KR101816700B1 - Apparatus and Method for continuously installing suspension scaffold step board - Google Patents

Apparatus and Method for continuously installing suspension scaffold step board Download PDF

Info

Publication number
KR101816700B1
KR101816700B1 KR1020160057723A KR20160057723A KR101816700B1 KR 101816700 B1 KR101816700 B1 KR 101816700B1 KR 1020160057723 A KR1020160057723 A KR 1020160057723A KR 20160057723 A KR20160057723 A KR 20160057723A KR 101816700 B1 KR101816700 B1 KR 101816700B1
Authority
KR
South Korea
Prior art keywords
pole
rail
scaffolding
footrest
clamp
Prior art date
Application number
KR1020160057723A
Other languages
Korean (ko)
Other versions
KR20170127281A (en
Inventor
오형순
김성엽
이종건
추길환
Original Assignee
대우조선해양 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대우조선해양 주식회사 filed Critical 대우조선해양 주식회사
Priority to KR1020160057723A priority Critical patent/KR101816700B1/en
Publication of KR20170127281A publication Critical patent/KR20170127281A/en
Application granted granted Critical
Publication of KR101816700B1 publication Critical patent/KR101816700B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/045Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on profiles, e.g. I or H profiles
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/06Consoles; Brackets
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/28Clips or connections for securing boards

Abstract

본 발명의 일면에 의하면, 해양플랜트 데크의 H빔을 이용하여 비계용 발판을 연속 설치하기 위한 장치에 있어서: 일측이 상기 H빔에 착탈 가능하게 고정되는 폴대(31); 일측이 상기 폴대의 타측에 회동 가능하게 연결되며, 발판을 지지하는 레일(32); 및 상기 폴대(31)의 일측 및 상기 레일(32)의 타측을 연결하여, 상기 폴대(31) 및 상기 레일(32)이 소정 각도 이상 벌어지지 않도록 하는 지지체;를 포함하여 이루어지는 것을 특징으로 한다.
이에 따라, 모듈형 발판과 내부용 행거식 발판을 기반으로 외부 작업용 비계를 손쉽게 설치하고 해체하여 작업자 등의 신속하고 안전한 접근이 가능하도록 하는 효과가 있다.
According to an aspect of the present invention, there is provided an apparatus for continuously installing a scaffolding footplate using an H beam of an offshore plant deck, the apparatus comprising: a pole 31 having one side detachably fixed to the H beam; A rail (32) rotatably connected at one side to the other side of the pole and supporting a footrest; And a support for connecting one side of the pole 31 and the other side of the rail 32 so that the pole 31 and the rail 32 do not extend beyond a predetermined angle.
Accordingly, an external work scaffold can be easily installed and disassembled based on a modular footrest and an inner hanging footrest, thereby enabling a quick and safe access to the worker.

Description

현수 비계용 발판연설 장치 및 방법{Apparatus and Method for continuously installing suspension scaffold step board}BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to a suspension scaffold step board,

본 발명은 해양플랜트의 설치/작업/검사를 위한 비계에 관한 것으로서, 보다 구체적으로는 외부 작업용 비계를 손쉽게 설치/해체하여 접근이 가능하도록 구성하기 위한 현수 비계용 발판연설 장치 및 방법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a scaffold for installation / operation / inspection of an offshore plant, and more particularly, to a scaffolding spokespreading apparatus and method for constructing a scaffold for external work such that the scaffold can easily be installed / disassembled and accessible.

통상적으로 해양플랜트의 비계 시스템은 수직으로 설치되는 외부 발판과 수평의 다단으로 설치되는 내부 발판으로 구분된다. 3단 모듈형의 해양플랜트의 경우 한 단의 높이는 대략 5~6m이고, 총 높이는 3단 모듈기준으로 대략 15~20m 정도이며, 전체적으로 작게는 수천장 많게는 수만장의 발판이 소요된다. 이와 같은 설계조건 하에서 발판 설치의 편의성을 높이기 위한 방안이 절실하다.Typically, the scaffold system of an offshore plant is divided into an external scaffold installed vertically and an internal scaffold installed horizontally. In the case of a three-stage modular offshore plant, the height of one stage is approximately 5 to 6 meters, and the total height is approximately 15 to 20 meters on the basis of a three-stage module. In total, several tens of thousands of footsteps are required. Under such design conditions, there is an urgent need to improve the convenience of the footrest installation.

비계용 발판 설치와 관련되어 참조할 수 있는 선행기술문헌으로 한국 등록특허공보 제1099396호(선행문헌 1), 한국 등록특허공보 제0598028호(선행문헌 2) 등이 알려져 있다.Korean Patent Publication No. 1099396 (Prior Art 1) and Korean Patent Registration No. 0598028 (Prior Art 2) are known as prior art documents which can be referred to in connection with the installation of scaffolding scaffolds.

선행문헌 1은 선반, 현수재, 크로스 빔, 조이스트, 바닥재, 연결 수단을 가지는 현수 비계에 있어서, 상기 현수 비계용 선반은 복수개의 지주재(支柱材)와, 인접하는 지주재 사이에 장착 및 분리 가능하도록 장착되는 복수개의 방호 패널을 구비하고, 상기 방호 패널의 양 측부에는 지주재로의 장착 부재가 설치된다. 이에, 단시간에 안전하고 용이하게 현수 비계를 조립 가능한 효과를 기대한다.In the hanging scaffold having a shelf, a hanging material, a cross beam, a joist, a bottom material, and a connecting means, the hanging scaffold shelf is mounted and separated between a plurality of strut members and adjacent strut members And a mounting member to a support member is provided on both sides of the protection panel. Thus, an effect of assuring a safe and easy assembly of the hanging scaffold in a short time is expected.

선행문헌 2는 발판지지구의 타단부에 클램프본체가 일체로 형성되고, 상기 클램프본체의 내측전후면에는 경사판과 고무패드가 부착된 수직판이 각각 고정설치되고, 상기 경사판과 수직판 사이에는 가이드핀이 고정설치되며 내측면에 고무패드가 부착된 클램핑판이 전후방으로 이동가능하게 삽입설치된다. 이에, 가설발판의 설치 및 해체작업에 소요되는 시간과 노력을 단축하는 효과를 기대한다.In the prior art document 2, the clamp body is integrally formed at the other end of the footrest support, and a vertical plate having a swash plate and a rubber pad is fixedly installed on the inner front and rear surfaces of the clamp body, and a guide pin is provided between the swash plate and the vertical plate. And a clamping plate having a rubber pad on its inner surface is inserted and installed so as to be movable forward and backward. Therefore, it is expected that the time and effort required for the installation and disassembly of the scaffolds are shortened.

상기한 선행문헌에 의하면 비계용 발판을 설치하는 편의성을 확보함을 요체로 하고 있으나, 해양플랜트 비계 시스템에 적용하여 기자재/시수 절감의 실효성을 높이기 위한 개선의 여지가 크다.According to the above-mentioned prior art documents, it is necessary to secure the convenience of installing a scaffolding footplate. However, there is a lot of room for improvement in order to increase the efficiency of equipment / water saving by applying it to an offshore plant scaffolding system.

1. 한국 등록특허공보 제1099396호 "현수 비계, 현수 비계용 선반 및 그 조립 시공법" (공개일자 : 2005.03.23.)1. Korean Patent Registration No. 1099396 entitled "Suspension Scaffolding, Suspension Scaffolding Shelf, and Assembly & Construction Method" (Published Date: March 23, 2005). 2. 한국 등록특허공보 제0598028호 "선체블록작업용 가설발판 설치대" (공개일자 : 2004.06.23.)2. Korean Registered Patent No. 0598028 entitled " Suspension Scaffolding Stand for Hull Block Work "(Open date: Jun. 23, 2004)

상기와 같은 종래의 문제점들을 개선하기 위한 본 발명의 목적은, 모듈형 발판과 내부용 행거식 발판을 기반으로 외부 작업용 비계를 설치하고 해체함에 있어서 높은 곳에 위치한 데크에 폴대와 발판을 결합하는 작업의 신속성과 안전성을 확보하는 현수 비계용 발판연설 장치 및 방법을 제공하는 데 있다.It is an object of the present invention to overcome the above-mentioned problems of the prior art by providing a method of assembling a scaffold for an external work on the basis of a modular scaffold and a hanger scaffold for internal use, And to provide a pedestrian scrambling device and method for ensuring promptness and safety.

상기 목적을 달성하기 위하여, 본 발명의 일면에 의하면, 해양플랜트 데크의 H빔을 이용하여 비계용 발판을 연속 설치하기 위한 장치에 있어서: 일측이 상기 H빔에 착탈 가능하게 고정되는 폴대; 일측이 상기 폴대의 타측에 회동 가능하게 연결되며, 발판을 지지하는 레일; 및 상기 폴대의 일측 및 상기 레일의 타측을 연결하여, 상기 폴대 및 상기 레일이 소정 각도 이상 벌어지지 않도록 하는 지지체;를 포함하여 이루어지는 것을 특징으로 한다.In order to achieve the above object, according to one aspect of the present invention, there is provided an apparatus for continuously installing a scaffolding footboard using H beams of an offshore plant deck, comprising: a pole having one side detachably fixed to the H beam; A rail rotatably connected to the other side of the pole on one side and supporting the footrest; And a support for connecting one side of the pole and the other side of the rail so that the pole and the rail do not extend beyond a predetermined angle.

본 발명의 세부 구성으로서, 상기 지지체는 폴대와 레일을 직각 상태로 유지하도록 연결하는 와이어를 구비하는 것을 특징으로 한다.As a detailed configuration of the present invention, the support is characterized by having a wire connecting the pole and the rail so as to maintain a right angle.

본 발명의 세부 구성으로서, 상기 인접된 폴대 사이에 결합력을 높이도록 설치되는 난간을 더 구비하는 것을 특징으로 한다.As a detailed configuration of the present invention, a railing provided to increase the coupling force between the adjacent poles is further provided.

본 발명의 세부 구성으로서, 상기 폴대는 H빔을 파지하도록 폴대의 상단에 고정되는 빔클램프, 난간을 파지하도록 폴대의 중간에 고정되는 U형클램프를 더 구비하는 것을 특징으로 한다.In a detailed configuration of the present invention, the pole further comprises a beam clamp fixed to the upper end of the pole so as to grasp the H beam, and a U-shaped clamp fixed to the middle of the pole to grip the railing.

본 발명의 변형예로서, 상기 U형클램프는 회동대를 개재하여 폴대의 외주면 상으로 위치변동 가능하게 설치되는 것을 특징으로 한다.As a modification of the present invention, the U-shaped clamp is provided so as to be positionally displaceable on the outer circumferential surface of the pole via a pivot.

본 발명의 세부 구성으로서, 상기 레일은 암수 구조로 맞물려 위치 고정 가능한 끼움대를 구비하는 것을 특징으로 한다.As a detailed configuration of the present invention, the rail is characterized in that it has a fitting base engageable with a male-female structure and capable of being fixed in position.

본 발명의 다른 일면에 의하면, 청구항 1의 구성을 기반으로 비계용 발판을 연속 설치하기 위한 방법에 있어서: 제1열의 결합지지체에서 폴대를 H빔에 맞물리고 레일을 펼쳐 발판을 거치하는 초기설치단계; 및 제2열 이후의 결합지지체에서 폴대와 레일을 동일한 방식으로 설치하고 발판을 거치하는 작업을 반복하는 반복설치단계;를 포함하여 이루어지는 것을 특징으로 한다.According to another aspect of the present invention, there is provided a method for continuously installing scaffolding scaffolds based on the configuration of claim 1, the method comprising: an initial installation step of engaging a pole with an H beam in a first row of support scaffolds, ; And repeating the steps of installing the pole and the rail in the same manner in the second and subsequent rows of the combined support and mounting the pedestal.

이상과 같이 본 발명에 의하면, 모듈형 발판과 내부용 행거식 발판을 기반으로 외부 작업용 비계를 손쉽게 설치하고 해체하여 작업자 등의 신속하고 안전한 접근이 가능하도록 하는 효과가 있다.As described above, according to the present invention, an external work scaffold can be easily installed and disassembled based on a modular footrest and an inner hanging footrest so that a quick and safe approach to the worker can be achieved.

도 1은 본 발명이 적용되는 해양플랜트의 비계 시스템을 나타내는 모식도
도 2는 본 발명에 따른 장치의 주요부를 나타내는 모식도
도 3 내지 도 5는 본 발명에 따른 장치로 비계를 시공하는 상태를 나타내는 구성도
1 is a schematic view showing a scaffold system of an offshore plant to which the present invention is applied;
Figure 2 is a schematic diagram showing the main part of the device according to the invention
3 to 5 are diagrams showing a state in which a scaffold is constructed by an apparatus according to the present invention

이하, 첨부된 도면에 의거하여 본 발명의 실시예를 상세하게 설명하면 다음과 같다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명의 일면은 해양플랜트 데크의 H빔을 이용하여 비계용 발판을 연속 설치하기 위한 장치에 관하여 제안한다. 도 1은 3단의 생산용 모듈(MD)로 구성되는 해양플랜트에서 다층의 데크(DK)가 구비된 상태를 예시한다. 본 발명의 공법은 기존의 외부비계(11)와 내부비계(12)를 축소하거나 배제함을 요지로 한다. 데크에 포함되는 다수의 H빔(15)을 활용하지만 반드시 이에 국한되는 것은 아니다.One aspect of the present invention proposes an apparatus for continuously installing scaffolding scaffolds using H beams of offshore plant decks. FIG. 1 illustrates a state where a multi-layered deck (DK) is provided in a marine plant composed of three stages of production modules (MD). In the method of the present invention, the conventional external scaffold 11 and internal scaffold 12 are reduced or eliminated. Utilizes but is not necessarily limited to a number of H beams 15 included in the deck.

한편, 도 1에서 미설명 부호 SF는 본 발명의 비계에 적용되는 의장용 발판(25)의 위치를 예시한다.On the other hand, in FIG. 1, reference numerals SF denote the positions of the footrests 25 to be applied to the scaffold of the present invention.

본 발명에 의하면 외부비계(11)를 축소 또는 대체하도록 복층으로 형성되는 발판모듈(20)이 상기 데크의 측면에 인접하여 작업 인원과 물자의 이동을 조력하도록 설치된다. 발판모듈(20)은 해양구조물의 데크 등에 결속하는 치구, 작업자의 승하강을 위한 사다리를 구비할 수도 있다.According to the present invention, a scaffolding module 20, which is formed in a multi-layer structure to reduce or replace the external scaffold 11, is installed adjacent to the side surface of the deck to assist movement of personnel and materials. The scaffolding module 20 may include a fixture bound to a deck or the like of an offshore structure, and a ladder for lifting and lowering the operator.

본 발명에 따르면 일측이 상기 H빔에 착탈 가능하게 고정되는 폴대(31)를 구비한다. 폴대(31)로서 강관과 같은 관재를 사용하는 것이 선호되지만 부분적으로 봉재를 포함할 수 있다.According to the present invention, there is provided a pole 31 on one side of which is detachably fixed to the H beam. Although it is preferred to use a tubular member such as a steel pipe as the pole 31, it may partially include a bar member.

또, 본 발명에 따르면 발판을 지지하는 레일(32)의 일측이 상기 폴대의 타측에 회동 가능하게 연결되는 구조이다. 레일(32)도 폴대(31)와 동일하게 강관과 같은 관재를 사용하는 것이 선호된다.Further, according to the present invention, one side of the rail 32 supporting the footrest is rotatably connected to the other side of the pole. It is preferable that the rails 32 use the same tubular member as the steel barrel 31 as the pole bar 31.

이와 같은 폴대(31)와 레일(32)가 힌지(33)를 개재하여 일체의 결합지지체(30)를 구성한다. 힌지(33)는 폴대(31)와 레일(32)의 하단 부분을 회동 가능하게 연결한다. 이에, 폴대(31)와 레일(32)의 결합지지체(30)는 보관이나 운반시 접고 비계용으로 사용시 신속한 펼침이 가능하다.The pole piece 31 and the rail 32 constitute an integral coupling support body 30 with the hinge 33 interposed therebetween. The hinge 33 rotatably connects the pole 31 and the lower end of the rail 32. Therefore, the supporting support body 30 of the pole 31 and the rail 32 can be quickly opened when used for folding or scaffolding in storage or transportation.

또, 본 발명에 따르면 지지체가 상기 폴대(31)의 일측 및 상기 레일(32)의 타측을 연결하여, 상기 폴대(31) 및 상기 레일(32)이 소정 각도 이상 벌어지지 않도록 하는 구조이다.According to the present invention, the supporting member connects one side of the pole 31 and the other side of the rail 32 so that the pole 31 and the rail 32 do not extend beyond a predetermined angle.

본 발명의 세부 구성으로서, 상기 지지체는 폴대(31)와 레일(32)을 직각 상태로 유지하도록 연결하는 와이어(35)를 구비하는 것을 특징으로 한다. 와이어(35)는 폴대(31)와 레일(32)에서 힌지(33)와 반대측으로 각각 연결된다. 시공 과정에서 폴대(31)와 레일(32)를 펼치면 와이어(35)가 팽팽하게 긴장되면서 도 2의 상태로 유지한다. 와이어(35)가 레일(32)와 연결되는 부분은 발판(25)의 단부와의 간섭을 피하도록 지지핀(도시 생략) 등을 이용하여 다소 돌출된 상태로 설치하는 것이 좋다. 지지핀의 단부에는 고리(도시 생략)를 부착하여 와이어(35)의 탈부착이 용이하도록 한다.As a detailed configuration of the present invention, the support is characterized by having a wire 35 connecting the pole 31 and the rail 32 so as to maintain a right angle. The wire 35 is connected to the pole 31 and the rail 32 on the opposite side of the hinge 33, respectively. When the pole 31 and the rail 32 are expanded in the construction process, the wire 35 is held in a state of FIG. 2 while being strained. It is preferable that the portion where the wire 35 is connected to the rail 32 is installed so as to protrude somewhat using a support pin (not shown) or the like so as to avoid interference with the end portion of the foot plate 25. [ A ring (not shown) is attached to the end of the support pin to facilitate detachment and attachment of the wire 35.

이때, 본 발명의 결합지지체(30)는 좌측와 우측으로 대향된 상태로 시공되므로 후술하는 것처럼 좌우측의 공용화를 위해 지지핀을 양측으로 돌출시키는 것이 바람직하다. 더욱 바람직하게는 지지핀이 레일(32)에서 슬라이딩하여 원하는 측면으로 돌출되는 구성이 선호된다. At this time, since the joint supporting body 30 of the present invention is constructed so as to be opposed to the left and right sides, it is preferable to protrude the support pins to both sides for sharing the left and right sides as described later. More preferably, the support pin slides on the rail 32 and protrudes to a desired side surface.

본 발명의 세부 구성으로서, 상기 인접된 폴대(31) 사이에 결합력을 높이도록 설치되는 난간(50)을 더 구비하는 것을 특징으로 한다. 도 2에서 구성의 간단성을 위해 난간(50)을 사각형으로 예시지만 사다리나 트러스 형태로 구성할 수도 있다. 어느 경우에나 난간(50)은 인접한 폴대(31) 사이에 결합되어 현수용 비계의 구조적 안정성을 높이면서 작업자 등의 추락을 방지한다.As a detailed construction of the present invention, a balustrade 50 is provided to increase the coupling force between the adjacent pole pieces 31. [ In FIG. 2, for the sake of simplicity of the configuration, the railing 50 is illustrated as a rectangle, but it may be configured as a ladder or a truss. In any case, the handrail 50 is coupled between the adjacent poles 31 to enhance the structural stability of the string receiving scaffold while preventing workers from falling.

본 발명의 세부 구성으로서, 상기 폴대(31)는 H빔(15)을 파지하도록 폴대(31)의 상단에 고정되는 빔클램프(42), 난간(50)을 파지하도록 폴대(31)의 중간에 고정되는 U형클램프(48)를 더 구비하는 것을 특징으로 한다. 상기 결합지지체(30)를 인접하게 연결하면서 구조적 강성을 높이도록 고정수단(40)을 구비하는 것이 좋다. 고정수단(40)은 일측으로 폴대(31)를 H빔(15)에 연결하면서 타측으로 폴대(31)를 연속적으로 연결하는 구조를 포함한다. 빔클램프(42)는 H빔(15)의 플랜지를 일측 또는 양측으로 파지하는 구조를 사용한다. U형클램프(48)는 폴대(31)의 외주면에 밀착되는 U자형 단면을 기반으로 하면서 난간(50)을 파지하기 위한 홈을 구비한다. 빔클램프(42)와 U형클램프(48)의 조임체로 볼트를 예시지만 매미고리를 비롯한 여타의 방식을 배제하는 것은 아니다. 이에, 고정수단(40)은 후술하는 도 3 내지 도 5와 같은 시공을 구현하여 다수의 발판(25)을 현수 상태로 지지한다.The pole 31 has a beam clamp 42 fixed to the top of the pole 31 to grasp the H beam 15 and a beam clamp 42 fixed to the top of the pole 31 to hold the handrail 50. [ And further includes a U-shaped clamp 48 fixed thereto. It is preferable to provide the fixing means 40 to increase the structural rigidity while connecting the coupling supports 30 adjacent to each other. The fixing means 40 includes a structure for connecting the pole 31 to the H beam 15 on one side while continuously connecting the pole 31 on the other side. The beam clamp 42 uses a structure that grasps the flange of the H beam 15 to one side or both sides. The U-shaped clamp 48 is provided with a groove for gripping the handrail 50 based on a U-shaped cross section which is in close contact with the outer circumferential surface of the pole 31. Although the bolt is exemplified by the clamping member of the beam clamp 42 and the U-shaped clamp 48, it does not exclude other methods including cicada rings. Thus, the fixing means 40 implements the construction as shown in FIGS. 3 to 5 to support a plurality of foot plates 25 in a suspended state.

본 발명의 변형예로서, 상기 U형클램프(48)는 회동대(46)를 개재하여 폴대(31)의 외주면 상으로 위치변동 가능하게 설치되는 것을 특징으로 한다. 전술한 것처럼 도 2의 좌우측 폴대(31)가 공용화된 구성이므로 U형클램프(48)가 난간(50)을 결합하는 위치가 변동될 수 있다. 회동대(46)는 폴대(31)의 외주면에 360˚ 회동 가능한 구조로 설치된다. 일예로, 도 2에서 회동대(46)가 폴대(31)에서 노출된 것으로 예시하지만 폴대(31)에 단턱에 의한 홈을 형성하고 회동대(46)를 수용할 수도 있다. 어느 경우에나 레일(32)를 폴대(31) 측으로 접는 경우 회동대(46)로 U형클램프(48)의 위치를 변경한 다음 결속할 수 있다.As a modification of the present invention, the U-shaped clamp 48 is provided so as to be positionally displaceable on the outer peripheral surface of the pole base 31 via a pivot 46. As described above, since the left and right poles 31 of FIG. 2 are configured in common, the position where the U-shaped clamp 48 engages with the handrail 50 can be varied. The pivot 46 is provided on the outer periphery of the pole 31 so as to be rotatable 360 degrees. For example, in FIG. 2, the pivot stand 46 is exposed in the pole section 31, but it may also be provided with a stepped groove in the pole section 31 to accommodate the pivot stand 46. In any case, when the rail 32 is folded toward the pole 31 side, the position of the U-shaped clamp 48 can be changed by the pivot 46, and then the binding can be performed.

본 발명의 세부 구성으로서, 상기 레일(32)은 암수 구조로 맞물려 위치 고정 가능한 끼움대(44)를 구비하는 것을 특징으로 한다. 도 2에서 레일(32)의 일단에 판형의 돌기를 타단에 돌기와 맞물리는 홈을 예시한다. 이러한 돌기와 홈으로 형성된 끼움대(44) 상에는 핀이나 볼트를 체결하기 위한 통공을 형성한다. 도시에는 생략하나 끼움대(44)는 레일(32)의 내경보다 다소 작은 직경으로 형성된 원형 돌기로 구성할 수 있다. 이 경우 원형 돌기와 맞물리는 레일(32)의 단부는 별도의 홈을 형성하지 않고 그대로 사용 가능하다. 어느 경우에나 끼움대(44)는 삼각형 구조로 연결되는 결합지지체(30)의 구조적 안정성을 높인다.As a detailed configuration of the present invention, the rail (32) is characterized by having a fitting base (44) engageable with a male and female structure and being positionally fixed. 2, a groove is formed at one end of the rail 32 to engage with and engage with a plate-like projection at the other end. A through hole for fastening a pin or a bolt is formed on the fitting base 44 formed by the protrusion and the groove. In the drawing, the fitting base 44 may be formed as a circular projection having a diameter slightly smaller than the inner diameter of the rail 32. [ In this case, the end of the rail 32 engaged with the circular protrusion can be used as it is without forming a separate groove. In any case, the fitting base 44 enhances the structural stability of the coupling support 30 connected by a triangular structure.

본 발명의 다른 일면에 의하면, 청구항 1의 구성을 기반으로 비계용 발판을 연속 설치하기 위한 방법에 있어서: 제1열의 결합지지체(30)에서 폴대(31)를 H빔에 맞물리고 레일(32)을 펼쳐 발판(25)을 거치하는 초기설치단계; 및 제2열 이후의 결합지지체(30)에서 폴대(31)와 레일(32)을 동일한 방식으로 설치하고 발판(25)을 거치하는 작업을 반복하는 반복설치단계;를 포함하여 이루어지는 것을 특징으로 한다. 제1열의 결합지지체(30)를 구성하는 초기설치단계는 전술한 발판모듈(20)을 활용하지만, 반복설치단계는 직전에 완성된 결합지지체(30)를 활용하여 동일한 패턴으로 작업을 속행한다.According to another aspect of the present invention, there is provided a method for continuously installing scaffolding scaffolds based on the configuration of claim 1, comprising the steps of: engaging a pole (31) with an H beam in a coupling support (30) An initial installation step of unfolding the foot plate 25 and mounting the foot plate 25; And repeating the operation of installing the pole 31 and the rail 32 in the same manner in the second and subsequent rows of the coupling support 30 and mounting the pedal 25 in the same manner . The initial mounting step constituting the first supporting row 30 of the first row utilizes the above-described footing module 20, but the repetitive mounting step continues the work in the same pattern utilizing the completed bonding support 30 immediately before.

시공의 일예로서, 도 3과 같이 폴대(31)를 H빔(15)에 맞물리고 레일(32)을 펼친 다음 발판(25)을 얹고, 도 4와 같이 제2열의 결합지지체(30)를 동일한 방식으로 설치한 다음 상호 끼움대(44)를 이용하여 연결하고, 도 5와 같이 제3열의 결합지지체(30)를 펼치고 동일한 방식으로 연속하여 설치를 진행한다. 물론 결합지지체(30)의 설치를 진행하는 과정에서 U형클램프(48)로 난간(50)을 설치한다.As an example of the construction, the pole base 31 is engaged with the H beam 15, the rail 32 is extended and the foot plate 25 is laid as shown in FIG. 3, and the second row of the coupling supports 30 And then connected to each other using the mutual sandwiching bracket 44, and the third supporting unit 30 is unfolded as shown in FIG. 5, and the installation is continued in the same manner. Of course, the railing 50 is provided by the U-shaped clamp 48 in the course of the installation of the coupling support 30. [

한편, 본 발명의 폴대(31)는 좌우측 공용화로 자재/관리 비용을 절감하는 구조이다. 이에 레일(32)가 폴대(31)를 기준으로 상호 반대 방향으로 회동되어야 하므로 와이어(35)의 연결 구조, 끼움대(44)의 맞물림 구조 등이 기구적 구속을 초래하지 않도록 구성된다.On the other hand, the pole 31 of the present invention has a structure for reducing material / management cost by sharing the right and left sides. The connecting structure of the wire 35 and the engaging structure of the fittable member 44 do not cause mechanical restraint because the rails 32 must be rotated in opposite directions with respect to the pole 31. [

본 발명은 기재된 실시예에 한정되는 것은 아니고, 본 발명의 사상 및 범위를 벗어나지 않고 다양하게 수정 및 변형할 수 있음은 이 기술의 분야에서 통상의 지식을 가진 자에게 자명하다. 따라서 그러한 변형예 또는 수정예들은 본 발명의 특허청구범위에 속한다 해야 할 것이다.It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit and scope of the invention as defined by the appended claims. It is therefore intended that such variations and modifications fall within the scope of the appended claims.

10: 비계 시스템 11: 외부비계
12: 내부비계 15: H빔
20: 발판모듈 25: 발판
30: 결합지지체 31: 폴대
32: 레일 33: 힌지
35: 와이어 40: 고정수단
42: 빔클램프 44: 끼움대
46: 회동대 48: U형클램프
50: 난간
10: Scaffolding system 11: External scaffolding
12: inner scaffold 15: H beam
20: Footstep module 25: Footstep
30: bonding support 31:
32: rail 33: hinge
35: wire 40: fixing means
42: beam clamp 44:
46: Rotating stand 48: U-shaped clamp
50: Railing

Claims (7)

해양플랜트 데크의 H빔을 이용하여 비계용 발판을 연속 설치하기 위한 장치에 있어서:
일측이 상기 H빔에 착탈 가능하게 고정되는 폴대(31);
일측이 상기 폴대의 타측에 회동 가능하게 연결되며, 발판을 지지하는 레일(32); 및
상기 폴대(31)의 일측 및 상기 레일(32)의 타측을 연결하여, 상기 폴대(31) 및 상기 레일(32)이 소정 각도 이상 벌어지지 않도록 하는 지지체;를 포함하되,
상기 폴대(31)는 H빔(15)의 일측 플랜지를 파지하도록 폴대(31)의 상단에 고정되는 빔클램프(42), 난간(50)을 파지하도록 폴대(31)의 중간에 고정되는 U형클램프(48)를 더 구비하고,
상기 레일(32)은 암수 구조이면서 통공에 핀이나 볼트를 체결한 힌지 구조로 맞물려 위치 고정 가능한 끼움대(44)를 구비하는 것을 특징으로 하는 현수 비계용 발판연설 장치.
An apparatus for continuously installing scaffolding scaffolds using H beams of offshore plant decks, comprising:
A pole (31) having one side detachably fixed to the H beam;
A rail (32) rotatably connected at one side to the other side of the pole and supporting a footrest; And
And a supporter connected to one side of the pole 31 and the other side of the rail 32 so that the pole 31 and the rail 32 do not extend beyond a predetermined angle,
The pole 31 includes a beam clamp 42 fixed to the upper end of the pole 31 to hold one flange of the H beam 15 and a U- Further comprising a clamp (48)
Characterized in that the rail (32) has a female thread structure and a fittable base (44) which can be held in position by being hinged by a pin or bolt fastened to the through hole.
청구항 1에 있어서,
상기 지지체는 폴대(31)와 레일(32)을 직각 상태로 유지하도록 연결하는 와이어(35)를 구비하는 것을 특징으로 하는 현수 비계용 발판연설 장치.
The method according to claim 1,
Characterized in that the support comprises a wire (35) connecting the pole (31) and the rail (32) to maintain the pole (32) at a right angle.
청구항 1에 있어서,
상기 인접된 폴대(31) 사이에 결합력을 높이도록 설치되는 난간(50)을 더 구비하는 것을 특징으로 하는 현수 비계용 발판연설 장치.
The method according to claim 1,
Further comprising a handrail (50) installed between the adjacent poles (31) to increase the binding force between the adjacent poles (31).
삭제delete 청구항 1에 있어서,
상기 U형클램프(48)는 회동대(46)를 개재하여 폴대(31)의 외주면 상으로 위치변동 가능하게 설치되는 것을 특징으로 하는 현수 비계용 발판연설 장치.
The method according to claim 1,
Characterized in that the U-shaped clamp (48) is disposed so as to be positionally displaceable on the outer peripheral surface of the pole base (31) via a pivotal table (46).
삭제delete 청구항 1의 구성을 기반으로 비계용 발판을 연속 설치하기 위한 방법에 있어서:
제1열의 결합지지체(30)에서 폴대(31)를 H빔에 맞물리고 레일(32)을 펼쳐 발판(25)을 거치하는 초기설치단계; 및
제2열 이후의 결합지지체(30)에서 폴대(31)와 레일(32)을 동일한 방식으로 설치하고 발판(25)을 거치하는 작업을 반복하는 반복설치단계;를 포함하여 이루어지는 것을 특징으로 하는 현수 비계용 발판연설 방법.
A method for continuously installing scaffolding scaffolds based on the configuration of claim 1,
An initial mounting step of engaging the pole 31 with the H beam in the first row of coupling supports 30 and unrolling the rail 32 to mount the foot plate 25; And
And an iterative mounting step of repeating an operation of mounting the pole (31) and the rail (32) in the same manner in the second and subsequent connecting supports (30) and mounting the footrest (25) Scaffolding method for scaffolding.
KR1020160057723A 2016-05-11 2016-05-11 Apparatus and Method for continuously installing suspension scaffold step board KR101816700B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160057723A KR101816700B1 (en) 2016-05-11 2016-05-11 Apparatus and Method for continuously installing suspension scaffold step board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160057723A KR101816700B1 (en) 2016-05-11 2016-05-11 Apparatus and Method for continuously installing suspension scaffold step board

Publications (2)

Publication Number Publication Date
KR20170127281A KR20170127281A (en) 2017-11-21
KR101816700B1 true KR101816700B1 (en) 2018-01-09

Family

ID=60808883

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160057723A KR101816700B1 (en) 2016-05-11 2016-05-11 Apparatus and Method for continuously installing suspension scaffold step board

Country Status (1)

Country Link
KR (1) KR101816700B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111926999A (en) * 2020-08-07 2020-11-13 吴科文 Anchor for building
CN111894257A (en) * 2020-08-07 2020-11-06 吴科文 Cantilever bottom beam rest end self-releasing anchorage for building

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100581685B1 (en) * 2005-04-12 2006-05-22 대우조선해양 주식회사 Connection apparatus of plate type for scaffolding system
KR101336732B1 (en) * 2013-05-09 2013-12-04 주식회사 케이에스알 Soundproofing wall

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100581685B1 (en) * 2005-04-12 2006-05-22 대우조선해양 주식회사 Connection apparatus of plate type for scaffolding system
KR101336732B1 (en) * 2013-05-09 2013-12-04 주식회사 케이에스알 Soundproofing wall

Also Published As

Publication number Publication date
KR20170127281A (en) 2017-11-21

Similar Documents

Publication Publication Date Title
KR101707403B1 (en) Gantry Tower Crane for Cargo Inspection
JPH10506444A (en) Scaffold assembly
US11680411B2 (en) System and method of assembling and installing commercial roofing
KR101816698B1 (en) Scaffold apparatus for offshore plant
WO1981001308A1 (en) Folding scaffold system
KR101816700B1 (en) Apparatus and Method for continuously installing suspension scaffold step board
JP4716948B2 (en) Safety rope support bracket
KR20040004565A (en) Device for human protection in scaffolding
JP3150645U (en) Safety belt support pole for scaffolding
KR20170123169A (en) Apparatus for supporting suspension scaffold pole
KR101691752B1 (en) The Boiler Superheater Platforms
KR101858539B1 (en) Scaffold clamp for multiple support
KR102027845B1 (en) Foldable scaffold frame
KR101707037B1 (en) A structure for assembled system scaffold and erecting method thereof
KR20120008547U (en) Bulk head working stand
US10526802B2 (en) Scaffold extensions
JP2002201792A (en) Prefabricated scaffolding
KR200288007Y1 (en) Rail railing (scaffolding) clamping device in the construction site.
KR101808296B1 (en) Method of installing scaffold for offshore plant
JP2003147954A (en) Advance handrail of framework scaffold
KR20200075370A (en) A standing structure bench using a crane
CN220058769U (en) Unit type hanging construction operation platform
KR102391260B1 (en) Detachable working tool for handrail
CN202731731U (en) Foldable ladder
KR20160016132A (en) Work platporm and method using work platporm

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant