KR100773118B1 - A method of equipment for passage that use underdrain and stell pipe propulsion - Google Patents

A method of equipment for passage that use underdrain and stell pipe propulsion Download PDF

Info

Publication number
KR100773118B1
KR100773118B1 KR1020060104068A KR20060104068A KR100773118B1 KR 100773118 B1 KR100773118 B1 KR 100773118B1 KR 1020060104068 A KR1020060104068 A KR 1020060104068A KR 20060104068 A KR20060104068 A KR 20060104068A KR 100773118 B1 KR100773118 B1 KR 100773118B1
Authority
KR
South Korea
Prior art keywords
propulsion
culvert
base
steel pipe
soil
Prior art date
Application number
KR1020060104068A
Other languages
Korean (ko)
Inventor
황선영
김학건
Original Assignee
석정건설(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 석정건설(주) filed Critical 석정건설(주)
Priority to KR1020060104068A priority Critical patent/KR100773118B1/en
Application granted granted Critical
Publication of KR100773118B1 publication Critical patent/KR100773118B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A method for constructing a passage using steel pipe propulsion and underdrains is provided to remove soil of a construction interval gradually, and to install the underdrains accurately by propelling propulsion steel pipes along outer surfaces of the underdrains. A propulsion base(14) and an arrival base(15) are installed at two sides of starting and ending parts. A propulsion apparatus is installed at the propulsion base to propel propulsion steel pipes(30) with the shape of mounting a first underdrain. The first underdrain is mounted on the propulsion base and the arrival base, respectively. A first soil removed part is formed by removing the soil placed on an inner construction interval as much as the installation length of the first underdrain. The first underdrain is mounted on the first soil removed part and connected to a second underdrain. The soil in the second underdrain is removed to form a second soil removed part, and then the first underdrain is mounted on the second soil removed part.

Description

강관 추진과 암거를 이용한 통로용 시설공법{A method of equipment for passage that use underdrain and stell pipe propulsion}A method of equipment for passage that use underdrain and stell pipe propulsion

도 1a 는 본 발명의 공법구간을 나타낸 종단면도Figure 1a is a longitudinal sectional view showing a construction section of the present invention

도 1b 는 본 발명의 공법구간을 나타낸 평면도Figure 1b is a plan view showing a construction section of the present invention

도 2a 는 본 발명의 추진 암거에 대한 설치상태 정면도Figure 2a is a front view of the installation state for the propulsion culvert of the present invention

도 2b 는 본 발명의 추진 암거에 대한 내측 벽체에 대한 측면도2B is a side view of the inner wall of the propulsion culvert of the present invention;

도 2c 는 본 발명의 추진 암거에 대한 조립상태의 외측 벽체에 대한 측면도Figure 2c is a side view of the outer wall in the assembled state for the propulsion culvert of the present invention;

도 3a 는 본 발명의 추진기지 설치상태에 대한 평면도Figure 3a is a plan view of the propulsion base installation state of the present invention

도 3b 는 본 발명의 추진기지 설치상태에 대한 단면도Figure 3b is a cross-sectional view of the propulsion base installation state of the present invention

도 3c 는 본 발명의 가이드 레일과 추진장치의 설치상태 평면도Figure 3c is a plan view of the installation state of the guide rail and the propulsion device of the present invention

도 3d 는 본 발명의 추진강관에 대한 연결상태 요부 확대도Figure 3d is an enlarged view of the main connection state of the propulsion steel pipe of the present invention

도 4a 는 본 발명의 추진 강관에 대한 실시예를 나타낸 정면도Figure 4a is a front view showing an embodiment of the propulsion steel pipe of the present invention

도 4b 는 본 발명의 추진 강관에 대한 실시예를 나타낸 측면도Figure 4b is a side view showing an embodiment of the propulsion steel pipe of the present invention

도 4c 는 본 발명의 추진 강관에 대한 다른 실시예를 나타낸 정면도4C is a front view showing another embodiment of the propulsion steel pipe of the present invention.

도 5a 는 본 발명의 추진기지와 도달기지를 완성하여 암거를 설치한 상태의 단면도Figure 5a is a cross-sectional view of the culvert installed by completing the propulsion base and the arrival base of the present invention

도 5b 는 본 발명의 추진기지에 추진장비를 설치한 상태의 단면도Figure 5b is a cross-sectional view of the propulsion equipment installed on the propulsion base of the present invention

도 5c 는 본 발명의 추진강관을 추진하는 상태의 단면도Figure 5c is a cross-sectional view of the state pushing the propulsion steel pipe of the present invention

도 5d 는 본 발명의 암거 내부의 흙을 제거한 상태의 면도Figure 5d is a shaving with the soil removed inside the culvert of the present invention

도 5e 는 본 발명의 암거 내부에 새로운 암거를 설치한 상태의 단면도Figure 5e is a cross-sectional view of a state installed a new culvert inside the culvert of the present invention

도 5f 는 본 발명의 암거 내부의 흙을 제거한 상태의 단면도Figure 5f is a cross-sectional view of removing the soil inside the culvert of the present invention

도 5g 는 본 발명의 추진강관의 내부에 암거를 설치하는 상태의 단면도Figure 5g is a cross-sectional view of the installation of the culvert in the interior of the propulsion steel pipe of the present invention.

도 5h 는 본 발명의 추진강관 내부에 암거를 설치한 상태의 단면도Figure 5h is a cross-sectional view of the culvert installed inside the propulsion steel pipe of the present invention.

도 5i 는 본 발명의 암거가 모두 연결된 상태를 나타낸 단면도Figure 5i is a cross-sectional view showing a state in which all the culverts of the present invention are connected

도 6a 는 본 발명의 추진기지와 도달기지를 완성하여 암거를 설치한 상태의 단면도Figure 6a is a cross-sectional view of the culvert installed by completing the propulsion base and the arrival base of the present invention;

도 6b 는 본 발명의 추진기지에 추진장비를 설치한 상태의 단면도Figure 6b is a cross-sectional view of the propulsion equipment installed on the propulsion base of the present invention.

도 6c 는 본 발명의 추진강관을 추진하는 상태의 단면도Figure 6c is a cross-sectional view of the state pushing a steel pipe of the present invention

도 6d 는 본 발명의 추진강관을 추진한 상태의 단면도Figure 6d is a cross-sectional view of the propulsion steel pipe of the present invention

도 6e 는 본 발명의 암거 내부의 흙을 제거한 상태의 면도Figure 6e is a shaving in a state of removing the soil inside the culvert of the present invention

도 6f 는 본 발명의 암거 내부에 새로운 암거를 설치한 상태의 단면도Figure 6f is a cross-sectional view of a new culvert installed inside the culvert of the present invention

도 6g 는 본 발명의 암거 내부의 흙을 제거한 상태의 단면도Figure 6g is a cross-sectional view of removing the soil inside the culvert of the present invention

도 6h 는 본 발명의 추진강관의 내부에 암거를 설치하는 상태의 단면도Figure 6h is a cross-sectional view of the installation of the culvert inside the propulsion steel pipe of the present invention.

도 6i 는 본 발명의 암거가 모두 연결된 상태를 나타낸 단면도Figure 6i is a cross-sectional view showing a state in which all the culverts of the present invention are connected

[도면의 주요 부분에 대한 부호의 설명][Description of Symbols for Main Parts of Drawing]

10 : 레일 11 : 공법구간10: rail 11: construction method section

12 : 옹벽구간 13, 13' : 기존도로12: Retaining wall section 13, 13 ': Existing road

14 : 추진기지 15 : 도달기지14: propulsion base 15: reach base

20, 20' : 암거 21 : 내측 벽체20, 20 ': Culvert 21: inner wall

22 : 외측 벽체 30 : 추진 강관22: outer wall 30: propulsion steel pipe

31 : 연결홈 32 : 연결돌기 31: connecting groove 32: connecting projection

33 : 흙 제거부 34 : 가지붕33: soil removal portion 34: eggplant roof

60 : 추진 장비 60: propulsion equipment

본 발명은 강관 추진과 암거를 이용한 통로용 시설공법에 관한 것으로서, 더욱 상세하게는 추진기지와 도달기지에 암거를 설치하고 이 암거를 기준으로 외측을 따라서 추진 강관을 서로 연결되도록 한 상태에서 공법구간의 흙을 제거하여 암거를 설치하는 과정으로 시공 가능한 강관 추진과 암거를 이용한 시설공법에 관한 것이다.The present invention relates to a facility construction method for the passage using steel pipe propulsion and culvert, and more specifically, to install a culvert at the propulsion base and the reach base, and the construction method in the state that the propulsion steel pipes are connected to each other along the outside based on the culvert The process of installing a culvert by removing dirt from the ground relates to the construction of steel pipe propulsion and facility construction using culverts.

일반적으로, 지중에 구조물을 축조하는 방식으로 개착 및 비개착에 의한 구조물 축조방식이 있다.In general, there is a structure construction method by the attachment and non-attachment in a way to build the structure in the ground.

기존 도로 및 철도 하부를 횡단해서 하수 암거나 지하차도 터널구조물 등을 설치해야 하는 경우 공사에 따른 걸림돌의 이전이 곤란하거나, 걸림돌 저촉, 차량 소통 장애 등으로 개착이 불가능하여 비개착공법이 요구되는바, 비개착에 의한 구조물 축조 공법에는 횡단하는 도로나 걸림돌의 양측으로 작업구 개념의 전진기지와 도달기지가 필수적이며, 대표적인 비개착식 지중구조물 축조공법으로는 함체견인공법과 강관 루프공법 등을 들 수 있다.When it is necessary to install sewage rock or underground tunnel structures across existing roads and railroads, it is difficult to transfer obstacles due to construction, or it is impossible to fix them due to obstacles or obstacles in vehicle communication. For the construction of the structure by non-adherence, forward and reach bases of the concept of work tools are essential to both sides of the crossing road and stumbling blocks. Can be.

함체 견인공법은 함체가 통과할 지중에 미리 소정의 크기를 갖는 함체지지용 가설용 강관을 전진기지에서 도달기지 방향으로 수평 되게 압입 통과시킨 후 견인할 함체의 반대 측 도달기지로부터 지중을 횡단하여 이어진 다수의 PC 강선을 현장에서 제작된 함체와 결속한 후, 견인하여 함체내의 내부토사를 제거하고, 이와 같은 견인과 출착작업을 반복하여 지중에 구조물을 설치하는 공법이다.The towing method of the enclosure is to press-through a steel pipe for supporting the housing, which has a predetermined size, in the horizontal direction from the forward base to the reach base, and then traverse the ground from the reach base on the opposite side of the enclosure to be towed. After binding a large number of PC steel wires to a manufactured enclosure on the site, it is towed to remove internal soil in the enclosure and to repeat the towing and landing operations.

그러나 이러한 공법은 함체 추진시 함체의 추진하중이나 추진함체와 이미 지중에 설치된 가설강관과의 통메 의해 함체 상부의 도로나 걸림돌에 침하가 발생할 우려가 있으며, 함체가 미리 제작되어 견인 설치되므로 함체의 규모가 커지게 되면 견인에 제악이 따르게 되고 작업장의 규모가 큰 편이므로 심도가 깊은 지하공간에서의 작업이 어려운 문제점이 있었다.However, this method may cause settlement of the road or obstacles on the upper part of the upper part of the hull due to the propulsion load of the hull or when the propulsion hull and the temporary steel pipe installed in the ground are already in the ground. The larger the size, the greater the traction and the greater the size of the workplace.

그리고 함체간의 연결부의 처리가 미흡하게 되면 누수가 발생할 염려가 있으므로 함체 견인공법의 단점 등에 의하여 미개착식 지중구조물 축조공법으로는 강관루프공법이 많이 적용되고 있는 실정이다.In addition, if the connection between the enclosures is insufficient, there is a risk of water leakage, and the steel pipe loop method is widely applied as an unattached underground structure construction method due to the drawbacks of the towing method.

종래의 강관루프공법은 구조물이 형성된 지중에 미리 강관을 순차적으로 압 입, 연결하여 강관 루프를 형성하고 강관 루프 안쪽의 내부 토사를 전부 제거하고 구조물을 축조하게 되며 굴착시 발생하는 강관 상부나 측면하중은 횡방향 지지보 및 가설기둥 등의 가설재로 지지한다.In the conventional steel pipe loop method, steel pipe loops are sequentially pressed and connected to the ground in which the structure is formed to form a steel pipe loop, to remove all the internal soil inside the steel pipe loop, and to build the structure. Is supported by temporary materials such as lateral support beams and temporary columns.

강관루프의 축조과정은, 전진기지에서 조성할 구체의 크기를 고려하여 구체 외측면에 가설용 강관을 수평 삽입하고 강관 내에 콘크리트를 타설하여 강관 루프를 형성한다.In the construction process of the steel pipe loop, the steel pipe loop is formed by horizontally inserting the temporary steel pipe into the outer surface of the sphere in consideration of the size of the sphere to be constructed in the forward base and placing concrete in the steel pipe.

전진기지로부터 구조물이 축조될 강관루프의 안쪽을 굴착하게 되는데 굴착은 상부하중과 측압에 대한 안전성을 고려하여 강관루프의 상측 부위로부터 하측 방향으로 단계별로 이루어진다.From the forward base, the inside of the steel pipe loop to be constructed is excavated. The excavation is performed step by step from the upper part of the steel pipe loop to the lower side in consideration of the safety of the upper load and the side pressure.

여기서 굴착은 1차 강관 루프 하면을 3m 내외의 심도로 굴착하게 되며, 강관루프에 사용된 강관은 단순한 고리 형태로 연결되어 있으므로 강관루프 하면과 측면에 강관과 직각방향으로 H형 강재로 횡방향 지지보를 설치하고 다수의 가설 기둥으로 받쳐 전 구간에 걸쳐 하중을 지지시켜야 하는 것이다.Here, the excavation is to excavate the bottom of the primary steel pipe loop with a depth of about 3m, and the steel pipes used in the steel pipe loops are connected in a simple loop shape, so they are supported horizontally with the H-shaped steel in the direction perpendicular to the steel pipes on the bottom and side of the steel pipe loops. The beams must be installed and supported by a number of temporary columns to support the load over the entire section.

결국, 기존의 강관루프는 강관 측면 중앙부에 한 쌍의 ㄱ 자형 고리와 T 자형 걸쇠가 단부에 부착된 요철의 연결구조로 삽입된 강관들을 상호 고리형태로 연결하여 시공하는 것이며, 이후 2차, 3차로 굴진하면서 이미 설치된 가설기둥을 설치 심도까지 하향으로 연장 설치해야 하는 문제점으로 인해 시공 중 침하의 우려가 크고, 기존에 설치한 가설재와의 저촉 문제로 공기가 늦춰지는 결점이 있었다.As a result, the existing steel pipe loop is constructed by connecting the steel pipes inserted into the connection structure of the concave-convex structure in which a pair of a-shaped ring and a T-shaped clasp are attached to the end in the center of the steel pipe in the form of a mutual ring, and then the secondary, 3 Due to the problem of extending the installation pillars downward to the installation depth while digging in the car, there is a high possibility of subsidence during construction, and there is a defect that the air is delayed due to a problem with the existing installation materials.

이러한 문제점의 발생을 해소하기 위하여 강관루프를 이용한 지중 축조물 공사시에 지중 축조물 공사의 규모나 심도에 구애받지 않고 별도의 횡방향 지지보의 설치 없이 가설 기둥만 설치하는 시공하는 것이 가능한 강관루프 구조체가 제안되었다.In order to solve this problem, a steel pipe loop structure that can be installed by installing only temporary columns without installing a transverse support beam regardless of the scale or depth of underground construction works when constructing underground structures using steel pipe loops Proposed.

그러나 강관루프 구조체 내부에 상 하부 슬래브 및 벽체부를 두고 있으나, 하중을 견디기 위하여 횡방향 지지보가 없다.However, the upper and lower slab and the wall portion inside the steel pipe roof structure, but there is no transverse support beam to withstand the load.

이러한 강관루프 구조체의 내부에 슬래브와 벽체부를 갖는 중량물인 암거를 강제로 추진하게 되므로 추진이 어렵거나 마찰력이 크게 발생하여 추진이 거의 불가능한 결점이 있었다.Since the culvert, which is a heavy material having a slab and a wall portion inside the steel pipe loop structure, is forcibly pushed, the propulsion is difficult or the friction force is largely generated, which makes the propulsion almost impossible.

본 발명은 이러한 종래의 결점을 해소하기 위하여 안출된 것으로, 추진기지와 도달기지에 암거를 성형한 후 이 암거의 외측 면을 따라서 추진 강관을 추진하여 서로 연결시켜 일체형을 이루도록 하여 추진 강관이 정렬된 상태에서 암거의 사이에 있는 공법구간의 흙을 암거가 설치될 구간만큼 제거해 나가면서 암거를 설치하는 방법으로 설치함을 목적으로 한다.The present invention has been made in order to solve the above-mentioned drawbacks, and after forming a culvert on the propulsion base and the reach base, the propulsion steel pipe is aligned by pushing the propulsion steel pipes along the outer surface of the culvert to connect with each other to form an integral. The purpose of the installation is to install the culvert while removing the soil of the construction area between the culverts as much as the section where the culvert will be installed.

본 발명은 추진기지와 도달기지에 추진 강관을 추진한 후 추진기지와 도달기지에 암거를 설치하고 암거의 사이에 있는 공법구간의 흙을 암거가 설치될 구간만큼 제거해 나가면서 암거를 설치하는 방법으로 설치함을 목적으로 한다.The present invention is to install a culvert while pushing the propulsion steel pipe to the propulsion base and the reach base, install the culvert in the propulsion base and the reach base and remove the soil of the construction area between the culvert as much as the culvert will be installed. It is intended for installation.

이러한 목적으로 이루어진 본 발명의 실시예를 첨부시킨 도면에 따라서 상세 하게 설명하기로 한다.Embodiments of the present invention made for this purpose will be described in detail with reference to the accompanying drawings.

도 1a는 본 발명의 공법구간을 나타낸 종단면도로, 도로나 레일(10)이 설치된 철도 등 공법구간(11)의 양측으로 옹벽구간(12)을 갖는 것이며, 본 발명의 바람직한 실시예를 나타내기 위하여 레일(10)이 설치된 철도의 양측으로 기존도로(13, 13')가 설치된 곳에 도 1b와 같이 적용한 것이다.Figure 1a is a longitudinal cross-sectional view showing a construction section of the present invention, having a retaining wall section 12 on both sides of the construction section 11, such as a road or railroad with a rail 10 is installed, to show a preferred embodiment of the present invention Where the rails 10 are installed on both sides of the existing road (13, 13 ') is installed as shown in Figure 1b.

본 발명의 암거(20)는 필요에 따라서 단일 통로 또는 복수의 통로를 갖도록 성형할 수 있으며, 복수의 통로를 갖는 경우에는 내측 벽체(21)를 두고 외측 벽체(22)는 공법구간(11)의 폭에 따라서 연속해서 연결하면서 마감하여 누수가 발생하지 않도록 하는 것이다.The culvert 20 of the present invention can be molded to have a single passage or a plurality of passages as necessary, and in the case of having a plurality of passages, the inner wall 21 is provided and the outer wall 22 is formed of the construction section 11. It connects according to the width and finishes to prevent leakage.

상기 암거(20)는 거푸집에서 성형할 때 그대로 콘크리트를 타설하거나, 거푸집의 내벽에 미리 스테인레스(24)를 설치하여 외측면을 감싸도록 하였다.The culvert 20 is to cast concrete as it is molded in the form, or to install the stainless steel 24 on the inner wall of the form in advance to surround the outer surface.

스테인레스(24)는 각 암거(20, 20')가 만나는 부분에서 용접이 이루어져 누수가 방지되도록 하였으며, 스테인레스(24)는 에폭시를 이용하여 암거(20, 20')의 상면 및 측면과 하면에서 접착이 이루어지도록 하는 것이다.The stainless steel 24 is welded at the parts where the culverts 20 and 20 'meet to prevent leakage, and the stainless steel 24 is bonded to the top, side, and bottom surfaces of the culverts 20 and 20' using epoxy. To make this happen.

추진기지(14)는 추진 강관(30)이 추진될 위치를 제외하고 토류벽(16)으로 감싸지도록 성형하며, 외측으로 H 파일(17)을 박아 고정하는 동시에 다양한 각도로 와이어를 박아 고정이 이루어지도록 하였다.The propulsion base 14 is shaped to be wrapped with the earth wall 16 except for the position where the propulsion steel pipe 30 is to be propelled, and the H pile 17 is driven and fixed to the outside to drive the wire at various angles. It was.

추진 강관(30)은 도 3d에 도시한 바와 같이, 소정의 길이로 사용하는 것이며, T 자 형으로 돌출된 연결돌기(32)와 이 연결돌기(32)를 수용하는 연결홈(31)이 반대편에 연결되어 있어서 연속해서 요철형으로 결합이 이루어지는 것이다.The propulsion steel pipe 30 is to be used in a predetermined length, as shown in Figure 3d, the connecting projection 32 protruding in the T-shape and the connecting groove 31 for receiving the connecting projection 32 is the opposite side It is connected to the concave and convex shape is made continuously.

추진기지(14)에는 추진장비(60)를 설치하여 추진 강관(30)을 추진하는 것이며, 추진 강관(30)의 전방에는 굴진기(61)를 연결하여 추진이 용이하도록 하였다.The propulsion base 14 is to promote the propulsion steel pipe 30 by installing the propulsion equipment 60, the front of the propulsion steel pipe 30 was connected to the excavator 61 to facilitate the propulsion.

이러한 구성으로 이루어진 본 발명의 추진 공법에 따라서 상세하게 설명하기로 한다.According to the propulsion method of the present invention having such a configuration will be described in detail.

도 5a에 도시한 바와 같이, 도로 또는 레일(10)이 설치된 철도의 공법구간(11) 양측의 옹벽구간(12) 중 어느 한 부분을 추진기지(14)로 만들고 다른 부분을 도달기지(15)로 만든다.As shown in FIG. 5A, one portion of the retaining wall section 12 on both sides of the construction section 11 of the road or rail 10 on which the road or the rail 10 is installed is used as the propulsion base 14 and the other part is the reaching base 15. Make it.

상기 추진기지(14)는 3면이 토류벽(16)을 막아 설치하는 설치며, H 파일(17)을 박고 내부로 와이어를 연결하여 토압에 무너지지 않도록 하였다.The propulsion base 14 is an installation in which three surfaces are installed by blocking the earth wall 16, and the H pile 17 is inserted to connect the wire to the inside so as not to collapse in the earth pressure.

상기 추진기지(14)와 도달기지(15)는 시, 종점부에 설치하며, 추진기지(14)의 규격은 암거(20)의 제작 가능하도록 설치하여야 한다.The propulsion base 14 and the reaching base 15 are installed at the end of the city, the standard of the propulsion base 14 should be installed to enable the manufacture of the culvert 20.

도 5b에 도시한 바와 같이, 추진기지(14)의 벽면에 추진장비(60)를 설치하고 그 전방에 추진 강관(30)을 설치하여 상면과 양측 면 및 하측 면 등 필요한 방향에 추진 강관(30)을 추진하는 것이다.As shown in FIG. 5B, the propulsion equipment 60 is installed on the wall of the propulsion base 14, and the propulsion steel pipe 30 is installed in front of the propulsion base 14 so that the propulsion steel pipe 30 is disposed in the required direction such as an upper surface, both sides, and a lower surface. ) Is to promote.

상기 추진 강관(30)은 도 4a에 도시한 바와 같이 지반이 약한 경우에는 암거(20)의 사면에 모두 위치하도록 설치하는 것이 가능하며, 도 4c에 도시한 바와 같이 지반이 강한 경우에는 암거(20)의 바닥면을 제외한 나머지 삼면에 위치하도록 설치한다.The propulsion steel pipe 30 can be installed so as to be located on all four sides of the culvert 20 when the ground is weak, as shown in Figure 4a, if the ground is strong, as shown in Figure 4c Install on three sides except the bottom.

도 5c에 도시한 바와 같이, 추진기지(14) 내에 설치한 추진장비(60)를 제거하고 추진 강관(30)이 양측으로 돌출된 부분에 거푸집을 설치한 후 도 5d에 도시한 바와 같이 추진 강관(30)의 내부에 암거(20)를 설치한다.As shown in FIG. 5C, after removing the propulsion equipment 60 installed in the propulsion base 14 and installing the formwork at a portion where the propulsion steel pipe 30 protrudes to both sides, the propulsion steel pipe as shown in FIG. 5D. The culvert 20 is installed in the inside of 30.

암거(20)를 설치하면 추진 강관(30)은 암거(20)의 외측에서 지지가 되며 가해지는 외력(하중)을 견디게 된다.When the culvert 20 is installed, the propulsion steel pipe 30 is supported at the outside of the culvert 20 and withstands an external force (load) applied thereto.

암거(20)의 설치가 완료되면 도 5e에 도시한 바와 같이 암거(20)의 내부에 흙을 일부 제거하는 흙 제거부(33)를 통하여 새로운 암거(20')를 설치할 폭을 만들고 이 흙 제거부(33)에 거푸집을 설치하여 도 5f에 도시한 바와 같이 새로운 암거(20')를 설치한다.When the installation of the culvert 20 is completed, as shown in FIG. 5E, a width to install a new culvert 20 ′ is made through the soil removing part 33 which removes part of the soil in the interior of the culvert 20. Formwork is installed in the reject 33 to install a new culvert 20 'as shown in FIG. 5F.

이때, 필요한 경우 가지붕(34)을 할 수 있으며, 외력이 강하지 않은 경우에는 하지 않을 수 있다.At this time, if necessary, the branch roof 34 may be used, and may not be performed when the external force is not strong.

암거(20')의 양생이 종료되면 도 5g에 도시한 바와 같이 암거(20')의 내부에 있는 흙을 제거하는 과정을 통하여 흙을 모두 제거한 후 흙 제거부(33')에 거푸집을 설치하여 도 5h에 도시한 바와 같이 암거를 설치함으로써 공법구간(11) 전체면을 연결하는 암거(20)를 도 5i와 같이 설치하는 것이다.When curing of the culvert 20 'is finished, as shown in FIG. 5G, all the soil is removed through the process of removing the soil inside the culvert 20', and then the formwork is installed in the soil removing part 33 '. As shown in FIG. 5H, the culvert 20 connecting the entire surface of the construction method section 11 is installed as shown in FIG. 5I by installing the culvert.

여기서 암거(20, 20')는 공법구간(11)이 긴 경우 거푸집을 더 여러 번 설치하는 것과 같이 공법구간(11)의 길이에 따라서 자유롭게 행해지는 것이다.Here, the culverts 20 and 20 'are freely made according to the length of the construction section 11, such as installing the formwork several times when the construction section 11 is long.

이와 같은 방법으로 암거(20, 20')를 연속해서 성형하여 공법구간(11)을 연결하는 것이며, 연결이 종료되면 추진 강관(30)의 내부를 콘크리트로 그라우팅한다.In this way, the culverts 20 and 20 'are continuously formed to connect the construction section 11, and when the connection is completed, grout the inside of the propulsion steel pipe 30 with concrete.

그리고 추진기지(14)와 도달기지(15)를 철거하고, 암거(20)와 추진 강관(30)의 양측에서 시, 종점부에 옹벽구간(12)을 옹벽처리하고 난간벽 및 포장공사, 부대공사를 마무리한다.Then, the propulsion base 14 and the reaching base 15 are dismantled, and the retaining wall section 12 is retained at the end of the city and the end at both sides of the culvert 20 and the propulsion steel pipe 30, and handrail walls, pavement works, and additional work are performed. To finish.

공법구간(11)에는 추진 암거(20)가 위치하게 되고, 옹벽구간(12)에는 접속 옹벽이 설치되어 기존도로(13, 13')와 연결작업이 종료되는 것이다.Propulsion culvert 20 is located in the construction method section 11, the connecting retaining wall is installed in the retaining wall section 12 is the existing work (13, 13 ') and the connection is completed.

이하에서는 본 발명의 다른 실시예를 공법에 따라서 상세하게 설명하기로 한다.Hereinafter, another embodiment of the present invention will be described in detail according to the construction method.

도로 또는 레일(10)이 설치된 철도의 공법구간(11) 양측의 옹벽구간(12) 중 어느 한 부분을 도 6a에 도시한 바와 같이, 추진기지(14)로 만들고 다른 부분을 도달기지(15)로 만든다.As shown in FIG. 6A, one portion of the retaining wall section 12 on both sides of the construction section 11 of the road or rail 10 on which the road or rail 10 is installed is formed as a propulsion base 14 and the other part reaches the base 15. Make it.

상기 추진기지(14)는 3면이 토류벽(16)을 막아 설치하는 설치며, H 파일(17)을 박고 내부로 와이어를 연결하여 토압에 무너지지 않도록 하였다.The propulsion base 14 is an installation in which three surfaces are installed by blocking the earth wall 16, and the H pile 17 is inserted to connect the wire to the inside so as not to collapse in the earth pressure.

상기 추진기지(14)와 도달기지(15)는 시, 종점부에 설치하며, 추진기지(14)의 규격은 암거(20)의 제작 가능하도록 설치하여야 한다.The propulsion base 14 and the reaching base 15 are installed at the end of the city, the standard of the propulsion base 14 should be installed to enable the manufacture of the culvert 20.

도 6b에 도시한 바와 같이, 추진기지(14)의 벽면에 추진장비(60)를 설치하고 추진기지(14)와 도달기지(15)에 각각 거푸집을 설치하여 암거(20)를 설치한다.As shown in FIG. 6B, the propulsion equipment 60 is installed on the wall of the propulsion base 14, and the culvert 20 is installed by installing the formwork at the propulsion base 14 and the reaching base 15, respectively.

도 6c에 도시한 바와 같이, 암거(20)의 외측면을 따라서 추진기지(14)와 도달기지(15)가 연결되도록 추진 강관(30)을 설치하여 상면과 양측 면 및 하측 면 등 필요한 방향에 추진 강관(30)을 추진하는 것이다.As shown in FIG. 6C, the propulsion steel pipe 30 is installed to connect the propulsion base 14 and the reaching base 15 along the outer surface of the culvert 20 to the required direction such as the upper surface, both sides, and the lower surface. It is to propel the propulsion steel pipe (30).

상기 추진 강관(30)은 도 4a에 도시한 바와 같이 지반이 약한 경우에는 암거(20)의 사면에 모두 위치하도록 설치하는 것이 가능하며, 도 4c에 도시한 바와 같이 지반이 강한 경우에는 암거(20)의 바닥면을 제외한 나머지 삼면에 위치하도록 설치한다.The propulsion steel pipe 30 can be installed so as to be located on all four sides of the culvert 20 when the ground is weak, as shown in Figure 4a, if the ground is strong, as shown in Figure 4c Install on three sides except the bottom.

도 6d에 도시한 바와 같이, 추진기지(14) 내에 설치한 추진장비(60)를 제거하고, 설치한 암거(20)는 외측에서 추진 강관(30)을 지지하며 가해지는 외력(하중)을 견디게 된다.As shown in FIG. 6D, the propulsion equipment 60 installed in the propulsion base 14 is removed, and the installed culvert 20 supports the propulsion steel pipe 30 from the outside to withstand the external force (load) applied. do.

도 6e에 도시한 바와 같이, 암거(20)의 내부에 흙을 일부 제거하여 흙 제거부(33)를 만들고 이 흙 제거부(33)에 거푸집을 설치하여 새로운 암거(20')를 설치할 폭을 만들고 도 6f에 도시한 바와 같이 새로운 암거(20')를 설치한다.As shown in Figure 6e, by removing some of the soil in the interior of the culvert 20 to create a soil removing portion 33 and by installing a formwork on the soil removing portion 33 to install a new culvert 20 ' And install a new culvert 20 'as shown in FIG. 6F.

이때, 필요한 경우 가지붕(34)을 할 수 있으며, 외력이 강하지 않은 경우에는 하지 않을 수 있다.At this time, if necessary, the branch roof 34 may be used, and may not be performed when the external force is not strong.

암거(20')의 양생이 종료되면 도 6g에 도시한 바와 같이 암거(20')의 내부에 있는 흙을 제거하는 과정을 통하여 흙을 모두 제거한 후 흙 제거부(33')에 거푸집을 설치하여 도 6h에 도시한 바와 같이 암거를 설치함으로써 공법구간(11) 전체면을 연결하는 암거(20)를 도 6i와 같이 설치하는 것이다.When curing of the culvert 20 'is finished, all the soil is removed through the process of removing the soil in the interior of the culvert 20' as shown in FIG. 6G, and then the mold is installed in the soil removing part 33 '. By installing a culvert as shown in FIG. 6H, the culvert 20 which connects the whole surface of the process section 11 is installed like FIG. 6I.

여기서 암거(20, 20')는 공법구간(11)이 긴 경우 거푸집을 더 여러 번 설치하는 것과 같이 공법구간(11)의 길이에 따라서 자유롭게 행해지는 것이다.Here, the culverts 20 and 20 'are freely made according to the length of the construction section 11, such as installing the formwork several times when the construction section 11 is long.

이와 같은 방법으로 암거(20, 20')를 연속해서 성형하여 공법구간(11)을 연 결하는 것이며, 연결이 종료되면 추진 강관(30)의 내부를 콘크리트로 그라우팅한다.In this way, the culverts 20 and 20 'are continuously molded to connect the construction section 11, and when the connection is completed, grout the interior of the propulsion steel pipe 30 with concrete.

그리고 추진기지(14)와 도달기지(15)를 철거하고, 암거(20)와 추진 강관(30)의 양측에서 시, 종점부에 옹벽구간(12)을 옹벽처리하고 난간벽 및 포장공사, 부대공사를 마무리한다.Then, the propulsion base 14 and the reaching base 15 are dismantled, and the retaining wall section 12 is retained at the end of the city and the end at both sides of the culvert 20 and the propulsion steel pipe 30, and handrail walls, pavement works, and additional work are performed. To finish.

공법구간(11)에는 추진 암거(20)가 위치하게 되고, 옹벽구간(12)에는 접속 옹벽이 설치되어 기존도로(13, 13')와 연결작업이 종료되는 것이다.Propulsion culvert 20 is located in the construction method section 11, the connecting retaining wall is installed in the retaining wall section 12 is the existing work (13, 13 ') and the connection is completed.

본 발명은 추진기지와 도달기지에 암거를 성형한 후 이 암거의 외측 면을 따라서 추진 강관을 추진하여 서로 연결시켜 일체형을 이루도록 하여 추진 강관이 정렬된 상태에서 암거의 사이에 있는 공법구간의 흙을 암거가 설치될 구간만큼 제거해 나가면서 암거를 설치해 나가는 방법으로 암거를 설치함으로써 신속하고 정확하게 암거의 설치작업을 수행할 수 있도록 하는 것이다.The present invention is to form a culvert on the propulsion base and the reach base and then push the propulsion steel pipes along the outer surface of the culvert to connect with each other to form an integrated structure so that the soil between the construction section between the culverts in the state of the propulsion steel pipes aligned. The culvert is installed in such a way as to install the culvert while removing the culvert as much as the section to be installed so that the culvert can be installed quickly and accurately.

본 발명은 추진기지와 도달기지에 추진 강관을 추진한 후 추진기지와 도달기지에 암거를 설치하고 암거의 사이에 있는 공법구간의 흙을 암거가 설치될 구간만큼 제거해 나가면서 암거를 설치해 나가는 방법으로 암거를 설치함으로써 신속하고 정확하게 암거의 설치작업을 수행할 수 있도록 하는 것이다.The present invention is to install a culvert while pushing the propulsion steel pipe to the propulsion base and the reach base, install the culvert in the propulsion base and the reach base, and remove the soil of the process area between the culvert as much as the culvert will be installed. By installing the culvert, the culvert can be installed quickly and accurately.

Claims (2)

횡단하려는 시, 종점부의 양측에 추진기지(14)와 도달기지(15)를 설치하고 공법구간에 강관을 추진하며 그 내부에 암거를 설치하는 공법에 있어서,In the construction method to install the propulsion base (14) and the reaching base (15) on both sides of the end portion to traverse, and to promote the steel pipe in the construction method section, the culvert is installed inside 상기 추진기지(14)에 추진장비(60)를 설치하여 추진기지(14)와 도달기지(15)에 공법구간(11)을 관통하는 추진 강관(30)이 암거(20)를 설치할 형태로 추진하는 단계;The propulsion steel tube 30 penetrating the construction method section 11 to the propulsion base 14 and the reaching base 15 by installing the propulsion equipment 60 in the propulsion base 14 is propelled in the form of installing the culvert 20. Doing; 상기 추진 강관(30)의 내부에서 추진기지(14)와 도달기지(15)에 각각 암거(20)를 설치하는 단계;Installing culverts 20 in the propulsion base 14 and the reaching base 15 in the propulsion steel pipe 30; 상기 암거(20)의 양측에서 내부 공법구간(11)에 있는 흙을 암거(20')를 설치할 간격만큼 제거하여 흙 제거부(33)를 만드는 단계;Making dirt removal unit 33 by removing dirt in the internal construction section 11 from both sides of the culvert 20 by an interval for installing the culvert 20 '; 상기 흙 제거부(33)에 암거(20')를 설치하여 암거(20)와 연결하는 단계;Installing a culvert 20 'at the soil removing part 33 to connect with the culvert 20; 상기 암거(20')의 내부에 있는 흙을 제거하여 흙 제거부(33')를 만드는 단계;Removing soil in the culvert 20 'to make a soil remover 33'; 상기 흙 제거부(33')에 암거(20)를 설치하여 공법구간(11)이 암거(20, 20')로 관통되도록 하는 단계를 포함하여 이루어짐을 특징으로 하는 강관 추진과 암거를 이용한 통로용 시설공법.Installing the culvert 20 in the soil removal unit 33 'for the passage using a steel pipe propulsion and culvert, characterized in that it comprises the step of penetrating the construction section 11 through the culvert (20, 20') Facility construction method. (삭제)(delete)
KR1020060104068A 2006-10-25 2006-10-25 A method of equipment for passage that use underdrain and stell pipe propulsion KR100773118B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060104068A KR100773118B1 (en) 2006-10-25 2006-10-25 A method of equipment for passage that use underdrain and stell pipe propulsion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060104068A KR100773118B1 (en) 2006-10-25 2006-10-25 A method of equipment for passage that use underdrain and stell pipe propulsion

Publications (1)

Publication Number Publication Date
KR100773118B1 true KR100773118B1 (en) 2007-11-02

Family

ID=39060741

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060104068A KR100773118B1 (en) 2006-10-25 2006-10-25 A method of equipment for passage that use underdrain and stell pipe propulsion

Country Status (1)

Country Link
KR (1) KR100773118B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100515689B1 (en) 2005-03-09 2005-09-16 석정건설(주) Construction establishment method and the structure that use small size steel pipe propulsion
KR100538272B1 (en) 2005-05-10 2005-12-21 건양씨엔이 (주) The methods of trenchless underway construction using pre-cast assembly concrete box

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100515689B1 (en) 2005-03-09 2005-09-16 석정건설(주) Construction establishment method and the structure that use small size steel pipe propulsion
KR100538272B1 (en) 2005-05-10 2005-12-21 건양씨엔이 (주) The methods of trenchless underway construction using pre-cast assembly concrete box

Similar Documents

Publication Publication Date Title
KR101161332B1 (en) Construction method of the underground tunnel
KR101388521B1 (en) Construction method of underground structure under the pier with supporting piles
KR101288601B1 (en) Underpass using precast concrete pile and bottom slab and method for constructing the same
JP4881555B2 (en) Construction method of underground structure
KR100712593B1 (en) Construction method of pipe roof structures
KR100562158B1 (en) Steel pipe roof construction method for building underground structure, roof structure therefor, and structure of steel pipe therefor
KR100825074B1 (en) Pipe roof structures and construction method of piperoof structures
KR20060097891A (en) Pipe roof structures and construction method of pipe roof structures
KR100784201B1 (en) Method for construction of tunnel
KR102134603B1 (en) Apparatus and method for constructing non-open cut structure
KR100773118B1 (en) A method of equipment for passage that use underdrain and stell pipe propulsion
KR100667170B1 (en) Underdrain structure for passage using pipe roller pushing method and that equipment method
KR200385542Y1 (en) Pipe roof structures
CN108729469B (en) Construction method of underground structure
KR100928566B1 (en) Roof assembly and constructing method thereof
KR20100035016A (en) Pipe roof structures and construction method of piperoof structures
KR100813910B1 (en) Pipe roof structure
KR102090700B1 (en) Continuous Steel Material constituting Wall Connected to Plurality of Units and Underground Structure Construction Method Using the Same
JPS6158640B2 (en)
JP3761173B2 (en) Connecting device for pipes in excavation grooves
KR101219451B1 (en) Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
KR101163743B1 (en) Underground structure construction method using h-shaped steel pipe
KR102170804B1 (en) Construction method of underground structure using special guidance pipe
KR101285987B1 (en) Improved Compound Roof Tunnel Method
KR100794810B1 (en) Excavation method of road and railroad lower part using deck unit jacking

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
G170 Publication of correction
FPAY Annual fee payment

Payment date: 20120813

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20130924

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20141016

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20151019

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20161013

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20171012

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20181023

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20191022

Year of fee payment: 13