KR101180455B1 - non cut off water supply method by non cut off water supply module equipment - Google Patents
non cut off water supply method by non cut off water supply module equipment Download PDFInfo
- Publication number
- KR101180455B1 KR101180455B1 KR1020120039392A KR20120039392A KR101180455B1 KR 101180455 B1 KR101180455 B1 KR 101180455B1 KR 1020120039392 A KR1020120039392 A KR 1020120039392A KR 20120039392 A KR20120039392 A KR 20120039392A KR 101180455 B1 KR101180455 B1 KR 101180455B1
- Authority
- KR
- South Korea
- Prior art keywords
- box
- pipe
- valve
- fluid
- induction
- Prior art date
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L55/00—Devices or appurtenances for use in, or in connection with, pipes or pipe systems
- F16L55/18—Appliances for use in repairing pipes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23D—PLANING; SLOTTING; SHEARING; BROACHING; SAWING; FILING; SCRAPING; LIKE OPERATIONS FOR WORKING METAL BY REMOVING MATERIAL, NOT OTHERWISE PROVIDED FOR
- B23D21/00—Machines or devices for shearing or cutting tubes
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L55/00—Devices or appurtenances for use in, or in connection with, pipes or pipe systems
- F16L55/16—Devices for covering leaks in pipes or hoses, e.g. hose-menders
- F16L55/1604—Devices for covering leaks in pipes or hoses, e.g. hose-menders by means of a by-pass conduit
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L55/00—Devices or appurtenances for use in, or in connection with, pipes or pipe systems
- F16L55/16—Devices for covering leaks in pipes or hoses, e.g. hose-menders
- F16L55/1608—Devices for covering leaks in pipes or hoses, e.g. hose-menders by replacement of the damaged part of the pipe
Abstract
Description
본발명은 부단수 모듈 장치를 이용한 부단수 시공방법에 관한 것으로, 보다 상세하게는 관절단박스와 관연결박스를 설치하여 유체가 흐르는 관을 절단하여 교체하는 부단수 모듈을 이용한 부단수 시공방법에 관한 것이다.The present invention relates to a sheet construction method using a section module apparatus, and more particularly, to a section construction method using a section module that cuts and replaces a pipe in which a fluid flows by installing a joint section box and a pipe connection box. It is about.
일반적으로 수도관과 같이 물이 지속적으로 흐르는 관이 노후되어 교체하거나 동파 및 사고 등에 의해 파손되었을 경우, 이를 교체 및 긴급히 보수하게 된다. 그리고 상기와 같이 교체 및 보수작업중 관을 차단할 수밖에 없었으며, 이 경우 물을 공급받는 자들은 물을 사용할 수 없어서 불편을 겪게 된다. 이러한 문제점을 개선하기 위해, 수도관 교체 및 보수공사중에도 물을 계속공급할 수 있는 부단수 장치나 방법들이 개발되었고, 일례로서,In general, when a pipe continuously flowing water, such as a water pipe, is replaced due to aging or broken by freezing and an accident, it is replaced and urgently repaired. And as described above was forced to shut off the pipe during the replacement and repair work, in this case, those who are supplied with water will be inconvenient because they can not use the water. To remedy this problem, water-reducing devices or methods have been developed to continuously supply water during water pipe replacement and repair work.
등록특허공보 등록번호 10-0741576호에는 억제하기 위한 외부팩커를 구비한 팽창팩커에 의해 상하수도관의 내부를 밀폐하는 차수부;상기 연결관의 상단에 구비되며, 유사시 차수밸브핸들을 이용하여 제수용 밸브로 사용하는 차수밸브;상기 차수밸브의 상단에 구비되는 원통형의 팩커실린더;상기 팩커실린더의 상단에 구비되는 원판상의 상부덮개;상기 차수부를 승강시키는 승강장치와;하단은 상기 차수부의 에어주입관에 연결되고, 상단은 상부덮개의 외부로 배출되는 주입튜브;를 포함하고, 상기 차수부는, 중앙의 하우징을 중심으로 내부고정슬리브와 외부고정슬리브가 순차적으로 구비되되, 상기 하우징의 외부와 팽창팩커의 내부 사이에는 에어주입관으로부터 공급된 공기가 유입되어 팽창팩커가 부풀어 오르도록 공간부가 형성됨을 특징으로 하는 상?하수도관 보수를 위한 비절단 차수장치가 공개되어 있다. Patent No. 10-0741576 discloses an ordered part for sealing the inside of the water supply and sewage pipe by an expansion packer having an external packer for suppressing; A degree valve used as a valve; a cylindrical packer cylinder provided at an upper end of the degree valve; an upper cover of a disc provided at an upper end of the packer cylinder; an elevating device for elevating the degree part; Is connected to, the upper end; the injection tube is discharged to the outside of the upper cover; including, the order portion, the inner fixing sleeve and the outer fixing sleeve is provided with a center around the center of the housing, the outside and the expansion packer Between the inside of the air supplied from the air inlet pipe is introduced, characterized in that the space is formed so as to swell the expansion pack On? The non-cutting-order apparatus for sewage pipe repair to the public.
또한, 등록특허공보 등록번호 10-0799480에는 수도관 보수를 위한 차수 장치에 있어서, 수도관에 결합되는 하부받침부와;상기 수도관에 형성된 절삭천공개구부 상부에 상기 수도관 내부와 연통되도록 상기 하부받침부에 결합되며 내부에 상기 수도관을 따라 흐르는 물의 방향과 수평으로 작동되어 상기 수도관의 절삭천공개구부를 통해 상기 물이 누출되지 않도록 상기 절삭천공개구부를 개폐하는 통수용차폐밸브가 구비된 통수용차폐밸브하우징과; 상기 통수용차폐밸브하우징의 상부에 설치되며 내부에 승강장치를 통해 승강동작하여 상기 통수용차폐밸브하우징과 상기 수도관의 절삭천공개구부를 관통하면서 상기 수도관 내부를 차폐하는 차수용밸브가 구비된 차수용밸브하우징을 포함하여 구성된 것을 특징으로 하는 수도관 보수를 위한 차수장치가 공개되어 있다. In addition, Patent Publication No. 10-0799480 has a lower support portion coupled to the water pipe in the water repelling device for water pipe repair; Coupled to the lower support portion to communicate with the inside of the water pipe on the upper cutting hole opening formed in the water pipe And a water blocking valve housing provided with a water blocking valve for opening and closing the cutting hole opening so that the water does not leak through the cutting hole opening of the water pipe to be operated horizontally with the direction of water flowing along the water pipe. A water supply valve is installed on an upper portion of the water blocking valve housing and is provided with a water leveling valve to shield the inside of the water pipe while passing through the water blocking valve housing and the cutting hole opening of the water pipe by moving up and down through a lifting device therein. A water repellent device for repairing a water pipe, comprising a housing, is disclosed.
그러나 상기와 같은 종래기술들은 부단수 장치를 이용한 부단수 시공방법이 복잡하며 부단수 작업을 위한 시간이 많이 소요됨으로써, 전체적인 공사시간이 길어지며 경비가 상승되고, 또한 부단수 작업 뒤에도 하자가 발생하는 등의 단점이 있었다. However, the prior art as described above is complicated by the method of construction of the number of units using the number of devices and the time required for the number of operations is increased, the overall construction time is increased, the cost is increased, and defects occur even after work There was such a disadvantage.
따라서 본 발명은 상기와 같은 문제점을 해결하고자 안출된 것으로, 관절단박스와 관연결박스를 설치하여 유체가 흐르는 관을 절단하여 유체를 유도함으로써, 관을 교체 또는 보수하는 작업중에도 유체의 단수가 없이 물을 원활하게 공급할 수 있으며, 또한 작업을 신속하고 간단하게 할 수 있는 부단수 모듈 장치를 이용한 부단수 시공방법을 제공하고자 하는 것이다.Therefore, the present invention has been made to solve the above problems, by installing a joint end box and a pipe connection box to induce the fluid by cutting the pipe flowing fluid, without the number of fluids during the operation of replacing or repairing the pipe It is intended to provide a method for constructing a sheet water using a sheet water module device that can supply water smoothly and can also perform work quickly and simply.
본발명은 부단수 모듈 장치를 이용한 부단수 시공방법에 관한 것으로, 유체가 흐르는 관을 절단한 후 유체를 유도하는 부단수 모듈 장치를 이용한 부단수 시공방법에 있어서, 관의 규격에 따라 부단수모듈장치의 하부박스(130)를 제작 및 설치하는 하부박스 설치단계; 상기 하부박스(130) 위에 샌드위치밸브(120)를 설치하고 밸브판(122)을 뒤로 당겨서 열어두는 샌드위치밸브 설치단계; 상기 샌드위치밸브(120)위에 상부절단박스(110)를 설치하는 상부절단박스 설치단계; 유압실린더를 동력원으로 하는 절단톱(140)이 승하강하며 관을 절단하는 관 절단 단계; 절단된 관(240)을 상부절단박스(110)의 내부 상부로 들어올려서 철거하는 단계; 샌드위치밸브(120)의 밸브판(122)을 앞으로 밀어서 유체를 차단하는 유체차단단계; 상부절단박스(110)를 철거하는 상부절단박스 철거단계; 상부절단박스(110)를 철거한 하부박스(130) 상부에 유체유도박스(210)를 설치하되 상기 유체유도박스(210)의 유도밸브(232)에 유도관의 일단을 연결하며 상기 유도관의 타단을 물을 공급하는 관에 연결하며, 상기 유체유도박스(210)의 유도밸브(232)는 열어두는 유체 유도박스 설치단계; 샌드위치밸브(120)를 개방하여 물을 공급하는측 관의 물이 하부박스(130), 상부의 유체유도박스(210)를 통하여 유도밸브(232), 유도관을 통해 물을 공급받는 관 방향으로 흘러가게 하는 샌드위치 밸브 개방단계; 막음판(230)을 하강시켜 물을 공급받는 측의 절단관의 절단부위를 막는 막음판 차단단계; 두 개의 관절단 모듈 장치 사이의 공사가 완료되면, 막음판(230)을 상승시켜 막음판(230)을 여는 막음판 개방단계; 샌드위치밸브(120)를 차단한 후 유체유도박스(210)를 철거하는 유체유도박스 철거단계; 차단판(320)을 샌드위치밸브(120) 대신 삽입설치하고 샌드위치밸브(120)를 철거하는 샌드위치밸브 철거단계; 를 포함하는 것을 특징으로 한다.The present invention relates to a sheet construction method using a section module apparatus, and in the section construction method using a section module apparatus for guiding a fluid after cutting a pipe in which a fluid flows, the section module according to a pipe standard A lower box installation step of manufacturing and installing the
따라서 본발명은 관절단박스와 관연결박스를 설치하여 유체가 흐르는 관을 절단하여 유체를 유도함으로써, 관을 교체 또는 보수하는 작업중에도 유체의 단수가 없이 물을 원활하게 공급할 수 있으며, 또한 작업을 신속하고 간단하게 할 수 있는 현저한 효과가 있다.Therefore, the present invention installs a joint end box and a pipe connection box to induce fluid by cutting a pipe through which the fluid flows, so that water can be smoothly supplied without changing the water even during the replacement or maintenance of the pipe. There is a significant effect that can be done quickly and simply.
도 1은 본발명 관절단박스 사시도
도 2는 도 1의 정면도
도 3은 본발명 하부박스 사시도
도 4는 본발명 관절단박스 부분절개도
도 5는 본발명 관절단박스 내부 사시도
도 6은 본발명 관절단박스의 띠톱이 관을 절단한 후 절단된 관에 철거관 승강봉이 결합된 상태도
도 7은 도 6의 평면도
도 8은 도 6의 측면도
도 9는 본발명 관절단박스의 철거관 승강봉이 절단된 관을 상부로 끌어올린 후의 사시도
도 10은 도 9의 정면도 및 부분상세도
도 11은 도 9의 평면도
도 12는 도 9의 측면도
도 13은 본발명 관절단박스의 작동 개략도
도 14는 본발명 관절단박스의 띠톱 작동 개략도
도 15는 본발명 관절단박스의 샌드위치 밸브 개략 사시도
도 16은 본발명 관절단박스의 샌드위치 작동(정면)도
도 17은 본발명 하부박스와 샌드위치 밸브의 결합도
도 18은 본발명 관연결박스 사시도
도 19는 도 18의 정면도
도 20은 본발명 관연결박스 내부도
도 21은 도 20의 정면도
도 22는 도 20의 평면도
도 23은 도 20의 측면도
도 24는 본발명 관연결박스에서 유체유도박스의 막음판이 하강하여 관의 절단된 부위를 막은 상태도
도 25는 도 24의 정면도
도 26은 도 24의 평면도
도 27은 도 24의 측면도
도 28은 본발명 관연결박스의 막음판 작동도
도 29는 본발명에서 차단판 설치 설명도
도 30은 본발명에서 맹판 설치 설명도
도 31은 본발명에서 차단판 설치조립도
도 32는 도 31의 정면도
도 33은 도 31의 평면도
도 34는 도 31의 측면도
도 35는 차단판 및 맹판 설치후 단면설명도1 is a perspective view of the joint box of the present invention
FIG. 2 is a front view of FIG. 1
3 is a perspective view of the lower box of the present invention
4 is a partial cutaway view of the joint box of the present invention
Figure 5 is a perspective view of the inner joint box of the present invention
6 is a state in which the demolition pipe lifting bar is coupled to the cut pipe after the band saw of the joint box of the present invention cut the pipe
Fig. 7 is a plan view of Fig. 6
8 is a side view of FIG. 6
Figure 9 is a perspective view of the demolition pipe lifting bar of the present invention articulated box after pulling up the cut pipe
10 is a front view and a partial detailed view of FIG.
11 is a top view of FIG. 9
12 is a side view of FIG. 9
Figure 13 is a schematic view of the operation of the joint box of the present invention
Figure 14 is a schematic view of the band saw operation of the present invention articulation box
15 is a schematic perspective view of the sandwich valve of the present invention articulated end box
Figure 16 is a sandwich operation (front) of the joint box of the present invention
17 is a coupling diagram of the present invention lower box and the sandwich valve
18 is a perspective view of the connection box of the present invention
19 is a front view of FIG. 18
20 is a view inside the connection box of the present invention
FIG. 21 is a front view of FIG. 20
FIG. 22 is a top view of FIG. 20
FIG. 23 is a side view of FIG. 20
24 is a state in which the blocking plate of the fluid induction box is lowered in the pipe connection box of the present invention to block the cut portion of the pipe
25 is a front view of FIG. 24;
FIG. 26 is a top view of FIG. 24.
FIG. 27 is a side view of FIG. 24
Figure 28 is the operation of the blocking plate of the present invention pipe connection box
Figure 29 is an explanatory view of the installation of a block plate in the present invention
30 is a diagram illustrating a blind installation in the present invention
Figure 31 is a block diagram installation assembly in the present invention
32 is a front view of FIG. 31;
33 is a top view of FIG. 31;
34 is a side view of FIG. 31;
35 is a cross-sectional view after installing the blocking plate and the blind plate
본발명은 부단수 모듈 장치를 이용한 부단수 시공방법에 관한 것으로, 유체가 흐르는 관을 절단한 후 유체를 유도하는 부단수 모듈 장치를 이용한 부단수 시공방법이다. 상기 부단수 시공방법에 대해 구체적으로 기재하면, 먼저 관의 규격에 따라 부단수모듈장치의 하부박스(130)를 제작 및 설치하는 하부박스를 설치한다. The present invention relates to a sheet construction method using a sheet module unit, and a sheet construction method using a sheet module unit for guiding a fluid after cutting a pipe through which a fluid flows. When describing in detail the method of construction of the sub-number, first, install a lower box for manufacturing and installing the
이후 상기 하부박스(130) 위에 샌드위치밸브(120)를 설치하고 밸브판(122)을 뒤로 당겨서 열어두게 된다.Thereafter, the
이후 상기 샌드위치밸브(120)위에 상부절단박스(110)를 설치한다. 그리고 유압실린더를 동력원으로 하는 절단톱(140)이 승하강하며 관을 절단하게 되며, 절단된 관(240)을 상부절단박스(110)의 내부 상부로 들어올려서 철거한다.Thereafter, the
그리고 샌드위치밸브(120)의 밸브판(122)을 앞으로 밀어서 유체를 차단하고, 상부절단박스(110)를 철거한다.Then, the
그리고 상부절단박스(110)를 철거한 하부박스(130) 상부에 유체유도박스(210)를 설치하되, 상기 유체유도박스(210)의 유도밸브(232)에 유도관의 일단을 연결하며 상기 유도관의 타단을 물을 공급하는 관에 연결하고, 상기 유체유도박스(210)의 유도밸브(232)는 열어둔다.And the
이 후샌드위치밸브(120)를 개방하여 물을 공급하는측 관의 물이 하부박스(130), 상부의 유체유도박스(210)를 통하여 유도밸브(232), 유도관을 통해 물을 공급받는 관 방향으로 흘러가게 하다.The water pipe of the side pipe for supplying water by opening the
이후 막음판(230)을 하강시켜 물을 공급받는 측의 절단관의 절단부위를 막는다. 그리고 통상 두 개의 관절단 모듈 장치를 공사하고자 하는 구간에 설치하고, 그 구간 사이에서 관교체공사나 관보수공사를 하므로, 상기 두 개의 관절단 모듈 장치 사이의 공사가 완료되면, 막음판(230)을 상승시켜 막음판(230)을 열게 된다.Since the
이 후 샌드위치밸브(120)를 차단한 후 유체유도박스(210)를 철거한다. After blocking the
그리고 마지막 단계로 차단판(320)을 샌드위치밸브(120) 대신 삽입설치하고 샌드위치밸브(120)를 철거하게 된다.
And the last step is to install the
본발명을 첨부도면에 의해 상세히 설명하면 다음과 같다.도 1은 본발명 관절단박스 사시도, 도 2는 도 1의 정면도, 도 3은 본발명 하부박스 사시도, 도 4는 본발명 관절단박스 부분절개도, 도 5는 본발명 관절단박스 내부 사시도, 도 6은 본발명 관절단박스의 띠톱이 관을 절단한 후 절단된 관에 철거관 승강봉이 결합된 상태도, 도 7은 도 6의 평면도, 도 8은 도 6의 측면도, 도 9는 본발명 관절단박스의 철거관 승강봉이 절단된 관을 상부로 끌어올린 후의 사시도, 도 10은 도 9의 정면도 및 부분상세도, 도 11은 도 9의 평면도, 도 12는 도 9의 측면도, 도 13은 본발명 관절단박스의 작동 개략도, 도 14는 본발명 관절단박스의 띠톱 작동 개략도, 도 15는 본발명 관절단박스의 샌드위치 밸브 개략 사시도, 도 16은 본발명 관절단박스의 샌드위치 작동(정면)도, 도 17은 본발명 하부박스와 샌드위치 밸브의 결합도, 도 18은 본발명 관연결박스 사시도, 도 19는 도 18의 정면도, 도 20은 본발명 관연결박스 내부도, 도 21은 도 20의 정면도, 도 22는 도 20의 평면도, 도 23은 도 20의 측면도, 도 24는 본발명 관연결박스에서 유체유도박스의 막음판이 하강하여 관의 절단된 부위를 막은 상태도, 도 25는 도 24의 정면도, 도 26은 도 24의 평면도, 도 27은 도 24의 측면도, 도 28은 본발명 관연결박스의 막음판 작동도, 도 29는 본발명에서 차단판 설치 설명도, 도 30은 본발명에서 맹판 설치 설명도, 도 31은 본발명에서 차단판 설치조립도, 도 32는 도 31의 정면도, 도 33은 도 31의 평면도, 도 34는 도 31의 측면도, 도 35는 차단판 및 맹판 설치후 단면설명도이다. The present invention will be described in detail with reference to the accompanying drawings. FIG. 1 is a perspective view of the joint box of the present invention, FIG. 2 is a front view of FIG. 1, FIG. 3 is a perspective view of the lower box of the present invention, and FIG. 4 is a joint box of the present invention. 5 is a perspective view of the inner end joint box, Figure 6 is a state in which the demolition pipe lifting bar is coupled to the cut pipe after the band saw of the present invention joint end box, Fig. 7 is 8 is a side view of FIG. 6, FIG. 9 is a perspective view of the demolition pipe lifting bar of the present invention joint end box after pulling up the cut pipe, FIG. 10 is a front view and a partial detail view of FIG. Figure 9 is a plan view of Figure 9, Figure 12 is a side view of Figure 9, Figure 13 is an operation schematic view of the present invention joint box, Figure 14 is a band saw operation schematic view of the present invention joint box, Figure 15 is a sandwich valve schematic of the present invention joint box 16 is a perspective view of the sandwich operation (front) of the present invention joint box, Figure 17 is a view Coupling view of the light lower box and the sandwich valve, Figure 18 is a perspective view of the present invention connection box, Figure 19 is a front view of Figure 18, Figure 20 is an inner view of the present invention connection box, Figure 21 is a front view of Figure 20, FIG. 22 is a plan view of FIG. 20, FIG. 23 is a side view of FIG. 20, FIG. 24 is a state diagram in which the blocking plate of the fluid induction box is lowered in the pipe connection box of the present invention to prevent a cut portion of the pipe, and FIG. 25 is a front view of FIG. FIG. 26 is a plan view of FIG. 24, FIG. 27 is a side view of FIG. 24, FIG. 28 is an operation view of a blocking plate of the present invention connecting box, FIG. 29 is an explanatory view of a blocking plate installation in the present invention, and FIG. Installation explanatory drawing, FIG. 31 is a block diagram installation assembly view of the present invention, FIG. 32 is a front view of FIG. 31, FIG. 33 is a plan view of FIG. 31, FIG. 34 is a side view of FIG. 31, FIG. Explanatory cross section.
본발명은 부단수 모듈 장치를 이용한 부단수 시공방법에 관한 것으로, 상기 부단수 모듈 장치는 유체가 흐르는 관을 절단하여 유체를 유도하기 위한 부단수 모듈 장치로서 관절단박스(100)와 관연결박스(200)로 이루어진다. The present invention relates to a section construction method using a section module apparatus, the section module apparatus is a section section module device for guiding a fluid by cutting a pipe through which a fluid flows, the
또한, 상기 관절단박스(100)는 내부에 절단톱(140)이 설치되어 있는 상부절단박스(110)와, 상기 상부절단박스(110) 하부에 설치되는 샌드위치밸브(120)와, 상기 샌드위치밸브(120) 하부에 설치되는 하부박스(130)로 구성된다. In addition, the
또한, 상기 절단톱(140)은 유압모터 또는 전기모터를 동력원으로 하는 띠톱장치인 것으로, 유압모터 또는 전기모터에 의해 회전되는 수직 구동축(142)과, 상기 수직구동축(142)으로부터 회전력을 전달받아 회전되는 반대편의 수직피동축(143)과, 상기 수직구동축(142)과 수직피동축(143) 사이에 설치되어 회전하며 관을 절단하는 띠톱(144)으로 구성되며, 상기 절단톱은 유압실린더에 의해 승하강되는 것이다. In addition, the cutting saw 140 is a band saw device using a hydraulic motor or an electric motor as a power source, and receives a rotational force from the
또한, 상기 관연결박스(200)는 내부에 막음판(230)이 설치되며 측면에는 유도밸브가 설치되어 있는 상부의 유체유도박스(210)와, 상기 유체유도박스(210) 하부에 설치되는 샌드위치밸브(120)와, 상기 샌드위치밸브(120) 하부에 설치되는 하부박스(130)로 구성되는 것이다. In addition, the
또한, 상기 막음판(230)은 유체유도박스(210) 상부에 설치된 유압실린더에 상단이 결합된 것으로, 유압실린더가 하강함에 따라서 하부박스(130) 하부까지 하강하여 물을 공급받는 측의 관인 절단된 관(240)의 절단부위면과 밀착되어 물의 흐름을 봉쇄하는 것이다. In addition, the blocking
곧, 본발명에서 사용되는 부단수 모듈 장치는 관절단박스(100)와 관연결박스(200)로 이루어진다. Soon, the water module module used in the present invention is composed of a
또한, 상기 관절단박스(100)는 내부에 절단톱(140)이 설치되어 있는 상부절단박스(110)와, 상기 상부절단박스(110) 하부에 설치되는 샌드위치밸브(120)와, 상기 샌드위치밸브(120) 하부에 설치되는 하부박스(130)로 구성된다. 상기 샌드위치밸브는 직사각형 형상의 케이스 내부에 직사각형 판상의 밸브가 설치되며, 상기 판형 밸브를 전후로 슬라이딩하며 물의 유로를 개폐하는 것으로, 도면에 도시된 것과 같이, 관용적으로 사용되는 밸브이다. In addition, the
그리고 본발명의 상기 절단톱(140)은 유압모터 또는 전기모터를 동력원으로 하는 띠톱장치인 것으로, 유압모터 또는 전기모터에 의해 회전되는 수직 구동축(142)과, 상기 수직구동축(142)으로부터 회전력을 전달받아 회전되는 반대편의 수직피동축(143)과, 상기 수직구동축(142)과 수직피동축(143) 사이에 설치되어 회전하며 관을 절단하는 띠톱(144)으로 구성된다. 그리고 상기 절단톱은 유압모터 또는 전기모터의 구동에 의해 유압실린더가 승하강함에 따라 승하강되며 상기 관을 절단하게 되는 것이다.
The cutting saw 140 of the present invention is a band saw device using a hydraulic motor or an electric motor as a power source, and includes a
그리고 상기와 같이 절단된 철거관은 상부절단박스의 내부 상부로 들어서 철거하게 되는 것으로, 상부절단박스의 상부에는 유압으로 가동되는 철거관 승강봉이 설치되어 있고, 상기 승강봉의 하부 단부는 나선부가 형성된 뾰족부가 형성되어 상기 뾰족부가 상기 철거관에 구멍을 뚫고 나선부에 고정한 후 유압에 의해 상부로 들어올리게 된다. 상기와 같이 들어올려진 철거관은 상기 상부절단박스의 내부 상부천정부분에 그대로 위치하게 된다. 그리고 다음공정에서 상부절단박스를 철거하고 관연결박스를 설치할 때 상부절단박스와 함께 철거된다.
And the demolition pipe cut as described above is to be removed by entering the inner upper portion of the upper cutting box, the upper portion of the upper cutting box is provided with a demolition pipe lifting rod that is hydraulically operated, the lower end of the elevating rod is a sharp point formed with a spiral An additional portion is formed so that the pointed portion is drilled in the demolition pipe and fixed to the spiral portion, and then lifted upward by hydraulic pressure. The demolition pipe lifted as described above is located in the upper ceiling portion of the upper cutting box as it is. In the next process, the upper cutting box is removed and the upper cutting box is removed together with the pipe connection box.
그리고 본발명의 관절단작업이 끝난 후 설치되는 관연결박스(200)는 내부에 막음판(230)이 설치되며, 바깥 측면에는 개폐가 가능한 유도밸브가 설치되어 있는 상부의 유체유도박스(210)와, 상기 유체유도박스(210) 하부에 설치되는 샌드위치밸브(120)와, 상기 샌드위치밸브(120) 하부에 설치되는 하부박스(130)로 구성된다. And the
상기 샌드위치밸브와 하부박스는 관절단박스에서 사용되는 것을 그대로 사용하며, 단지 관절단박스의 상부박스를 철거하고 대신 내부에 막음판이 설치된 유체유도박스(210)를 교체설치하는 것이다. The sandwich valve and the lower box is used as it is used in the joint end box, it is to just remove the upper box of the joint end box and replace and install the
상기 막음판(230)은 직사각형 또는 원형 형상으로서 유체유도박스(210) 상부에 위치하는 유압실린더에 상단이 결합되어, 유압실린더가 하강하면 따라서 하부박스(130)까지 하강하여 물을 공급받는 관측인 절단된 관(240)의 절단부위면과 밀착되어 절단부위를 막게되는 것이다. The blocking
이 후 두 개의 관절단모듈 사이의 배관공사가 완료되면, 막음판을 상승시켜 막음판을 열게 되고, 그리고 샌드위치밸브를 차단한 후 유체유도박스를 철거하며, 샌드위치 밸브 상부에 차단장치(310)를 설치한 후 샌드위치 밸브를 열고, 유압모터 및 전기모터의 구동장치에 의해 차단판이 하강하게 되어 유체가 상부로 유출되는 것을 차단한다. 차단판은 상기 샌드위치 밸브의 밸브판 위치보다 하부까지 내려간다. 이후 차단장치를 철거하고 샌드위치 밸브를 철거한다. 그리고 최종적으로 맹플랜지(End cap)를 설치한다. 상기 두 개의 관절단모듈은 배관관로에 그대로 두어 물공급관으로 이용하게 되는 것이다.
After the piping work between the two joint end module is completed, the blocking plate is raised to open the blocking plate, and after closing the sandwich valve, the fluid induction box is removed, and the
본발명의 작업순서를 구체적으로 기재하면 다음과 같다. 먼저 관의 규격에 따라 하부박스를 제작 및 설치한다. 이 후 상기 하부박스 위에 샌드위치밸브를 설치하고 밸브를 열어두게 된다. 이 후 상기 샌드위치밸브위에 상부 절단 박스를 설치한다. The working sequence of the present invention is described in detail as follows. First, manufacture and install the lower box according to the standard of the pipe. After that, the sandwich valve is installed on the lower box and the valve is left open. After that, the upper cut box is installed on the sandwich valve.
그리고 상기 상부 절단 박스 내부에 설치된 절단톱을 작동하는 것으로, 상기 절단톱은 유압모터 또는 전기모터를 동력원으로 하며, 유압모터 또는 전기모터에 상하운동되는 실린더가 하강함에 따라 절단톱이 하강하며 관을 절단하게 된다. And by operating a cutting saw installed inside the upper cutting box, the cutting saw is a power source of a hydraulic motor or an electric motor, the cutting saw is lowered as the cylinder descends up and down the hydraulic motor or electric motor descends the pipe Will cut.
그리고 상기와 같이 절단된 철거관은 상부절단박스의 내부 상부로 들어서 철거하게 된다. 상부절단박스의 상부에는 유압모터 또는 전기모터에 의해 가동되는 철거관 승강봉이 설치되어 있고, 상기 승강봉의 하부단부는 나선부가 형성된 뾰족부가 형성되어 상기 뾰족부가 상기 철거관에 구멍을 뚫고 나선부에 고정한 후 상부로 들어올리게 된다. 상기와 같이 들어올려진 철거관은 상기 상부절단박스의 내부 상부천정부분에 위치하게 된다. And the demolition pipe cut as described above is to be removed by entering the inner upper portion of the upper cutting box. The upper part of the upper cutting box is provided with a demolition pipe elevating rod which is operated by a hydraulic motor or an electric motor, and the lower end of the elevating rod is formed with a pointed portion formed with a spiral, and the pointed portion drills a hole in the demolition pipe and is fixed to a spiral portion. It is then lifted to the top. The demolition pipe lifted as described above is located in the upper ceiling portion of the upper cutting box.
그리고 상기와 같이 철거관을 들어올린후 샌드위치밸브내부의 밸브를 밀어서 유체를 차단하게 된다. 이후 상부절단박스를 철거한다. Then, after lifting the demolition pipe as described above, the fluid is blocked by pushing the valve inside the sandwich valve. After that, remove the upper cutting box.
이 후 상기와 같이 상부절단박스를 철거한 곳에 유체유도박스를 설치하되, 상기 유체유도박스의 유도밸브에 유도관의 일단을 연결하며 상기 유도관의 타단에는 유도밸브가 설치되고 이후 샌드위치밸브를 개방하여 막음판을 하강시켜 물을 공급받는 측의 절단관의 절단부위를 막은 뒤 상기 유도밸브를 개방하여 물을 공급하는 관에 연결되게 한다. Thereafter, the fluid induction box is installed where the upper cutting box is removed as described above, but one end of the induction pipe is connected to the induction valve of the fluid induction box, and an induction valve is installed at the other end of the induction pipe, and then the sandwich valve is opened. By lowering the blocking plate to block the cut portion of the cutting pipe on the side receiving water to open the induction valve to be connected to the pipe for supplying water.
이 후 두 개의 관절단모듈 사이의 공사가 완료되면, 막음판을 상승시켜 막음판을 열게 된다. After the construction between the two joint end module is completed, the blocking plate is raised to open the blocking plate.
그리고 샌드위치밸브를 차단한 후 유체 유도박스를 철거하며, 차단장치(310)를 샌드위치 밸브위에 설치한 후 샌드위치 밸브를 열게 되고, 유압모터 및 전기모터의 구동장치에 의해 차단판이 하강하게 되어 상부로 유출되려는 유체를 차단한다. 차단판은 상부철판과, 상기 상부철판보다 면적이 적은 하부철판 이중으로 설치된다. 그리고 상기 하부박스의 상면은 테두리를 따라서 홈이 형성되어 있고, 테두리 하부에는 단턱이 형성되어 있어서, 상기 상부철판에는 회전가능한 결합편이 상면에 설치되어 있어서, 상기 하부철판을 먼저 하부박스에 삽입하고 단턱에 걸려 고정시키고, 상부철판을 삽입한 후, 상부철판의 결합편을 회전시켜 상기 하부박스 테두리 홈에 삽입시켜 고정한다. 이 후 차단장치를 철거하고, 샌드위치 밸브를 철거한 후, 최종적으로 맹플랜지(End cap)를 설치하는 것이다. Then, after the sandwich valve is shut off, the fluid induction box is removed, the
따라서 본발명은 관절단박스와 관연결박스를 설치하여 유체가 흐르는 관을 절단하여 유체를 유도함으로써, 관을 교체 또는 보수하는 작업중에도 유체의 단수가 없이 물을 원활하게 공급할 수 있으며, 또한 작업을 신속하고 간단하게 할 수 있는 현저한 효과가 있다. Therefore, the present invention installs a joint end box and a pipe connection box to induce fluid by cutting a pipe through which the fluid flows, so that water can be smoothly supplied without changing the water even during the replacement or maintenance of the pipe. There is a significant effect that can be done quickly and simply.
100 : 관절단박스 200 : 관연결박스
110 : 상부절단박스 130 : 하부박스
120 : 샌드위치밸브 121 : 밸브케이스
122 : 밸브판 140 : 절단톱
142 : 수직구동축
143 : 수직피동축 144 : 띠톱
145 : 철거관 승강봉
210 : 유체유도박스 230 : 막음판
231 : 실링 232 : 유도밸브
240 : 절단된 관(물을 공급받는 측)
310 : 차단장치 320: 차단판
330 : 맹판(맹플랜지, End Cap) 340 : 상부철판
341 : 결합편 350 : 하부철판100: joint end box 200: pipe connection box
110: upper cutting box 130: lower box
120: sandwich valve 121: valve case
122: valve plate 140: cutting saw
142 vertical drive shaft
143: vertical driven axis 144: band saw
145: demolition pipe lifting bar
210: fluid induction box 230: blocking plate
231: sealing 232: induction valve
240: cut pipe (side receiving water)
310: blocking device 320: blocking plate
330: blind plate (blind flange, end cap) 340: upper steel plate
341: coupling piece 350: lower steel plate
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020120039392A KR101180455B1 (en) | 2012-04-16 | 2012-04-16 | non cut off water supply method by non cut off water supply module equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020120039392A KR101180455B1 (en) | 2012-04-16 | 2012-04-16 | non cut off water supply method by non cut off water supply module equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101180455B1 true KR101180455B1 (en) | 2012-09-06 |
Family
ID=47073935
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020120039392A KR101180455B1 (en) | 2012-04-16 | 2012-04-16 | non cut off water supply method by non cut off water supply module equipment |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101180455B1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20160005996A (en) | 2014-07-08 | 2016-01-18 | 이세창 | Repair waste pipe connection structure using improved model method |
WO2020010403A1 (en) * | 2018-07-12 | 2020-01-16 | RBH Engineering Pty Ltd | Dewatering mobile track machine |
CN111633375A (en) * | 2020-06-05 | 2020-09-08 | 杭州临江环保热电有限公司 | Slurry supply pipe repairing device and repairing process thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11287385A (en) | 1998-02-06 | 1999-10-19 | Suiken Technology:Kk | Method and device for cutting existing pipe and valve inserting method with no water interruption |
JP2001187993A (en) | 1999-12-28 | 2001-07-10 | Suido Gijutsu Kaihatsu Kiko:Kk | Construction method for changing fluid transport route and fluid transport route changing device used therefor |
JP2005106082A (en) | 2003-09-26 | 2005-04-21 | Cosmo Koki Co Ltd | Installation method of gate valve in continuous water construction method |
KR100799480B1 (en) | 2002-12-02 | 2008-01-31 | 조희남 | Apparatus and method for repairing water pipe |
-
2012
- 2012-04-16 KR KR1020120039392A patent/KR101180455B1/en not_active IP Right Cessation
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11287385A (en) | 1998-02-06 | 1999-10-19 | Suiken Technology:Kk | Method and device for cutting existing pipe and valve inserting method with no water interruption |
JP2001187993A (en) | 1999-12-28 | 2001-07-10 | Suido Gijutsu Kaihatsu Kiko:Kk | Construction method for changing fluid transport route and fluid transport route changing device used therefor |
KR100799480B1 (en) | 2002-12-02 | 2008-01-31 | 조희남 | Apparatus and method for repairing water pipe |
JP2005106082A (en) | 2003-09-26 | 2005-04-21 | Cosmo Koki Co Ltd | Installation method of gate valve in continuous water construction method |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20160005996A (en) | 2014-07-08 | 2016-01-18 | 이세창 | Repair waste pipe connection structure using improved model method |
WO2020010403A1 (en) * | 2018-07-12 | 2020-01-16 | RBH Engineering Pty Ltd | Dewatering mobile track machine |
CN111633375A (en) * | 2020-06-05 | 2020-09-08 | 杭州临江环保热电有限公司 | Slurry supply pipe repairing device and repairing process thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107178675B (en) | Method and device for realizing replacement of pipe section or valve without stopping water on water supply pipeline | |
KR101180455B1 (en) | non cut off water supply method by non cut off water supply module equipment | |
WO2020228620A1 (en) | Flushing and overhauling system, flushing method and overhauling method for drainage pipeline | |
KR101026625B1 (en) | Water pipe rehabilitation and replacement method using line stopping system without water sevice disruption | |
KR101157080B1 (en) | Packer tilting apparatus and method for lateral lining(pal) | |
JP4938479B2 (en) | Gas shutoff method for gas piping | |
KR101199002B1 (en) | non cut off water supply module equipment | |
KR101515934B1 (en) | Apparatus for Softening and Keeping the Pipeline Repairing Reinforcement Tube and Non-Excavation Type Pipeline Reparing Method using the Same | |
KR101309333B1 (en) | Pipe changing method | |
KR101191394B1 (en) | A hot tapping stopping machine | |
KR101352658B1 (en) | Cutting saw structure of non cut off water supply module equipment | |
KR101137553B1 (en) | Manhole repairing method for preventing noise and dust | |
KR101419593B1 (en) | sealing plate structure of non cut off water supply module equipment | |
CN111810718B (en) | Method for repairing large-diameter sewage main pipe | |
KR100964629B1 (en) | line stopping apparatus for flow pipe | |
KR102157841B1 (en) | Damage replacement device and replacement method of the damaged pipe using the same | |
KR101068118B1 (en) | Check Valve Installed Between Branched Pipe and Main Pipe | |
CN212178239U (en) | Pipeline plugging device | |
JP4642521B2 (en) | Infinite water control body installation device for existing fluid pipes | |
JP4642522B2 (en) | Infinite water control body installation device for existing fluid pipes | |
CN213145754U (en) | Be used for prosthetic integration tube coupling location jacking device of major diameter sewage main pipe | |
JP2007032373A (en) | Structure of casing of horizontal shaft pump for pump gate, horizontal shaft pump for pump gate, and pump gate facility | |
KR100721968B1 (en) | Bypass type plugging apparatus for maintenance during working | |
KR200461774Y1 (en) | Installation apparatus of the window for checking the interior of fitting for stopping gas of flowing in gas pipe | |
KR101203967B1 (en) | Device for repairing valve |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20150917 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20160721 Year of fee payment: 5 |
|
LAPS | Lapse due to unpaid annual fee |