KR101692586B1 KR1020140132740A KR20140132740A KR101692586B1 KR 101692586 B1 KR101692586 B1 KR 101692586B1 KR 1020140132740 A KR1020140132740 A KR 1020140132740A KR 20140132740 A KR20140132740 A KR 20140132740A KR 101692586 B1 KR101692586 B1 KR 101692586B1
Authority
KR
South Korea
Prior art keywords
construction
finishing
type
estimate
information
Prior art date
Application number
KR1020140132740A
Other languages
Korean (ko)
Other versions
KR20160010251A (en
Inventor
윤명철
Original Assignee
윤명철
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 윤명철 filed Critical 윤명철
Priority to KR1020140132740A priority Critical patent/KR101692586B1/en
Publication of KR20160010251A publication Critical patent/KR20160010251A/en
Application granted granted Critical
Publication of KR101692586B1 publication Critical patent/KR101692586B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F17/00Digital computing or data processing equipment or methods, specially adapted for specific functions
    • G06F17/10Complex mathematical operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Abstract

본 발명은 BIM을 이용한 건축 개산견적을 위한 단위단가 정보 연산 및 분류 방법에 관한 것으로, BIM을 이용한 건축 개산견적을 위해 구조객체 및 마감 재료 구분을 위해 각 코드 선정 단계(S100a); 구조객체 및 마감 재료의 각 공사종류 분류단계(S100b); 각 공사종류에 해당하는 일위대가를 데이타베이스에서 추출하는 단계(S100d); 각 공사종류의 일위대가 합으로 건축 구조객체 및 마감 재료의 단위단가를 산정하는 단계(S100c); 단위단가 정보와 구조객체 단위체적(㎥) 및 마감 재료 단위면적(㎡)을 연산하는 BIM(S200)을 통해 건축물 정보모델에서 해당 구조객체 체적(㎥) 정보와 생성된 구조객체 단위단가가 곱셈되어 연산되는 단계(S200c); 건축물 정보모델에서 해당 마감 재료 면적(㎡) 정보와 생성된 마감 재료 단위단가가 곱셈되어 연산되는 단계(S200a); 상기 생성된 구조 코드 및 마감 코드와 상기 정보모델에 포함된 구조객체 및 마감 재료 개산견적 결과 값이 포함된 정보모델이 생성되는 단계로 하는 개산견적을 위한 단위단가 정보 연산 및 분류 방법을 제공함으로써, 구조 및 마감에 단위단가를 연계하여 건축물의 정보모델 생성과 함께 산출물량에 대해 개산견적을 실시간으로 확인할 수 있는 효과가 있다.The present invention relates to a unit price information calculation and classification method for estimating a building construction using a BIM, wherein each code selection step (S100a) for distinguishing a structural object and a finishing material for estimating an architectural approximation using the BIM; Each construction type classification step of the structural object and the finishing material (S100b); A step (S100d) of extracting a greatest value corresponding to each construction type from the database; A step (S100c) of calculating the unit price of the building structural object and the finishing material by summing the greatest of each construction type; The structural object volume (m 3) information is multiplied by the unit price of the generated structural object unit in the building information model through the BIM (S200) for calculating the unit price information, the structural object unit volume (m 3) and the finishing material unit area A step of calculating S200c; A step (S200a) in which the finishing material area (m2) information is multiplied by the generated finishing material unit price in the building information model; And generating an information model including the generated structure code and the finishing code, the structural object included in the information model, and the resultant estimating result of the finishing material estimate, by providing the unit price information calculation and classification method for the estimate estimation, It is possible to confirm the estimate estimate in real time on the output quantity of the building together with the information model of the building by linking the unit price to the structure and the finish.

Description

BIM을 이용한 건축 개산견적을 위한 단위단가 정보 연산 및 분류 방법{Composed unit cost Information for Operational Architectural Rough Estimation using BIM and Classification}[0001] The present invention relates to a method of calculating unit cost information for building estimation using a BIM,

본 발명은 BIM을 이용한 개산견적을 위한 정보모델 생성에서, 건축 구조 RC(철근콘크리트), SRC(철골철근콘크리트), SC(철골콘크리트) 및 구조부위(기초, 기둥, 보, 옹벽, 슬래브, 계단)의 콘크리트, 철근, 거푸집 정보를 포함한 코드 정보와 각 구조 공사종류 일위대가의 합인 단위체적(㎥) 단위단가를 포함한 비용 정보가, 건축물의 구조객체 체적(㎥)과의 곱셈 연산으로 개산견적 정보모델 생성을 위한 정보 연산 및 분류 방법에 관한 것이다.The present invention relates to an information model for estimating an estimate using a BIM, the method comprising the steps of: constructing an architectural structure RC (reinforced concrete), SRC (steel reinforced concrete), SC (steel concrete), and structural parts (foundation, pillar, beam, retaining wall, ) Is calculated by multiplying the structural object volume (㎥) of the building with the cost information including the code information including the concrete, reinforcing bar, and form information of the building and the unit price (㎥) And an information calculation and classification method for generating an information model.

또한, 건축 마감 부위(바닥, 벽, 천장)에 적용되는 부위별 재료 정보를 포함한 코드 정보와 각 마감 공사종류 일위대가의 합인 단위면적(㎡) 단위단가를 포함한 비용 정보가, 건축물의 마감 재료 면적(㎡)과의 곱셈 연산으로 개산견적 연산 정보모델 생성을 위한 정보 연산 및 분류 방법에 관한 것이다.In addition, the cost information including the code information including the material information per part applied to the building finishing area (floor, wall, ceiling) and the unit area (m 2) unit price, which is the sum of the finishing work type and the finishing cost, And an area (m 2) to calculate an estimate computation information model.

BIM(Building Information Modeling) 기술은 3차원 가상공간에서의 설계기술로 건설정보가 포함된 모델 생성이 가능하고, 모델 생성과 동시에 개산견적 연산과 모델 변경에 따라 자동으로 개산견적 정보 변경이 가능한 매개변수 연산으로 정보모델을 생성하는 설계 기술을 의미한다.The BIM (Building Information Modeling) technology is a 3D virtual space design model that enables construction of a model that includes construction information, Means a design technique for generating an information model by operation.

건축에 표준화를 위해 많은 연구개발이 이루어지고 있고 정부차원에서도 설계 의무화를 추진하고 있고, 최근에는 토목, 플랜트, 기계설비 분야로 확대되면서 산업전반에 기술이 가속화되고 있다.
또한, 공공 발주 공사의 BIM 기술 적용에 개산견적 적용을 의무화되면서, 기존의 2차원 형상정보 도면의 한계에서 3차원 형상의 속성정보 활용을 통한 BIM 설계가 필수적인 기술 분야로 발전하고 있다.
Many researches and developments have been made for the standardization of the construction, and the government is also making mandatory design. In recent years, technology has been accelerated in the industry as it has been expanded to civil engineering, plant and machinery facilities.
Also, as the application of the estimate estimate to the application of the BIM technology of the public ordering construction is obliged, the BIM design through the utilization of the property information of the three dimensional shape is developing as the technical field which is essential in the limit of the existing two dimensional shape information drawing.

기존 건축설계에서는 2차원 정보를 활용하여 3차원 건축물을 도면화 하면서 설계과정에 따른 시간과 인력이 낭비되고 건축물의 종합적인 도면 검토가 어려웠다.
또한, 설계변경에 따른 비효율적이고 반복적인 작업이 많아 건축설계 고유의 디자인 작업에 어려움이 있어, 건축설계 과정에 BIM 정보 모델을 활용하면, 정보모델 생성과 동시에 자동으로 개산견적이 가능하고 실시간 비용 확인이 가능하여 비용을 고려한 신뢰성 있는 건축 BIM 설계가 가능한 기술이다.
In the existing architectural design, time and manpower according to the designing process were wasted and it was difficult to review the comprehensive drawing of the building while making the 3D structure using 2D information.
In addition, since there are many inefficient and repetitive tasks due to design changes, it is difficult to design work unique to the architectural design. Therefore, when the BIM information model is used in the architectural design process, This is a technology capable of designing reliable architectural BIM considering costs.

본 발명은 건축 구조(RC, SRC, SC) 및 구조부위(기초, 기둥, 보, 옹벽, 슬래브, 계단)의 콘크리트, 철근, 거푸집 정보를 포함한 코드 정보와 각 구조 공사종류 일위대가의 합인 단위체적(㎥) 단위단가를 포함한 비용 정보가, 건축물의 구조객체 체적(㎥)과의 곱셈 연산으로 개산견적 정보모델 생성을 위한 정보 연산 및 분류 방법을 제공하고자한다.The present invention relates to a structure of a building structure (RC, SRC, SC) and structural information (base, pillar, beam, retaining wall, slab, stairs) We propose an information computation and classification method for generating an estimate estimation information model by multiplying the cost information including volume (㎥) unit price with the structure object volume (㎥) of the building.

또한, 건축 마감 부위(바닥, 벽, 천장)에 적용되는 부위별 재료 정보를 포함한 코드 정보와 각 마감 공사종류 일위대가의 합인 단위면적(㎡) 단위단가를 포함한 비용 정보가, 건축물의 마감 재료 면적(㎡)과의 곱셈 연산으로 개산견적 정보모델 생성을 위한 정보 연산 및 분류 방법을 제공하고자한다.In addition, the cost information including the code information including the material information per part applied to the building finishing area (floor, wall, ceiling) and the unit area (m 2) unit price, which is the sum of the finishing work type and the finishing cost, We propose an information computation and classification method for generating estimate information model by multiplication with area (㎡).

상기와 같은 과제를 해결하기 위해,In order to solve the above problems,

본 발명은 건축물을 구조객체 및 마감 재료 개산견적 단계로 구분하여, 구조객체는 구조 공사종류 RC, SRC, SC 중 해당 공사종류를 선별하는 단계(S300a); 상기 구조 공사종류에서 구조부위인 기초, 기둥, 보, 옹벽, 슬래브, 계단 중 해당 구조부위가 선별되는 단계(S300b); 상기 구조부위에서 구조객체 콘크리트, 거푸집, 철근, 철골 중 해당 구조객체가 선별되는 단계(S300c); 상기 구조공사종류, 구조부위, 구조객체를 포함한 구조 코드가 생성되는 단계(S310); 상기 구조객체 일위대가를 산정하기 위해 해당 공사종류를 분류하는 단계(S320a); 상기 분류한 구조객체의 공사종류별 일위대가를 데이타베이스(D/B: Data Base)에서 추출하는 단계(S320b); 상기 공사종류별 일위대가들을 합하여 단위체적(㎥) 단위단가를 산정하는 단계(S320c); 상기 구조객체의 단위체적(㎥)과 상기 단위단가가 곱셈되어 해당 구조객체의 개산견적이 산정되는 단계(S330); 상기 선정된 구조객체 코드와 상기 산정된 구조객체의 개산견적이 포함되어 구조객체 정보모델이 생성되는 단계(S340); 구조객체 정보모델의 코드와 해당 개산견적 결과가 출력되는 단계(S350);로 하는 건축물 구조 개산견적을 위한 단위단가 정보 연산 및 분류 방법을 제공한다.The present invention divides a building into a structural object and a finishing material project estimate step, and the structural object selects a construction type among the construction construction types RC, SRC, and SC (S300a); A step S300b of selecting the structural part of the foundation, the column, the beam, the retaining wall, the slab, and the stairs as the structural part in the structure construction type; A corresponding structural object among the structural object concrete, formwork, reinforcing bar, and steel frame is selected at the structural site (S300c); A step S310 of generating a structure code including the structure type, the structure part, and the structure object; (S320a) classifying the construction type to calculate the greatest value of the structural object; Extracting, in a database (D / B: Data Base), a daily maximum value for each construction type of the classified structural object (S320b); A step (S320c) of calculating the unit price (unit: m3) unit price by summing up the above-mentioned one-by- A step S330 of multiplying the unit volume m3 of the structural object by the unit price to estimate an estimate estimate of the structural object; A step S340 of generating a structural object information model by including the estimated structural object code and an estimate estimate of the estimated structural object; And a step (S350) in which the code of the structural object information model and the estimated estimation result are output (S350).

또한, 마감 재료는 마감 부위 바닥, 벽, 천장 중 해당 부위 선별 단계(S400a); 상기 마감 부위에서 해당 마감 재료가 선별되는 단계(S400b); 상기 마감 부위, 마감 재료를 포함한 마감 코드가 생성되는 단계(S410); 상기 마감 부위의 마감 재료 일위대가를 산정하기 위해 해당 공사종류를 분류하는 단계(S420a); 상기 분류한 마감 재료의 공사종류별 일위대가를 데이타베이스에서 추출하는 단계(S420b); 상기 공사종류별 일위대가들을 합하여 단위면적(㎥) 단위단가를 산정하는 단계(S420c); 상기 마감 재료 정보의 면적(㎡)과 상기 단위단가가 곱셈되어 해당 마감 재료의 개산견적이 산정되는 단계(S430); 상기 선정된 마감 코드와 상기 산정된 마감 재료 개산견적이 포함되어 마감 재료 정보모델이 생성되는 단계(S440); 마감 재료 코드와 개산견적 결과가 출력되는 단계(S450);로 하는 건축 마감 재료 개산견적을 위한 단위단가 정보 연산 및 분류 방법을 제공한다.In addition, the finishing material may include a step S400a of selecting a floor of a finishing area, a wall, or a ceiling; (S400b) the corresponding finishing material is selected at the finishing site; A step S410 of generating a finishing cord including the finishing material and the finishing material; (S420a) classifying the type of construction to calculate the upper limit of the finishing material of the finishing part; A step (S420b) of extracting, from the database, a daily maximum value for each type of construction of the classified finishing material; A step S420c of calculating the unit price per unit area (m3) by summing up the daily price for each construction type; A step (S430) in which the area (m2) of the finishing material information is multiplied by the unit price to estimate an estimate of the finishing material; (S440) a finishing material information model is generated including the selected finishing cord and the estimated finishing material estimating estimate; And a step of outputting a finishing material code and a result of an estimate (S450). The unit cost information calculation and classification method for estimating a construction finishing material estimate is provided.

또한, 상기 건축 구조 공사종류(S300a), 구조부위(S300b), 구조객체(S300c)를 포함한 구조 코드는 도 5 구성 형식을 이용하는 것이 바람직하다.In addition, it is preferable that the structure code including the construction construction type S300a, the structure part S300b, and the structure object S300c uses the configuration format of FIG.

또한, 상기 건축 마감 부위(S400a)와 마감 재료(S400b)는 도 6 구성 형식을 이용하는 것이 바람직하다.In addition, it is preferable that the construction finishing part S400a and the finishing material S400b use the configuration of Fig. 6.

또한, 상기 건축 구조객체 및 마감 재료 공사종류별 일위대가들을 합산한 단위체적(㎥) 단위단가(S320c) 및 단위면적(㎡) 단위단가(S420c)는 도 4 구성 형식이 바람직하다.In addition, the unit volume (m3) unit price S320c and the unit area (m2) unit price S420c obtained by summing the building materials of the building structural object and the finishing material construction type are preferably in the configuration shown in Fig.

또한, 건축물의 구조객체 및 마감 재료의 단위단가를 생성하기 위한 일위대가 데이타베이스(S100d)의 구성은 건설공사표준품셈 기준의 공사종류별 일위대가 기준을 하는 것이 바람직하다.In addition, it is preferable that the configuration of the one-dimensional database (S100d) for generating the unit price of the structural object and the finishing material of the building is based on the one-size standard of the construction type standard of the standard of construction construction standard.

본 발명에 의하여 건축 구조 공사종류(RC, SRC, SC) 및 구조부위(기초, 기둥, 보, 옹벽, 슬래브, 계단)의 콘크리트, 거푸집, 철근, 철골 정보를 포함한 코드 정보와 각 구조 공사종류 일위대가의 합인 단위체적(㎥) 단위단가를 포함한 비용 정보가, 건축물의 구조객체 체적(㎥)과의 곱셈 연산으로 개산견적 정보모델 생성을 위한 정보 연산 및 분류 방법에 관한 것이다. 이러한 건축 구조(RC, SRC, SC) 및 구조부위(기초, 기둥, 보, 옹벽, 슬래브, 계단)의 콘크리트, 철근, 거푸집 정보를 일괄된 코드 정보로 관리할 수 있어, 공사종류별 일위대가의 합인 단위단가 비용 정보와 연계하여 활용할 수 있다. According to the present invention, the code information including concrete, formwork, reinforcing steel and steel frame information of the construction type construction (RC, SRC, SC) and structural parts (foundation, pillar, beam, retaining wall, slab, stairs) The present invention relates to an information calculation and classification method for generating an estimate estimation information model by multiplying the cost information including the unit price (unit: m 3) unit price of the greatest value by the structural object volume (m 3) of the building. It is possible to manage concrete, reinforced concrete, and formwork information of these building structures (RC, SRC, SC) and structural parts (foundation, columns, beams, retaining walls, slabs and stairs) with collective code information. It can be used in conjunction with the unit price information of the unit of integration.

또한, 구조객체 형태와 코드 정보 및 단위단가를 연계하여 활용할 수 있다.In addition, the structure object type, code information, and unit cost can be used in conjunction with each other.

또한, 건축 구조 공사종류, 구조부위, 구조객체를 추가되어도 코드 확장이 가능하다.In addition, it is possible to extend the code even if the construction type, structure part, and structure object are added.

또한, 구조 정보모델 변경 시에도 단위단가 정보가 산출물량에 실시간 반영된 개산견적 확인이 가능하다.In addition, even when the structural information model is changed, it is possible to confirm the estimate estimate in which the unit price information is reflected in the calculated quantity in real time.

또한, 건축 구조 정보모델에 해당 코드 적용으로 내역서 산출 시 코드 정보 확인만으로 구조객체 및 해당 구조 정보모델의 개산견적 확인이 가능하다.In addition, it is possible to confirm the estimate estimate of the structural object and the corresponding structural information model only by checking the code information when calculating the statement by applying the corresponding code to the structural structural information model.

건축 마감은 건축 부위(바닥, 벽, 천장)에 적용되는 부위별 재료 정보를 포함한 코드 정보와 각 마감 공사종류 일위대가의 합인 단위면적(㎡) 단위단가를 포함한 비용 정보가, 건축물의 마감 재료 물량과의 곱셈으로 개산견적 정보모델 생성을 위한 정보 분류 방법을 제공한다. 이러한 건축 마감 분류 기준으로 일괄된 코드 정보로 관리할 수 있어, 공사종류별 일위대가의 합인 단위단가 비용 정보와 동일한 기준으로 활용할 수 있다.The construction finishing includes the cost information including the code information including the material information per site applied to the building site (floor, wall, ceiling) and the unit area (m 2) unit price, which is the sum of the finishing work type of each finishing construction, We propose an information classification method for generating estimate information model by multiplication with quantity. It is possible to manage with code information that is collectively classified by these building finishing classification standards, so that it can be utilized as the same standard as the unit cost cost information which is a sum of the unit price per construction type.

또한, 마감 재료 형태와 코드 정보 및 단위단가를 연계하여 활용할 수 있다.Further, the shape of the finishing material, the code information, and the unit price can be used in conjunction with each other.

또한, 건축 마감 재료 공사종류 정보가 추가되어도 코드 확장이 가능하다.In addition, code expansion is possible even if construction type material construction type information is added.

또한, 마감 재료 정보모델 변경 시에도 단위단가 정보가 산출물량에 실시간 반영된 개산견적 확인이 가능하다.In addition, even when the finishing material information model is changed, it is possible to confirm the estimate estimate in which the unit price information is reflected in the calculated quantity in real time.

또한, 건축 마감 재료 정보모델에 해당 코드 적용으로 내역서 산출 시 코드 정보 확인만으로 마감 재료 및 해당 마감 재료의 개산견적 확인이 가능하다.In addition, it is possible to confirm estimate information of finishing materials and corresponding finishing materials only by checking code information when calculating the statement by applying the code to the information of building finishing material information model.

도 1은 본 발명의 대표도로 건축물의 구조객체 및 마감재료에 대하여 각 코드선정, 공사종류 분류, 일위대가 데이타베이스 정보가 단위단가 생성 모듈에 적용되어, 구조객체 및 마감 재료 연산 모듈을 통한 건축물 정보모델 생성 모듈 적용 방법의 개념도.
도 2는 본 발명에서 건축물의 구조객체 개산견적 정보 연산 및 분류 방법과, 건축물의 마감 재료 개산견적 정보 연산 및 분류 방법에 대하여 구체적인 순서도.
도 4는 본 발명에서 슬래브 공사를 위해 각 공사종류분류에서 섬유보강 콘크리트의 일위대가 구성항목들의 합계를 나타낸 단위단가 사례 이미지.
도 5는 건축 구조 공사종류, 구조부위, 구조객체를 구성하는 구조코드를 나타낸 개념표.
도 6은 건축 마감 재료 부위별, 재료 코드를 구성하는 마감코트를 나타낸 개념표.
FIG. 1 is a block diagram illustrating a construction object and a finishing material according to a preferred embodiment of the present invention; FIG. A conceptual diagram of how to apply the information model generation module.
FIG. 2 is a flowchart illustrating a method for computing and classifying estimating information on a structure object, estimating information on a building, and calculating and classifying estimating information on a finishing material for a building according to the present invention.
Fig. 4 is a unit price example image showing the sum of the constituent items of the fiber reinforced concrete in each construction type classification for the slab construction in the present invention.
FIG. 5 is a conceptual table showing the structure codes of construction type, structure part, and structure object.
6 is a conceptual table showing a finishing coat constituting a material code for each building finishing material part.

이하, 도면을 참조하여 본 발명을 보다 상세하게 설명한다.
본 발명은 BIM을 이용한 건축 구조객체(콘크리트, 철근, 거푸집, 철골) 및 마감 부위(바닥, 벽, 천장)별 마감 재료를 포함한 각 코드 정보가 건축 구조객체에는 각 객체(콘크리트, 거푸집, 철근, 철골) 공사종류 단위단가와 구조객체 체적(㎥)과의 곱셈 연산 값이 건축물정보모델에 적용되고, 건축 마감 재료는 부위별 적용되는 재료 공사종류 단위단가와 재료 면적과의 곱셈 연산 값이 건축정보모델에 적용되는 개산견적을 위한 단위단가 정보 연산 및 정보 분류 방법에 관한 것으로, BIM을 이용한 건축 개산견적을 위해 구조객체 및 마감 재료 구분을 위해 각 코드 선정 단계(S100a); 구조객체 및 마감 재료의 각 공사종류 분류단계(S100b); 각 공사종류에 해당하는 일위대가를 데이타베이스에서 추출하는 단계(S100d); 각 공사종류의 일위대가 합으로 건축 구조객체 및 마감 재료의 단위단가를 산정하는 단계(S100c); 단위단가 정보와 구조객체 단위체적(㎥) 및 마감 재료 단위면적(㎡)을 연산하는 BIM(S200)을 통해 건축물 정보모델에서 해당 구조객체 체적(㎥) 정보와 생성된 구조객체 단위단가가 곱셈되어 연산되는 단계(S200c); 건축물 정보모델에서 해당 마감 재료 면적(㎡) 정보와 생성된 마감 재료 단위단가가 곱셈되어 연산되는 단계(S200a); 상기 생성된 구조 코드 및 마감 코드와 상기 정보모델에 포함된 구조객체 및 마감 재료 개산견적 결과 값이 포함된 정보모델이 생성되는 단계로 하는 개산견적을 위한 단위단가 정보 연산 및 분류 방법을 제공한다.
Hereinafter, the present invention will be described in more detail with reference to the drawings.
The present invention relates to a method and a system for constructing a structural object such as a concrete structure, a concrete structure, a concrete structure, a reinforced concrete structure, a steel structure, And the product of building type unit price and structural object volume (㎥) is applied to the building information model, and the construction finishing material is the construction material (S100a) for classification of structural objects and finishing materials for building estimate estimation using BIM; Each construction type classification step of the structural object and the finishing material (S100b); A step (S100d) of extracting a greatest value corresponding to each construction type from the database; A step (S100c) of calculating the unit price of the building structural object and the finishing material by summing the greatest of each construction type; The structural object volume (m 3) information is multiplied by the unit price of the generated structural object unit in the building information model through the BIM (S200) for calculating the unit price information, the structural object unit volume (m 3) and the finishing material unit area A step of calculating S200c; A step (S200a) in which the finishing material area (m2) information is multiplied by the generated finishing material unit price in the building information model; And generating an information model including the generated structure code and a finishing code, a structural object included in the information model, and a result of estimating a finishing material estimate, and a step of calculating and classifying the unit cost information.

건축 구조객체의 개산견적을 위한 단위단가 정보 연산 및 분류 방법은,The unit price information calculation and classification method for estimating an estimate of an architectural structure object,

도 2를 참조하여 건축 구조객체에 대하여 구체적으로 개산견적을 위한 단위단가 정보 연산 및 분류 방법을 설명하면 더욱 명백해질 것이다. 본 명세서 및 청구범위에 사용한 건축 구조객체인 콘크리트, 거푸집, 철근, 철골 4가지 객체(S300c)는 상위 건축 구조부위인 기초, 기둥, 보, 옹벽, 슬래브, 계단 중 선별한 부위(S300b)에 해당하는 객체 분류이며, 구조부위인 기초, 기둥, 보, 옹벽, 슬래브, 계단 6가지 요소는 상위 건축 구조 공사종류인 RC(철근콘크리트), SRC(철골철근콘크리트), SC(철골콘크리트) 구조 중 선별한 공사종류(S300a)에 해당하는 구조부위 분류이다. 따라서 건축 구조객체인 콘크리트, 거푸집, 철근, 철골 각 객체는 상위 분류를 포함한 객체 기준으로 도 5의 구성과 같으며, 각 구조객체는 독립적인 시스템을 구성하는 개별 요소를 의미한다.More specifically, the unit price information calculation and classification method for estimating an estimate of an architectural structure object will be described with reference to FIG. Four objects (S300c) of concrete, formwork, steel, and steel, which are the structural structural objects used in the present specification and claims, correspond to the selected part (S300b) of the base structure, the column, the beam, the retaining wall, the slab, (Steel reinforced concrete), SRC (steel reinforced concrete), and SC (steel concrete) structures, which are the top architectural structure construction types. It is a structural site classification corresponding to a construction type (S300a). Therefore, concrete object, concrete object, formwork, reinforcing steel, steel frame object, which is an object of construction, is the same as that of FIG. 5 based on object including upper classification, and each structural object means an individual element constituting an independent system.

예를 들면, RC-WAL-C 구조 코드는 철근콘크리트 공사의 옹벽에 적용된 콘크리트를 의미하고, SRC-COL-C 구조 코드는 철골철근콘크리트 공사의 기둥에 적용된 콘크리트를 의미하며, 공사종류 및 구조부위, 구조객체를 추가하면 더 많은 구조 코드 생성이 가능하다.For example, RC-WAL-C structure code means concrete applied to the retaining wall of reinforced concrete construction, SRC-COL-C structure code means concrete applied to columns of steel reinforced concrete construction, , It is possible to generate more structure codes by adding structural objects.

또한, 구조객체의 코드가 선정(S310)되면, 해당 구조객체의 일위대가를 산정하기 위해 각 콘크리트, 거푸집, 철근, 철골 객체에 적용되는 시공 기준의 공사종류를 분류(S320a)한다.When the code of the structural object is selected (S310), the construction type of the construction standard applied to each concrete, formwork, reinforcing bar, and steel frame object is classified (S320a) in order to calculate the maximum value of the structural object.

예를 들면, 철근콘크리트 기둥 객체에 적용된 공사종류는 시멘트, 모래, 자갈, 노무비(콘크리트공 인건비, 보통인부 인건비), 기구손료 등의 공사종류가 포함된다.
또한, 철근 객체에 적용된 공사종류는 소철선, 노무비(철근공, 보통인부), 기계기구 손료 등의 공사종류가 포함된다.
또한, 거푸집 객체에 적용된 공사종류는 합판, 각재, 철선, 못, 박리제, 형틀목공, 보통인부, 기구손료 등의 공사종류이 포함된다.
For example, the types of construction applied to reinforced concrete column objects include construction types such as cement, sand, gravel, labor (concrete and labor costs), and equipment finishing.
In addition, the types of construction applied to the rebar objects include the construction types such as small iron wire, labor (steel bar, ordinary laborer), and machine tool finishing.
In addition, the type of work applied to form objects includes plywood, timber, wire, nail, stripper, mold work, ordinary worker, and tool finishing.

또한, 분류한 구조객체 공사종류별 일위대가를 데이타베이스에서 추출(S320b)하여 구조객체의 각 공사종류 순서에 대입되어, 구조객체의 각 공사종류의 일위대가들을 합하여, 해당 구조객체의 단위체적(㎥) 단위단가를 산정(S320c)한다.In addition, the one-dimensional magnitude of the classified structural object construction type is extracted from the database (S320b), and the magnitude of each magnitude of each construction type of the structural object is substituted into the construction type order of the structural object, (M < 3 >) (step S320c).

예를 들면, 철근콘크리트 기둥 객체에 적용된 콘크리트의 각 공사종류 일위대가는 시멘트, 모래, 자갈, 노무비(콘크리트공 인건비, 보통인부 인건비), 손료 등의 각 공사종류를 단위체적(㎥) 당 소요되는 비용으로 환산하여 만들고, 단위체적(㎥) 당 각 공사종류의 비용인 일위대가를 합하여, 구조객체 콘크리트 단위체적(㎥) 비용인 단위단가를 산정한다.For example, each construction type of concrete applied to a reinforced concrete column object can be classified into three types, namely, cement, sand, gravel, labor cost (concrete labor cost, normal labor cost) And the unit cost of the structural object concrete unit volume (m 3) is calculated by summing the unit cost (m 3), which is the cost of each construction type, and the unit cost.

또한, 상기 구조객체(S300c)의 단위체적(㎥)과 상기 공사종류별 일위대가들을 합한 단위단가가(S320c) 곱셈 연산되어 해당 구조객체의 개산견적이 산정(S330)된다.In addition, the unit price m3 of the structural object S300c and the unit price of the building type S3 are multiplied by S320c to calculate an estimate estimate of the structural object S330.

또한, 상기 생성된 구조객체 코드(S310)와 상기 산정된 구조객체의 개산견적(S330)이 포함되어 구조객체 정보모델이 생성된다(S340).In addition, the generated structure object code (S310) and the estimate estimate (S330) of the calculated structure object are included to generate a structure object information model (S340).

또한, 구조객체 정보모델의 코드와 개산견적 결과가 출력되어 완료된다(S350).In addition, the code of the structural object information model and the estimate estimation result are outputted and completed (S350).

이와 같은 구조객체 개산견적을 위한 단위단가 정보 연산 및 분류 방법은 건축 구조부위별 객체의 선정에 따라 구조객체 단위단가와 구조객체 단위체적(㎥) 연산 결과 값과 해당 코드 정보가 출력되어 완료된다.The unit cost information calculation and classification method for estimating the structural object estimate is completed by outputting the structural object unit cost, the structural object unit volume (m3) operation result value and the corresponding code information according to the selection of the object according to the building structure part.

건축 마감 재료의 개산견적을 위한 단위단가 정보 연산 및 분류 방법은,The unit price information calculation and classification method for estimating an estimate of building finishing materials,

도 2를 참조하여 건축 마감 재료에 대하여 구체적으로 개산견적을 위한 단위단가 정보 연산 및 분류 방법을 설명하면 더욱 명백해질 것이다. 건축 마감 재료는 마감 부위 바닥(IF), 벽(IW), 천장(IC) 중 마감 재료 적용을 위한 부위를 선별(S400a)하고, 지정된 부위에 적용하고자 하는 마감 재료를 선별(S400b)하여, 마감 부위 및 마감 재료 정보를 포함한 마감 코드를 도 6과 같은 구성으로 선정(S410)한다.With reference to FIG. 2, a description will be made as to how to calculate and classify the unit price information for estimating an estimate for a building finishing material. The construction finishing material is selected in S400a for the application of the finishing material among the finishing floor IF, wall IW and IC, S400b is selected for the finishing material to be applied to the designated site, And a finishing code including the finishing material information and the finishing material information is selected (S410) as shown in FIG.

예를 들면, IF-PRO 마감 코드는 내부 바닥에 위치한 무기질 탄성방수를 의미하고, IW-GYP 마감 코드는 내부 벽에 위치한 석고보드를 의미하는 것으로, 마감 부위를 내부 및 외부로 구분하여 지정할 수 있고, 마감 재료도 추가하면 더 많은 마감 코드 생성이 가능하다.For example, the IF-PRO finishing cord refers to mineral elastic waterproofing located on the inner bottom, and the IW-GYP finishing cord refers to a gypsum board located on the inner wall. You can also create more finishing codes by adding finishing materials.

또한, 상기 선별한 마감 부위의 마감 재료의 일위대가를 산정하기 위해 해당 공사종류을 분류(S420a)한다.In addition, in order to calculate the maximum value of the finishing material of the selected finishing area, the construction type is classified (S420a).

예를 들면, 벽면 부위의 수성페인트 공사종류는 퍼티, 연마지, 도장공, 기구손료 등의 공사종류이 포함된다.For example, the types of water paint works on the wall surface include types of construction such as putty, abrasive paper, painter, and instrument finishing.

또한, 상기 분류한 마감 재료의 공사종류별 일위대가를 데이타베이스에서 추출(S420b)하여 마감 재료의 각 공사종류 순서에 대입되어, 마감 재료의 각 공사종류의 일위대가들을 합하여, 해당 마감 재료의 단위면적(㎡) 단위단가를 산정(S420c)한다.In step S420b, the maximum degree of each type of the finishing material classified by the type of construction is extracted from the database to be assigned to each type of construction type of the finishing material so that the greatest amount of each type of finishing material is combined, The unit price (unit) (m2) unit price is calculated (S420c).

예를 들면, 벽면 부위에 적용된 수성페인트 각 공사종류 일위대가는 퍼티, 연마지, 도장공, 기구손료 등의 각 공사종류를 단위면적(㎡) 당 소요되는 비용으로 환산하여 만들고, 단위면적(㎡) 당 각 공사종류의 비용인 일위대가를 합하여, 벽면 부위의 마감 재료 수성페인트 단위면적(㎡) 비용인 단위단가를 산정한다.For example, water-based paints applied to the wall surface are classified into various types of work such as putty, abrasive paper, painter, and instrument finishing, in terms of cost per unit area (㎡) Calculate unit cost, which is the unit cost of water paint (㎡) of the finishing material on the wall surface, together with the cost of each construction type.

또한, 상기 마감 재료(S400b)의 단위면적(㎡)과 상기 공사종류별 일위대가들을 합한 단위단가가(S420c) 곱셈 연산되어 해당 마감 재료의 개산견적이 산정(S430)된다.In addition, the unit cost (m2) of the finishing material (S400b) and the unit price of the work type (S420c) are multiplied to calculate the estimated cost of the finishing material (S430).

또한, 상기 생성된 마감 코드(S410)와 상기 생성된 마감 재료의 개산견적(S430)이 포함되어 마감 재료 정보모델이 생성된다(S440).In addition, a finishing material information model is generated by including the generated finishing code (S410) and the generated estimate of the finishing material (S430) (S440).

또한, 마감 재료 코드와 개산견적 결과가 출력되어 완료된다(S450).In addition, the finishing material code and the estimate estimation result are outputted and completed (S450).

이와 같은 마감 부위별 재료 개산견적을 위한 단위단가 정보 연산 및 분류 방법은 건축 마감 부위별 재료의 선정에 따라 마감 재료 단위단가와 마감 재료 단위면적(㎡) 연산 결과 값과 해당 코드 정보가 출력되어 완료된다.
다시 말해, 작업자(S100)에 의해 공사종류에 해당되는 코드선정 모듈(S100a)에서 공사종류의 대분류인 RC, SRC, SC 중 건축구조 선별(S300a)과, 공사종류의 중분류인 기초, 기둥, 보, 옹벽, 슬래브, 계단 중 구조부위 선별(S300b)과, 공사종류의 소분류인 콘크리트, 거푸집, 철근, 철골 중 구조객체를 선별(S300b)하여 공사종류를 선별하는 단계(S300) 및 작업자(S100)에 의해 마감종류에 해당되는 코드선정 모듈(S100a)에서 바닥, 벽, 천장 중 마감부위 선별(S400a)과, 무기질탄성방수, 석고보드, 시멘트몰탈, 자기질타일, 수성페인트 등 마감재료를 선별(S400b)하여 마감종류를 선별하는 단계(S400)를 수행하고,
다음에 작업자(S100)에 의해 공사종류에 해당되는 분류 모듈(S100b)에 선별된 공사종류를 대입하여 구조코드를 선정(S310)함과 동시에 구조코드에 해당되는 공사종류를 분류하는 단계(S320a) 및 작업자(S100)에 의해 마감종류에 해당되는 분류 모듈(S100b)에 선별된 마감종류를 대입하여 마감코드를 선정(S410)함과 동시에 마감코드에 해당되는 마감종류를 분류하는 단계(S420a)를 수행한다.
뒤이어, 작업자(S100)에 의해 데이타베이스(S100d)에서 공사종류의 분류에 해당되는 일위대가(S320b) 및 마감종류의 분류에 해당되는 일위대가(S420b)를 추출하여 BIM(S200)에 입력하고, BIM(S200)의 단위단가 생성 모듈(S100c)에서 건축물의 단위체적(㎥)에 대해 공사종류의 분류에 해당되는 일위대가(S320b)를 연산하여 구조의 단위단가(S320c)를 고정수치로 생성하는 단계(S320) 및 건축물의 단위면적(㎡)에 대해 마감종류의 분류에 해당되는 일위대가(S420b)를 연산하여 마감의 단위단가(S420c)를 고정수치로 생성하는 단계(S420)를 수행한 후에,
다음으로, BIM(S200)의 정보모델 생성 모듈(S200b)을 통해 건축물의 공사종류에 해당되는 정보모델 생성하는 단계(S340) 및 건축물의 마감종류에 해당되는 정보모델을 생성하는 단계(S440)를 수행한다.
따라서, BIM(S200)의 구조 개산견적 연산 모듈(S200c)에서 상기 정보모델 생성(S440)과 동시에, 정보모델의 전체체적(㎥)에 대해 구조의 단위단가(S320c)를 곱하여 구조의 개산견적을 산정하는 단계(S330)와 함께,
BIM(S200)의 마감 개산견적 연산 모듈(S200a)에서 상기 정보모델 생성(S440)과 동시에, 정보모델의 전체면적(㎡)에 대해 마감의 단위단가(S420c)를 곱하여 마감의 개산견적을 산정하는 단계(S430)를 수행하여
마지막으로, 상기 구조 개산견적 연산 모듈(S200c)로부터 정보모델에 해당되는 구조 개산견적 결과를 출력하는 단계(S350) 및 상기 마감 개산견적 연산 모듈(S200a)로부터 정보모델에 해당되는 마감 개산견적 결과를 출력하는 단계(S450)를 수행한다.
According to the unit price information calculation and classification method for estimating the material cost estimate for each finishing site, the finishing material unit price, the finishing material unit area (m2) calculation result value and the corresponding code information are outputted according to the selection of the material for each building finishing site, do.
In other words, in the code selection module (S100a) corresponding to the construction type by the worker (S100), selection of a building structure (S300a) among the major construction categories RC, SRC and SC and a basic structure, (S 300) and selecting a construction type (S 300) by selecting a structural object (S300b) from a structural wall, a retaining wall, a slab and a stair (S300b), and a structural object among concrete, form, (S400a), and a finishing material such as an inorganic elastic waterproofing, a gypsum board, a cement mortar, a magnetic material tile, and a water-based paint is selected in a code selection module (S100a) corresponding to the finishing type (S400) of selecting a finishing type,
Next, a construction code is selected (S310) by substituting the construction type selected in the classification module (S100b) corresponding to the construction type by the worker (S100) and a construction type corresponding to the construction code is classified (S320a) And a worker S100 assigns the selected finishing type to the classification module S100b corresponding to the finishing type to select a finishing code in S410 and classify the finishing type corresponding to the finishing code in operation S420a .
Subsequently, the worker S100 extracts a job corresponding to the classification of the construction type (S320b) and a job corresponding to the classification of the finishing type (S420b) in the database (S100d) and inputs it to the BIM (S320b) corresponding to the classification of the construction type with respect to the unit volume (m3) of the building in the unit unit price generation module (S100c) of the BIM (S200) to calculate the unit unit price (S320c) A step S420 of generating a fixed unit value S420c of the finishing unit by computing a unit price S420b corresponding to the classification of the finishing type with respect to the unit area m2 of the building, , ≪ / RTI >
Next, a step S340 of generating an information model corresponding to the construction type of the building through the information model creation module S200b of the BIM S200, and a step S440 of generating an information model corresponding to the type of finish of the building .
Therefore, at the same time as the above information model generation (S440) in the structure estimate calculation module S200c of the BIM (S200), the total volume (m3) of the information model is multiplied by the unit unit price S320c of the structure, Along with calculating S330,
At the same time as the above information model creation (S440) in the finish estimate estimate calculation module (S200a) of the BIM (S200), the total area (m2) of the information model is multiplied by the unit price of the finish (S420c) Step S430 is performed
Finally, a structural estimate estimate result corresponding to the information model is output from the structural estimate estimate calculation module (S200c) (S350), and a final estimate estimate result corresponding to the information model is obtained from the finish estimate estimate operation module (S200a) (S450).

상술한 바와 같이 본 발명은 BIM을 이용한 건축 개산견적을 위한 단위단가 정보 연산 및 분류 방법을 활용한, 건축 구조객체 및 마감 재료 건축정보모델 생성과정에서 실시간 개산견적 확인이 가능한 시스템 구성을 하고 있다.
또한, 건축물 정보모델에 포함된 코드와 개산견적 비용을 추출 및 비교하면 정보모델 형상 검토와 동시에 추출한 코드 정보 및 개산견적 비용을 고려할 수 있어, BIM 기술에 따른 시각적 형상, 속성정보 분류, 매개변수 연산 특징을 효과적으로 활용한 내역서 작성이 가능할 것이다.
As described above, the present invention provides a system configuration capable of confirming a real time projected estimate in the process of generating a construction information object and a building material information model using a unit price information calculation and classification method for estimating a building construction using BIM.
In addition, when extracting and comparing the code included in the building information model and the estimate cost, it is possible to consider the extracted code information and the estimate cost cost at the same time as the review of the information model shape, and the visual shape, attribute information classification, It will be possible to make a statement utilizing the features effectively.

S100 : 작업자
S100a : 공사종류 및 마감종류 코드선정 모듈
S100b : 공사종류 및 마감종류 분류 모듈
S100c : 단위단가 생성 모듈
S100d : 일위대가 데이타베이스(D/B)
S200 : BIM
S200a : 마감 개산견적 연산 모듈
S200b : 정보모델 생성 모듈
S200c : 구조 개산견적 연산 모듈
S300 : 건축 구조 공사종류별 구조부위의 구조객체 선별 단계
S300a : 구조 공사종류 RC, SRC, SC 중 공사종류 선별 단계
S300b : 구조부위 기초, 기둥, 보, 옹벽, 슬래브, 계단 선별 단계
S300c : 구조객체 콘크리트, 거푸집, 철근, 철골 선별 단계
S310 : 구조 공사종류, 구조부위, 구조객체를 포함한 구조 코드생성 단계
S320 : 단위단가 산정을 위해 공사종류 분류, 일위대가 데이타베이스 추출, 단위단가 생성 단계
S320a : 구조객체 일위대가 산정을 위해 공사종류 분류 단계
S320b : 구조객체의 공사종류별 일위대가 데이타베이스 추출 단계
S320c : 공사종류별 일위대가를 합하여 구조객체 단위단가 생성 단계
S330 : 구조객체의 단위체적(㎥)과 단위단가가 곱셈 연산되어 개산견적이 산정되는 단계
S340 : 구조객체 코드와 구조객체의 개산견적이 포함되어 구조객체 정보모델이 생성되는 단계
S350 : 구조객체 정보모델의 코드와 해당 개산견적 결과가 출력되는 단계
S400 : 마감 부위 및 마감 재료 선별 단계
S400a : 마감 부위 바닥, 벽, 천장 선별 단계
S400b : 마감 부위에 해당 마감재료 선별 단계
S410 : 마감 부위, 마감 재료를 포함한 마감 코드 생성 단계
S420 : 마감 부위의 마감 재료별 일위대가를 합하여 단위단가 생성 단계
S420a : 마감 부위의 마감재료 일위대가 산정을 위해 공사종류 분류 단계
S420b : 마감 재료의 공사종류별 일위대가 데이타베이스에서 추출 단계
S420c : 공사종류별 일위대가들을 합하여 마감 재료 단위단가를 산정하는 단계
S430 : 마감 재료 단위면적(㎡)과 단위단가가 곱셈되어 개산견적이 산정되는 단계
S440 : 마감 코드와 마감 재료 개산견적이 포함되어 마감 재료 정보모델이 생성되는 단계
S450 : 마감 재료 코드와 개산견적 결과가 출력되는 단계
S100: Worker
S100a: Construction type and finishing type code selection module
S100b: Construction type and finishing type classification module
S100c: Unit price generating module
S100d: One large database (D / B)
S200: BIM
S200a: Deadline Estimate Estimation Operation Module
S200b: Information model generation module
S200c: Estimation computation module
S300: Construction Structural Construction Selecting the structural objects of construction site by construction type
S300a: Type of construction construction Selection of construction type in RC, SRC, SC
S300b: Step of selecting structural foundation, columns, beams, retaining walls, slabs, stairs
S300c: Structural objects Concrete, formwork, steel, steel
S310: Construction code generation step including structure type, structure part, and structural object
S320: Classification of the construction type for the unit price, extraction of the database for one unit, unit price creation step
S320a: Construction category classification stage for calculation of structural objects
S320b: Extraction of database structure by construction type
S320c: Creation of unit price of structural object unit by sum of work size per construction type
S330: a step of estimating an estimate by multiplying the unit volume (m < 3 >) of the structural object by the unit price,
S340: The step of constructing the structural object information model by including the structural object code and the estimate estimate of the structural object
S350: the step of outputting the code of the structural object information model and the result of the estimation estimate
S400: Step of selecting the finishing area and the finishing material
S400a: Finishing area floor, wall, ceiling selection step
S400b: Selection of the finishing material corresponding to the finishing area
S410: Finish code creation step including finishing area, finishing material
S420: the unit cost of each finishing material is calculated
S420a: Construction type classification step for calculation of the finishing material for the finishing area
S420b: Extraction from the database of work size by work type of finishing material
S420c: Calculating the unit price of the finishing material by summing up the greatest amount per construction type
S430: the step of estimating the estimate by multiplying the unit area of the finishing material (m2) by the unit cost
S440: Step where the finish material information model is created, including the finish code and finish material estimate estimate
S450: Step of outputting the finishing material code and the result of the estimation estimate

Claims (6)

작업자(S100)에 의해 공사종류에 해당되는 코드선정 모듈(S100a)에서 공사종류의 대분류인 RC, SRC, SC 중 건축구조 선별(S300a)과, 공사종류의 중분류인 기초, 기둥, 보, 옹벽, 슬래브, 계단 중 구조부위 선별(S300b)과, 공사종류의 소분류인 콘크리트, 거푸집, 철근, 철골 중 구조객체를 선별(S300b)하여 공사종류를 선별하는 단계(S300) 및 작업자(S100)에 의해 마감종류에 해당되는 코드선정 모듈(S100a)에서 바닥, 벽, 천장 중 마감부위 선별(S400a)과, 무기질탄성방수, 석고보드, 시멘트몰탈, 자기질타일, 수성페인트 등 마감재료를 선별(S400b)하여 마감종류를 선별하는 단계(S400)와;
작업자(S100)에 의해 공사종류에 해당되는 분류 모듈(S100b)에 선별된 공사종류를 대입하여 구조코드를 선정(S310)함과 동시에 구조코드에 해당되는 공사종류를 분류하는 단계(S320a) 및 작업자(S100)에 의해 마감종류에 해당되는 분류 모듈(S100b)에 선별된 마감종류를 대입하여 마감코드를 선정(S410)함과 동시에 마감코드에 해당되는 마감종류를 분류하는 단계(S420a)와;
작업자(S100)에 의해 데이타베이스(S100d)에서 공사종류의 분류에 해당되는 일위대가(S320b) 및 마감종류의 분류에 해당되는 일위대가(S420b)를 추출하여 BIM(S200)에 입력하고, BIM(S200)의 단위단가 생성 모듈(S100c)에서 건축물의 단위체적(㎥)에 대해 공사종류의 분류에 해당되는 일위대가(S320b)를 연산하여 구조의 단위단가(S320c)를 고정수치로 생성하는 단계(S320) 및 건축물의 단위면적(㎡)에 대해 마감종류의 분류에 해당되는 일위대가(S420b)를 연산하여 마감의 단위단가(S420c)를 고정수치로 생성하는 단계(S420)와;
BIM(S200)의 정보모델 생성 모듈(S200b)을 통해 건축물의 공사종류에 해당되는 정보모델 생성하는 단계(S340) 및 건축물의 마감종류에 해당되는 정보모델을 생성하는 단계(S440)와;
BIM(S200)의 구조 개산견적 연산 모듈(S200c)에서 상기 정보모델 생성(S440)과 동시에, 정보모델의 전체체적(㎥)에 대해 구조의 단위단가(S320c)를 곱하여 구조의 개산견적을 산정하는 단계(S330)와;
BIM(S200)의 마감 개산견적 연산 모듈(S200a)에서 상기 정보모델 생성(S440)과 동시에, 정보모델의 전체면적(㎡)에 대해 마감의 단위단가(S420c)를 곱하여 마감의 개산견적을 산정하는 단계(S430)와;
상기 구조 개산견적 연산 모듈(S200c)로부터 정보모델에 해당되는 구조 개산견적 결과를 출력하는 단계(S350) 및 상기 마감 개산견적 연산 모듈(S200a)로부터 정보모델에 해당되는 마감 개산견적 결과를 출력하는 단계(S450)를 포함하는 것을 특징으로 하는 BIM을 이용한 건축 개산견적을 위한 단위단가 정보 연산 및 분류 방법.
In the code selection module S100a corresponding to the construction type by the worker S100, the building structure selection (S300a) among the major construction categories RC, SRC and SC (S300a) and the basic classification of construction type, columns, beams, retaining walls, (S300b) selecting a construction site among slabs and stairs and selecting a construction object (S300b) among concrete objects, concrete objects, formwork, reinforcing bars and steel frame objects as a construction type (S300b) A finishing material such as inorganic elastic waterproofing, a gypsum board, a cement mortar, a magnetic material tile, and a water-based paint is selected (S400b) by a code selection module S100a Selecting a kind (S400);
(S310) of assigning the selected construction type to the classification module (S100b) corresponding to the construction type by the worker (S100) and sorting the type of construction corresponding to the structure code (S320a) (S100), selecting a finishing type selected in the classification module (S100b) corresponding to the finishing type, selecting a finishing code (S410), and classifying the finishing type corresponding to the finishing code (S420a);
The worker S100 extracts the work size corresponding to the classification of the construction type in operation S320b and the largest work size S420b corresponding to the classification of the work type in the database S100d and inputs it to the BIM S200, (S320b) corresponding to the classification of the construction type with respect to the unit volume (m3) of the building in the unit unit price generation module (S100c) of the BIM (S200) A step S420 of calculating a unit price S420c corresponding to the classification of the closing type for the unit area m2 of the building and a unit price S420c for the finishing operation S420;
A step S340 of generating an information model corresponding to the construction type of the building through the information model creation module S200b of the BIM S200 and a step S440 of generating an information model corresponding to the finishing type of the building;
Simultaneously with the above-described information model generation (S440) in the structural estimate estimation calculation module (S200c) of the BIM (S200), the total volume (m3) of the information model is multiplied by the unit price of the structure (S320c) Step S330;
At the same time as the above information model creation (S440) in the finish estimate estimate calculation module (S200a) of the BIM (S200), the total area (m2) of the information model is multiplied by the unit price of the finish (S420c) Step S430;
A step S350 of outputting a structure estimation estimate corresponding to the information model from the structural estimate estimation calculation module S200c and a step of outputting a final estimation estimation result corresponding to the information model from the estimation estimation calculation module S200a (S450). The method of calculating and classifying the unit price information for estimating the building construction using the BIM.
삭제delete 삭제delete 삭제delete 삭제delete 삭제delete
KR1020140132740A 2014-10-02 2014-10-02 Composed unit cost Information for Operational Architectural Rough Estimation using BIM and Classification KR101692586B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140132740A KR101692586B1 (en) 2014-10-02 2014-10-02 Composed unit cost Information for Operational Architectural Rough Estimation using BIM and Classification

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140132740A KR101692586B1 (en) 2014-10-02 2014-10-02 Composed unit cost Information for Operational Architectural Rough Estimation using BIM and Classification

Publications (2)

Publication Number Publication Date
KR20160010251A KR20160010251A (en) 2016-01-27
KR101692586B1 true KR101692586B1 (en) 2017-01-03

Family

ID=55309534

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140132740A KR101692586B1 (en) 2014-10-02 2014-10-02 Composed unit cost Information for Operational Architectural Rough Estimation using BIM and Classification

Country Status (1)

Country Link
KR (1) KR101692586B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107944122A (en) * 2017-11-18 2018-04-20 巧夺天宫(深圳)科技有限公司 A kind of Wall Classification method, system and electronic equipment based on Building Information Model
KR20200072176A (en) 2018-12-12 2020-06-22 주식회사 대성이엔씨 Reinforcing bar classification code usage system and its application method for effective BIM
KR102303028B1 (en) 2020-12-14 2021-09-17 한국안전기술연합(주) Apparatus and Method for Calculating structure of construction
KR102598143B1 (en) 2023-03-02 2023-11-03 주식회사 파이브디위드 Method of quantity and quality control of itemized statement of cost

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101720062B1 (en) * 2016-06-28 2017-03-27 주식회사 스튜엇 프라이스 앤 파트너스 Construction Cost Management System Utilizing Partial Classifications
CN107330153B (en) * 2017-06-06 2020-10-09 中国建筑股份有限公司 Two-stage parameterization construction method for prefabricated concrete structure BIM model
CN107748824A (en) * 2017-11-06 2018-03-02 中国铁路设计集团有限公司 A kind of concrete frame core-tube system design method based on BIM technology
CN108268715B (en) * 2018-01-18 2022-03-08 东南大学 Steel bridge deck pavement construction simulation method based on BIM technology
CN110955700A (en) * 2019-11-25 2020-04-03 国网江苏省电力工程咨询有限公司 4D mode-based engineering cost lean control method and system
CN112907281A (en) * 2021-02-05 2021-06-04 广东丰帆工程咨询有限公司 Engineering cost management method and system based on BIM technology
KR102633969B1 (en) * 2023-06-27 2024-02-07 주식회사 두올테크 the amount calculation and displaying comparison management system for construction work
KR102633970B1 (en) * 2023-06-27 2024-02-07 주식회사 두올테크 the amount calculation and displaying comparison management system for remodeling construction work

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101335109B1 (en) * 2013-02-22 2013-12-03 경희대학교 산학협력단 Schematic estimation method of the frame works using building information

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101335109B1 (en) * 2013-02-22 2013-12-03 경희대학교 산학협력단 Schematic estimation method of the frame works using building information

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
윤명철, "건축설계 BIM기반 모델의 견적모델 활용 프로세스 연구", 대한건축학회 논문집 계획계 제29권 제9호(통권299호), 2013년9월, pp. 95 ~ 102*

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107944122A (en) * 2017-11-18 2018-04-20 巧夺天宫(深圳)科技有限公司 A kind of Wall Classification method, system and electronic equipment based on Building Information Model
KR20200072176A (en) 2018-12-12 2020-06-22 주식회사 대성이엔씨 Reinforcing bar classification code usage system and its application method for effective BIM
KR102303028B1 (en) 2020-12-14 2021-09-17 한국안전기술연합(주) Apparatus and Method for Calculating structure of construction
KR102598143B1 (en) 2023-03-02 2023-11-03 주식회사 파이브디위드 Method of quantity and quality control of itemized statement of cost

Also Published As

Publication number Publication date
KR20160010251A (en) 2016-01-27

Similar Documents

Publication Publication Date Title
KR101692586B1 (en) Composed unit cost Information for Operational Architectural Rough Estimation using BIM and Classification
KR101592762B1 (en) Automatic quantity calculation method for calculating rough estimate using BIM in construction design stage and information classification system
Khosakitchalert et al. Automated modification of compound elements for accurate BIM-based quantity takeoff
Brumana et al. Survey and scan to BIM model for the knowledge of built heritage and the management of conservation activities
Golghate et al. Pushover analysis of 4 storey’s reinforced concrete building
KR101264055B1 (en) Quantity take-off method using building information for schematic estimation
KR102038043B1 (en) Providing method of building cost estimate
KR20170062632A (en) Method for performing BIM-integrated productivity simulation for generating construction plan
KR20010007818A (en) System And Method For Estimate Bill Of Materials Using Two Dimensional CAD Interface
Salam HBIM-a sustainable approach for heritage buildings restoration in Egypt
KR101162458B1 (en) Method of construction planning of supertall buildings
Arif et al. BIM implementation in mall laves project construction Surabaya
Banfi et al. The Arch of Peace of Milan and its historic memory: From 3D survey and HBIM to mixed reality (VR-AR)
Jiang et al. Towards automated constructability checking: A case study of aligning design information with formwork decisions
KR101976514B1 (en) Providing method of building cost estimate
Khosakitchalert et al. Development of BIM-based quantity takeoff for light-gauge steel wall framing systems.
JP6799344B1 (en) Architectural system
Tejaswini et al. A Comparative Study on Various Stages of Level of Details in Advanced 3D Building Construction Using BIM Tools
Mehta et al. Optimization of member size and materials for multistoried RCC buildings using ETABS
Pastia 3D Printing of Buildings. Limits, Design, Advantages and Disadvantages. Could This Technique Contribute to Sustainability of Future Buildings?
Kulkarni et al. Role of Building Information Modelling in Construction
Maraqa et al. Role of Lean and VDC in Reducing Physical and Operational Waste and Environmental Impact
Scheer et al. CAD-BIM requirements for masonry design process of concrete blocks
Hasan Quantification of Construction Waste through BIM
Attia Workflows for the automation of 4D & 5D BIM models: master thesis no.: 154/II. GR-BIM

Legal Events

Date Code Title Description
G15R Request for early opening
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
AMND Amendment
GRNT Written decision to grant
X701 Decision to grant (after re-examination)
FPAY Annual fee payment

Payment date: 20191003

Year of fee payment: 4