KR101620365B1 KR1020150059465A KR20150059465A KR101620365B1 KR 101620365 B1 KR101620365 B1 KR 101620365B1 KR 1020150059465 A KR1020150059465 A KR 1020150059465A KR 20150059465 A KR20150059465 A KR 20150059465A KR 101620365 B1 KR101620365 B1 KR 101620365B1
Authority
KR
South Korea
Prior art keywords
transformer
circuit
power
contact
parallel operation
Prior art date
Application number
KR1020150059465A
Other languages
Korean (ko)
Inventor
차보영
이승철
Original Assignee
이승철
차보영
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이승철, 차보영 filed Critical 이승철
Priority to KR1020150059465A priority Critical patent/KR101620365B1/en
Application granted granted Critical
Publication of KR101620365B1 publication Critical patent/KR101620365B1/en

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/26Arrangements for eliminating or reducing asymmetry in polyphase networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The circuit-breaker is installed on the input circuit for each substation so that the ON-contact is maintained only by one of the two circuit-breakers. If power is supplied to the first transformer, the second transformer, and the third transformer, If the fault occurs in the adjacent ground transformer, keep the ON contact point of the transformer in order to operate the first transformer and the second transformer in parallel and supply the power through the DC converter and the input and output circuit breaker. 3 The transformer supplies the commercial power output to the commercial load at the tram stop via the low-pressure half.

Description

BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to a tram-

Trams for supplying power to low-rise trams in the crossover section, and underground transformers and switchboards installed in the grounds of buses.

Generally, the low-rise low-floor tram is a roadside tram that travels along a railway with a special trajectory. It has no smoke and is advantageous for improvement of the city aesthetics.

In such a low-voltage low-tension tram, the power is supplied to the vehicle through the cable in the crossover section, and the vehicle is driven using the power of the battery mounted in the vehicle during the crossover section.

At this time, depending on the characteristics of the route, the crossover section and the crosstalk section may be mixed, and the system should be stably operated in the crosstalk / crosstalk or crosstalk / crosstalk transition sections.

The conventional unguided low-elevation tram can mount the battery in the vehicle and can drive the vehicle using the energy stored in the battery even in the unguided section without a line.

In other words, the DC / DC converter is controlled so that the charging power of the battery is inputted to the inverter and converted into the AC power to propel the vehicle by driving the motor.

Claim 5 of the present invention relates to a switchboard for receiving a load in parallel, comprising: a transformer, a circuit switcher, a transformer switcher, a terminal block, a current transformer, a circuit breaker, The circuit-switching device is installed on the input circuit for each substation so that only one of the two circuit-switching devices holds the ON-contact; Terminal block is a terminal block that receives power line from low voltage section of transformer, fixes and branches it, and supplies power line to circuit breaker through current transformer; The current transformer measures the amount of current for each transformer by dividing the power line branched through the terminal block and transmits the current amount measured by the main control unit through the control line; The microprocessor main controller receives the current of the transformer receiving the power through the current transformer and maintains the OFF contact of the transformer when the use rate of the transformer is less than the manager input value input to the microprocessor. , The transformer switching unit is operated in parallel with the ON contact maintained, and when the receiving substation receives power from the other substation, the switching unit switches the contact of the circuit switching unit to the opposite contact, Parallel operation There is a load distribution automatic controller.

Seismic Design Plate and Seismic Design Plate Seismic Design Plate and Seismic Design Plate In a switchboard, a spring and a support plate are stacked inside a lower plate, a ball is placed on the plate, a top plate is covered, and air is sucked through an air inlet by a vacuum pump, The space between the plates is brought into a vacuum state, and then the electromagnetic valve is closed to fix the upper plate and the lower plate; When the earthquake is detected by the earthquake detection sensor, the control unit composed of the microprocessor opens the solenoid valve and air is sucked into the space between the upper plate and the lower plate, And the earthquake-resistant design plate is different from the earthquake-resistant plate according to whether the earthquake occurs or not by buffering vibration between the upper plate and the lower plate.

Korea Patent Registration No. 10-0993464 Switching Board Parallel Operation Load Distribution Automatic Controller Korea Patent Registration No. 10-1011388 Seismic Design Plate and Seismic Design Plate Switchboard

Even when some substations are out of power, the power supply is effectively switched to other substations, and DC power of more than 10,000 volts is supplied to the trams, and commercial power is supplied to the trams and buses. 110 to 380 volts It is installed underground in transformer and switchboard to supply direct current and alternating current. It is installed inside the waterproof concrete block in the form of finished product by reflecting the seismic design. .

It provides stable power to two faults and supplies power for various trams using three transformers.

Because it is installed in the ground, it is bad in external environment such as humidity, flood, etc., so remote monitoring control is applied.

A seismic isolation device is installed between a waterproof concrete block and a metal enclosure to produce an integrated product that reflects seismic design.

Stable two-wire faucet, effective parallel operation, dedicated tram voltage supply, power supply for general commercial power supply and battery fast charging, and waterproof concrete and metal housing integrated with seismic design. Provides various common services such as status monitoring and remote control, remote power ON / OFF for commercial power load, remote troubleshooting for simple fault, kiosk, broadcasting, tram and bus arrival guidance, security surveillance camera and Yi-Fi service.

Figure 1 is a simplified block diagram of the present invention.
Figure 2 is a schematic
Figure 3 is a simplified power supply schematic of the present invention

Underground transformer composed of automatic load distributing controller, circuit switcher, transformer switcher, first transformer, second transformer, third transformer, DC converter, low pressure panel, ground terminal block, drain pump, It is a tramp power supply switchgear which is integrated into a watertight concrete block and combined with an earthquake plate inside the waterproof concrete block.

Parallel operation Load sharing The circuit-switching unit controlled by the controller is installed on the input circuit for each substation so that the ON-contact is maintained only by one of the two circuit-switching units, and power is supplied to the first, second and third transformers, If the receiving substation is out of power, it receives power from another substation, and it is a circuit changeover device which switches the contact of the circuit changeover device to the opposite contact.

Parallel Operation The load transformer under the control of the load control automatic controller switches the transformer switcher to the ON contact when a failure occurs in the adjacent underground transformer and operates the first transformer and the second transformer in parallel to operate the DC transformer, It is a transformer switch that supplies power.

The third transformer supplies AC 110V to 380V commercial power output to the drain pump and monitoring tower via the low-pressure half.

The smart surveillance controller consists of internal surveillance camera, surveillance sensor and current transformer, and it can measure the current status, voltage, and current measured through photographed image data of the internal surveillance camera and through the circuit breaker, transformer switcher, DC converter, Temperature, humidity, leakage, and flood data measured by the data and monitoring sensors to the control center control server through the monitoring tower local server.

Parallel operation The load distribution automatic controller drives the drain pump when immersion data is detected through the monitoring sensor.

Parallel operation Load distribution Automatic controller, circuit change machine, transformer switcher, first transformer, second transformer, third transformer, DC converter, low pressure panel, ground terminal block, drain pump, smart monitoring controller are integrated into metal enclosure The ground through the ground terminal block and the bottom of the metal housing are joined to the top plate of the seismic plate and the bottom plate is combined with the waterproof concrete block surrounding the outside of the metal housing core.

Surveillance tower is composed of surveillance camera, emergency bell, tower surveillance controller, amplifier integrated speaker, warning light, floodlight, wireless router, heart defibrillator controlled by local server and remote server controlled by control center control server connected to network. It is integrated into the inside of the surveillance tower.

The control center control server is connected to the local server and receives a video image of a CCTV surveillance camera and a smart surveillance controller internal surveillance camera to a control center control server; and the control center control server controls a local server to control an amplifier- And the control center control server opens the two-way communication path through the emergency bell when the emergency bell operation is performed, and the control center control server controls the warning light and the floodlighting unit.

The tower monitoring controller is composed of a state monitoring module, an open / close monitor, and a power supply, and is installed inside the monitoring tower housing.

The control center control server transmits the door open event to the control center control server through the state monitoring module, via the commercial power source / non-contact power source, the network connection type presence / absence data, and the open / close monitor.

The power supply unit receives AC power through the surge protector and converts the AC power into DC to supply power to the monitoring tower, but controls power ON / OFF by the control of the control center control server.

The control center control server transmits the surveillance camera image and the door open event to the control center control server when the lock open detection event is generated through the two-way communication path between the control center control server and the control center control server through the monitor.

The wireless router receives an external ISP (Internet Service Provider) network and provides a wireless Internet service through a wireless router.

The local server transmits the battery charge status data to the control center control server through the wireless communication, such as daily self-defibrillator self-daily, weekly, monthly check and failure, and the battery charge status data.

Parallel operation The load distribution automatic controller receives power from other substations when the receiving substation is out of power. It switches the contact of the circuit changeover control and the contact breaker when the underground transformer fails. After switching off the contact point, it switches the transformer switching device inside the adjacent ground transformer to ON contact point. A parallel transformer, a parallel transformer, a transformer, a parallel transformer, a parallel transformer, a transformer, and a transformer. The transformer is connected in parallel with the transformer, Tram power supply switchboard CCTV surveillance camera surveillance control system.

Referring to FIG. 3, the core control method will be described in detail.

Parallel operation The load distribution automatic controller controls the switching of the contact of the circuit-breaker when the receiving substation receives power from the other substation in case of power failure.

In addition, when the ground transformer (second ground transformer) fails, the transformer switching device in the adjacent ground transformer (first ground transformer) is switched to the ON contact after the input contactor (second input breaker) (First section) through the first DC converter and the first draw-in interrupter by parallel operation of the first transformer and the second transformer inside the first transformer, (Notch-On) connected to the power supply unit, and power supply including the fault section (second section) is provided as the main feature of the present invention.

In one embodiment,

By adding a monitor, the kiosk (bus arrival guide terminal) function can be added to the lighting unit to further implement the lighting function.

In one embodiment,

The tram power supply switchgear is composed of an underground transformer consisting of a parallel operation load distribution controller, a circuit switcher, a transformer switcher, a first transformer, a second transformer, a third transformer, a DC converter, And the earthquake-resistant tram power supply switchgear and monitoring tower combined with the seismic proof plate inside the waterproof concrete block are installed in the local server receiving the remote control from the control center control server connected to the network and the CCTV surveillance camera controlled by the local server, CCTV surveillance monitoring the tram stop and trunk power supply switchboard with a monitoring tower that is integrated into the monitoring tower, such as emergency bell, IP phone, tower supervisory controller, amplifier integrated speaker, warning light, floodlight, wireless router, heart defibrillator Camera surveillance control system.

Parallel operation Load sharing The circuit-switching unit controlled by the controller is installed on the input circuit for each substation so that the ON-contact is maintained only by one of the two circuit-switching units, and power is supplied to the first, second and third transformers, If the receiving substation is out of power, it receives power from another substation, and it is a circuit changeover device which switches the contact of the circuit changeover device to the opposite contact.

Parallel Operation The load transformer under the control of the load control automatic controller switches the transformer switcher to the ON contact when a failure occurs in the adjacent underground transformer and operates the first transformer and the second transformer in parallel to operate the DC transformer, It is a transformer switch that supplies power.

The third transformer supplies the commercial power output to the surveillance tower via the low-voltage section.

The smart surveillance controller consists of internal surveillance camera, surveillance sensor and current transformer, and it can measure the current status, voltage, and current measured through photographed image data of the internal surveillance camera and through the circuit breaker, transformer switcher, DC converter, Temperature, humidity, leakage, and immersion data measured by data and surveillance sensors are transmitted to the surveillance tower.

Parallel operation Load distribution Automatic controller, circuit change machine, transformer switcher, first transformer, second transformer, third transformer, DC converter, low pressure panel, smart monitoring controller are built in the metal enclosure, Is coupled to an upper plate of an earthquake-proof plate, and the lower plate is joined with a waterproof concrete block surrounding the outside of the center of the metal housing.

The control center control server is connected to the local server and receives a video image of a CCTV surveillance camera and a smart surveillance controller internal surveillance camera to a control center control server; and the control center control server controls a local server to control an amplifier- And the control center control server opens the two-way communication path through the IP telephone when the emergency bell operation is performed, and the control center control server controls the warning light and the light emitter.

The tower monitoring controller includes a control server, a status monitoring module, an open / close monitor, a lock device, and a power supply unit, and is installed inside the monitoring tower housing.

The control center control server transmits the door open event to the control center control server through the state monitoring module, via the commercial power source / non-contact power source, the network connection type presence / absence data, and the open / close monitor.

The power supply unit receives AC power through the surge protector and converts the AC power into DC to supply power to the monitoring tower, but controls power ON / OFF by the control of the control center control server.

The control center control server transmits the surveillance camera image and the door open event to the control center control server when the lock open detection event is generated through the two-way communication path between the control center control server and the control center control server through the monitor.

The wireless router receives an external ISP (Internet Service Provider) network and provides a wireless Internet service through a wireless router.

The local server transmits its own daily, weekly, monthly failure check and failure data, and battery charge status data of the cardiac defibrillator to the control center control server through short-range wireless communication.

Parallel operation The load distribution automatic controller receives power from other substations when the receiving substation is out of power. It switches the contact of the circuit changeover control and the contact breaker when the underground transformer fails. After switching off the contact point, it switches the transformer switching device inside the adjacent ground transformer to ON contact point. Parallel tran- sistor power supply switchboard that features parallel operation and load sharing automatic controller that connects faulty section by connecting parallel connection and adjacent junctions and connecting power supply including failure section through DC converter and input breaker CCTV surveillance camera surveillance Control system.

In one embodiment,

The tram power supply switchgear is composed of an underground transformer consisting of a parallel operation load distribution controller, a circuit switcher, a transformer switcher, a first transformer, a second transformer, a third transformer, a DC converter, Tram power distribution switchgear built in one piece; Parallel operation Load sharing The circuit-switching unit controlled by the controller is installed on the input circuit for each substation so that the ON-contact is maintained only by one of the two circuit-switching units, and power is supplied to the first, second and third transformers, A circuit-switched device that converts the contact of the circuit-transferring device to the opposite contact, receiving power from another substation when the receiving substation is out of power; Parallel Operation The load transformer under the control of the load control automatic controller switches the transformer switcher to the ON contact when a failure occurs in the adjacent underground transformer and operates the first transformer and the second transformer in parallel to operate the DC transformer, A transformer switch for powering; The third transformer supplies the utility power output to the tram stop via the low-pressure half; The smart surveillance controller consists of internal surveillance camera, surveillance sensor and current transformer, and it can measure the current status, voltage, and current measured through photographed image data of the internal surveillance camera and through the circuit breaker, transformer switcher, DC converter, Temperature, humidity, leak, and flood data measured by data and surveillance sensors to the control center control server; Parallel operation The load distribution automatic controller receives power from other substations when the receiving substation is out of power. It switches the contact of the circuit changeover control and the contact breaker when the underground transformer fails. After switching off the contact point, it switches the transformer switching device inside the adjacent ground transformer to ON contact point. Parallel tran- sistor power supply switchboard that features parallel operation and load sharing automatic controller that connects faulty section by connecting parallel connection and adjacent junctions and connecting power supply including failure section through DC converter and input breaker CCTV surveillance camera surveillance Control system.

In one embodiment,

The seismic isolation plate is constructed by stacking a spring and a base plate on the bottom plate, placing the ball on the bottom plate, covering the top plate, compressing the air through the air intake port by a compression pump, and compressing the space between the upper plate and the lower plate When the earthquake is detected through the earthquake detection sensor, the control valve opens the solenoid valve and air is released to the space between the upper plate and the lower plate, And the upper plate and the lower plate are vibratable with respect to the upper plate and the lower plate by means of balls.

In one embodiment,

A tramway power distribution switchboard comprising a metal enclosure and a built-in metal enclosure and installed inside the underground waterproofing concrete, characterized in that the metal enclosure is a closed enclosure for filling nitrogen gas therein to prevent moisture generation. CCTV surveillance camera surveillance control system.

1: Insulation section (Notch-On)

Claims (9)

delete delete delete delete The tram power supply switchgear is composed of an underground transformer consisting of a parallel operation load distribution controller, a circuit switcher, a transformer switcher, a first transformer, a second transformer, a third transformer, a DC converter, Tram power distribution switchgear built in one piece;
Parallel operation Load sharing The circuit-switching unit controlled by the controller is installed on the input circuit for each substation so that the ON-contact is maintained only by one of the two circuit-switching units, and power is supplied to the first, second and third transformers, A circuit-switched device that converts the contact of the circuit-transferring device to the opposite contact, receiving power from another substation when the receiving substation is out of power;
Parallel Operation The load transformer under the control of the load control automatic controller switches the transformer switcher to the ON contact when a failure occurs in the adjacent underground transformer and operates the first transformer and the second transformer in parallel to operate the DC transformer, A transformer switch for powering;
The third transformer supplies the utility power output to the tram stop via the low-pressure half;
The smart surveillance controller consists of internal surveillance camera, surveillance sensor and current transformer, and it can measure the current status, voltage, and current measured through photographed image data of the internal surveillance camera, and through the circuit breaker, transformer switcher, DC converter, Temperature, humidity, leak, and flood data measured by data and surveillance sensors to the control center control server;
Parallel operation The load distribution automatic controller receives power from other substations when the receiving substation is out of power. It switches the contact of the circuit changeover control and the contact breaker when the underground transformer fails. After switching off the contact point, it switches the transformer switching device inside the adjacent ground transformer to ON contact point. And a parallel operation load distributing automatic controller for connecting the insulated sections by connecting the parallel operation and the adjacent branches to the ON contacts and supplying power including the fault section through the DC converter and the input and output circuit breaker.
The power line switchgear is composed of an underground transformer composed of an automatic controller for parallel operation of load distribution, a circuit switcher, a transformer switcher, a first transformer, a second transformer, a low voltage switch, and a smart surveillance controller. Switchboard;
Parallel operation Load sharing circuit switcher controlled by automatic controller is installed on the input circuit for each substation so that the ON contact is maintained only by one of the two circuit switches, so that power is supplied to the first transformer and the second transformer, A circuit-switched device that converts the contact of the circuit-change-over device to the opposite contact when receiving power from another substation;
Parallel operation The transformer switch under the control of the load distribution automatic controller switches the transformer switcher to the ON contact when a failure occurs in the adjacent ground transformer and operates the transformer in parallel with the first transformer and the second transformer, A selector;
Smart surveillance controller consists of internal surveillance camera, surveillance sensor, and current transformer, and displays the current status, voltage, current data, and surveillance measured through photographed image data of the internal surveillance camera, a circuit breaker, a transformer switcher, Temperature, humidity, leak, and flood data measured by the sensor to the control center control server;
Parallel operation The load distribution automatic controller receives power from other substations when the receiving substation is out of power. It switches the contact of the circuit changeover control and the contact breaker when the underground transformer fails. After switching off the contact point, it switches the transformer switching device inside the adjacent ground transformer to ON contact point. And a parallel operation load distributing automatic controller for connecting the insulation sections and connecting the fault sections via a breaker to connect the ON and OFF terminals of the parallel branching and adjacent branches.
delete delete delete
KR1020150059465A 2015-04-28 2015-04-28 The transforming panel supplying electric power to catenary tram KR101620365B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150059465A KR101620365B1 (en) 2015-04-28 2015-04-28 The transforming panel supplying electric power to catenary tram

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150059465A KR101620365B1 (en) 2015-04-28 2015-04-28 The transforming panel supplying electric power to catenary tram

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR1020150095932A Division KR101658360B1 (en) 2015-07-06 2015-07-06 The transforming panel supplying electric power to catenary tram and the controlling system of a CCTV

Publications (1)

Publication Number Publication Date
KR101620365B1 true KR101620365B1 (en) 2016-05-12

Family

ID=56025023

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150059465A KR101620365B1 (en) 2015-04-28 2015-04-28 The transforming panel supplying electric power to catenary tram

Country Status (1)

Country Link
KR (1) KR101620365B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110797978A (en) * 2019-10-31 2020-02-14 国网河北省电力有限公司电力科学研究院 Intelligent station terminal with edge computing capability and fault judgment method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008062680A (en) 2006-09-05 2008-03-21 Kawasaki Heavy Ind Ltd Low floor type tramcar
JP2008062880A (en) 2006-09-11 2008-03-21 Toyota Industries Corp Cargo fixing device in transporting device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008062680A (en) 2006-09-05 2008-03-21 Kawasaki Heavy Ind Ltd Low floor type tramcar
JP2008062880A (en) 2006-09-11 2008-03-21 Toyota Industries Corp Cargo fixing device in transporting device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110797978A (en) * 2019-10-31 2020-02-14 国网河北省电力有限公司电力科学研究院 Intelligent station terminal with edge computing capability and fault judgment method

Similar Documents

Publication Publication Date Title
KR101658360B1 (en) The transforming panel supplying electric power to catenary tram and the controlling system of a CCTV
CN103996986A (en) Box type energy storage transformer substation structure
CN201413939Y (en) Electrical interlocking system of inlet wire and interconnection switch for switch apparatus
CN201994576U (en) Double-bus bar fixed metallic enclosed switching device
KR101620365B1 (en) The transforming panel supplying electric power to catenary tram
KR101742600B1 (en) Distributing borad with uninterruptible function
US20230361541A1 (en) Tower, particularly for a high-voltage overhead electric transmission line, equipped with switchgear unit and related protection, command and control system
CN201178294Y (en) Automation apparatus of composite distribution network
CN102751783B (en) Switching circuit for power supplies of high-power diesel engine generator and transformer
CN201813091U (en) Single-phase preassembled box type transformer substation
CN101549655B (en) Outdoor 2 multiply 27.5 kV solid-sealing vacuum modular device of electrified railway
CN201166680Y (en) Device of electric power high-voltage measuring box for preventing electricity fraudulent use
CN203312657U (en) Mining explosion-proof type high-voltage vacuum power distribution device
CN203193175U (en) Lightning-protection double-case environmentally friendly gas-insulated metal-enclosed switchgear
CN207021223U (en) A kind of convergence control cabinet using integrated control device
CN104518440B (en) The intelligent Prefabricated high-low voltage transformer substations of 10kV
CN205811402U (en) A kind of solid insulated fully-closed killer switch equipment
CN206132883U (en) Circuit breaker heating circuit monitoring devices
CN104953703A (en) Double-power-supply control box with anti-misoperation function
CN213484519U (en) Subway contact net DC power supply integrated device
CN207926271U (en) The circuit of power of alterating and direct current isolation input for motor electric heater unit
RU45055U1 (en) LOCAL RESERVATION ITEM OF LINEAR CONSUMERS (KRUN-PMR)
CN219643423U (en) Three-station isolating switch cabinet with uninterrupted switching function
CN101800136A (en) Non-time difference double-power supply breaker
CN201307715Y (en) No-condensation fault-isolation type ring net switching station