KR101912742B1 - Assessment Method and System of Safety Level of High Voltage Electrical Facilities - Google Patents

Assessment Method and System of Safety Level of High Voltage Electrical Facilities Download PDF

Info

Publication number
KR101912742B1
KR101912742B1 KR1020160160643A KR20160160643A KR101912742B1 KR 101912742 B1 KR101912742 B1 KR 101912742B1 KR 1020160160643 A KR1020160160643 A KR 1020160160643A KR 20160160643 A KR20160160643 A KR 20160160643A KR 101912742 B1 KR101912742 B1 KR 101912742B1
Authority
KR
South Korea
Prior art keywords
evaluation
score
target facility
safety
target
Prior art date
Application number
KR1020160160643A
Other languages
Korean (ko)
Other versions
KR20180060766A (en
Inventor
임용배
김동우
이기연
문현욱
Original Assignee
한국전기안전공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국전기안전공사 filed Critical 한국전기안전공사
Priority to KR1020160160643A priority Critical patent/KR101912742B1/en
Publication of KR20180060766A publication Critical patent/KR20180060766A/en
Application granted granted Critical
Publication of KR101912742B1 publication Critical patent/KR101912742B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/003Environmental or reliability tests
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/327Testing of circuit interrupters, switches or circuit-breakers
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/26Government or public services

Landscapes

  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • General Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • Environmental & Geological Engineering (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

본 발명은 대상설비 및 평가요소 별 가중치 적용 및 환경요소를 반영하고, 실시간 환경 데이터와 연계 가능한 특고압 전기설비 안전등급 평가 방법 및 시스템에 관한 것으로서, 특고압 전기설비의 대상설비 별 평가요소에 대해 AHP 기법을 이용하여 가중치를 적용하여 대상설비별 안전도 점수를 산출하며 외부 환경 실시간 데이터를 반영하여 가중치를 보정하고 최종 안전등급을 보정한다.The present invention relates to a method and system for evaluating the safety level of an extra-high voltage electrical equipment capable of reflecting real-time environmental data and reflecting the application of weighting factors and environmental factors of the target facilities and evaluation factors. AHP method is used to calculate the safety score for the target facility by applying the weight, and the weight is corrected by reflecting the external environment real time data and the final safety grade is corrected.

Description

특고압 전기설비 안전등급 평가 방법 및 시스템{Assessment Method and System of Safety Level of High Voltage Electrical Facilities}[0001] The present invention relates to a method and system for evaluating the safety level of a high-

본 발명은 특고압 전기설비 안전등급 평가에 관한 것으로서, 대상설비 및 평가요소 별 가중치 적용 및 환경요소를 반영하고, 실시간 환경 데이터와 연계 가능한 특고압 전기설비 안전등급 평가 방법 및 시스템에 관한 것이다.The present invention relates to the evaluation of the safety level of a high-voltage electrical equipment, and relates to a method and system for evaluating the safety level of an extra-high voltage electrical equipment that can reflect real-time environmental data and reflect the weighting application and environmental factors of the target equipment and evaluation factors.

선행 기술(특허등록 제10-1636772호)는 전기안전지수가 탑재된 피뢰설비 평가시스템 및 그 방법에 관한 것으로서, IEC62305의 피뢰시스템 구성에 대한 적정한 평가를 수행하는 전기안전지수가 탑재된 피뢰설비 평가시스템 및 그 방법에 관한 것이다. Prior Art (Patent Registration No. 10-1636772) relates to a system and method for evaluating a lightning arrester facility equipped with an electrical safety index, and a lightning arrester facility equipped with an electrical safety index to perform an appropriate evaluation of a lightning arrester system configuration of IEC62305 System and method thereof.

이는 피뢰시스템을 수뢰부, 인하도선, 접지, 등전위본딩, SPD의 5개 시스템으로 분류하여 안전정도에 대한 수치화가 가능하고, 피뢰시스템을 구성하는 각 부분에 대한 세부 안전지수 확인으로 적정한 시설투자를 하도록 유도할 수 있으며, 피뢰시스템 현장적용 방법에 대한 체계화를 통해 객관성 있는 표준을 적용할 수 있고, 피뢰시스템에 대한 각 부분의 안전지수 및 전체 안전지수를 통한 평가대상물의 안전등급을 제공할 수 있는 효과가 있다.It is possible to quantify the degree of safety by classifying the lightning protection system into five systems of air-termination, down-conductor, grounding, equipotential bonding, and SPD and confirm the detailed safety index for each part constituting the lightning protection system. The system can be applied to the objectively standardized system through the application method of the lightning protection system, and it is possible to provide the safety rating of the evaluation object through the safety index of each part for the lightning protection system and the total safety index It is effective.

그러나 상기 피뢰시스템의 각 구성별로 측정한 측정값을 고정된 기준값을 이용하여 안전지수로 수치화함에 따라 사용 환경 조건의 변화를 반영하지 못하여 안전등급의 신뢰도가 저하되며, 고객 입장을 고려한 설비 노후 및 기기 상태에 대한 등급제시가 불가능하다.However, since the measured values measured for each component of the lightning protection system are numerically expressed by the safety index using the fixed reference value, reliability of the safety grade is degraded due to failure to reflect changes in the use environment conditions. It is not possible to present a status rating.

또한 사용환경조건 외에도 외부의 기상 또는 전기설비 사고 통계 데이터가 평가에 실시간으로 반영될 필요가 있으나, 종래 기술을 검색해 보면 전력수요예측이나 태양광 발전 분야에서만 이와 같은 통계 데이터가 활용되고 있는 실정이어서 특고압 전기설비 안전등급 평가 분야에서의 개선이 시급하다.In addition, in addition to the environmental conditions, it is necessary that the statistical data of external weather or electric equipment accident is reflected in real time in the evaluation. However, when the conventional technology is searched, such statistical data is utilized only in the electric power demand prediction and solar power generation fields. Improvement in safety rating of high-voltage electrical equipment is urgent.

한국등록특허 제1636772호Korean Patent No. 1636772

본 발명은 특고압 전기설비 각 평가요소의 가중치 조정 및 환경요소를 반영하여 안전등급을 도출하고, 전기설비 사고 통계 데이터 및 기상청통계 데이터 등의 실시간 환경 통계 데이터를 반영하여 가중치 및 안전등급을 추가 보정하는 것을 특징으로 하는 특고압 전기설비 안전등급 평가 방법 및 시스템을 제공한다.The present invention derives the safety level by reflecting the weight adjustment of each evaluation element of the high voltage electrical equipment and the environmental factors and further adding the weight and the safety grade by reflecting the real-time environmental statistical data such as the electric facility accident statistical data and the weather station statistics data A method and system for evaluating the safety level of an extra-high voltage electrical equipment.

본 발명은 i) 특고압 전기설비의 대상설비 별 평가요소를 설정하는 단계; ii) 상기 대상설비의 평가요소 별 독립평가점수를 획득하는 단계; iii) 상기 대상설비 및 평가요소에 대해 AHP 기법을 이용하여 가중치를 산출하는 단계; iv) 상기 평가요소별 독립평가점수에 해당 가중치를 적용하고, 동일한 대상설비에 속하는 평가요소들의 점수를 합산하여 대상설비별 안전도 점수를 산출하는 단계; v) 각 대상설비별 사용 환경 조건에 따른 평가요소를 설정하고 환경요소 평가 점수를 도출하는 단계; vi) 상기 iv)단계의 대상설비별 안전도 점수와 상기 v)단계의 환경요소 평가점수를 반영하여 대상설비별 안전도 점수를 보정하는 단계; vii) 상기 vi)단계에서 보정된 대상설비별 안전도 점수에 상기 대상설비별 가중치를 적용한 뒤 합산하여 특고압 전기설비 안전등급을 도출하는 단계; 및 viii) 실시간 환경 통계 데이터를 연계하여 상기 안전등급을 보정하는 단계; 를 포함하는, 특고압 전기설비 안전등급 평가 방법을 제공한다.The present invention relates to a method for controlling a high voltage electrical equipment, ii) obtaining an independent evaluation score for each evaluation element of the target facility; iii) calculating a weight using the AHP technique for the target facility and the evaluation factor; iv) calculating the safety score of the target facility by applying the weight to the independent evaluation score of each evaluation factor and summing the scores of the evaluation factors belonging to the same target facility; v) setting an evaluation factor according to the use environment condition for each target facility and deriving an environmental factor score; vi) correcting the safety degree score of the target facility by reflecting the safety score of the target facility in the step iv) and the environmental element evaluation score of the step v); vii) deriving the safety rating of the high-voltage electrical equipment after applying the weights of the target equipment to the safety degree score of the target equipment corrected in the step vi); And viii) correlating real-time environmental statistical data to correct the safety rating; And a method for evaluating the safety level of an extra-high voltage electrical equipment.

본 발명의 다른 특징에 의하면, 특고압설비와 연결되어 컴퓨터 네트워크 기반의 데이터 처리 수단을 포함하는특고압 전기설비 안전등급 평가 시스템에 있어서, 특고압 전기설비의 대상설비별 평가요소를 설정하고, 상기 대상설비의 평가요소 별 독립평가점수를 획득하는 설정부; 상기 대상설비 및 평가요소에 대해 AHP 기법을 이용하여 가중치를 산출하는 가중치 산출부; 상기 평가요소별 독립평가점수에 해당 가중치를 적용하고, 동일한 대상설비에 속하는 평가요소들의 점수를 합산하여 대상설비별 안전도 점수를 산출하는 제1연산부; 각 대상설비별 사용 환경 조건에 따른 평가요소를 설정하고 환경요소 평가 점수를 도출하는 제2연산부; 상기 대상설비별 안전도 점수와 상기 환경요소 평가점수를 반영하여 대상설비별 안전도 점수를 보정하는 제3연산부; 상기 보정된 대상설비별 안전도 점수에 상기 대상설비별 가중치를 적용한 뒤 합산하여 특고압 전기설비 안전등급을 도출하는 제4연산부; 및 실시간 환경 통계 데이터를 연계하여 상기 안전등급을 보정하는 제5연산부;를 포함하는, 특고압 전기설비 안전등급 평가 시스템을 제공한다.According to another aspect of the present invention, there is provided a system for evaluating safety ratings of an extra-high voltage electrical equipment including data processing means based on a computer network connected to a special high voltage equipment, A setting unit for obtaining an independent evaluation score for each evaluation element of the target facility; A weight calculation unit for calculating a weight using the AHP scheme for the target facility and the evaluation factor; A first calculation unit for applying the weight to the independent evaluation score of each evaluation factor and summing the scores of evaluation factors belonging to the same target facility to calculate a safety score for each facility; A second computing unit for setting an evaluation factor according to use environment conditions for each target facility and deriving an environmental element evaluation score; A third calculation unit for correcting the safety degree score of the target facility by reflecting the safety degree score of the target facility and the environmental factor evaluation score; A fourth calculator for calculating a safety rating of an extra-high voltage electrical equipment by applying a weight for each of the target equipments to the corrected safety score of the target equipment, And a fifth arithmetic unit for correlating real-time environmental statistical data with the safety level.

사용 환경 조건을 반영하여 각 대상설비 별 평가요소에 대한 평가 점수를 도출하고 실시간 사고 및 기후 등의 데이터를 반영하여 보정함에 따라, 특고압 전기설비 각 대상설비별 안전등급 평가가 가능하고, 특고압 전기 설비의 안전등급에 대한 신뢰도를 근본적으로 향상시킬 수 있는 효과가 있다.It is possible to evaluate the safety rating of each high-voltage electrical equipment at each facility by deriving the evaluation score for the evaluation factors for each target facility by reflecting the environmental conditions and reflecting the data such as real-time thinking and climate. The reliability of the safety level of the electrical equipment can be fundamentally improved.

또한, 특고압 전기설비의 객관적 전기안전 확보 및 관리를 통해 안전진단 활성화를 통한 수익 창출 가능하며, 위험요소 및 위험인자 요소 관리를 통한 효율적 재해 저감 및 객관적 전기안전 확보 및 관리를 위한 근거 마련이 가능하다.In addition, it is possible to generate profit through activation of safety diagnosis through securing and managing objective electric safety of special high-voltage electrical equipment, and it is possible to establish basis for effective disaster reduction and objective electric safety assurance and management through risk factor and risk factor management Do.

도 1은 본 발명에 따른 안전등급 평가 방법의 처리 흐름도이다.
도 2는 본 발명에 따른 안전등급 평가의 대상설비와 평가요소 간의 계층구조도이다.
도 3 내지 도 7은 본 발명에 따른 특고압 전기설비의 대상설비별 안전등급 평가 과정을 대상설비별로 도식화한 도면이다.
도 8은 안전등급 도출 과정을 도식화한 도면이다.
도 9는 외부 데이터와 연계하여 안전등급을 보정하는 과정을 도식화한 도면이다.
도 10은 본 발명에 따른 안전등급 평가 시스템의 구성관계도이다.
1 is a process flow chart of a safety rating evaluation method according to the present invention.
FIG. 2 is a hierarchical structure diagram between a target facility and evaluation elements of a safety grade evaluation according to the present invention. FIG.
3 to 7 are diagrams illustrating the process of evaluating the safety level of the target high-voltage electrical equipment according to the present invention.
8 is a diagram illustrating a process of deriving a safety level.
9 is a diagram illustrating a process of correcting the safety level in association with external data.
10 is a configuration diagram of the safety rating system according to the present invention.

본 발명은 특고압 전기설비에 최적화되고 기후 등 전기환경 변화에 적응 가능한 안전등급 평가 방법 및 시스템을 제안하는바, 도면을 참조하여 해당 기술사상에 대해 상세히 설명한다.The present invention proposes a safety rating evaluation method and system that is optimized for extra-high voltage electrical equipment and adaptable to changes in the electrical environment such as climate, and the technical idea will be described in detail with reference to the drawings.

도 1은 본 발명에 따른 특고압 전기설비 안전등급 평가 방법의 처리 흐름도로서, 대상설비별 평가요소 설정단계(s10), 평가요소별 독립평가점수 획득단계(s20), 가중치 산출단계(s30), 대상설비별 안전도 점수 산출단계(s40), 환경요소 평가점수 산출단계(s50), 대상설비별 안전도 점수 보정단계(s60), 안전등급 도출단계(s70) 및 안전등급 보정단계(s80)를 포함한다.FIG. 1 is a flowchart of a method for evaluating the safety level of an extra-high voltage electrical equipment according to the present invention. The process includes setting an evaluation factor for each equipment (s10), acquiring an independent evaluation score for each evaluation factor (s20) (S60), safety factor score (s60), safety level deriving step (s70), and safety level correction step (s80). .

대상설비별 평가요소 설정단계(s10)는 특고압 전기설비의 대상설비별 평가요소를 설정하는 것이며, 상기 대상설비 또는 평가요소는 2 단계 이상의 계층 구조로 세분화 될 수 있는데, 이 경우에는 최종단계의 대상설비 별 최종단계 평가요소의 독립평가점수를 기준으로 처리된다.The evaluation factor setting step (s10) for each target facility sets an evaluation factor for each target facility of the extra-high voltage electrical equipment, and the target equipment or evaluation factor can be divided into two or more hierarchical levels. In this case, It is based on the independent evaluation score of the final stage evaluation factor for each facility.

즉, 상기 특고압 전기설비의 대상설비는 인입선, 개폐기, MOF, 차단기 및 변압기를 포함하는데, 상기 인입선의 경우에는 가공인입선과 지중인입선으로 더 세분할 수 있고, 변압기의 경우에는 몰드변압기와 유입변압기로 세분하여 2 단계로 계층화된 대상설비를 구성할 수 있으며 이때 대상설비는 최종단계의 몰드변압기 및 유입변압기가 되어 선택적 평가도 가능하다. 평가요소 역시 마찬가지 방식으로 1단계 평가요소로부터 더욱 세분화하여 평가할 수 있으며 최종단계의 평가요소를 기준으로 평가가 수행된다.That is, the target facility of the extra-high voltage electrical equipment includes a lead wire, a switch, a MOF, a breaker, and a transformer. In the case of the lead wire, the lead wire may be divided into a machining lead wire and an underground lead wire. The target facility can be selected as the final stage mold transformer and the inflow transformer. The evaluation element can be further subdivided from the first stage evaluation element in the same way and the evaluation is performed based on the final evaluation element.

평가요소별 독립평가점수 획득단계(s20)에서는 대상설비의 평가요소 별 독립평가점수를 획득하여 설정하는데, 대상설비의 계층이 2단계 이상으로 세분화 되는 경우, 최종단계 대상설비의 평가요소 별 독립평가점수를 획득한다. In the step of acquiring the independent evaluation score by evaluation element (s20), the independent evaluation score of each evaluation element is acquired and set. When the hierarchy of the target facility is subdivided into two or more stages, the independent evaluation Score.

도 2는 상기 평가요소가 2단계로 계층화한 구조를 도식화한 것으로, 세부 평가요소의 독립평가점수를 기준으로 안전등급 도출 프로세스가 진행되는 것이며, 모든 대상설비와 평가요소에는 가중치가 설정된다.FIG. 2 is a diagram illustrating a structure in which the evaluation element is layered in two levels. The safety grade deriving process is performed based on the independent evaluation score of the sub-evaluation elements, and weight is set for all the target facilities and evaluation elements.

가중치 산출단계(s30)는 상기 대상설비 및 평가요소에 대해 기본적으로 AHP 기법을 이용하여 가중치를 산출하고, 전기설비 사고 통계 및 기상청 통계 등의 실시간 외부 환경 통계 데이터를 이용하여 가중치를 보정할 수 있다.The weight calculation step s30 may calculate the weight using the AHP technique and correct the weight using the real-time external environment statistical data such as the electric equipment accident statistics and the weather station statistics .

AHP 기법에 의한 가중치 산출 방법은 다음과 같다.The weighting method by the AHP technique is as follows.

(단계 1) 평가 대상 항목의 내용과 수량을 정한다.(Step 1) Determine the content and quantity of the item to be evaluated.

(단계 2) 평가 대상 항목간 중요도를 기준으로 쌍대 비교를 한다. 이때, 쌍대 비교를 위한 설문표를 작성하여야 하며, 응답별 배점을 결정한다. 만약, 평가 대상 항목수가 n개 이면 설문의 수는

Figure 112016117133298-pat00001
개 이다.(Step 2) A pair comparison is made based on the importance between items to be evaluated. At this time, a questionnaire table for the comparison of the pair should be prepared and the score of each response is determined. If the number of items to be evaluated is n, the number of surveys is
Figure 112016117133298-pat00001
It is a dog.

(단계 3) 쌍대 비교 결과 도출된 수치를 가지고 n×n행렬을 만든다. (Step 3) Create an n × n matrix with the derived values from the pair comparison.

(단계 4) 행렬의 각 요소를 열의 합으로 나눈다. (n×n 행렬)(Step 4) Divide each element of the matrix by the sum of the columns. (nxn matrix)

(단계 5) 각 행의 평균을 구한다.(nX1행렬)(Step 5) The average of each row is obtained. (NX1 matrix)

(단계 6) 일관성 지수(CI : Consistency Index)를 계산한다. 여기서, CI=(λ-n)/(n-1) 이며, λ는 다음의 순서로 도출된다. (Step 6) Calculate the Consistency Index (CI). Here, CI = (? - n) / (n-1), and? Is derived in the following order.

(단계 6-1) (단계 3)에서 도출된 행렬과 (단계 5)에서 도출된 행렬을 곱한다. (n by 1행렬)   (Step 6-1) and the matrix derived in (step 3) and the matrix derived in (step 5). (n by 1 matrix)

(단계 6-2) (단계 6-1)에서 도출된 행렬의 각각의 요소를 (단계 5)에서 구한 행렬의 각각의 요소로 나눈다.   (Step 6-2) Divide each element of the matrix derived in (step 6-1) by each element of the matrix obtained in (step 5).

(단계 6-3) (단계 6-2)에서 구한 행렬의 평균값을 구한다.   (Step 6-3) and obtains the average value of the matrix obtained in (step 6-2).

(단계 7) CI ≤ 0.1 이면 (단계 5)에서 산출된 값을 가중치로 선택하고, CI>0.1 이면 산출된 값을 가중치에서 배제한다.(Step 7) If CI? 0.1, the value calculated in (Step 5) is selected as the weight, and if CI> 0.1, the calculated value is excluded from the weight.

대상설비별 안전도 점수 산출단계(s40)는 상기 평가요소별 독립평가점수에 해당 가중치를 적용하고, 동일한 대상설비에 속하는 평가요소들의 점수를 합산하여 대상설비별 안전도 점수를 산출한다. The safety score calculation step (s40) of the target facility applies the weight to the independent evaluation score of each evaluation factor, and calculates the safety score of the target facility by adding the scores of the evaluation factors belonging to the same target facility.

환경요소 평가점수 산출단계(s50)는 각 대상설비별 사용 환경 조건에 따른 평가요소를 설정하고 환경요소 평가 점수를 도출하며, 상기 사용 환경 조건에 따른 평가요소는 사용기간, 부하율, 지역 및 업종을 포함할 수 있다. 상기 환경요소 평가점수 역시 본 발명에 따른 가중치가 반영된다.The environmental factor score calculation step (s50) sets the evaluation factor according to the use environment conditions for each target facility, derives the score of the environmental factor, and the evaluation factor according to the use environment condition includes the usage period, load factor, . The environmental factor score also reflects the weight according to the present invention.

대상설비별 안전도 점수 보정단계(s60)는 상기 대상설비별 안전도 점수와 상기 환경요소 평가점수를 반영하여 대상설비별 안전도 점수를 보정한다.In the safety degree score correction step (s60) for each target facility, the safety degree score of the target facility is corrected by reflecting the safety degree score of the target facility and the environmental factor evaluation score.

도 3은 대상설비인 인입선에 대한 안전도 점수 산출 실시예로서, 인입선은 가공인입선과 지중인입선으로 대상설비가 세분화되어 있다. Fig. 3 shows an example of calculation of the safety degree score for the lead-in line as the target facility, and the lead-in line is subdivided into the processing lead-in line and the ground lead-in line.

가공인입선과 지중인입선 평가의 평가요소는 동일하나 가중치에 차이가 있으며, 인입선의 안전도 점수는 상기 대상설비의 독립평가점수에 상기 가중치를 곱한 값을 합산하고, 사용기간, 부하율, 지역 및 업종을 포함하는 사용 환경 조건에 따른 평가요소 별 가중치를 적용하여 산출된 환경요소 평가점수를 곱하여 대상설비별 안전도 점수를 보정한다. The evaluation factor of the processing lead-in line and the underground lead-in line is the same, but there is a difference in the weight, and the safety degree score of the lead-in line is obtained by multiplying the independent evaluation score of the target facility by the weighted value, The safety factor score of the target facility is corrected by multiplying the environmental factor evaluation score calculated by applying the weighting factor of the evaluation factor according to the use environment condition included.

도 4는 개폐기의 안전도 점수 산출과정을 도식화한 것으로서, 인입구개폐기와 고장구간 개폐기로 세분화되고, 평가요소과 가중치가 각기 달리 적용되어 있음을 알 수 있다. FIG. 4 is a diagram illustrating the process of computing the safety score of the switch, which is divided into an inlet switch and a failure switch. It can be seen that the evaluation factor and the weight are differently applied.

또한 환경요소 평가의 평가요소는 동일하나 적용된 가중치는 대상설비에 따라 차이가 있음을 알 수 있다. In addition, evaluation factors of the environmental factor evaluation are the same, but it can be understood that the applied weight is different according to the target facility.

도 5는 대상설비인 MOF의 안전도 점수 산출과정을 도식화한 것으로서, 외관 및 설치상태, 변류기의 과전류 강도, MOF선정평가, 절연상태, 접지상태를 평가요소 으로 하고, MOF에 적합한 환경요소 평가점수가 반영된다.FIG. 5 is a diagram illustrating the process of calculating the safety degree of the MOF as a target facility. The evaluation factor is the appearance and installation state, the overcurrent intensity of the current transformer, the MOF selection evaluation, the insulation state, Is reflected.

도 6은 대상설비인 차단기의 안전도 점수 산출과정을 도식화한 것으로서, 외관상태, 설치상태, 차단기 동작상태, 절연상태 및 접지상태를 평가요소으로 하고, AHP기법에 의해 산출된 가중치를 적용한 환경요소 평가점수를 반영한다.FIG. 6 is a diagram illustrating the process of calculating the degree of safety of a circuit breaker as a target facility. It is assumed that the appearance state, the installation state, the breaker operation state, the insulation state and the grounding state are used as the evaluation factors and the environmental factors applying the weight calculated by the AHP technique It reflects the evaluation score.

도 7은 대상설비인 변압기에 대한 안전도 점수 산출 실시예로서, 몰드변압기와 유입변압기로 대상설비가 세분화되어 각각의 가중치가 적용되어 있으며, 환경요소 평가점수가 최종 반영되어 변압기의 안전도 점수를 보정하여 제공한다. Fig. 7 shows an example of safety score calculation for a transformer as a target facility. The target facility is subdivided into a mold transformer and an inflow transformer, and each weight is applied. The score of the environmental factor is finally reflected, Corrected.

안전등급 도출단계(s70)는, 도 8에 도시돤 바와 같이, 상기 보정된 대상설비별 안전도 점수에 상기 대상설비별 가중치를 적용한 뒤 합산하여 특고압 전기설비 안전등급을 도출한다. In the safety level deriving step (s70), as shown in FIG. 8, the safety level of the high-voltage electrical equipment is derived by applying the weights of the target equipment to the corrected safety degree score of the target equipment and summing them.

아래 표는 안전등급 도출 기준의 실시예로서 점수대별로 등급을 설정할 수 있다.The following table is an example of the safety level derivation standard and can be set for each scoring scale.

Figure 112016117133298-pat00002
Figure 112016117133298-pat00002

안전등급 보정단계(s80)는, 도 9에 도시된 바와 같이, 실시간 환경 통계 데이터를 연계하여 상기 안전등급을 보정하는 것인데, 상기 실시간 환경 통계 데이터는 기상청 통계 데이터 및 전기설비 사고 통계 데이터를 포함한다.9, the safety level correction step (s80) is to correct the safety level by linking real-time environmental statistical data, as shown in FIG. 9, where the real-time environmental statistical data includes weather station statistics data and electrical equipment accident statistical data .

본 발명의 다른 특징에 의하면, 특고압설비와 연결되어 컴퓨터 네트워크 기반의 데이터 처리 수단을 포함하는 특고압 전기설비 안전등급 평가 시스템을 제공하는바, 도 10에 도시된 바와 같이, 설정부(10), 가중치 산출부(20), 제1연산부(30), 제2연산부(40), 제3연산부(50), 제4연산부(60) 및 제5연산부(70)를 포함한다.According to another aspect of the present invention, there is provided an extra-high voltage electrical equipment safety rating evaluation system including a data processing unit based on a computer network connected to a special high voltage equipment. As shown in FIG. 10, A weight calculator 20, a first calculator 30, a second calculator 40, a third calculator 50, a fourth calculator 60 and a fifth calculator 70.

특고압 전기설비 안전등급 평가 시스템은 상술한 안전등급 평가 방법을 수행하는 수단의 집합인바, 이하에서는 기능에 대한 중복 설명은 생략한다.The high-voltage electrical equipment safety class evaluation system is a set of means for performing the above-described safety class evaluation method.

설정부(10)는 특고압 전기설비의 대상설비별 평가요소를 설정하고, 상기 대상설비의 평가요소 별 독립평가점수를 획득하는 수단으로서, 상기 대상설비 또는 평가요소는 2 단계 이상의 계층 구조로 세분화되고, 최종단계의 대상설비 별 최종단계 평가요소의 독립평가점수를 설정한다. The setting unit 10 is a means for setting an evaluation factor for each target facility of the extra-high voltage electrical equipment and acquiring an independent evaluation score for each evaluation factor of the target facility. The target equipment or evaluation factor is divided into two or more hierarchical levels And sets the independent evaluation score of the final stage evaluation factor for the target equipment at the final stage.

상기 특고압 전기설비의 대상설비는 인입선, 개폐기, MOF, 차단기 및 변압기를 포함한다.The target facility of the extra-high voltage electrical equipment includes a lead wire, a switch, a MOF, a breaker, and a transformer.

가중치 산출부(20)는 상기 대상설비 및 평가요소에 대해 AHP 기법을 이용하여 가중치를 산출하며, 전기설비 사고 통계 및 기상청 통계 등의 실시간 외부 환경 통계 데이터를 이용하여 가중치를 보정할 수 있다.The weight calculation unit 20 calculates a weight value using the AHP technique for the target facility and the evaluation factor, and can correct the weight using real-time external environment statistics data such as electric facility accident statistics and weather station statistics.

제1연산부(30) 상기 평가요소별 독립평가점수에 해당 가중치를 적용하고, 동일한 대상설비에 속하는 평가요소들의 점수를 합산하여 대상설비별 안전도 점수를 산출한다.The first calculation unit 30 calculates the safety score of the target facility by applying the weight to the independent evaluation score for each evaluation factor and adding the scores of the evaluation factors belonging to the same target facility.

제2연산부(40)는 각 대상설비별 사용 환경 조건에 따른 평가요소를 설정하고 환경요소 평가 점수를 도출하며, 사용 환경 조건에 따른 평가요소는 사용기간, 부하율, 지역 및 업종을 포함할 수 있다. 상기 제2연산부의 환경요소 평가점수 역시 각 평가요소별 본 발명에 따른 가중치가 반영된다.The second arithmetic unit 40 sets an evaluation factor according to the use environment condition for each target facility and derives an environmental factor evaluation score, and the evaluation factor according to the use environment condition may include a usage period, a load factor, a region, and an industry . The environmental factor evaluation score of the second operation unit also reflects the weight according to the present invention for each evaluation factor.

제3연산부(50)는 상기 대상설비별 안전도 점수와 상기 환경요소 평가점수를 반영하여 대상설비별 안전도 점수를 보정하며, 제4연산부(60)는 상기 보정된 대상설비별 안전도 점수에 상기 대상설비별 가중치를 적용한 뒤 합산하여 특고압 전기설비 안전등급을 도출한다.The third arithmetic unit 50 corrects the safety degree score of the target facility by reflecting the safety degree score of the target facility and the environmental factor evaluation score and the fourth arithmetic unit 60 corrects the safety degree score of the target facility After applying the weights to the target facilities, the safety rating of the high voltage electrical equipment is derived.

제5연산부(70)는 실시간 환경 통계 데이터를 연계하여 상기 안전등급을 보정하는 바, 상기 실시간 환경 통계 데이터는 기상청 통계 데이터 및 전기설비 사고 통계 데이터를 포함한다.The fifth calculation unit 70 correlates real-time environmental statistical data to correct the safety level. The real-time environmental statistical data includes meteorological station statistics data and electrical equipment accident statistical data.

10 : 설정부 20 : 가중치 산출부
30 : 제1연산부 40 : 제2연산부
50 : 제3연산부 60 : 제4연산부
70 : 제5연산부
10: setting unit 20: weight calculating unit
30: first calculation unit 40: second calculation unit
50: third arithmetic section 60: fourth arithmetic section
70: fifth calculation section

Claims (14)

특고압설비와 연결되어 컴퓨터 네트워크 기반의 데이터 처리 수단을 포함하는 특고압 전기설비 안전등급 평가 시스템의 전기설비 안전도 평가 방법에 있어서,
i) 특고압 전기설비의 대상설비 별 평가요소를 설정하는 단계;
ii) 상기 대상설비의 평가요소 별 독립평가점수를 획득하는 단계;
iii) 상기 대상설비 및 평가요소에 대해 AHP 기법을 이용하여 가중치를 산출하고 산출된 가중치를 실시간 외부 환경 통계 데이터를 이용하여 보정하는 단계;
iv) 상기 평가요소별 독립평가점수에 해당 가중치를 적용하고, 동일한 대상설비에 속하는 평가요소들의 점수를 합산하여 대상설비별 안전도 점수를 산출하는 단계 ;
v) 각 대상설비별 사용 환경 조건에 따른 평가요소를 설정하고 환경요소 평가 점수를 도출하는 단계;
vi) 상기 iv)단계의 대상설비별 안전도 점수와 상기 v)단계의 환경요소 평가점수를 반영하여 대상설비별 안전도 점수를 보정하는 단계;
vii) 상기 vi)단계에서 보정된 대상설비별 안전도 점수에 상기 대상설비별 가중치를 적용한 뒤 합산하여 특고압 전기설비 안전등급을 도출하는 단계; 및
viii) 실시간 환경 통계 데이터를 연계하여 상기 안전등급을 보정하는 단계; 를 포함하고,
상기 vi) 단계의 각 대상설비의 독립평가점수에 가중치를 곱한 후 합산하여 산출된 대상설비별 안전도 점수를 사용기간, 부하율, 지역 및 업종을 포함하는 사용 환경 조건 별에 따른 평가요소 각각에 각 가중치를 곱한 후 합산한 뒤 산출된 환경요소 평가점수를 곱하여 보정하는 특고압 전기설비 안전등급 평가 방법.
A method for evaluating electrical safety of a high-voltage electrical equipment safety grade evaluation system including data processing means based on a computer network connected to a high-voltage equipment,
i) setting an evaluation factor for the target equipment of the high voltage electrical equipment;
ii) obtaining an independent evaluation score for each evaluation element of the target facility;
iii) calculating weights using the AHP technique for the target facility and evaluation factors, and correcting the calculated weights using real-time external environment statistical data;
iv) calculating the safety score of the target facility by applying the weight to the independent evaluation score of each evaluation factor and summing the scores of the evaluation factors belonging to the same target facility;
v) setting an evaluation factor according to the use environment condition for each target facility and deriving an environmental factor score;
vi) correcting the safety degree score of the target facility by reflecting the safety score of the target facility in the step iv) and the environmental element evaluation score of the step v);
vii) deriving the safety rating of the high-voltage electrical equipment after applying the weights of the target equipment to the safety degree score of the target equipment corrected in the step vi); And
viii) correcting the safety level by linking real-time environmental statistical data; Lt; / RTI >
The safety score of the target facility, which is calculated by multiplying the independent evaluation score of each target facility in step vi) by the weight, is added to each of the evaluation factors according to the usage environment conditions including the usage period, load ratio, A method for evaluating the safety level of an extra-high voltage electrical equipment in which a weight is multiplied, and then the result is multiplied by the calculated score of the environmental factor.
제1항에 있어서,
상기 대상설비 또는 평가요소는 2 단계 이상의 계층 구조로 세분화되고, 최종단계의 대상설비 별 최종단계 평가요소의 독립평가점수를 기준으로 처리되는, 특고압 전기설비 안전등급 평가 방법.
The method according to claim 1,
Wherein said target facility or evaluation element is subdivided into a hierarchical structure of two or more levels and processed based on the independent evaluation score of the final stage evaluation element of each target facility at the final stage.
제2항에 있어서,
상기 1 단계의 계층 구조의 특고압 전기설비의 대상설비 및 평가요소는 인입선, 개폐기, MOF, 차단기 및 변압기를 포함하고,
상기 인입선에 대한 2 단계의 대상설비는 가공인입선과 지중인입선이고,
상기 개폐기에 대한 상기 2 단계의 대상 설비는 인입구개폐기와 고장구간 개폐기이며,
상기 MOF에 대한 평가요소는 외관 및 설치상태, 변류기의 과전류 강도, MOF선정평가, 절연상태, 및 접지상태이며,
상기 차단기에 대한 평가요소는 외관상태, 설치상태, 차단기 동작상태, 절연상태 및 접지상태이며,
상기 변압기에 대한 상기 2 단계의 대상 설비는 몰드변압기 및 유입변압기로 세분화하는 특고압 전기설비 안전등급 평가 방법.
3. The method of claim 2,
The target equipment and evaluation elements of the above-mentioned hierarchical high voltage electrical equipment include a lead wire, a switch, a MOF, a breaker, and a transformer,
The two-stage target facility for the lead-in wire is a process lead-in line and an underground lead-in line,
The target facility of the second stage for the switch is an inlet switch and a fault section switch,
The evaluation factors for the MOF are the appearance and installation state, the overcurrent strength of the current transformer, the MOF selection evaluation, the insulation state, and the ground state,
The evaluation element for the circuit breaker is an appearance state, an installation state, a breaker operation state, an insulation state and a ground state,
The method of claim 1, wherein the target facility of the second stage for the transformer is subdivided into a mold transformer and an inflow transformer.
삭제delete 삭제delete 삭제delete 제1항에 있어서,
상기 실시간 환경 통계 데이터는 기상청 통계 데이터 및 전기설비 사고 통계 데이터를 포함하는, 특고압 전기설비 안전등급 평가 방법.
The method according to claim 1,
Wherein the real-time environmental statistical data includes Meteorological Administration statistical data and electrical equipment accident statistical data.
특고압설비와 연결되어 컴퓨터 네트워크 기반의 데이터 처리 수단을 포함하는특고압 전기설비 안전등급 평가 시스템에 있어서,
특고압 전기설비의 대상설비별 평가요소를 설정하고, 상기 대상설비의 평가요소 별 독립평가점수를 획득하는 설정부;
상기 대상설비 및 평가요소에 대해 AHP 기법을 이용하여 가중치를 산출하고, 산출된 가중치를 실시간 외부 환경 통계 데이터를 이용하여 보정하는 가중치 산출부;
상기 평가요소별 독립평가점수에 해당 가중치를 적용하고, 동일한 대상설비에 속하는 평가요소들의 점수를 합산하여 대상설비별 안전도 점수를 산출하는 제1연산부;
각 대상설비별 사용 환경 조건에 따른 평가요소를 설정하고 환경요소 평가 점수를 도출하는 제2연산부;
상기 대상설비별 안전도 점수와 상기 환경요소 평가점수를 반영하여 대상설비별 안전도 점수를 보정하는 제3연산부;
상기 보정된 대상설비별 안전도 점수에 상기 대상설비별 가중치를 적용한 뒤 합산하여 특고압 전기설비 안전등급을 도출하는 제4연산부; 및
실시간 환경 통계 데이터를 연계하여 상기 안전등급을 보정하는 제5연산부;를 포함하고,
각 대상설비의 독립평가점수에 가중치를 곱한 후 합산하여 산출된 대상설비별 안전도 점수를 사용기간, 부하율, 지역 및 업종을 포함하는 사용 환경 조건 별에 따른 평가요소 각각에 각 가중치를 곱한 후 합산한 뒤 산출된 환경요소 평가점수를 곱하여 보정하는 특고압 전기설비 안전등급 평가 시스템.
A high-voltage electrical equipment safety rating system comprising a computer network-based data processing means connected to a high-voltage equipment,
A setting unit for setting an evaluation factor for each target facility of the extra high voltage electrical equipment and obtaining an independent evaluation score for each evaluation factor of the target equipment;
A weight calculation unit for calculating weights using the AHP scheme for the target facility and the evaluation factors and correcting the calculated weights using real-time external environment statistical data;
A first calculation unit for applying the weight to the independent evaluation score of each evaluation factor and summing the scores of evaluation factors belonging to the same target facility to calculate a safety score for each facility;
A second computing unit for setting an evaluation factor according to use environment conditions for each target facility and deriving an environmental element evaluation score;
A third calculation unit for correcting the safety degree score of the target facility by reflecting the safety degree score of the target facility and the environmental factor evaluation score;
A fourth calculator for calculating a safety rating of an extra-high voltage electrical equipment by applying a weight for each of the target equipments to the corrected safety score of the target equipment, And
And a fifth operation unit for correlating the real-time environment statistical data to correct the safety level,
The safety score of the target facility, which is calculated by multiplying the independent evaluation score of each target facility by the weight, is multiplied by each weighting factor according to each use environment condition including usage period, load rate, region and industry, And then multiplying the calculated score by the environmental element evaluation score.
제8항에 있어서,
상기 대상설비 또는 평가요소는 2 단계 이상의 계층 구조로 세분화되고, 최종단계의 대상설비 별 최종단계 평가요소의 독립평가점수를 기준으로 처리되는, 특고압 전기설비 안전등급 평가 시스템.
9. The method of claim 8,
Wherein the target facility or evaluation element is subdivided into two or more hierarchical levels and the independent evaluation score of the final stage evaluation element of the final stage of the target facility is processed.
제9항에 있어서,
상기 1 단계의 계층 구조의 특고압 전기설비의 대상설비 및 평가요소는 인입선, 개폐기, MOF, 차단기 및 변압기를 포함하고,
상기 인입선에 대한 2 단계의 대상설비는 가공인입선과 지중인입선이고,
상기 개폐기에 대한 상기 2 단계의 대상 설비는 인입구개폐기와 고장구간 개폐기이며,
상기 MOF에 대한 평가요소는 외관 및 설치상태, 변류기의 과전류 강도, MOF선정평가, 절연상태, 및 접지상태이며,
상기 차단기에 대한 평가요소는 외관상태, 설치상태, 차단기 동작상태, 절연상태 및 접지상태이며,
상기 변압기에 대한 상기 2 단계의 대상 설비는 몰드변압기 및 유입변압기로 세분화하는 특고압 전기설비 안전등급 평가 시스템.
10. The method of claim 9,
The target equipment and evaluation elements of the above-mentioned hierarchical high voltage electrical equipment include a lead wire, a switch, a MOF, a breaker, and a transformer,
The two-stage target facility for the lead-in wire is a process lead-in line and an underground lead-in line,
The target facility of the second stage for the switch is an inlet switch and a fault section switch,
The evaluation factors for the MOF are the appearance and installation state, the overcurrent strength of the current transformer, the MOF selection evaluation, the insulation state, and the ground state,
The evaluation element for the circuit breaker is an appearance state, an installation state, a breaker operation state, an insulation state and a ground state,
Wherein the target facilities of the second stage for the transformer are subdivided into a mold transformer and an inflow transformer.
삭제delete 삭제delete 삭제delete 제8항에 있어서,
상기 실시간 환경 통계 데이터는 기상청 통계 데이터 및 전기설비 사고 통계 데이터를 포함하는, 특고압 전기설비 안전등급 평가 시스템.

9. The method of claim 8,
The real-time environmental statistical data includes the Meteorological Administration statistical data and the electric facility accident statistical data.

KR1020160160643A 2016-11-29 2016-11-29 Assessment Method and System of Safety Level of High Voltage Electrical Facilities KR101912742B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160160643A KR101912742B1 (en) 2016-11-29 2016-11-29 Assessment Method and System of Safety Level of High Voltage Electrical Facilities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160160643A KR101912742B1 (en) 2016-11-29 2016-11-29 Assessment Method and System of Safety Level of High Voltage Electrical Facilities

Publications (2)

Publication Number Publication Date
KR20180060766A KR20180060766A (en) 2018-06-07
KR101912742B1 true KR101912742B1 (en) 2018-10-30

Family

ID=62621881

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160160643A KR101912742B1 (en) 2016-11-29 2016-11-29 Assessment Method and System of Safety Level of High Voltage Electrical Facilities

Country Status (1)

Country Link
KR (1) KR101912742B1 (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111160673A (en) * 2018-11-07 2020-05-15 内蒙古电力(集团)有限责任公司内蒙古电力经济技术研究院分公司 Post-evaluation method and computing device for electric power construction project
CN109406898B (en) * 2018-11-07 2020-12-25 福州大学 Method for comprehensively evaluating insulation aging degree of oil paper by fusing multiple characteristic quantities
CN109754152A (en) * 2018-11-23 2019-05-14 国网天津市电力公司 Same period line loss end achievement evaluation method based on Extension AHP
CN109523200A (en) * 2019-01-03 2019-03-26 东北大学 Foundry's safety evaluation comprehensive weight calculation method based on least square method
CN110472835A (en) * 2019-07-24 2019-11-19 南方电网科学研究院有限责任公司 A kind of route wind resistance appraisal procedure, device and storage medium
KR102282978B1 (en) * 2019-12-03 2021-07-29 대한민국(기상청장) System and method for evaluating risk of rainfall disaster
CN111105153A (en) * 2019-12-13 2020-05-05 西安交通大学 Satellite health state multi-stage fuzzy evaluation method based on AHP-entropy weight method
CN111275292B (en) * 2020-01-07 2023-08-29 华电电力科学研究院有限公司 Grounding grid state evaluation method based on fuzzy analytic hierarchy process
CN111353691B (en) * 2020-02-18 2022-05-06 国网信通亿力科技有限责任公司 Power grid difference analysis method based on analytic hierarchy process
CN116295611B (en) * 2023-02-01 2023-10-13 广东省国瑞质量检验有限公司 Experimental data acquisition method, device, equipment and storage medium

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101636772B1 (en) 2014-12-30 2016-07-07 한국 전기안전공사 System for evaluating the lightning protection equipment with electrical safety index and method therefor

Also Published As

Publication number Publication date
KR20180060766A (en) 2018-06-07

Similar Documents

Publication Publication Date Title
KR101912742B1 (en) Assessment Method and System of Safety Level of High Voltage Electrical Facilities
Panteli et al. Power system resilience to extreme weather: Fragility modeling, probabilistic impact assessment, and adaptation measures
Gautam et al. Resilience assessment of distribution systems integrated with distributed energy resources
CN107230015B (en) Power distribution network toughness evaluation method based on system information entropy
Farajollahi et al. Sectionalizing switch placement in distribution networks considering switch failure
CN109687426B (en) Fault rate parameter modeling method, device, equipment and storage medium
CN103246939B (en) Safe operation of electric network risk case on-line identification method based on security margin
dos Santos et al. Predicting equipment outages due to voltage sags
CN107132762A (en) Online Static security assessment method based on forecast failure collection automatic screening
JP5775399B2 (en) Damage evaluation method for lightning protection equipment, damage evaluation equipment for lightning protection equipment, damage evaluation method for transformers, damage evaluation equipment for transformers
Abbasghorbani et al. Circuit breakers maintenance planning for composite power systems
de Oliveira et al. Voltage sags: Validating short-term monitoring by using long-term stochastic simulation
CN110797863B (en) Economic dispatching method considering safety constraints of N-1 and N-2 of power grid
Bajaj et al. A single index for voltage quality ranking in the distribution power networks using multiple criteria decision‐making
CN111598377A (en) Method and system for acquiring regional power grid reference risk on line
CN104849586A (en) Region screening method of alternating current short-circuit test
Francis et al. Information-based reliability weighting for failure mode prioritization in photovoltaic (PV) module design
CN104915787A (en) Method and system for correcting equipment failure rate and method and system for evaluating reliability of distribution network
CN115579845A (en) Relay protection fixed value analysis and verification method based on big data analysis
Papic et al. Overview of common mode outages in power systems
Yue et al. Outage data collection and parameter estimation for an improved probabilistic contigency analysis
Naidu et al. A novel framework for resilient overhead power distribution networks
Ciapessoni et al. A risk-based resilience assessment tool to anticipate critical system conditions in case of natural threats
Lu et al. A probabilistic load flow method considering transmission network contingency
JP6818658B2 (en) Power system monitoring system, power system monitoring method, and program

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant