KR100470067B1 - An apparatus for crushing the blocking brick using the insight of blow pipe in furnace - Google Patents

An apparatus for crushing the blocking brick using the insight of blow pipe in furnace Download PDF

Info

Publication number
KR100470067B1
KR100470067B1 KR10-2002-0079004A KR20020079004A KR100470067B1 KR 100470067 B1 KR100470067 B1 KR 100470067B1 KR 20020079004 A KR20020079004 A KR 20020079004A KR 100470067 B1 KR100470067 B1 KR 100470067B1
Authority
KR
South Korea
Prior art keywords
pressure water
inner hole
sealing
pipe
blast furnace
Prior art date
Application number
KR10-2002-0079004A
Other languages
Korean (ko)
Other versions
KR20040051144A (en
Inventor
정진식
김홍곤
이태훈
Original Assignee
주식회사 포스코
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 포스코 filed Critical 주식회사 포스코
Priority to KR10-2002-0079004A priority Critical patent/KR100470067B1/en
Publication of KR20040051144A publication Critical patent/KR20040051144A/en
Application granted granted Critical
Publication of KR100470067B1 publication Critical patent/KR100470067B1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B02CRUSHING, PULVERISING, OR DISINTEGRATING; PREPARATORY TREATMENT OF GRAIN FOR MILLING
    • B02CCRUSHING, PULVERISING, OR DISINTEGRATING IN GENERAL; MILLING GRAIN
    • B02C23/00Auxiliary methods or auxiliary devices or accessories specially adapted for crushing or disintegrating not provided for in preceding groups or not specially adapted to apparatus covered by a single preceding group
    • B02C23/18Adding fluid, other than for crushing or disintegrating by fluid energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Food Science & Technology (AREA)
  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

본 발명은 고로의 블로우파이프가 배치되는 풍구를 밀봉하는 밀봉내화물을 파쇄하는 장치에 관한 것이다.The present invention relates to an apparatus for crushing a sealed refractory sealing a tuyere in which a blowpipe of a blast furnace is disposed.

본 발명은 관찰구(131)의 단부에 형성된 수나사부(131)와 나사결합되도록 선단내주면에 암나사부(11a)를 형성하고, 몸체(11)중앙을 관통하는 내부공(12)을 개폐하는 밸브부재(12)를 길이중앙에 갖추며, 후단에 퀵조인트(40)의 암부(40a)가 일체로 장착된 중공원통형 연결부(10); 상기 퀵조인트(40)의 암부(40a)와 조립되는 숫부(40b)가 선단에 일체로 장착되고, 몸체(21)중앙을 관통하는 내부공(22)의 내주면에 밀봉용 오링(23)이 장착되어 상기 연결부(10) 후단에 조립되는 중공원통형 실링부(20) 및, 상기 실링부(20)의 내부공(22)과 상기 연결부(10)의 내부공(22)내로 수평하게 삽입되는 일정길이의 고압수분사파이프(31)를 갖추고, 상기 고압수분사파이프(31)의 후단과 연결관(33)을 매개로 연결되며, 고압의 분사수가 공급되는 고압수라인(34)이 연결되는 분사건(32)을 갖추어 상기 풍구(120)내부를 밀폐하는 밀봉내화물(170)을 고압수로서 파쇄하는 고압수분사부(30)를 포함하여 구성된다.The present invention forms a female threaded portion (11a) on the inner peripheral surface of the front end to be screwed with the male screw portion 131 formed at the end of the observation port 131, the valve for opening and closing the inner hole 12 through the center of the body (11) A hollow-cylindrical cylindrical connection portion 10 having a member 12 at the center of length and having an arm 40a of the quick joint 40 integrally mounted at a rear end thereof; The male part 40b assembled with the arm part 40a of the quick joint 40 is integrally mounted at the tip, and the sealing O-ring 23 is mounted on the inner circumferential surface of the inner hole 22 passing through the center of the body 21. And a predetermined length that is horizontally inserted into the hollow hollow cylindrical sealing part 20 and the inner hole 22 of the sealing part 20 and the inner hole 22 of the connecting part 10, which are assembled at the rear end of the connecting part 10. Equipped with a high-pressure water spray pipe 31 of the injection gun connected to the rear end of the high-pressure water spray pipe 31 and the connection pipe 33, the high-pressure water line 34 is supplied with high-pressure spray water And a high pressure water injection part 30 for crushing the sealed refractory 170 sealing the inside of the tuyere 120 as high pressure water.

본 발명에 의하면, 노벽보수작업동안 풍구의 내부통로를 밀폐하는 밀봉내화물을 고로 블로우파이프의 관찰구를 통하여 수평하게 삽입되는 고압수분사파이프의 고압수로서 작업자의 작업부하없이 완벽하게 파쇄하여 파쇄효율성을 높일 수 있다.According to the present invention, as the high-pressure water of the high-pressure water injection pipe is inserted horizontally through the observation port of the blast furnace blow pipe, the sealing refractory sealing the inner passage of the tuyere during the repair of the furnace wall completely crushing efficiency without the operator's work load Can increase.

Description

고로 블로우 파이프의 관찰구를 이용한 밀봉내화물 파쇄장치{AN APPARATUS FOR CRUSHING THE BLOCKING BRICK USING THE INSIGHT OF BLOW PIPE IN FURNACE}Sealed refractory shredding device using blast furnace blow pipe observation port {AN APPARATUS FOR CRUSHING THE BLOCKING BRICK USING THE INSIGHT OF BLOW PIPE IN FURNACE}

본 발명은 고로의 블로우파이프가 배치되는 풍구를 밀봉하는 밀봉내화물을 파쇄하는 장치에 관한 것으로, 보다 상세히는 노벽보수작업동안 풍구의 내부통로를 밀폐하는 밀봉내화물을 고로 블로우파이프의 관찰구를 통하여 수평하게 삽입되는 고압수분사파이프의 고압수로서 작업자의 작업부하없이 완벽하게 파쇄하여 파쇄효율성을 높일 수 있는 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치에 관한 것이다.The present invention relates to a device for crushing the sealed refractory to seal the tuyere in which the blowpipe of the blast furnace is disposed, more specifically, through the observation port of the blast furnace blowpipe through the sealed refractory to seal the inner passage of the tuyere during furnace wall repair work The high pressure water of the high-pressure water spray pipe is inserted into a sealed refractory crushing device using the observation hole of the blast furnace blow pipe that can be completely crushed without the workload of the operator to increase the crushing efficiency.

일반적으로 제철소의 고로조업은 도 1에 도시한 바와같이, 고로(100)상부에 설치된 장입장치(미도시)를 이용하여 철광석과 코크스(COKE)를 번갈아 층상으로 장입하고, 상기 고로(100)의 하부로부터는 열풍로(미도시)에서 데워진 열풍을 상기 고리(100)의 하부외주면에 일정간격을 두고 복수개 장착된 풍구(120)를 통하여 불어넣게 되면, 상기 고로(100)내부에 장입된 철광석이 환원되어 용선 및 슬래그를제조하는 것이다.In general, as shown in FIG. 1, the blast furnace operation of the steel mill alternately loads iron ore and coke into layers using a charging device (not shown) installed on the blast furnace 100 and alternately charges the blast furnace 100. When the hot air heated in the hot stove (not shown) is blown through a plurality of wind holes 120 mounted at a predetermined interval on the lower outer peripheral surface of the ring 100, the iron ore charged in the blast furnace 100 is It is reduced to produce molten iron and slag.

그리고, 대형 고로(100)의 경우 열풍이 공급되는 풍구(120)가 34개, 용선 및 슬래그가 출선되는 출선구(110)가 4개 정도 설치되고, 상기 풍구(120)에는 미분탄을 고로내로 취입하는 미분탄취입라인(140)을 갖는 블로우파이프(130)가 각각 삽입되고, 상기 블로우파이프(130)는 열풍로로부터 고온의 공기인 열풍이 공급되는 환고리형의 송풍환상관(150)으로부터 복수개 분기되는 분기관(151)에 각각 연결구성된다.And, in the case of the large blast furnace 100, 34 air vents 120 to which hot air is supplied, and about 4 outlets 110 to which molten iron and slag are discharged are installed, and the blast holes 120 are blown with pulverized coal into the blast furnace. Blow pipes 130 having a pulverized coal injection line 140 is inserted, respectively, the blow pipes 130 are a plurality of branches from the ring-shaped blow ring pipe 150 is supplied with hot air is hot air from the hot air furnace It is connected to each branch pipe 151 is configured.

이에 따라, 상기 고로(100)내에서 생산된 용선과 슬래그는 2개의 대각선 방향 출선구(110)를 번갈아 가면서 개공하여 연속적으로 노외로 배출하게 되고, 열풍은 상기 송풍환상관(150)에 설치된 블라우파이프(130)가 삽입되는 풍구(120)를 통하여 로내로 공급된다.Accordingly, the molten iron and slag produced in the blast furnace 100 are alternately opened by alternating two diagonal exit ports 110, and continuously discharged to the outside of the furnace, and hot air is blown in the blower pipe 150. The right pipe 130 is supplied into the furnace through the tuyere 120 is inserted.

한편, 상기와 같은 고로(100)의 장수명화를 위해서 고로내부를 보수하는 방법의 일환으로서 노벽을 보수하는 작업은 장시간의 휴풍이 필요하게 되므로 고로의 휴풍직후 상기 고로하부 외주면에 다수개 설치된 각 풍구(120)의 선단은 진흙형태의 옥토인 밀봉내화물를 이용하여 약 200mm 정도 밀폐한다.On the other hand, as part of the method for repairing the interior of the blast furnace for the long life of the blast furnace 100 as described above, the work of repairing the furnace wall requires a long period of rest, so after the absence of the blast furnace, each of the plurality of wind holes installed on the outer peripheral surface of the blast furnace bottom The tip of the 120 is sealed about 200 mm using a sealed refractory material in the form of clay.

이러한 밀봉내화물(170)을 이용한 풍구(120)선단의 밀폐는 노내 코크스의 연소를 방지하고, 노벽을 보수하는 작업시 노내 관찰을 위한 시야를 확보하는 한편, 가스발생을 최소화하여 보수용 스프래이 장치를 보호하기 위한 것이다.The sealing of the tip of the tuyere 120 using the sealed refractory 170 prevents combustion of the coke in the furnace, secures the field of view for the observation in the furnace during the work of repairing the furnace wall, and minimizes the generation of gas, thereby minimizing gas generation. Is to protect.

그리고, 고로내로 열풍을 재송풍하는 작업전 노저의 용융물을 활성화시키고, 원주방향으로의 원활한 가스흐름을 도와 조기에 노열을 확보할 수 있도록출선구(110)의 상부에 위치한 소수의 풍구(120)를 제외한 다수의 풍구(120)의 선단은 옥토인 밀봉내화물(170)로서 견고하게 다져 밀봉한다.In addition, a small number of tuyere 120 located at the upper portion of the outlet 110 to activate the melt of the furnace prior to the operation of re-blowing the hot air into the blast furnace, and to ensure the early heat by helping the smooth gas flow in the circumferential direction. Except for the tip of the plurality of air holes 120 is tightly sealed by octopus sealed refractory 170 is sealed.

이어서, 상기 고로내로의 재송풍개시 후 일정시간이 경과하면, 풍량 4500㎥/Min으로 상당시간 유지하다가 풍량을 2000㎥/Min으로 공급하는 재감풍조업을 실시할 때, 작업자는 1200°이상의 높은 열풍에 직접 노출된 상태에서 일정길이를 갖는 찌름봉을 이용하여 상기 풍구(120)선단을 밀폐하고, 고열에서 소성된 밀봉내화물(170)을 파쇄하는 작업을 고로내부의 노벽을 스프레이보수하는 작업을 수행한 다음, 반드시 필연적으로 수행하였다.Subsequently, when a certain time elapses after the start of re-blowing into the blast furnace, the operator maintains the air volume at 4500 m 3 / Min for a considerable time, and then performs a re-wind operation to supply the air volume at 2000 m 3 / Min. Sealing the tip of the tuyere 120 using a stick rod having a predetermined length in a state directly exposed to the spray, and crushing the sealed refractory material 170 fired at a high temperature to spray repair the furnace wall inside the blast furnace Then, it was necessarily performed.

그러나, 상기와 같이 풍구(120)선단의 밀봉내화물(170)을 고온의 열풍에 노출된 조건에서 수작업으로 파쇄하는 작업시 안전성이 보장되지 않는 문제점을 해결하기 위해서, 대한민국 실용신안 제 1998-25488호에서는 도 2(a)에 도시한 바와 같이 미분탄을 취입하도록 블로우파이프(130)에 경사지게 장착되는 미분탄취입라인(PCI: Pulverized Coal Injection)(140)의 미분탄취입랜스(141)후단에 중공형 소켓(145)을 교체가능하게 장착하고, 상기 소켓(145), 미분탄취입랜스(141)의 내부로 2구경 분사노즐이 단부에 형성된 고압수분사파이프(161)를 갖는 고압수분사기(160)을 설치하였다.However, in order to solve the problem that the safety is not guaranteed during the operation of manually crushing the sealed refractory 170 at the tip of the tuyere 120 exposed to high temperature hot air, Korean Utility Model No. 1998-25488 In Figure 2 (a) as shown in Figure 2 (a) to the inlet of the pulverized coal injection line (141) of the pulverized coal injection line (PCI: Pulverized Coal Injection) (140) which is mounted obliquely to the blow pipe 130 to blow the pulverized coal ( 145 is installed in a replaceable manner, and a high-pressure water sprayer 160 having a high-pressure water spray pipe 161 formed at the end of the socket 145 and the pulverized coal injection lance 141 is installed. .

이에 따라, 상기 블로우파이프(130)의 선단내부를 밀봉하는 밀봉내화물(170)에 상기 고압수분사파이프(161)의 노즐이 근접하도록 상기 고압수분사파이프(161)를 삽입한 상태에서, 고압으로 분사되는 고압수에 의해서 하여 밀봉내화물로서 폐쇄된 풍구(120)선단을 관통하였다.Accordingly, the high pressure water spray pipe 161 is inserted into the sealed refractory 170 sealing the inner end of the blow pipe 130 so that the nozzle of the high pressure water spray pipe 161 is close to the high pressure. The high pressure water sprayed penetrated the end of the tuyere 120 closed as a sealed refractory.

그러나, 상기 종래의 작업방법은 다음과 같은 문제점이 있었다.However, the conventional working method has the following problems.

첫째, 상기 미분탄 취입랜스(141)내에 삽입된 고압수분사파이프(161)를 통한 풍구(120)선단내부의 밀봉내화물(170)을 파쇄하는 작업은 도 2(b)에 도시한 바와같이, 상기 미분탄 취입랜스(140)의 설치각도(Θ)가 54°로 경사져 있기 때문에 이를 통하여 고압의 분사수를 분사하는 범위가 한정적이고, 이로 인하여 상기 밀봉내화물(170)을 완전히 파쇄하는데 한계가 있어 파쇄효율을 저하시켰다.First, the operation of crushing the sealed refractory 170 inside the tip of the tuyere 120 through the high-pressure water injection pipe 161 inserted into the pulverized coal injection lance 141 is as shown in FIG. Since the installation angle Θ of the pulverized coal injection lance 140 is inclined at 54 °, the range of spraying high-pressure jetting water is limited, thereby limiting the crushing of the sealed refractory 170 completely. Lowered.

둘째, 3~4명의 작업자가 현장에서 장시간 동안 직접 수작업으로 상기 밀봉내화물(170)을 파쇄하여 풍구(120)를 관통하는 작업을 수행함과 동시에 또다른 작업자가 상기 풍구(120)의 정반대편, 블로우파이프에 내부관찰이 용이하도록 설치된 관찰구(131)를 통하여 파쇄여부를 수시로 확인해야만 하기 때문에 작업부하가 많이 발생되는 문제점이 있었다.Secondly, three to four workers directly break the sealed refractory 170 by hand for a long time in the field to carry out the work through the tuyere 120 and at the same time another worker on the opposite side of the tuyere 120, blow There is a problem in that a lot of work load occurs because it must be checked from time to time whether the crushing through the observation port 131 installed to facilitate the internal observation on the pipe.

따라서, 본 발명은 상기와 같은 종래의 문제점을 해소하기 위하여 제안된 것으로, 그 목적은 노벽보수작업동안 풍구의 내부통로를 밀폐하는 밀봉내화물을 고로 블로우파이프의 관찰구내로 삽입되는 고압수분사파이프의 고압수로서 작업자의 작업부하없이 완전하게 파쇄하여 파쇄효율성을 높일 수 있는 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치를 제공하고자 한다.Accordingly, the present invention has been proposed to solve the above-mentioned conventional problems, and its object is to provide a high pressure water spray pipe in which a sealed refractory sealing the inner passage of the tuyere is inserted into the blast furnace blow pipe observation hole during the furnace wall repair operation. The present invention provides a sealed refractory shredding apparatus using a blast furnace blow pipe observation port that can be completely shredded as a high-pressure water without a worker's workload to increase the shredding efficiency.

도 1은 일반적인 고로에 채용되는 블로우파이프를 도시한 구성도,1 is a configuration diagram showing a blow pipe employed in a general blast furnace,

도 2(a)(b)는 종래기술에 따른 밀봉내화물 파새장치를 도시한 구성도 및 작동상태도,Figure 2 (a) (b) is a block diagram showing the structure and operation state of the sealed refractory seeding device according to the prior art,

도 3은 본 발명에 따른 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치에 채용되는 연결부와 밀봉부를 도시한 종단면도,3 is a longitudinal sectional view showing a connection portion and a sealing portion employed in the sealed refractory shredding apparatus using the observation port of the blast furnace blow pipe according to the present invention;

도 4는 본 발명에 따른 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치를 도시한 조립도,4 is an assembly view showing a sealed refractory crushing device using the observation port of the blast furnace blow pipe according to the present invention,

도 5는 본 발명에 따른 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치를 도시한 사용상태도,5 is a use state diagram showing the sealed refractory crushing device using the observation port of the blast furnace blow pipe according to the present invention,

도 6은 본 발명에 따른 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치의 사용상태를 도시한 상세도.Figure 6 is a detailed view showing the state of use of the sealed refractory crushing device using the observation port of the blast furnace blow pipe according to the present invention.

* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

10 ...... 연결부 11a ..... 암나사부10 ...... Connection 11a ..... Female thread

12,22 ... 내부공 13 ...... 밸브부재12,22 ... inner hole 13 ...... Valve member

20 ...... 실링부 23 ...... 오링20 ...... Sealing section 23 ...... O-ring

24 ...... 나사부재 24b ..... 스틸볼24 ...... Screw member 24b ..... Steel ball

25 ...... 엔드플레이트 26 ...... 패킹부재25 ...... End plate 26 ...... Packing member

30 ...... 고압수분사부 31 ...... 고압수분사파이프30 ...... High pressure water spray section 31 ...... High pressure water spray pipe

32 ...... 분사건 34 ...... 고압수라인32 ...... Spray gun 34 ...... High pressure water line

120 ..... 풍구 130 ..... 블로우파이프120 ..... Blowhole 130 ..... Blowpipe

131 ..... 관찰구 170 ..... 밀봉내화물131 ..... observation port 170 ..... sealed refractory

상기와 같은 목적을 달성하기 위한 기술적인 구성으로써, 본 발명은,As a technical configuration for achieving the above object, the present invention,

상부로 철광석과 코크스가 장입되고, 하부외주면에 복수개의 풍구가 장착되며, 상기 풍구를 통하여 열풍과 미분탄을 공급하도록 미분탄취입랜스를 장착한 블로우파이프를 갖추고, 상기 블로우파이프에 로내부를 관찰하는 관찰구를 갖주어 용선 및 슬래그를 제조하는 고로에 있어서Iron ore and coke are charged to the upper part, and a plurality of blowholes are mounted on the lower outer circumference, and a blowpipe equipped with a pulverized coal injection lance is provided to supply hot air and pulverized coal through the blowhole, and observe the inside of the furnace in the blowpipe. In the blast furnace for making molten iron and slag with a sphere

상기 관찰구의 단부에 형성된 수나사부와 나사결합되도록 선단내주면에 암나사부를 형성하고, 몸체중앙을 관통하는 내부공을 개폐하는 밸브부재를 길이중앙에 갖추며, 후단에 퀵조인트의 암부가 일체로 장착된 중공원통형 연결부;A hollow body in which a female member is formed on the inner circumferential surface of the distal end so as to be screwed with the male screw formed at the end of the observation port, and has a valve member for opening and closing the inner hole penetrating the center of the body at the center of length, and the female part of the quick joint is integrally mounted at the rear end. Cylindrical connection;

상기 퀵조인트의 암부와 조립되는 숫부가 선단에 일체로 장착되고, 몸체중앙을 관통하는 내부공의 내주면에 밀봉용 오링이 장착되어 상기 연결부 후단에 조립되는 중공원통형 실링부 및The male part assembled with the female part of the quick joint is integrally mounted at the front end, and the sealing O-ring is mounted on the inner circumferential surface of the inner hole passing through the center of the body, and the hollow cylinder cylindrical sealing part assembled at the rear end of the connection part;

상기 실링부의 내부공과 상기 연결부의 내부공내로 수평하게 삽입되는 일정길이의 고압수분사파이프를 갖추고, 상기 고압수분사파이프의 후단과 연결관을 매개로 연결되며, 고압의 분사수가 공급되는 고압수라인이 연결되는 분사건을 갖추어 상기 풍구내부를 밀폐하는 밀봉내화물을 고압수로서 파쇄하는 고압수분사부를 포함함을 특징으로 하는 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치를 마련함에 의한다.A high pressure water line having a predetermined length of a high pressure water spray pipe horizontally inserted into the inner hole of the sealing part and the inner part of the connecting part, connected to a rear end of the high pressure water spray pipe by a connection pipe, and to which high pressure spray water is supplied. The present invention provides a sealed refractory crushing apparatus using a blast furnace blow pipe observation port, characterized in that it comprises a high pressure water injection unit for crushing the sealed refractory sealing the inside of the tuyere with high pressure water.

이하, 본 발명에 대하여 보다 상세히 설명한다.Hereinafter, the present invention will be described in more detail.

도 3은 본 발명에 따른 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치에 채용되는 연결부와 밀봉부를 도시한 종단면도이고, 도 4는 본 발명에 따른 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치를 도시한 조립도이며, 도 5는 본 발명에 따른 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치를 도시한 사용상태도이고, 도 6은 본 발명에 따른 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치의 사용상태를 도시한 상세도이다.Figure 3 is a longitudinal cross-sectional view showing the connecting portion and the sealing portion employed in the sealed refractory crushing apparatus using the observation port of the blast furnace blow pipe according to the present invention, Figure 4 is a sealed refractory fracture using the observation port of the blast furnace blow pipe according to the present invention 5 is an assembly view showing the apparatus, FIG. 5 is a state diagram showing a sealed refractory crushing apparatus using the observation hole of the blast furnace blow pipe according to the present invention, Figure 6 is a seal using the observation hole of the blast furnace blow pipe according to the present invention It is a detailed figure which shows the use condition of the refractory crushing apparatus.

본 발명의 장치(1)는 도 3 내지 6에 도시한 바와같이, 하부외주면에 복수개의 풍구(120)를 장착하고, 상기 풍구(120)를 통하여 열풍과 미분탄을 공급하도록 미분탄취입랜스(141)를 장착한 블로우파이프(130)를 갖추어 용선 및 슬래그를 제조하는 고로의 로벽보수작업시 상기 풍구(120)의 선단내부를 밀폐하도록 채워진 밀봉내화물을 상기 블로우파이프(130)의 관찰구(131)를 통하여 삽입되는 고압수분사파이프(31)의 고압수로서 완전하고, 안전하게 파쇄하여 풍구(120)를 관통하는 것으로서, 이러한 장치(1)는 중공원통형 연결부(10), 중공원통형 실링부(20) 및 고압수분사부(30)로 구성된다.3 to 6, the apparatus 1 of the present invention is equipped with a plurality of tuyere 120 on the lower outer peripheral surface, pulverized coal blowing lance 141 to supply hot air and pulverized coal through the tuyere 120 The refractory wall of the blast furnace for manufacturing the molten iron and slag equipped with a blow pipe (130) equipped with a sealing refractory material filled to seal the inside of the tip end of the tuyere 120, the observation hole 131 of the blow pipe 130 As a high-pressure water of the high-pressure water spray pipe 31 inserted through, completely and safely crushed to penetrate through the tuyere 120, such a device (1) is a hollow-cylindrical connection portion 10, hollow-cylindrical sealing portion (20) and Consists of a high pressure water injection unit (30).

즉, 상기 연결부(10)는 상기 블로우파이프(130)에 장착되는 관찰구(131)의 단부 외주면에 형성된 수나사부(131a)와 나사결합되도록 선단내주면에 암나사부(11a)를 형성한 일정길이의 중공원통부재이다.That is, the connecting portion 10 has a predetermined length of female threaded portion 11a formed on the inner circumferential surface of the tip so as to be screwed with the male screw portion 131a formed on the outer circumferential surface of the end of the observation port 131 mounted on the blowpipe 130. It is a hollow park member.

상기 연결부(10)의 몸체(11)길이중앙에는 몸체중앙을 관통하는 내부공(12)의 내부유로를 개폐하여 상기 블로우파이프(130)내의 열풍이 외부로 배출되지 못하도록 밸브부재(13)를 장착하며, 상기 몸체(11)후단에는 퀵조인트(40)의 암부(40a)가 일체로 장착된다.The valve member 13 is installed at the center of the body 11 of the connection part 10 so as to open and close the inner flow path of the inner hole 12 penetrating the center of the body so that the hot air in the blowpipe 130 is not discharged to the outside. The rear end of the body 11 is integrally mounted with an arm portion 40a of the quick joint 40.

그리고, 상기 실링부(20)는 몸체중앙에 내부공을 관통형성하고, 상기 연결부(10)의 몸체(11)후단과 대응하는 몸체(21)선단에는 상기 퀵조인트(40)의 암부(40a)와 조립되는 숫부(40b)가 일체로 장착되는 한편, 상기 몸체(21)의내부공(22)길이중앙에는 상기 내부공(22)내로 삽입되는 고압수분사파이프(31)의 외주면에 밀착되는 밀봉용 오링(23)이 장착된다.And, the sealing portion 20 is formed through the inner hole in the center of the body, the end of the body 21 corresponding to the rear end of the body 11 of the connecting portion 10, the arm portion 40a of the quick joint 40 While the male part 40b to be assembled with the body is integrally mounted, the inner hole 22 of the body 21 has a length centered in close contact with the outer circumferential surface of the high-pressure water spray pipe 31 inserted into the inner hole 22. The o-ring 23 is mounted.

여기서, 상기 실링부(20)의 몸체(21)에는 상기 내부공(22)과 직교하는 나사공(24a)을 복수개 관통형성하고, 상기 내부공내로 삽입되는 고압수분사수파이프(31)의 외주면과 접하여 지지하는 스틸볼(24b)을 하부로 탄력지지하는 나사부재(24)를 복수개의 각 나사공(24a)에 조립한다.Here, the body 21 of the sealing portion 20 is formed through a plurality of threaded holes (24a) orthogonal to the inner hole 22, and the outer peripheral surface of the high-pressure water spray pipe 31 inserted into the inner hole The screw member 24 which elastically supports the steel ball 24b which contacts and supports below is assembled in each of the several screw hole 24a.

그리고, 상기 스틸볼(24b)은 상기 나사공(24a)내에 하부로의 이탈이 곤란하도록 삽입되이 몸체일부가 상기 내부공(22)내로 노출되며, 상기 스틸볼(24b)과 나사부재(24)사이에는 상기 스틸볼(24b)을 직하부로 탄력지지하도록 스프링부재를 갖추어 구성하여도 좋다.In addition, the steel ball 24b is inserted into the screw hole 24a so that it is difficult to be separated from the lower part, and the body part is exposed into the inner hole 22, and the steel ball 24b and the screw member 24 are exposed. A spring member may be provided between the steel balls 24b to elastically support the steel balls 24b directly below.

또한, 상기 실링부(20)의 몸체(21)후단에는 상기 내부공(22)과 일치하는 관통공(25a)을 관통형성한 엔드플레이트(25)를 복수개의 체결부재(25b)로서 조립하고, 상기 엔드플레이트(25)와 상기 몸체(21)후단사이에는 상기 고압수분사파이프(31)의 외주면과 내부공(22)의 내주면사이를 밀봉하도록 U자단면상의 환고리형 패킹부재(26)를 장착한다.In addition, the rear end of the body 21 of the sealing portion 20 is assembled with a plurality of fastening members 25b, the end plate 25 through which the through-hole 25a corresponding to the inner hole 22 is formed. Between the end plate 25 and the rear end of the body 21, an annular packing member 26 having a U-shaped cross section is sealed to seal between the outer circumferential surface of the high-pressure water spray pipe 31 and the inner circumferential surface of the inner hole 22. Mount it.

한편, 상기 풍구(120)내부를 밀폐하고 있는 밀봉내화물(170)을 파쇄하도록 고압수를 분사하는 고압수분사부(30)는 상기 실링부(20)의 내부공(22)과 상기 연결부(10)의 내부공(12)내로 삽입되고, 삽입시 상기 풍구(120)의 밀봉내화물(170)에 고압수가 분사되는 선단이 근접할 정도의 일정길이를 갖는 고압수분사파이프(31)를 갖추어 구성한다.On the other hand, the high-pressure water injection unit 30 for spraying high-pressure water to crush the sealed refractory 170, which is sealed inside the tuyere 120, the inner hole 22 and the connecting portion 10 of the sealing portion 20 It is inserted into the inner hole 12 of the high pressure water injection pipe 31 having a predetermined length such that the tip of the high-pressure water is injected into the sealed refractory 170 of the tuyere 120 is close.

상기 고압수분사파이프(31)의 후단은 연결관(33)을 매개로 하여 고압수분사조절용 손잡이(35)를 갖는 분사건(32)과 연결되고, 상기 분사건(32)은 외부로부터 고압의 분사수가 공급되는 고압수라인(34)과 연결된다.The rear end of the high pressure water injection pipe 31 is connected to the injection gun 32 having the high pressure water injection adjustment knob 35 through the connecting pipe 33, and the injection gun 32 is connected to the high pressure from the outside. It is connected to the high pressure water line 34 to which the injection water is supplied.

이에 따라, 상기 분사건(32)을 취부하고 있는 작업자의 손잡이(35)조작에 의해서 상기 고압수분사수파이프(31)를 통하여 고압수가 전방으로 분사되거나 분사가 중단되는 것이다.Accordingly, the high pressure water is injected forward through the high pressure water injection pipe 31 or the injection is stopped by the operation of the handle 35 of the worker mounting the injection gun 32.

상기한 구성을 갖는 본 발명의 작용에 대해 설명한다.The operation of the present invention having the above configuration will be described.

고로(100)의 내벽을 보수하는 작업후 상기 고로(100)내로 열풍을 재송풍하는 작업시 출선구(110) 상부에 위치한 소수의 풍구(120)를 제외한 다수의 나머지 풍구(120)는 옥토인 밀봉내화물로서 폐쇄된 상태에서 재송풍이 시작된다.After repairing the inner wall of the blast furnace 100, a plurality of remaining tuyere 120, except for a small number of tuyere 120 located above the outlet 110 during the operation of re-blowing the hot air into the blast furnace 100 is octoin Re-blowing is started in the closed state as a sealed refractory.

그리고, 상기 재송풍 작업개시후 일정시간이 경과하여 고로내 원주별 가스 흐름과 기타 조업지수가 정상 조업치에 다다른 시점이나 인위적인 노황 제어를 위해서 상기 풍구(120)의 내부통로를 밀폐하고 있는 밀봉내화물(170)은 무감풍 상황에서 제거하게 된다.Then, a certain time elapses after the start of the re-ventilation operation, the gas flow and the other operation index within the blast furnace reaches the normal operation value, or the sealing that seals the internal passage of the tuyere 120 for artificial yellowing control. The refractory 170 is removed in a non-sensitized situation.

그리고, 상기 고로(100)의 내부상태를 풍구(120)를 통하여 확인할 수 있도록 블로우파이프(130)에 설치된 관찰구(131)의 수나사부(131a)에 연결부(10)의 암나사부(11a)를 체결하여 상기 관찰구(131)에 연결부(10)를 조립한다.The female screw portion 11a of the connecting portion 10 is connected to the male screw portion 131a of the observation port 131 installed in the blowpipe 130 so that the internal state of the blast furnace 100 can be confirmed through the tuyere 120. By assembling the connecting portion 10 to the observation port 131.

이러한 상태에서, 본 발명의 장치(1)를 이용하여 상기 풍구(120)의 밀봉내화물(170)을 제거하는 작업은, 먼저 상기 연결부(10)의 몸체(11)에 장착된 밸브부재(13)를 닫힘작동시켜 상기 고로(100)내부의 열풍이 외부로 배출되는 것을차단한다.In this state, the operation of removing the sealed refractory 170 of the tuyere 120 using the apparatus 1 of the present invention, first, the valve member 13 mounted on the body 11 of the connecting portion 10 By closing the operation to block the hot air inside the blast furnace 100 is discharged to the outside.

그리고, 상기 연결부(10)의 후단에 장착된 퀵조인트(40)의 암부(40a)와 상기 실링부(20)의 숫부(40b)를 서로 조립하여 상기 연결부(10)와 실링부(20)의 내부공(12)(22)이 서로 연통되도록 조립한다.Then, the arm portion 40a of the quick joint 40 mounted at the rear end of the connecting portion 10 and the male portion 40b of the sealing portion 20 are assembled with each other to form the connection portion 10 and the sealing portion 20. The inner holes 12, 22 are assembled to communicate with each other.

연속하여, 고압수라인(34)에 연결된 분사건(32)의 고압수분사파이프(31)를 상기 실링부(20)의 내부공(22)내로 삽입하고, 상기 고압수분사파이프(31)의 선단을 연결부(10)의 내부공(22)을 통하여 닫힘작동된 상기 밸브부재(13)근방까지 삽입한다.Subsequently, the high pressure water injection pipe 31 of the injection gun 32 connected to the high pressure water line 34 is inserted into the inner hole 22 of the sealing portion 20, and the high pressure water injection pipe 31 The tip is inserted through the inner hole 22 of the connecting portion 10 to the vicinity of the valve member 13 which is closed.

그리고. 상기 고압수분사파이프(31)의 선단이 상기 밸브(13)까지 삽입된 상태에서 상기 실링부(20)의 몸체(21)에 구비된 나사부재(24)를 조이거나 풀어서 상기 고압수분사파이프(31)의 중심과 상기 풍구(120)의 중심이 서로 일치되도록 상기 고압분사파이프(31)의 위치를 조절함과 동시에 실링상태를 점검한다.And. Tighten or loosen the screw member 24 provided on the body 21 of the sealing portion 20 in a state where the tip of the high pressure water injection pipe 31 is inserted to the valve 13 so that the high pressure water injection pipe ( 31 and check the sealing state while adjusting the position of the high-pressure injection pipe 31 so that the center of the tuyere 120 coincides with each other.

그리고, 상기 고압수분사파이프(31)의 위치조절과 실링상태의 확인이 끝나면, 상기 밸브부재(13)를 개방작동하여 연결부(10)의 내부공(12)을 개방하고, 이를 통하여 상기 고압수분사파이프(31)를 상기 블로우 파이프(130)내부로 전진시키고, 그 선단부가 상기 풍구(120)의 밀봉내화물(170)에 접근할 때 3700mm 정도의 길이를 갖는 고압수분사파이피(31)의 전진삽입을 종료한다.When the position adjustment of the high pressure water injection pipe 31 and the checking of the sealing state are completed, the valve member 13 is opened to open the inner hole 12 of the connection part 10, and thereby the high pressure water Advance of the high pressure water injection pipe 31 having a length of about 3700 mm when the injection pipe 31 is advanced into the blow pipe 130 and its front end approaches the sealing refractory 170 of the tuyere 120. Terminate insertion.

이러한 상태에서, 상기 분사건(32)의 손잡이(35)를 이용하여 고압수라인(34)을 통하여 상기 고압수분사파이프(31)내로 고압의 분사수를 공급하면, 그 단부로터 고압으로 분사되는 고압수에 의해서 상기 밀봉내화물(170)을 파쇄하여 상기풍구(120)를 개통한다.In this state, when the high pressure jet water is supplied into the high pressure water injection pipe 31 through the high pressure water line 34 using the handle 35 of the injection gun 32, the end rotor is sprayed at high pressure. The sealing refractory 170 is crushed by high pressure water to open the air vent 120.

이러한 경우, 상기 고압수분사파이프(31)는 블로우파이프(130)의 내부공에 수평하게 삽입되어 상기 밀봉내화물(170)의 표면에 수직한 방향으로 고압수를 고압으로 분사할 수 있어 상기 밀봉내화물(170)을 파쇄하는 효율을 높일수 있다.In this case, the high-pressure water spray pipe 31 is inserted into the inner hole of the blowpipe 130 horizontally to inject high-pressure water at a high pressure in a direction perpendicular to the surface of the sealed refractory 170, the sealed refractory The efficiency of crushing 170 can be improved.

그리고, 상기 실링부(20)의 내부공(22)은 상기 고압분사파이프(31)의 외경보다 크고, 상기 연결부(10)의 내부공(12)내경보다 작은 크기로 구성되어 상기 고압분사파이프(31)의 내주면과 상기 실링부(20)의 내부공(22)내주면사이에 일정크기의 간격을 형성한다. 이에 따라, 고압수분사시 상기 나사부재(24)하부단의 스틸볼(24b)에 지지된 상기 고압수분사파이프(31)는 상기 스틸볼(24b)을 중심으로 하여 수평한 고압수분사파이프(31)의 선단을 경사지게 움직이면서 고압수를 분사하여 상기 풍구(120)의 내주면에 잔류하는 밀봉내화물(170)을 완벽하게 파쇄할 수 있는 것이다.In addition, the inner hole 22 of the sealing portion 20 is larger than the outer diameter of the high-pressure injection pipe 31, the inner hole 12 of the connection portion 10 is configured to a size smaller than the high-pressure injection pipe ( A predetermined size gap is formed between the inner circumferential surface of 31 and the inner circumferential surface of the inner hole 22 of the sealing portion 20. Accordingly, the high pressure water injection pipe 31 supported by the steel ball 24b at the lower end of the screw member 24 during the high pressure water injection is horizontally pressurized with the steel ball 24b. By spraying the high pressure water while inclining the tip of the) it is possible to completely crush the sealed refractory 170 remaining on the inner circumferential surface of the tuyere (120).

또한, 상기 고압수분사파이프(31)가 설치되는 관찰구(131)가 작업자의 근접이 용이한 바닥면으로부터 1000mm의 높이에 구비되어 있기 때문에, 작업자가 고압수분사파이프(31)를 삽입하여 고압수를 분사하는 작업성이 편리하다.In addition, since the observation port 131 in which the high-pressure water injection pipe 31 is installed is provided at a height of 1000 mm from the bottom surface where the operator can easily approach, the operator inserts the high-pressure water injection pipe 31 to supply a high pressure. Workability of spraying water is convenient.

그리고, 상기 실링부(20)와 연결부(10)가 착탈이 용이한 퀵조인트(40)로 연결되어 장치의 조립, 해체가 쉽고, 인접하는 다른 풍구(120)에서의 밀봉내화물(170)을 파쇄하기 이한 위치이동이 용이하다.In addition, the sealing part 20 and the connection part 10 are connected to the quick joint 40 which is easily detachable, so that the assembly and disassembly of the device can be easily performed, and the sealing refractory 170 at the other air hole 120 is crushed. The following positional movement is easy.

상술한 바와같은 본 발명에 의하면, 블로우파이프의 관찰구내로 수평하게삽입되는 고압수분사파이프의 고압수로서 풍구의 내부통로를 밀폐하는 밀봉내화물을 파쇄함으로서, 고로의 노벽보수후 풍구의 밀봉내화물을 파쇄하는 작업시간 및 작업부하를 현저히 줄일 수 있기 때문에, 고로의 노황을 신속하게 정상적으로 복귀할 수 있어 작업생산량의 감소를 방지할 수 있다.According to the present invention as described above, by breaking the sealed refractory sealing the inner passage of the tuyere as high pressure water of the high-pressure water spray pipe inserted horizontally into the observation hole of the blowpipe, the sealed refractory of the tuyere after repairing the furnace wall of the blast furnace Since the working time and work load which are crushed can be reduced significantly, the blast furnace aging can be returned to normal normally, and the reduction of work volume can be prevented.

또한, 고로의 노황 제어가 용이하며 높은 압력과 고온(1200℃)의 열풍으로부터 작업자를 안전하게 보호하여 안전사고를 방지할 수 있는 효과가 얻어진다.In addition, it is easy to control the furnace blast furnace, and the effect is obtained to safely protect the operator from hot air of high pressure and high temperature (1200 ℃) to prevent safety accidents.

본 발명은 특정한 실시예에 관련하여 도시하고 설명하였지만, 이하의 청구범위에 의해 마련되는 본 발명의 정신이나 분야를 벗어나지 않는 한도내에서 본 발명이 다양하게 개조 및 변화될수 있다는 것을 당업계에서 통상의 지식을 가진자는 용이하게 알수 있음을 밝혀두고자 한다.While the invention has been shown and described with respect to specific embodiments thereof, it will be apparent to those skilled in the art that various changes and modifications can be made without departing from the spirit or scope of the invention as set forth in the claims below. I would like to clarify that knowledge is easy to know.

Claims (4)

상부로 철광석과 코크스가 장입되고, 하부외주면에 복수개의 풍구(120)가 장착되며, 상기 풍구(120)를 통하여 열풍과 미분탄을 공급하도록 미분탄취입랜스(141)를 장착한 블로우파이프(130)를 갖추고, 상기 블로우파이프(130)에 로내부를 관찰하는 관찰구(131)를 갖주어 용선 및 슬래그를 제조하는 고로에 있어서Iron ore and coke is charged to the upper, a plurality of blowholes 120 is mounted on the lower outer peripheral surface, the blowpipe 130 equipped with a pulverized coal injection lance 141 to supply hot air and pulverized coal through the blowhole 120 In the blast furnace for manufacturing molten iron and slag by having an observation port 131 for observing the inside of the furnace in the blow pipe 130 상기 관찰구(131)의 단부에 형성된 수나사부(131)와 나사결합되도록 선단내주면에 암나사부(11a)를 형성하고, 몸체(11)중앙을 관통하는 내부공(12)을 개폐하는 밸브부재(12)를 길이중앙에 갖추며, 후단에 퀵조인트(40)의 암부(40a)가 일체로 장착된 중공원통형 연결부(10);A valve member (11a) is formed on the inner circumferential surface of the distal end so as to be screwed into the male screw portion (131) formed at the end of the observation port (131), and opens and closes the inner hole (12) passing through the center of the body (11). 12) having a center of the length, the rear end of the hollow-cylindrical cylindrical connection portion 10 is integrally mounted with the arm portion 40a of the quick joint 40; 상기 퀵조인트(40)의 암부(40a)와 조립되는 숫부(40b)가 선단에 일체로 장착되고, 몸체(21)중앙을 관통하는 내부공(22)의 내주면에 밀봉용 오링(23)이 장착되어 상기 연결부(10) 후단에 조립되는 중공원통형 실링부(20) 및The male part 40b assembled with the arm part 40a of the quick joint 40 is integrally mounted at the tip, and the sealing O-ring 23 is mounted on the inner circumferential surface of the inner hole 22 passing through the center of the body 21. And the hollow-cylindrical cylindrical sealing part 20 which is assembled at the rear end of the connection part 10 and 상기 실링부(20)의 내부공(22)과 상기 연결부(10)의 내부공(22)내로 수평하게 삽입되는 일정길이의 고압수분사파이프(31)를 갖추고, 상기 고압수분사파이프(31)의 후단과 연결관(33)을 매개로 연결되며, 고압의 분사수가 공급되는 고압수라인(34)이 연결되는 분사건(32)을 갖추어 상기 풍구(120)내부를 밀폐하는 밀봉내화물(170)을 고압수로서 파쇄하는 고압수분사부(30)를 포함함을 특징으로 하는 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치.It is provided with a high-pressure water spray pipe 31 of a predetermined length horizontally inserted into the inner hole 22 of the sealing portion 20 and the inner hole 22 of the connecting portion 10, the high-pressure water spray pipe 31 It is connected via the rear end of the connection pipe 33 and the injection gun 32 is connected to the high-pressure water line 34 is supplied with a high-pressure injection water is sealed refractory 170 to seal the inside of the tuyere 120 Sealed refractory crushing device using the observation port of the blast furnace blow pipe, characterized in that it comprises a high-pressure water spraying unit for crushing the high pressure water. 제 1항에 있어서,The method of claim 1, 상기 실링부(20)의 몸체(21)에는 상기 내부공(22)과 직교하는 나사공(24a)을 복수개 관통형성하고, 상기 내부공내로 삽입되는 고압수분사수파이프(31)의 외주면과 접하여 지지하는 스틸볼(24b)을 하부로 탄력지지하는 나사부재(24)를 복수개의 각 나사공(24a)에 조립함을 특징으로 하는 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치.A plurality of threaded holes 24a orthogonal to the inner hole 22 are formed in the body 21 of the sealing part 20 and supported in contact with the outer circumferential surface of the high-pressure water spray pipe 31 inserted into the inner hole. Sealed refractory crushing device using a blast furnace blow pipe observation port characterized in that the assembly of the screw member (24) for supporting the steel ball (24b) to the lower portion in the plurality of screw holes (24a). 제 1항에 있어서,The method of claim 1, 상기 실링부(20)의 몸체(21)후단에는 상기 내부공(22)과 일치하는 관통공(25a)을 관통형성한 엔드플레이트(25)를 복수개의 체결부재(25b)로서 조립하고, 상기 엔드플레이트(25)와 상기 몸체(21)후단사이에는 상기 고압수분사파이프(31)의 외주면과 내부공(22)의 내주면사이를 밀봉하도록 U자단면상의 환고리형 패킹부재(26)를 장착함을 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치.At the rear end of the body 21 of the sealing portion 20, an end plate 25 through which a through hole 25a corresponding to the inner hole 22 is formed is assembled as a plurality of fastening members 25b, and the end Between the plate 25 and the rear end of the body 21 is equipped with a ring-shaped packing member 26 on the U-shaped section so as to seal between the outer peripheral surface of the high-pressure water spray pipe 31 and the inner peripheral surface of the inner hole 22. Sealed refractory shredding device using the observation port of the blast furnace. 제 1항에 있어서,The method of claim 1, 상기 실링부(20)의 내부공(22)은 상기 고압분사파이프(31)의 외경보다 크고,상기 연결부(10)의 내부공(12)내경보다 작은 크기로 구성됨을 특징으로 하는 고로 블로우파이프의 관찰구를 이용한 밀봉내화물 파쇄장치.The inner hole 22 of the sealing portion 20 is larger than the outer diameter of the high-pressure injection pipe 31, the blast furnace blow pipe, characterized in that the size is smaller than the inner diameter of the inner hole 12 of the connection portion 10 Sealed refractory shredding device using the observation port.
KR10-2002-0079004A 2002-12-12 2002-12-12 An apparatus for crushing the blocking brick using the insight of blow pipe in furnace KR100470067B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0079004A KR100470067B1 (en) 2002-12-12 2002-12-12 An apparatus for crushing the blocking brick using the insight of blow pipe in furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0079004A KR100470067B1 (en) 2002-12-12 2002-12-12 An apparatus for crushing the blocking brick using the insight of blow pipe in furnace

Publications (2)

Publication Number Publication Date
KR20040051144A KR20040051144A (en) 2004-06-18
KR100470067B1 true KR100470067B1 (en) 2005-02-05

Family

ID=37345141

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0079004A KR100470067B1 (en) 2002-12-12 2002-12-12 An apparatus for crushing the blocking brick using the insight of blow pipe in furnace

Country Status (1)

Country Link
KR (1) KR100470067B1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100682092B1 (en) * 2006-03-21 2007-02-12 주식회사 포스코 Lens protection apparatus for reheating furnace
KR101614604B1 (en) 2014-07-15 2016-04-22 주식회사 포스코 Method for opening tuyere of blast furnace
CN106595316A (en) * 2016-11-30 2017-04-26 宝钢工程技术集团有限公司 Metallurgical spray gun with replaceable gun head

Also Published As

Publication number Publication date
KR20040051144A (en) 2004-06-18

Similar Documents

Publication Publication Date Title
KR100470067B1 (en) An apparatus for crushing the blocking brick using the insight of blow pipe in furnace
KR101203651B1 (en) Apparatus for destroying bird's nest in blast furnace
CN201413042Y (en) Nonimmersed top-blown lance
KR100805719B1 (en) Apparatus for penetrate tuyere of furnace shut
KR20020048161A (en) Making apparatus of protective wall for tapping hole
KR100504372B1 (en) Mending material spray apparatus of coke dry quenching
CN220284120U (en) Peeping device for blast furnace
KR200309410Y1 (en) Blast Furnace Refractory Shredder
CN218710610U (en) Oxygen lance with adjustable oxygen content
CN212575993U (en) Combined spray gun protective sleeve
CN216677729U (en) Medicine crushing and scattering device for barrel of boiler denitration machine
CN219735305U (en) Oil gun oil leakage prevention device and oil gun thereof
CN101310027A (en) Tuvere tuyere of melter-gasifier
CN216473311U (en) Anti-blocking purging control device for electrode spray ring of electric furnace
KR100418981B1 (en) pulverized coal injection lance location control apparatus
KR101076164B1 (en) Apparatus for crushing out side wall of tuyere of blast-furnace
KR20010048090A (en) Lance for blowing waste scum in blast furnace with closing prevention function
KR20030052185A (en) Apparatus for closing tapping hole of molten steel furnace
KR100865239B1 (en) Apparatus of blowing in fine particle coal for double cooling and complete combustion of fine particle
CN117403017A (en) Blast furnace protective cooling device and use method thereof
KR100432130B1 (en) Tuyere nozzle intercepter and apparatus for smashing the same
KR980008157U (en) Foreign material removal device at the end of the furnace air lance
KR20130014801A (en) Apparatus for blocking up a tuyere
KR100460661B1 (en) An apparatus for adjusting the water level in a degassing tower of a blast furnace gas collecting line
KR20020047764A (en) The Piercing Apparatus of Blowing Lance for Pulverizer

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130107

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20140124

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20150115

Year of fee payment: 11

LAPS Lapse due to unpaid annual fee