라 시공 인력 단말에 시공 안내 콘텐츠가 제공되는 일 예.
도 7은 본 발명의 일 실시 예에 따른 흙막이 가시설 공법의 선정 장치의 구성도.
도 8은 본 발명의 일 실시 예에 따른 컴퓨팅 장치의 내부 구성의 일 예.
1 is a flow chart of a method of selecting a clogging construction method according to an embodiment of the present invention.
2 is an example in which the earthquake tent construction method is selected and provided based on the ground data collected according to an embodiment of the present invention.
Figure 3 is an example in which the selection criteria of the earthquake tentacles are adjusted up according to the weather data collected according to an embodiment of the present invention.
Figure 4 is an example in which the displacement of the earthquake tent is monitored by a sensor module installed in the earthquake tent according to an embodiment of the present invention.
5 is an example in which reinforcement work information is provided to a site manager terminal according to an embodiment of the present invention.
6 is an example in which construction guide content is provided to a construction manpower terminal according to an embodiment of the present invention.
Figure 7 is a block diagram of a selection device of a clogging construction method according to an embodiment of the present invention.
8 is an example of an internal configuration of a computing device according to an embodiment of the present invention.

이하에서는, 다양한 실시 예들 및/또는 양상들이 이제 도면들을 참조하여 개시된다. 하기 설명에서는 설명을 목적으로, 하나이상의 양상들의 전반적 이해를 돕기 위해 다수의 구체적인 세부사항들이 개시된다. 그러나, 이러한 양상(들)은 이러한 구체적인 세부사항들 없이도 실행될 수 있다는 점 또한 본 발명의 기술 분야에서 통상의 지식을 가진 자에게 인식될 수 있을 것이다. 이후의 기재 및 첨부된 도면들은 하나 이상의 양상들의 특정한 예시적인 양상들을 상세하게 기술한다. 하지만, 이러한 양상들은 예시적인 것이고 다양한 양상들의 원리들에서의 다양한 방법들 중 일부가 이용될 수 있으며, 기술되는 설명들은 그러한 양상들 및 그들의 균등물들을 모두 포함하고자 하는 의도이다.In the following, various embodiments and / or aspects are now disclosed with reference to the drawings. In the following description, for purposes of explanation, numerous specific details are set forth in order to provide a thorough understanding of one or more aspects. However, it will also be appreciated by one of ordinary skill in the art that this aspect (s) may be practiced without these specific details. The following description and the annexed drawings set forth in detail certain illustrative aspects of the one or more aspects. However, these aspects are exemplary and some of the various methods in the principles of the various aspects may be used and the descriptions described are intended to include all such aspects and their equivalents.

본 명세서에서 사용되는 "실시 예", "예", "양상", "예시" 등은 기술되는 임의의 양상 또는 설계가 다른 양상 또는 설계들보다 양호하다거나, 이점이 있는 것으로 해석되지 않을 수도 있다.As used herein, “an embodiment”, “an example”, “aspect”, “an example”, and the like, may not be construed that any aspect or design described is better or advantageous than other aspects or designs. .

또한, "포함한다" 및/또는 "포함하는"이라는 용어는, 해당 특징 및/또는 구성요소가 존재함을 의미하지만, 하나이상의 다른 특징, 구성요소 및/또는 이들의 그룹의 존재 또는 추가를 배제하지 않는 것으로 이해되어야 한다.In addition, the terms "comprises" and / or "comprising" mean that such features and / or components are present, but exclude the presence or addition of one or more other features, components, and / or groups thereof. It should be understood that it does not.

또한, 제 1, 제 2 등과 같이 서수를 포함하는 용어는 다양한 구성요소들을 설명하는데 사용될 수 있지만, 상기 구성요소들은 상기 용어들에 의해 한정되지는 않는다. 상기 용어들은 하나의 구성요소를 다른 구성요소로부터 구별하는 목적으로만 사용된다. 예를 들어, 본 발명의 권리 범위를 벗어나지 않으면서 제 1 구성요소는 제 2 구성요소로 명명될 수 있고, 유사하게 제 2 구성요소도 제 1 구성요소로 명명될 수 있다. 및/또는 이라는 용어는 복수의 관련된 기재된 항목들의 조합 또는 복수의 관련된 기재된 항목들 중의 어느 항목을 포함한다.In addition, terms including ordinal numbers such as first and second may be used to describe various components, but the components are not limited by the terms. The terms are used only for the purpose of distinguishing one component from another. For example, without departing from the scope of the present invention, the first component may be referred to as the second component, and similarly, the second component may also be referred to as the first component. The term and / or includes a combination of a plurality of related items or any item of a plurality of related items.

또한, 본 발명의 실시 예들에서, 별도로 다르게 정의되지 않는 한, 기술적이거나 과학적인 용어를 포함해서 여기서 사용되는 모든 용어들은 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자에 의해 일반적으로 이해되는 것과 동일한 의미를 가지고 있다. 일반적으로 사용되는 사전에 정의되어 있는 것과 같은 용어들은 관련 기술의 문맥 상 가지는 의미와 일치하는 의미를 가지는 것으로 해석되어야 하며, 본 발명의 실시 예에서 명백하게 정의하지 않는 한, 이상적이거나 과도하게 형식적인 의미로 해석되지 않는다.In addition, in the embodiments of the present invention, unless otherwise defined, all terms used herein including technical or scientific terms are generally understood by those skilled in the art to which the present invention belongs. It has the same meaning. Terms such as those defined in the commonly used dictionaries should be interpreted as having meanings consistent with the meanings in the context of the related art, and ideally or excessively formal meanings are not defined clearly in the embodiments of the present invention. Not interpreted as

본 발명은 흙막이 가시설 공법의 선정 방법에 관한 것으로서 시공 현장의 지질 특성과 관련한 지반 데이터와 건축물의 설계 조건을 고려하여 시공 현장에 매칭되는 흙막이 가시설 공법을 선정하되, 시공 현장에 대응되는 지역의 기상 데이터를 이용하여 기상 요소가 고려된 흙막이 가시설 공법의 선정 방법을 제공하는 것에 제1 목적이, 시공 현장에 설치된 흙막이 가시설을, 센서 모듈을 통해 모니터링을 수행하고, 실시간으로 변위를 계측하여 현장 관리자 단말 측에 보강이 필요한 영역의 보강 작업 정보를 제공하여줄 수 있는 흙막이 가시설 공법의 선정 방법을 제공하는 것에 제2 목적이 있다.The present invention relates to a method for selecting a temporary wall construction method, but considering the ground data related to the geological characteristics of the construction site and the design conditions of the building, the construction of the mud wall construction method matching the construction site is selected, but the weather data of the area corresponding to the construction site. The first object of the present invention is to provide a method of selecting a temporary block construction method considering a weather element by using a sensor module to monitor a temporary block installation installed at a construction site through a sensor module and measure displacement in real time. The second object of the present invention is to provide a method of selecting a temporary block construction method that can provide information on reinforcement work in an area requiring reinforcement.

상술한 목적을 달성하기 위한 본 발명의 설명에 있어서, 이하에서는 첨부된 도면을 참조하여 본 발명을 더욱 구체적으로 설명하기로 한다.In the description of the present invention for achieving the above object, it will be described below in more detail with reference to the accompanying drawings.

이에 도 1을 참조하면, 도 1에서는 본 발명의 일 실시 예에 따른 흙막이 가시설 공법의 선정 방법에 대한 흐름도를 도시하였다.1, FIG. 1 is a flowchart illustrating a method of selecting a clogging construction method according to an embodiment of the present invention.

먼저, 흙막이 가시설이 설치되는 시공 현장에 대한 지반 조사를 수행하여 시공 현장의 지질 특성과 관련한 지반 데이터를 수집하는 지반 데이터 수집 단계(S10)가 수행될 수 있다.First, a ground data collection step (S10) of collecting ground data related to geological characteristics of a construction site by performing a ground survey on a construction site in which an earthquake temporary installation is installed may be performed.

이때, S10 단계에서 수행되는 지반 조사는, 흙막이 가시설의 설치를 위하여 통상적으로 수행되는 흙막이 가시설 공법 선정 및 본조사 내용을 결정하기 위한 예비 조사와, 흙막이 가시설 공법의 설계, 시공 및 유지 관리에 필요한 정보를 얻기 위해 수행되는 본 조사가 수행되는 것으로 이해될 수 있다.At this time, the ground survey carried out in the step S10, the preliminary survey to determine the selection of the earthquake temporary installation method and the content of the main survey that is usually performed for the installation of the earthquake temporary facility, and the information necessary for the design, construction and maintenance of the earthquake temporary facility construction method It can be understood that the present investigation carried out to obtain is carried out.

더욱 구체적인 예로서, 예비 조사의 조사 항목으로서, 입지 조건과 주변 조건, 지형 및 지사, 토질 및 지하수, 매설물 및 장애물, 도로 및 교통 상황 정보가 수집될 수 있으며, 본 조사의 조사 항목으로서 물리 특성, 역학 특성, 압축 특성 및 지하수 특성에 대한 정보가 수집될 수 있다.More specifically, as a survey item of the preliminary survey, location and surrounding conditions, topography and branches, soil and groundwater, landfills and obstacles, road and traffic situation information may be collected, and physical characteristics, Information about mechanical, compressive and groundwater properties can be collected.

즉, 이러한 조사는 하나 이상의 계측 기기로 수행될 수 있으며, S10 단계의 수행에 의하여, 시공 현장 및 시공 현장 주변에 대한 지반 데이터를 수집하여 흙막이 가시설 공법을 선정하는 베이스 자료로서 이용하게 되는 것이다.That is, the survey can be performed with one or more measuring instruments, and by performing the step S10, the ground data for the construction site and the construction site surroundings are collected and used as a base material for selecting the earthquake temporary construction method.

한편, 상술한 S10 단계의 수행 후, 지반 데이터 조건과 건축물의 설계 조건을 고려하여 하나 이상의 흙막이 가시설 공법이 저장되어 있는 데이터베이스 상에서 매칭되는 흙막이 가시설 공법을 선정하는 흙막이 가시설 공법 선정 단계(S20)가 수행될 수 있다.On the other hand, after performing the above-described step S10, in consideration of the ground data conditions and design conditions of the building, the earthquake temporary installation method selection step (S20) of selecting a matching earthquake temporary construction method on the database in which one or more earthquake temporary construction methods are stored is performed. Can be.

이때, 상술한 S20 단계는 상술한 지반 데이터로부터 시공 현장에 요구되는 흙막이 가시설의 최소 내하력을 산출할 수 있는데, 상술한 최소 내하력은 통상적으로 이용되는 단순보법, 연속보법, 탄성보법, 탄소성보법 및 유한요소법 중 적어도 어느 하나를 포함하는 방식으로 산출될 수 있는 것으로 이해될 것이다.At this time, the above-mentioned step S20 can calculate the minimum load capacity of the earthquake temporary installation required for the construction site from the above-described ground data, the above-mentioned minimum load capacity is a simple method, continuous beam, elastic beam, carbon fiber, and It will be appreciated that it can be calculated in a manner that includes at least one of the finite element methods.

또한, 상술한 최소 내하력 산출의 다른 실시 예로서, 본 발명에서는 타 시공 현장에 대한 흙막이 가시설의 설계 이력을 수집하여, 시공 현장의 지반 데이터 조건과, 건축물의 설계 조건이 가장 유사한 타 시공 현장에서 산출된 최소 내하력 값을 이용할 수도 있으며 본 발명은 이에 제한하지 않는다.In addition, in another embodiment of the above-described minimum load carrying capacity calculation, the present invention collects the design history of the temporary wall construction for other construction sites, and calculates the construction data at other construction sites where the ground data conditions of the construction site and the design conditions of the building are most similar. Minimum load capacity values may be used and the present invention is not limited thereto.

상술한 실시 예들에 의하여, 상술한 S20 단계에서 선정되는 흙막이 가시설 공법은, 데이터베이스에 기 저장된 공법들 중 산출된 최소 내하력을 만족하는 흙막이 가시설 공법을 선정하여 제공할 수 있으며, 이에 따라 시공 현장에는, 지반 붕괴의 위험으로부터 안전성이 극대화된 흙막이 가시설이 설치될 수 있게 된다.According to the embodiments described above, the earthquake tent construction method selected in step S20 can be provided by selecting the earthquake tent construction method that satisfies the minimum load capacity calculated from the pre-stored methods in the database, and thus, the construction site, It will be possible to install a temporary screening facility with maximum safety against the risk of ground collapse.

한편, 본 발명에서는 상술한 S20 단계의 수행에 있어서, 시공 현장에 대한 기상 데이터를 더 수집하여 흙막이 가시설 공법의 선정 기준 중 하나로서 이용하는 것이 바람직하다.On the other hand, in the present invention, in performing the above-described step S20, it is preferable that the weather data for the construction site is further collected and used as one of the selection criteria of the temporary wall construction method.

더욱 구체적으로, 흙막이 가시설로 인한 지반 붕괴에는 부실 시공이 가장 큰 문제점으로 지적되고 있으나, 이와 더불어 예기치 못한 우천으로 인한 강수량 증가에 의하여 토압 및 수압이 증가하면서 흙막이 가시설이 붕괴되는 사고가 발상하는 사례 역시 증가하고 있어 해소 방안이 요구되어 왔다.More specifically, the poor construction is pointed out as the biggest problem in the ground collapse due to the earthquake temporary facility.In addition, the case of the accident that the earthquake temporary facility collapses due to the increase of earth pressure and water pressure due to unexpected precipitation increase due to rainy weather. Increasingly, there has been a demand for a solution.

이에 본 발명에서는, 이러한 문제를 해소하기 위하여, 흙막이 가시설 공법의 선정 기준으로서 과거 기상 데이터 및 예측된 기상 데이터 중 적어도 어느 하나를 포함하는 기상 데이터를 이용하여 흙막이 가시설 공법의 선정 기준으로서 이용함으로써 기상 악화에 따른 흙막이 가시설고 관련한 안전 사고를 미연에 방지할 수 있도록 한다. Accordingly, in the present invention, in order to solve such a problem, weather deterioration by using the weather data including at least one of past weather data and predicted weather data as a selection criterion of the clogging temporary construction method as a selection criterion of the clogging temporary construction method To prevent the safety accidents related to the earthquake barriers and related accidents.

이에 대한 제1 실시 예로써, 본 발명에서는, 기상 데이터로서 기상 관측 서버를 통해 수집된 미래의 예측된 기상 데이터를 흙막이 가시설 공법의 선정 기준으로서, 이용할 수 있다. As a first embodiment of this, in the present invention, the future predicted weather data collected through the weather observation server as the weather data can be used as a selection criterion of the clogging construction method.

더욱 구체적인 실시 예로서, 흙막이 가시설의 설치가 예정된 시공 기간이 7월 1일부터 8월 1일이라고 가정해볼 때, 기상 관측 서버에서 미래의 예측된 기상 데이터를 수집한 결과, 시공 기간에 우천이 발생하는 것으로 판단될 시, 흙막이 가시설의 선정 기준을 상향 조정하여 상대적으로 큰 내하력을 갖는 흙막이 시설이 선정되도록 할 수 있는 것이다.As a more specific example, assuming that the construction period scheduled for the installation of the temporary wall temporary facility is from July 1 to August 1, rainy weather occurs during the construction period as a result of collecting the predicted weather data from the weather observation server. If it is judged to be, it is possible to raise the selection criteria of the temporary blocking facility, so that the retaining facility having a relatively large load capacity can be selected.

한편, 상술한 기상 데이터에 대한 제2 실시 예로써, 본 발명에서는 시공 현장에 대한 기상 데이터를 더 수집하여, 흙막이 가시설 공법의 선정 기준 중 하나로 이용하되, 상술한 기상 데이터는 상술한 시공 현장에 대한 과거의 누적된 기상 데이터를 통계적으로 분석하여 도출된 우천 발생 기간에 대한 기상 데이터가 이용될 수 있다.On the other hand, as a second embodiment of the above-described weather data, in the present invention, the weather data for the construction site is further collected, and used as one of the selection criteria of the earthquake temporary construction method, the above-mentioned weather data for the construction site described above Weather data for the period of rainy weather derived by statistically analyzing past accumulated weather data can be used.

더욱 구체적으로, S20 단계의 수행 시점에서부터 과거 10년 이내의 누적된 기상 데이터를 이용하여 우천 발생 기간에 대한 기상 데이터를 도출하고, 이렇게 도출된 우천 발생 기간과, 흙막이 가시설의 설치가 예정된 시공 기간의 중복 구간이 존재하는지 여부를 판단하여, 중복 기간이 존재할 시, 흙막이 가시설의 선정 기준을 상향하여 상대적으로 큰 내하력을 갖는 가시설이 선정되도록 할 수 있는 것이다.More specifically, by using the accumulated weather data within the past 10 years from the time of performing the step S20 to derive the weather data for the period of rainy weather, the resulting rainy weather period, and the construction period of the construction period is scheduled to install By determining whether there is an overlapping section, when there is an overlapping period, it is possible to raise the selection criteria for the temporary block installation and to select a provisional facility having a relatively large load capacity.

즉, 상술한 제1 실시 예 및 제2 실시 예에서 살펴본 바와 같이, 본 발명에서는 흙막이 가시설의 선정 기준으로서 기상 데이터를 더 고려함에 따라서, 흙막이 가시설이 설치되는 기간 중 강수량이 늘어나 토압 및 수압이 증가하고, 지반의 물리적 상태가 변동되더라도, 이에 대하여 충분히 견뎌낼 수 있는 흙막이 가시설을 제공할 수 있는 효과가 있다.That is, as described in the above-described first and second embodiments, the present invention further considers the weather data as a selection criterion for the earthquake tent installation, so that the precipitation increases during the period in which the tent tent installation facility is installed, and the earth pressure and the water pressure increase. In addition, even if the physical state of the ground is changed, there is an effect that can provide a temporary block capable of withstanding this.

또 다른 한편, 상술한 S20 단계의 또 다른 실시 예로서, S20 단계에 선정된 흙막이 가시설의 실제 설치 시공을 수행하는 시공 인력 단말에는, 선정된 흙막이 가시설 공법에 요구되는 자재 정보, 시공 순서 및 시공 유의사항 정보 중 적어도 어느 하나를 포함하는 시공 안내 콘텐츠가 제공될 수 있다.On the other hand, as another embodiment of the above-described step S20, the construction manpower terminal performing the actual installation and construction of the earthwork temporary installation selected in step S20, material information, construction order and construction attention required for the selected earthwork temporary installation method Construction guide content including at least one of the item information may be provided.

더욱 구체적으로 선정된 흙막이 가시설 공법에 대한 자재 정보로서, 에측된 자재 종류 및 수량에 대한 정보가 제공될 수 있으며, 흙막이 가시설의 설치 프로세스를 나타내는 시공 순서 및 선정된 흙막이 가시설 공법의 유의 사항 정보가 제공될 수 있는 것이다.More specifically, the material information for the selected mud tent construction method can be provided, and information on the type and quantity of the measured materials can be provided, and the construction order showing the installation process of the mud tent temporary facility and information on the notice of the selected mud tent temporary construction method are provided. It can be.

상술한 시공 안내 콘텐츠는 시공 인력 단말의 출력 수단에서 출력 가능한 텍스트, 이미지 및 영상 중 적어도 어느 하나를 포함하는 형태로서 출력 제공될 수 있다.The above-described construction guide content may be provided as an output including at least one of a text, an image, and an image output from the output means of the construction manpower terminal.

이때, 상술한 실시 예의 더욱 바람직한 실시 예로서, 시공 인력의 시공 이해도를 더욱 극대화하기 위한 수단으로, 선정된 흙막이 가시설 공법에 대한 타 시공 현장을 촬영한 영상 콘텐츠로서 제공하는 것이 바람직하며, 이에 따라 시공 인력의 시공 실수를 최소화하여 부실 시공을 방지할 수 있게 되는 효과가 있다.At this time, as a more preferred embodiment of the above-described embodiment, as a means for further maximizing the construction comprehension of the construction personnel, it is preferable to provide as a video content photographing the other construction site for the selected earth block temporary construction method, and thus construction There is an effect that it is possible to prevent poor construction by minimizing the construction mistakes of manpower.

한편, 상술한 S20 단계의 수행 후, 선정된 흙막이 가시설 공법을 기초로 시공 현장에 흙막이 가시설의 설치 시공을 수행하되, 흙막이 가시설의 일 영역에는 하나 이상의 센서 모듈이 설치되도록 하여 센서 모듈로부터 흙막이 가시설의 변위를 계측하여 모니터링을 수행하는 모니터링 단계(S30)가 수행될 수 있다.On the other hand, after performing the above-described step S20, on the basis of the selected earthquake provisional construction method to perform the installation of the earthquake provisional installation on the construction site, one or more sensor modules are installed in one area of the earthquake provisional facility to install the earthquake temporary installation from the sensor module Monitoring step (S30) for measuring by measuring the displacement can be performed.

이때, 흙막이 가시설에 설치되는 센서 모듈은, 예를 들어 지중 경사계, 침하계, 하중계, 지하 수위계, 변형률계, 수압계 및 토압계 중 적어도 어느 하나를 포함하는 센서 모듈로 이해될 것이다.At this time, the sensor module installed in the earthquake tent installation, for example, will be understood as a sensor module including at least any one of the underground inclinometer, settlement system, load gauge, underground water gauge, strain gauge, hydraulic pressure gauge and earth pressure gauge.

일 예로써, 상술한 지중 경사계는, 흙막이 가시설의 배면의 하부 지층까지 설치하여 수평 변위를 계측할 수 있도록 하는 것이 바람직하다.As an example, it is preferable that the above-described underground inclinometer is installed up to the lower strata of the rear surface of the earthenware temporary facility so that the horizontal displacement can be measured.

또한 지하 수위계 역시 흙막이 가시설의 배면에 설치하여 시공 현장 주변의 지하 수위 거동을 측정할 수 있도록 하는 것이 좋고, 변형률계는 지보 수단인 버팀보에 설치하여 버팀보에 작용하는 응력이 측정될 수 있도록 설치되는 것이 바람직하다.In addition, it is recommended that the underground water gauge be installed on the back of the earthquake temporary facility so that the ground water level behavior around the construction site can be measured, and the strain gauge is installed in the brace, which is the supporting means, so that the stress acting on the brace can be measured. desirable.

또한, 침하계는, 흙막이 가시설의 배면 및 시공 현장과 인접한 구조물이 위치한 지반에 설치하여 지반의 침하를 측정할 수 있도록 하는 것이 바람직하며, 하중계, 수압계 및 토압계는, 흙막이 가시설의 벽체에 설치되어, 벽체에 인가되는 하중, 수압, 및 토압을 측정할 수 있도록 하는 것이 좋다.In addition, it is preferable that the settlement system is installed on the ground where the structure adjacent to the backside and construction site of the earthquake temporary facility is located so that the settlement of the ground can be measured, and the load gauge, the hydraulic pressure gauge and the earth pressure gauge are installed on the wall of the earthquake temporary facility. It is good to be able to measure the load, hydraulic pressure, and earth pressure applied to the wall.

한편, 본 발명의 더욱 바람직한 실시 예에 있어서, 상술한 센서 모듈은, 흙막이 가시설이 설치되는 시공 현장을 기준으로 기 설정된 반경 내에 존재하는 주변 현장에 더 설치되도록 할 수 있다.On the other hand, in a more preferred embodiment of the present invention, the above-described sensor module, it is possible to be further installed in the surrounding site existing within a predetermined radius on the basis of the construction site where the earthquake temporary installation is installed.

즉, 본 발명에서는 이러한 하나 이상의 센서 모듈에 의하여 계측되는 변위 데이터를 현장 관리자 단말에서 실시간 모니터링이 가능하도록 하여 시공 현장에 대한 안전 관리를 더욱 체계적으로 수행할 수 있다.That is, in the present invention, the displacement data measured by the at least one sensor module can be monitored in real time in the field manager terminal, so that safety management of the construction site can be more systematically performed.

또한, 상술하였듯이 S30 단계에서는 시공 현장의 지반은 물론이고 인접 구조물이 위치한 지반 중 적어도 어느 하나를 포함하는 지반의 변위 계측을 통한 모니터링이 가능해져 시공 현장과 인접 지역에 대한 안전 사고 대비를 더욱 철저히 수행할 수 있게 되는 효과가 있다.In addition, as described above, in the step S30, monitoring can be performed by measuring displacement of the ground including at least one of the ground where the adjacent structure is located as well as the construction site, thereby more thoroughly preparing for safety accidents in the construction site and the adjacent area. There is an effect that can be done.

한편, 상술한 S30 단계의 수행 후, 계측된 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단될 시, 현장 관리자 단말에 흙막이 가시설에 요구되는 보강 작업 정보를 제공하는 보강 작업 정보 제공 단계(S40)가 수행될 수 있다.On the other hand, after performing the above-described step S30, when it is determined that the measured displacement of the temporary tent equipment is out of the preset maximum allowable displacement amount, reinforcement work information providing step of providing the reinforcement work information required for the temporary tent facility to the site manager terminal ( S40) may be performed.

더욱 구체적으로, 앞서 언급한 센서 모듈에는 센서 모듈마다 기 설정된 최대 허용 변위량이 설정되어 있는 것으로서, 이에 따라 상술한 S40 단계에서는 센서 모듈로부터 계측된 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단되는 대상에 대한 보강 작업 정보를 제공할 수 있게 된다.More specifically, in the above-described sensor module, the preset maximum allowable displacement amount is set for each sensor module. Accordingly, in the above-described step S40, it is determined that the displacement of the temporary facility measured from the sensor module is out of the preset maximum allowable displacement amount. It is possible to provide information on reinforcement work for the target.

예를 들어 하중계에 설정된 최대 허용 변위량이 +5ton이고, 실시간으로 계측된 하중이 +5.1ton일 경우, 하중 분산을 위한 흙막이 가시설의 벽체 보강 혹은 지보 수단의 보강에 대한 작업 정보를 현장 관리자 단말에 제공할 수 있게 되는 것이다.For example, if the maximum allowable displacement set in the load gauge is +5 tons and the load measured in real time is +5.1 tons, the site manager terminal provides work information on the reinforcement of the wall of the retaining wall or reinforcement of the supporting means for load distribution. You can do it.

이때, 상술한 보강 작업 정보는, 앞서 흙막이 가시설 공법의 선정되어 제공되는 예와 마찬가지로, 실제 보강 시공을 수행하는 시공 인력 단말에 보강 작업에 대한 시공 안내 콘텐츠를 더 제공할 수도 있으며, 본 발명은 이에 제한하지 않는다.At this time, the above-mentioned reinforcement work information, as in the above example provided by the selection of the temporary block construction method, may further provide a construction guide content for the reinforcement work to the construction manpower terminal performing the actual reinforcement construction, the present invention is Do not limit.

또한, 상술한 S40 단계의 더욱 바람직한 실시 예로서, 센서 모듈에 의하여 실시간으로 계측되는 변위량이 기 설정된 최대 허용 변위량을 초과하거나, 최대 허용 변위량을 초과하는 것에 임박한 것으로 판단되는 경우, 이러한 위기 상황을 알리기 위한 알림 메시지를 현장 관리자 단말에 송출하고, 이에 대한 즉각적이 대응이 수행되도록 함이 바람직할 것이다.In addition, as a more preferred embodiment of the above-described step S40, when the displacement amount measured in real time by the sensor module is determined to exceed the maximum allowable displacement amount, or to exceed the maximum allowable displacement amount, to inform the crisis situation It is desirable to send a notification message for the field manager terminal, and to immediately respond to this.

종합적으로, 상술한 S10 내지 S40 단계의 수행에 의하여, 시공 현장에 대한 과거 및 예측된 기상데이터를 이용하여 흙막이 가시설 공법을 선정하게 됨에 따라서, 지반 조사 시점 이후, 단기간에 강우량이 많아져 토압 및 수압이 증대되더라도 증대된 토압 및 수압의 측압에 저항할 수 있는 흙막이 가시설을 제공할 수 있게 되는 효과가 있다.Overall, by performing the above-described step S10 to S40, as the soil barrier construction method is selected by using the past and predicted weather data for the construction site, the rainfall is increased in the short term after the ground survey time, the earth pressure and water pressure Even if this is increased, there is an effect that it is possible to provide a temporary block capable of resisting the increased earth pressure and lateral pressure of the hydraulic pressure.

또한, 본 발명의 일 실시 예에 따르면, 시공 현장에 설치된 흙막이 가시설을, 센서 모듈을 통해 모니터링을 수행하여 원격지에서도 흙막이 가시설의 관리가 가능해지는 효과가 있으며, 실시간으로 변위를 계측하여 현장 관리자 단말 측에 보강이 필요한 영역의 보강 작업 정보를 제공하여 줌에 따라서 흙막이 가시설의 안정성이 극대화되는 효과가 있다.In addition, according to an embodiment of the present invention, by monitoring through the sensor module module installed in the construction site, through the sensor module has the effect that it is possible to manage the construction of the temporary block from a remote location, by measuring the displacement in real time on the site manager terminal side By providing information on reinforcement work in areas that require reinforcement, the stability of the temporary shelter facility can be maximized.

또한, 본 발명의 일 실시 예에 따르면, 시공 현장은 물론이고, 시공 현장에 인접한 인접 구조물의 변위 계측을 통한 모니터링을 수행하여, 지반 공사 수행 시 발생할 수 있는 각종 안전 사고를 미연에 방지할 수 있게 되는 효과가 있다.In addition, according to an embodiment of the present invention, as well as the construction site, by performing the monitoring by measuring the displacement of the adjacent structure adjacent to the construction site, it is possible to prevent various safety accidents that may occur when performing the ground work in advance. It is effective.

또한, 본 발명의 일 실시 예에 따르면, 선정된 흙막이 가시설 공법에 대한 시공 안내 콘텐츠를 시공 인력 단말에 제공하여, 체계적인 시공이 수행되도록 하며, 시공 유의사항을 상기 시켜 시공 인력의 시공 실수를 최소화할 수 있게 되어 시공 품질 저하를 미연에 방지할 수 있는 효과가 있다.In addition, according to an embodiment of the present invention, by providing the construction guide content for the selected earth block temporary construction method to the construction manpower terminal, so that systematic construction is carried out, by reminding the construction notes to minimize the construction mistakes of construction personnel It is possible to prevent the deterioration in construction quality in advance.

이상과 같이 실시 예들이 비록 한정된 실시 예와 도면에 의해 설명되었으나, 해당 기술 분야에서 통상의 지식을 가진 자라면 상기의 기재로부터 다양한 수정 및 변형이 가능하다.Although the embodiments have been described with reference to the limited embodiments and the drawings as described above, various modifications and variations are possible to those skilled in the art from the above description.

도 2에서는 본 발명의 일 실시 예에 따라 수집된 지반 데이터를 기초로 흙막이 가시설 공법이 선정되어 제공되는 일 예가 도시되어 있으며, 이하의 설명에 있어서 도 1에 대한 설명과 중복되는 불필요한 실시 예에 대한 설명은 생략하기로 한다.FIG. 2 illustrates an example in which an earthquake temporary construction method is selected and provided based on ground data collected according to an embodiment of the present invention. In the following description, an unnecessary embodiment overlapping with the description of FIG. 1 will be described. The description will be omitted.

도 2의 100을 참조하면, 수집된 지반 데이터 조건과 건축물의 설계 조건을 기초로 한 시공 영역 지반 특성 정보(1001)가 도시되어 있다.Referring to 100 of FIG. 2, construction area ground characteristic information 1001 is illustrated based on collected ground data conditions and building design conditions.

이때, 상술한 지반 특성 정보(1001)는 도시된 지반의 강도, 지하 수위, 시공 영역 면적 외에도, 지층 종류, 심도, 암석 일측 강도, 공내 재하, 공내 전단, 시추공영상 촬영 중 적어도 어느 하나를 포함하는 지반 조사 결과에 따른 정보가 제공되는 것으로 이해될 것이다.In this case, the above-described ground property information 1001 includes at least one of ground strength, underground water level, construction area area, ground layer type, depth, rock strength on one side, in-vehicle loading, in-hole shearing, and borehole imaging. It will be appreciated that information will be provided based on the results of the soil survey.

한편 이러한 조사 결과를 종합하여, 본 발명에서는 최소 내하력을 도출하고, 도출된 최소 내하력을 만족하는 공법을 선정하여 공법 매칭 결과(1002)로서 제공할 수 있게 된다.On the other hand, by combining the results of the investigation, the present invention can derive the minimum load capacity, select a method that satisfies the derived minimum load capacity can be provided as a method matching result 1002.

즉, 도 2의 화면 100에서의 실시 예에서는 시공 영역의 특성을 고려하여 선정된 공법으로서, 벽체는, C.I.P(Cast In Place Pile)이, 지보 방식으로는 Strut 방식(버팀보 방식)이 선정된 것을 알 수 있다.That is, in the embodiment of the screen 100 of FIG. 2, as the construction method selected in consideration of the characteristics of the construction area, CIP (Cast In Place Pile) is selected as the wall, and the Strut method is selected as the support method. Able to know.

한편 상술한 데이터베이스에는, 예를 들어, 흙막이 벽체로서 H-Pile 및 흙막이판 공법, CIP 공법, SCW 공법, 지하 연속벽 공법이, 지보 수단으로서 자립공법, 역타 공법, 버팀보 공법, 앵커 공법, 소일네일링 공법, 레이커 공법에 대한 공법 정보가 저장되어 있을 수 있으며, 바람직하게는, 흙막이 벽체와, 지보 수단의 조합에 의한 각각의 최소 내하력이 산출되어 관리되도록 함으로써, 앞서 시공 영역에 대하여 산출된 최소 내하력을 만족하는 흙막이 가시설 공법을 선정하여 제공할 수 있게 된다.On the other hand, the above-mentioned database includes, for example, H-Pile and cladding method, CIP method, SCW method, underground continuous wall method as a retaining wall, self-supporting method, reverse punching method, butt beam method, anchor method, small nail as a supporting means. The method information for the ring method and the raker method may be stored. Preferably, the minimum load capacity calculated for the construction area is calculated by managing and calculating the minimum load capacity by the combination of the retaining wall and the support means. It will be possible to select and provide a temporary block construction method that satisfies the requirements.

이상과 같이 실시 예들이 비록 한정된 실시 예와 도면에 의해 설명되었으나, 해당 기술 분야에서 통상의 지식을 가진 자라면 상기의 기재로부터 다양한 수정 및 변형이 가능하다.Although the embodiments have been described with reference to the limited embodiments and the drawings as described above, various modifications and variations are possible to those skilled in the art from the above description.

도 3에서는 본 발명의 일 실시 예에 따라 수집된 기상 데이터에 따라 흙막이 가시설의 선정 기준이 상향 조정되는 일 예가 도시되어 있으며, 이하의 설명에 있어서 도 1 및 2에 대한 설명과 중복되는 불필요한 실시 예에 대한 설명은 생략하기로 한다.FIG. 3 illustrates an example in which a selection criterion of an earthquake temporary facility is upwardly adjusted according to weather data collected according to an embodiment of the present invention. In the following description, an unnecessary embodiment overlaps with the description of FIGS. 1 and 2. Description of the description will be omitted.

한편 도3의 화면 110A 및 110B를 참조하면, 양 실시 예 모두 다 기상 데이터를 더 수집하여 흙막이 가시설 공법을 선정하는 예를 도시하였으나, 110A에서는 흙막이 가시설 설치 기간 중 우천 확률이 상대적으로 낮은 경우, 110B에서는 흙막이 가시설 설치 기간 중 우천 확률이 상대적으로 높은 경우에 대한 실시 예를 각각 도시하였다. Meanwhile, referring to the screens 110A and 110B of FIG. 3, both examples show an example in which a weather barrier construction method is selected by collecting more weather data. However, in 110A, when the rain probability is relatively low during the installation period, 110B In FIG. 3, examples of the case where the rain probability is relatively high during the installation period of the temporary wall facility are shown.

이에 양 실시 예를 비교하여보면, 동일한 지반 데이터 조건을 갖는 시공 영역에 있어서, 우천 확률이 상대적으로 낮은 실시 예인 110A에서는 공법 매칭 결과로서, 벽체는 C.I.P, 지보 방식은 strut가 선정된 반면, 우천 확률이 상대적으로 높은 실시 예인 110B에서는 공법 매칭 결과로서 벽체는 강널 말뚝이, 지보 방식은 Anchor가 선정됨을 알 수 있다.Comparing the two embodiments, in the construction area having the same ground data conditions, in the case of 110A, which is an embodiment with a relatively low rain probability, as a method matching result, the wall is CIP, the strut is selected as the support method, while the rain probability is selected. In the relatively high embodiment 110B, as a result of the method matching, it can be seen that the steel plate is selected as the pile and the anchor is selected as the anchor.

이때, 강널 말뚝과 지보 방식은 C.I.P 및 strut에 비하여 상대적으로 자재의 단면 강성이 크고, 우수한 항복 응력 및 토압 저항력을 가진 자재인 것으로 이해될 것이다.At this time, the steel sheet pile and support method will be understood to be a material having a relatively large cross-sectional stiffness, excellent yield stress and earth pressure resistance compared to C.I.P and strut.

즉, 본 발명에서는 시공 현장에 대하여 흙막이 가시설이 설치되는 기간 중의 기상 상황을 고려하여, 흙막이 가시설 선정 공법의 선정 기준을 상향할지 여부를 결정함에 따라서, 지반 조사 시점 이후, 단기간에 강우량이 많아져 토압 및 수압이 증대되더라도 증대된 토압 및 수압의 측압에 저항할 수 있는 흙막이 가시설을 제공할 수 있게 되는 효과가 있다.That is, in the present invention, considering the weather conditions during the period when the temporary wall installations are installed in the construction site, whether to increase the selection criteria of the temporary wall construction selection method, the rainfall is increased in a short period of time after the ground investigation, the earth pressure And even if the water pressure is increased, there is an effect that it is possible to provide a temporary block that can resist the increased earth pressure and side pressure of the water pressure.

한편, 도 3의 실시 예에서는 기상 데이터로서 예측된 기상 데이터를 이용하는 실시 예에 한정하여 설명하였으나, 앞서 언급한 바와 같이 기상 데이터는 과거의 누적된 기상 데이터를 통계적으로 분석하여 도출된 우천 발생 기간에 대한 기상 데이터가 이용될 수도 있으며 본 발명은 이에 제한하지 않는다.Meanwhile, in the embodiment of FIG. 3, the present invention has been described with reference to an embodiment using weather data predicted as weather data. However, as mentioned above, the weather data may be generated during a rain occurrence period derived by statistically analyzing past accumulated weather data. Weather data may also be used and the present invention is not so limited.

이상과 같이 실시 예들이 비록 한정된 실시 예와 도면에 의해 설명되었으나, 해당 기술 분야에서 통상의 지식을 가진 자라면 상기의 기재로부터 다양한 수정 및 변형이 가능하다.Although the embodiments have been described with reference to the limited embodiments and the drawings as described above, various modifications and variations are possible to those skilled in the art from the above description.

도 4에서는 본 발명의 일 실시 예에 따라 흙막이 가시설에 설치된 센서 모듈에 의하여 흙막이 가시설의 변위가 모니터링 되는 일 예가 도시되어 있으며, 이하의 설명에 있어서 도 1 내지 3에 대한 설명과 중복되는 불필요한 실시 예에 대한 설명은 생략하기로 한다.In FIG. 4, an example in which the displacement of the retaining facility is monitored by a sensor module installed in the retaining facility according to an embodiment of the present invention is illustrated. In the following description, an unnecessary embodiment overlaps with the description of FIGS. 1 to 3. Description of the description will be omitted.

도 4의 화면 140을 참조하면, 현장 관리자 단말에는 흙막이 가시설의 일 영역 및 흙막이 가시설과 인접하게 설치된 센서 모듈에 의하여 시공 현장에 대한 모니터링 결과(1201)와 시공 현장과 인접한 구조물에 대한 실시간 모니터링 결과(1202)가 제공될 수 있다.Referring to screen 140 of FIG. 4, the site manager terminal includes a monitoring result 1201 for a construction site and a real-time monitoring result for a structure adjacent to the construction site by a sensor module installed adjacent to one area of the temporary wall facility and the temporary wall facility. 1202) may be provided.

이때, 모니터링 결과는, 흙막이 가시설의 시공 시점을 기준으로 증가되거나 감소된 변위량에 대한 정보가 제공되는 것으로 이해될 것이다.At this time, the monitoring results, it will be understood that the information on the amount of displacement increased or decreased based on the construction time of the temporary block installation.

한편, 모니터링에 대한 더욱 바람직한 실시 예로써, 모니터링 결과를 현장 관리자 단말에 제공함에 있어서, 센서 모듈에 의해 계측된 변위량을 기 설정된 최대 허용 변위량과 비교하여, 그 근접 정도에 따라 안전, 주의 요망, 위험 중 적어도 어느 하나에 해당하는 상태 정보를 더 제공하여 줄 수도 있으며, 본 발명은 이에 제한하지 않는다. On the other hand, in a more preferred embodiment of the monitoring, in providing the monitoring results to the field manager terminal, the displacement measured by the sensor module compared with the preset maximum allowable displacement, safety, attention, risk according to the proximity It is also possible to further provide status information corresponding to at least one of the present invention, but the present invention is not limited thereto.

이상과 같이 실시 예들이 비록 한정된 실시 예와 도면에 의해 설명되었으나, 해당 기술 분야에서 통상의 지식을 가진 자라면 상기의 기재로부터 다양한 수정 및 변형이 가능하다.Although the embodiments have been described with reference to the limited embodiments and the drawings as described above, various modifications and variations are possible to those skilled in the art from the above description.

도 5에서는 본 발명의 일 실시 예에 따라 현장 관리자 단말에 보강 작업 정보가 제공되는 일 예가 도시되어 있으며, 이하의 설명에 있어서 도 1 내지 4에 대한 설명과 중복되는 불필요한 실시 예에 대한 설명은 생략하기로 한다.In FIG. 5, an example in which reinforcement work information is provided to a site manager terminal according to an embodiment of the present invention is illustrated. In the following description, a description of unnecessary embodiments overlapping with the description of FIGS. 1 to 4 is omitted. Let's do it.

이에 도 5에 도시된 화면 130을 참조하면, 보강 작업에 대한 정보를 제공하는데 앞서, 본 발명에서는, 흙막이 가시설의 일 영역 혹은 흙막이 가시설과 인접한 영역에 설치된 센서 모듈에 의하여 계측된 모니터링 결과(1301)를 제공하여줄 수 있다.Referring to the screen 130 illustrated in FIG. 5, prior to providing information on the reinforcement work, in the present invention, the monitoring result 1301 measured by the sensor module installed in one region of the earthenware temporary facility or an area adjacent to the earthenware temporary facility Can provide.

한편 모니터링 결과(1301)로 출력되는 데이터는, 센서 모듈에서 계측된 변위량에 있어서, 기 설정된 최대 허용 변위량을 초과하는 값을 가진 영역에 대한 정보가 출력되는 것으로 이해될 수 있으며, 이에 따라 보강이 요구되는 영역에 대한 보강 작업 정보(1302)를 생성할 수 있게 된다.On the other hand, the data output as the monitoring result 1301, it can be understood that in the displacement amount measured in the sensor module, information about the region having a value exceeding the preset maximum allowable displacement amount is output, so that reinforcement is required. It is possible to generate the reinforcement work information 1302 for the area to be.

더욱 구체적인 실시 예로서 도 5의 화면 130을 예로 들면, 모니터링 결과(1301)로서 토사 하중이 증가 함에 따라 보강 작업이 필요성이 요구되고 있으며, 본 발명에서는 보강 작업 정보(1302)로서 흙막이 가시설의 설치 영역에 중간 말뚝을 추가하는 보강 작업을 지시하여 증가한 토사 하중에 대한 대응 방안을 제공하고 있음을 알 수 있다.As a more specific embodiment, taking the screen 130 of FIG. 5 as an example, as the monitoring result 1301, as the soil load increases, the reinforcement work is required, and in the present invention, the installation area of the clogging facility as the reinforcement work information 1302 is provided. It can be seen that it provides a countermeasure against increased soil load by directing reinforcement work to add intermediate piles.

즉 상술한 실시 예와 같이, 센서 모듈에 의해 실시간으로 변위를 계측하여 현장 관리자 단말 측에 보강이 필요한 영역의 보강 작업 정보를 제공하여 줌에 따라서 흙막이 가시설의 설치 안정성이 극대화되는 효과가 있다.That is, as in the above-described embodiment, by measuring the displacement in real time by the sensor module to provide the reinforcement work information of the area that needs to be reinforced to the field manager terminal side, there is an effect that the installation stability of the masonry temporary facility is maximized.

이상과 같이 실시 예들이 비록 한정된 실시 예와 도면에 의해 설명되었으나, 해당 기술 분야에서 통상의 지식을 가진 자라면 상기의 기재로부터 다양한 수정 및 변형이 가능하다.Although the embodiments have been described with reference to the limited embodiments and the drawings as described above, various modifications and variations are possible to those skilled in the art from the above description.

도 6에서는 본 발명의 일 실시 예에 따라 시공 인력 단말에 시공 안내 콘텐츠가 제공되는 일 예가 도시되어 있으며, 이하의 설명에 있어서 도 1 내지 5에 대한 설명과 중복되는 불필요한 실시 예에 대한 설명은 생략하기로 한다.6 illustrates an example in which construction guide content is provided to a construction manpower terminal according to an embodiment of the present invention, and description of unnecessary embodiments overlapping with the description of FIGS. 1 to 5 will be omitted in the following description. Let's do it.

이에 도 6을 참조하면, 시공 인력 단말에는 도 6에 도시된 화면 140과 같은 선정된 흙막이 가시설에 대한 시공 안내 콘텐츠가 제공될 수 있다.Thus, referring to FIG. 6, the construction manpower terminal may be provided with construction guide content for the selected earth block temporary facility such as the screen 140 illustrated in FIG. 6.

이때 상술한 시공 안내 콘텐츠는, 앞서 언급한 바와 같이, 텍스트, 이미지 및 영상 중 적어도 어느 하나를 포함하는 형태로 제공될 수 있으며, 140에서는 텍스트와 영상을 포함하는 형태로 제공되는 시공 안내 콘텐츠가 도시되어 있음을 확인할 수 있다.In this case, as described above, the construction guide content may be provided in a form including at least one of a text, an image, and an image, and at 140, the construction guide content is provided in a form including a text and an image. It can be confirmed.

한편, 시공 안내 콘텐츠에는, 선정된 흙막이 가시설 공법에 대한 정보와, 이에 대한 세부 정보로서 1401에 표현된 바와 같이, 시공 순서가 제공될 수 있다.Meanwhile, the construction guide content may be provided with information on the selected earthquake provisional construction method and a construction order, as expressed in 1401 as detailed information thereof.

또한, 이러한 시공 순서와 더불어, 더욱 자세한 시공 정보를 제공하기 위하여, 시공과 관련한 타 시공 현장에서 촬영된 실제 시공 영상 데이터(1402)가 더 제공될 수도 있다. In addition, in addition to the construction order, in order to provide more detailed construction information, actual construction image data 1402 taken at another construction site related to construction may be further provided.

또한, 이와 더불어 시공 안내 콘텐츠에는 선정된 흙막이 가시설 공법의 시공 유의사항(1403)을 더 제공하여 줄 수 있으며, 이에 따라 체계적인 시공이 수행되도록 하며, 시공 유의사항을 상기 시켜 시공 인력의 시공 실수를 최소화할 수 있게 되어 시공 품질 저하를 미연에 방지할 수 있는 효과가 있다.In addition, the construction guide content can be further provided with the construction precautions (1403) of the selected earthquake provisional construction method, accordingly to ensure that the construction is carried out, and to remind the construction precautions to minimize the construction mistakes of construction personnel It is possible to prevent the deterioration of the construction quality in advance can have an effect.

이상과 같이 실시 예들이 비록 한정된 실시 예와 도면에 의해 설명되었으나, 해당 기술 분야에서 통상의 지식을 가진 자라면 상기의 기재로부터 다양한 수정 및 변형이 가능하다.Although the embodiments have been described with reference to the limited embodiments and the drawings as described above, various modifications and variations are possible to those skilled in the art from the above description.

도 7에서는 본 발명의 일 실시 예에 따른 흙막이 가시설 공법의 선정 장치(10)에 대한 구성도가 도시되어 있으며, 이하의 설명에 있어서 도 1 내지 6에 대한 설명과 중복되는 불필요한 실시 예에 대한 설명은 생략하기로 한다.In FIG. 7 is a block diagram of the selection device 10 of the earthquake temporary construction method according to an embodiment of the present invention, in the following description of the unnecessary embodiment that overlaps with the description for Figures 1 to 6 Will be omitted.

도 7에 도시된 바와 같이, 본 발명에서 개시하는 하나 이상의 프로세서 및 상기 프로세서에서 수행 가능한 명령들을 저장하는 하나 이상의 메모리를 포함하는 컴퓨팅 장치(10)로 구현되는 흙막이 가시설 공법의 선정 장치(10)는, 바람직하게 지반 데이터 수집부(11), 흙막이 가시설 공법 선정부(12), 모니터링부(13) 및, 보강 작업 정보 제공부(14)를 포함할 수 있다.As illustrated in FIG. 7, the apparatus 10 for selecting a clogging construction method implemented by the computing device 10 including one or more processors and one or more memories for storing instructions that may be executed by the processor may be provided. Preferably, the ground data collection unit 11, earthquake temporary construction method selection unit 12, the monitoring unit 13, and may include a reinforcement work information providing unit (14).

이때, 상술한 지반 데이터 수집부(11)는, 흙막이 가시설이 설치되는 시공 현장에 대한 지반 조사를 수행하여 시공 현장의 지질 특성과 관련된 지반 데이터를 수집하는 기능을 수행하게 되는데, 이때 상술한 지반 데이터 수집부(11)는, 하나 이상의 지반 조사 장비(20)(계측 기기)로부터 측정되는 측정값을 입력 받아 지반 데이터로 수집할 수 있게 되는 것이다.At this time, the above-described ground data collection unit 11 performs a ground survey on the construction site where the earthquake temporary installation is installed to perform the function of collecting ground data related to the geological characteristics of the construction site. The collection unit 11 is to be able to receive the measured value measured from one or more ground survey equipment 20 (measurement device) to collect as ground data.

즉 상술한 지반 데이터 수집부(11)는 앞서 도 1의 S10 단계가 수행하는 기능을 모두 수행 가능한 것으로 이해될 수 있으며, 이에 따라 시공 현장 및 현장 주변에 대한 지반 데이터가 수집되게 됨에 따라서 후술할 흙막이 가시설 공법 선정부(12)의 베이스 자료로서 이용될 수 있게 된다.That is, the above-described ground data collector 11 may be understood to be capable of performing all the functions performed by the step S10 of FIG. 1, and thus ground data to be described later will be collected as the ground data for the construction site and the site surroundings are collected. It can be used as the base material of the temporary construction method selection unit 12.

한편 상술한 흙막이 가시설 공법 선정부(12)는, 앞서 지반 데이터 수집부(11)에서 수집한 지반 데이터 조건과 건축물의 설계 조건을 고려하여 하나 이상의 흙막이 가시설 공법이 저장되어 있는 데이터베이스(30) 상에서 매칭되는 흙막이 가시설 공법을 선정하는 기능을 수행한다.On the other hand, the above-mentioned earthquake temporary construction method selection unit 12 is matched on the database 30 in which one or more earthquake temporary construction methods are stored in consideration of the ground data conditions collected by the ground data collection unit 11 and the design conditions of the building. This function is to select the temporary block construction method.

즉, 상술한 흙막이 가시설 공법 선정부(12)는, 앞서 도 1에서 언급한 S20 단계가 수행하는 기능을 모두 수행 가능한 것으로 이해될 수 있으며, 이에 따라, 과거 및 미래 시점 중 적어도 어느 하나로부터 예측된 기상 데이터를 고려한 흙막이 가시설 공법을 선정할 수 있게 된다.That is, the above-described brick wall construction method selection unit 12 may be understood to be capable of performing all of the functions performed by the step S20 mentioned in FIG. 1, and thus, may be predicted from at least one of past and future time points. It is possible to select the temporary block construction method considering the weather data.

이에 따라, 본 발명에서는 단순히 지반 조사 시점의 지반 상태만을 고려한 것이 아닌, 우천으로 인하여 토양의 물리적 특성의 변화가 발생한 경우까지 고려하여 도출된 최소 내하력을 만족하는 흙막이 가시설 공법이 선정될 수 있으며, 이러한 이유로, 흙막이 가시설의 부실 시공에 의한 지반 붕괴 위험성이 현저히 저감된 흙막이 가시설이 설치될 수 있는 효과가 있다.Accordingly, in the present invention, not only considering the ground state at the time of the ground survey, but also considering the case of the change in the physical properties of the soil due to the rain can be selected a temporary barrier construction method that satisfies the minimum load capacity derived from, For this reason, there is an effect that the earthquake provisional facility in which the risk of ground collapse due to poor construction of the earthquake provisional facility is significantly reduced can be installed.

또한 이와 더불어, 상술한 흙막이 가시설 공법 선정부(12)는, 시공 인력 단말에 선정된 흙막이 가시설 공법에 대한 시공 안내 콘텐츠를 더 제공하여줄 수도 있으며 본 발명은 이에 제한하지 않는다. In addition, the above-described earthwork temporary construction method selection unit 12 may further provide a construction guide content for the earthwork temporary construction method selected in the construction manpower terminal, but the present invention is not limited thereto.

한편 상술한 모니터링부(13)는, 흙막이 가시설 공법을 기초로 시공 현장에 흙막이 가시설의 설치 시공을 수행하되, 흙막이 가시설의 일 영역에는 하나 이상의 센서 모듈(50)이 설치되도록 하여 센서 모듈(50)로부터 흙막이 가시설의 변위를 계측하여 모니터링하는 기능을 수행한다.On the other hand, the above-described monitoring unit 13, the installation of the earthquake temporary installation on the construction site based on the earthquake temporary construction method, one or more sensor modules 50 to be installed in one area of the earthquake temporary installation sensor module 50 It measures and monitors displacement of earthquake tents.

즉, 상술한 모니터링부(13)는, 앞서 도 1에서 언급한 S30 단계가 수행하는 기능을 모두 수행 가능한 것으로 이해될 수 있으며, 이에 따라, 시공 현장에 대한 안전 관리를 더욱 체계적으로 수행할 수 있게 됨은 물론이고, 시공 현장과 인접한 구조물이 설치된 지반에 대한 모니터링이 가능해져 안전 사고에 대한 대비를 더욱 철저히 수행할 수 있게 되는 효과가 있다.That is, the above-described monitoring unit 13 may be understood to be able to perform all the functions performed by the step S30 mentioned in FIG. 1 above, so that the safety management of the construction site can be more systematically performed. Of course, it is possible to monitor the ground where the structure adjacent to the construction site is installed, so that it is possible to more thoroughly prepare for safety accidents.

또 다른 한편, 상술한 보강 작업 정보 제공부(14)는, 앞서 언급한 모니터링부(13)의 기능 수행 결과, 계측된 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단될 경우, 현장 관리자 단말(40)에 흙막이 가시설에 요구되는 보강 작업 정보를 제공하는 기능을 수행할 수 있다.On the other hand, the above-mentioned reinforcement work information providing unit 14, the site manager, if it is determined that the measured displacement of the temporary wall temporary equipment out of the preset maximum allowable displacement amount, as a result of performing the function of the above-described monitoring unit 13, The terminal 40 may perform a function of providing information on the reinforcement work required for the temporary blocking facility.

즉, 상술한 보강 작업 정보 제공부(14)는, 앞서 도 1에서 언급한 S40 단계가 수행하는 기능을 모두 수행 가능한 것으로 이해될 수 있으며 이에 따라, 흙막이 가시설의 취약 지점에 대한 보강 작업이 신속히 수행될 수 있도록 하여, 안정적이면서, 경제성 및 시공 기간의 단축을 도모할 수 있게 되는 효과가 있다. That is, the above-mentioned reinforcement work information providing unit 14 may be understood to be able to perform all the functions performed by the above-mentioned step S40 in FIG. 1 and, accordingly, reinforcement work for the weak point of the earthenware temporary installation is performed quickly. It is possible to achieve a stable, economical and it is possible to shorten the construction period.

이상과 같이 실시 예들이 비록 한정된 실시 예와 도면에 의해 설명되었으나, 해당 기술 분야에서 통상의 지식을 가진 자라면 상기의 기재로부터 다양한 수정 및 변형이 가능하다.Although the embodiments have been described with reference to the limited embodiments and the drawings as described above, various modifications and variations are possible to those skilled in the art from the above description.

또 다른 한편 도 8에서는 본 발명의 일 실시 예에 따른 컴퓨팅 장치의 내부 구성의 일 예를 도시하였으며, 이하의 설명에 있어서, 상술한 도 1 내지 7에 대한 설명과 중복되는 불필요한 실시 예에 대한 설명은 생략하기로 한다.Meanwhile, FIG. 8 illustrates an example of an internal configuration of the computing device according to an embodiment of the present disclosure. In the following description, a description of unnecessary embodiments overlapping with the description of FIGS. 1 to 7 will be provided. Will be omitted.

도 8에 도시한 바와 같이, 컴퓨팅 장치(10000)은 적어도 하나의 프로세서(processor)(11100), 메모리(memory)(11200), 주변장치 인터페이스(peripheral interface)(11300), 입/출력 서브시스템(I/O subsystem)(11400), 전력 회로(11500) 및 통신 회로(11600)를 적어도 포함할 수 있다. 이때, 컴퓨팅 장치(10000)은 촉각 인터페이스 장치에 연결된 유저 단말이기(A) 혹은 전술한 컴퓨팅 장치(B)에 해당될 수 있다.As shown in FIG. 8, the computing device 10000 includes at least one processor 1100, a memory 11200, a peripheral interface 11300, an input / output subsystem ( I / O subsystem 11400, power circuit 11500, and communication circuit 11600 at least. In this case, the computing device 10000 may correspond to a user terminal A connected to the tactile interface device A or the computing device B described above.

메모리(11200)는, 일례로 고속 랜덤 액세스 메모리(high-speed random access memory), 자기 디스크, 에스램(SRAM), 디램(DRAM), 롬(ROM), 플래시 메모리 또는 비휘발성 메모리를 포함할 수 있다. 메모리(11200)는 컴퓨팅 장치(10000)의 동작에 필요한 소프트웨어 모듈, 명령어 집합 또는 그밖에 다양한 데이터를 포함할 수 있다.The memory 11200 may include, for example, high-speed random access memory, magnetic disk, SRAM, DRAM, ROM, flash memory, or nonvolatile memory. have. The memory 11200 may include a software module, an instruction set, or other various data necessary for the operation of the computing device 10000.

이때, 프로세서(11100)나 주변장치 인터페이스(11300) 등의 다른 컴포넌트에서 메모리(11200)에 액세스하는 것은 프로세서(11100)에 의해 제어될 수 있다.In this case, accessing the memory 11200 from another component such as the processor 11100 or the peripheral device interface 11300 may be controlled by the processor 11100.

주변장치 인터페이스(11300)는 컴퓨팅 장치(10000)의 입력 및/또는 출력 주변장치를 프로세서(11100) 및 메모리 (11200)에 결합시킬 수 있다. 프로세서(11100)는 메모리(11200)에 저장된 소프트웨어 모듈 또는 명령어 집합을 실행하여 컴퓨팅 장치(10000)을 위한 다양한 기능을 수행하고 데이터를 처리할 수 있다.The peripheral interface 11300 may couple an input and / or output peripheral of the computing device 10000 to the processor 11100 and the memory 11200. The processor 11100 may execute a software module or an instruction set stored in the memory 11200 to perform various functions and process data for the computing device 10000.

입/출력 서브시스템(11400)은 다양한 입/출력 주변장치들을 주변장치 인터페이스(11300)에 결합시킬 수 있다. 예를 들어, 입/출력 서브시스템(11400)은 모니터나 키보드, 마우스, 프린터 또는 필요에 따라 터치스크린이나 센서 등의 주변장치를 주변장치 인터페이스(11300)에 결합시키기 위한 컨트롤러를 포함할 수 있다. 다른 측면에 따르면, 입/출력 주변장치들은 입/출력 서브시스템(11400)을 거치지 않고 주변장치 인터페이스(11300)에 결합될 수도 있다.Input / output subsystem 11400 may couple various input / output peripherals to peripheral interface 11300. For example, the input / output subsystem 11400 may include a controller for coupling a peripheral device such as a monitor or keyboard, a mouse, a printer, or a touch screen or a sensor, as necessary, to the peripheral interface 11300. According to another aspect, the input / output peripherals may be coupled to the peripheral interface 11300 without passing through the input / output subsystem 11400.

전력 회로(11500)는 단말기의 컴포넌트의 전부 또는 일부로 전력을 공급할 수 있다. 예를 들어 전력 회로(11500)는 전력 관리 시스템, 배터리나 교류(AC) 등과 같은 하나 이상의 전원, 충전 시스템, 전력 실패 감지 회로(power failure detection circuit), 전력 변환기나 인버터, 전력 상태 표시자 또는 전력 생성, 관리, 분배를 위한 임의의 다른 컴포넌트들을 포함할 수 있다.The power circuit 11500 may supply power to all or part of the components of the terminal. For example, power circuit 11500 may include a power management system, one or more power sources such as batteries or alternating current (AC), charging systems, power failure detection circuits, power converters or inverters, power status indicators or power sources. It can include any other components for creation, management, distribution.

통신 회로(11600)는 적어도 하나의 외부 포트를 이용하여 다른 컴퓨팅 장치와 통신을 가능하게 할 수 있다.The communication circuit 11600 may enable communication with another computing device using at least one external port.

또는 상술한 바와 같이 필요에 따라 통신 회로(11600)는 RF 회로를 포함하여 전자기 신호(electromagnetic signal)라고도 알려진 RF 신호를 송수신함으로써, 다른 컴퓨팅 장치와 통신을 가능하게 할 수도 있다.Alternatively, as described above, the communication circuit 11600 may include an RF circuit to transmit and receive an RF signal, also known as an electromagnetic signal, to enable communication with other computing devices.

이러한 도 8의 실시 예는, 컴퓨팅 장치(10000)의 일례일 뿐이고, 컴퓨팅 장치(11000)은 도 8에 도시된 일부 컴포넌트가 생략되거나, 도 8에 도시되지 않은 추가의 컴포넌트를 더 구비하거나, 2개 이상의 컴포넌트를 결합시키는 구성 또는 배치를 가질 수 있다. 예를 들어, 모바일 환경의 통신 단말을 위한 컴퓨팅 장치는 도 8에도시된 컴포넌트들 외에도, 터치스크린이나 센서 등을 더 포함할 수도 있으며, 통신 회로(1160)에 다양한 통신방식(WiFi, 3G, LTE, Bluetooth, NFC, Zigbee 등)의 RF 통신을 위한 회로가 포함될 수도 있다. 컴퓨팅 장치(10000)에 포함 가능한 컴포넌트들은 하나 이상의 신호 처리 또는 어플리케이션에 특화된 집적 회로를 포함하는 하드웨어, 소프트웨어, 또는 하드웨어 및 소프트웨어 양자의 조합으로 구현될 수 있다.8 is only an example of the computing device 10000, and the computing device 11000 may include some components shown in FIG. 8, or may include additional components not shown in FIG. 8, or may include two components. It may have a configuration or arrangement that combines two or more components. For example, the computing device for a communication terminal in a mobile environment may further include a touch screen or a sensor, in addition to the components shown in FIG. 8, and various communication schemes (WiFi, 3G, LTE) in the communication circuit 1160. , Bluetooth, NFC, Zigbee, etc.) may include a circuit for RF communication. Components that may be included in the computing device 10000 may be implemented in hardware, software, or a combination of both hardware and software, including integrated circuits specialized for one or more signal processing or applications.

본 발명의 실시 예에 따른 방법들은 다양한 컴퓨팅 장치를 통하여 수행될 수 있는 프로그램 명령(instruction) 형태로 구현되어 컴퓨터 판독 가능 기록매체에 기록될 수 있다. 특히, 본 실시 예에 따른 프로그램은 PC 기반의 프로그램 또는 모바일 단말 전용의 어플리케이션으로 구성될 수 있다. 본 발명이 적용되는 애플리케이션은 파일 배포 시스템이 제공하는 파일을 통해 이용자 단말에 설치될 수 있다. 일 예로, 파일 배포 시스템은 이용자 단말이기의 요청에 따라 상기 파일을 전송하는 파일 전송부(미도시)를 포함할 수 있다.Methods according to an embodiment of the present invention can be implemented in the form of program instructions that can be executed by various computing devices and recorded on a computer readable recording medium. In particular, the program according to the present embodiment may be configured as a PC-based program or an application dedicated to a mobile terminal. An application to which the present invention is applied may be installed in a user terminal through a file provided by a file distribution system. For example, the file distribution system may include a file transmitter (not shown) for transmitting the file at the request of the user terminal.

이상에서 설명된 장치는 하드웨어 구성요소, 소프트웨어 구성요소, 및/또는 하드웨어 구성요소 및 소프트웨어구성요소의 조합으로 구현될 수 있다. 예를 들어, 실시 예들에서 설명된 장치 및 구성요소는, 예를 들어, 프로세서, 콘트롤러, ALU(arithmetic logic unit), 디지털 신호 프로세서(digital signal processor), 마이크로컴퓨터, FPGA(field programmable gate array), PLU(programmable logic unit), 마이크로프로세서, 또는 명령(instruction)을 실행하고 응답할 수 있는 다른 어떠한 장치와 같이, 하나 이상의 범용 컴퓨터 또는 특수 목적컴퓨터를 이용하여 구현될 수 있다. 처리 장치는 운영 체제(OS) 및 상기 운영 체제상에서 수행되는 하나 이상의 소프트웨어 애플리케이션을 수행할 수 있다. 또한, 처리 장치는 소프트웨어의 실행에 응답하여, 데이터를 접근, 저장, 조작, 처리 및 생성할 수도 있다. 이해의 편의를 위하여, 처리 장치는 하나가 사용되는 것으로 설명된 경우도 있지만, 해당 기술 분야에서 통상의 지식을 가진 자는, 처리 장치가 복수 개의 처리 요소(processing element) 및/또는 복수 유형의 처리 요소를 포함할 수 있음을 알 수 있다. 예를 들어, 처리 장치는 복수 개의 프로세서 또는 하나의 프로세서 및 하나의 콘트롤러를 포함할 수 있다. 또한, 병렬 프로세서(parallel processor)와 같은, 다른 처리 구성(processing configuration)도 가능하다.The apparatus described above may be implemented as a hardware component, a software component, and / or a combination of hardware components and software components. For example, the devices and components described in the embodiments may include, for example, a processor, a controller, an arithmetic logic unit (ALU), a digital signal processor, a microcomputer, a field programmable gate array (FPGA), It may be implemented using one or more general purpose or special purpose computers, such as a programmable logic unit (PLU), microprocessor, or any other device capable of executing and responding to instructions. The processing device may execute an operating system (OS) and one or more software applications running on the operating system. The processing device may also access, store, manipulate, process, and generate data in response to the execution of the software. For convenience of understanding, one processing device may be described as being used, but one of ordinary skill in the art will appreciate that the processing device includes a plurality of processing elements and / or a plurality of types of processing elements. It can be seen that it may include. For example, the processing device may include a plurality of processors or one processor and one controller. In addition, other processing configurations are possible, such as parallel processors.

소프트웨어는 컴퓨터 프로그램(computer program), 코드(code), 명령(instruction), 또는 이들 중 하나 이상의 조합을 포함할 수 있으며, 원하는 대로 동작하도록 처리 장치를 구성하거나 독립적으로 또는 결합적으로 (collectively) 처리 장치를 명령할 수 있다. 소프트웨어 및/또는 데이터는, 처리 장치에 의하여 해석되거나 처리 장치에 명령 또는 데이터를 제공하기 위하여, 어떤 유형의 기계, 구성요소(component), 물리적 장치, 가상장치(virtual equipment), 컴퓨터 저장 매체 또는 장치에 영구적으로, 또는 일시적으로 구체화(embody)될 수 있다. 소프트웨어는 네트워크로 연결된 컴퓨팅 장치상에 분산되어서, 분산된 방법으로 저장되거나 실행될 수도 있다. 소프트웨어 및 데이터는 하나 이상의 컴퓨터 판독 가능 기록 매체에 저장될 수 있다.The software may include a computer program, code, instructions, or a combination of one or more of these, and configure the processing device to operate as desired, or process it independently or in combination. You can command the device. Software and / or data may be any type of machine, component, physical device, virtual equipment, computer storage medium or device in order to be interpreted by or to provide instructions or data to the processing device. It may be embodied permanently or temporarily. The software may be distributed over networked computing devices so that they are stored or executed in a distributed manner. Software and data may be stored on one or more computer readable recording media.

실시 예에 따른 방법은 다양한 컴퓨터 수단을 통하여 수행될 수 있는 프로그램 명령 형태로 구현되어 컴퓨터 판독 가능 기록매체에 기록될 수 있다. 상기 컴퓨터 판독 가능 기록매체는 프로그램 명령, 데이터 파일, 데이터 구조 등을 단독으로 또는 조합하여 포함할 수 있다. 상기 매체에 기록되는 프로그램 명령은 실시 예를 위하여 특별히 설계되고 구성된 것들이거나 컴퓨터 소프트웨어 당업자에게 공지되어 사용 가능한 것일 수도 있다. 컴퓨터 판독 가능 기록 매체의 예에는 하드 디스크, 플로피 디스크 및 자기 테이프와 같은 자기 매체(magnetic media), CD-ROM, DVD와 같은 광 기록 매체(optical media), 플롭티컬 디스크(floptical disk)와 같은 자기-광 매체(magneto-optical media), 및 롬(ROM), 램(RAM), 플래시 메모리 등과 같은 프로그램 명령을 저장하고 수행하도록 특별히 구성된 하드웨어 장치가 포함된다. 프로그램 명령의 예에는 컴파일러에 의해 만들어지는 것과 같은 기계어 코드뿐만 아니라 인터프리터 등을 사용해서 컴퓨터에 의해서 실행될 수 있는 고급 언어 코드를 포함한다. 상기된 하드웨어 장치는 실시예의 동작을 수행하기 위해 하나 이상의 소프트웨어 모듈로서 작동하도록 구성될 수 있으며, 그 역도 마찬가지이다.Method according to the embodiment is implemented in the form of program instructions that can be executed by various computer means may be recorded on a computer readable recording medium. The computer-readable recording medium may include program instructions, data files, data structures, etc. alone or in combination. Program instructions recorded on the media may be those specially designed and constructed for the purposes of the present disclosure, or they may be of the kind well-known and available to those having skill in the computer software arts. Examples of computer-readable recording media include magnetic media such as hard disks, floppy disks, and magnetic tape, optical media such as CD-ROMs, DVDs, and magnetic disks, such as floppy disks. Magneto-optical media, and hardware devices specifically configured to store and execute program instructions, such as ROM, RAM, flash memory, and the like. Examples of program instructions include not only machine code generated by a compiler, but also high-level language code that can be executed by a computer using an interpreter or the like. The hardware device described above may be configured to operate as one or more software modules to perform the operations of the embodiments, and vice versa.

이상과 같이 실시 예들이 비록 한정된 실시 예와 도면에 의해 설명되었으나, 해당 기술 분야에서 통상의 지식을 가진 자라면 상기의 기재로부터 다양한 수정 및 변형이 가능하다. 예를 들어, 설명된 기술들이 설명된 방법과 다른 순서로 수행되거나, 및/또는 설명된 시스템, 구조, 장치, 회로 등의 구성요소들이 설명된 방법과 다른 형태로 결합 또는 조합되거나, 다른 구성요소 또는 균등물에 의하여 대치되거나 치환되더라도 적절한 결과가 달성될 수 있다. 그러므로, 다른 구현들, 다른 실시 예들 및 특허청구범위와 균등한 것들도 후술하는 특허청구범위의 범위에 속한다.Although the embodiments have been described with reference to the limited embodiments and the drawings as described above, various modifications and variations are possible to those skilled in the art from the above description. For example, the described techniques may be performed in a different order than the described method, and / or components of the described systems, structures, devices, circuits, etc. may be combined or combined in a different form than the described method, or other components. Or even if replaced or substituted by equivalents, an appropriate result can be achieved. Therefore, other implementations, other embodiments, and equivalents to the claims are within the scope of the claims that follow.

Claims (9)

하나 이상의 프로세서 및 상기 프로세서에서 수행 가능한 명령들을 저장하는 하나 이상의 메모리를 포함하는 컴퓨팅 장치에서 구현되는 흙막이 가시설 공법의 선정 방법에 있어서,
흙막이 가시설이 설치되는 시공 현장에 대한 지반 조사를 수행하여 상기 시공 현장의 지질 특성과 관련된 지반 데이터를 수집하는 지반 데이터 수집 단계;
상기 지반 데이터 조건과 건축물의 설계 조건을 고려하여 하나 이상의 흙막이 가시설 공법이 저장되어 있는 데이터베이스 상에서 매칭되는 흙막이 가시설 공법을 선정하는 흙막이 가시설 공법 선정 단계;
선정된 흙막이 가시설 공법을 기초로 상기 시공 현장에 흙막이 가시설의 설치 시공을 수행하되, 상기 흙막이 가시설의 일 영역에는 하나 이상의 센서 모듈이 설치되도록 하여, 상기 센서 모듈로부터 상기 흙막이 가시설의 변위를 계측하여 모니터링을 수행하는 모니터링 단계; 및
상기 모니터링 단계의 수행 결과, 계측된 상기 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단될 경우, 현장 관리자 단말에 상기 흙막이 가시설에 요구되는 보강 작업 정보를 제공하되, 계측된 상기 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단되는 대상에 대한 보강 작업 정보 및 보강 작업의 종류로서 흙막이 가시설의 벽체 보강 또는 지보 수단의 보강에 대한 작업 정보를 포함하는 보강 작업 정보를 제공하는 보강 작업 정보 제공 단계;를 포함하고,
상기 보강 작업 정보 제공 단계는,
모니터링 결과를 상기 현장 관리자 단말에 제공 시, 상기 센서 모듈에 의해 계측된 변위량을 기 설정된 최대 허용 변위량과 비교하여, 그 근접 정도에 따라 안전, 주의 요망, 위험 중 적어도 어느 하나에 해당하는 상태 정보를 제공하고,
상기 흙막이 가시설 공법 선정 단계는,
상기 지반 데이터로부터, 상기 시공 현장에 요구되는 흙막이 가시설의 최소 내하력을 산출하고, 산출된 상기 최소 내하력을 만족하는 흙막이 가시설 공법이 선정되도록 하되, 상기 최소 내하력 산출 시, 타 시공 현장에 대한 흙막이 가시설의 설계 이력을 수집하여, 상기 시공 현장의 지반 데이터 조건과, 건축물의 설계 조건이 가장 유사한 타 시공 현장에서 산출된 최소 내하력 값을 이용하여 최소 내하력을 산출하고,
상기 흙막이 가시설 공법 선정 단계는,
상기 시공 현장에 대한 기상 데이터를 더 수집하여 상기 흙막이 가시설 공법의 선정 기준 중 하나로 이용하되,
상기 기상 데이터는 기상 관측 서버를 통해 수집된, 상기 시공 현장에 대한 미래의 예측된 기상 데이터이고, 상기 예측된 기상 데이터로부터 상기 흙막이 가시설의 설치가 예정된 시공 기간에 우천이 예상되는 경우, 흙막이 가시설의 선정 기준을 상향 조정하여 상대적으로 큰 내하력을 갖는 흙막이 가시설이 선정될 수 있도록 하고,
상기 흙막이 가시설 공법 선정 단계는,
상기 시공 현장에 대한 기상 데이터를 더 수집하여 상기 흙막이 가시설 공법의 선정 기준 중 하나로 이용하되,
상기 기상 데이터는, 상기 시공 현장에 대한 과거의 누적된 기상 데이터를 통계적으로 분석하여 도출된 우천 발생 기간에 대한 기상 데이터이고, 상기 우천 발생 기간과 상기 흙막이 가시설의 설치가 예정된 시공 기간이 중복되는 경우, 상기 흙막이 가시설의 선정 기준을 상향 조정하여 상대적으로 큰 내하력을 갖는 흙막이 가시설이 선정될 수 있도록 하는 것을 특징으로 하고,
상기 센서 모듈은, 상기 흙막이 가시설이 설치되는 상기 시공 현장을 기준으로 기 설정된 반경 내에 존재하는 주변 현장에 더 설치되도록 하여,
상기 모니터링 단계의 수행 시, 상기 시공 현장의 지반 및 인접 구조물의 지반을 포함하는 지반의 변위 계측을 통한 모니터링이 가능해지도록 하는 것을 특징으로 하는 흙막이 가시설 공법의 선정 방법.
In the method of selecting a clogging method implemented in a computing device comprising at least one processor and at least one memory for storing instructions executable by the processor,
A ground data collection step of collecting ground data related to the geological characteristics of the construction site by performing a ground survey on a construction site in which an earthwork temporary facility is installed;
Selecting a clogging provision method for selecting a matching clogging provision method on a database in which one or more clogging provision methods are stored in consideration of the ground data conditions and design conditions of a building;
Based on the selected earthquake temporary installation method, the installation of the earthquake temporary facility at the construction site is carried out, and one or more sensor modules are installed in one area of the earthquake temporary facility, and the displacement of the earthquake temporary facility from the sensor module is monitored. Monitoring step to perform; And
As a result of performing the monitoring step, if it is determined that the measured displacement of the tent temporary equipment is out of a preset maximum allowable displacement amount, the site manager terminal provides information on reinforcement work required for the tent temporary equipment, Reinforcement work information that provides reinforcement work information for the object whose displacement is found to be outside the preset maximum allowable displacement amount and the reinforcement work information including the work information about the reinforcement of the wall or the supporting means as a kind of reinforcement work. Providing step;
The reinforcing work information providing step,
When providing the monitoring result to the field manager terminal, the displacement amount measured by the sensor module is compared with a preset maximum allowable displacement amount, and state information corresponding to at least one of safety, attention, and danger according to the proximity level is determined. Offering,
The earthquake temporary construction method selection step,
From the ground data, the minimum load carrying capacity required for the construction site for the construction site is calculated, and the construction of the construction site to meet the minimum load capacity is to be selected, the calculation of the minimum load capacity, when calculating the minimum load capacity, By collecting the design history, the minimum load capacity is calculated by using the minimum load capacity value calculated at other construction sites where the ground data conditions of the construction site and the design conditions of the building are most similar,
The earthquake temporary construction method selection step,
Collect more weather data about the construction site and use it as one of the selection criteria of the temporary wall construction method,
The weather data is future forecasted weather data for the construction site collected through a weather observation server, and when the rain is expected in the construction period where the installation of the screening facility is scheduled from the forecasted weather data, Adjusting the selection criteria upwards to allow the selection of earthquake tents with relatively large load capacity,
The earthquake temporary construction method selection step,
Collect more weather data about the construction site and use it as one of the selection criteria of the temporary wall construction method,
The weather data is weather data for a period of rain occurrence, which is derived by statistically analyzing past cumulative weather data for the construction site, and the construction period in which the rain occurrence period and the construction of the earthquake tent are scheduled to overlap. Characterized in that to increase the selection criterion of the temporary wall temporary facility to allow the earthquake temporary facility having a relatively large load capacity to be selected,
The sensor module is to be further installed in the surrounding site existing within a predetermined radius on the basis of the construction site where the earthenware temporary installation is installed,
When performing the monitoring step, it is possible to monitor by measuring the displacement of the ground including the ground of the construction site and the ground of the adjacent structure, it is characterized in that the selection method of the clogging construction method.
삭제delete 삭제delete 삭제delete 삭제delete 제1항에 있어서,
상기 흙막이 가시설의 시공 인력 단말에는,
상기 선정된 흙막이 가시설 공법에 요구되는 자재 정보, 시공 순서 및 시공 유의 사항 정보 중 적어도 어느 하나를 포함하는 시공 안내 콘텐츠가 제공되고,
상기 시공 안내 콘텐츠는, 상기 시공 인력 단말의 출력 수단에서 출력 가능한 텍스트, 이미지 및 영상 중 적어도 어느 하나를 포함하는 형태로서 출력 제공되는 것을 특징으로 하는 흙막이 가시설 공법의 선정 방법.
The method of claim 1,
In the construction workforce terminal of the said earthenware temporary facility,
A construction guide content including at least one of material information, construction order, and construction precaution information required for the selected retaining construction method is provided.
And the construction guide content is provided as a form including at least one of a text, an image, and an image that can be output by the output means of the construction manpower terminal.
제1항에 있어서,
상기 센서 모듈은,
지중 경사계, 침하계, 하중계, 지하 수위계, 변형률계, 수압계 및 토압계 중 적어도 어느 하나를 포함하는 것을 특징으로 하는 흙막이 가시설 공법의 선정 방법.
The method of claim 1,
The sensor module,
A method of selecting an earthquake temporary construction method comprising at least one of an underground inclinometer, a sediment gauge, a load gauge, an underground water gauge, a strain gauge, a hydraulic pressure gauge, and a earth pressure gauge.
하나 이상의 프로세서 및 상기 프로세서에서 수행 가능한 명령들을 저장하는 하나 이상의 메모리를 포함하는 컴퓨팅 장치로 구현되는 흙막이 가시설 공법의 선정 장치에 있어서,
흙막이 가시설이 설치되는 시공 현장에 대한 지반 조사를 수행하여 상기 시공 현장의 지질 특성과 관련된 지반 데이터를 수집하는 지반 데이터 수집부;
상기 지반 데이터 조건과 건축물의 설계 조건을 고려하여 하나 이상의 흙막이 가시설 공법이 저장되어 있는 데이터베이스 상에서 매칭되는 흙막이 가시설 공법을 선정하는 흙막이 가시설 공법 선정부;
선정된 흙막이 가시설 공법을 기초로 상기 시공 현장에 흙막이 가시설의 설치 시공을 수행하되, 상기 흙막이 가시설의 일 영역에는 하나 이상의 센서 모듈이 설치되도록 하여, 상기 센서 모듈로부터 상기 흙막이 가시설의 변위를 계측하여 모니터링을 수행하는 모니터링부; 및
상기 모니터링부의 기능 수행 결과, 계측된 상기 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단될 경우, 현장 관리자 단말에 상기 흙막이 가시설에 요구되는 보강 작업 정보를 제공하되, 계측된 상기 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단되는 대상에 대한 보강 작업 정보 및 보강 작업의 종류로서 흙막이 가시설의 벽체 보강 또는 지보 수단의 보강에 대한 작업 정보를 포함하는 보강 작업 정보를 제공하는 보강 작업 정보 제공부;를 포함하고,
상기 보강 작업 정보 제공부는,
모니터링 결과를 상기 현장 관리자 단말에 제공 시, 상기 센서 모듈에 의해 계측된 변위량을 기 설정된 최대 허용 변위량과 비교하여, 그 근접 정도에 따라 안전, 주의 요망, 위험 중 적어도 어느 하나에 해당하는 상태 정보를 제공하고,
상기 흙막이 가시설 공법 선정부는,
상기 지반 데이터로부터, 상기 시공 현장에 요구되는 흙막이 가시설의 최소 내하력을 산출하고, 산출된 상기 최소 내하력을 만족하는 흙막이 가시설 공법이 선정되도록 하되, 상기 최소 내하력 산출 시, 타 시공 현장에 대한 흙막이 가시설의 설계 이력을 수집하여, 상기 시공 현장의 지반 데이터 조건과, 건축물의 설계 조건이 가장 유사한 타 시공 현장에서 산출된 최소 내하력 값을 이용하여 최소 내하력을 산출하고,
상기 흙막이 가시설 공법 선정부는,
상기 시공 현장에 대한 기상 데이터를 더 수집하여 상기 흙막이 가시설 공법의 선정 기준 중 하나로 이용하되,
상기 기상 데이터는 기상 관측 서버를 통해 수집된, 상기 시공 현장에 대한 미래의 예측된 기상 데이터이고, 상기 예측된 기상 데이터로부터 상기 흙막이 가시설의 설치가 예정된 시공 기간에 우천이 예상되는 경우, 흙막이 가시설의 선정 기준을 상향 조정하여 상대적으로 큰 내하력을 갖는 흙막이 가시설이 선정될 수 있도록 하고,
상기 흙막이 가시설 공법 선정부는,
상기 시공 현장에 대한 기상 데이터를 더 수집하여 상기 흙막이 가시설 공법의 선정 기준 중 하나로 이용하되,
상기 기상 데이터는, 상기 시공 현장에 대한 과거의 누적된 기상 데이터를 통계적으로 분석하여 도출된 우천 발생 기간에 대한 기상 데이터이고, 상기 우천 발생 기간과 상기 흙막이 가시설의 설치가 예정된 시공 기간이 중복되는 경우, 상기 흙막이 가시설의 선정 기준을 상향 조정하여 상대적으로 큰 내하력을 갖는 흙막이 가시설이 선정될 수 있도록 하는 것을 특징으로 하고,
상기 센서 모듈은, 상기 흙막이 가시설이 설치되는 상기 시공 현장을 기준으로 기 설정된 반경 내에 존재하는 주변 현장에 더 설치되도록 하여,
상기 모니터링부의 기능 수행 시, 상기 시공 현장의 지반 및 인접 구조물의 지반을 포함하는 지반의 변위 계측을 통한 모니터링이 가능해지도록 하는 것을 특징으로 하는 흙막이 가시설 공법의 선정 장치.
An apparatus for selecting a clogging construction method implemented by a computing device including at least one processor and at least one memory for storing instructions executable by the processor,
A ground data collection unit configured to collect ground data related to the geological characteristics of the construction site by performing a ground survey on a construction site in which an earthquake temporary facility is installed;
An earthquake temporary construction method selecting unit which selects a matching earthquake temporary construction method on a database in which one or more earthquake temporary construction methods are stored in consideration of the ground data conditions and design conditions of a building;
Based on the selected earthquake temporary installation method, the installation of the earthquake temporary facility at the construction site is carried out, and one or more sensor modules are installed in one area of the earthquake temporary facility, and the displacement of the earthquake temporary facility from the sensor module is monitored. Monitoring unit to perform; And
As a result of performing the function of the monitoring unit, if it is determined that the measured displacement of the tent temporary equipment is out of a preset maximum allowable displacement amount, the reinforcement work information required for the tent temporary facility is provided to a site manager terminal, Reinforcement work information that provides reinforcement work information for the object whose displacement is found to be outside the preset maximum allowable displacement amount and the reinforcement work information including the work information about the reinforcement of the wall or the supporting means as a kind of reinforcement work. It includes; providing;
The reinforcement work information providing unit,
When providing the monitoring result to the field manager terminal, the displacement amount measured by the sensor module is compared with a preset maximum allowable displacement amount, and state information corresponding to at least one of safety, attention, and danger according to the proximity level is determined. Offering,
The earthquake temporary construction method selection unit,
From the ground data, the minimum load carrying capacity required for the construction site for the construction site is calculated, and the construction of the construction site to meet the minimum load capacity is to be selected, the calculation of the minimum load capacity, when calculating the minimum load capacity, By collecting the design history, the minimum load capacity is calculated by using the minimum load capacity value calculated at other construction sites where the ground data conditions of the construction site and the design conditions of the building are most similar,
The earthquake temporary construction method selection unit,
Collect more weather data about the construction site and use it as one of the selection criteria of the temporary wall construction method,
The weather data is future forecasted weather data for the construction site collected through a weather observation server, and when the rain is expected in the construction period where the installation of the screening facility is scheduled from the forecasted weather data, Adjusting the selection criteria upwards to allow the selection of earthquake tents with relatively large load capacity,
The earthquake temporary construction method selection unit,
Collect more weather data about the construction site and use it as one of the selection criteria of the temporary wall construction method,
The weather data is weather data for a period of rain occurrence, which is derived by statistically analyzing past cumulative weather data for the construction site, and the construction period in which the rain occurrence period and the construction of the earthquake tent are scheduled to overlap. Characterized in that to increase the selection criterion of the temporary wall temporary facility to allow the earthquake temporary facility having a relatively large load capacity to be selected,
The sensor module is to be further installed in the surrounding site existing within a predetermined radius on the basis of the construction site where the earthenware temporary installation is installed,
When performing the function of the monitoring unit, it is possible to monitor by measuring the displacement of the ground including the ground of the construction site and the ground of the adjacent structure, it is characterized in that the apparatus for selecting a clogging construction method.
컴퓨터 판독가능 기록 매체로서,
상기 컴퓨터 판독가능 기록 매체는, 컴퓨팅 장치로 하여금 이하의 단계들을 수행하도록 하는 명령들을 저장하며, 상기 단계들은:
흙막이 가시설이 설치되는 시공 현장에 대한 지반 조사를 수행하여 상기 시공 현장의 지질 특성과 관련된 지반 데이터를 수집하는 지반 데이터 수집 단계;
상기 지반 데이터 조건과 건축물의 설계 조건을 고려하여 하나 이상의 흙막이 가시설 공법이 저장되어 있는 데이터베이스 상에서 매칭되는 흙막이 가시설 공법을 선정하는 흙막이 가시설 공법 선정 단계;
선정된 흙막이 가시설 공법을 기초로 상기 시공 현장에 흙막이 가시설의 설치 시공을 수행하되, 상기 흙막이 가시설의 일 영역에는 하나 이상의 센서 모듈이 설치되도록 하여, 상기 센서 모듈로부터 상기 흙막이 가시설의 변위를 계측하여 모니터링을 수행하는 모니터링 단계; 및
상기 모니터링 단계의 수행 결과, 계측된 상기 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단될 경우, 현장 관리자 단말에 상기 흙막이 가시설에 요구되는 보강 작업 정보를 제공하되, 계측된 상기 흙막이 가시설의 변위가 기 설정된 최대 허용 변위량을 벗어난 것으로 판단되는 대상에 대한 보강 작업 정보 및 보강 작업의 종류로서 흙막이 가시설의 벽체 보강 또는 지보 수단의 보강에 대한 작업 정보를 포함하는 보강 작업 정보를 제공하는 보강 작업 정보 제공 단계;를 포함하고,
상기 보강 작업 정보 제공 단계는,
모니터링 결과를 상기 현장 관리자 단말에 제공 시, 상기 센서 모듈에 의해 계측된 변위량을 기 설정된 최대 허용 변위량과 비교하여, 그 근접 정도에 따라 안전, 주의 요망, 위험 중 적어도 어느 하나에 해당하는 상태 정보를 제공하고,
상기 흙막이 가시설 공법 선정 단계는,
상기 지반 데이터로부터, 상기 시공 현장에 요구되는 흙막이 가시설의 최소 내하력을 산출하고, 산출된 상기 최소 내하력을 만족하는 흙막이 가시설 공법이 선정되도록 하되, 상기 최소 내하력 산출 시, 타 시공 현장에 대한 흙막이 가시설의 설계 이력을 수집하여, 상기 시공 현장의 지반 데이터 조건과, 건축물의 설계 조건이 가장 유사한 타 시공 현장에서 산출된 최소 내하력 값을 이용하여 최소 내하력을 산출하고,
상기 흙막이 가시설 공법 선정 단계는,
상기 시공 현장에 대한 기상 데이터를 더 수집하여 상기 흙막이 가시설 공법의 선정 기준 중 하나로 이용하되,
상기 기상 데이터는 기상 관측 서버를 통해 수집된, 상기 시공 현장에 대한 미래의 예측된 기상 데이터이고, 상기 예측된 기상 데이터로부터 상기 흙막이 가시설의 설치가 예정된 시공 기간에 우천이 예상되는 경우, 흙막이 가시설의 선정 기준을 상향 조정하여 상대적으로 큰 내하력을 갖는 흙막이 가시설이 선정될 수 있도록 하고,
상기 흙막이 가시설 공법 선정 단계는,
상기 시공 현장에 대한 기상 데이터를 더 수집하여 상기 흙막이 가시설 공법의 선정 기준 중 하나로 이용하되,
상기 기상 데이터는, 상기 시공 현장에 대한 과거의 누적된 기상 데이터를 통계적으로 분석하여 도출된 우천 발생 기간에 대한 기상 데이터이고, 상기 우천 발생 기간과 상기 흙막이 가시설의 설치가 예정된 시공 기간이 중복되는 경우, 상기 흙막이 가시설의 선정 기준을 상향 조정하여 상대적으로 큰 내하력을 갖는 흙막이 가시설이 선정될 수 있도록 하는 것을 특징으로 하고,
상기 센서 모듈은, 상기 흙막이 가시설이 설치되는 상기 시공 현장을 기준으로 기 설정된 반경 내에 존재하는 주변 현장에 더 설치되도록 하여,
상기 모니터링 단계의 수행 시, 상기 시공 현장의 지반 및 인접 구조물의 지반을 포함하는 지반의 변위 계측을 통한 모니터링이 가능해지도록 하는 것을 특징으로 하는 컴퓨터 판독가능 기록 매체.
A computer readable recording medium,
The computer readable recording medium stores instructions for causing a computing device to perform the following steps, the steps:
A ground data collection step of collecting ground data related to the geological characteristics of the construction site by performing a ground survey on a construction site in which an earthwork temporary facility is installed;
Selecting a clogging provision method for selecting a matching clogging provision method on a database in which one or more clogging provision methods are stored in consideration of the ground data conditions and design conditions of a building;
Based on the selected earthquake temporary installation method, the installation of the earthquake temporary facility at the construction site is carried out, and one or more sensor modules are installed in one area of the earthquake temporary facility, and the displacement of the earthquake temporary facility from the sensor module is monitored. Monitoring step to perform; And
As a result of performing the monitoring step, if it is determined that the measured displacement of the tent temporary equipment is out of a preset maximum allowable displacement amount, the site manager terminal provides information on reinforcement work required for the tent temporary equipment, Reinforcement work information that provides reinforcement work information for the object whose displacement is found to be outside the preset maximum allowable displacement amount and the reinforcement work information including the work information about the reinforcement of the wall or the supporting means as a kind of reinforcement work. Providing step;
The reinforcing work information providing step,
When providing the monitoring result to the field manager terminal, the displacement amount measured by the sensor module is compared with a preset maximum allowable displacement amount, and state information corresponding to at least one of safety, attention, and danger according to the proximity level is determined. Offering,
The earthquake temporary construction method selection step,
From the ground data, the minimum load carrying capacity required for the construction site for the construction site is calculated, and the construction of the construction site to meet the minimum load capacity is to be selected, the calculation of the minimum load capacity, when calculating the minimum load capacity, By collecting the design history, the minimum load capacity is calculated by using the minimum load capacity value calculated at other construction sites where the ground data conditions of the construction site and the design conditions of the building are most similar,
The earthquake temporary construction method selection step,
Collect more weather data about the construction site and use it as one of the selection criteria of the temporary wall construction method,
The weather data is future forecasted weather data for the construction site collected through a weather observation server, and when the rain is expected in the construction period where the installation of the screening facility is scheduled from the forecasted weather data, Adjusting the selection criteria upwards to allow the selection of earthquake tents with relatively large load capacity,
The earthquake temporary construction method selection step,
Collect more weather data about the construction site and use it as one of the selection criteria of the temporary wall construction method,
The weather data is weather data for a period of rain occurrence, which is derived by statistically analyzing past cumulative weather data for the construction site, and the construction period in which the rain occurrence period and the construction of the earthquake tent are scheduled to overlap. Characterized in that to increase the selection criterion of the temporary wall temporary facility to allow the earthquake temporary facility having a relatively large load capacity to be selected,
The sensor module is to be further installed in the surrounding site existing within a predetermined radius on the basis of the construction site where the earthenware temporary installation is installed,
And when performing the monitoring step, monitoring by displacement measurement of the ground including the ground of the construction site and the ground of the adjacent structure is enabled.
KR1020190076936A 2019-06-27 2019-06-27 Method, apparatus and computer readable recording medium for selecting construction method of earth retaining wall KR102051331B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190076936A KR102051331B1 (en) 2019-06-27 2019-06-27 Method, apparatus and computer readable recording medium for selecting construction method of earth retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190076936A KR102051331B1 (en) 2019-06-27 2019-06-27 Method, apparatus and computer readable recording medium for selecting construction method of earth retaining wall

Publications (1)

Publication Number Publication Date
KR102051331B1 true KR102051331B1 (en) 2020-01-08

Family

ID=69154143

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190076936A KR102051331B1 (en) 2019-06-27 2019-06-27 Method, apparatus and computer readable recording medium for selecting construction method of earth retaining wall

Country Status (1)

Country Link
KR (1) KR102051331B1 (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102137045B1 (en) * 2020-01-21 2020-07-23 임창진 Temporary structure of sheathing having monitoring means
KR102137200B1 (en) * 2020-02-11 2020-07-23 주식회사 유앤씨 construction method of soil retaining wall using square steel pipe
KR102143969B1 (en) * 2020-01-03 2020-08-12 정경한 Prestressed Cast in Place Concrete Pile Assembly for Retaining Wall And Method for Constructing the Same
KR102146372B1 (en) * 2020-05-12 2020-08-20 (주) 코리아에스이 Retaining Wall without Wale Beam, Wall Structure combined such Retaining Wall and Concrete Wall, and Constructing Method thereof
KR102162460B1 (en) * 2020-03-03 2020-10-06 토우산업 주식회사 Height extension assembly for pile in temporary soil shearing system and Method for constructing and dismantling of temporary soil shearing system
CN112343098A (en) * 2020-09-25 2021-02-09 北京大成国测科技有限公司 Level monitoring system and method for building envelope top
KR102244515B1 (en) * 2020-09-29 2021-04-26 주식회사 비던 Management server for sheathing structure
KR102260321B1 (en) * 2020-11-02 2021-06-02 박성희 Construction of a management system for a civil engineering construction site and a civil engineering construction site management device using the same
KR102290462B1 (en) * 2020-12-04 2021-08-13 최문학 Method, apparatus and coumputer-readable medium for evaluating construction for sheathing timbering
KR102340766B1 (en) * 2021-03-16 2021-12-17 미래가설산업(주) Method, apparatus and system for providing design data for system scaffolding based on cloud computing system of proccessing bigdata
KR20230125659A (en) 2022-02-21 2023-08-29 디엘이앤씨 주식회사 Design method of underground exterior wall using PHC retaining wall as permanent exterior wall

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090107379A (en) * 2008-04-08 2009-10-13 연세대학교 산학협력단 Method and system for selecting excavation method for underground construction
KR20100056138A (en) * 2008-11-19 2010-05-27 연세대학교 산학협력단 The system and means for providing the information of excavation methods for the construction of building substructure
KR101132640B1 (en) * 2010-04-30 2012-04-02 한국표준과학연구원 Safety evaluation method for soil shearing work
KR101936121B1 (en) * 2017-12-13 2019-04-03 지에스건설주식회사 Construction management system of offshore structure using wether data and building information modeling (bim) data

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090107379A (en) * 2008-04-08 2009-10-13 연세대학교 산학협력단 Method and system for selecting excavation method for underground construction
KR20100056138A (en) * 2008-11-19 2010-05-27 연세대학교 산학협력단 The system and means for providing the information of excavation methods for the construction of building substructure
KR101132640B1 (en) * 2010-04-30 2012-04-02 한국표준과학연구원 Safety evaluation method for soil shearing work
KR101936121B1 (en) * 2017-12-13 2019-04-03 지에스건설주식회사 Construction management system of offshore structure using wether data and building information modeling (bim) data

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102143969B1 (en) * 2020-01-03 2020-08-12 정경한 Prestressed Cast in Place Concrete Pile Assembly for Retaining Wall And Method for Constructing the Same
KR102137045B1 (en) * 2020-01-21 2020-07-23 임창진 Temporary structure of sheathing having monitoring means
KR102137200B1 (en) * 2020-02-11 2020-07-23 주식회사 유앤씨 construction method of soil retaining wall using square steel pipe
KR102162460B1 (en) * 2020-03-03 2020-10-06 토우산업 주식회사 Height extension assembly for pile in temporary soil shearing system and Method for constructing and dismantling of temporary soil shearing system
KR102146372B1 (en) * 2020-05-12 2020-08-20 (주) 코리아에스이 Retaining Wall without Wale Beam, Wall Structure combined such Retaining Wall and Concrete Wall, and Constructing Method thereof
CN112343098A (en) * 2020-09-25 2021-02-09 北京大成国测科技有限公司 Level monitoring system and method for building envelope top
CN112343098B (en) * 2020-09-25 2021-12-10 北京大成国测科技有限公司 Level monitoring system and method for building envelope top
KR102244515B1 (en) * 2020-09-29 2021-04-26 주식회사 비던 Management server for sheathing structure
KR102260321B1 (en) * 2020-11-02 2021-06-02 박성희 Construction of a management system for a civil engineering construction site and a civil engineering construction site management device using the same
KR102290462B1 (en) * 2020-12-04 2021-08-13 최문학 Method, apparatus and coumputer-readable medium for evaluating construction for sheathing timbering
KR102340766B1 (en) * 2021-03-16 2021-12-17 미래가설산업(주) Method, apparatus and system for providing design data for system scaffolding based on cloud computing system of proccessing bigdata
KR20230125659A (en) 2022-02-21 2023-08-29 디엘이앤씨 주식회사 Design method of underground exterior wall using PHC retaining wall as permanent exterior wall

Similar Documents

Publication Publication Date Title
KR102051331B1 (en) Method, apparatus and computer readable recording medium for selecting construction method of earth retaining wall
KR101132640B1 (en) Safety evaluation method for soil shearing work
Hsieh et al. Three-dimensional numerical analysis of deep excavations with cross walls
Tan et al. Statistical analyses on a database of deep excavations in Shanghai soft clays in China from 1995–2018
Jia et al. Study on ground settlement and structural deformation for large span subway station using a new pre-supporting system
Lin et al. An extended TODIM-based model for evaluating risks of excavation system
JP2017027488A (en) Simple alarm system for reinforcing soil wall
JP2014037745A (en) Soil foundation specification determination method, soil foundation specification determination system and soil foundation specification determination program
Wang et al. The history of rescuing reinforcement and the preliminary study of preventive protection system for the cliff of Mogao Grottoes in Dunhuang, China
Yamany et al. Modelling of cast-in-place concrete tunnel liners condition
CN106547960A (en) A kind of tunnel closes on the construction method of Historical Buildings
Guo et al. Multi-objective optimization of geosynthetic-reinforced and pile-supported embankments
KR101191131B1 (en) Displacement measurement device of earth retaining temporary structure
Dai et al. Fuzzy comprehensive evaluation model for construction risk analysis in urban subway
Li et al. Distress evaluation and remediation for a high-rise building with pile-raft foundation
Askarian et al. Design of deep urban excavations using life cycle cost in comparison with acceptable risk and conventional method
JP5405535B2 (en) Landslide maintenance management system and landslide maintenance management method
Prusov Aspects of the influence assessment of the new construction during the reconstruction of urban territory areas in the dense building conditions
Lyman et al. Estimating System Stiffness of Soil Nailing Wall for Deep Excavation in Clay
JP2005196399A (en) Management system, method and program for construction machine and computer readable recording medium for recording this management program
Marr Why Monitor Performance?
KR102550072B1 (en) Diagnosis apparatus for accident risk detection of retaining wall and monitoring method of thereof
JP7129364B2 (en) Road restoration support system, road restoration support method and road restoration support program
KR102203678B1 (en) System for monitoring underground space using curb and method thereof
Weerasekera et al. Challenges Faced on Geotechnical Assessment Process on Adjacent Structures

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant