KR101395633B1 - Water pressure measurement apparatus for electrolysis - Google Patents

Water pressure measurement apparatus for electrolysis Download PDF

Info

Publication number
KR101395633B1
KR101395633B1 KR1020120091152A KR20120091152A KR101395633B1 KR 101395633 B1 KR101395633 B1 KR 101395633B1 KR 1020120091152 A KR1020120091152 A KR 1020120091152A KR 20120091152 A KR20120091152 A KR 20120091152A KR 101395633 B1 KR101395633 B1 KR 101395633B1
Authority
KR
South Korea
Prior art keywords
hydraulic
hydraulic pressure
hose
support
fastening
Prior art date
Application number
KR1020120091152A
Other languages
Korean (ko)
Other versions
KR20140025634A (en
Inventor
박규원
김성태
이해돈
박용석
신현혁
Original Assignee
(주) 테크로스
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 테크로스 filed Critical (주) 테크로스
Priority to KR1020120091152A priority Critical patent/KR101395633B1/en
Publication of KR20140025634A publication Critical patent/KR20140025634A/en
Application granted granted Critical
Publication of KR101395633B1 publication Critical patent/KR101395633B1/en

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F1/00Treatment of water, waste water, or sewage
    • C02F1/46Treatment of water, waste water, or sewage by electrochemical methods
    • C02F1/461Treatment of water, waste water, or sewage by electrochemical methods by electrolysis
    • C02F1/46104Devices therefor; Their operating or servicing
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B13/00Conduits for emptying or ballasting; Self-bailing equipment; Scuppers

Abstract

본 발명은 전기분해장치의 수압 측정장치에 관한 것이다. 이러한 전기분해장치의 수압 측정장치는 선박평형수를 전기분해 처리하는 전기분해장치의 해수 유출구 측면에 위치하고, 해수 유출구의 단면과 상응하는 형상을 갖고 있으며, 구멍을 구비하는 제1 지지판, 해수 유출구와 인접하지 않는 제1 지지판의 측면에 위치하고, 둘 이상의 지지대를 구비하는 제1 유압호스 장착부 지지대, 제1 지지판 및 제1 유압호스 장착부 지지대 사이에 위치하고, 한 단부는 제1 지지판의 구멍에 연결되어 전기분해장치 내부의 선박평형수를 유입 받는 수압 측정 호스, 수압 측정 호스에 연결되어 수압 측정 호스 내부를 흐르는 선박평형수의 수압을 계측하고 표시하는 수압 계측기, 제1 유압호스 장착부의 지지대에 연결되고, 외부의 유압 장치로부터 전달 받는 유압 변동에 따라 유압이 유입 받거나 또는 유압을 외부로 배출하는 유압호스, 제1 유압호스 장착부의 상기 지지대에 구비되고, 유압호스 내부의 유압 변동에 따라 수평 방향으로 위치 이동하는 유압 전달 배관, 유압 전달 배관에 연결되고, 유압 전달 배관의 위치 이동에 따라 수평 방향으로 위치 이동하는 체결 위치 변동부, 그리고 체결 위치 변동부에 연결되는 제1 체결부, 제1 체결부에 연결되고 지지대에 연결되는 제2 체결부 및 제3 체결부를 포함한다. 이로 인해, 전기분해장치 내부의 선박평형수의 수압을 효율적으로 측정할 수 있다.The present invention relates to an apparatus for measuring the water pressure of an electrolytic apparatus. The apparatus for measuring the water pressure of the electrolytic apparatus is located on the side of the sea water outlet of the electrolytic apparatus for electrolyzing the ballast water and has a shape corresponding to the cross section of the sea water outlet and includes a first support plate having a hole, The first support plate and the first hydraulic hose mount support, which are located on the sides of the first support plate which are not adjacent to each other, and which are provided between the first hydraulic hose mount support, the first support plate and the first hydraulic hose mount support, A pressure measuring hose connected to the hydraulic pressure measuring hose for measuring the hydraulic pressure of the ballast water flowing in the hydraulic pressure measuring hose and connected to a support of the first hydraulic hose mounting part, The hydraulic pressure is supplied or the hydraulic pressure is discharged to the outside in accordance with the hydraulic pressure transmitted from the external hydraulic device The hydraulic hose is connected to the hydraulic pressure transmitting pipe and the hydraulic pressure transmitting pipe which are provided on the support base of the first hydraulic hose mounting portion and move in the horizontal direction according to the hydraulic pressure fluctuation in the hydraulic hose. And a first coupling part connected to the coupling position varying part, a second coupling part connected to the first coupling part, and a third coupling part connected to the supporting part. Therefore, the water pressure of the ballast water inside the electrolytic apparatus can be efficiently measured.

Description

전기분해장치의 수압 측정 장치{WATER PRESSURE MEASUREMENT APPARATUS FOR ELECTROLYSIS}[0001] WATER PRESSURE MEASUREMENT APPARATUS FOR ELECTROLYSIS [0002]

본 발명은 전기분해장치의 수압 측정 장치에 관한 것이다.The present invention relates to an apparatus for measuring the water pressure of an electrolytic apparatus.

선박에는 선박에 유입되는 선박평형수(밸러스트수, ballast water)의 농도를 유지하기 위해 선박평형수 관리 시스템(BWMS, ballast water management system)이 설치된다. 선박평형수 관리 시스템에 유입된 선박평형수의 농도를 유지하는 한 방법으로, 선박평형수를 전기 분해 처리 할 수 있다.The ship is equipped with a ballast water management system (BWMS) to maintain the concentration of ballast water (ballast water) entering the ship. As a method of maintaining the concentration of ship ballast water entering the ship ballast water management system, the ballast water can be electrolyzed.

이와 같이 선박평형수의 농도 유지를 위한 전기 분해 처리 과정에서 전기 분해 장치가 사용될 수 있다. 전기 분해 장치는 챔버(chamber)에 선박평형수를 유입 받고, 복수개 구비된 전극을 이용하여 선박평형수를 전기분해 처리 한다.In this way, an electrolytic apparatus can be used in the electrolytic treatment process for maintaining the concentration of the ballast water. The electrolytic apparatus receives vessel ballast water into a chamber and electrolyzes the ballast water using a plurality of electrodes.

이러한 종래의 선박평형수 전기분해 장치의 안정성을 확보하기 위해서 전기분해 장치의 수압을 측정해야 하며, 선박평형수 전기분해 장치에 수압 측정용 관을 연결함으로써 전기분해 장치 내부의 수압이 적정 압력을 유지하는 지 판단했다. 따라서, 선박평형수 전기분해 장치에 수압 측정용 관을 연결하기 위해서는 선박평형수 전기분해 장치에 형성된 복수개의 플랜지(flange)에 사람이 직접 볼트를 체결해야 하므로 힘과 시간이 많이 소요된다는 문제가 있었다.In order to secure the stability of such a conventional ballast water electrolytic apparatus, the water pressure of the electrolytic apparatus should be measured, and the water pressure inside the electrolytic apparatus is maintained at an appropriate pressure by connecting the pipe for measuring the water pressure to the ballast water electrolytic apparatus . Therefore, in order to connect the pipe for measuring the pressure of water to the ballast water electrolytic apparatus, there is a problem that the bolt must be directly fastened to a plurality of flanges formed in the ballast water electrolytic apparatus, so that it takes much time and power .

그리고, 인력을 이용하여 전기분해 장치의 플랜지 부위에 볼트를 연결하고 수압 측정용 관을 연결하는 동안 선박평형수 전기분해 장치 내부에 담겨 있던 선박평형수가 플랜지 부위를 통해 외부로 배출되므로 볼트 및 수압 측정용 관을 연결하는 데 어려움이 있다는 문제가 있었다.Since the ballast water contained in the ballast water electrolytic apparatus is discharged to the outside through the flange portion while connecting the bolt to the flange portion of the electrolytic apparatus using the attraction force and connecting the pipe for measuring the water pressure, There was a problem that it was difficult to connect the pipes.

본 발명이 이루고자 하는 기술적 과제는 전기분해 장치의 수압 측정 효율을 향상시키기 위한 것이다.SUMMARY OF THE INVENTION The present invention has been made in order to improve the water pressure measurement efficiency of the electrolytic apparatus.

본 발명의 한 특징에 따른 전기분해장치의 수압 측정장치는 해수 유입구 및 해수 유출구를 구비하고 외부로부터 유입된 선박평형수를 전기분해 처리하는 전기분해장치의 상기 해수 유출구 측면에 위치하고, 상기 해수 유출구의 단면과 상응하는 형상을 갖고 있으며, 구멍을 구비하는 제1 지지판, 상기 해수 유출구와 인접하지 않는 상기 제1 지지판의 측면에 위치하고, 둘 이상의 지지대를 구비하는 제1 유압호스 장착부 지지대, 상기 제1 지지판 및 상기 제1 유압호스 장착부 지지대 사이에 위치하고, 한 단부는 상기 제1 지지판의 상기 구멍에 연결되어 상기 전기분해장치 내부의 선박평형수를 유입 받는 수압 측정 호스, 상기 수압 측정 호스에 연결되어 상기 수압 측정 호스 내부를 흐르는 선박평형수의 수압을 계측하고 표시하는 수압 계측기, 상기 지지대에 연결되고, 외부의 유압 장치로부터 전달 받는 유압 변동에 따라 유압을 유입 받거나 또는 유압을 외부로 배출하는 유압호스,The apparatus for measuring the water pressure of an electrolytic apparatus according to one aspect of the present invention includes a seawater inlet port and a seawater outlet port and is located on the side of the seawater outlet port of the electrolytic apparatus for electrolyzing the ballast water introduced from the outside, A first support plate having a shape corresponding to a cross section and having a hole, a first hydraulic hose mounting portion support located at a side of the first support plate that is not adjacent to the seawater outlet, and having at least two supports, And one end of the hydraulic hose is connected to the hole of the first support plate and connected to the hydraulic pressure measurement hose to receive the ballast water inside the electrolysis apparatus, A water pressure meter for measuring and displaying the hydraulic pressure of the ballast water flowing in the measuring hose, A hydraulic hose that is connected to the base and receives hydraulic pressure or discharges the hydraulic pressure to the outside in accordance with a hydraulic pressure variation transmitted from an external hydraulic device,

상기 지지대에 구비되고, 상기 유압호스 내부의 유압 변동에 따라 수평 방향으로 위치 이동하는 유압 전달 배관, 상기 유압 전달 배관에 연결되고, 상기 유압 전달 배관의 위치 이동에 따라 수평 방향으로 위치 이동하는 체결 위치 변동부, 그리고A hydraulic pressure transmission pipe provided on the support and moving in a horizontal direction in accordance with a hydraulic pressure variation in the hydraulic hose; a hydraulic pressure transmission pipe connected to the hydraulic pressure transmission pipe, Variable part, and

상기 체결 위치 변동부에 연결되는 제1 체결부, 제1 체결부에 연결되고 상기 지지대에 연결되는 제2 체결부 및 제3 체결부를 포함한다.A first fastening portion connected to the fastening position changing portion, a second fastening portion connected to the first fastening portion, and a third fastening portion connected to the support portion.

상기 유압호스 내부의 유압이 외부로 배출될 때 상기 체결 위치 변동부의 위치는 상기 제1 지지판 위치에서 상기 제1 유압호스 장착부 지지대의 위치로 이동하고, 상기 체결 위치 변동부의 위치 이동에 따라 상기 제1 체결부는 상기 체결 위치 변동부와 수직하는 방향으로 위치하고, 상기 제1 체결부의 위치 변동에 따라 상기 제1 체결부에 연결된 상기 제2 체결부의 일측면이 상기 제1 지지판과 수평하도록 위치하는 것이 좋다.Wherein when the hydraulic pressure in the hydraulic hose is discharged to the outside, the position of the clamping position varying part moves from the first supporting plate position to the position of the first hydraulic hose mounting part support, The fastening portion may be located in a direction perpendicular to the fastening position varying portion and one side of the second fastening portion connected to the first fastening portion may be positioned to be horizontal with the first supporting plate in accordance with the positional change of the first fastening portion.

상기 제2 체결부는 단부를 더 포함하고, 상기 제2 체결부의 일측면이 상기 제1 지지판과 수평하도록 위치할 때, 상기 단부는 상기 제1 지지판과 맞닿는 것이 좋다.The second fastening portion may further include an end portion, and when one side of the second fastening portion is positioned to be horizontal with respect to the first support plate, the end portion may abut the first support plate.

상기 유압호스 내부에 외부로부터 유압이 유입될 때 상기 체결 위치 변동부의 위치는 상기 제1 유압호스 장착부 지지대의 위치에서 상기 제1 지지판 위치로 이동하고, 상기 체결 위치 변동부의 위치 이동에 따라 상기 제1 체결부가 상기 체결 위치 변동부와 수평하는 방향으로 위치하고, 상기 제1 체결부의 위치 변동에 따라 상기 제1 체결부에 연결된 상기 제2 체결부의 일측면이 상기 제1 지지판과 떨어지도록 위치하는 것이 좋다.Wherein the position of the clamping position changing portion moves from the position of the first hydraulic hose mounting portion support to the position of the first supporting plate when hydraulic pressure flows from the outside into the hydraulic hose, The fastening portion may be positioned in a direction parallel to the fastening position varying portion and one side of the second fastening portion connected to the first fastening portion may be positioned to be separated from the first support plate in accordance with the positional change of the first fastening portion.

이러한 특징에 따르면, 제1 지지판에 형성된 구멍에 연결된 수압 측정 장치를 통해 전기분해장치의 선박평형수를 수압 측정 하게 되므로, 짧은 시간에 전기분해장치의 수압을 측정 가능하다는 효과가 있다.According to this feature, since the ballast water of the electrolysis apparatus is measured through the water pressure measuring device connected to the hole formed in the first support plate, the water pressure of the electrolysis device can be measured in a short time.

도 1은 본 발명의 한 실시예에 따른 전기분해장치의 수압 측정 장치의 사시도이다.
도 2는 본 발명의 한 실시예에 따른 전기분해장치의 수압 측정 장치의 일부를 도시한 사시도이다.
도 3은 본 발명의 한 실시예에 따른 전기분해장치의 수압 측정 장치에 있어서 제4 지지대 주변의 구조 및 유압에 따른 구조 변경을 도시한 측면도이다.
1 is a perspective view of an apparatus for measuring a water pressure of an electrolytic apparatus according to an embodiment of the present invention.
2 is a perspective view showing a part of a water pressure measuring apparatus of an electrolytic apparatus according to an embodiment of the present invention.
FIG. 3 is a side view showing a structure around the fourth support and a structure change according to the hydraulic pressure in the apparatus for measuring a water pressure of an electrolytic apparatus according to an embodiment of the present invention.

아래에서는 첨부한 도면을 참고로 하여 본 발명의 실시예에 대하여 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art can easily carry out the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In order to clearly illustrate the present invention, parts not related to the description are omitted, and similar parts are denoted by like reference characters throughout the specification.

그러면 첨부한 도면을 참고로 하여 본 발명의 한 실시예에 따른 전기분해 장치의 수압 측정 장치에 대하여 설명한다.Hereinafter, an apparatus for measuring a water pressure of an electrolytic apparatus according to an embodiment of the present invention will be described with reference to the accompanying drawings.

먼저, 도 1 내지 도 3를 참고로 하여, 본 발명의 한 실시예에 따른 전기분해 장치의 수압 측정 장치에 대하여 상세하게 설명한다.First, a water pressure measuring apparatus of an electrolytic apparatus according to an embodiment of the present invention will be described in detail with reference to FIGS. 1 to 3. FIG.

도 1 내지 도 3을 참고로 하면, 본 발명의 한 실시예에 따른 전기분해 장치의 수압 측정 장치는 전기분해 장치(10)를 지지하기 위한 전기분해장치 받침대(100), 전기분해 장치(10)에 선박평형수를 유입 받기 위한 해수 유입구(22)의 일측을 지지하는 제2 지지판(210), 그리고 전기분해 장치(10) 내부의 선박평형수 배출을 위한 해수 유출구(12)의 일측을 지지하는 제1 지지판(210)을 구비한다.1 to 3, an apparatus for measuring the water pressure of an electrolytic apparatus according to an embodiment of the present invention includes an electrolytic apparatus support 100 for supporting the electrolytic apparatus 10, an electrolytic apparatus 10, A second support plate 210 for supporting one side of the seawater inlet 22 for receiving the ballast water in the electrolyzer 10 and a second support plate 210 for supporting one side of the seawater outlet 12 for discharging the ballast water in the electrolyzer 10 And a first support plate 210.

전기분해 장치(10)는 일측면에 제1 지지부(11) 및 제2 지지부(21)를 구비함으로써 전기분해장치 받침대(100) 위에 놓여진다.The electrolytic device 10 is placed on the electrolytic device pedestal 100 by having the first supporting part 11 and the second supporting part 21 on one side.

제1 지지판(110) 및 제2 지지판(210)은 전기분해장치(10)의 해수 유출구(12) 또는 해수 유입구(22)와 상응하도록 원형 형상을 가진다. 이 때, 제1 지지판(110) 또는 제2 지지판(210)의 어느 한 부위에 구멍(110a)이 형성된다. The first support plate 110 and the second support plate 210 have a circular shape corresponding to the seawater outlet 12 or the seawater inlet 22 of the electrolytic apparatus 10. At this time, a hole 110a is formed in either one of the first support plate 110 or the second support plate 210.

그리고, 사각 형상을 갖는 제1 유압호스 장착부 지지대(120)는 제1 지지판(110)의 측면에 위치하고, 이 때 제1 유압호스 장착부 지지대(120)는 제1 지지판(110)이 해수 유출구(12)를 바라보지 않는 다른 한 측면에 위치한다.The first hydraulic hose mounting part support base 120 having a rectangular shape is located on a side surface of the first support plate 110. The first hydraulic hose mounting support base 120 is supported by the first support plate 110 at the sea water outlet 12 ) On the other side.

제1 유압호스 장착부 지지대(120)가 제1 지지판(110)의 측면에 위치하는 것과 마찬가지로, 제1 지지판(110)과 마주 보며 위치하는 제2 지지판(210)의 측면에 사각형상을 갖는 제2 유압호스 장착부 지지대(미도시)가 위치한다. 이 때 제2 유압호스 장착부 지지대(미도시)는 제2 지지판(210)이 해수 유입구(22)를 바라보지 않는 다른 한 측면에 위치한다.The first support plate 110 and the second support plate 210 are positioned on the side of the first support plate 110 and the second support plate 210 facing the first support plate 110, The hydraulic hose mounting support (not shown) is located. At this time, the second hydraulic hose attachment support (not shown) is located on the other side of the second support plate 210 that does not face the seawater inlet 22.

그리고, 제1 받침대(101)가 제1 유압호스 장착부 지지대(120) 하부에 위치함으로써 제1 유압호스 장착부 지지대(120)를 받치고, 제2 받침대(102)는 제2 유압호스 장착부 지지대(미도시) 하부에 위치하여 제2 유압호스 장착부 지지대(미도시)를 받친다.The first pedestal 101 supports the first hydraulic hose mounting support 120 by being positioned below the first hydraulic hose mounting support 120 and the second pedestal 102 supports the second hydraulic hose mounting support 120 ) To support the second hydraulic hose mounting support (not shown).

제1 받침대(101)에는 제1 유압호스 장착부 지지대(120)를 수평 방향으로 이동시키기 위한 제1 이동부(101a) 및 제2 이동부(101b)를 구비하고, 이와 마찬가지로 제2 받침대(102)에는 제2 유압호스 장착부 지지대(미도시)를 이동하기 위한 제3 이동부(미도시) 및 제4 이동부(미도시)를 구비한다.The first pedestal 101 is provided with a first moving part 101a and a second moving part 101b for moving the first hydraulic hose mounting part support 120 in the horizontal direction, A third moving part (not shown) and a fourth moving part (not shown) for moving the second hydraulic hose mounting part support (not shown).

제1 지지판(110)과 제2 지지판(210)이 서로 마주보도록 대응되게 구성되는 것과 같이, 제1 지지판(110)에 연결되는 구성요소들이 제2 지지판(210)에 서로 마주보도록 대응되게 위치하며 동일한 동작을 수행한다. 따라서, 이하의 설명에서는 제1 지지판(110)과 그 주변 구성요소들만 설명하고, 제2 지지판(210)과 그 주변 구성요소들에 대해서는 설명하지 않는다.The first support plate 110 and the second support plate 210 are configured to face each other so that the components connected to the first support plate 110 are positioned to face each other on the second support plate 210 The same operation is performed. Therefore, in the following description, only the first support plate 110 and its surrounding components will be described, and the second support plate 210 and its surrounding components will not be described.

계속해서, 도1 내지 도 3을 참조로 하여 계속해서 본 발명의 구성을 설명하면 제1 유압호스 장착부 지지대(120)와 제1 지지판(110)은 일정 거리(3cm 내지 5cm 가량) 이격되어 위치한다. 1 to 3, the first hydraulic hose mounting portion support 120 and the first support plate 110 are spaced apart from each other by a predetermined distance (about 3 cm to 5 cm) .

이 때, 제1 유압호스 장착부 지지대(120)와 제1 지지판(110) 사이에 형성된 틈에 수압 측정 호스(140)가 위치한다.At this time, the hydraulic pressure measuring hose 140 is positioned in a gap formed between the first hydraulic hose mounting portion supporter 120 and the first supporting plate 110.

수압 측정 호스(140)는 제1 지지판(110)에 형성된 구멍(110a)을 통해 전기분해장치(10)의 해수 유출구(12)와 연결되고, 해수 유출구(12)를 통해 배출되는 전기분해장치(10) 내부의 선박평형수를 전달 받는다.The water pressure measuring hose 140 is connected to the seawater outlet 12 of the electrolytic apparatus 10 through the hole 110a formed in the first supporting plate 110 and to the electrolytic apparatus 10) receives the ship ballast water inside.

수압 측정 호스(140)는 호스 내부를 흐르는 선박평형수의 흐름을 제어하기 위한 밸브(미도시)를 포함한다.The hydraulic pressure measurement hose 140 includes a valve (not shown) for controlling the flow of the ballast water flowing in the hose.

예를 들어, 수압 측정 호스(140)의 밸브가 열려 있는 상태에서는 전기분해장치(10) 내부의 선박평형수가 수압 측정 호스(140)로 흘러 들어가고, 밸브가 닫혀 있는 상태에서는 전기분해장치(10) 내부의 선박평형수가 수압 측정 호스(140)로 들어가지 않는다.For example, when the valve of the hydraulic pressure hose 140 is open, the ballast water in the electrolytic apparatus 10 flows into the hydraulic pressure measurement hose 140. When the valve is closed, The inner ballast water does not enter the hydraulic pressure measurement hose 140.

수압 측정 호스(140)의 한 단부는 제1 지지판(110)에 형성된 구멍(110a)에 연결된다. 추후 전기분해 장치(10)의 수압 측정을 위해, 본 발명 전기분해 장치의 수압 측정 장치에 전기분해장치(10)를 연결함에 따라, 제1 지지판(110)과 전기분해장치(10)의 해수 유출구(12)가 닿게 되면, 전기분해 장치(10) 내부의 선박평형수가 해수 유출구(12) 및 제1 지지판(110)에 형성된 구멍(110a)을 통해 외부로 배출된다. 그리고, 구멍(110a)을 통해 배출된 선박평형수가 제1 지지판(110)의 구멍(110a)에 연결된 수압 측정 호스(140) 내부로 유입된다.One end of the hydraulic pressure hose 140 is connected to the hole 110a formed in the first support plate 110. [ The electrolytic apparatus 10 is connected to the water pressure measuring apparatus of the electrolytic apparatus of the present invention for measuring the water pressure of the electrolytic apparatus 10 so that the first support plate 110 and the seawater outlet The ballast water inside the electrolytic apparatus 10 is discharged to the outside through the seawater outlet 12 and the hole 110a formed in the first supporting plate 110. [ The ballast water discharged through the hole 110a flows into the water pressure measurement hose 140 connected to the hole 110a of the first support plate 110. [

수압 계측기(141)는 수압 측정 호스(140)의 일측에 구비되고, 수압 측정 호스(140) 내부를 흐르는 선박평형수의 수압을 측정하여 표시한다. The hydraulic pressure gauge 141 is provided on one side of the hydraulic pressure hose 140 and measures and displays the hydraulic pressure of the ballast water flowing in the hydraulic pressure hose 140.

제1 지지판(110)에 형성된 구멍(110a)에 연결되지 않는 수압 측정 호스(140)의 다른 단부는 수압 측정 호스(140) 내부에 유입되었다가 외부로 배출되는 선박평형수를 보관하기 위한 물탱크 등에 연결된다.The other end of the water pressure measurement hose 140 which is not connected to the hole 110a formed in the first support plate 110 is connected to a water tank for storing the ballast water to be introduced into the water pressure measurement hose 140, And the like.

또한, 사각 형상을 갖는 제1 유압호스 장착부 지지대(120)의 가로 길이 및 세로 길이는 제1 지지판(110)의 지름보다 크게 형성된다. In addition, the length and the length of the first hydraulic hose mount support base 120 having a rectangular shape are larger than the diameter of the first support plate 110.

그리고, 제1 지지대(130a), 제2 지지대(130b), 제3 지지대(130c), 그리고 제4 지지대(130d)가 제1 유압호스 장착부 지지대(120)에 연결된다. 이 때, 제1 지지대(130a) 내지 제4 지지대(130d)는 제1 유압호스 장착부 지지대(120)의 각 꼭지점에 각각 위치한다.The first support base 130a, the second support base 130b, the third support base 130c and the fourth support base 130d are connected to the first hydraulic hose support support base 120. [ In this case, the first to fourth supports 130a to 130d are located at the respective vertexes of the first hydraulic hose mount support 120, respectively.

제1 지지대(130a)에는 제1 유압호스(151) 및 제2 유압호스(152)가 연결되고, 제2 지지대(130b)에는 제3 유압호스(161) 및 제4 유압호스(162)가 연결되며, 제3 지지대(130c)에는 제5 유압호스(171) 및 제6 유압호스(172)가 연결된다. 그리고, 제4 지지대(130d)에는 제7 유압호스(181) 및 제8 유압호스(182)가 각각 연결된다.A first hydraulic hose 151 and a second hydraulic hose 152 are connected to the first support base 130a and a third hydraulic hose 161 and a fourth hydraulic hose 162 are connected to the second support base 130b And a fifth hydraulic hose 171 and a sixth hydraulic hose 172 are connected to the third support 130c. The seventh hydraulic hose 181 and the eighth hydraulic hose 182 are connected to the fourth support base 130d.

여기서, 제1 지지대(130a) 내지 제4 지지대(130d)를 구성하는 요소들은 서로 동일한 구조를 갖고 동일한 동작을 수행하므로, 이하의 설명에서는 제4 지지대(130d)에 위치하는 구성요소들을 중심으로 설명하며, 제1 지지대(130a) 내지 제3 지지대(130c)의 구성 요소들에 대해서는 설명하지 않는다.Since the elements constituting the first to fourth supports 130a to 130d have the same structure and perform the same operation as the first to third supports 130a to 130d in the following description, And the components of the first to third supports 130a to 130c are not described.

그러나, 설명되지 않는 구성요소들은 이미 설명된 구성요소들과 동일한 구성을 가지며 동일한 동작을 수행하므로, 도2 및 도 3에는 도시하지 않은 구성요소들이 설명되지 않음으로 인해 구성 또는 동작을 실시불가 하다고 오해되지 않아야 할 것이다. However, since the unexplained components have the same configuration and perform the same operation as the components already described, the components or components not shown in FIGS. 2 and 3 are not described. It should not be.

제4 지지대(130d)는 'ㄱ' 형상 또는 'ㄴ' 형상과 같이 90도 각도로 꺾여 있고, 제1 유압호스 장착부 지지대(120)와 제1 지지판(110) 사이의 이격된 틈에 위치한다.The fourth support 130d is bent at an angle of 90 degrees as in the 'a' shape or the 'a' shape and is located in a spaced gap between the first hydraulic hose mount support 120 and the first support plate 110.

여기서, 제4 지지대(130d)의 일측은 제1 유압호스 장착부 지지대(120)와 닿도록 연결되고, 제1 유압호스 장착부 지지대(120)와 연결되지 않는 제4 지지대(130d)의 다른 일측에 유압호스 연결부(181a, 182a)가 연결된다.One side of the fourth support base 130d is connected to the first hydraulic hose support support base 120 and the other side of the fourth support base 130d which is not connected to the first hydraulic hose support base 120, Hose connections 181a, 182a are connected.

이 때, 제7 유압호스 연결부(181a)에는 제7 유압호스(181)가 연결되고, 제8 유압호스 연결부(182a)에는 제8 유압호스(182)가 연결된다.A seventh hydraulic hose 181 is connected to the seventh hydraulic hose connecting portion 181a and an eighth hydraulic hose 182 is connected to the eighth hydraulic hose connecting portion 182a.

제4 유압 배관(183a)은 제7 유압호스 연결부(181a) 및 제8 유압호스 연결부(182a) 사이에 위치하고, 제4 유압 배관(183a)는 제7 유압호스(181) 및 제8 유압호스(182) 내부의 유압을 전달 받는다.The fourth hydraulic pipe 183a is located between the seventh hydraulic hose connecting portion 181a and the eighth hydraulic hose connecting portion 182a and the fourth hydraulic pipe 183a is located between the seventh hydraulic hose 181 and the eighth hydraulic hose 182a. 182).

제4 유압전달 배관(183)은 제4 유압 배관(183a)과 연결된다. 제4 유압전달 배관(183)은 제8 유압호스 연결부(182a)의 측면에 위치하고, 제4 유압 배관(183a) 내부의 유압 흐름에 따라 수평 방향으로 이동한다.The fourth hydraulic pressure transmission pipe 183 is connected to the fourth hydraulic pressure pipe 183a. The fourth hydraulic pressure transmission pipe 183 is located on the side of the eighth hydraulic hose connection portion 182a and moves in the horizontal direction according to the hydraulic pressure flow inside the fourth hydraulic pressure pipe 183a.

예를 들어, 제7 유압호스(181) 및 제8 유압호스(182)로부터 제4 유압배관(183a) 내부에 유압이 유입될 때는, 제4 유압전달 배관(183)이 도3의 (a)에 도시한 바와 같이 위치한다. 반면에, 제4 유압배관(183a) 내부의 유압이 제7 유압호스(181) 및 제8 유압호스(182)로 배출될 때는, 제4 유압전달 배관(183)이 도3의 (b)에 도시한 바와 같이 위치한다. For example, when the hydraulic pressure flows into the fourth hydraulic pressure pipe 183a from the seventh hydraulic hose 181 and the eighth hydraulic hose 182, As shown in Fig. On the other hand, when the hydraulic pressure inside the fourth hydraulic pressure pipe 183a is discharged to the seventh hydraulic pressure hose 181 and the eighth hydraulic pressure hose 182, the fourth hydraulic pressure transmission pipe 183 is connected to the As shown in FIG.

제4 유압전달 배관(183)이 제8 유압호스 연결부(182a)와 인접하지 않는 제4 유압전달 배관(183)의 한 단부에는 제4 체결 위치 변동부(184)가 위치한다. The fourth fastening position changing portion 184 is located at one end of the fourth hydraulic pressure transmitting pipe 183 where the fourth hydraulic pressure transmitting pipe 183 is not adjacent to the eighth hydraulic hose connecting portion 182a.

그리고, 제1 체결부(185)의 한쪽 단부는 제4 체결 위치 변동부(184)와 연결되고, 제1 체결부(185)의 다른 한쪽 단부는 제2 체결부(186)와 연결된다.One end of the first fastening portion 185 is connected to the fourth fastening position varying portion 184 and the other end of the first fastening portion 185 is connected to the second fastening portion 186.

이 때, 제3 체결부(187)의 한쪽 단부는 제1 체결부(185)의 가운데 부분과 연결되고, 제3 체결부(187)의 다른 한쪽 단부는 제4 돌출부(185a)와 연결된다.At this time, one end of the third fastening portion 187 is connected to the middle portion of the first fastening portion 185, and the other end of the third fastening portion 187 is connected to the fourth projecting portion 185a.

제4 돌출부(185a)는 제4 지지대(130a)에 위치하고, 제3 체결부(187)와 제2 체결부(186)과 각각 연결된다.The fourth projection 185a is located on the fourth support 130a and connected to the third coupling part 187 and the second coupling part 186, respectively.

이와 같이, 제4 지지대(130d) 주변에 구성되는 제1 체결부(185), 제2 체결부(186), 그리고 제3 체결부(187)에 있어서, 제1 체결부(185)는 체결 위치 변동부(184)의 위치 변동에 따라 위치가 변하게 되고, 이에 따라 제2 체결부(186) 및 제3 체결부(187)의 위치도 변하게 된다.As described above, in the first fastening portion 185, the second fastening portion 186, and the third fastening portion 187 formed around the fourth support 130d, the first fastening portions 185 are fastened to the fastening portions 185, The position of the second fastening portion 186 and the position of the third fastening portion 187 are changed according to the positional variation of the variable portion 184.

예를 들어, 도3의 (a)에서는 유압 전달 배관(183)이 좌측으로 돌출되어 있고 따라서 체결 위치 변동부(184)도 좌측으로 돌출되도록 위치한다. 이 때, 체결 위치 변동부(184)에 연결된 제1 체결부(185)는 가로 방향으로 누워 있는 상태로 위치하게 되고, 제1 체결부(185)의 위치에 따라 제3 체결부(187)는 수평 방향으로 위치하며, 제2 체결부(186)는 'v' 형상으로 위치한다.For example, in FIG. 3 (a), the hydraulic pressure transmission pipe 183 protrudes to the left, so that the clamping position varying portion 184 also protrudes to the left. At this time, the first fastening part 185 connected to the fastening position varying part 184 is located in a state of being laid in the transverse direction, and the third fastening part 187, depending on the position of the first fastening part 185, And the second fastening portion 186 is positioned in the 'v' shape.

그러나, 도3의 (b)와 같이 유압 전달 배관(183)이 우측으로 위치하면 체결 위치 변동부(184)는 돌출되지 않고 제8 유압호스 연결부(182a)와 인접한 위치에 위치한다. 이 때, 체결 위치 변동부(184)에 연결된 제1 체결부(185)는 세로 방향으로 위치하게 되고, 제1 체결부(185)의 위치에 따라 제3 체결부(187)도 세로 방향으로 위치하게 되며, 제2 체결부(186)는 'ㄴ' 형상으로 위치한다.However, when the hydraulic pressure transmission pipe 183 is positioned to the right as shown in FIG. 3 (b), the fastening position varying portion 184 does not protrude and is located at a position adjacent to the eighth hydraulic hose connecting portion 182a. At this time, the first fastening portion 185 connected to the fastening position varying portion 184 is positioned in the vertical direction, and the third fastening portion 187 is also positioned in the vertical direction according to the position of the first fastening portion 185 And the second fastening portion 186 is positioned in an 'a' shape.

제2 체결부(186)는 단부(188)를 더 구비한다. 단부(188)에는 고무 패킹(189)이 부착되는데, 고무 패킹(189)은 제2 체결부(186)가 도3의 (b)와 같이 위치했을 때 제2 체결부(186)가 제1 지지판(100)에 직접 닿는 것을 방지하기 위함이다.
The second fastening portion 186 further includes an end portion 188. A rubber packing 189 is attached to the end portion 188 such that when the second fastening portion 186 is positioned as shown in Figure 3 (b), the second fastening portion 186 is fixed to the first support plate 186. [ (100).

다음으로, 도1 내지 도3을 참조하여 본 발명 전기분해장치의 수압 측정 장치의 동작 및 이를 이용하여 전기분해장치(10)의 수압을 측정하는 동작에 대하여 상세하게 설명한다.Next, the operation of the water pressure measuring apparatus of the electrolytic apparatus of the present invention and the operation of measuring the water pressure of the electrolytic apparatus 10 using the apparatus will be described in detail with reference to FIG. 1 to FIG.

먼저, 제1 이동부(101a) 및 제2 이동부(101b)를 이용하여 제1유압호스 장착부 지지대(120)를 전기분해장치 받침대(100)로부터 멀어지도록 위치시킨다. 이 때, 도면에는 도시되지 않았으나 제2 유압호스 장착부(미도시) 역시 전기분해장치 받침대(100)로부터 멀어지도록 위치시킨다.First, the first hydraulic hose mounting portion support base 120 is positioned away from the electrolytic apparatus pedestal 100 by using the first moving portion 101a and the second moving portion 101b. At this time, although not shown in the drawing, the second hydraulic hose mounting portion (not shown) is also located away from the electrolytic apparatus pedestal 100.

그리고, 공중에서 기중기와 같은 들 것을 이용하여 전기분해장치(10)의 몸체에 로프(1)를 묶고, 수직 방향으로 로프(1)를 끌어올림으로써 전기분해장치(10)를 공중으로 끌어올린다. 그런 다음, 공중으로 끌어올려진 전기분해장치(10)를 전기분해장치 받침대(100) 위에 올려놓는다. Then, the rope 1 is tied to the body of the electrolytic apparatus 10 by lifting the rope 1 in the vertical direction by using a lifter such as a crane in the air, thereby pulling up the electrolytic apparatus 10 to the air. Then, the electrolytic device 10 pulled up to the air is placed on the electrolytic device pedestal 100.

이 때, 전기분해 장치(10) 하단면에 형성된 제1 지지부(11) 및 제2 지지부(21)를 이용하여 전기분해장치(10)를 전기분해장치 받침대(100) 위에 올린다.At this time, the electrolytic device 10 is placed on the electrolytic device pedestal 100 by using the first supporting part 11 and the second supporting part 21 formed on the lower end face of the electrolytic device 10.

다음으로, 전기분해장치(10)로부터 떨어져 위치하는 제1 유압호스 장착부 지지대(120) 및 제2 유압호스 장착부 지지대(미도시)를 전기분해장치(10) 방향으로 수렴하도록 이동시킨다. Next, the first hydraulic hose mounting portion support 120 and the second hydraulic hose mounting portion support (not shown) located away from the electrolytic device 10 are moved to converge toward the electrolytic device 10. [

이 때, 제1 유압호스 장착부 지지대(120)의 이동은 제1 이동부(101a) 및 제2 이동부(101b)를 통해 이루어지고, 제2 유압호스 장착부 지지대(미도시) 역시 이와 같은 동작으로 이동한다.At this time, the movement of the first hydraulic hose mounting portion support base 120 is performed through the first moving portion 101a and the second moving portion 101b, and the second hydraulic hose mounting portion support (not shown) Move.

그리고 도면에 도시되지는 않았으나 제2 유압호스 장착부 지지대(미도시)를 전기분해 장치(10)의 해수 유입구(22)와 인접하도록 위치시킴으로써, 전기분해 장치 받침대(100) 위에 놓여진 전기분해장치(10)의 해수 유출구(12) 및 해수 유입구(22)가 제1 지지판(110) 및 제2 지지판(210)에 각각 닿도록 위치하게 된다.(Not shown), but by placing the second hydraulic hose mount support (not shown) adjacent to the seawater inlet 22 of the electrolyzer 10, the electrolytic apparatus 10 And the seawater inlet port 22 and the seawater inlet port 22 are positioned so as to touch the first support plate 110 and the second support plate 210, respectively.

더욱 상세하게는, 제1 유압호스 장착부 지지대(120)를 전기분해 장치(10)의 해수 유출구(12)와 인접하도록 위치시키고, 제1 지지판(110)에 형성된 구멍(110a)에 수압 측정 호스(140)를 연결한다. More specifically, the first hydraulic hose mount support 120 is positioned adjacent to the seawater outlet 12 of the electrolytic apparatus 10, and a hole 110a formed in the first support plate 110 is connected to a hydraulic pressure measurement hose 140).

그런 다음, 전기분해장치(10) 내부의 선박평형수의 수압 측정을 위하여 외부의 유압 장치(미도시)를 구동함으로써 수압 측정 장치에 구비된 유압호스들(151, 152, …, 181, 182) 내부의 유압을 배출한다.Then, the hydraulic hoses 151, 152, ..., 181 and 182 provided in the hydraulic pressure measuring apparatus are driven by driving an external hydraulic apparatus (not shown) for measuring the hydraulic pressure of the ballast water in the electrolytic apparatus 10, And the internal hydraulic pressure is discharged.

이 때, 유압 장치(미도시)의 구동에 따라 제1 유압호스(151), 제2 유압호스(152), 제3 유압호스(161), 제4 유압호스(162), 제5 유압호스(171), 제6 유압호스(172), 제7 유압호스(181), 그리고 제8 유압호스(182) 내부의 유압이 동시에 외부로 배출된다.At this time, the first hydraulic hose 151, the second hydraulic hose 152, the third hydraulic hose 161, the fourth hydraulic hose 162, and the fifth hydraulic hose (not shown) 171, the sixth hydraulic hose 172, the seventh hydraulic hose 181, and the eighth hydraulic hose 182 are simultaneously discharged to the outside.

도3의 (b)에 도시한 것과 같이, 제4 유압 배관(183a) 내부의 유압이 제7 유압호스(181) 및 제8 유압호스(182)를 통해 외부로 배출되게 되고, 제4 유압 배관(1830a) 내부의 유압이 배출됨에 따라, 제4 유압 전달 배관(183)의 위치가 체결 위치 변동부(184)에서 제8 유압호스 연결부(182a) 방향으로 변동된다.The hydraulic pressure in the fourth hydraulic pipe 183a is discharged to the outside through the seventh hydraulic hose 181 and the eighth hydraulic hose 182 as shown in FIG. The position of the fourth hydraulic pressure transmission pipe 183 varies in the direction from the engagement position varying portion 184 to the eighth hydraulic hose connection portion 182a as the hydraulic pressure in the hydraulic pressure transmission pipe 1830a is discharged.

그리고, 제4 유압 전달 배관(183)의 위치가 변동됨에 따라 체결 위치 변동부(184)의 위치가 변동되고, 또한 제2 체결부(186)의 위치도 변동되게 되어 최종적으로는 제2 체결부(186)에 연결된 단부(188) 및 고무 패킹(189)이 해수 유출구(12)에 닿게 된다.As the position of the fourth hydraulic pressure transmission pipe 183 is changed, the position of the fastening position varying portion 184 is changed, and the position of the second fastening portion 186 is also changed. As a result, The end 188 and the rubber packing 189 connected to the seawater outlet 186 contact the seawater outlet 12.

설명한 바와 같이, 유압이 외부로 배출되면서 제1 유압호스 장착부 지지대(120)에 연결된 제1 지지대(130a) 내지 제4 지지대(130d)에 형성된 고무패킹들(189 등)이 제1 지지판(110)에 닿게 된다. The rubber packings 189 and the like formed on the first to third support rods 130a to 130d connected to the first hydraulic hose mount support 120 are discharged from the first support plate 110 while the hydraulic pressure is discharged to the outside, .

위의 동작과 같이 제1 지지판(110)이 해수 유출구(12) 및 제1 유압호스 장착부 지지대(120)와 인접하도록 위치하게 되면, 밸브가 열려 있는 상태의 수압 측정 호스(140)가 제1 지지판(110)의 구멍(110a)을 통해 해수 유출구(12)와 연결된다. 이 때, 전기분해 장치(10) 내부의 선박평형수가 수압 측정 호스(140)에 흘러 들어가게 된다.When the first support plate 110 is positioned adjacent to the seawater outlet 12 and the first hydraulic hose mount support 120 as in the above operation, Is connected to the seawater outlet (12) through the hole (110a) of the casing (110). At this time, the ballast water inside the electrolytic apparatus 10 flows into the water pressure measuring hose 140.

그리고 이 때, 수압 계측기(141)는 수압 측정 호스(140) 내부를 흐르는 선박평형수의 수압을 측정하여 표시한다.At this time, the hydraulic pressure gauge 141 measures and displays the hydraulic pressure of the ballast water flowing in the hydraulic pressure hose 140.

전기분해장치(10) 내부의 선박평형수에 대한 수압 측정이 완료되면, 전기분해장치(10)를 수압 측정 장치로부터 탈거하기 위하여 외부의 유압 장치(미도시)에 유압을 공급한다.When the water pressure measurement on the ballast water inside the electrolytic apparatus 10 is completed, the hydraulic pressure is supplied to an external hydraulic apparatus (not shown) to remove the electrolytic apparatus 10 from the hydraulic pressure measurement apparatus.

유압 장치(미도시)에 유압이 공급됨에 따라 제1 유압호스(151), 제2 유압호스(152), 제3 유압호스(161), 제4 유압호스(162), 제5 유압호스(171), 제6 유압호스(172), 제7 유압호스(181), 그리고 제8 유압호스(182) 내부로 동시에 유압이 유입된다.The first hydraulic hose 151, the second hydraulic hose 152, the third hydraulic hose 161, the fourth hydraulic hose 162 and the fifth hydraulic hose 171 The sixth hydraulic hose 172, the seventh hydraulic hose 181, and the eighth hydraulic hose 182, respectively.

도3에 도시된 제4 지지대(130d)의 구성을 중심으로 설명하면, 제7 유압호스(181) 및 제8 유압호스(182)로 유입된 유압은 제4 유압 배관(183a) 내부로 전달되고, 따라서 제4 유압 배관(183a)에 연결된 제4 유압 전달 배관(183)이 수평 방향으로 돌출된다.3, the hydraulic pressure introduced into the seventh hydraulic hose 181 and the eighth hydraulic hose 182 is transmitted to the inside of the fourth hydraulic pipe 183a So that the fourth hydraulic pressure transmission pipe 183 connected to the fourth hydraulic pressure pipe 183a projects horizontally.

또한, 제4 유압 전달 배관(183)의 위치 변동에 따라 체결 위치 변동부(184)의 위치도 변동 되므로 제1 체결부(185)의 위치가 바뀌게 되며, 따라서 제2 체결부(186)의 단부(188)에 연결된 고무패킹(189)이 제1 지지판(110)과 거리가 멀어지게 된다.The position of the fastening position varying portion 184 is also changed in accordance with the positional change of the fourth hydraulic pressure transmitting pipe 183 so that the position of the first fastening portion 185 is changed, The rubber packing 189 connected to the first support plate 188 is distanced from the first support plate 110.

따라서, 제4 지지대(130d)는 제1 체결부(185) 내지 제3 체결부(187)에 의해 고정되지 않고 이동이 자유로워지게 되고, 제1 지지대(130a), 제2 지지대(130b), 제3 지지대(130c)도 마찬가지로 각각의 체결부들로부터 자유로워진다. Accordingly, the fourth support 130d is not fixed by the first coupling part 185 to the third coupling part 187 but is free to move, and the first support part 130a, the second support part 130b, The third support 130c is likewise freed from the respective fasteners.

그리고 나서, 제1 이동부(101a) 및 제2 이동부(101b)를 이용하여 제1 유압호스 장착부 지지대(120)를 전기분해장치(10)에서 멀어지는 방향으로 이동시키고, 제2 유압호스 장착부 지지대(미도시) 역시 전기분해장치(10)에서 멀어지는 방향으로 이동시킨 후, 공중의 기중기와 같은 들 것과 로프(1)를 이용하여 수압 측정이 완료된 전기분해장치(10)를 전기분해장치 받침대(100)로부터 떨어트림으로써 수압 측정 과정을 완료한다.Then, the first hydraulic hose mounting portion support base 120 is moved in the direction away from the electrolytic apparatus 10 by using the first moving portion 101a and the second moving portion 101b, and the second hydraulic hose mounting portion support 120 (Not shown) is moved in a direction away from the electrolytic apparatus 10, and then the electrolytic apparatus 10, which is the same as a public crane, and which has undergone hydraulic pressure measurement using the rope 1, ) To complete the hydrostatic measurement process.

그리고, 해수 유출구(12)에 연결된 제1 지지판(110)의 구멍(110a) 및 구멍(110a)에 연결된 수압 측정 호스(140)를 통해 외부로 배출되는 전기분해 장치(10) 내의 선박평형수는 수압 측정 호스(140)에 구비된 수압 계측기(141)에서 수압이 계측되며 계측된 수압 값이 표시된다.The ballast water in the electrolyzer 10 discharged to the outside through the hole 110a of the first supporting plate 110 connected to the seawater outlet 12 and the water pressure measuring hose 140 connected to the hole 110a The water pressure is measured by the water pressure meter 141 provided in the water pressure measuring hose 140 and the measured water pressure value is displayed.

수압 측정이 완료되면 외부의 유압 장치에서 유압을 변동시켜 제1 유압호스(151) 내지 제8 유압호스(182) 내부에 유압을 유입하고, 이에 따라 제1 유압 전달 배관(153) 내지 제4 유압 전달 배관(183) 등의 위치가 변동되게 되므로, 고무 패킹들(159, 169, 179, 189)이 해수 유출구(12) 또는 해수 유입구(22)로부터 멀어지게 된다.When hydraulic pressure measurement is completed, the hydraulic pressure is changed in an external hydraulic device to introduce hydraulic pressure into the first hydraulic hose 151 through the eighth hydraulic hose 182, and thereby the first hydraulic pressure transmission pipe 153 to the fourth hydraulic pressure The rubber packing 159, 169, 179, 189 is moved away from the seawater outlet 12 or the seawater inlet 22 since the position of the delivery pipe 183 is changed.

그리고, 제1 이동부(101a) 및 제2 이동부(101b)를 통해 제1 유압호스 장착부 지지대(120)를 이동시켜(반대편의 제2 유압호스 장착부 지지대도 마찬가지로 이동시킴) 제1 지지판(110) 및 제2 지지판(210)을 전기분해장치(10)와 떨어지도록 위치시킨다.The first hydraulic hose mounting portion support base 120 is moved through the first moving portion 101a and the second moving portion 101b so as to move the second hydraulic hose mounting base support on the opposite side, And the second support plate 210 are placed apart from the electrolytic apparatus 10. [

마지막으로, 수압 측정이 완료된 전기분해장치(10)를 공중의 기중기와 같은 들 것을 이용하여 로프(1)에 묶어 본 발명 전기분해 장치의 수압 측정 장치로부터 탈거시킨다.
Finally, the electrolytic apparatus 10 with the hydrostatic pressure measurement completed is bundled with the rope 1 using a hoist, such as a public hoist, to remove it from the hydrostatic measuring apparatus of the electrolytic apparatus of the present invention.

이상에서 본 발명의 실시예에 대하여 상세하게 설명하였지만 본 발명의 권리범위는 이에 한정되는 것은 아니고 다음의 청구범위에서 정의하고 있는 본 발명의 기본 개념을 이용한 당업자의 여러 변형 및 개량 형태 또한 본 발명의 권리범위에 속하는 것이다.While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed exemplary embodiments, It belongs to the scope of right.

10 : 전기분해장치 100 : 전기분해장치 받침대
110 : 제1 지지판 120 : 제1 유압호스 장착부 지지대
130a~130d : 제 N 지지대 140 : 수압 측정 호스
141 : 수압 계측기 181, 182: 유압호스
183 : 유압 전달 배관 184 : 체결 위치 변동부
185 : 제1 체결부 186 : 제2 체결부
187 : 제3 체결부 188 : 단부
189 : 고무 패킹 210 : 제2 지지판
10: electrolytic apparatus 100: electrolytic apparatus stand
110: first supporting plate 120: first hydraulic hose mounting part support
130a to 130d: N-th support 140: Hydraulic pressure measuring hose
141: Hydraulic measuring instrument 181, 182: Hydraulic hose
183: Hydraulic transmission piping 184: Clamping position variation part
185: first fastening part 186: second fastening part
187: third fastening part 188: end
189: Rubber packing 210: Second support plate

Claims (4)

해수 유입구 및 해수 유출구를 구비하고 외부로부터 유입된 선박평형수를 전기분해 처리하는 전기분해장치의 상기 해수 유출구 측면에 위치하고, 상기 해수 유출구의 단면과 상응하는 형상을 갖고 있으며, 구멍을 구비하는 제1 지지판,
상기 해수 유출구와 인접하지 않는 상기 제1 지지판의 측면에 위치하고, 둘 이상의 지지대를 구비하는 제1 유압호스 장착부 지지대,
상기 제1 지지판 및 상기 제1 유압호스 장착부 지지대 사이에 위치하고, 한 단부는 상기 제1 지지판의 상기 구멍에 연결되어 상기 전기분해장치 내부의 선박평형수를 유입 받는 수압 측정 호스,
상기 수압 측정 호스에 연결되어 상기 수압 측정 호스 내부를 흐르는 선박평형수의 수압을 계측하고 표시하는 수압 계측기,
상기 지지대에 연결되고, 외부의 유압 장치로부터 전달 받는 유압 변동에 따라 유압을 유입 받거나 또는 유압을 외부로 배출하는 유압호스,
상기 지지대에 연결되고, 상기 유압호스 내부의 유압 변동에 따라 수평 방향으로 위치 이동하는 유압 전달 배관,
상기 유압 전달 배관에 연결되고, 상기 유압 전달 배관의 위치 이동에 따라 수평 방향으로 위치 이동하는 체결 위치 변동부,
상기 체결 위치 변동부에 연결되어 상기 체결 위치 변동부의 위치 이동에 따라 위치 이동하는 제1 체결부,
상기 제1 체결부 및 상기 지지대에 연결되어 상기 제1 체결부의 위치 이동에 따라 위치 이동하는 제2 체결부, 그리고
상기 제1 체결부 및 상기 지지대에 연결되어 상기 제1 체결부의 위치 이동에 따라 위치 이동하는 제3 체결부
를 포함하는 전기분해장치의 수압 측정 장치.
An electrolytic apparatus having a seawater inlet and a seawater outlet and electrolytically processing the ballast water introduced from the outside, the electrolytic apparatus having a shape corresponding to an end face of the seawater outlet, A support plate,
A first hydraulic hose mounting portion support positioned on a side surface of the first support plate that is not adjacent to the seawater outlet and having two or more supports,
A hydraulic pressure measuring hose connected to the hole of the first supporting plate to receive the ballast water in the electrolytic apparatus,
A water pressure meter connected to the water pressure measurement hose for measuring and displaying the water pressure of the ballast water flowing in the water pressure measurement hose,
A hydraulic hose which is connected to the support and receives hydraulic pressure or discharges the hydraulic pressure to the outside in accordance with a hydraulic pressure fluctuation transmitted from an external hydraulic pressure device,
A hydraulic pressure transmission pipe connected to the support and moving in a horizontal direction in accordance with a hydraulic pressure variation in the hydraulic hose,
A clamping position changing part connected to the hydraulic pressure transmitting pipe and moving in the horizontal direction according to the movement of the hydraulic pressure transmitting pipe,
A first fastening portion connected to the fastening position changing portion and moved in accordance with a positional shift of the fastening position changing portion,
A second fastening portion connected to the first fastening portion and the support, the second fastening portion being moved according to the positional movement of the first fastening portion,
And a third fastening part connected to the first fastening part and the support and moving according to the positional movement of the first fastening part,
And an electrolytic apparatus for electrolyzing water.
제1항에서,
상기 유압호스 내부의 유압이 외부로 배출될 때 상기 체결 위치 변동부는 상기 제1 지지판에서 상기 제1 유압호스 장착부 지지대의 방향으로 위치 이동하고,
상기 체결 위치 변동부의 위치 이동에 따라 상기 제1 체결부는 상기 체결 위치 변동부와 수직하는 방향으로 위치하고,
상기 제1 체결부의 위치 변동에 따라 상기 제1 체결부에 연결된 상기 제2 체결부의 일측면이 상기 제1 지지판과 수평하도록 위치하는 전기분해장치의 수압 측정 장치.
The method of claim 1,
When the hydraulic pressure in the hydraulic hose is discharged to the outside, the clamping position varying part is moved in the direction of the first hydraulic hose mounting part support from the first supporting plate,
The first fastening portion is positioned in a direction perpendicular to the fastening position varying portion in accordance with the movement of the fastening position changing portion,
And one side surface of the second fastening portion connected to the first fastening portion is positioned to be level with the first support plate in accordance with the positional change of the first fastening portion.
제2항에서,
상기 제2 체결부는 단부를 더 포함하고,
상기 제2 체결부의 일측면이 상기 제1 지지판과 수평하도록 위치할 때, 상기 단부는 상기 제1 지지판과 맞닿는 전기분해장치의 수압 측정장치.
3. The method of claim 2,
Wherein the second fastening portion further comprises an end,
Wherein the end portion abuts the first support plate when one side of the second fastening portion is positioned to be horizontal with the first support plate.
제1항에서,
상기 유압호스 내부에 외부로부터 유압이 유입될 때 상기 체결 위치 변동부의 위치는 상기 제1 유압호스 장착부 지지대에서 상기 제1 지지판 방향으로 위치 이동하고,
상기 체결 위치 변동부의 위치 이동에 따라 상기 제1 체결부가 상기 체결 위치 변동부와 수평하는 방향으로 위치하고,
상기 제1 체결부의 위치 변동에 따라 상기 제1 체결부에 연결된 상기 제2 체결부의 일측면이 상기 제1 지지판과 떨어지도록 위치하는 전기분해장치의 수압 측정 장치.
The method of claim 1,
When the hydraulic pressure is supplied from the outside to the inside of the hydraulic hose, the position of the clamping position varying portion moves from the first hydraulic hose mounting portion support to the first support plate,
The first fastening portion is positioned in a direction parallel to the fastening position varying portion in accordance with the movement of the fastening position varying portion,
Wherein one side of the second fastening portion connected to the first fastening portion is positioned to be separated from the first support plate in accordance with a change in the position of the first fastening portion.
KR1020120091152A 2012-08-21 2012-08-21 Water pressure measurement apparatus for electrolysis KR101395633B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120091152A KR101395633B1 (en) 2012-08-21 2012-08-21 Water pressure measurement apparatus for electrolysis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120091152A KR101395633B1 (en) 2012-08-21 2012-08-21 Water pressure measurement apparatus for electrolysis

Publications (2)

Publication Number Publication Date
KR20140025634A KR20140025634A (en) 2014-03-05
KR101395633B1 true KR101395633B1 (en) 2014-05-19

Family

ID=50640582

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120091152A KR101395633B1 (en) 2012-08-21 2012-08-21 Water pressure measurement apparatus for electrolysis

Country Status (1)

Country Link
KR (1) KR101395633B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1129089A (en) * 1997-07-08 1999-02-02 T K Shitsupingu Japan Kk Automatic ballast water exchanging system
JP2000070942A (en) 1998-09-04 2000-03-07 Zojirushi Corp Ionized water forming device
JP2002086131A (en) 2000-09-11 2002-03-26 Kankyo Kogaku:Kk Method for managing water treatment system and water treatment apparatus
KR20050033651A (en) * 2002-08-23 2005-04-12 사우디 아라비안 오일 컴퍼니 Ballast exchange system for marine vessels

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1129089A (en) * 1997-07-08 1999-02-02 T K Shitsupingu Japan Kk Automatic ballast water exchanging system
JP2000070942A (en) 1998-09-04 2000-03-07 Zojirushi Corp Ionized water forming device
JP2002086131A (en) 2000-09-11 2002-03-26 Kankyo Kogaku:Kk Method for managing water treatment system and water treatment apparatus
KR20050033651A (en) * 2002-08-23 2005-04-12 사우디 아라비안 오일 컴퍼니 Ballast exchange system for marine vessels

Also Published As

Publication number Publication date
KR20140025634A (en) 2014-03-05

Similar Documents

Publication Publication Date Title
US7938957B2 (en) Method and apparatus of submersible intake equipment
CN106247011B (en) A kind of splicing of major diameter Long-distance Pipeline for Water Conveyance, sinking system and method
KR101395633B1 (en) Water pressure measurement apparatus for electrolysis
JP2012526233A5 (en)
CN103696460B (en) Oblique-casing water intake method and device
CN206685019U (en) A kind of physics teaching buoyant device
CN204314153U (en) Nonmetal pipeline pressure testing device
CN205120323U (en) Experimental apparatus is sealed to cylinder head
CN215811120U (en) Pulley counter weight type magnetic float liquid level meter
CN205175717U (en) Defeated distribution network pilot scale test platform
CN206814469U (en) Tower-type aerator system
CN204848834U (en) Agitating unit is blent to white spirit
CN209081984U (en) A kind of preventing oil pipe sulks phosphating plant
CN211401366U (en) Magnetic turning plate liquid level meter fixing structure
KR20130003889U (en) Water flowing apparatus for experiment
CN220486509U (en) Integrative hoist and mount formula intelligence caisson water injection device
RU126695U1 (en) PLANT FOR PRODUCING SODIUM HYPOCHLORITE
CN202442860U (en) Pipeline analog detector
CN207383109U (en) It is a kind of that there is the irrigation rig of tree straightening
CN203216679U (en) MED injection pump leakage detection auxiliary device
CN210070917U (en) Convenient open caisson differential settlement observation device
CN210243105U (en) Complete set bellows gas tightness testing arrangement
CN213446390U (en) Dosing device of water treatment system for three-dimensional electro-Fenton-like degradation of ketoprofen
CN215323169U (en) Supporting device
CN108191042A (en) A kind of portable aeration oxygenator for biochemistry pool

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170405

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20180504

Year of fee payment: 5