KR101426874B1 - Construction structure and method for concrete pile - Google Patents

Construction structure and method for concrete pile Download PDF

Info

Publication number
KR101426874B1
KR101426874B1 KR1020140025839A KR20140025839A KR101426874B1 KR 101426874 B1 KR101426874 B1 KR 101426874B1 KR 1020140025839 A KR1020140025839 A KR 1020140025839A KR 20140025839 A KR20140025839 A KR 20140025839A KR 101426874 B1 KR101426874 B1 KR 101426874B1
Authority
KR
South Korea
Prior art keywords
reinforcing
reinforcing bar
reinforcing bars
steel wire
concrete
Prior art date
Application number
KR1020140025839A
Other languages
Korean (ko)
Inventor
오종헌
Original Assignee
오종헌
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 오종헌 filed Critical 오종헌
Priority to KR1020140025839A priority Critical patent/KR101426874B1/en
Application granted granted Critical
Publication of KR101426874B1 publication Critical patent/KR101426874B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1607Shapes round, e.g. circle
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0034Steel; Iron in wire form
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B37/00Nuts or like thread-engaging members

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a structure and method for constructing a concrete pile. The structure for constructing a concrete pile in the present invention comprises: a plurality of reinforcing bars arranged in a row or a multi-row along a circle trajectory; a concrete wall cured by being placed to the outer side of the reinforcing bars and in which a groove processing unit for exposing the reinforcing bars is formed on the top in order for the top of the reinforcing bar to be partially exposed; and a steel wire individually connected to the reinforcing bar in the groove processing unit for exposing the reinforcing bars of the concrete wall.

Description

콘크리트 파일 시공 구조 및 방법{Construction structure and method for concrete pile}Technical Field [0001] The present invention relates to a concrete pile construction method,

본 발명은, 콘크리트 파일 시공 구조 및 방법에 관한 것으로서, 보다 상세하게는, 측방향으로의 휨 변형 문제를 해소할 수 있는 콘크리트 파일 시공 구조 및 방법에 관한 것이다.
The present invention relates to a concrete pile construction method and method, and more particularly, to a pile construction method and a concrete pile construction method capable of solving the problem of lateral deflection.

파일(pile)은 땅속에 관입 지주로 하는 막대 형상의 재료, 또는 관(pipe) 형태의 구조물을 일컫는다.A pile is a rod-shaped material that penetrates into the ground, or a pipe-like structure.

파일은 지지력의 전달기구와 사용방법에 따라 선단지지파일, 하부 지반에 의한 지지파일, 마찰파일, 다지기 파일, 스톱 파일, 횡력 저항파일 등으로 분류된다.The files are classified according to the transmission mechanism of the support force and the usage method, such as the end support file, the support file by the lower ground, the friction file, the chop file, the stop file, and the lateral resistance file.

또한 파일은 재료에 의해서도 나무 파일, 강 파일, 콘크리트 파일 등으로 분류될 수 있다.The files can also be classified as wood files, steel files, concrete files, etc., depending on the material.

나무 파일은 부식되지 않도록 항상 지하수가 있는 장소에서 부담하중이 작은 마찰파일로서 사용된다.Wood files are used as a friction file with a small burden load in places where there is always ground water to prevent corrosion.

강 파일은 특히 흙막이용 메일 파일로 많이 사용된다. 물론, 강 파일과 콘크리트 파일이 혼용되어 사용되는 경우가 잦다.River files are often used as e-mail files. Of course, steel files and concrete files are often used in combination.

콘크리트 파일은 일반 기초, 교량 하부구조, 호안(護岸) 축조, 항만 구조물 등에 범용적으로 사용된다.Concrete piles are commonly used for general foundations, bridge infrastructure, revetment construction, and harbor structures.

콘크리트 파일은 시공 비용이 상대적으로 저렴하면서도 강한 지지력과 하중을 제공할 수 있기 때문에 토목 공사에서 콘크리트 파일의 사용 비중이 큰 것으로 알려지고 있다.Concrete piles are known to have a high proportion of use of concrete piles in civil engineering works because they can provide relatively strong support force and load, while the construction cost is relatively low.

한편, 종래에는 원 궤적을 따라 철근을 1열로 배치한 후, 철근의 길이 방향을 따라 군데군데에 일정 간격을 두고 링(ring) 형상의 링 철근을 배치하여 뼈대를 만든 후, 콘크리트를 타설하여 콘크리트 파일을 시공하여 왔다.Conventionally, after arranging the reinforcing bars in a single row along a circular trajectory, ring reinforcing rings of a ring shape are arranged at predetermined intervals along the longitudinal direction of the reinforcing bars to form a skeleton, File has been installed.

하지만, 이와 같이 시공되는 종래의 콘크리트 파일의 경우, 하중에 대한 저항력은 그리 나쁘지 않지만 측방향으로의 휨 변형에 취약한 문제점이 야기되고 있으므로 이러한 점을 보완하기 위한 기술 개발이 필요한 실정이다.
However, in the case of the conventional concrete pavement constructed in this way, the resistance against the load is not so bad, but the pavement is liable to be deflected in the lateral direction. Therefore, it is necessary to develop a technique to overcome this problem.

대한민국특허청 출원번호 제10-1995-0029066호Korea Patent Office Application No. 10-1995-0029066 대한민국특허청 출원번호 제10-2006-0059035호Korea Patent Office Application No. 10-2006-0059035 대한민국특허청 출원번호 제10-2009-0086345호Korea Patent Office Application No. 10-2009-0086345 대한민국특허청 출원번호 제10-2011-0067716호Korea Patent Office Application No. 10-2011-0067716

본 발명의 목적은, 측방향으로의 휨 변형 문제를 해소할 수 있는 콘크리트 파일 시공 구조 및 방법을 제공하는 것이다.
It is an object of the present invention to provide a concrete pavement construction structure and a method capable of solving the problem of lateral warpage deformation.

상기 목적은, 원 궤적을 따라 일열 또는 다열로 배치되는 다수의 철근; 상기 다수의 철근의 외측으로 타설되어 양생되며, 상기 철근의 상단부가 부분적으로 노출되도록 철근 노출용 홈 가공부가 상단부에 형성되는 콘크리트 벽체; 및 상기 콘크리트 벽체의 철근 노출용 홈 가공부 영역에서 상기 철근과 개별적으로 연결되는 강선을 포함하는 것을 특징으로 하는 콘크리트 파일 시공 구조에 의해 달성된다.The above objects are achieved by a reinforcing bar comprising: a plurality of reinforcing bars arranged in a row or a row along a circular trajectory; A concrete wall formed at an upper end of the plurality of reinforcing bars to be cured by being poured into the reinforcing bars and to be exposed for partially exposing an upper end of the reinforcing bars; And a steel wire separately connected to the reinforcing bars in a groove machining area for the reinforcing bars of the concrete wall.

상기 다수의 철근이 상기 원 궤적을 따라 다열로 배치될 수 있도록 상기 다수의 철근을 지지하며, 상기 철근의 길이 방향을 따라 이격 배치되는 다수의 철근 지지용 원판을 더 포함할 수 있다.The apparatus may further include a plurality of reinforcing bars for supporting the plurality of reinforcing bars so that the plurality of reinforcing bars can be arranged in rows along the circular trajectory and spaced apart from each other along the longitudinal direction of the reinforcing bars.

상기 다수의 철근 지지용 원판 각각은, 중앙 영역에 관통공이 형성되는 도넛(doughnut) 형상의 원판 플레이트; 상기 원판 플레이트의 판면 원주 방향을 따라 형성되며, 상기 다수의 철근이 1열로 삽입되는 다수의 1열 철근 삽입부; 상기 원판 플레이트의 둘레면 원주 방향을 따라 형성되며, 상기 다수의 철근이 2열로 삽입되는 다수의 2열 철근 삽입부; 및 상기 다수의 1열 철근 삽입부들 사이사이에 형성되어 콘크리트가 통과되는 다수의 콘크리트 통과공을 포함하며, 상기 1열 철근 삽입부는 구멍(hole)의 형태이고, 상기 2열 철근 삽입부는 홈(groove)의 형태일 수 있다.Wherein each of the plurality of reinforcing bar supporting discs comprises: a donut-shaped disc plate having a through hole formed in a central region thereof; A plurality of one-column reinforcing inserts formed along the circumferential direction of the plate surface of the disc plate, the plurality of reinforcing bars being inserted in one row; A plurality of two-column reinforcing inserts formed along the circumferential direction of the disc plate, the plurality of reinforcing bars being inserted in two rows; And a plurality of concrete passing holes formed between the plurality of one-column reinforcing bars, through which the concrete passes, wherein the one-column reinforcing bars are in the form of holes, the two- ). ≪ / RTI >

상기 철근 노출용 홈 가공부에 배치되되 상기 철근에 끼워지는 철근 지지용 와셔; 및 상기 철근 지지용 와셔에 이웃하게 배치되며, 양단부가 상기 철근과 상기 강선에 고정되어 연결되는 철근/강선 연결부재를 더 포함할 수 있다.A washer for supporting the reinforcing bar, which is disposed in the reinforcing bar exposing groove processing part and is fitted to the reinforcing bar; And a reinforcing steel / steel wire connecting member disposed adjacent to the reinforcing steel washer and having both ends fixedly connected to the reinforcing steel and the steel wire.

상기 철근/강선 연결부재는 양단부가 상기 철근과 상기 강선에 각각 나사식으로 연결되는 나사식 너트이며, 상기 철근/강선 연결부재와 연결되는 상기 철근과 상기 강선의 단부에는 나사산이 형성될 수 있다.The reinforcing steel / steel wire connecting member is a threaded nut having both ends thereof threadedly connected to the steel wire and the steel wire, and a thread may be formed at the ends of the steel wire and the steel wire connected to the steel wire / steel wire connecting member.

상기 철근/강선 연결부재는, 상기 철근의 상단부에 고정되는 철근 고정용 쵸크; 및 상기 철근 고정용 쵸크에 연결되고 상기 강선의 하단부에 고정되는 강선 고정용 너트를 포함하며, 상기 철근 고정용 쵸크는 일측으로 갈수록 폭이 점진적으로 좁아지는 절두원추 형상을 가지며, 상기 철근 고정용 쵸크는 원주 방향을 따라 분할된 다수의 쵸크 단위 분할체를 구비하며, 상기 강선 고정용 너트에 고정되는 상기 강선의 하단부에는 나사산이 형성될 수 있다.The reinforcing bar / steel wire connecting member includes: a reinforcing bar fixing choke fixed to an upper end of the reinforcing bar; And a steel wire fixing nut connected to the reinforcing steel chock and fixed to a lower end of the steel wire, wherein the reinforcing steel fixing choke has a truncated cone shape gradually narrowing in width toward one side, A plurality of choke unit divided bodies divided along the circumferential direction may be provided, and a thread may be formed at a lower end portion of the steel wire fixed to the steel wire fixing nut.

한편, 상기 목적은, 다수의 철근을 1열로 배치하는 철근 1열 배치단계; 상기 다수의 철근의 외측으로 콘크리트를 타설하여 양생시킴으로써 콘크리트 벽체를 형성시키는 콘크리트 벽체 형성단계; 상기 콘크리트 벽체의 상단부에 상기 철근의 상단부가 부분적으로 노출되는 철근 노출용 홈 가공부를 형성시키는 철근 노출용 홈 가공부 형성단계; 상기 철근에 끼워지도록 하면서 상기 철근 노출용 홈 가공부에 철근 지지용 와셔를 배치하는 철근 지지용 와셔 배치단계; 및 철근/강선 연결부재를 준비하여 상기 철근 노출용 홈 가공부 영역에서 상기 철근/강선 연결부재를 통해 상기 철근과 상기 강선을 체결하는 철근과 강선 체결단계를 포함하는 것을 특징으로 하는 콘크리트 파일 시공 구조에 의해서도 달성된다.The above object is also achieved by a reinforcing bar comprising: a plurality of reinforcing rods arranged in a row; A concrete wall forming step of forming a concrete wall by pouring and curing concrete outside the plurality of reinforcing bars; A step of forming a groove for forming a reinforcing bar for forming a reinforcing bar-forming groove for partially exposing an upper end of the reinforcing bar at an upper end of the concrete wall; A washer supporting washer placing step of placing a reinforcing steel supporting washer in the reinforcing steel exposed groove processing part while being fitted to the reinforcing steel; And a reinforcing bar and a steel wire fastening step of preparing a reinforcing steel / steel wire connecting member and fastening the reinforcing steel wire and the steel wire through the reinforcing steel / steel wire connecting member in the reinforcing steel groove forming area. .

상기 콘크리트 벽체 형성단계의 수행 전에 다수의 철근 지지용 원판을 이용하여 상기 다수의 철근을 2열로 배치하는 철근 2열 배치단계를 더 포함할 수 있다.
The method may further include arranging the plurality of reinforcing bars in two rows using a plurality of supporting bars for reinforcing bars before performing the concrete wall forming step.

본 발명에 따르면, 측방향으로의 휨 변형 문제를 해소할 수 있는 효과가 있다.According to the present invention, it is possible to solve the problem of lateral warpage deformation.

또한 본 발명에 따르면, 하중에 대한 저항력 역시 종전보다 훨씬 높게 유지할 수 있음은 물론 철근과 강선과의 연결 작업을 보다 쉽고 용이하게 수행할 수 있어 작업의 효율을 향상시킬 수 있으면서도 전체적인 공기 단축 효과를 제공할 수 있다.Further, according to the present invention, it is possible to maintain the resistance against the load much higher than before, and to perform the connection work between the reinforcing bars and the steel wire more easily and easily, thereby improving the work efficiency, can do.

또한 본 발명의 경우, 철근 노출용 홈 가공부를 국소적으로 만들고 이곳을 통해 철근과 강선을 연결시키고 있기 때문에 콘크리트 파일의 상단부 전체를 절단하여 왔던 종래기술 대비 폐콘크리트의 발생량을 현저하게 감소시킬 수 있으며, 이를 통해 환경 보호에 기여할 수 있는 효과가 있다.
In addition, since the grooved portion for reinforcing bars is locally made and the reinforcing bars and the steel wires are connected to each other through the groove, the amount of waste concrete can be remarkably reduced compared to the prior art, , Thereby contributing to environmental protection.

도 1은 본 발명의 일 실시예에 따른 콘크리트 파일 시공 방법에 의해 시공된 콘크리트 파일에 대한 구조이다.
도 2 내지 도 8은 도 1의 콘크리트 파일을 시공하기 위한 단계적 공정도이다.
도 9는 도 1의 콘크리트 파일을 시공하기 위한 콘크리트 파일 시공 방법의 플로차트이다.
도 10은 철근/강선 연결부재의 변형예로서 철근/강선 연결부재에 의해 철근과 강선이 연결되는 과정을 도시한 도면이다.
도 11은 도 10에 도시된 철근 고정용 쵸크의 사시도이다.
도 12는 본 발명의 다른 실시예에 따른 콘크리트 파일 시공 방법에 의해 시공된 콘크리트 파일에서 철근과 철근 지지용 원판의 배치 상태를 개략적으로 도시한 도면이다.
도 13은 철근 지지용 원판의 사시도이다.
도 14는 평면도이다.
도 15는 도 14에 철근을 배치한 상태의 도면이다.
도 16은 도 12의 콘크리트 파일을 시공하기 위한 콘크리트 파일 시공 방법의 플로차트이다.
1 is a structure of a concrete file constructed by a method of constructing a concrete file according to an embodiment of the present invention.
FIGS. 2 to 8 are step-by-step process diagrams for constructing the concrete pile of FIG.
FIG. 9 is a flowchart of a concrete file construction method for constructing the concrete file of FIG. 1;
10 is a view showing a process of connecting a reinforcing bar and a steel wire by a reinforcing bar / steel wire connecting member as a modification of the reinforcing steel wire connecting member.
11 is a perspective view of the reinforcing bar fixing choke shown in Fig.
12 is a view schematically showing the arrangement state of a reinforcing bar and a reinforcing steel supporting plate in a concrete file constructed by a method of constructing a concrete pile according to another embodiment of the present invention.
13 is a perspective view of a reinforcing bar supporting disk.
14 is a plan view.
Fig. 15 is a view showing a state in which reinforcing bars are arranged in Fig. 14. Fig.
FIG. 16 is a flowchart of a concrete file construction method for constructing the concrete file of FIG. 12;

이하, 첨부도면을 참조하여 본 발명의 바람직한 실시예를 설명한다.Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.

도 1은 본 발명의 일 실시예에 따른 콘크리트 파일 시공 방법에 의해 시공된 콘크리트 파일에 대한 구조, 도 2 내지 도 8은 도 1의 콘크리트 파일을 시공하기 위한 단계적 공정도, 그리고 도 9는 도 1의 콘크리트 파일을 시공하기 위한 콘크리트 파일 시공 방법의 플로차트이다.FIG. 1 is a view showing a structure of a concrete file constructed by a concrete file construction method according to an embodiment of the present invention, FIGS. 2 to 8 are stepwise process drawings for constructing a concrete file of FIG. 1, A concrete file construction method for constructing a concrete file of a concrete file.

이들 도면을 참조하면, 본 발명의 일 실시예에 따른 콘크리트 파일 시공 구조는 도 1과 같은 형태로 시공되는 것으로서, 콘크리트 벽체(130), 철근 지지용 와셔(140), 그리고 철근/강선 연결부재(150)를 포함한다.Referring to these drawings, a concrete pile construction according to an embodiment of the present invention is constructed as shown in Fig. 1, and includes a concrete wall 130, a washer supporting washer 140, and a reinforcing steel / 150).

본 실시예의 경우, 도 1처럼 철근(1)이 1열로 시공되기 때문에 후술할 철근 지지용 원판(110)은 사용되지 않을 수도 있다. 물론, 철근 지지용 원판(110)이 선택적으로 사용되더라도 관계는 없다.In the case of this embodiment, since the reinforcing bar 1 is constructed in one row as shown in FIG. 1, the reinforcing bar supporting disk 110 to be described later may not be used. Of course, even if the reinforcing bar supporting disk 110 is selectively used, it is not relevant.

콘크리트 벽체(130)는 다수의 철근(1)의 외측으로 타설되어 양생된다. 도 1처럼 외부에서 볼 때, 1열로 배치되는 철근(1)은 안 보일 수 있다.The concrete wall body 130 is cured by being poured outside the plurality of reinforcing bars 1. When seen from the outside as in Fig. 1, the reinforcing bars 1 arranged in one row can not be seen.

강선(2)은 콘크리트 벽체(130)의 상단부에서 철근(1)과 개별적으로 연결되는 구조물이다. 도 1에 도시된 것처럼 강선(2)의 상단부에는 와셔(W)와 너트(N)가 결합될 수 있다.The steel wire 2 is a structure that is individually connected to the reinforcing bar 1 at the upper end of the concrete wall body 130. 1, the washer W and the nut N may be coupled to the upper end of the steel wire 2. [

강선(2)이 콘크리트 벽체(130)의 상단부에서 철근(1)과 개별적으로 연결되기 위해, 콘크리트 벽체(130)의 상단부에는 철근(1)의 상단부가 부분적으로 노출되도록 철근 노출용 홈 가공부(131)가 형성된다. 종전과 달리, 철근 노출용 홈 가공부(131)를 국소적으로 만들고 이곳을 통해 철근(1)과 강선(2)을 연결시키고 있기 때문에 콘크리트 파일의 상단부 전체를 절단하여 왔던 종래기술 대비 폐콘크리트의 발생량을 현저하게 감소시킬 수 있으며, 이를 통해 환경 보호에 기여할 수 있는 효과가 있다.The upper end of the reinforcing bar 1 is partially exposed at the upper end of the concrete wall 130 so that the steel wire 2 is individually connected to the reinforcing bar 1 at the upper end of the concrete wall body 130 131 are formed. Unlike the prior art, since the reinforcing bars are formed locally and the reinforcing bars 1 and the steel wires 2 are connected to each other through the grooves, the entire upper end portion of the concrete pile is cut, It is possible to remarkably reduce the amount of generated electricity, thereby contributing to environmental protection.

철근 지지용 와셔(140)는 철근(1)의 상단부가 부분적으로 노출되도록 콘크리트 벽체(130)의 상단부에 홈 가공되는 철근 노출용 홈 가공부(131)에 배치되되 철근(1)에 끼워지는 구조물이다.The reinforcing steel supporting washer 140 is disposed in the reinforcing steel exposed groove processing part 131 which is formed in the upper end portion of the concrete wall body 130 such that the upper end of the reinforcing steel rod 1 is partially exposed, to be.

본 실시예에서 철근 지지용 와셔(140)는 강도가 우수한 평 와셔로 적용될 수 있으나 반드시 그러한 것은 아니다.In the present embodiment, the reinforcing steel washer 140 can be applied as a flat washer having high strength, but this is not necessarily the case.

철근/강선 연결부재(150)는 철근 지지용 와셔(140)에 이웃하게 배치되며, 양단부가 철근(1)과 강선(2)에 고정되어 연결되는 구조물이다.The reinforcing steel / steel wire connecting member 150 is disposed adjacent to the reinforcing steel washer 140 and has both ends fixedly connected to the reinforcing bars 1 and the steel wire 2.

다양한 형태의 철근/강선 연결부재(150)가 적용될 수 있는데, 본 실시예의 경우, 철근/강선 연결부재(150)는 그 양단부가 철근(1)과 강선(2)에 각각 나사식으로 연결되는 나사식 너트로 적용된다.The reinforcing bar / steel wire connecting member 150 may be formed by a screw having both ends thereof threadably connected to the reinforcing bar 1 and the steel wire 2, respectively, in the present embodiment, It is applied as an expression nut.

나사식 너트로 철근/강선 연결부재(150)가 적용되는 경우, 나사식 너트에 나사식으로 체결될 수 있도록 철근(1)과 강선(2)의 단부에 나사산(1a,2a)을 형성시킬 수 있다.When the reinforcing bar / steel wire connecting member 150 is applied with a threaded nut, threads 1a and 2a may be formed at the end portions of the reinforcing bar 1 and the steel wire 2 so as to be threadably fastened to the threaded nut. have.

이처럼 나사식 너트로 철근/강선 연결부재(150)를 적용하는 것이 가장 간편하면서도 쉬운 연결 방식일 수 있다.Thus, it is the easiest and easiest way to connect the reinforcing steel wire connecting member 150 with the threaded nut.

이하, 도 1과 같은 형태의 콘크리트 파일을 시공하는 방법에 대해 설명한다.Hereinafter, a method of constructing a concrete pile of the type shown in FIG. 1 will be described.

우선, 다수의 철근(1)을 1열로 배치하고(S10), 다수의 철근(1)의 외측으로 콘크리트를 타설하여 양생시킴으로써 콘크리트 벽체(130)를 형성시킨다(S20). 이 상태의 일부가 도 2에 도시되어 있다.First, a plurality of reinforcing bars 1 are arranged in a row (S10), concrete is placed outside the plurality of reinforcing bars 1 and cured to form a concrete wall 130 (S20). A part of this state is shown in Fig.

다음, 도 2와 같은 상태에서 도 3처럼 콘크리트 벽체(130)의 상단부에 철근(1)의 상단부가 부분적으로 노출되는 철근 노출용 홈 가공부(131)를 형성시킨다(S30).Next, in the state of FIG. 2, a reinforcing bar exposing groove processing part 131 is formed at the upper end of the concrete wall 130 as shown in FIG. 3 (S30), in which the upper end of the reinforcing bar 1 is partially exposed.

그리고는 도 4처럼 철근(1)에 끼워지도록 하면서 철근 노출용 홈 가공부(131)에 철근 지지용 와셔(140)를 배치한다(S40).Then, the washer supporting washer 140 is disposed in the reinforcing bar-exposing groove processing part 131 so as to be fitted in the reinforcing bar 1 as shown in FIG. 4 (S40).

그런 다음, 도 5처럼 나사식 너트로서의 철근/강선 연결부재(150)를 준비한 후, 도 6 내지 도 8처럼 철근 노출용 홈 가공부(131) 영역에서 철근/강선 연결부재(150)를 통해 철근(1)과 강선(2)을 체결함으로써(S50), 도 1과 같은 형태의 콘크리트 파일을 간편하게 시공할 수 있다. 이때의 철근/강선 연결부재(150)는 앞서 기술한 것처럼 철근(1)과 강선(2)의 단부에 형성된 나사산(1a,2a)에 나사 결합될 수 있다.Then, after preparing the reinforcing bar / steel wire connecting member 150 as a threaded nut as shown in FIG. 5, the reinforcing bar / steel wire connecting member 150 is inserted into the reinforcing bar / The concrete pile 1 and the steel wire 2 are fastened (S50), so that a concrete pile of the same shape as in Fig. 1 can be easily installed. The reinforcing bar / steel wire connecting member 150 may be screwed to the threads 1a and 2a formed at the ends of the reinforcing bar 1 and the steel wire 2 as described above.

이와 같은 구조와 작용을 갖는 본 실시예에 따르면, 철근(1)과 강선(2)의 연결 작업을 보다 쉽고 용이하게 수행할 수 있어 작업의 효율을 향상시킬 수 있으면서도 전체적인 공기 단축 효과를 제공할 수 있게 된다.According to the present embodiment having such a structure and function, it is possible to more easily and easily perform the connection operation between the reinforcing bar 1 and the steel wire 2, thereby improving the work efficiency, .

또한 본 발명의 경우, 철근 노출용 홈 가공부(131)를 국소적으로 만들고 이곳을 통해 철근(1)과 강선(2)을 연결시키고 있기 때문에 콘크리트 파일의 상단부 전체를 절단하여 왔던 종래기술 대비 폐콘크리트의 발생량을 현저하게 감소시킬 수 있으며, 이를 통해 환경 보호에 기여할 수 있게 된다.Further, according to the present invention, since the reinforcing bar groove forming part 131 is locally made and the reinforcing bar 1 and the steel wire 2 are connected to each other through the groove, the entire upper end portion of the concrete pile is cut, The amount of generated concrete can be remarkably reduced, thereby contributing to environmental protection.

도 10은 철근/강선 연결부재의 변형예로서 철근/강선 연결부재에 의해 철근과 강선이 연결되는 과정을 도시한 도면이고, 도 11은 도 10에 도시된 철근 고정용 쵸크의 사시도이다.10 is a view showing a process of connecting a reinforcing bar and a steel wire by a reinforcing bar / steel wire connecting member, and FIG. 11 is a perspective view of the reinforcing bar fixing chuck shown in FIG.

전술한 실시예의 경우, 철근/강선 연결부재(150)가 나사식 너트로 적용되었다.In the case of the above-described embodiment, the reinforcing bar / steel wire connecting member 150 is applied with a screw nut.

하지만, 본 실시예의 경우, 철근/강선 연결부재(250)는 도 10 및 도 11처럼 철근 고정용 쵸크(251)와 강선 고정용 너트(252)를 구비하는 구조물로 적용될 수도 있다.However, in the case of the present embodiment, the reinforcing steel / steel wire connecting member 250 may be applied to a structure including the reinforcing bars fixing chock 251 and the steel wire fixing nut 252 as shown in FIGS. 10 and 11.

이러한 경우, 철근 고정용 쵸크(251)는 철근(1)의 상단부에 고정되고, 강선 고정용 너트(252)는 철근 고정용 쵸크(251)에 연결되고 강선(2)의 하단부에 고정됨으로써 철근(1)과 강선(2)을 연결시킬 수 있다.In this case, the reinforcing bar fixing chock 251 is fixed to the upper end of the reinforcing bar 1, the reinforcing steel fixing nut 252 is connected to the reinforcing bar fixing chock 251 and fixed to the lower end of the reinforcing bar 25, 1) and the steel wire (2).

다시 말해, 철근 고정용 쵸크(251)와 강선 고정용 너트(252)가 연결된 하나의 구조물이 철근/강선 연결부재(250)이며, 이를 통해 철근(1)과 강선(2)이 연결될 수 있다.In other words, one structure in which the reinforcing bar fixing chock 251 and the steel wire fixing nut 252 are connected is a reinforcing bar / steel wire connecting member 250 through which the reinforcing bar 1 and the steel wire 2 can be connected.

이때, 도 11에 도시된 것처럼 철근/강선 연결부재(250)의 철근 고정용 쵸크(251)는 일측으로 갈수록 폭이 점진적으로 좁아지는 절두원추 형상을 가질 수 있는데, 철근 고정용 쵸크(251)는 원주 방향을 따라 분할된 다수의 쵸크 단위 분할체(251a)를 구비할 수 있다. 이와 같은 철근 고정용 쵸크(251)에 철근(1)의 상단부가 빡빡하게 끼워지면서 고정될 수 있다.11, the reinforcing bars 251 of the reinforcing bars / steel wire connecting members 250 may have a truncated conical shape gradually narrowing toward the one side. The reinforcing bar fixing chocks 251 And a plurality of choke unit divided bodies 251a divided along the circumferential direction. The upper end of the reinforcing bar 1 can be fixedly fitted to the reinforcing bars 251 by tightly fitting.

강선 고정용 너트(252)는 강선(2)의 하단부에 고정되는 부분이다. 강선 고정용 너트(252)에 강선(2)의 하단부가 고정될 수 있도록 강선 고정용 너트(252)에 고정되는 강선(2)의 하단부에는 나사산(2a)이 가공되어 형성될 수 있다.The steel wire fixing nut 252 is a portion fixed to the lower end of the steel wire 2. A thread 2a may be formed on the lower end of the steel wire 2 fixed to the steel wire fixing nut 252 so that the lower end of the steel wire 2 can be fixed to the steel wire fixing nut 252.

도 12는 본 발명의 다른 실시예에 따른 콘크리트 파일 시공 방법에 의해 시공된 콘크리트 파일에서 철근과 철근 지지용 원판의 배치 상태를 개략적으로 도시한 도면, 도 13은 철근 지지용 원판의 사시도, 도 14는 평면도, 도 15는 도 14에 철근을 배치한 상태의 도면, 그리고 도 16은 도 12의 콘크리트 파일을 시공하기 위한 콘크리트 파일 시공 방법의 플로차트이다.FIG. 12 is a view schematically showing an arrangement state of a reinforcing bar and a reinforcing steel supporting disk in a concrete file constructed by a concrete file construction method according to another embodiment of the present invention. FIG. 13 is a perspective view of a reinforcing steel supporting disk, Fig. 15 is a view showing a state in which reinforcing bars are arranged in Fig. 14, and Fig. 16 is a flowchart of a concrete file construction method for constructing a concrete pile in Fig.

이들 도면을 참조하면, 본 실시예의 경우, 철근(2)이 2열로 배치됨으로써 콘크리트 파일을 형성하는 경우에 해당되는데, 도 12 및 도 15처럼 철근(2)이 2열로 배치되는 경우, 다수의 철근 지지용 원판(110)이 사용될 수 있다.Referring to these figures, in the case of the present embodiment, the reinforcing bars 2 are arranged in two rows to form a concrete pile. When the reinforcing rods 2 are arranged in two rows as shown in Figs. 12 and 15, The supporting disk 110 may be used.

본 실시예처럼 다수의 철근 지지용 원판(110)이 사용되면서 다수의 철근 지지용 원판(110)을 통해 철근(1)이 2열로 시공될 경우, 측방향으로의 휨 변형 문제를 해소할 수 있다.When a plurality of reinforcing bar supporting disks 110 are used and the reinforcing bars 1 are installed in two rows through a plurality of reinforcing steel supporting disks 110 as in the present embodiment, the problem of lateral warping can be solved .

또한 아래의 구조적인 특징으로 인해 하중에 대한 저항력 역시 종전보다 훨씬 높게 유지할 수 있음은 물론 철근(1)과 강선(2)의 연결 작업을 보다 쉽고 용이하게 수행할 수 있어 작업의 효율을 향상시킬 수 있다.In addition, due to the following structural features, the resistance against load can be maintained much higher than before, and the connection work between the reinforcing bar 1 and the steel wire 2 can be easily and easily performed, have.

이하, 철근 지지용 원판(110)에 대해 상세히 설명한다.Hereinafter, the reinforcing bar supporting disk 110 will be described in detail.

철근 지지용 원판(110)은 도 13 내지 도 15에 도시된 바와 같이, 다수의 철근(1)이 원 궤적을 따라 다열로 배치될 수 있도록 다수의 철근(1)을 지지하며, 철근(1)의 길이 방향을 따라 이격 배치되는 구조물이다.As shown in FIGS. 13 to 15, the reinforcement supporting disk 110 supports a plurality of reinforcing bars 1 so that a plurality of reinforcing bars 1 can be arranged in multiple rows along a circular path, As shown in Fig.

종전의 링 형태와는 달리 본 실시예에서 철근 지지용 원판(110)은 판 구조물로 이루어지며, 철근(1)을 2열로 지지할 수 있다.Unlike the conventional ring type, in the present embodiment, the reinforcing bar supporting disk 110 is made of a plate structure and can support the reinforcing bar 1 in two rows.

이처럼 철근 지지용 원판(110)에 의해 철근(1)이 2열로 지지되기 때문에 종전과 달리 측방향으로의 휨 변형 문제를 해소할 수 있게 되는 것이다.Since the reinforcement 1 is supported in two rows by the reinforcement supporting disk 110, the lateral deflection problem can be solved.

참고로, 본 실시예의 경우, 철근(1)이 2열로 지지되고 있으나 철근(1)은 3열 이상으로 지지될 수도 있을 것이다.For reference, in this embodiment, the reinforcing bar 1 is supported in two rows, but the reinforcing bar 1 may be supported in three or more rows.

이러한 철근 지지용 원판(110)은 원판 플레이트(111), 1열 철근 삽입부(112), 2열 철근 삽입부(113), 그리고 콘크리트 통과공(114)을 포함한다.The reinforcement supporting disk 110 includes a disk plate 111, a single column reinforcing insert 112, a double column reinforcing insert 113, and a concrete passage hole 114.

원판 플레이트(111)는 도넛(doughnut) 형상의 판 구조물로서, 그 중앙 영역에는 관통공(111a)이 형성된다.The disk plate 111 is a plate structure having a donut shape, and a through hole 111a is formed in the central area thereof.

1열 철근 삽입부(112)는 원판 플레이트(111)의 판면 원주 방향을 따라 형성되며, 다수의 철근(1)이 1열로 삽입되는 부분이다.The one-row reinforcing insert 112 is formed along the circumferential direction of the plate surface of the disc plate 111, and is a portion where a plurality of reinforcing bars 1 are inserted in one row.

본 실시예에서 1열 철근 삽입부(112)는 구멍(hole)의 형태로 가공될 수 있다. 1열 철근 삽입부(112)의 개수는 도시된 것을 벗어나 다양하게 변경 적용될 수 있다.In this embodiment, the one-column reinforcing insert 112 can be formed in the form of a hole. The number of the one-column reinforcing inserts 112 may be variously changed from that shown.

2열 철근 삽입부(113)는 원판 플레이트(111)의 둘레면 원주 방향을 따라 형성되며, 다수의 철근(1)이 2열로 삽입되는 부분이다.The two-row reinforcing insert 113 is formed along the circumferential direction of the circumferential surface of the disc plate 111, and is a portion where a plurality of reinforcing bars 1 are inserted in two rows.

1열 철근 삽입부(112)와 달리, 2열 철근 삽입부(113)는 홈(groove)의 형태로 가공될 수 있다. 2열 철근 삽입부(113)의 개수 역시, 도시된 것을 벗어나 다양하게 변경 적용될 수 있다.Unlike the one-row reinforcing insert 112, the two-row reinforcing insert 113 can be machined into a groove. The number of the two-column reinforcing inserts 113 can also be variously changed outside the illustrated.

참고로, 본 실시예의 경우, 2열 철근 삽입부(113)가 1열 철근 삽입부(112)와 달리 홈의 형태로 되어 있으나 1열 철근 삽입부(112)와 2열 철근 삽입부(113) 모두가 구멍(hole)의 형태로 가공될 수도 있을 것이며, 이러한 사항 모두는 본 발명의 권리범위에 속한다 하여야 할 것이다.In the present embodiment, the two-row reinforcing bar insertion portion 113 is formed in a groove shape unlike the one-row reinforcing bar insertion portion 112, but the one-row reinforcing bar insertion portion 112 and the two- All of which may be processed in the form of holes, all of which are within the scope of the present invention.

콘크리트 통과공(114)은 다수의 1열 철근 삽입부(112)들 사이사이에 형성되어 콘크리트가 통과되는 부분이다.The concrete passage hole 114 is formed between a plurality of one-column reinforcing inserts 112 to allow the concrete to pass through.

콘크리트 통과공(114)이 1열 철근 삽입부(112) 및 2열 철근 삽입부(113)와 달리 사각 형상으로 되어 있으나 이는 하나의 예일 뿐이다. 따라서 콘크리트 통과공(114)의 형상에 본 발명의 권리범위가 제한될 수 없다.The concrete passage hole 114 is rectangular in shape, unlike the one-row reinforcing steel insert 112 and the two-row reinforcing steel insert 113, but this is only one example. Therefore, the scope of right of the present invention can not be limited to the shape of the concrete passage hole 114.

이하, 본 실시예에 따른 콘크리트 파일을 시공하는 방법에 대해 설명한다.Hereinafter, a method of constructing a concrete pile according to the present embodiment will be described.

우선, 다수의 철근 지지용 원판(110)을 이용하여 다수의 철근(1)을 1열로 배치한 후(S10), 이어 철근(1)을 2열로 배치한 다음(S15), 철근(1)들 및 철근 지지용 원판(110)들의 외측으로 콘크리트를 타설하여 양생시킴으로써 콘크리트 벽체(130)를 형성시킨다(S20).First, a plurality of reinforcing bars 1 are arranged in one line by using a plurality of reinforcing bar supporting discs 110, and then the reinforcing bars 1 are arranged in two rows (S15) And reinforced concrete supporting plates 110. The concrete wall 130 is formed by curing the concrete by placing the concrete outside the reinforcing steel supporting disks 110 (S20).

다음, 콘크리트 벽체(130)의 상단부에 철근(1)의 상단부가 부분적으로 노출되는 철근 노출용 홈 가공부(131)를 형성시킨다(S30).Next, a reinforcing bar exposing groove processing part 131 is formed at the upper end of the concrete wall body 130, in which the upper end of the reinforcing bar 1 is partially exposed (S30).

그리고는 철근(1)에 끼워지도록 하면서 철근 노출용 홈 가공부(131)에 철근 지지용 와셔(140)를 배치하고(S40), 철근/강선 연결부재(150,250)를 준비한 후, 철근 노출용 홈 가공부(131) 영역에서 철근/강선 연결부재(150)를 통해 철근(1)과 강선(2)을 체결함으로써(S50), 콘크리트 파일을 간편하게 시공할 수 있다.Then, the washer supporting washer 140 is disposed in the reinforcing bar exposure groove forming part 131 so as to be fitted into the reinforcing bar 1 (S40), the reinforcing bar / steel connecting members 150 and 250 are prepared, It is possible to easily construct a concrete pile by fastening the reinforcing bar 1 and the steel wire 2 through the reinforcing steel / steel wire connecting member 150 in the region of the machining portion 131 (S50).

이와 같은 구조와 작용을 갖는 본 실시예가 적용되더라도 측방향으로의 휨 변형 문제를 해소할 수 있게 된다.Even if this embodiment having such a structure and an action is applied, it is possible to solve the problem of lateral warping.

또한 본 실시예에 따르면, 하중에 대한 저항력 역시 종전보다 훨씬 높게 유지할 수 있음은 물론 철근(1)과 강선(2)의 연결 작업을 보다 쉽고 용이하게 수행할 수 있어 작업의 효율을 향상시킬 수 있으면서도 전체적인 공기 단축 효과를 제공할 수 있게 된다.Also, according to the present embodiment, the resistance against load can be maintained to be much higher than before, and the connecting operation between the reinforcing bar 1 and the steel wire 2 can be performed more easily and easily, It is possible to provide the overall air shortening effect.

또한 본 발명의 경우, 철근 노출용 홈 가공부(131)를 국소적으로 만들고 이곳을 통해 철근(1)과 강선(2)을 연결시키고 있기 때문에 콘크리트 파일의 상단부 전체를 절단하여 왔던 종래기술 대비 폐콘크리트의 발생량을 현저하게 감소시킬 수 있으며, 이를 통해 환경 보호에 기여할 수 있게 된다.Further, according to the present invention, since the reinforcing bar groove forming part 131 is locally made and the reinforcing bar 1 and the steel wire 2 are connected to each other through the groove, the entire upper end portion of the concrete pile is cut, The amount of generated concrete can be remarkably reduced, thereby contributing to environmental protection.

이와 같이 본 발명은 기재된 실시예에 한정되는 것이 아니고, 본 발명의 사상 및 범위를 벗어나지 않고 다양하게 수정 및 변형할 수 있음은 이 기술의 분야에서 통상의 지식을 가진 자에게 자명하다. 따라서 그러한 수정예 또는 변형예들은 본 발명의 특허청구범위에 속한다 하여야 할 것이다.
It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention. Accordingly, such modifications or variations are intended to fall within the scope of the appended claims.

1 : 철근 2 : 강선
2a : 나사산 110 : 철근 지지용 원판
111 : 원판 플레이트 111a : 관통공
112 : 1열 철근 삽입부 113 : 2열 철근 삽입부
114 : 콘크리트 통과공 130 : 콘크리트 벽체
131 : 철근 노출용 홈 가공부 140 : 철근 지지용 와셔
150 : 철근/강선 연결부재 151 : 철근 고정용 쵸크
151a : 쵸크 단위 분할체 152 : 강선 고정용 너트
1: Reinforcement 2: Steel wire
2a: thread 110: disc for reinforcing steel support
111: disc plate 111a: through-hole
112: 1 thermal rebar insert 113: 2 thermal rebar insert
114: Concrete passing hole 130: Concrete wall
131: grooving part for reinforcing bar exposure 140: washer for reinforcing bar
150: Reinforcing / Steel connecting member 151: Reinforcing chock
151a: Choke unit divided body 152: Steel wire fixing nut

Claims (7)

원 궤적을 따라 다열로 배치되는 다수의 철근;
상기 다수의 철근의 외측으로 타설되어 양생되며, 상기 철근의 상단부가 부분적으로 노출되도록 철근 노출용 홈 가공부가 상단부에 형성되어 있는 콘크리트 벽체;
상기 콘크리트 벽체의 철근 노출용 홈 가공부 영역에서 상기 철근과 개별적으로 연결되는 강선;
상기 다수의 철근이 상기 원 궤적을 따라 다열로 배치될 수 있도록 상기 다수의 철근을 지지하며, 상기 철근의 길이 방향을 따라 이격 배치되는 다수의 철근 지지용 원판;
상기 철근 노출용 홈 가공부에 배치되되 상기 철근에 끼워지는 철근 지지용 와셔; 및
상기 철근 지지용 와셔에 이웃하게 배치되되, 양단부가 상기 철근과 상기 강선에 고정되어 연결되는 철근/강선 연결부재; 를 포함하되,
상기 다수의 철근 지지용 원판 각각은 중앙 영역에 관통공이 형성되는 도넛(doughnut) 형상의 원판 플레이트와, 상기 원판 플레이트의 판면 원주 방향을 따라 형성되며, 상기 다수의 철근이 1열로 삽입되는 다수의 1열 철근 삽입부와, 상기 원판 플레이트의 둘레면 원주 방향을 따라 형성되며, 상기 다수의 철근이 2열로 삽입되는 다수의 2열 철근 삽입부와, 상기 다수의 1열 철근 삽입부들 사이사이에 형성되어 콘크리트가 통과되는 다수의 콘크리트 통과공을 포함하고, 상기 1열 철근 삽입부는 구멍(hole)의 형태로 이루어지고, 상기 2열 철근 삽입부는 구멍의 형태 또는 홈(groove)의 형태로 이루어지고,
상기 철근/강선 연결부재는 상기 철근의 상단부에 고정되는 철근 고정용 쵸크와, 상기 철근 고정용 쵸크에 연결되고 상기 강선의 하단부에 고정되는 강선 고정용 너트를 포함하되, 상기 철근 고정용 쵸크는 일측으로 갈수록 폭이 점진적으로 좁아지는 절두원추 형상을 가지고, 원주 방향을 따라 분할된 다수의 쵸크 단위 분할체를 구비하고, 상기 강선 고정용 너트에 고정되는 상기 강선의 하단부에는 나사산이 형성되는,
것을 특징으로 하는 콘크리트 파일 시공 구조.
A plurality of reinforcing bars arranged in a row along the circular trajectory;
A concrete wall in which the reinforcing bars are formed at the upper end of the reinforcing bars so that the upper ends of the reinforcing bars are partially exposed;
A steel wire separately connected to the reinforcing bars in a region of the reinforced concrete exposed groove of the concrete wall;
A plurality of steel reinforcing bars supporting the plurality of reinforcing bars so that the plurality of reinforcing bars can be arranged in rows along the circular trajectory and spaced apart along the longitudinal direction of the reinforcing bars;
A washer for supporting the reinforcing bar, which is disposed in the reinforcing bar exposing groove processing part and is fitted to the reinforcing bar; And
A reinforcing bar / steel connecting member disposed adjacent to the washer supporting washer and having both ends fixedly connected to the reinforcing bar and the steel wire; , ≪ / RTI &
Wherein each of the plurality of reinforcing bar supporting discs has a donut-shaped disc plate in which a through hole is formed in a central region, a plurality of reinforcing bars formed along the circumferential direction of the plate surface of the disc plate, A plurality of two-row reinforcing inserts formed along the circumferential direction of the circumferential surface of the disc plate, the plurality of reinforcing bars being inserted in two rows, and a plurality of reinforcing bars formed between the plurality of reinforcing bars, And a plurality of concrete through holes through which concrete passes, wherein the one-column reinforcing insert is in the form of a hole, the two-column reinforcing insert is in the form of a hole or a groove,
Wherein the reinforcing steel / steel wire connecting member includes a reinforcing bar fixing choke fixed to an upper end of the reinforcing bar, and a steel fixing nut connected to the reinforcing bar fixing choke and fixed to a lower end of the reinforcing bar, A plurality of choke unit divided bodies divided along the circumferential direction and having a truncated conical shape in which the width progressively narrows toward a lower end of the steel wire fixing nut and a thread is formed in a lower end portion of the steel wire fixed to the steel wire fixing nut,
Wherein the concrete pile construction structure is a pile structure.
삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete
KR1020140025839A 2014-03-05 2014-03-05 Construction structure and method for concrete pile KR101426874B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140025839A KR101426874B1 (en) 2014-03-05 2014-03-05 Construction structure and method for concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140025839A KR101426874B1 (en) 2014-03-05 2014-03-05 Construction structure and method for concrete pile

Publications (1)

Publication Number Publication Date
KR101426874B1 true KR101426874B1 (en) 2014-08-06

Family

ID=51749622

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140025839A KR101426874B1 (en) 2014-03-05 2014-03-05 Construction structure and method for concrete pile

Country Status (1)

Country Link
KR (1) KR101426874B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102092257B1 (en) * 2019-11-20 2020-05-26 신병철 Concrete structure and construction metohds
CN113737779A (en) * 2021-10-21 2021-12-03 湖北捷固筑工科技有限公司 Steel bar connection adjusting nut, assembly and precast pile and foundation bearing platform connecting structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030009832A (en) * 2001-07-24 2003-02-05 삼성중공업 주식회사 Device fixing bar and structure for connecting head of steel pile and concrete footing of the same
KR20030009834A (en) * 2001-07-24 2003-02-05 삼성중공업 주식회사 Device fixing bar and structure for connecting head of steel pile and concrete footing of the same
KR20060090381A (en) * 2005-02-07 2006-08-10 백규호 Appratus and method for connection between concrete pile head and concrete footing
KR101027800B1 (en) * 2010-04-12 2011-04-07 주식회사 아이콘텍이앤씨 Prefabricated revet construction and method for constructing the same

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030009832A (en) * 2001-07-24 2003-02-05 삼성중공업 주식회사 Device fixing bar and structure for connecting head of steel pile and concrete footing of the same
KR20030009834A (en) * 2001-07-24 2003-02-05 삼성중공업 주식회사 Device fixing bar and structure for connecting head of steel pile and concrete footing of the same
KR20060090381A (en) * 2005-02-07 2006-08-10 백규호 Appratus and method for connection between concrete pile head and concrete footing
KR101027800B1 (en) * 2010-04-12 2011-04-07 주식회사 아이콘텍이앤씨 Prefabricated revet construction and method for constructing the same

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102092257B1 (en) * 2019-11-20 2020-05-26 신병철 Concrete structure and construction metohds
CN113737779A (en) * 2021-10-21 2021-12-03 湖北捷固筑工科技有限公司 Steel bar connection adjusting nut, assembly and precast pile and foundation bearing platform connecting structure

Similar Documents

Publication Publication Date Title
AU2013249345B2 (en) Multiple pile foundation locking systems
EP2248951B1 (en) Method and device for determining the axial force progression in a pressure-grouted anchor
DE102011106431B3 (en) Arrangement for supporting a tension member, in particular a stay cable, transversely to its longitudinal direction
JP3184322U (en) Solar panel mount
CN204530483U (en) Capping construction support
KR101426874B1 (en) Construction structure and method for concrete pile
KR101764369B1 (en) apparatus for fastening grating
JP2015113703A (en) Energy-dissipating junction assembly and aseismic structure using the same
US20200123768A1 (en) Permanent Concrete Formwork And Method For Manufacturing A Metal-Concrete Composite Structure Using Such A Formwork
KR101083119B1 (en) Structure of wood deck and its eco-friendly construction method
JP2018096184A (en) Steel plate floor instant bridge
JP6502125B2 (en) Reinforced concrete perforated beam
EP3433448B1 (en) Frame element with a support head, and building scaffold comprising such a frame element
SE536197C2 (en) Reinforcing elements for casting comprising annular portions and reinforcement including such reinforcing elements
JP5819449B2 (en) Solar panel support jig
CN204326607U (en) A kind of assembled steel reinforced machining shed
CN103276851B (en) Steel core concrete column with ribbing and method for designing thereof
CN212611997U (en) Positioner suitable for assembled bridge bearing platform reinforcing bar
KR101235758B1 (en) Plate jig for installing anchor bolts
EP2685028A2 (en) Method for production of shuttering tie rod and shuttering tie rod
JP5357592B2 (en) Protective fence
RU2533168C1 (en) Support grid-filter for fuel assembly of nuclear reactor
JP2017227028A (en) Fastening-fixing structure of reinforcement
JP5806629B2 (en) Length adjustment member for new structural member for steel tower restoration
JP6566481B2 (en) Removal mechanism, temporary pillar, and removal method

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20190729

Year of fee payment: 6