KR100655135B1 - Construction method of electric switchboard - Google Patents

Construction method of electric switchboard Download PDF

Info

Publication number
KR100655135B1
KR100655135B1 KR1020060068196A KR20060068196A KR100655135B1 KR 100655135 B1 KR100655135 B1 KR 100655135B1 KR 1020060068196 A KR1020060068196 A KR 1020060068196A KR 20060068196 A KR20060068196 A KR 20060068196A KR 100655135 B1 KR100655135 B1 KR 100655135B1
Authority
KR
South Korea
Prior art keywords
electrical
electrical switchboard
spring
switchboard
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
KR1020060068196A
Other languages
Korean (ko)
Inventor
홍창선
Original Assignee
주식회사 진솔엔지니어링건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 진솔엔지니어링건축사사무소 filed Critical 주식회사 진솔엔지니어링건축사사무소
Priority to KR1020060068196A priority Critical patent/KR100655135B1/en
Application granted granted Critical
Publication of KR100655135B1 publication Critical patent/KR100655135B1/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B1/00Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
    • H02B1/26Casings; Parts thereof or accessories therefor
    • H02B1/40Wall-mounted casings; Parts thereof or accessories therefor
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/08Distribution boxes; Connection or junction boxes
    • H02G3/12Distribution boxes; Connection or junction boxes for flush mounting
    • H02G3/121Distribution boxes; Connection or junction boxes for flush mounting in plain walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Vibration Prevention Devices (AREA)

Abstract

건물의 진동 또는 충격등에 의해서 전기배전반에 접속된 전력케이블의 접속상태의 느슨해짐을 방지할 수 있도록 충격 및 진동을 감쇠시킬 수 있도록 한 전기배전반의 시공방법에 관한 것이다. 이 시공방법은 전면부가 개방되고 양측면 및 저면부에 결합구멍(21)(22)이 형성된 전기배전반박스(20)를 거푸집에 고정시키고, 결합구멍(21)(22)에 스프링케이스(30)를 결합시키고, 콘크리트를 타설하고 양생하여 전기배전반박스(20) 및 스프링케이스(30)를 콘크리트에 매입시킨 후, 각 결합구멍(21)(22)을 통하여 스프링케이스(30)에 스프링(50)을 결합시키고, 전기배전반박스(20)보다 상대적으로 작은 전기배전반(40)을 전기배전반박스(20)내에 위치시키고, 각 결합구멍(21)(22)에 대응되는 전기배전반(40)의 측면 및 저면부에 스프링(50)과 연결되게 댐퍼(60)를 결합고정시킨다. 이와 같은 시공방법은 진동이나 충격으로 전기배전반(40)의 진동/충격을 흡수하여 전기배전반 내의 전기접속단자의 안정된 접속상태를 장기간 유지할 수 있게 한다.The present invention relates to a construction method of an electrical switchgear capable of attenuating shock and vibration so as to prevent loosening of a connection state of a power cable connected to an electrical switchgear by a vibration or shock of a building. In this construction method, the front panel is opened and the electrical switchboard box 20 having the coupling holes 21 and 22 formed on both sides and the bottom is fixed to the formwork, and the spring case 30 is attached to the coupling holes 21 and 22. After coupling, placing and curing concrete to embed the electrical switchboard box 20 and the spring case 30 in the concrete, the spring 50 to the spring case 30 through each coupling hole (21) (22) The electrical switchboard 40, which is smaller than the electrical switchboard box 20, is positioned in the electrical switchboard box 20, and the side and bottom of the electrical switchboard 40 corresponding to each coupling hole 21,22. Coupling and fixing the damper 60 to be connected to the spring 50 to the part. Such a construction method absorbs the vibrations / shocks of the electrical switchboard 40 by vibrations or shocks, thereby making it possible to maintain a stable connection state of the electrical connection terminals in the electrical switchboard for a long time.

Description

전기배전반의 시공방법{A construction method of Switch Board}Construction method of switchboard {A construction method of Switch Board}

도 1은 통상의 전기배전반을 개략 정면도,1 is a schematic front view of a conventional electric switchboard;

도 2는 본 발명 시공방법에 사용되는 전기배전반박스 및 스프링케이스를 나타낸 사시도,Figure 2 is a perspective view showing an electrical switchboard box and a spring case used in the construction method of the present invention,

도 3은 본 발명 시공방법으로 시공된 전기배전반을 나타낸 개략도,3 is a schematic view showing an electric switchboard constructed by the present invention construction method,

도 4는 도 3의 요부 확대도이다.4 is an enlarged view illustrating main parts of FIG. 3.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

20...전기배전반박스 30...스프링케이스20 ... Electric switchboard box 30 ... Spring case

40...전기배전반 50...스프링40 ... electric switchboard 50 ... spring

60...댐퍼60 ... damper

본 발명은 전기배전반의 시공방법에 관한 것으로써, 특히 건물의 진동 또는 충격등에 의해서 전기배전반에 접속된 전력케이블의 접속상태가 느슨해지거나 풀어짐을 방지할 수 있도록 충격 및 진동을 감쇠시킬 수 있도록 한 전기배전반의 시공방법에 관한 것이다.The present invention relates to a construction method of an electric switchboard, and in particular, the electric power to attenuate shock and vibration to prevent the connection state of the power cable connected to the electric switchboard from loosening or loosening due to vibration or shock of a building. It is about construction method of switchboard.

전기배전반(Switch Board)은 발전소, 변전소, 전기시설이 되어 있는 대형 건물 등의 시설에 설치되는 장비로서, 전로(電路)의 개폐나 기기의 제어를 용이하게 한다.Switch boards are equipment installed in facilities such as power plants, substations, and large buildings with electrical facilities, and facilitate the opening and closing of converters and controlling devices.

일반적으로 전기배전반은 도 1에서와 같이, 베이스 판넬(10)에 인입선(13)으로부터 메인 배선용 차단기(11), 배선용 차단기(12), 누전 차단기 등 각종 차단기 및 계전기 등이 연결설치되고, 각각의 차단기 및 계전기 등이 전기적으로 연결되어 있는 장비이다.In general, as shown in FIG. 1, various breakers and relays such as a main wiring breaker 11, a wiring breaker 12, an earth leakage breaker, and the like are connected to the base panel 10 from the lead line 13. Circuit breaker and relay are electrically connected.

전기배전반은 외부로부터 공급되는 전력을 연결되어 있는 다수의 하부 기기로 배분하는 동시에 전력 공급을 개폐하는 가능을 갖는다.The electric switchboard is capable of distributing power supplied from the outside to a plurality of lower devices connected thereto and simultaneously opening and closing the power supply.

이와 같이 외부전원을 배분하도록 전기적으로 접속되어 있는 전기배전반은 건물의 진동이나 충격등이 장기간 지속되면서 전기접속 단자의 조임상태가 풀어지게 된다.In this way, the electrical switchboard electrically connected to distribute the external power is released for a long time as the vibration or shock of the building continues.

따라서 건물의 전기실 담당자는 일정기간 간격으로 접속단자를 점검하여 단자의 접촉 불량을 사전에 예방하고 안전한 전기사용을 할 수 있도록 한다.Therefore, the person in charge of the electrical room of the building checks the connection terminal at regular intervals to prevent the poor contact of the terminal in advance and to use the safe electricity.

통상 건축물의 벽체는 실내와 실외를 구획하는 기본기능과 더불어 보온기능 및 방음방진 기능을 갖도록 설계된다.In general, the walls of the building is designed to have a thermal insulation function and a soundproof dustproof function as well as the basic function of partitioning the indoor and outdoor.

그러나 종래에는 벽체 전체적으로 방음방진을 위해 내장재가 투입되므로 벽체가 구조적으로 저하될 뿐만 아니라 건설비용의 증가를 가져왔으며, 이러한 건물전체의 방진방음구조는 전기배전반이 설치되는 국부적 진동 및 충격으로부터 보호되기에는 부족하다.However, in the past, since the interior materials are put into the entire wall for soundproof dustproofing, not only the wall is structurally degraded, but also the construction cost is increased. Such a soundproof soundproof structure of the whole building is not protected from local vibration and shocks in which the electric switchboard is installed. Lack.

본 발명은 상기와 같은 문제점을 감안하여 창출한 것으로써, 건물의 진동이나 충격등이 장기간 지속되더라도 전기접속 단자의 조임상태가 안정되게 장기간 유지될 수 있도록 하여 전기점검자의 점검주기를 연장시킬 수 있도록 한 전기배전반의 시공방법을 제공하는 데 목적이 있다.The present invention was created in view of the above problems, so that even if the vibration or shock of a building lasts for a long time, the tightening state of the electrical connection terminal can be stably maintained for a long time, so that the inspection period of the electric inspector can be extended. The purpose is to provide a construction method of an electric switchboard.

상기 목적을 달성하는 본 발명은 인입선으로부터 메인 배선용 차단기, 배선용 차단기등 각종 차단기 및 계전기 등이 연결설치되고 각각의 차단기 및 계전기 등이 전기적으로 연결되는 전기배전반을 건물의 콘크리트벽체에 시공하는 전기배전반의 시공방법에 있어서,The present invention to achieve the above object of the electrical switchgear to install the electrical switchboard connected to the various circuit breakers and relays, such as the main wiring breaker, the wiring breaker from the lead wire, and each breaker and the relay is electrically connected to the concrete wall of the building In the construction method,

전면부가 개방되고 측면 및 저면부에 결합구멍이 형성된 전기배전반박스를 거푸집에 고정시키고, 상기 결합구멍에 스프링케이스를 결합시키고, 콘크리트를 타설하고 양생하여 상기 전기배전반박스 및 스프링케이스를 콘크리트에 매입시킨 후,The electrical switchboard box having the front part open and the coupling hole formed at the side and the bottom is fixed to the formwork, the spring case is coupled to the coupling hole, the concrete is poured and cured, and the electrical switchboard box and the spring case are embedded in the concrete. after,

상기 각 결합구멍을 통하여 상기 스프링케이스에 스프링을 결합시키고, 상기 전기배전반박스보다 상대적으로 작은 전기배전반을 전기배전반박스내에 위치시키고,Coupling a spring to the spring case through each of the coupling holes, and placed in the electrical switchboard box relatively smaller than the electrical switchboard box,

상기 결합구멍에 대응되는 전기배전반의 측면 및 저면부에 상기 스프링과 연결되게 댐퍼를 결합고정시키되,The damper is coupled and fixed to the side and bottom surface of the electrical switchboard corresponding to the coupling hole to be connected to the spring,

댐퍼는 전기배전반에 고정되는 댐퍼케이스와, 댐퍼케이스에 수용되는 오일과, 댐퍼케이스에 슬라이딩 이동되며 상기 오일이 통과되는 구멍이 형성된 피스톤 과, 일단이 상기 피스톤과 연결되고 타단이 상기 스프링과 접촉하는 피스톤로드로 구성하는 것을 특징으로 한다.The damper is a damper case fixed to the electrical switchboard, the oil accommodated in the damper case, a piston which is slidably moved in the damper case and formed with a hole through which the oil passes, and one end is connected to the piston and the other end is in contact with the spring. It is characterized by comprising a piston rod.

이하 첨부된 도면을 참조하면서 본 발명에 따른 바람직한 실시예를 상세히 설명한다. Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명 시공방법은 전기배전반(40)이 건물의 진동이나 충격으로부터 전기접속단자의 풀림을 최소화하여 전기담당자로 하여금 점검주기를 연장시키고, 전기접속 단자의 조임상태가 안정되게 장기간 유지될 수 있도록 한다.The construction method of the present invention, the electrical switchboard 40 to minimize the loosening of the electrical connection terminal from the vibration or impact of the building to allow the electrician to extend the inspection period, so that the tightening state of the electrical connection terminal can be stably maintained for a long time. .

본 발명 시공방법에 적용되는 전기배전반(40)은 통상과 마찬가지로 인입선으로부터 메인 배선용 차단기, 배선용 차단기등 각종 차단기 및 계전기 등이 연결설치되고 각각의 차단기 및 계전기 등이 전기적으로 연결된다.The electrical switchboard 40 applied to the construction method of the present invention is connected to various circuit breakers and relays such as the main circuit breaker and the circuit breaker from the lead wire as usual, and each circuit breaker and the relay are electrically connected.

도 2 내지 도 4를 참조하면, 본 발명 시공방법은 전면부가 개방되고 양측면 및 저면부에 결합구멍(21)(22)이 형성된 전기배전반박스(20)를 거푸집(미도시)에 고정시키고, 상기 결합구멍(21)(22)에 스프링케이스(30)를 결합시키고, 콘크리트를 타설하고 양생하여 상기 전기배전반박스(20) 및 스프링케이스(30)를 콘크리트에 매입시킨다.2 to 4, the construction method of the present invention is fixed to the formwork (not shown) the electrical switchboard box 20, the front portion is opened and the coupling holes 21, 22 formed on both sides and the bottom surface, The spring case 30 is coupled to the coupling holes 21 and 22, and the concrete is poured and cured to embed the electric switchboard box 20 and the spring case 30 in concrete.

이어서 상기 각 결합구멍(21)(22)을 통하여 스프링케이스(30)에 스프링(50)을 결합시키고, 상기 전기배전반박스(20)보다 상대적으로 작은 전기배전반(40)을 전기배전반박스(20)내에 위치시키고,Subsequently, the spring 50 is coupled to the spring case 30 through the coupling holes 21 and 22, and the electrical switchboard box 20 is smaller than the electrical switchboard box 20. Within the

상기 결합구멍(21)(22)에 대응되는 전기배전반(40)의 측면 및 저면부에 상기 스프링(50)과 연결되게 댐퍼(60)를 결합고정시킨다. 이때 댐퍼(60)는 도 4에서와 같이, 전기배전반(40)의 측면과 저면에 구멍을 형성하여 내측에서 결합시킨다. The damper 60 is coupled and fixed to the side and bottom surfaces of the electrical switchboard 40 corresponding to the coupling holes 21 and 22 to be connected to the spring 50. At this time, the damper 60, as shown in Figure 4, to form a hole in the side and bottom of the electrical switchboard 40 is coupled to the inside.

상기 댐퍼(60)는 전기배전반(40)에 고정되는 댐퍼케이스(61)와, 댐퍼케이스(61)에 수용되는 오일(70)과, 댐퍼케이스(61)에 슬라이딩 이동되며 상기 오일(70)이 통과되는 구멍(62a)이 형성된 피스톤(62)과, 일단이 상기 피스톤(62)과 연결되고 타단이 상기 스프링(50)과 접촉하는 피스톤로드(63)로 구성한다.The damper 60 is a damper case 61 is fixed to the electrical switchboard 40, the oil 70 accommodated in the damper case 61, and the damper case 61 is slidably moved to the oil 70 A piston 62 having a hole 62a formed therethrough, and a piston rod 63 having one end connected to the piston 62 and the other end contacting the spring 50.

상기와 같은 시공방법은 전기배전반(40)과 전기배전반박스(20) 사이에 스프링(50)과 댐퍼(60)의 설치를 간편하게 하고, 전기배전반 주변의 진동이나 충격시 스프링(50)의 완충 및 스프링(50) 자체진동을 피스톤(62)의 이동에 따른 감쇠로 전기배전반(40)의 진동을 흡수한다. The construction method as described above facilitates the installation of the spring 50 and the damper 60 between the electrical switchboard 40 and the electrical switchboard box 20, and buffers the spring 50 during vibration or impact around the electrical switchboard. The vibration of the electric switchboard 40 is absorbed by damping of the spring 50 itself by the movement of the piston 62.

예컨대, 도 4를 참조하면, 충격 또는 진동이 좌측방향으로 되는 경우, 댐퍼(60)의 피스톤로드(63)에 의해서 스프링(50)이 압축되고, 동시에 피스톤(62)이 댐퍼케이스(61) 내에서 우측으로 이동되며, 오일(70)은 작은 구멍(62a)을 통하여 피스톤(62)의 좌측공간으로 서서히 이동되게 되면서 진동 및 충격을 흡수하게 한다. 이와 같은 일련의 동작은 채용하는 스프링(50)의 강성, 구멍(62a)의 크기, 오일(70)의 점도에 따라 미세하게 동작되도록 시공한다.For example, referring to FIG. 4, when the shock or vibration is in the left direction, the spring 50 is compressed by the piston rod 63 of the damper 60, and at the same time the piston 62 is in the damper case 61. Is moved to the right side, the oil 70 is slowly moved to the left space of the piston 62 through the small hole (62a) to absorb the vibration and shock. Such a series of operations are constructed to operate finely according to the rigidity of the spring 50 to be employed, the size of the hole 62a, and the viscosity of the oil 70.

상술한 바와 같은 본 발명은 상기 본원의 정신과 범위를 이탈함이 없이 상기 실시예에 한정되지 아니하고 많은 변형을 가하여 실시될 수 있음은 두 말 할 것도 없다.Needless to say, the present invention as described above can be implemented by many modifications without being limited to the above embodiments without departing from the spirit and scope of the present application.

상술한 바와 같은 본 발명은 전기배전반박스(20) 및 스프링케이스(30)를 콘 크리트벽체를 시공하면서 매입시공하고, 전기배전반(40)과 전기배전반박스(20) 사이에 스프링(50)과 댐퍼(60)를 설치함으로써, 외부 진동이나 충격으로 전기배전반(40)의 진동/충격을 흡수하여 전기배전반 내의 전기접속단자의 안정된 접속상태를 장기간 유지할 수 있게 한다.In the present invention as described above, the electrical switchboard box 20 and the spring case 30 is embedded while constructing the concrete wall, the spring 50 and the damper between the electrical switchboard 40 and the electrical switchboard box 20 By providing 60, the vibration / shock of the electrical switchboard 40 can be absorbed by external vibration or shock, so that the stable connection state of the electrical connection terminals in the electrical switchboard can be maintained for a long time.

또한, 댐퍼케이스(61)에 오일(70)을 충진하고 피스톤의 구멍(62a)을 통하여 오일이 이동되도록 함으로써 스프링 자체 진동을 감쇠시켜, 스프링 자체 여진에 의한 전기배전반의 진동을 최소화한다.In addition, the damper case 61 is filled with oil 70 and the oil is moved through the hole 62a of the piston, thereby damping the vibration of the spring itself, thereby minimizing the vibration of the electrical switchboard due to the spring self-excitation.

Claims (1)

인입선으로부터 메인 배선용 차단기, 배선용 차단기등 각종 차단기 및 계전기 등이 연결설치되고 각각의 차단기 및 계전기 등이 전기적으로 연결되는 전기배전반을 건물의 콘크리트벽체에 시공하는 전기배전반의 시공방법에 있어서,In the construction method of the electrical switchboard, which is installed on the concrete wall of the building, the electrical switchboard, which is connected to the circuit breaker for the main wiring, the circuit breaker and the like, and the various circuit breakers and relays are electrically connected to each other. 전면부가 개방되고 양측면 및 저면부에 결합구멍(21)(22)이 형성된 전기배전반박스(20)를 거푸집에 고정시키고, 상기 결합구멍(21)(22)에 스프링케이스(30)를 결합시키고, 콘크리트를 타설하고 양생하여 상기 전기배전반박스(20) 및 스프링케이스(30)를 콘크리트에 매입시킨 후,Fixing the electrical switchboard box 20, the front portion is opened and the coupling holes 21, 22 formed on both sides and the bottom portion in the formwork, the spring case 30 is coupled to the coupling holes 21, 22, After placing and curing concrete to purchase the electrical switchboard box 20 and the spring case 30 in concrete, 상기 각 결합구멍(21)(22)을 통하여 상기 스프링케이스(30)에 스프링(50)을 결합시키고, 상기 전기배전반박스(20)보다 상대적으로 작은 전기배전반(40)을 전기배전반박스(20)내에 위치시키고,The spring 50 is coupled to the spring case 30 through the coupling holes 21 and 22, and the electrical switchboard box 20 is smaller than the electrical switchboard box 20. Within the 상기 각 결합구멍(21)(22)에 대응되는 전기배전반(40)의 측면 및 저면부에 상기 스프링(50)과 연결되게 댐퍼(60)를 결합고정시키되,The damper 60 is coupled and fixed to the side and bottom surface of the electrical switchboard 40 corresponding to each of the coupling holes 21 and 22 to be connected to the spring 50. 댐퍼(60)는 전기배전반(40)에 고정되는 댐퍼케이스(61)와, 댐퍼케이스(61)에 수용되는 오일(70)과, 댐퍼케이스(61)에 슬라이딩 이동되며 상기 오일(70)이 통과되는 구멍(62a)이 형성된 피스톤(62)과, 일단이 상기 피스톤(62)과 연결되고 타단이 상기 스프링(50)과 접촉하는 피스톤로드(63)로 구성하는 것을 특징으로 하는 전기배전반의 시공방법. The damper 60 is a damper case 61 fixed to the electrical switchboard 40, the oil 70 accommodated in the damper case 61, and the damper case 61 is slidably moved and the oil 70 passes therethrough. Construction method of the electric switchgear characterized in that it comprises a piston 62 having a hole 62a is formed, and a piston rod 63, one end of which is connected to the piston 62 and the other end of which contacts the spring 50. .
KR1020060068196A 2006-07-20 2006-07-20 Construction method of electric switchboard Expired - Fee Related KR100655135B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060068196A KR100655135B1 (en) 2006-07-20 2006-07-20 Construction method of electric switchboard

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060068196A KR100655135B1 (en) 2006-07-20 2006-07-20 Construction method of electric switchboard

Publications (1)

Publication Number Publication Date
KR100655135B1 true KR100655135B1 (en) 2006-12-08

Family

ID=37732495

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060068196A Expired - Fee Related KR100655135B1 (en) 2006-07-20 2006-07-20 Construction method of electric switchboard

Country Status (1)

Country Link
KR (1) KR100655135B1 (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101038748B1 (en) 2011-02-18 2011-06-03 이삼종 Connector for underground distribution line connection
KR101181430B1 (en) * 2012-03-09 2012-09-19 (주)원테크 Distribution board
CN103353053A (en) * 2013-06-28 2013-10-16 深圳市英威腾电气股份有限公司 Keyboard stand compatible with multiple models of installation ports
KR101380308B1 (en) 2014-01-28 2014-04-02 노재호 Connection type protecting apparatus for underground distribution line
KR101560190B1 (en) 2015-04-09 2015-10-26 주식회사 남동인덱스 A distributing board having the earthquake-proof function
KR101569914B1 (en) 2015-06-30 2015-11-27 (주)한진엔지니어링 Distributing board structure in an apartment
KR101601905B1 (en) * 2015-12-15 2016-03-10 (주)화신파워텍 Transformers installation structure
KR101620065B1 (en) * 2015-09-24 2016-05-11 주식회사 라이트 제림 Distribution box which is possible short-circuit resistant of the cable
CN106785966A (en) * 2016-12-20 2017-05-31 国网山东省电力公司东明县供电公司 It is easy to mobile power distribution cabinet and is easy to the power distribution cabinet of braking
CN106803646A (en) * 2015-11-26 2017-06-06 德尔瑞(天津)机电设备有限公司 A kind of damping switch cabinet
CN107575528A (en) * 2017-08-14 2018-01-12 浙江水利水电学院 Accurate communication equipment vibration absorber
CN107800051A (en) * 2016-08-29 2018-03-13 江苏德驰电气有限公司 A kind of high reliability direct-current switch cabinet
CN108598918A (en) * 2018-06-19 2018-09-28 张丽聪 A kind of high voltage power distributing cabinet that easy access is safeguarded
CN108963839A (en) * 2018-10-30 2018-12-07 大连理工江苏研究院有限公司 A kind of electromechanical integration power distribution cabinet protection radiator
KR102100144B1 (en) * 2019-09-19 2020-04-14 (주)이명이앤씨건축사사무소 Power distribution unit of apartment house equipped with seismic design
CN111244858A (en) * 2020-01-21 2020-06-05 福建成田科技有限公司 Cable antidetonation support
KR102309080B1 (en) * 2021-05-06 2021-10-06 (주)신한티이씨 Distribution cable protection device for buildings
KR102355907B1 (en) * 2021-05-27 2022-02-08 서한컨설탄트(주) Integrated terminal box for apartment houses with earthquake-proof performance
KR102567814B1 (en) 2023-03-14 2023-08-17 엑스티지(주) Front hatch system electric control panel device
KR102579392B1 (en) 2022-10-20 2023-09-22 태원전기(주) Switch board with improved constructability

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101038748B1 (en) 2011-02-18 2011-06-03 이삼종 Connector for underground distribution line connection
KR101181430B1 (en) * 2012-03-09 2012-09-19 (주)원테크 Distribution board
CN103353053A (en) * 2013-06-28 2013-10-16 深圳市英威腾电气股份有限公司 Keyboard stand compatible with multiple models of installation ports
KR101380308B1 (en) 2014-01-28 2014-04-02 노재호 Connection type protecting apparatus for underground distribution line
KR101560190B1 (en) 2015-04-09 2015-10-26 주식회사 남동인덱스 A distributing board having the earthquake-proof function
KR101569914B1 (en) 2015-06-30 2015-11-27 (주)한진엔지니어링 Distributing board structure in an apartment
KR101620065B1 (en) * 2015-09-24 2016-05-11 주식회사 라이트 제림 Distribution box which is possible short-circuit resistant of the cable
CN106803646B (en) * 2015-11-26 2019-03-05 德尔瑞(天津)机电设备有限公司 A kind of damping switch cabinet
CN106803646A (en) * 2015-11-26 2017-06-06 德尔瑞(天津)机电设备有限公司 A kind of damping switch cabinet
KR101601905B1 (en) * 2015-12-15 2016-03-10 (주)화신파워텍 Transformers installation structure
CN107800051A (en) * 2016-08-29 2018-03-13 江苏德驰电气有限公司 A kind of high reliability direct-current switch cabinet
CN106785966A (en) * 2016-12-20 2017-05-31 国网山东省电力公司东明县供电公司 It is easy to mobile power distribution cabinet and is easy to the power distribution cabinet of braking
CN107575528A (en) * 2017-08-14 2018-01-12 浙江水利水电学院 Accurate communication equipment vibration absorber
CN107575528B (en) * 2017-08-14 2019-04-16 浙江水利水电学院 Accurate communication equipment vibration absorber
CN108598918A (en) * 2018-06-19 2018-09-28 张丽聪 A kind of high voltage power distributing cabinet that easy access is safeguarded
CN108963839A (en) * 2018-10-30 2018-12-07 大连理工江苏研究院有限公司 A kind of electromechanical integration power distribution cabinet protection radiator
KR102100144B1 (en) * 2019-09-19 2020-04-14 (주)이명이앤씨건축사사무소 Power distribution unit of apartment house equipped with seismic design
CN111244858A (en) * 2020-01-21 2020-06-05 福建成田科技有限公司 Cable antidetonation support
CN111244858B (en) * 2020-01-21 2020-12-29 福建成田科技有限公司 Cable antidetonation support
KR102309080B1 (en) * 2021-05-06 2021-10-06 (주)신한티이씨 Distribution cable protection device for buildings
KR102355907B1 (en) * 2021-05-27 2022-02-08 서한컨설탄트(주) Integrated terminal box for apartment houses with earthquake-proof performance
KR102579392B1 (en) 2022-10-20 2023-09-22 태원전기(주) Switch board with improved constructability
KR102567814B1 (en) 2023-03-14 2023-08-17 엑스티지(주) Front hatch system electric control panel device

Similar Documents

Publication Publication Date Title
KR100655135B1 (en) Construction method of electric switchboard
KR100939475B1 (en) Earthquake-proofing distribute &amp; switch board
KR101829126B1 (en) Distribution Panel with Vibration Proof
KR101276252B1 (en) Distributing board
KR101181430B1 (en) Distribution board
KR102106768B1 (en) Assembly type electrical control box
KR101681111B1 (en) A high and low voltage metal-clad switchgear having earthquake-proof construction
KR101349791B1 (en) Vibration proof unit and distributing board using the same
KR100939576B1 (en) Switchgear having quake-proof performance
KR20090117086A (en) Seismic Closed Switchgear
KR101488422B1 (en) Distribution board having earthquake-proof means
KR102032420B1 (en) Earthquake for case
KR101593174B1 (en) A switchgear panel
KR101371679B1 (en) transparent distribution box
KR102264956B1 (en) Distribution panel
KR20130074387A (en) Distribution panel for water proof
KR101681108B1 (en) A high and low voltage metal-clad switchgear having earthquake-proof construction
KR101012733B1 (en) Vibration Absorption Switchgear
KR102260306B1 (en) Electric panel of seismic capability
KR102336857B1 (en) Pull-out type buried underground distribution board for stable power supply
KR101541655B1 (en) Earthquake-proof switch board of earthquake-control installed with steel body mode absorbing vibration according to weight of composing equipment
KR101607241B1 (en) Vibration Isolation Device and Distributing Board, Control Board comprising the same
KR102416437B1 (en) Earthquake-proof device and switchgear having same
JP2024085762A (en) Substation facility for electric power station and construction method thereof
KR101571557B1 (en) Seismic switchboard equipped with anti vibration device housing

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

St.27 status event code: A-0-1-A10-A12-nap-PA0109

PA0201 Request for examination

St.27 status event code: A-1-2-D10-D11-exm-PA0201

A302 Request for accelerated examination
PA0302 Request for accelerated examination

St.27 status event code: A-1-2-D10-D17-exm-PA0302

St.27 status event code: A-1-2-D10-D16-exm-PA0302

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

P13-X000 Application amended

St.27 status event code: A-2-2-P10-P13-nap-X000

E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

St.27 status event code: A-1-2-D10-D21-exm-PE0902

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

P13-X000 Application amended

St.27 status event code: A-2-2-P10-P13-nap-X000

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

St.27 status event code: A-1-2-D10-D22-exm-PE0701

N231 Notification of change of applicant
PN2301 Change of applicant

St.27 status event code: A-3-3-R10-R13-asn-PN2301

St.27 status event code: A-3-3-R10-R11-asn-PN2301

GRNT Written decision to grant
PR0701 Registration of establishment

St.27 status event code: A-2-4-F10-F11-exm-PR0701

PR1002 Payment of registration fee

St.27 status event code: A-2-2-U10-U11-oth-PR1002

Fee payment year number: 1

PG1601 Publication of registration

St.27 status event code: A-4-4-Q10-Q13-nap-PG1601

PN2301 Change of applicant

St.27 status event code: A-5-5-R10-R13-asn-PN2301

St.27 status event code: A-5-5-R10-R11-asn-PN2301

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 4

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 5

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 6

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

PN2301 Change of applicant

St.27 status event code: A-5-5-R10-R11-asn-PN2301

PN2301 Change of applicant

St.27 status event code: A-5-5-R10-R14-asn-PN2301

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

P14-X000 Amendment of ip right document requested

St.27 status event code: A-5-5-P10-P14-nap-X000

P14-X000 Amendment of ip right document requested

St.27 status event code: A-5-5-P10-P14-nap-X000

P16-X000 Ip right document amended

St.27 status event code: A-5-5-P10-P16-nap-X000

Q16-X000 A copy of ip right certificate issued

St.27 status event code: A-4-4-Q10-Q16-nap-X000

FPAY Annual fee payment

Payment date: 20121130

Year of fee payment: 7

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 7

P15-X000 Request for amendment of ip right document rejected

St.27 status event code: A-5-5-P10-P15-nap-X000

FPAY Annual fee payment

Payment date: 20131129

Year of fee payment: 8

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 8

PN2301 Change of applicant

St.27 status event code: A-5-5-R10-R13-asn-PN2301

St.27 status event code: A-5-5-R10-R11-asn-PN2301

FPAY Annual fee payment

Payment date: 20141125

Year of fee payment: 9

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 9

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 10

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

P22-X000 Classification modified

St.27 status event code: A-4-4-P10-P22-nap-X000

FPAY Annual fee payment

Payment date: 20161201

Year of fee payment: 11

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 11

LAPS Lapse due to unpaid annual fee
PC1903 Unpaid annual fee

St.27 status event code: A-4-4-U10-U13-oth-PC1903

Not in force date: 20171202

Payment event data comment text: Termination Category : DEFAULT_OF_REGISTRATION_FEE

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

P22-X000 Classification modified

St.27 status event code: A-4-4-P10-P22-nap-X000

PC1903 Unpaid annual fee

St.27 status event code: N-4-6-H10-H13-oth-PC1903

Ip right cessation event data comment text: Termination Category : DEFAULT_OF_REGISTRATION_FEE

Not in force date: 20171202

R18-X000 Changes to party contact information recorded