KR101580194B1 - Socket member, composite bridge using the same and the construction method thereof. - Google Patents

Socket member, composite bridge using the same and the construction method thereof. Download PDF

Info

Publication number
KR101580194B1
KR101580194B1 KR1020150064615A KR20150064615A KR101580194B1 KR 101580194 B1 KR101580194 B1 KR 101580194B1 KR 1020150064615 A KR1020150064615 A KR 1020150064615A KR 20150064615 A KR20150064615 A KR 20150064615A KR 101580194 B1 KR101580194 B1 KR 101580194B1
Authority
KR
South Korea
Prior art keywords
concrete
socket member
steel girder
steel
bridge
Prior art date
Application number
KR1020150064615A
Other languages
Korean (ko)
Inventor
엄영호
Original Assignee
주식회사 아라엔텍
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 아라엔텍 filed Critical 주식회사 아라엔텍
Priority to KR1020150064615A priority Critical patent/KR101580194B1/en
Application granted granted Critical
Publication of KR101580194B1 publication Critical patent/KR101580194B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The socket member (200) of the present invention comprises an inserting unit (190) into which a steel girder (200) installed at the top of an abutment (10) is inserted to allow expansion and contraction of the steel girder (200), and has a structure where both side surface units, the top/bottom surface units, and the rear surface unit of the inserting unit (190) are synthesized. The composite bridge using the socket member (200) of the present invention comprises: an abutment (10); a socket member (100) installed on the top of the abutment; a steel girder (200) whose end is inserted into the socket member (100); floor plate concrete (20) formed on the top of the steel girder (200) into one body; corner unit concrete (30) formed to surround the top of the abutment (10) and the socket member (100); and, a distancing member (300) combined with the end of the floor plate concrete (20) to let the corner concrete (30) and the floor plate concrete (20) move separately while installed on the top of the steel girder (200). Since the socket member (200) considering the maximum expansion quantity and the maximum contraction quantity of the steel girder is installed, the steel girder (200) made into one body with the floor plate concrete (20) is inserted into the socket member (200) to be free from transformation by temperature, dry contraction, and creep. Therefore, expansion and contraction of the top structure, which is the girder with the floor plate concrete added, is possible while maintaining the Rahmen bridge type without an elastic support fixture, and the span length can be longer than that of a Rahmen bridge.

Description

공장제작형 소켓부재, 이와 공장제작된 강재거더를 이용한 강합성 교량 및 그 시공방법 {SOCKET MEMBER, COMPOSITE BRIDGE USING THE SAME AND THE CONSTRUCTION METHOD THEREOF.}TECHNICAL FIELD [0001] The present invention relates to a steel composite bridge using a factory-made socket member, a factory manufactured steel girder, and a construction method thereof.

본 발명은 토목 기술분야에 관한 것으로서, 상세하게는 교량 구조물 및 그 시공방법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a civil engineering field, and more particularly, to a bridge structure and a construction method thereof.

일반적인 교량 구조물은 거더교와 라멘교로 구분된다. The general bridge structure is divided into girder bridge and ramen bridge.

현재 가장 폭넓게 사용되는 거더교와 라멘교가 갖는 특징은 다음과 같다.The most widely used girder bridge and ramen bridge today have the following characteristics.

우선 거더교는 강재 또는 콘크리트로 제작된 거더를 교대위에 설치된 교좌장치(B)에 거치하고 신축이음장치를 설치한후 바닥판 콘크리트를 타설하는 공정을 갖는다.First, the girder bridge has a process of placing a girder made of steel or concrete on an alternatingly installed co-ordinate device B, installing a stretch joint device, and then pouring the bottom plate concrete.

도 3에 도시된 바와 같이 거더교는 신축이음장치(A)와 교좌장치(B)에 의해 신축거동이 가능해 진다.As shown in Fig. 3, the girder bridges can be stretched and shrunk by the expansion joint device A and the contour device B, respectively.

즉, 온도, 건조수축, Creep. 사용하중 등의 외력이 작용할때 교량의 상부구조물(거더+바닥판 콘크리트)은 신축거동이 가능하다.That is, temperature, drying shrinkage, Creep. The upper structure (girder + bottom plate concrete) of the bridge can be expanded and contracted when an external force such as working load acts.

그러나 신축이음장치(A)와 교좌장치(B)는 사용하중(차량, 도보하중 등)에 의해 일정시간 사용 후 교체가 필요한 소모성 재품으로 지속적인 유지관리가 팔요하다.However, the expansion joints (A) and the tilting device (B) are consumable items that need to be replaced after a certain period of time due to the usage load (vehicle, walking load, etc.).

또한, 집중호우와 홍수로 인한 하천범람과 범람시 발생한 부유물질에 의해서 신축이음장치(A)와 교좌장치(B)가 파손되는 문제가 있다.In addition, there is a problem that the expansion joint device (A) and the contour device (B) are damaged due to floods caused by heavy rainfall and floods and floating substances generated during flooding.

상기와 같은 유지관리의 불편함을 극복하고자 개발된 것이 라멘교형식의 교량이다. To overcome the inconvenience of maintenance as described above, it is a bridge of the bridge type.

라멘교는 신축이음장치(A)와 교좌장치(B)를 없애고, 교대부와 상부구조물(거더+바닥판 콘크리트)을 일체화 시키는 구조이다.The ramen bridge is a structure that eliminates the expansion joint (A) and the co-ordinate device (B), and integrates the shift part and the upper structure (girder + bottom plate concrete).

그러나 교대부와 상부구조물을 일체화 시켜 구조물의 유지관리가 수월해 지는 대신 장지간의 교량에는 경제성이 떨어지는 문제를 가지고 있다, However, there is a problem that the maintenance of the structure is facilitated by integrating the shift part and the superstructure,

즉, 우각부를 강절형태로 일체화 시키는 구조때문에 30m 이상의 교량에서는 온도, 건조수축, Creep. 사용하중 모두가 구조물에 외력으로 작용하게 되어 구조물의 크기가 커져 경제성이 떨어지는 문제점을 갖고 있다.In other words, due to the structure that the rudder part is integrated into the form of a wire, temperature, dry shrinkage, Creep. All of the working load acts on the structure as an external force, and the size of the structure becomes large, which leads to a problem of poor economical efficiency.

본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 강합성 교량의 지간길이를 확대시키면서, 신축이음장치와 교좌장치를 배제하여 유지관리의 편의를 도모함은 물론, 온도, 건조수축, Creep 및 사용하중에 대하여 신축거동이 가능한 강합성 교량 및 그 시공방법을 제공하는 것을 그 목적으로 한다.SUMMARY OF THE INVENTION The present invention has been made in order to solve the above-described problems, and it is an object of the present invention to provide a steel composite bridge capable of expanding the length of a steel composite bridge, And to provide a steel composite bridge capable of elongating and contracting with respect to a working load and a construction method thereof.

상기 과제의 해결을 위하여, 본 발명은 교대(10) 또는 교각(40)의 상부에 설치된 강재거더(200)의 신축거동을 허용하도록 상기 강재거더(200)가 삽입되는 삽입부(190);를 구비하고, 상기 삽입부(190)의 양 측면부, 상/하면부가 폐합된 구조를 갖는 것을 특징으로 하는 소켓부재(100)를 제시한다.In order to solve the above problems, the present invention is characterized in that an insertion portion 190 into which the steel girder 200 is inserted to allow the expansion and contraction behavior of the steel girder 200 installed on the upper part of the alternation 10 or the bridge 40 And both side portions and top / bottom portions of the inserting portion 190 are closed.

상기 소켓부재(100)의 후면부가 폐합된 구조를 갖는 것이 바람직하다.It is preferable that the rear surface portion of the socket member 100 is closed.

상기 교대(10)의 상부에 결합되는 하판부(120); 상기 하판부(120)의 상면에 결합되고, 상기 삽입부(190)를 형성하는 한쌍의 측방 폐합부(110); 외측면에 형성된 마감부(160);를 포함하는 소켓부재(100)가 바람직하다.A lower plate portion 120 coupled to an upper portion of the alternation 10; A pair of lateral closing portions 110 coupled to the upper surface of the lower plate portion 120 and forming the insertion portions 190; And a finishing portion 160 formed on the outer side of the socket member 100.

상기 하판부(120)의 상면에는 상기 강재거더(200)의 신축거동시 마찰을 방지하기 위한 슬라이딩패드(500)가 설치된 것을 특징으로 하는 소켓부재(100)가 바람직하다.The upper surface of the lower plate part 120 is preferably provided with a sliding pad 500 for preventing friction during the expansion and contraction of the steel girder 200.

상기 한쌍의 측방 폐합부(110)의 외측면에는 폐합부 스터드(130)가 형성된 것을 특징으로 하는 소켓부재(100)가 바람직하다.The socket member 100 is preferably formed on the outer side surfaces of the pair of side closing parts 110 with a closing part stud 130.

상기 교대(10)의 고정용 앵커(600)에 의해 고정되도록, 상기 하판부(120)에는 상기 고정용 앵커(600)가 관통하는 앵커공(170)이 형성된 것을 특징으로 하는 소켓부재(100)가 바람직하다.Wherein an anchor hole (170) through which the fixing anchor (600) passes is formed in the lower plate part (120) so as to be fixed by the fixing anchor (600) .

상기 강재거더(200)가 I형 단면인 경우, 상기 삽입부(190)가 상기 강재거더(200)에 대응하도록, 상기 한 쌍의 측방 폐합부(110)의 상단에는 상기 강재거더(200)의 상부플랜지가 삽입되는 상부연장부(111)가 형성되고, 상기 한 쌍의 측방 폐합부(110)의 하단에는 상기 강재거더(200)의 하부플랜지가 삽입되는 하부연장부(112)가 형성되며, 상기 앵커공(170)에 결합하는 상기 고정용 앵커(600)가 공통으로 결합하도록 하부 연장부(112)에 하부 연장부공(180)이 형성된 것을 특징으로 하는 소켓부재(100)가 바람직하다.When the steel girder 200 has an I-shaped cross section, the upper end of the pair of side closing portions 110 is formed at the upper end of the steel girder 200 so that the inserting portion 190 corresponds to the steel girder 200. An upper extension portion 111 into which the upper flange is inserted is formed and a lower extension portion 112 into which the lower flange of the steel girder 200 is inserted is formed at the lower end of the pair of side closing portions 110, The lower extension portion 112 is formed with a lower extension portion 180 so that the fixing anchor 600 coupled to the anchor hole 170 is commonly connected.

상기 소켓부재(100)를 이용한 강합성 콘크리트 교량은 상기 교대(10); 상기 교대(10)의 상부에 설치된 상기 소켓부재(100); 상기 소켓부재(100)에 단부가 삽입되는 상기 강재거더(200); 상기 강재거더(200)의 상부에 일체로 형성된 바닥판 콘크리트(20); 상기 교대(10)의 상부 및 상기 소켓부재(100)를 둘러 싸도록 형성된 우각부 콘크리트(30); 상기 우각부 콘크리트(30)와 바닥판 콘크리트(20)가 분리 거동하도록, 상기 바닥판 콘크리트(20)의 단부에 결합하고, 상기 강재거더(200)의 상부에 설치되는 이격부재(300);를 포함하는 것이 바람직하다.The steel composite concrete bridge using the socket member (100) comprises the alternating (10); The socket member (100) installed on the top of the alternating (10); The steel girder (200) having an end inserted into the socket member (100); A bottom plate concrete 20 integrally formed on the upper portion of the steel girder 200; A right angle concrete 30 formed to surround the upper portion of the alternation 10 and the socket member 100; A spacing member 300 coupled to an end of the bottom plate concrete 20 and installed on the upper portion of the steel girder 200 so that the right frame concrete 30 and the bottom plate concrete 20 are separated from each other, .

상기 소켓부재(100)를 이용한 강합성 콘크리트 교량은 상기 교각(40); 상호 반대방향을 향하도록 상기 교각(40)의 상부에 설치된 상기 소켓부재(100); 상기 소켓부재(100)의 양측의 삽입부에 단부가 삽입되는 복수의 상기 강재거더(200); 상기 강재거더(200)의 상부에 일체로 형성된 바닥판 콘크리트(20); 상기 교각(40)의 상부 및 상기 소켓부재(100)를 둘러 싸도록 형성된 교각부 콘크리트(50); 상기 교각부 콘크리트(50)와 바닥판 콘크리트(20)가 분리 거동하도록, 상기 바닥판 콘크리트(20)의 단부에 결합하고, 상기 강재거더(200)의 상부에 설치되는 이격부재(300);를 포함하는 것이 바람직하다.The steel composite concrete bridge using the socket member 100 comprises the bridge 40; The socket member (100) installed on an upper portion of the bridge pier (40) so as to face mutually opposite directions; A plurality of the steel girders 200 into which the ends are inserted into the insertion portions on both sides of the socket member 100; A bottom plate concrete 20 integrally formed on the upper portion of the steel girder 200; Pierced concrete (50) formed to surround the upper portion of the pier (40) and the socket member (100); A spacing member 300 coupled to an end of the bottom plate concrete 20 and installed on the upper portion of the steel girder 200 so that the bridge pillar concrete 50 and the bottom plate concrete 20 are separated from each other, .

상기 이격부재(300)는 상기 소켓부재(100)에 인접하도록 상기 강재거더(200)의 상부에 횡방향으로 설치되는 것이 바람직하다. The spacing member 300 is preferably installed laterally on the upper portion of the steel girder 200 so as to be adjacent to the socket member 100.

상기 이격부재(300)를 이용한 강합성 콘크리트 교량은 상기 교대(10); 상기 교대(10)의 상부에 설치된 복수의 상기 소켓부재(100); 복수의 상기 소켓부재(200)에 단부가 각각 삽입되는 복수의 상기 강재거더(200); 북수의 상기 강재거더(200)의 상부에 공통으로 결합하는 상기 바닥판 콘크리트(20); 상기 교대(10)의 상부 및 상기 복수의 소켓부재(100)를 둘러 싸도록 형성된 상기 우각부 콘크리트(30); 상기 우각부 콘크리트(30)와 바닥판 콘크리트(20)가 분리 거동하도록, 상기 바닥판 콘크리트(20)의 단부에 결합하고, 상기 복수의 강재거더(200) 단부에 공통으로 결합한 상기 이격부재(300);를 포함하는 것이 바람직하다.The steel composite concrete bridge using the spacing member (300) is formed by the alternation (10); A plurality of the socket members (100) provided on the upper portion of the shift (10); A plurality of steel girders (200) into which end portions are respectively inserted into the plurality of socket members (200); The bottom plate concrete 20 commonly connected to the upper part of the steel girder 200 of the north water; The right corner concrete 30 formed to surround the upper portion of the alternation 10 and the plurality of socket members 100; The separating member 300 is coupled to an end of the bottom plate concrete 20 and joined to the ends of the plurality of steel girders 200 so that the right and left concrete 30 and the bottom plate concrete 20 are separated from each other. ). ≪ / RTI >

상기 이격부재(300)는 상기 바닥판 콘크리트(20)의 단부가 삽입되는 함몰부(310)를 갖는 것이 바람직하다.The spacing member 300 preferably has a depression 310 into which the end of the bottom plate concrete 20 is inserted.

상기 이격부재(300)는 상기 바닥판 콘크리트(20)와 상기 이격부재(300)의 결합을 강화하도록, 상기 함몰부(310)에 이격부재 스터드(340)가 형성된 것이 바람직하다. It is preferable that the spacing member 300 is formed with a spacing member stud 340 in the depression 310 to enhance the coupling between the bottom plate concrete 20 and the spacing member 300.

상기 강재거더(200)는 "I"형 "

Figure 112015044381527-pat00001
"형, 또는 "□"형인 것이 바람직하다.The steel girder 200 is an "I"
Figure 112015044381527-pat00001
"Or""type.

상기 소켓부재(200)를 이용한 강합성 콘크리트 교량은 상기 교대(10);상기 교대(10)의 상부에 설치된 상기 소켓부재(100); 상기 소켓부재(100)에 단부가 삽입됨과 아울러, 하부플랜지 단부에 길이방향으로 장공(210)이 형성된 강재거더(200); 하판부공(170) 및 장공(210)을 공통으로 관통하여 교대에 결합하는 고정용 앵커(600); 상기 강재거더(200)의 상부 및 상기 소켓부재(100)를 둘러 싸도록 형성된 우각부 콘크리트(30); 상기 우각부 콘크리트(30)와 바닥판 콘크리트(20)가 분리 거동하도록, 상기 바닥판 콘크리트(20)의 상부에 설치되는 이격부재(300);를 포함하는 것이 바람직하다.The steel composite concrete bridge using the socket member (200) comprises the alternating (10); the socket member (100) installed on the upper portion of the alternation (10); A steel girder 200 having an end portion inserted into the socket member 100 and a long hole 210 formed in a longitudinal direction of the lower flange end; A fixing anchor 600 which passes through the lower plate holes 170 and the elongated holes 210 in common and alternately joins them; A right angle concrete 30 formed to surround the upper portion of the steel girder 200 and the socket member 100; And a spacing member 300 installed on the bottom plate concrete 20 such that the right-angle concrete 30 and the bottom-plate concrete 20 are separated from each other.

상기 소켓부재(200)를 이용한 강합성 콘크리트 교량은 상기 교대(10); 상기 교대(10)의 상부에 설치된 상기 소켓부재(100); 상기 소켓부재(100)에 단부가 삽입됨과 아울러, 하부플랜지 단부에 길이방향으로 장공(210)이 형성된 상기 강재거더(200); 상기 하부연장부공(180), 하판부공(170) 및 장공(210)을 공통으로 관통하여 교대에 결합하는 고정용 앵커(600); 상기 강재거더(200)의 상부 및 상기 소켓부재(100)를 둘러 싸도록 형성된 우각부 콘크리트(30); 상기 우각부 콘크리트(30)와 바닥판 콘크리트(20)가 분리 거동하도록, 상기 바닥판 콘크리트(20)의 상부에 설치되는 이격부재(300);를 포함하는 것이 바람직하다. The steel composite concrete bridge using the socket member (200) comprises the alternating (10); The socket member (100) installed on the top of the alternating (10); The steel girder (200) having an end portion inserted into the socket member (100) and having an elongated hole (210) formed in a longitudinal direction at a lower flange end; A fixing anchor 600 passing through the lower extension hole 180, the lower plate hole 170, and the elongated hole 210 in common and alternately engaged; A right angle concrete 30 formed to surround the upper portion of the steel girder 200 and the socket member 100; And a spacing member 300 installed on the bottom plate concrete 20 such that the right-angle concrete 30 and the bottom-plate concrete 20 are separated from each other.

본 발명은 강합성 콘크리트 교량의 시공방법으로서, 상기 교대(10)를 시공하는 교대시공단계; 상기 교대(10)의 상면에 상기 소켓부재(100)의 상기 하판부(120)를 설치하는 하판부시공단계; 상기 하판부(120) 상면에 상기 강재거더(200)를 거치하는 강재거더설치단계; 상기 소켓부재(100)의 상기 하판부(120)에 한 쌍의 상기 폐합부(110)와 상기 마감부(160)를 결합하는 소켓부마감시공단계; 상기 강재거더(200)의 상부에 횡방향으로 이격부재(300)를 설치하는 이격부재설치단계; 상기 우각부 콘크리트(30) 및 바닥판 콘크리트(20)의 타설을 위해 거푸집을 설치하는 거푸집설치단계: 상기 거푸집 설치 후, 콘크리트를 타설하는 콘크리트타설단계;의 시공방법을 갖는 것이 바람직하다.The present invention relates to a method of constructing a steel composite concrete bridge, comprising: an alternating construction step of constructing the alternation (10); A lower plate part mounting step of mounting the lower plate part 120 of the socket member 100 on the upper surface of the alternating body 10; A steel girder installation step for mounting the steel girder 200 on the upper surface of the lower plate 120; A socket part finishing step of coupling a pair of the closing part 110 and the finishing part 160 to the lower plate part 120 of the socket member 100; A step of installing a spacing member (300) in an upper portion of the steel girder (200) in a lateral direction; It is preferable that the method of the present invention includes a method of installing a concrete form for installing the right-angle concrete 30 and the bottom-floor concrete 20: a method of placing the concrete after the concrete is installed.

본 발명의 강합성 콘크리트 연속교의 시공방법으로서, 상기 교각(40)을 시공하는 교각 시공단계; 상기 교각(40)의 상면에 상기 소켓부재(100)의 상기 하판부(120)를 설치하는 하판부시공단계; 상기 하판부(120) 상면에 상기 강재거더(200)를 거치하는 강재거더설치단계; 상기 소켓부재(100)의 상기 하판부(120)에 한 쌍의 상기 폐합부(110)를 결합하는 소켓부마감시공단계; 상기 강재거더(200)의 상부에 횡방향으로 이격부재(300)를 설치하는 이격부재설치단계; 상기 교각부 콘크리트(50) 및 바닥판 콘크리트(20)의 타설을 위해 거푸집을 설치하는 거푸집설치단계:상기 거푸집 설치 후, 콘크리트를 타설하는 콘크리트타설단계;의 시공방법을 갖는 것이 바람직하다.A method of constructing a composite composite concrete continuous bridge of the present invention, comprising: a pier construction step of constructing the bridge bridge (40); A lower plate construction step of installing the lower plate portion 120 of the socket member 100 on the upper surface of the bridge pier 40; A steel girder installation step for mounting the steel girder 200 on the upper surface of the lower plate 120; A socket part finishing step of fitting a pair of the closing parts 110 to the lower plate part 120 of the socket member 100; A step of installing a spacing member (300) in an upper portion of the steel girder (200) in a lateral direction; It is preferable to have a construction method of installing a concrete form for installing the pier portion concrete 50 and the bottom plate concrete 20: a concrete pouring step for pouring concrete after the pouring of the concrete.

본 발명은 강재거더가 삽입되는 소켓부재(100)와 강재거더 상부에 설치되는 이격부재(300)를 이용하여, 교량의 지간 길이를 증대시키고, 신축이음장치(A)와 탄성받침(B) 없이 교량의 상부구조물(거더+바닥판콘크리트)이 신축거동할 수 있도록 시공된 강합성 교량 구조물을 제시한다.The present invention is characterized in that the length of a bridge is increased by using a socket member 100 in which a steel girder is inserted and a spacing member 300 provided in an upper portion of a steel girder and the length of the bridge is increased without the expansion joint device A and the elastic support B We present a steel composite bridge structure constructed so that the upper structure of the bridge (girder + bottom plate concrete) can be stretched and shrunk.

도 1 내지 도 2는 종래의 라멘 구조물을 도시한 것으로서,
도 1은 종래의 강합성 라멘교를 도시한 단면도.
도 2는 종래의 콘크리트 라멘교를 도시한 단면도.
도 3은 종래의 거더교를 도시한 단면도.
도 4는 종래의 콘크리트 연속 라멘교를 도시한 단면도.
도 5 이하는 본 발명의 실시예를 도시한 것으로서,
도 5는 교량의 제1실시예의 제1 사시도.
도 6는 교량의 제1실시예의 제2 사시도.
도 7은 소켓부재의 제1실시예의 사시도.
도 8,9은 교량의 제1실시예의 사용상태를 도시한 측면도.
도 10는 소켓부재의 제1실시예의 단면도.
도 11은 강재거더의 제1,2,3실시예의 사시도.
도 12는 소켓부재의 제2실시예의 사시도.
도 13은 강재거더와 소켓부재의 제2실시예의 단면도.
도 14은 강재거더와 소켓부재의 제3실시예의 단면도.
도 15는 이격부재의 단면도.
도 16은 연속교량의 제1실시예의 단면도.
도 17은 연속교량의 제2실시예의 단면도.
Figures 1 and 2 illustrate a conventional raymen structure,
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a cross-sectional view of a conventional steel composite ramen bridge. FIG.
2 is a cross-sectional view showing a conventional concrete raymen bridge.
3 is a sectional view showing a conventional girder bridge.
4 is a cross-sectional view of a conventional concrete continuous rammen bridge.
5 shows an embodiment of the present invention,
5 is a first perspective view of a first embodiment of a bridge;
6 is a second perspective view of a first embodiment of a bridge;
7 is a perspective view of a first embodiment of a socket member;
8 and 9 are side views showing the use state of the first embodiment of the bridge.
10 is a sectional view of a first embodiment of a socket member;
11 is a perspective view of the first, second and third embodiments of the steel girder.
12 is a perspective view of a second embodiment of the socket member;
13 is a sectional view of a second embodiment of a steel girder and a socket member.
14 is a sectional view of a third embodiment of a steel girder and a socket member.
15 is a sectional view of the spacing member.
16 is a sectional view of a first embodiment of a continuous bridge;
17 is a sectional view of a second embodiment of a continuous bridge;

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 7에 도시된 바와 같이, 본 발명에 의한 소켓부재(200)는 교대(10)또는 교각(40)의 상부에 설치된 강재거더(200)의 신축거동을 허용하도록 강재거더(200)가 삽입되는 삽입부(190);를 구비하고, 삽입부(190)의 양 측면부, 상/하면부가 폐합된 구조를 갖는다.7, the socket member 200 according to the present invention is configured such that the steel girder 200 is inserted to allow the expansion and contraction behavior of the steel girder 200 installed on the upper portion of the alternation 10 or the bridge 40 (190), and both side portions and top / bottom portions of the insertion portion (190) are closed.

위 소켓부재(200)를 이용한 강합성 교량은 교대(10); 교대(10)의 상부에 설치된 소켓부재(100); 소켓부재(100)에 단부가 삽입되는 강재거더(200); 강재거더(200)의 상부에 일체로 형성된 바닥판 콘크리트(20); 교대(10)의 상부 및 소켓부재(100)를 둘러 싸도록 형성된 우각부 콘크리트(30); 우각부 콘크리트(30)와 바닥판 콘크리트(20)가 분리 거동하도록, 바닥판 콘크리트(20)의 단부에 결합하고, 강재거더(200)의 상부에 설치되는 이격부재(300);를 포함하여 구성된다.The steel composite bridges using the upper socket member (200) are alternately (10); A socket member (100) installed on an upper portion of the shift (10); A steel girder 200 into which an end is inserted into the socket member 100; A bottom plate concrete 20 integrally formed on the upper portion of the steel girder 200; A right angle concrete 30 formed to surround the upper portion of the shift 10 and the socket member 100; And a spacing member 300 coupled to an end of the bottom plate concrete 20 and installed on the upper portion of the steel girder 200 so that the left and right concrete 30 and the bottom plate concrete 20 are separated from each other. do.

이 경우, 교대(100)에 설치된 소켓부재(100)는 강합성 거더교의 신축거동을 가능하게 한다. In this case, the socket member 100 installed in the shift 100 enables the expansion and contraction behavior of the steel composite girder bridge.

즉, 강재거더(200)의 최대신장량과 최대수축량을 고려하여 소켓부재(200)를 설치하기 때문에 바닥판콘크리트(20)와 일체화된 강재거더(200)는 소켓부재(200)에 삽입되어 온도, 건조수축, Creep에 의한 변형에 자유롭게 신축거동 할 수 있다.That is, since the socket member 200 is installed in consideration of the maximum elongation amount and the maximum shrinkage amount of the steel girder 200, the steel girder 200 integrated with the bottom plate concrete 20 is inserted into the socket member 200, It can freely expand and contract due to deformation caused by drying shrinkage and creep.

또한 종래기술에 의한 교량과 같이, 신축이음장치(A)와 교좌장치(B)가 없기 때문에 유지관리가 용이하고, 상부구조물(거더+바닥판콘크리트)의 신축거동이 가능하기 때문에 기존 라멘교 보다 긴 경간길이를 가질 수 있다.In addition, since there is no expansion joint device (A) and a tilting device (B) as in the case of a conventional bridge, it is easy to maintain and expand and contract the upper structure (girder + bottom plate concrete) It can have a long span length.

바닥판 콘크리트(20)와 우각부 콘크리트(30)는 동시에 타설되는 것이 좋다.It is preferable that the bottom plate concrete 20 and the right corner concrete 30 are simultaneously poured.

강재거더(200)의 상부에 설치된 이격부재(300) 때문에 바닥판 콘크리트와 우각부 콘크리트는 분리거동하고, 바닥판 콘크리트와 우각부 콘크리트가 분리 되어도 이격부재(300)의 상부 플랜지가 이격된 공간부를 덮고 있기 때문에 운행 차량의 덜컹거림을 방지할 수 있다.(도 9 참고)The bottom plate concrete and the right corner concrete are separated from each other due to the spacing member 300 provided on the upper portion of the steel girder 200 and the space where the upper flange of the spacer member 300 is separated from the bottom plate concrete and the right- It is possible to prevent the running vehicle from jolting. (See Fig. 9)

교량 양단의 교대부에 설치되는 소켓부재는 후면부가 폐합된 구조를 갖는 것이 바람직하다.It is preferable that the socket member provided at the alternating portions at both ends of the bridge has a structure in which the rear portion is closed.

이 경우, 소켓부재는 전면부에 강재거더가 삽입되는 삽입부가 형성되고, 후면부와 양 측면부, 상/하면부는 폐합된 구조를 취하여, 우각부 콘크리트 타설시 소켓내부로 콘크리트가 침투하는 것을 차단한다.In this case, the socket member is formed with an inserting portion into which a steel girder is inserted in the front portion, and a rear portion, both side portions, and upper and lower portions are closed so as to prevent the concrete from penetrating into the socket when the right side portion is poured.

연속교의 교각(40)에는 상호 반대방향을 향하도록 교각(40) 상부에 설치된 소켓부재(100); 소켓부재(100)의 양측의 삽입부에 단부가 삽입되는 복수의 강재거더(200); 강재거더(200)의 상부에 일체로 형성된 바닥판 콘크리트(20); 교각(40)의 상부 및 소켓부재(100)를 둘러 싸도록 형성된 교각부 콘크리트(50); 교각부 콘크리트(50)와 바닥판 콘크리트(20)가 분리거동하도록, 바닥판 콘크리트(20)의 단부에 결합하고, 강재거더(200)의 상부에 설치되는 이격부재(300)가 설치되는 것이 바람직하다.A socket member 100 installed on the bridge pier 40 so as to face mutually opposite directions; A plurality of steel girders (200) into which the ends are inserted into the insertion portions on both sides of the socket member (100); A bottom plate concrete 20 integrally formed on the upper portion of the steel girder 200; A pierced concrete 50 formed to surround the top of the pier 40 and the socket member 100; It is preferable that a spacing member 300 which is coupled to an end of the bottom plate concrete 20 and installed on the upper portion of the steel girder 200 is installed so that the bridge concrete 50 and the bottom plate concrete 20 are separated from each other Do.

기존의 연속 콘크리트 라멘교는 3경간으로 75m 까지 시공이 가능하다.Conventional continuous concrete rammen bridge can be constructed up to 75m with 3 spans.

물론 75m 이상의 연속 콘크리트 라멘교 시공이 가능하지만 교대(또는 교각)와 바닥판 콘크리트의 강절 구조로 인해 75m이상의 교량에는 적용성이 떨어지는 문제점이 있다.(도 4 참고)Of course, it is possible to apply continuous concrete rammen bridge of 75 m or more, but there is a problem that applicability is lowered to bridge of 75 m or more due to the alternation (or pier) and the structure of the bottom plate concrete.

그러나 본 발명의 소켓부재(100)를 이용한 연속교는 소켓부재(100)가 설치된 교대(10)와 교각(40)에서 강재거더(200)와 바닥판 콘크리트(20)가 신축거동을 할 수 있기 때문에 100m 이상의 연속교에도 적용이 가능하다.However, in the continuous bridge using the socket member 100 of the present invention, since the steel girder 200 and the bottom plate concrete 20 can perform the stretching and shrinking behavior at the pivot 10 and the pier 40 where the socket member 100 is installed, Therefore, it can be applied to continuous bridges over 100m.

또한, 별도의 신축이음장치(A)와 교좌장치(B)가 없기 때문에 유지관리가 용이 하다.In addition, since there is no separate expansion joint device A and the coordinate device B, maintenance is easy.

구체적으로 설명하면, 소켓부재는 교대(10)의 상부에 결합되는 하판부(120);와 하판부(120)의 상면에 결합되면서, 삽입부(190)를 형성하는 한쌍의 측방 폐합부(110); 그리고 외측면에 형성된 마감부(160);를 포함하여 구성되는 것이 바람직하다.Specifically, the socket member includes a lower plate 120 coupled to the upper portion of the shift 10, and a pair of side closure portions 110 (not shown) coupled to the upper surface of the lower plate 120, ); And a finishing unit 160 formed on the outer surface.

이 경우, 소켓부재는 하판부(120), 측방폐합부(110) 및 마감부(160)로 구성되기 때문에 소켓부재의 내측에 삽입부(190)가 형성되는 구조가 된다.In this case, since the socket member is composed of the lower plate portion 120, the side closing portion 110, and the finishing portion 160, the insertion portion 190 is formed inside the socket member.

소켓부재와 강재거더의 설치순서는 우선 하판부(120)를 설치한 후 강재거더(200)를 거치하고, 이후 측방폐합부(110)와 마감부(160)를 결합하는 공정을 취한다.The installation procedure of the socket member and the steel girder is such that the lower plate portion 120 is installed first and then the steel girder 200 is mounted and then the side closing portion 110 and the finishing portion 160 are joined.

때문에, 강재거더(200)와 소켓부재(100)를 설치하는 공정에 별도의 장비나 추가 공정이 필요하지 않아 기존 공법과 비교하여 시공성이 우수하다.Therefore, the steel girder 200 and the socket member 100 do not require additional equipment or additional steps in the process, which is superior in workability to the existing method.

뿐만아니라, 강재거더 거치 후 측방폐합부(110)와 마감부(160)의 결합에 의해 강재거더(200)를 감싸는 구조가 되기 때문에, 강재거더 거치 후 별도의 거더전도방지장치가 없더라도 강재거더가 안정한 상태를 유지하게 된다.In addition, since the steel girder 200 is enclosed by the combination of the side closing portion 110 and the finishing portion 160 after the steel girder is mounted, even if there is no separate device for preventing the falling of the steel girder, And a stable state is maintained.

강재거더가 삽입되는 소켓부재의 하판부(120) 상면에는 강재거더(200)의 신축거동시 마찰을 방지하기 위한 슬라이딩패드(500)가 설치된 것이 바람직하다.It is preferable that a sliding pad 500 is installed on the upper surface of the lower plate 120 of the socket member in which the steel girder is inserted to prevent friction during the expansion and contraction of the steel girder 200.

이 경우, 슬라이딩 패드(500)는 강재거더의 하부플랜지가 소켓부재(100)의 하판부(120) 상면에서 신축거동을 할때, 마찰 저항을 줄여주고 소음과 마찰에 의한 부재 파손을 방지한다. In this case, when the lower flange of the steel girder exerts the expansion and contraction on the upper surface of the lower plate 120 of the socket member 100, the sliding pad 500 reduces frictional resistance and prevents damage to the member due to noise and friction.

한쌍의 측방 폐합부(110)를 갖는 소켓부재의 외측면에는 폐합부 스터드(130)가 형성된 것이 바람직하다.It is preferable that the closing part studs 130 are formed on the outer surface of the socket member having the pair of side closing parts 110.

이 경우, 소켓부재(100)의 폐합부 스터드(130)에 의해 우각부 콘크리트(30)와 소켓부재는 결합력이 높아지고 균열저항성이 향상된다.In this case, the joining portion stud 130 of the socket member 100 increases the coupling force between the right-angled portion concrete 30 and the socket member, and the crack resistance is improved.

소켓부재(100)의 하판부(120)에는 교대(10)에 삽입되어 상측으로 돌출된 고정용 앵커(600)가 관통하는 앵커공(170)이 형성된 것이 바람직하다.It is preferable that the lower plate 120 of the socket member 100 is formed with an anchor holes 170 through which the fixing anchor 600 protruded upward is inserted.

이 경우, 교대(10)의 상면에 삽입 고정된 고정용 앵커(600)를 하판부 앵커공(170)에 관통시켜 고정할 수 있기 때문에 하판부(120)의 설치가 빠르고 안정적으로 이루어질 수 있다.In this case, since the fixing anchor 600 inserted and fixed on the upper surface of the shift 10 can be fixed through the lower plate anchor hole 170, the lower plate 120 can be installed quickly and stably.

또한, 교대부에서 발생할 수 있는 하판부의 시공오차를 고정용 앵커(600)와 와셔를 이용하여 보정 할 수 있다.In addition, the work error of the lower plate portion, which may occur in the alternate portion, can be corrected by using the fixing anchor 600 and the washer.

상기 와셔는 소켓부재의 하판부 하부와 교대 상부 사이의 고정용 앵커에 끼워 사용할 수 있다. The washer may be inserted into a fixing anchor between the lower portion of the lower plate portion of the socket member and the alternating upper portion.

본 발명의 소켓부재에 삽입되는 강재거더(200)가 I형 단면인 경우, 삽입부(190)가 강재거더(200)에 대응하도록, 한 쌍의 측방 폐합부(110)의 상단에는 강재거더(200)의 상부플랜지가 삽입되는 상부연장부(111)가 형성되고, 한 쌍의 측방 폐합부(110)의 하단에는 강재거더(200)의 하부플랜지가 삽입되는 하부연장부(112)가 형성되며, 앵커공(170)에 결합하는 고정용 앵커(600)가 공통으로 결합하도록 하부 연장부(112)에 하부 연장부공(180)이 형성된 소켓부재(100)인 것이 바람직하다.When the steel girder 200 to be inserted into the socket member of the present invention is an I-shaped section, the upper portion of the pair of side closing portions 110 is provided with a steel girder (not shown) so that the insertion portion 190 corresponds to the steel girder 200 The lower extension part 112 is formed at the lower end of the pair of side closing parts 110 to receive the lower flange of the steel girder 200 And the lower extension portion 112 is formed with a lower extension portion 180 such that the fixing anchor 600 coupled to the anchor hole 170 is commonly connected.

즉, 사용되는 강재거더의 형상에 맞는 소켓부재를 사용하면, 강재거더의 전도방지가 효과적으로 이루어질 수 있다.That is, by using a socket member that conforms to the shape of the steel material girder to be used, it is possible to effectively prevent the steel material girder from being conducted.

또한, 하판부 앵커공(170)과 하부 연장부(112)에 형성된 하부연장부공(180)에 고정용 앵커(600)를 공통으로 결합시키면 강재거더와 소켓부재를 신속하게 고정할 수 있다.(도 10)It is also possible to fasten the steel girder and the socket member quickly by joining the fixing anchor 600 to the lower extension portion 180 formed in the lower plate anchor hole 170 and the lower extension portion 112. 10)

강재거더(200)의 상부에 설치되는 이격부재(300)는 소켓부재(100)에 인접하도록 횡방향으로 설치되는 것이 바람직하다.It is preferable that the spacing member 300 provided on the upper portion of the steel girder 200 is installed in the lateral direction so as to be adjacent to the socket member 100.

이격부재(300)를 우각부와 바닥판 사이에 설치함으로써, 콘크리트 타설시 우각부 콘크리트(30)가 바닥판 콘크리트와 결합하는 것을 방지하기 때문에 시공성이 우수하면서도, 우각부와 바닥판의 완전 분리가 가능하여 상부구조물의 안정적인 신축구조를 이룰 수 있게 된다.(도 6)Since the spacing member 300 is disposed between the right and left bottom plates, it is possible to prevent the concrete 30 from being coupled with the bottom plate concrete when the concrete is poured, So that a stable expansion and contraction structure of the upper structure can be attained (Figure 6). [

또한, 이격부재는 강재거더의 상부에 볼트결합 또는 용접에 의해 결합되기 때문에 시공속도가 빠르다는 장점이 있다.In addition, since the spacing members are coupled to the upper part of the steel girder by bolting or welding, there is an advantage that the construction speed is fast.

본원발명에 의한 교량은, 교대(10); 교대(10)의 상부에 설치된 복수의 소켓부재(100); 복수의 소켓부재(200)에 단부가 각각 삽입되는 복수의 강재거더(200);를 포함하고, 복수의 강재거더(200)의 상부에 공통으로 결합하는 바닥판 콘크리트(20); 교대(10)의 상부 및 복수의 소켓부재(100)를 둘러 싸도록 형성된 우각부 콘크리트(30)를 포함하는 것이 바람직하다.A bridge according to the present invention comprises: an alternating (10); A plurality of socket members (100) provided on an upper portion of the shift (10); A bottom plate concrete (20) including a plurality of steel girders (200) into which end portions are respectively inserted into a plurality of socket members (200), and which are commonly connected to upper portions of a plurality of steel girders (200); It is preferable to include a right-angle concrete 30 formed to surround the upper portion of the alternation 10 and the plurality of socket members 100.

기존 거더교는 교대위에 거더본수 만큼의 교좌장치를 설치해야 하고, 거더거치시 1차 가용접을 통해 강재거더와 교좌장치를 결합해야 한다. Existing girder bridges should be installed with a number of gussets on the alternating girders, and the steel girders and the gussets should be connected through the first available girders when the girders are mounted.

이후 바닥판 타설과 가보로 타설 이후에 본 용접을 통하여 교좌장치와 거더를 본용접해야 하는 번거로움이 있다.Thereafter, it is troublesome to weld the turret device and the girder through this welding after the installation of the bottom plate and the piling.

또한, 복수개의 거더에 각각의 전도방지 장치를 설치하여 바닥판 타설 전까지 유지관리를 해야 한다.Further, each of the plurality of girders is required to be provided with an anti-reflection device so as to maintain maintenance until the bottom plate is poured.

그러나 복수의 소켓부재(100)를 이용한 강합성 교량은 복수의 강재거더(200)를 설치할 때 복수개의 소켓부재(100)와 강재거더(200)를 용이하게 설치할 수 있어 공사기간을 단축할 수 있다.However, the steel composite bridge using the plurality of socket members 100 can easily install the plurality of socket members 100 and the steel girder 200 when the plurality of steel girders 200 are installed, thereby shortening the construction period .

거더와 소켓부재의 결합이 완료되면 별도의 거더전도방지장치 또는 추가되는 용접공정이 없기 때문에 시공이 빠르고 안정적이다,When the connection between the girder and the socket member is completed, the construction is fast and stable because there is no separate girder preventing device or additional welding process,

또한, 복수의 강재거더(200)와 이격부재(300)가 격자구조로 설치되기 때문에 바닥판 콘크리트와 우각부 콘크리트의 양생 전이라도 안정적인 구조를 유지할 수 있다. In addition, since the plurality of steel girders 200 and the spacing member 300 are provided in a lattice structure, a stable structure can be maintained even before curing of the bottom plate concrete and the right corner concrete.

이격부재(300)는 바닥판 콘크리트(20)의 단부가 삽입되는 함몰부(310)를 갖는 것이 바람직하다.The separating member 300 preferably has a depression 310 into which the end of the bottom plate concrete 20 is inserted.

함몰부(310)는 바닥판 콘크리트의 단부를 보호하면서 바닥판 콘크리트와의 안정적인 결합을 가능하게 한다.(도 8)The depressions 310 enable stable coupling with the bottom plate concrete while protecting the ends of the bottom plate concrete (Figure 8).

또한, 바닥판 콘크리트(20)와 이격부재(300)의 결합을 강화하도록, 함몰부(310)에는 이격부재 스터드(340)가 형성된 것이 바람직하다. In addition, it is preferable that a spacing member stud 340 is formed in the depression 310 to enhance the coupling between the bottom plate concrete 20 and the spacing member 300.

위 경우 바닥판 콘크리트(20), 강재거더(200) 및 이격부재(300)의 결합을 더욱 견고하게 할 수 있다.The combination of the bottom plate concrete 20, the steel girder 200, and the spacing member 300 can be further strengthened.

강재거더(200)는 "I"형 "

Figure 112015044381527-pat00002
"형, 또는 "□"형인 것이 바람직하다.The steel girder 200 is an "I"
Figure 112015044381527-pat00002
"Or""type.

위 경우, 교량의 지간장(교량길이)과 교폭(교량의 폭원)에 따라 합리적인 단면을 선택하여 강재량을 줄일 수 있고, 강재거더의 본수를 조절하여 경제적인 강합성 교량의 설계를 가능하게 한다.In this case, it is possible to reduce the amount of steel by selecting a reasonable cross section according to the bridge length (bridge length) and bridge width (bridge width of bridge), and it is possible to design economical steel composite bridge by controlling the number of steel girders.

본발명에 의한 교량은 교대(10); 교대(10)의 상부에 설치된 소켓부재(100); 소켓부재(100)에 단부가 삽입됨과 아울러, 하부플랜지 단부에 길이방향으로 장공(210)이 형성된 강재거더(200); 하판부공(170) 및 장공(210)을 공통으로 관통하여 교대에 결합하는 고정용 앵커(600); 강재거더(200)의 상부 및 소켓부재(100)를 둘러 싸도록 형성된 우각부 콘크리트(30); 우각부 콘크리트(30)와 바닥판 콘크리트(20)가 분리 거동하도록, 바닥판 콘크리트(20)의 상부에 설치되는 이격부재(300);를 포함하는 것이 바람직하다. The bridge according to the present invention comprises an alternating (10); A socket member (100) installed on an upper portion of the shift (10); A steel girder (200) having an end inserted into the socket member (100) and a long hole (210) formed in a longitudinal direction at a lower flange end; A fixing anchor 600 which passes through the lower plate holes 170 and the elongated holes 210 in common and alternately joins them; A right angle concrete 30 formed to surround the upper portion of the steel girder 200 and the socket member 100; And a spacing member 300 installed on the bottom plate concrete 20 such that the right and left concave 30 and the bottom plate concrete 20 are separated from each other.

위 경우, 교대(10)에 소켓부재(100)와 "

Figure 112015044381527-pat00003
"형, 또는 "□"형의 강재거더(200)를 설치하는 구조로서, 하판부공(170), 강재거더의 하부플랜지 장공(210)에 고정용 앵커(600)를 동시에 고정 설치하기 때문에 공사기간을 단축할 수 있고, 거더의 전도를 방지할 수 있다. In this case, the socket member 100 and the "
Figure 112015044381527-pat00003
Since the fixing anchor 600 is fixed to the lower plate hole 170 and the lower flange slot 210 of the steel girder at the same time as the structure for installing the steel girder 200 of the " And it is possible to prevent the girder from being conducted.

본원발명에 의한 교량은 소켓부재(100)에 단부가 삽입됨과 아울러, 하부플랜지 단부에 길이방향으로 장공(210)이 형성된 강재거더(200); 하부연장부공(180), 하판부공(170) 및 장공(210)을 공통으로 관통하여 교대에 결합하는 고정용 앵커(600);를 포함하는 것이 바람직하다.The bridge according to the present invention comprises a steel girder (200) having an end portion inserted into a socket member (100) and a long hole (210) formed in a longitudinal direction at a lower flange end; And a fixing anchor 600 that alternately passes through the lower extension hole 180, the lower plate hole 170, and the elongated hole 210 in common.

위 경우, 교대(10)에 소켓부재(100)와 I형의 강재거더(200)를 설치하는 구조로서, 하판부공(170), 하부연장부공(180) 및 I형의 강재거더의 하부플랜지 장공(210)에 고정용 앵커(600)를 동시에 고정 설치하기 때문에 공사기간을 단축할 수 있고, 거더의 전도를 방지할 수 있다. In the above case, the socket member 100 and the I-shaped steel girder 200 are installed in the alternating system 10. The lower plate hole 170, the lower extension hole 180, and the lower flange slot of the I- Since the fixing anchor 600 is fixed and fixed to the bottom plate 210 at the same time, the construction period can be shortened and the girder can be prevented from being conducted.

본 발명에 의한 교량 시공방법은 다음 공정에 의해 이루어진다.The method of constructing a bridge according to the present invention is performed by the following process.

우선 교대(10)를 시공하고, 교대(10)의 상면에 소켓부재(100)의 하판부(120)를 설치한다.First, the alternating section 10 is installed, and the lower plate section 120 of the socket member 100 is installed on the upper surface of the alternating section 10.

위 경우, 교대에 설치되어 있는 고정용 앵커에 소켓부재의 하판부를 삽입공정하는 구조이기 때문에 시공시간이 짧고, 설치가 용이하다.In this case, since the lower plate portion of the socket member is inserted into the fixing anchor provided in the alternating structure, the construction time is short and installation is easy.

이후, 하판부(120) 상면에 강재거더(200)를 거치하고, 소켓부재(100)의 하판부(120)에 한 쌍의 폐합부(110)와 마감부(160)를 결합한다.The steel girder 200 is mounted on the upper surface of the lower plate 120 and the pair of closing portions 110 and the closing portion 160 are coupled to the lower plate 120 of the socket member 100.

이 경우, 강재거더는 별도의 전도방지 장치가 없더라도 소켓부재에 의해 안정적으로 거치된다.In this case, the steel girder is stably held by the socket member even if there is no separate anti-scattering device.

강재거더와 소켓부재의 시공이 완료되면, 강재거더(200)의 상부에 횡방향으로 이격부재(300)를 설치하고, 우각부 콘크리트(30) 및 바닥판 콘크리트(20)의 타설을 위해 거푸집을 설치한다.When the construction of the steel girder and the socket member is completed, the spacing member 300 is installed on the upper part of the steel girder 200 in the transverse direction, and the mold is poured to the right side concrete 30 and the bottom plate concrete 20 Install it.

이 경우, 강재거더와 이격부재가 격자구조로 설치되기 때문에 거푸집 설치와 콘크리트 양생공정까지 강재거더는 안정적인 상태를 유지하게 된다.In this case, since the steel girder and the spacing member are installed in a lattice structure, the steel girder remains stable until the formwork installation and the concrete curing process.

거푸집 설치 이후에는, 콘크리트를 타설하고 양생한다. After the formwork is installed, concrete is laid and cured.

본 발명에 의한 연속교 시공방법은 다음 공정에 의해 이루어 진다.The continuous casting method according to the present invention is carried out by the following process.

우선 교각(40)을 시공하고 교각(40)의 상면에 소켓부재(100)의 하판부(120)를 설치한다.The pier 40 is installed and the lower plate 120 of the socket member 100 is installed on the upper surface of the pier 40.

이후 하판부(120) 상면에 강재거더(200)를 거치하고, 소켓부재(100)의 하판부(120)에 한 쌍의 폐합부(110)를 결합한다.Thereafter, the steel girder 200 is mounted on the upper surface of the lower plate portion 120 and the pair of closing portions 110 are coupled to the lower plate portion 120 of the socket member 100.

강재거더(200)와 소켓부재(100)의 시공이 완료되면, 강재거더(200)의 상부에 횡방향으로 이격부재(300)를 설치하고, 교각부 콘크리트(50) 및 바닥판 콘크리트(20)의 타설을 위해 거푸집을 설치한다.When the construction of the steel girder 200 and the socket member 100 is finished, the spacing member 300 is installed laterally on the upper part of the steel girder 200 and the pierced concrete 50 and the bottom plate concrete 20 are installed, The mold is installed for the installation.

거푸집 설치 이후에는, 콘크리트를 타설하고 양생한다.After the formwork is installed, concrete is laid and cured.

이 경우, 신축이음장치(A)와 교좌장치(B)치 없이도 100m 이상의 연속교를 시공 할 수 있다.In this case, a continuous bridge of 100 m or more can be constructed without the expansion joint device (A) and the coordinate device (B).

이는 연속교의 교각부에 설치되는 소켓부재(100)에 의해 강재거더(200)와 바닥판 콘크리트(20)가 신축거동이 가능해 지기 때문이다.This is because the steel girder 200 and the bottom plate concrete 20 can be stretched and shrunk by the socket member 100 installed at the bridge portion of the continuous bridge.

따라서 별도의 유지관리가 필요없는 중/소하천, 지방하천에 설치되는 기존 연속 콘크리트 라멘교를 대체 할 수 있고, 연속 콘크리트 라멘교의 길이 한계를 극복할 수 있는 장점이 있다.Therefore, it is possible to replace the existing continuous concrete ramen bridge installed in the middle / small river and the local stream which does not need separate maintenance, and it is possible to overcome the limit of the length of the continuous concrete ramen bridge.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.

A : 신축이음장치 B : 탄성받침
10 : 교대 20 : 바닥판 콘크리트
30 : 우각부 콘크리트 40 : 교각
50 : 교각부 콘크리트 100 : 소켓부재
110 : 측방 폐합부 120 : 하판부
160 : 마감부 190 : 삽입부
200 : 강재거더 210 : 장공
300 : 이격부재 500 : 슬라이딩패드
600 : 고정용 앵커
A: Expansion joint B: Elastic bearing
10: alternating 20: bottom plate concrete
30: Right Angle Concrete 40: Pier
50: bridge part concrete 100: socket member
110: side closure part 120: lower plate part
160: finishing portion 190: insertion portion
200: Steel girder 210: Slot
300: spacing member 500: sliding pad
600: Fixing anchor

Claims (18)

교대(10) 또는 교각(40)의 상부에 설치된 강재거더(200)의 신축거동을 허용하도록 상기 강재거더(200)가 삽입되는 삽입부(190);를 구비하고,
상기 삽입부(190)의 양 측면부, 상/하면부가 폐합된 구조를 갖는 것을 특징으로 하는 소켓부재(100).
And an inserting portion 190 into which the steel girder 200 is inserted to allow the expansion and contraction behavior of the steel girder 200 installed on the upper part of the alternation 10 or bridge pier 40,
Wherein the inserting portion (190) has a structure in which both side portions and top / bottom portions are closed.
제1항에 있어서,
상기 소켓부재(100)의 후면부가 폐합된 구조를 갖는 것을 특징으로 하는 소켓부재(100)
The method according to claim 1,
Wherein the socket member (100) has a structure in which a rear portion of the socket member (100) is closed.
제2항에 있어서,
상기 교대(10)의 상부에 결합되는 하판부(120);
상기 하판부(120)의 상면에 결합되고, 상기 삽입부(190)를 형성하는 한쌍의 측방 폐합부(110);
외측면에 형성된 마감부(160);를 포함하는 것을 특징으로 하는 소켓부재(100).
3. The method of claim 2,
A lower plate portion 120 coupled to an upper portion of the alternation 10;
A pair of lateral closing portions 110 coupled to the upper surface of the lower plate portion 120 and forming the insertion portions 190;
And a finishing portion (160) formed on the outer side of the socket member (100).
제3항에 있어서,
상기 하판부(120)의 상면에는 상기 강재거더(200)의 신축거동시 마찰을 방지하기 위한 슬라이딩패드(500)가 설치된 것을 특징으로 하는 소켓부재(100).
The method of claim 3,
Wherein a sliding pad (500) is provided on the upper surface of the lower plate part (120) to prevent friction during the expansion and contraction of the steel girder (200).
제3항에 있어서,
상기 한쌍의 측방 폐합부(110)의 외측면에는 폐합부 스터드(130)가 형성된 것을 특징으로 하는 소켓부재(100).
The method of claim 3,
Wherein the outer side surfaces of the pair of side closing parts (110) are formed with a closing part stud (130).
제3항에 있어서,
상기 교대(10)의 고정용 앵커(600)에 의해 고정되도록,
상기 하판부(120)에는 상기 고정용 앵커(600)가 관통하는 앵커공(170)이 형성된 것을 특징으로 하는 소켓부재(100)
The method of claim 3,
Is fixed by the fixing anchor (600) of the alternating (10)
Wherein an anchor hole (170) through which the fixing anchor (600) passes is formed in the lower plate part (120)
제6항에 있어서,
상기 강재거더(200)가 I형 단면인 경우, 상기 삽입부(190)가 상기 강재거더(200)에 대응하도록,
상기 한 쌍의 측방 폐합부(110)의 상단에는 상기 강재거더(200)의 상부플랜지가 삽입되는 상부연장부(111)가 형성되고,
상기 한 쌍의 측방 폐합부(110)의 하단에는 상기 강재거더(200)의 하부플랜지가 삽입되는 하부연장부(112)가 형성되며,
상기 앵커공(170)에 결합하는 상기 고정용 앵커(600)가 공통으로 결합하도록 하부 연장부(112)에 하부 연장부공(180)이 형성된 것을 특징으로 하는 소켓부재(100).
The method according to claim 6,
When the steel girder 200 is an I-shaped section, the inserting portion 190 is formed so as to correspond to the steel girder 200,
An upper extension portion 111 is formed at an upper end of the pair of lateral closing portions 110 to insert the upper flange of the steel girder 200,
A lower extension 112 is formed at a lower end of the pair of lateral closing parts 110, into which the lower flange of the steel girder 200 is inserted,
Wherein a lower extension portion (180) is formed in the lower extension portion (112) so that the fixing anchor (600) coupled to the anchor hole (170) is commonly connected.
제3항 내지 제7항 중 어느 한 항의 소켓부재(100)를 이용한 강합성 콘크리트 교량으로서,
상기 교대(10);
상기 교대(10)의 상부에 설치된 상기 소켓부재(100);
상기 소켓부재(100)에 단부가 삽입되는 상기 강재거더(200);
상기 강재거더(200)의 상부에 일체로 형성된 바닥판 콘크리트(20);
상기 교대(10)의 상부 및 상기 소켓부재(100)를 둘러 싸도록 형성된 우각부 콘크리트(30);
상기 우각부 콘크리트(30)와 바닥판 콘크리트(20)가 분리 거동하도록, 상기 바닥판 콘크리트(20)의 단부에 결합하고, 상기 강재거더(200)의 상부에 설치되는 이격부재(300);를
포함하는 것을 특징으로 하는 강합성 콘크리트 교량.
A steel composite concrete bridge using the socket member (100) according to any one of claims 3 to 7,
Said alternating (10);
The socket member (100) installed on the top of the alternating (10);
The steel girder (200) having an end inserted into the socket member (100);
A bottom plate concrete 20 integrally formed on the upper portion of the steel girder 200;
A right angle concrete 30 formed to surround the upper portion of the alternation 10 and the socket member 100;
A spacing member 300 coupled to an end of the bottom plate concrete 20 and installed on the upper portion of the steel girder 200 so that the right frame concrete 30 and the bottom plate concrete 20 are separated from each other,
Wherein the composite bridges are made of steel.
제3항 내지 제7항 중 어느 한 항의 소켓부재(100)를 이용한 강합성 콘크리트 교량으로서
상기 교각(40);
상호 반대방향을 향하도록 상기 교각(40)의 상부에 설치된 상기 소켓부재(100);
상기 소켓부재(100)의 양측의 삽입부(190)에 단부가 삽입되는 복수의 상기 강재거더(200);
상기 강재거더(200)의 상부에 일체로 형성된 바닥판 콘크리트(20);
상기 교각(40)의 상부 및 상기 소켓부재(100)를 둘러 싸도록 형성된 교각부 콘크리트(50);
상기 교각부 콘크리트(50)와 바닥판 콘크리트(20)가 분리 거동하도록, 상기 바닥판 콘크리트(20)의 단부에 결합하고, 상기 강재거더(200)의 상부에 설치되는 이격부재(300);를
포함하는 것을 특징으로 하는 강합성 콘크리트 교량
A steel composite concrete bridge using the socket member (100) according to any one of claims 3 to 7
The bridge 40;
The socket member (100) installed on an upper portion of the bridge pier (40) so as to face mutually opposite directions;
A plurality of the steel girders 200 into which the ends are inserted into the inserting portions 190 on both sides of the socket member 100;
A bottom plate concrete 20 integrally formed on the upper portion of the steel girder 200;
Pierced concrete (50) formed to surround the upper portion of the pier (40) and the socket member (100);
A spacing member 300 coupled to an end of the bottom plate concrete 20 and installed on the upper portion of the steel girder 200 so that the bridge pillar concrete 50 and the bottom plate concrete 20 are separated from each other,
A steel composite concrete bridge characterized by comprising
제8항에 있어서,
상기 이격부재(300)는 상기 소켓부재(100)에 인접하도록 상기 강재거더(200)의 상부에 횡방향으로 설치되는 것을 특징으로 하는 강합성 콘크리트 교량.
9. The method of claim 8,
Wherein the spacing member (300) is installed laterally on the upper portion of the steel girder (200) so as to be adjacent to the socket member (100).
제10항에 있어서,
상기 교대(10);
상기 교대(10)의 상부에 설치된 복수의 상기 소켓부재(100);
복수의 상기 소켓부재(200)에 단부가 각각 삽입되는 복수의 상기 강재거더(200);
북수의 상기 강재거더(200)의 상부에 공통으로 결합하는 상기 바닥판 콘크리트(20);
상기 교대(10)의 상부 및 상기 복수의 소켓부재(100)를 둘러 싸도록 형성된 상기 우각부 콘크리트(30);
상기 우각부 콘크리트(30)와 바닥판 콘크리트(20)가 분리 거동하도록, 상기 바닥판 콘크리트(20)의 단부에 결합하고, 상기 복수의 강재거더(200) 단부에 공통으로 결합한 상기 이격부재(300);를
포함하는 것을 특징으로 하는 강합성 콘크리트 교량.
11. The method of claim 10,
Said alternating (10);
A plurality of the socket members (100) provided on the upper portion of the shift (10);
A plurality of steel girders (200) into which end portions are respectively inserted into the plurality of socket members (200);
The bottom plate concrete 20 commonly connected to the upper part of the steel girder 200 of the north water;
The right corner concrete 30 formed to surround the upper portion of the alternation 10 and the plurality of socket members 100;
The separating member 300 is coupled to an end of the bottom plate concrete 20 and joined to the ends of the plurality of steel girders 200 so that the right and left concrete 30 and the bottom plate concrete 20 are separated from each other. );
Wherein the composite bridges are made of steel.
제8항에 있어서,
상기 이격부재(300)는 상기 바닥판 콘크리트(20)의 단부가 삽입되는 함몰부(310)를 갖는 것을 특징으로 하는 강합성 콘크리트 교량.
9. The method of claim 8,
Wherein the spacing member (300) has a depression (310) into which the end of the bottom plate concrete (20) is inserted.
제12항에 있어서,
상기 바닥판 콘크리트(20)와 상기 이격부재(300)의 결합을 강화하도록,
상기 함몰부(310)에는 이격부재 스터드(340)가 형성된 것을 특징으로 하는 강합성 콘크리트 교량.
13. The method of claim 12,
To strengthen the coupling between the bottom plate concrete (20) and the spacing member (300)
And a spacing member stud (340) is formed on the depression (310).
제8항에 있어서,
상기 강재거더(200)는 "I"형 "
Figure 112015108373743-pat00004
"형, 또는 "□"형인 것을 특징으로 하는 강합성 콘크리트 교량.
9. The method of claim 8,
The steel girder 200 is an "I"
Figure 112015108373743-pat00004
Type "or""type.
제6항의 소켓부재(200)를 이용한 강합성 콘크리트 교량으로서,
상기 교대(10);
상기 교대(10)의 상부에 설치된 상기 소켓부재(100);
상기 소켓부재(100)에 단부가 삽입됨과 아울러,
하부플랜지 단부에 길이방향으로 장공(210)이 형성된 강재거더(200);
하판부공(170) 및 장공(210)을 공통으로 관통하여 교대에 결합하는 고정용 앵커(600);
상기 강재거더(200)의 상부 및 상기 소켓부재(100)를 둘러 싸도록 형성된 우각부 콘크리트(30);
상기 우각부 콘크리트(30)와 바닥판 콘크리트(20)가 분리 거동하도록, 상기 바닥판 콘크리트(20)의 상부에 설치되는 이격부재(300);를 포함하는 것을 특징으로 하는 강합성 콘크리트 교량.
A steel composite concrete bridge using the socket member (200) of claim 6,
Said alternating (10);
The socket member (100) installed on the top of the alternating (10);
An end portion is inserted into the socket member 100,
A steel girder 200 having an elongated hole 210 formed in a longitudinal direction at a lower flange end;
A fixing anchor 600 which passes through the lower plate holes 170 and the elongated holes 210 in common and alternately joins them;
A right angle concrete 30 formed to surround the upper portion of the steel girder 200 and the socket member 100;
And a spacing member (300) installed on the bottom plate concrete (20) so that the right frame concrete (30) and the bottom plate concrete (20) are separated from each other.
제7항의 소켓부재(200)를 이용한 강합성 콘크리트 교량으로서,
상기 교대(10);
상기 교대(10)의 상부에 설치된 상기 소켓부재(100);
상기 소켓부재(100)에 단부가 삽입됨과 아울러,
하부플랜지 단부에 길이방향으로 장공(210)이 형성된 상기 강재거더(200);
상기 하부연장부공(180), 하판부공(170) 및 장공(210)을 공통으로 관통하여 교대에 결합하는 고정용 앵커(600);
상기 강재거더(200)의 상부 및 상기 소켓부재(100)를 둘러 싸도록 형성된 우각부 콘크리트(30);
상기 우각부 콘크리트(30)와 바닥판 콘크리트(20)가 분리 거동하도록, 상기 바닥판 콘크리트(20)의 상부에 설치되는 이격부재(300);를 포함하는 것을 특징으로 하는 강합성 콘크리트 교량.
A steel composite concrete bridge using the socket member (200) of claim 7,
Said alternating (10);
The socket member (100) installed on the top of the alternating (10);
An end portion is inserted into the socket member 100,
The steel girder (200) having a slot (210) formed in the longitudinal direction at a lower flange end;
A fixing anchor 600 passing through the lower extension hole 180, the lower plate hole 170, and the elongated hole 210 in common and alternately engaged;
A right angle concrete 30 formed to surround the upper portion of the steel girder 200 and the socket member 100;
And a spacing member (300) installed on the bottom plate concrete (20) so that the right frame concrete (30) and the bottom plate concrete (20) are separated from each other.
제8항의 강합성 콘크리트 교량의 시공방법으로서,
상기 교대(10)를 시공하는 교대시공단계;
상기 교대(10)의 상면에 상기 소켓부재(100)의 상기 하판부(120)를 설치하는 하판부시공단계;
상기 하판부(120) 상면에 상기 강재거더(200)를 거치하는 강재거더설치단계;
상기 소켓부재(100)의 상기 하판부(120)에 한 쌍의 상기 폐합부(110)와 마감부(160)를 결합하는 소켓부마감시공단계;
상기 강재거더(200)의 상부에 횡방향으로 이격부재(300)를 설치하는 이격부재설치단계;
상기 우각부 콘크리트(30) 및 바닥판 콘크리트(20)의 타설을 위해 거푸집을 설치하는 거푸집설치단계:
상기 거푸집 설치 후, 콘크리트를 타설하는 콘크리트타설단계;를 포함하는 것을 특징으로 하는 교량구조물 시공방법.
A method of constructing a composite composite concrete bridge of claim 8,
An alternating construction step for constructing the alternation (10);
A lower plate part mounting step of mounting the lower plate part 120 of the socket member 100 on the upper surface of the alternating body 10;
A steel girder installation step for mounting the steel girder 200 on the upper surface of the lower plate 120;
A socket part finishing step of joining the pair of closing parts 110 and the finishing part 160 to the lower plate part 120 of the socket member 100;
A step of installing a spacing member (300) in an upper portion of the steel girder (200) in a lateral direction;
A mold setting step for setting a mold for pouring the right-angle concrete 30 and the bottom-plate concrete 20;
And a concrete pouring step of pouring concrete after the mold is installed.
제9항의 강합성 콘크리트 교량의 시공방법으로서,
상기 교각(40)을 시공하는 교각 시공단계;
상기 교각(40)의 상면에 상기 소켓부재(100)의 상기 하판부(120)를 설치하는 하판부시공단계;
상기 하판부(120) 상면에 상기 강재거더(200)를 거치하는 강재거더설치단계;
상기 소켓부재(100)의 상기 하판부(120)에 한 쌍의 상기 폐합부(110)를 결합하는 소켓부마감시공단계;
상기 강재거더(200)의 상부에 횡방향으로 이격부재(300)를 설치하는 이격부재설치단계;
상기 교각부 콘크리트(50) 및 바닥판 콘크리트(20)의 타설을 위해 거푸집을 설치하는 거푸집설치단계:
상기 거푸집 설치 후, 콘크리트를 타설하는 콘크리트타설단계;를 포함하는 것을 특징으로 하는 교량구조물 시공방법.
A method of constructing a composite composite concrete bridge of claim 9,
A pier construction step for constructing the pier 40;
A lower plate construction step of installing the lower plate portion 120 of the socket member 100 on the upper surface of the bridge pier 40;
A steel girder installation step for mounting the steel girder 200 on the upper surface of the lower plate 120;
A socket part finishing step of fitting a pair of the closing parts 110 to the lower plate part 120 of the socket member 100;
A step of installing a spacing member (300) in an upper portion of the steel girder (200) in a lateral direction;
A mold installation step for installing a mold for pouring the pier section concrete 50 and the bottom plate concrete 20;
And a concrete pouring step of pouring concrete after the mold is installed.
KR1020150064615A 2015-05-08 2015-05-08 Socket member, composite bridge using the same and the construction method thereof. KR101580194B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150064615A KR101580194B1 (en) 2015-05-08 2015-05-08 Socket member, composite bridge using the same and the construction method thereof.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150064615A KR101580194B1 (en) 2015-05-08 2015-05-08 Socket member, composite bridge using the same and the construction method thereof.

Publications (1)

Publication Number Publication Date
KR101580194B1 true KR101580194B1 (en) 2015-12-24

Family

ID=55084391

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150064615A KR101580194B1 (en) 2015-05-08 2015-05-08 Socket member, composite bridge using the same and the construction method thereof.

Country Status (1)

Country Link
KR (1) KR101580194B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101808825B1 (en) * 2016-12-02 2017-12-13 (주)아이오컨스텍 Support device for leveling-adjustment and displacement recipience and overturning prevention of upper girder and Rahmen bridge using of the same
KR20210053003A (en) * 2019-11-01 2021-05-11 한국도로공사 Reinforcement device for approach slab and approach slab construction methods using thereof
KR102475152B1 (en) * 2021-12-30 2022-12-06 이보베 Steel composite ramen bridge

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100622452B1 (en) * 2005-02-01 2006-09-13 현대제철 주식회사 Multi-H section steel girder compounded part
KR100894542B1 (en) * 2008-11-18 2009-04-24 주식회사 승화이엔씨 Jointless bridge
KR100966144B1 (en) * 2009-05-08 2010-06-25 이엔이건설주식회사 Rahmen bridge construction method with abutment socket and tendon
KR101305522B1 (en) * 2013-04-08 2013-09-06 주식회사 길교이앤씨 Bridge with structure for joining beams and columns

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100622452B1 (en) * 2005-02-01 2006-09-13 현대제철 주식회사 Multi-H section steel girder compounded part
KR100894542B1 (en) * 2008-11-18 2009-04-24 주식회사 승화이엔씨 Jointless bridge
KR100966144B1 (en) * 2009-05-08 2010-06-25 이엔이건설주식회사 Rahmen bridge construction method with abutment socket and tendon
KR101305522B1 (en) * 2013-04-08 2013-09-06 주식회사 길교이앤씨 Bridge with structure for joining beams and columns

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101808825B1 (en) * 2016-12-02 2017-12-13 (주)아이오컨스텍 Support device for leveling-adjustment and displacement recipience and overturning prevention of upper girder and Rahmen bridge using of the same
KR20210053003A (en) * 2019-11-01 2021-05-11 한국도로공사 Reinforcement device for approach slab and approach slab construction methods using thereof
KR102352543B1 (en) 2019-11-01 2022-01-19 한국도로공사 Reinforcement device for approach slab and approach slab construction methods using thereof
KR102475152B1 (en) * 2021-12-30 2022-12-06 이보베 Steel composite ramen bridge

Similar Documents

Publication Publication Date Title
KR101394193B1 (en) Incremental launching apparatus for launching concrete slab for composite bridge using form of buried type
KR101580194B1 (en) Socket member, composite bridge using the same and the construction method thereof.
KR101547629B1 (en) Steel girder with end diaphragm and semi-integral abutment bridge construction method therewith
JP2011220100A (en) Solid viaduct structure and construction method of the same
JP3844743B2 (en) Box girder bridge structure and its construction method
KR101694396B1 (en) Girder for semi-integral bridge and bridge construction method therewith
JP6846322B2 (en) Manufacturing method of precast segment
JP2020090785A (en) Widening structural body, widening structure, floor slab widening construction method, and floor slab renewal method
CN103835238B (en) A kind of high pier cable stayed bridge No. 0 block non-stand construction method and the structure in constructing
KR101447722B1 (en) Composite rahmen bridge and construction method thereof
KR101257941B1 (en) Steel box girder and construction method for girder thereof
KR101562603B1 (en) Precast pedestrian crossover bridge and the construction method therefor
KR100992870B1 (en) Expansion and construction joint apparatus for a bridge
JP5043879B2 (en) How to install width expansion materials for road bridges
KR101448390B1 (en) Connecting structure of square steel strip and square steel supporting beam
KR101824963B1 (en) Hybrid composite girder and construction method therewith
KR101351806B1 (en) Rahmen bridge construction method with longitudinal and transverse pre-moment girder
KR101358879B1 (en) Construction method for continuous bridge using confined concrete
KR20200072986A (en) Pseudo jointless bridge construction made of steel plate girder with overhanged end widen and extended flange composed of concrete block
CN109594651A (en) A kind of steel pipe fashioned iron regeneration concrete column-PEC steel girder frame and assembly method
JP2016044494A (en) Construction method of foundation
JP2018178588A (en) Bridge construction method
KR101064193B1 (en) Articulation type expansion joint apparatus
KR101109461B1 (en) Flexible connecting joint for bridge
KR100554533B1 (en) Construction method for rhamen type hybrid bridge using the post rigid system

Legal Events

Date Code Title Description
AMND Amendment
E601 Decision to refuse application
X091 Application refused [patent]
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20190328

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20191217

Year of fee payment: 5