KR100599817B1 - Blind flange for nuclear fuel transportation tube - Google Patents

Blind flange for nuclear fuel transportation tube Download PDF

Info

Publication number
KR100599817B1
KR100599817B1 KR1020040066737A KR20040066737A KR100599817B1 KR 100599817 B1 KR100599817 B1 KR 100599817B1 KR 1020040066737 A KR1020040066737 A KR 1020040066737A KR 20040066737 A KR20040066737 A KR 20040066737A KR 100599817 B1 KR100599817 B1 KR 100599817B1
Authority
KR
South Korea
Prior art keywords
opening
flange
pipe
closing member
closing
Prior art date
Application number
KR1020040066737A
Other languages
Korean (ko)
Other versions
KR20060018385A (en
Inventor
조성은
Original Assignee
주식회사 무진기연
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 무진기연 filed Critical 주식회사 무진기연
Priority to KR1020040066737A priority Critical patent/KR100599817B1/en
Publication of KR20060018385A publication Critical patent/KR20060018385A/en
Application granted granted Critical
Publication of KR100599817B1 publication Critical patent/KR100599817B1/en

Links

Images

Classifications

    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21CNUCLEAR REACTORS
    • G21C19/00Arrangements for treating, for handling, or for facilitating the handling of, fuel or other materials which are used within the reactor, e.g. within its pressure vessel
    • G21C19/20Arrangements for introducing objects into the pressure vessel; Arrangements for handling objects within the pressure vessel; Arrangements for removing objects from the pressure vessel
    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21FPROTECTION AGAINST X-RADIATION, GAMMA RADIATION, CORPUSCULAR RADIATION OR PARTICLE BOMBARDMENT; TREATING RADIOACTIVELY CONTAMINATED MATERIAL; DECONTAMINATION ARRANGEMENTS THEREFOR
    • G21F5/00Transportable or portable shielded containers
    • G21F5/06Details of, or accessories to, the containers
    • G21F5/10Heat-removal systems, e.g. using circulating fluid or cooling fins
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • High Energy & Nuclear Physics (AREA)
  • Plasma & Fusion (AREA)
  • Monitoring And Testing Of Nuclear Reactors (AREA)

Abstract

본 발명은 원자로 빌딩내부로 핵연료 빌딩에 저장된 핵연료를 이송하는 이송관의 끝단을 개폐하는 핵연료 이송관용 블라인드 플랜지에 관한 것으로, 더욱 상세하게는, 상기 이송관 일단에 형성된 관플랜지보다 비교적 좁은 폭의 면을 가지는 링형상을 가지고 관플랜지에 볼팅결합되며, 일측면으로 돌설된 한 쌍의 롤러브라켓이 원주방향으로 다수개 형성되고, 이 롤러브라켓에는 관플랜지의 일측면으로부터 소정거리 이격되게 가압롤러가 제1회전축에 의해 회전가능하게 결합되며, 이송관의 중공부보다 비교적 큰 중공부가 형성된 고정부재와; 상기 고정부재의 중공부에 삽입되어 관플랜지에 밀착되며, 타측면에 패킹이 원주방향으로 함입된 개폐부재와; 상기 개폐부재를 고정부재의 중공부에서 관플랜지 일측면에 개폐시키기 위한 개폐부재의 개폐수단을 포함한다.The present invention relates to a blind flange for a fuel delivery pipe that opens and closes an end of a delivery pipe for transporting fuel stored in a nuclear fuel building into a reactor building. More specifically, a plane having a relatively narrow width than a pipe flange formed at one end of the delivery pipe It has a ring shape and is bolted to the pipe flange, a pair of roller brackets protruding in one side is formed in a plurality of circumferential direction, the pressure roller is provided in the roller bracket spaced a predetermined distance from one side of the pipe flange A fixing member rotatably coupled by one rotating shaft and having a hollow portion relatively larger than the hollow portion of the transfer pipe; An opening and closing member inserted into the hollow part of the fixing member to be in close contact with the pipe flange and having the packing circumferentially inserted into the other side; And an opening and closing means of the opening and closing member for opening and closing the opening and closing member on one side of the pipe flange in the hollow portion of the fixing member.

따라서, 핵연료 저장빌딩에서 원자로 빌딩내부로 핵연료를 이송할 때 신속하게 이송관을 개폐할 수 있도록 함으로써, 연료공급 및 교체에 따른 작업소요시간을 단축함은 물론 원자로 빌딩내의 방사능에 작업자가 노출되는 시간을 최소화 함으로써 작업자의 안전을 도모할 수 있는 핵연료 이송관용 블라인드 플랜지을 제공한다.Therefore, the transfer pipe can be opened and closed quickly when transferring fuel from the fuel storage building to the inside of the reactor building, thereby reducing the time required for fuel supply and replacement and exposing the worker to radiation in the reactor building. It provides a blind flange for fuel delivery pipes that can improve worker safety by minimizing the

핵연료, 원자로, 이송관, 플랜지, 블라인드Nuclear fuel, reactor, transfer pipe, flange, blind

Description

핵연료 이송관용 블라인드 플랜지{Blind flange for nuclear fuel transportation tube}Blind flange for nuclear fuel transportation tube

도 1은 종래 블라인드 플랜지의 구조를 도시한 도면.1 is a view showing the structure of a conventional blind flange.

도 2는 본 발명 블라인드 플랜지의 구조를 도시한 종단면도.Figure 2 is a longitudinal sectional view showing the structure of the blind flange of the present invention.

도 3은 본 발명 블라인드 플랜지의 구조를 도시한 정면도.Figure 3 is a front view showing the structure of the blind flange of the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

101 : 고정부재 102 : 롤러브라켓101: fixing member 102: roller bracket

103 : 가압롤러 104 : 개폐부재103: pressure roller 104: opening and closing member

105 : 회전브라켓 106 : 연동부105: rotation bracket 106: linkage

107 : 제3회전축 108 : 구동베벨기어107: third rotating shaft 108: driving bevel gear

109 : 손잡이 110 : 구동나사부109: handle 110: drive screw

111 : 잠금쇠 112 : 밀착부111: fastener 112: close contact

113 : 가이드브라켓 114 : 회전방지부재113: guide bracket 114: rotation preventing member

115 : 고정브라켓 116 : 스토퍼115: fixing bracket 116: stopper

117 : 볼트 118 : 베어링117: bolt 118: bearing

119 : 홀더119: Holder

본 발명은 원자로 빌딩내부로 핵연료 빌딩에 저장된 핵연료를 이송하는 이송관의 끝단을 개폐하는 핵연료 이송관용 블라인드 플랜지에 관한 것으로, 특히, 핵연료 저장빌딩에서 원자로 빌딩내부로 핵연료를 이송할 때 신속하게 이송관을 개폐할 수 있도록 함으로써, 연료공급 및 교체에 따른 작업소요시간을 단축함은 물론 원자로 빌딩내의 방사능에 작업자가 노출되는 시간을 최소화 함으로써 작업자의 안전을 도모할 수 있는 핵연료 이송관용 블라인드 플랜지을 제공한다.The present invention relates to a blind flange for a fuel delivery pipe that opens and closes an end of a delivery pipe for transporting fuel stored in a fuel building into a reactor building. In particular, the invention relates to a fast delivery pipe when a fuel is transferred from a fuel storage building to a reactor building. By opening and closing the valve, it is possible to shorten the work time required for fuel supply and replacement, as well as to provide a blind flange for a nuclear fuel delivery pipe that can improve the safety of the operator by minimizing the exposure time of the operator to the radiation in the reactor building.

일반적으로 원자력 발전소의 핵연료 빌딩과 원자로 빌딩 간에는 도 2에 도시된 바와 같이 핵연료 이송용 이송관(1)(종래의 이송관과 본 발명의 이송관은 동일하므로 동일한 번호를 부여함)이 설치된다.In general, between the nuclear fuel building and the nuclear reactor building of the nuclear power plant, a nuclear fuel transfer pipe 1 (the conventional transfer pipe and the transfer pipe of the present invention are given the same number) as shown in FIG. 2.

상기 핵연료 빌딩측 이송관에는 게이트 밸브(도시하지 않음)를 설치하고 원자로 빌딩측의 이송관에는 블라인드 플랜지(3)를 설치한다.A gate valve (not shown) is installed in the nuclear fuel building transport pipe, and a blind flange 3 is installed in the nuclear transport building transport pipe.

블라인드 플랜지(3)는 핵연료 빌등의 내외부를 방사능적으로 안전하게 차단하는 플랜지커버이며, 원자로 빌딩측에는 작업자가 내려가서 볼트(4)를 해체하고 블라인드 플랜지(3)를 열어 연료를 이송시킨 다음에 다시 내려가서 블라인드 플랜지(3)로 이송관(1)을 차단하는 작업을 수행하게 된다.The blind flange (3) is a flange cover that radioactively and securely blocks the inside and outside of the nuclear fuel bill, etc. The operator goes down to the reactor building to disassemble the bolt (4), open the blind flange (3) to transfer the fuel, and then lower it again. Go to perform the operation of blocking the feed pipe (1) to the blind flange (3).

이러한, 블라인드 플랜지(3)는 가장자리에 방사상으로 다수개의 체결공이 형성되어 있으며 이와 대응되게 이송관(1)에도 다수개의 체결공이 방사상으로 형성되어 이들이 볼트(4)에 의해 각각 체결됨으로써, 이송관(1)이 차단되는 것이다.The blind flange 3 has a plurality of fastening holes radially formed at the edge thereof, and a plurality of fastening holes are radially formed in the conveying pipe 1 so that they are fastened by bolts 4, respectively. 1) is blocked.

상기한 종래의 핵연료 이송관용 블라인드 플랜지(3)는 작업자에 의해 개폐되는 방식을 채택하고 있으므로, 핵연료 이송작업이 상당시간 지연되는 문제점이 있으며, 이때, 작업자는 내방사능의를 착용하고 있다하더라도 제한된 시간을 초과하여 노출될 수 없기 때문에 시간이 지연되면 될 수록 작업자에게는 방사능에 의한 피폭이 예상되며, 이에 따라 제한된 시간이 경과하기 전에 작업자가 수시로 교체되어야 하는 비능률적인 작업이 이루어지고 있었다.Since the conventional blind flange 3 for the fuel transfer pipe adopts a method of opening and closing by a worker, there is a problem that the nuclear fuel transfer operation is delayed for a considerable time. In this case, even if the worker wears radiation resistant clothing, a limited time is required. As the time delay is delayed, the workers are expected to be exposed to radioactivity because they cannot be exposed beyond this time. Therefore, inefficient work has been performed in which workers have to be replaced from time to time before the limited time has elapsed.

아울러, 블라인드 플랜지(3)는 핵연료를 재장전하는 수조 중에서도 가장 낮은 곳에 위치하므로 핵연료를 이송하기 전에 사전조치로 방사능 유출을 방지하기 위해 채워 넣은 물을 배수하더라도 완전배수는 곤란하다.In addition, since the blind flange (3) is located at the lowest position among the tanks for reloading the nuclear fuel, it is difficult to completely drain even if the filled water is drained in order to prevent radioactive leakage before the nuclear fuel is transported.

따라서, 방사능 오염도가 가장 높으며, 이런곳에서 블라인드 플랜지(3)를 개폐하는 데 장시간을 소요한다는 것은 작업자가 방사능에 피복될 개연성이 다분하고, 공간선량률도 상대적으로 높기 때문에 우려하지 않을 수 없다.Therefore, the radioactive contamination degree is the highest, and it takes a long time to open and close the blind flange 3 in such a place that the operator is likely to be covered with radioactivity and the space dose rate is relatively high.

물론, 블라인드 플랜지(3)에 설치된 실(seal)을 교체할 때도 마찬가지의 문제점이 제기되며, 대규모 원자력 발전소의 경우에는 반경이 더 큰 이송관과 블라인드 플랜지(2)를 사용하는 관계로 체결되는 볼트(4)수가 더 많고 이에 따라 방사능의 피폭이 심각하게 우려되는 문제점을 갖는다.Of course, the same problem arises when replacing the seal installed in the blind flange 3, and in the case of a large nuclear power plant, bolts fastened due to the use of a larger radius of transfer pipe and a blind flange 2 (4) It has a larger number and thus has a serious concern about the exposure of radioactivity.

상기한 문제점을 해결하기 위하여 안출된 본 발명은, 핵연료 빌딩과 원자로 빌딩간에 설치되는 핵연료 이송용 이송관에 블라인드 플랜지를 신속하고도 안전하게 개폐할 수 있도록 하여 작업자의 안전은 물론 효율적인 작업이 이루어질 수 있 도록 하는데 그 목적이 있다.The present invention has been made in order to solve the above problems, it is possible to open and close the blind flange quickly and safely in the nuclear fuel transfer transport pipe installed between the fuel building and the reactor building can be made safe and efficient work of the operator. The purpose is to make it happen.

상기한 목적은, 원자로 빌딩내부로 핵연료 빌딩에 저장된 핵연료를 이송하는 이송관의 끝단을 개폐하는 핵연료 이송관용 블라인드 플랜지에 있어서, 상기 이송관 일단에 형성된 관플랜지보다 비교적 좁은 폭의 면을 가지는 링형상을 가지고 관플랜지에 볼팅결합되며, 일측면으로 돌설된 한 쌍의 롤러브라켓이 원주방향으로 다수개 형성되고, 이 롤러브라켓에는 관플랜지의 일측면으로부터 소정거리 이격되게 가압롤러가 제1회전축에 의해 회전가능하게 결합되며, 이송관의 중공부보다 비교적 큰 중공부가 형성된 고정부재와; 상기 고정부재의 중공부에 삽입되어 관플랜지에 밀착되며, 타측면에 패킹이 원주방향으로 함입된 개폐부재와; 상기 개폐부재를 고정부재의 중공부에서 관플랜지 일측면에 개폐시키기 위한 개폐부재의 개폐수단을 포함한다.The above object is a blind flange for a fuel delivery pipe for opening and closing an end of a delivery pipe for transporting fuel stored in a nuclear fuel building into a reactor building, the ring having a relatively narrow surface than the tube flange formed at one end of the delivery pipe. It is bolted to the pipe flange with a pair of roller brackets protruding in one side is formed in a plurality of circumferential direction, the roller bracket is a pressure roller by a first rotating shaft spaced a predetermined distance from one side of the pipe flange A fixing member rotatably coupled and having a hollow portion relatively larger than the hollow portion of the transfer pipe; An opening and closing member inserted into the hollow part of the fixing member to be in close contact with the pipe flange and having the packing circumferentially inserted into the other side; And an opening and closing means of the opening and closing member for opening and closing the opening and closing member on one side of the pipe flange in the hollow portion of the fixing member.

그리고, 상기 개폐부재의 개폐수단은, 상기 개폐부재의 일측면 중심으로부터 소정거리 이격된 위치에서 가압롤러와 중심점까지 가상의 선으로 이어지는 직선상의 개폐부재 일측면에 결합되며, 회전이 형성된 다수개의 회전브라켓과; 상기 회전브라켓에 회전가능하게 제2회전축이 각각 삽결되며, 일단에는 연동베벨기어가 각각 축설된 다수개의 연동부와; 상기 고정부의 일측면 중심에서 일측방으로 돌설되는 제3회전축과; 상기 연동부의 다수개의 연동베벨기어와 치합되도록 제3회전축에 회전가능하게 외감결합되는 구동베벨기어와; 상기 구동베벨기어의 타단에 볼팅결합되어 구동베벨기어를 회전시키도록 된 손잡이와; 상기 연동부의 제2회전축 타단에 결합되는 구동나사부에 체결되는 나사공이 형성되며, 구동나사부의 회전방향에 따라 가압롤러의 하부로 승강하도록 된 잠금쇠와; 상기 잠금쇠의 타단이 가압롤러의 하부로 진입하는 길이에 따라 개폐부재가 관플랜지에 밀착되도록 하기 위해 잠금쇠의 타단 일단면이 다단으로 면취된 밀착부와; 상기 잠금쇠가 가이드공으로 관통되게 하여 잠금쇠가 직선왕복운동하도록 개폐부재의 전면에 결합되는 가이드브라켓과; 상기 개폐부재의 일측면에 밀착되도록 밀착면을 가지며 잠금쇠의 일단에 결합되는 회전방지부재를 포함한다.And, the opening and closing means of the opening and closing member is coupled to one side of the linear opening and closing member leading to the imaginary line to the pressure roller and the center point at a position spaced a predetermined distance from the center of one side of the opening and closing, a plurality of rotations formed Brackets; A plurality of interlocking parts respectively rotatably inserted into the rotatable brackets, one end of which has interlocking bevel gears; A third rotating shaft protruding from one side center of the fixing part to one side; A driving bevel gear rotatably coupled to a third rotating shaft to be engaged with a plurality of interlocking bevel gears of the interlocking part; A handle bolted to the other end of the drive bevel gear to rotate the drive bevel gear; A locking hole which is coupled to a driving screw part coupled to the other end of the second rotating shaft of the interlocking part, and is configured to be lifted to a lower portion of the pressure roller according to the rotation direction of the driving screw part; An adhesive part in which the other end surface of the clamp is chamfered in multiple stages so that the opening / closing member is in close contact with the pipe flange according to the length of the other end of the clamp being pushed into the lower portion of the pressing roller; A guide bracket coupled to the front of the opening / closing member such that the clamp is penetrated by the guide hole so that the clamp is linearly reciprocated; It includes a rotation preventing member having a close contact surface to be in close contact with one side of the opening and closing member is coupled to one end of the clamp.

또한, 상기 가압롤러와 중심점까지 가상의 선으로 이어지는 직선상의 개폐부재 소정위치에 결합되는 'ㄱ'자의 고정브라켓과; 상기 고정브라켓에 상단에 체결되어 승강되는 잠금쇠의 하단에 간섭되도록 하는 스토퍼를 더 포함하는 것이 바람직하다.In addition, the 'b' of the fixed bracket coupled to a predetermined position of the linear opening and closing member leading to the virtual line to the pressure roller and the center point; It is preferable to further include a stopper to be coupled to the upper end of the fixing bracket to interfere with the lower end of the lifting clamp.

이하, 본 발명의 구성 및 작용을 첨부된 도면 도 2와 도 3을 참조하여 설명하면 다음과 같으며, 여기서, 도 3은 구동베벨기어(108)와 손잡이의 도시를 생략한 것이다.Hereinafter, the configuration and operation of the present invention will be described with reference to FIGS. 2 and 3 as follows, where FIG. 3 omits the illustration of the driving bevel gear 108 and the handle.

원자로 빌딩내의 이송관(1) 일단에 형성된 관플랜지(2)에는 이 관플랜지(2)보다 비교적 좁은 폭의 면을 가지는 링형상의 고정부재(101)를 도시된 바와 같이 볼트(117)로 볼팅결합시킨다.In the tube flange 2 formed at one end of the transfer pipe 1 in the reactor building, a bolt-shaped 117 is bolted to the ring-shaped fixing member 101 having a surface having a relatively narrower width than the tube flange 2. Combine.

여기서, 상기한 고정부재(101)는 관플랜지(2)에 결합된 상태에서 하술하는 개폐부재(104)가 관플랜지(2)에 결합될 수 있도록 하는 것이므로, 개폐부재(104)의 개폐작업시 볼트(117)를 해체하는 작업은 할 필요가 없다.Here, since the fixing member 101 is to be coupled to the tube flange 2, the opening and closing member 104 described below in the state coupled to the tube flange (2), during the opening and closing operation of the opening and closing member 104 There is no need to dismantle the bolt 117.

상기한 고정부재(101)는 이송관(1)의 중공부(1a)보다 비교적 큰 중공부(101a)를 가지며, 이송관(1)과 고정부재(101)가 결합된 상태에서는 관플랜지(2)와 고정부재(101)는 도 2에 도시된 바와 같이 다단의 단면형상을 갖게 된다.The fixing member 101 has a hollow portion 101a that is relatively larger than the hollow portion 1a of the conveying tube 1, and the tube flange 2 is in a state in which the conveying tube 1 and the fixing member 101 are coupled to each other. ) And the fixing member 101 has a multi-stage cross-sectional shape as shown in FIG.

또한, 상기 관플랜지(2)의 일측면에는 한 쌍의 롤러브라켓(102)이 돌설되며, 이 롤러브라켓(102)은 원주방향(방사상)으로 다수개 형성되는 바, 상기 롤러브라켓(102)에는 가압롤러(103)가 제1회전축(103a)에 의하여 회전가능하게 각각 결합된다.In addition, a pair of roller brackets 102 protrude from one side of the pipe flange 2, and a plurality of roller brackets 102 are formed in a circumferential direction (radial), and the roller brackets 102 The pressure roller 103 is rotatably coupled to each other by the first rotation shaft 103a.

이때, 상기 가압롤러(103)는 고정부재(101)의 일측면과 소정거리 이격된 상태로 결합되어 하술하게 될 잠금쇠(111)가 고정부재(101)와 롤러브라켓(102) 사이로 삽입될 수 있게 한다.At this time, the pressing roller 103 is coupled to be spaced apart from one side of the fixing member 101 by a predetermined distance so that the clamp 111 to be described below can be inserted between the fixing member 101 and the roller bracket 102. do.

한편, 상기 고정부재(101)의 중공부에 삽입되어 관플랜지(2)의 일측면에 밀착됨으로써, 이송관(1)을 폐쇄하도록 된 개폐부재(104)는, 타측면에 패킹(104a)(실(seal))이 도 2와 같이 원주방향으로 함입되어 있으며, 개폐부재(104)의 일측면 중심점으로부터 소정거리 이격된 위치에서 가압롤러(103)와 중심점까지 가상의 선으로 이어지는 직선상에 도 3에 도시된 바와 같이 회전공(105a)(부싱)이 형성된 다수개의 회전브라켓(105)을 볼팅결합시키되, 가압롤러(103)와 대응되도록 원주방향으로 다수개 결합시킨다.On the other hand, the opening and closing member 104 is inserted into the hollow portion of the fixing member 101 to be in close contact with one side of the pipe flange (2), the closing member 104 to close the transfer pipe 1, the packing 104a ( A seal is recessed in the circumferential direction as shown in FIG. As shown in FIG. 3, the plurality of rotating brackets 105 having the rotating holes 105a (bushings) are bolted and coupled to each other in a circumferential direction so as to correspond to the pressure roller 103.

그리고, 상기 회전브라켓(105)에는 연동부(106)가 결합되는 바, 회전공(105a)에는 제2회전축(106a)을 회전가능하게 삽결하되, 중심점을 향하는 제2회전축(106a)의 일단에는 연동베벨기어(106b)가 배치되도록 하며, 원주방향으로 다수개 결합된 회전브라켓(105)에는 도 3에 도시된 바와 같이 각각 연동부(106)를 결합시킨다.And, the interlocking portion 106 is coupled to the rotary bracket 105, the rotary hole 105a is rotatably inserted into the second rotary shaft 106a, one end of the second rotary shaft 106a toward the center point The interlocking bevel gear 106b is disposed, and the interlocking portions 106 are coupled to the rotating brackets 105 coupled to the circumferential direction, respectively, as shown in FIG. 3.

한편, 상기 고정부재(101)의 일측면 중심에는 일측방으로 제3회전축(107)이 돌설되며, 이 제3회전축(107)에는 구동베벨기어(108)가 베어링(118)과 함께 회전가능하게 외감되는 바, 상기 구동베벨기어(108)는 도 2에 도시된 바와 같이 원주방향으로 다수개 배치된 연동부(106)의 연동베벨기어(106b)와 치합된다.On the other hand, the third rotation shaft 107 protrudes in one side in the center of one side of the fixing member 101, the driving bevel gear 108 is rotatable with the bearing 118 in the third rotation shaft 107 As shown in FIG. 2, the driving bevel gear 108 is engaged with the interlocking bevel gear 106b of the interlocking part 106 arranged in circumferential direction.

아울러, 상기 구동베벨기어(108)를 회전시킬 수 있도록 구동베벨기어(108)의 타단에는 손잡이(109)가 볼팅결합는 바, 본 발명에서는 손잡이(109)의 형상 및 모양을 한정하지 않는다.In addition, the handle 109 is bolted to the other end of the driving bevel gear 108 to rotate the driving bevel gear 108, in the present invention does not limit the shape and shape of the handle 109.

여기서, 연동부(106)와 구동베벨기어(108)의 외부노출을 막기 위해 마감캡(도시하지 않음)이 채택결합될 수도 있으나 이는 선택적인 것으로 본 발명의 목적달성과 관계가 없으므로 그 도시와 설명을 생략하기로 한다.Here, a closing cap (not shown) may be adopted to prevent the external exposure of the interlocking portion 106 and the driving bevel gear 108, but this is optional and does not relate to achieving the object of the present invention and description thereof. Will be omitted.

한편, 상기 연동부(106)의 제2회전축(106a) 타단(가압롤러(103) 방향)에는 나사산이 형성된 소정길이의 구동나사부(110)를 결합시키고, 구동나사부(110)의 회전방향에 따라 개폐부재(104)의 중심점과 가압롤러(103)의 방향 중 어느 하나로 승강하도록 된 잠금쇠(111)를 구동나사부(110)의 타단에 체결하며, 여기서, 상기 잠금쇠(111)의 일단에는 구동나사부(110)에 체결되는 나사공(111a)이 소정깊이로 형성되어 있음은 물론이다.On the other hand, the other end of the second rotation shaft (106a) of the interlocking portion 106 (the direction of the pressing roller 103) is coupled to the drive screw unit 110 of a predetermined length formed with a thread, according to the rotation direction of the drive screw unit 110 A fastener 111 which is to be elevated in one of the center point of the opening and closing member 104 and the direction of the pressure roller 103 is fastened to the other end of the driving screw part 110, wherein one end of the fastener 111 is a driving screw part ( Of course, the screw holes 111a fastened to the 110 are formed to have a predetermined depth.

그리고, 상기 잠금쇠(111)가 구동나사부(110)에 의하여 가압롤러(103)의 하부로 진입하게 될 경우, 가압롤러(103)로 진입하게 됨에 따라 개폐부재(104)가 관플랜지(2)에 밀착되도록 하기 위해 잠금쇠(111)의 타단에는 도 2에 도시된 바와 같이 일단면이 다단으로 면취된 밀착부(112)를 형성하고, 끝단면은 소정의 각도로 경사면을 형성하여 가압롤러(103)의 하부로 유도가 용이하게 하는 것이 바람직하다.In addition, when the clamp 111 enters the lower portion of the pressure roller 103 by the driving screw part 110, the opening and closing member 104 enters the pressure roller 103 and the opening and closing member 104 is connected to the pipe flange 2. In order to be in close contact with the other end of the clamp 111 to form a close contact portion 112 chamfered in one end surface in multiple stages, as shown in Figure 2, the end surface forms an inclined surface at a predetermined angle to the pressure roller 103 It is desirable to facilitate the induction to the bottom of.

여기서, 상기 잠금쇠(111)가 개폐부재(104)와 가압롤러(103)측으로 직선왕복운동하며, 가압롤러(103)에 의해 가압될 때, 개폐부재(104)가 관플랜지(2)측으로 밀착되도록 하기 위해서는 잠금쇠(111)를 고정하여야 하는 바, 잠금쇠(111)와 개폐부재(104) 사이에는 각각 가이드브라켓(113)을 볼팅결합시켜 상기 잠금쇠(111)가 가이드브라켓(113)의 가이드공(113a)에 관통되도록 함으로써, 잠금쇠(111)에 작용하는 가압력이 개폐부재(104)에 전달되도록 한다.Here, when the clamp 111 is a linear reciprocating motion toward the opening and closing member 104 and the pressure roller 103, and when pressed by the pressure roller 103, the opening and closing member 104 is in close contact with the tube flange (2) side. In order to fix the fasteners 111, the fasteners 111 and the opening and closing member 104 are bolted to the guide brackets 113, respectively, so that the fasteners 111 are guide holes 113a of the guide brackets 113. By passing through), the pressing force acting on the clamp 111 is transmitted to the opening and closing member 104.

여기서, 본 발명은 가이드브라켓(113)이 개폐부재(104)의 일측면에 볼팅결합되는 것을 예시하였으나, 본 발명에 의한 가이드브라켓(113)은 개폐부재(104)와 일체일 수도 있으며, 별개체일 경우 개폐부재(104)의 일측면에 볼팅될 수도 있으며, 개폐부재(104)의 외경면으로부터 'ㅜ'자 가이드홈(도시하지 않음)을 형성하고, 여기에 가이드브라켓(113)이 삽입되어 볼팅결합되게 할 수도 있는 것으로, 이것은 본 발명의 목적을 달성하기 위한 하나의 방편이므로 다양하게 채택될 수 있는 것이고, 본 발명은 잠금쇠(111)를 가이드함과 동시에 잠금쇠(111)에 작용하는 가압력이 개폐부재(104)로 전달되게 하면 되는 것이므로 이러한 다양한 방법의 채택은 본 발명의 권리범위에 해당된다고 보아야 될 것이다.Here, the present invention has been illustrated that the guide bracket 113 is bolted to one side of the opening and closing member 104, the guide bracket 113 according to the present invention may be integral with the opening and closing member 104, a separate body In one case it may be bolted to one side of the opening and closing member 104, from the outer diameter surface of the opening and closing member 104 to form a 'tt' shaped guide groove (not shown), the guide bracket 113 is inserted here It may be to be bolted, this is one way to achieve the object of the present invention can be adopted in various ways, the present invention guides the clamping 111 and at the same time the pressing force acting on the clamping 111 Since it is to be delivered to the opening and closing member 104 it will be seen that the adoption of these various methods fall within the scope of the present invention.

한편, 상기 잠금쇠(111)의 일단에는 상기 구동나사부(110)의 회전에 따라 잠금쇠(111)가 직선운동함에 있어 나사방향으로 회전하는 것을 방지하기 위하여 회전방지부재(114)를 결합시키는 바, 이 회전방지부재(114)는 개폐부재(104)의 일측면에 밀착되는 편평한 밀착면을 가진다.On the other hand, one end of the clamp 111 is coupled to the anti-rotation member 114 in order to prevent the clamp 111 to rotate in the screw direction in the linear movement according to the rotation of the drive screw unit 110, this The anti-rotation member 114 has a flat contact surface in close contact with one side of the opening and closing member 104.

그리고, 도면중 미 설명된 홀더(119)는 개폐부재(104)를 크레인으로 들어올리거나 이동시킬때 크레인에 연결되는 것으로서 단지 중량체를 운반작업하는 데 필요한 것이다.In addition, the holder 119, which is not described in the drawing, is connected to a crane when lifting or moving the opening and closing member 104 by a crane, which is only necessary for carrying a heavy body.

따라서, 이송관(1)을 개폐하고자 할 경우에는 상술한 바와 같이 고정부재(101)가 관플랜지(2)에 볼팅결합된 상태임을 전제하고, 개폐부재(104)의 홀더(119)를 크레인에 연결하고 개폐부재(104)를 들어올려 고정부재(101)의 중공부에 삽입시켜 관플랜지(2)의 일측면에 밀착시킨다.Therefore, in the case of opening and closing the transfer pipe 1, the holder 119 of the opening / closing member 104 is attached to the crane on the premise that the fixing member 101 is bolted to the pipe flange 2 as described above. Connect and lift the opening and closing member 104 is inserted into the hollow portion of the fixing member 101 to be in close contact with one side of the tube flange (2).

이와 같은 상태에서 작업자가 손잡이(109)를 파지하여 일측 방향으로 회전시키면 구동베벨기어(108)가 일측방향으로 회전시키면서 구동베벨기어(108)에 치합된 다수개의 연동베벨기어(106b)가 동시에 회전하는 바, 이때, 상기 연동부(106)를 고정하는 회전브라켓(105)의 회전공(105a)에 삽결된 제2회전축(106a)이 자회전하면서 구동나사부(110)를 회전시킨다.In this state, when the worker grips the handle 109 and rotates in one direction, the driving bevel gear 108 rotates in one direction while the plurality of interlocking bevel gears 106b engaged with the driving bevel gear 108 rotate simultaneously. At this time, the second rotating shaft 106a inserted into the rotating hole 105a of the rotating bracket 105 fixing the linking unit 106 rotates the driving screw unit 110 while self-rotating.

따라서, 상기 구동나사부(110)는 잠금쇠(111)의 나사공(111a)에 체결된 상태 이므로 구동나사부(110)가 회전하게 되면 잠금쇠(111)는 구동나사부(110)의 나사산을 따라 가압롤러(103)측으로 승강하게 된다.Therefore, since the driving screw part 110 is fastened to the screw hole 111a of the clamping part 111, when the driving screw part 110 is rotated, the clamping part 111 is pressurized along the thread of the driving screw part 110. To the 103) side.

그리고, 상기 잠금쇠(111)의 끝단에 다단으로 면취된 밀착부(112)는 가압롤러(103)의 하부에 밀착되면서 점점 승강하게 되어 가압롤러(103)를 가압하게 되는 바, 상기 가압롤러(103)는 회전이 가능하지만 롤러브라켓(102)에 고정된 상태이므로 일측방향으로 이동은 불가능하다.And, the close contact portion 112 chamfered to the end of the clamp 111 is gradually pushed up and down while being in close contact with the lower portion of the pressure roller 103 to press the pressure roller 103, the pressure roller 103 ) Is rotatable, but because it is fixed to the roller bracket 102, movement in one direction is impossible.

따라서, 상기 가압롤러(103)를 가압하는 잠금쇠(111)의 가압력은 잠금쇠(111)가 직선 왕복운동하도록 고정하는 가이드브라켓(113)에 반사작용하게 되며, 가이드브라켓은 개폐부재(104)에 결합된 상태이므로, 결국, 잠금쇠(111)의 가압력은 개폐부재(104)를 이송관(1)측으로 가압하는 힘으로 작용하게 되므로 잠금쇠(111)가 승강할수록 개폐부재(104)는 이송관(1)의 관플랜지(2)에 더욱 밀착되는 것이다.Therefore, the pressing force of the clamp 111 to press the pressing roller 103 is reflected to the guide bracket 113 for fixing the clamp 111 to reciprocate linearly, the guide bracket is coupled to the opening and closing member 104 Since it is in a state, eventually, the pressing force of the clasp 111 acts as a force for pressing the opening and closing member 104 toward the conveying pipe 1 side, so that the clasp 111 is raised and lowered so that the opening and closing member 104 is the conveying pipe 1. Will be in close contact with the tube flange (2).

여기서, 상기 잠금쇠(111)가 승강할 때에는 회전방지부재(114)의 편평한 밀착면이 개폐부재(104)의 일측면에 밀착된 상태이므로 잠금쇠(111)가 회전되려 하지 않고 가이드브라켓(113)의 가이드공(113a)을 따라 그대로 승강하게 된다.Here, when the clamp 111 is raised and lowered, the flat contact surface of the rotation preventing member 114 is in close contact with one side of the opening and closing member 104, so that the clamp 111 is not rotated and the guide bracket 113 does not rotate. Ascending and descending along the guide hole (113a).

아울러, 상기 가압롤러(103)와 중심점까지 가상의 선으로 이어지는 직선상의 개폐부재(104) 소정위치에는 'ㄱ'자의 고정브라켓(115)을 결합하는 바, 잠금쇠(111)가 완전히 승강하여 멈추었을 때, 회전방지부재(114)가 위치되는 곳의 하부의 개폐부재(104) 일측면에 고정브라켓(115)을 결합시키고, 이 고정브라켓(115)의 상단에 스토퍼(116)를 체결시켜 승강된 잠금쇠(111)가 자칫 하 강하게 될 경우 회전방지부재(114)와 스토퍼(116)가 간섭되도록 하여 하강을 방지하도록 하는 것이 바람직하다.In addition, the pressing roller 103 and the bar opening and closing member 104 in a straight line leading to the virtual point to the predetermined point to the bar of the 'b' to combine the fixing bracket 115, the stopper 111 is completely lifted and stopped At this time, the fixing member 115 is coupled to one side of the opening / closing member 104 at the bottom of the anti-rotation member 114, and the stopper 116 is fastened to the upper end of the fixing bracket 115 to be elevated. When the clamp 111 is lowered itself, it is preferable to prevent the rotation preventing member 114 and the stopper 116 to interfere to prevent the falling.

반대로, 상기 개폐부재(104)를 고정부재(101) 및 관플랜지(2)로부터 탈거하고자 할 경우에는 상기한 스토퍼(116)의 체결상태를 풀어서 회전방지부재(114)와의 간섭을 해제하고, 손잡이(109)를 타측방향으로 돌리면 구동베벨기어(108)와 연동베벨기어(106b) 및 구동나사부(110)에 의해 잠금쇠(111)가 하강하면서 가압롤러(103)를 가압하는 힘을 해제하게 되며, 이때, 개폐부재(104)는 관플랜지(2)로부터 해체될 수 있게 된다.On the contrary, when the opening member 104 is to be removed from the fixing member 101 and the pipe flange 2, the stop state of the stopper 116 is released to release the interference with the rotation preventing member 114, and the handle By turning 109 in the other direction, the locking bevel 111 is lowered by the driving bevel gear 108, the interlocking bevel gear 106b, and the driving screw part 110 to release the force to pressurize the pressure roller 103. At this time, the opening and closing member 104 can be disassembled from the tube flange (2).

상기한 바와 같이 본 발명은 이송관을 개폐하기 위해서 매번 다수개의 볼트를 체결/해체하는 번거로움 없이 손잡이를 회전시켜 잠금쇠가 가압롤러를 가압하여 개폐부재가 관플랜지에 밀착되도록 함으로써, 이송관의 개폐에 소요되는 작업시간을 최소화할 수 있게 되었으며, 이에 따라, 작업자가 방사능에 노출되는 시간을 최소화 함으로써, 방사능 피폭에 의한 안전사고를 사전에 예방하고 작업의 효율성을 극대화할 수 있는 효과를 가진다.As described above, the present invention rotates the handle without the hassle of fastening / disassembling a plurality of bolts each time in order to open and close the transfer pipe so that the clasp presses the pressure roller so that the opening and closing member is in close contact with the pipe flange. It is possible to minimize the work time required for this, and accordingly, by minimizing the time the worker is exposed to radiation, it has the effect of preventing safety accidents due to radiation exposure in advance and maximizing the efficiency of the work.

Claims (3)

원자로 빌딩내부로 핵연료 빌딩에 저장된 핵연료를 이송하는 이송관(1)의 끝단을 개폐하는 핵연료 이송관용 블라인드 플랜지에 있어서,In the blind flange for the fuel transfer pipe for opening and closing the end of the transfer pipe (1) for transferring the fuel stored in the fuel building into the reactor building, 상기 이송관(1) 일단에 형성된 관플랜지(2)보다 좁은 폭의 면을 가지는 링형상을 가지고 관플랜지(2)에 볼팅결합되며, 일측면으로 돌설된 한 쌍의 롤러브라켓(102)이 원주방향으로 다수개 형성되고, 이 롤러브라켓(102)에는 관플랜지(2)의 일측면으로부터 일정거리 이격되게 가압롤러(103)가 제1회전축(103a)에 의해 회전가능하게 결합되며, 이송관(1)의 중공부(1a)보다 큰 중공부(101a)가 형성된 고정부재(101)와;A pair of roller brackets 102 circumferentially bolted to the tube flange 2 having a ring shape having a narrower surface than the tube flange 2 formed at one end of the transfer tube 1, and protruding to one side A plurality of rollers are formed in the direction, and the roller bracket 102 is rotatably coupled by the first rotating shaft 103a to the pressure roller 103 so as to be spaced a predetermined distance from one side of the pipe flange 2, and the transfer pipe ( A fixing member 101 having a hollow portion 101a larger than the hollow portion 1a of 1); 상기 고정부재(101)의 중공부(101a)에 삽입되어 관플랜지(2)에 밀착되며, 타측면에 패킹(104a)이 원주방향으로 함입된 개폐부재(104)와;An opening / closing member 104 inserted into the hollow portion 101a of the fixing member 101 to be in close contact with the pipe flange 2 and having the packing 104a recessed in the circumferential direction on the other side thereof; 상기 개폐부재(104)를 고정부재(101)의 중공부(101a)에서 관플랜지(2) 일측면에 개폐시키기 위한 개폐부재(104)의 개폐수단을 포함하는 것을 특징으로 하는 핵연료 이송관용 블라인드 플랜지.Blind flange for nuclear fuel transport pipe, characterized in that it comprises an opening and closing means of the opening and closing member 104 for opening and closing the opening and closing member 104 in the hollow portion 101a of the fixing member 101 to one side of the tube flange (2). . 제1항에 있어서,The method of claim 1, 상기 개폐부재(104)의 개폐수단은,Opening and closing means of the opening and closing member 104, 상기 개폐부재(104)의 일측면 중심으로부터 이격된 위치에서 가압롤러(103)와 중심점까지 가상의 선으로 이어지는 직선상의 개폐부재(104) 일측면에 결합되며, 회전공(105a)이 형성된 다수개의 회전브라켓(105)과;A plurality of rotary holes 105a are coupled to one side of the linear opening / closing member 104 leading to an imaginary line from the pressure roller 103 to the center point at a position spaced from the center of one side of the opening and closing member 104. A rotating bracket 105; 상기 회전브라켓(105)에 회전가능하게 제2회전축(106a)이 각각 삽결되며, 일단에는 연동베벨기어(106b)가 각각 축설된 다수개의 연동부(106)와;A plurality of interlocking parts 106 each rotatably inserted into the rotation bracket 105, and one end of which an interlocking bevel gear 106b is formed; 상기 고정부재(101)의 일측면 중심에서 일측방으로 돌설되는 제3회전축(107)과;A third rotary shaft 107 protruding from one side center of the fixing member 101 to one side; 상기 연동부(106)의 다수개의 연동베벨기어(106b)와 치합되도록 제3회전축(107)에 회전가능하게 외감결합되는 구동베벨기어(108)와;A driving bevel gear (108) rotatably coupled to the third rotation shaft (107) to be engaged with a plurality of interlocking bevel gears (106b) of the interlocking portion (106); 상기 구동베벨기어(108)의 타단에 볼팅결합되어 구동베벨기어(108)를 회전시키도록 된 손잡이(109)와;A handle 109 bolted to the other end of the drive bevel gear 108 to rotate the drive bevel gear 108; 상기 연동부(106)의 제2회전축(106a) 타단에 결합되는 구동나사부(110)에 체결되는 나사공(111a)이 형성되며, 구동나사부(110)의 회전방향에 따라 가압롤러(103)의 하부로 승강하도록 된 잠금쇠(111)와;A screw hole 111a is fastened to the driving screw part 110 coupled to the other end of the second rotating shaft 106a of the interlocking part 106, and the pressure roller 103 is formed according to the rotational direction of the driving screw part 110. A catch 111 to be lifted downward; 상기 잠금쇠(111)의 타단이 가압롤러(103)의 하부로 진입하는 길이에 따라 개폐부재(104)가 관플랜지(2)에 밀착되도록 하기 위해 잠금쇠(111)의 타단 일단면이 다단으로 면취된 밀착부(112)와;One end surface of the other end of the clamp 111 is chamfered in multiple stages so that the opening and closing member 104 is in close contact with the pipe flange 2 according to the length of the other end of the clamp 111 entering the lower portion of the pressure roller 103. An adhesion part 112; 상기 잠금쇠(111)가 가이드공(113a)으로 관통되게 하여 잠금쇠(111)가 직선왕복운동하도록 개폐부재(104)의 전면에 결합되는 가이드브라켓(113)과;A guide bracket 113 coupled to the front surface of the opening / closing member 104 such that the clasp 111 penetrates into the guide hole 113a so that the clasp 111 moves in a straight reciprocating motion; 상기 개폐부재(104)의 일측면에 밀착되도록 밀착면을 가지며 잠금쇠(111)의 일단에 결합되는 회전방지부재(114)를 포함하는 것을 특징으로 하는 핵연료 이송관용 블라인드 플랜지.Blind flange for a nuclear fuel transfer pipe, characterized in that it comprises a rotation preventing member 114 having a close contact with one side of the opening and closing member 104 and coupled to one end of the clamp (111). 제2항에 있어서,The method of claim 2, 상기 가압롤러(103)와 중심점까지 가상의 선으로 이어지는 직선상의 개폐부재(104)에 결합되는 'ㄱ'자의 고정브라켓(115)과;A 'b' fixing bracket 115 coupled to the pressurizing roller 103 and a linear opening / closing member 104 leading to a virtual line up to a center point; 상기 고정브라켓(115) 상단에 체결되어 승강되는 잠금쇠(111)의 하단에 간섭되도록 하는 스토퍼(116)를 더 포함하는 것을 특징으로 핵연료 이송관용 블라인드 플랜지.And a stopper (116) for interfering with the lower end of the fastening bracket (111) which is fastened to the upper end of the fixing bracket (115).
KR1020040066737A 2004-08-24 2004-08-24 Blind flange for nuclear fuel transportation tube KR100599817B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040066737A KR100599817B1 (en) 2004-08-24 2004-08-24 Blind flange for nuclear fuel transportation tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040066737A KR100599817B1 (en) 2004-08-24 2004-08-24 Blind flange for nuclear fuel transportation tube

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0024177U Division KR200369283Y1 (en) 2004-08-24 2004-08-24 Blind flange for nuclear fuel transportation tube

Publications (2)

Publication Number Publication Date
KR20060018385A KR20060018385A (en) 2006-03-02
KR100599817B1 true KR100599817B1 (en) 2006-07-14

Family

ID=37126020

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040066737A KR100599817B1 (en) 2004-08-24 2004-08-24 Blind flange for nuclear fuel transportation tube

Country Status (1)

Country Link
KR (1) KR100599817B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101128641B1 (en) 2010-12-31 2012-03-26 한국수력원자력 주식회사 Blind flange guard and accommodating apparatus of fuel transfer tube in nuclear power plant

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101141778B1 (en) * 2010-10-28 2012-05-03 한국전력기술 주식회사 Nuclear fuel transfer tube blind flange clamping device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07243565A (en) * 1994-03-08 1995-09-19 Power Reactor & Nuclear Fuel Dev Corp Flange type remotely fixed pipe fitting
KR960702085A (en) * 1994-02-23 1996-03-28 클라우드-요헨 라트-니겔·귄터 볼프 SLIDE VALVE MOUNTED ON ROLLERS.IN PARTICULATR A GOGGLE VALVE
KR19980040097A (en) * 1996-11-29 1998-08-17 죤 에이취. 뮬홀랜드 Remote Closure for Fuel Transfer Tubes
KR200286856Y1 (en) 2002-05-17 2002-08-27 주식회사 무진기연 Automatic open-close apparatus of blind flange for nuclear fuel forwarding tube for nuclear power plant

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR960702085A (en) * 1994-02-23 1996-03-28 클라우드-요헨 라트-니겔·귄터 볼프 SLIDE VALVE MOUNTED ON ROLLERS.IN PARTICULATR A GOGGLE VALVE
JPH07243565A (en) * 1994-03-08 1995-09-19 Power Reactor & Nuclear Fuel Dev Corp Flange type remotely fixed pipe fitting
KR19980040097A (en) * 1996-11-29 1998-08-17 죤 에이취. 뮬홀랜드 Remote Closure for Fuel Transfer Tubes
KR200286856Y1 (en) 2002-05-17 2002-08-27 주식회사 무진기연 Automatic open-close apparatus of blind flange for nuclear fuel forwarding tube for nuclear power plant

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101128641B1 (en) 2010-12-31 2012-03-26 한국수력원자력 주식회사 Blind flange guard and accommodating apparatus of fuel transfer tube in nuclear power plant

Also Published As

Publication number Publication date
KR20060018385A (en) 2006-03-02

Similar Documents

Publication Publication Date Title
US6252922B1 (en) Method of handling a nuclear reactor and an apparatus used in the handling method
KR100599817B1 (en) Blind flange for nuclear fuel transportation tube
CN113803500A (en) High-magnification gear valve based on rapid sealing of large-flow pipeline
KR200369283Y1 (en) Blind flange for nuclear fuel transportation tube
CN111306398B (en) Water conservancy pipeline patching device convenient to installation
CN104806756A (en) Wedge block type quick opening blind plate
CN113648962A (en) Stirring mixing reaction equipment for chemical materials
US5169593A (en) Control rod drive handling tools for nuclear reactor
CN102951385B (en) Manhole device of storage tank
KR101248809B1 (en) link type locking device
KR200471865Y1 (en) Apparatus for preventing the bending of piston rod of plugging machine for stopping gas flowing in gas pipe
CN113666056B (en) Embedded scraper conveyor chain plate component
CN203127538U (en) Manhole device for storage tank
US20110088353A1 (en) Docking device comprising two coupling closures for the environmentally sealed transfer of bulk material, having at least one locking unit
CN113731252A (en) Drum mixer
CN209877612U (en) Novel rotary kiln convenient to feeding
CN210623625U (en) Large-scale high-temperature high-vacuum double-gate valve
CN115581942A (en) Step tunnel type leacher
CN208764360U (en) The plug-type headstock gear of turntable for subdivision annular fast opening blind
CN208007955U (en) A kind of clear device for coal for apron feeder
CN113231678A (en) Milling machine for machining spline shaft and machining process of milling machine
CN110085332A (en) A kind of guiding device of reactor control rod beam
CN204802437U (en) Light -duty concrete bucket of eccentric unloading
KR102280069B1 (en) Transfer device with extended life
CN113858228B (en) Lock disassembling clamp, robot and lock disassembling system

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130103

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140425

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20150724

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170829

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20180725

Year of fee payment: 13