KR100280694B1 - Wet sanders - Google Patents

Wet sanders Download PDF

Info

Publication number
KR100280694B1
KR100280694B1 KR1019980009152A KR19980009152A KR100280694B1 KR 100280694 B1 KR100280694 B1 KR 100280694B1 KR 1019980009152 A KR1019980009152 A KR 1019980009152A KR 19980009152 A KR19980009152 A KR 19980009152A KR 100280694 B1 KR100280694 B1 KR 100280694B1
Authority
KR
South Korea
Prior art keywords
sand
soft ground
conveyor
caterpillar
spreader
Prior art date
Application number
KR1019980009152A
Other languages
Korean (ko)
Other versions
KR19980019437A (en
Inventor
배병갑
Original Assignee
배병갑
주식회사대양피디디
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 배병갑, 주식회사대양피디디 filed Critical 배병갑
Priority to KR1019980009152A priority Critical patent/KR100280694B1/en
Publication of KR19980019437A publication Critical patent/KR19980019437A/en
Application granted granted Critical
Publication of KR100280694B1 publication Critical patent/KR100280694B1/en

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

본 발명은 습지주행용 모래포설기에 관한 것으로서, 더욱 상세하게는 소정의 부력을 가지는 모래포설기에 모래를 상차한 뒤에 초연약지반 및 물과 뻘이 혼재된 기역(이하 습지라 칭함)을 주행하면서, 콘베어를 이용하여 습지에 균일한 두께로 모래를 포설할 수 있도록 함으로서, 편중포설로 인한 지반의 융기(隆起) 및 침강(沈降)을 방지 할 수 있도록 하고, 그로 인하여 지반의 교란 내지 파괴를 미연에 예방할 수 있도록 하기 위한 것이다.The present invention relates to a sand spreader for wetland driving, and more particularly, after the sand is loaded on the sand spreader having a predetermined buoyancy, the ultra soft ground and the base and water and 뻘 mixed with the air (hereinafter referred to as wetland), Conveyors allow sand to be deposited in wetlands with a uniform thickness, thereby preventing ground uplift and sedimentation due to uneven snowing, thereby preventing ground disturbances and destruction. This is to help prevent.

상기 본 발명에 의한 습지주행용 모래포설기는, 습지 등의 연약지반에 모래를 포설하여 연약지반을 단단하게 하는 습지주행용 모래포설기에 있어서, 프레임(15)의 양측에는 속이 비어 부력이 작용하는 캐터필러폰툰(PONTOON:11)이 고정설치되고, 상기 캐터필러폰툰(11)의 외주연 전둘레에는 다수개의 트랙슈(12)가 링크식으로 연결된 캐터필러(13)가 구동롤러(14)에 의해 선회토록 권회설치되어 하체(10)를 구성하며, 상기 하체(10)의 상측에는 양측에 모래유실커버(25)가 설치된 콘베어(20)가 구동모터(21)에 의해 선회토록 설치된 것을 특징으로 한다.The wet sand running sand spreader according to the present invention, in the wet sand running sand spreader to install the sand in the soft ground, such as wetlands to harden the soft ground, the caterpillar buoyancy acts on both sides of the frame (15) A pontoon (PONTOON) 11 is fixedly installed, and a caterpillar 13, in which a plurality of track shoes 12 are linked by a drive roller 14, is wound around the outer circumferential edge of the caterpillar pontoon 11 by a driving roller 14. It is installed to constitute a lower body 10, the upper side of the lower body 10 is characterized in that the conveyor 20, the sand loss cover 25 is installed on both sides is installed to be rotated by the drive motor 21.

Description

습지주행용 모래포설기Wet sanders

본 발명은 습지주행용 모래포설기에 관한 것으로서, 더욱 상세하게는 소정의 부력을 가지는 모래포설기에 모래를 상차한 뒤에 습지를 주행하면서 습지에 균일한 두께로 모래를 포설(鋪設)할 수 있도록 함으로서, 편중포설로 인한 지반의 융기(隆起) 및 침강(沈降)을 방지 할 수 있도록 하고, 그로 인하여 지반의 교란 내지 파괴를 미연에 예방할 수 있도록 하기 위한 것이다.The present invention relates to a sand spreader for wetland driving, and more particularly, by allowing sand to be deposited in a uniform thickness while driving the wetland after loading sand in a sand spreader having a predetermined buoyancy, The purpose of the present invention is to prevent elevation and sedimentation of the ground due to uneven laying, thereby preventing ground disturbance or destruction.

일반적으로 준설매립지와 같은 초연약지반을 원하는 부지로 개량하기 위해서는 개펄이나 준설매립지와 같은 연약지반에 매트를 깔고, 그 위에 일정한 두께로 모래를 포설하여 지반을 단단하게 한뒤에, 연약지반 개량용 장비를 투입시켜 연약지반을 개량하게 된다.In general, in order to improve the super soft ground such as dredged landfill to the desired site, the mat is laid on the soft ground such as squirt or dredged landfill, sand is deposited to a certain thickness on it, and then the ground is hardened. It will improve the soft ground.

상기와 같이 연약지반에 모래를 포설하는 공법은 도 1에 도시된 바와 같이 습지형 불도우저를 이용하여 연약지반에 모래를 포설하는 공법이 널리 사용되며, 도 2에 도시된 바와같은 고압펌프를 이용하여 물과 함께 모래를 살포하는 공법도 사용되고 있다.As described above, the method of laying sand on the soft ground is widely used as a method of laying sand on the soft ground using a wetland-type bulldozer as shown in FIG. 1, and using a high pressure pump as shown in FIG. 2. A method of spraying sand with water is also used.

상기 도 1에 도시된 바와 같은 습지형 불도우저를 이용하는 공법은, 개량할 개펄이나 준설매립지와 같은 초연약지반(4)에 습지형 불도우저(1)를 이용하여 연약지반에 모래(3)를 포설하는 것으로, 이는 연약지반에 모래를 포설하기 위하여 연약지반에 중량물의 습지형 불도우저를 투입시키게 되면, 습지형 불도우저의 자중에 의해 습지형 불도우저가 투입된 지반이 가라앉고, 또한, 시방서상에 제시된 두께로 일정하게 넓은 면적을 포설하기에는 많은 문제점이 발생하게 된다.In the method using the wetland-type bulldozer as shown in FIG. 1, sand (3) is laid on the soft-ground by using the wetland-type bulldozer (1) on the super soft ground (4), such as a scavenger or dredging landfill to be improved. When the heavy wetland-type bulldozer is placed in the soft ground to install sand on the soft ground, the ground into which the wetland-type bulldozer is injected is submerged by the weight of the wetland-type bulldozer. There are many problems to install a large area.

상기와 같은 문제점이 있음에도 불구하고, 여태껏 마땅한 공법이 개발된 바가 없기에 습지형 불도우저를 사용하여 연약지반 개량공사를 진행하여 왔으나, 이는 초기에 습지형 불도우저의 자중과 모래포설하중에 의해 모래 포설개시부에는 다량의 모래가 포설되게 되고 앞으로 나갈수록 모래가 적게 포설되어 국부침강을 야기시키는 문제점과, 모래포설거리가 과다할 경우에는 공사수행이 불가능한 문제점을 아울러 지니고 있었다.In spite of the above problems, since the proper method has not been developed so far, we have been carrying out soft ground improvement work using wetland-type bulldozer, but this is the beginning of sand laying due to the weight and sand load of wetland-type bulldozer. There was a problem in that a large amount of sand was laid, and less sand was laid out in the future, causing local sedimentation, and a problem that construction could not be carried out when the sand spreading distance was excessive.

그리고, 상기 도 2에 도시된 고압펌프를 사용하는 공법의 경우에는 고압펌프(2)를 이용하여 물과 함께 모래를 살포하는 것인데, 근거리에는 모래(3)중의 굵은 모래(3a)입자들만이 포설되고, 원거리에는 모래중의 가볍고 가는 모래(3b)입자들만 포설되게 된다.In the method using the high pressure pump illustrated in FIG. 2, sand is sprayed together with water using a high pressure pump 2, and only coarse sand 3a particles in the sand 3 are installed at a short distance. In the long distance, only light and fine sand (3b) particles in the sand will be installed.

상기와 같이 굵은 모래(3a)와 가는 모래(3b)가 분리되어 포설됨에 따라 지반의 강도가 불균일하게 되어 차기투입장비의 주행에 제약이 따르는 문제점과, 굵은 모래가 포설된 근거리는 모래와 함께 분사되는 물 및 지하에서 올라오는 과잉 간극수가 쉽게 배출되나, 미세립자가 포설된 원거리에는 모래와 함께 분사된 물 및 지하에서 올라오는 과잉간극수가 쉽게 배수가 되지 않는 등 수평배수층의 확보가 어려운 문제점을 지니고 있었다.As the coarse sand (3a) and fine sand (3b) is separated and laid as described above, the strength of the ground becomes non-uniform, and there is a problem in that the driving of the next charging equipment is limited, and the coarse sand is sprayed together with the near sand It is difficult to secure a horizontal drainage layer, such as the excess water from the water and the underground, which is easily discharged, but the microparticles are installed in the far distance. there was.

본 발명은 상기와 같은 문제점을 해결 하기위한 것으로서, 본 발명의 목적은 소정의 부력을 지니고 있어서 습지 등의 연약지반에서 용이하게 주행하면서, 초연약지반에 균일한 두께로 모래를 포설할 수 있도록 하는 습지주행용 모래포설기를 제공하기 위한 것이다.The present invention is to solve the above problems, the object of the present invention is to have a predetermined buoyancy to easily sand in the soft ground, such as wetlands, while laying a sand with a uniform thickness on the super soft ground To provide wet sanders.

상기와 같은 목적을 달성하기 위한 본 발명은, 습지 등의 연약지반에 모래를 포설하여 연약지반을 단단하게 하는 습지주행용 모래포설기에 있어서, 프레임의 양측에는 속이 비어 부력이 작용하는 캐터필러폰툰이 고정설치되고, 상기 캐터필러폰툰의 외주연에는 다수개의 트랙슈가 링크식으로 연결된 캐터필러가 구동롤러에 의해 선회토록 권회설치되어 하체를 구성하며, 상기 하체의 상측에는 양측에 모래유실커버가 설치된 콘베어가 구동모터에 의해 선회토록 설치되어 있다.The present invention for achieving the above object, in the wet sand running sand spreader for laying the soft ground by laying sand on the soft ground, such as wetlands, the caterpillar pontoon fixed buoyant buoyancy acts on both sides of the frame Caterpillar pontoons are installed on the outer periphery of the caterpillar pontoon is connected to a plurality of track shoes are linked by a rotating roller to rotate the lower body to form a lower body, the upper side of the lower body has a conveyor cover with sand loss cover is installed on the drive motor It is installed to turn by.

또한, 상기 하체의 상측에는 하측이 개구된 호퍼부를 구비한 모래적재함이 지지대에 의해 설치된 것을 특징으로 한다.In addition, on the upper side of the lower body is characterized in that the sand storage box having a hopper portion with an open side is installed by a support.

도 1은 종래에 불도우저를 이용하여 연약지반에 모래를 포설하는 공법을 나 타내는 설명도.1 is an explanatory diagram showing a conventional method for laying sand on a soft ground using a bulldozer;

도 2는 종래에 고압펌트를 이용하여 연약지반에 모래를 포설하는 공법을 나 타내는 설명도.Figure 2 is an explanatory diagram showing a conventional method for laying sand on the soft ground using a high pressure pump.

도 3은 본 발명의 일실시예를 나타내는 측면도.Figure 3 is a side view showing an embodiment of the present invention.

도 4는 본 발명의 이실시예를 나타내는 측면도.Figure 4 is a side view showing this embodiment of the present invention.

도 5는 도 4에 도시된 본 발명의 정면도이다.5 is a front view of the present invention shown in FIG.

〈도면의 주요부분에 대한 부호의 설명〉<Explanation of symbols for main parts of drawing>

10. 하체 11. 캐터필러폰툰10. Lower body 11. Caterpillar pontoons

12. 트랙슈 13. 캐터필러12. Track Shoe 13. Caterpillar

14. 구동롤러 15. 프레임14. Drive roller 15. Frame

16. 받침지지구 20. 콘베어16. Supporting Base 20. Conveyor

21. 구동모터 22. 모래적재함21. Drive motor 22. Sand loading

23. 호퍼부 24. 지지대23. Hopper section 24. Support stand

25. 모래유실커버25. Sand loss cover

이하, 첨부된 도면에 따라 본 발명을 상세하게 설명하면 다음과 같다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

도 3은 본 발명의 일실시예를 나타내는 측면도이고, 도 4는 본 발명의 이실시예를 나타내는 측면도이며, 도 5는 도 4에 도시된 본 발명의 정면도이다.Figure 3 is a side view showing an embodiment of the present invention, Figure 4 is a side view showing this embodiment of the present invention, Figure 5 is a front view of the present invention shown in FIG.

먼저, 도 3에 도시된 본 발명의 습지주행용 모래포설기는 프레임(15)의 양측에 속이 비어 부력이 작용하는 탱크형태의 캐터필러폰툰(11)이 고정설치되고, 상기 캐터필러폰툰(11)의 외주연에는 다수개의 트랙슈(12)가 링크식으로 연결된 캐터필러(13)가 구동롤러(14)에 의해 선회토록 권회설치되어 하체(10)를 구성한다.First, the wet sand running sand spreader of the present invention shown in FIG. 3 is fixed to the tank-type caterpillar pontoon (11) in which buoyancy acts on both sides of the frame (15), the outside of the caterpillar pontoon (11) At the periphery, the caterpillar 13, in which a plurality of track shoes 12 are linked, is wound around the drive roller 14 to be pivoted to form the lower body 10. As shown in FIG.

상기 하체(10)의 상측에는 모래가 적재되어 연약지반에 모래를 살포하는 콘베어(20)가 구동모터(21)에 의해 선회토록 설치되며, 상기 콘베어(20)의 양측에는 콘베어(20)에 적재된 모래가 콘베어(20)의 외측으로 흘러내려 유실되는 것을 커버하는 모래유실커버(25)가 설치되어 있다.On the upper side of the lower body 10, the sand is loaded and the conveyor 20 for spraying sand on the soft ground is installed to be swiveled by the driving motor 21, and both sides of the conveyor 20 are loaded on the conveyor 20. A sand loss cover 25 is installed to cover the lost sand flowing out of the conveyor 20 to be lost.

이때, 상기 콘베어(20)는 본 발명의 모래포설기의 폭과 동일한 폭으로 넓게 설치되어 다량의 모래가 콘베어(20)의 상측에 적재될 수 있도록 되어 있다.At this time, the conveyor 20 is installed in the same width as the sand spreader of the present invention so that a large amount of sand can be loaded on the upper side of the conveyor (20).

그리고, 도 4 및 도 5에 도시된 본 발명의 이실시예는 일실시예의 모래포설기의 상측에 모래적재함(22)을 설치한 것으로 하체(10)의 구성에 대해서는 설명을 생략하고, 추가설치된 구성에 대해서만 설명하기로 한다.In addition, this embodiment of the present invention shown in Figures 4 and 5 is provided with a sand box 22 on the upper side of the sand spreader of one embodiment, the description of the configuration of the lower body 10 will be omitted, additionally installed Only the configuration will be described.

즉, 이실시예에 의한 모래포설기는 상기 콘베어(20)의 상측에 하측이 개구된 호퍼부(23)를 구비한 모래적재함(22)이 지지대(24)에 의해 설치된다. 이때, 상기 콘베어(20)는 본 발명의 모래포설기의 폭과 동일한 폭으로 넓게 설치되며, 모래가 적재되는 모래적재함(22)도 콘베어(20)의 폭과 동일하거나 다소 좁게 형성되어 있다.That is, the sand sanding machine according to the present embodiment is provided with a sand holder 22 having a hopper portion 23 having a lower side opened on the upper side of the conveyor 20 by a support 24. At this time, the conveyor 20 is installed in the same width as the width of the sand sanding machine of the present invention, the sand loading box 22 is loaded sand is also formed the same or somewhat narrower than the width of the conveyor (20).

그리고, 상기 콘베어(20)의 선단부 즉, 모래적재함(22)에서 낙하되는 모래가 받쳐지는 부분(이하 모래수수부라 칭함)이 콘베어(20)의 전방측 연약지반으로 모래가 낙하되는 부분(이하 모래포설부라 칭함)보다 높게 경사지게 설치되는 것이 바람직하며, 상기 모래적재함(22)의 호퍼부(23) 말단부와 모래수수부사이는 소정의 간격을 두고 근접하게 설치되며, 상기 콘베어(20)의 양측에는 콘베어(20)에 적재된 모래가 콘베어(20)의 외측으로 흘러내려 유실되는 것을 커버하는 모래유실커버(25)가 설치되어 있다.In addition, the tip portion of the conveyor 20, that is, the portion where the sand falling from the sand carrier 22 (hereinafter referred to as the sand-receiving portion) is a portion where the sand falls to the front soft ground of the conveyor 20 (hereinafter sand) It is preferable to be installed inclined higher than the installation portion, and the hopper portion 23 end portion and the sand milling portion of the sand carrier 22 is installed in close proximity at a predetermined interval, the conveyor 20 on both sides of the conveyor A sand loss cover 25 is provided to cover the sand loaded on the 20 flowing out of the conveyor 20 to be lost.

또한, 도 5에 도시된 바와 같이 모래적재함(22)의 하측과 프레임(15)의 사이에는 중량물의 모래적재함(22)을 받쳐주는 받침지지구(16)가 상향설치되어 모래적재함(22)에 적재된 모래의 무게에 의해 모래적재함(22)이 처지는 것에 대비하는 것이다.In addition, as shown in FIG. 5, between the lower side of the sand carrier 22 and the frame 15, a supporting support 16 supporting the sand carrier 22 of the heavy body is upwardly installed to the sand carrier 22. This is to prepare the sand stack 22 to sag by the weight of the loaded sand.

이와 같이 구성된 본 발명의 작용효과를 살펴보면 다음과 같다.Looking at the effects of the present invention configured as described above are as follows.

먼저, 도 3에 도시된 본 발명의 일실시예부터 살펴보기로한다.First, it will be described from an embodiment of the present invention shown in FIG.

연약지반에 본 발명의 일실시예에 의한 모래포설기를 이용하여 모래를 포설하고자 할 경우에는 크레인이나 페이로다 등의 장비를 이용하여 콘베어(20)의 상측에 일정한 두께로 모래를 적재한 뒤에, 습지 등의 개량할 지반으로 본 발명의 모래포설기가 이동을 한다.When sand is to be laid using a sand spreader according to an embodiment of the present invention on a soft ground, after loading sand with a predetermined thickness on the upper side of the conveyor 20 by using equipment such as a crane or payload, The sand spreader of the present invention moves to the ground to be improved.

상기 본 발명의 모래포설기는 하체(10), 특히 캐터필러폰툰(11)이 커다란 통체로 형성되어서 부력이 작용하게 하도록 되어 있어서, 초연약지반 및 물과 뻘이 혼재된 지역 등의 습지를 주행하여도 본 발명의 모래포설기가 연약지반으로 빠지는 일이 없이 주행이 가능하다.The sand spreader of the present invention is a lower body 10, in particular caterpillar pontoon (11) is formed in a large cylinder so that the buoyancy acts, even if you run through wetlands such as ultra soft ground and water and water mixed area Sand sanding machine of the present invention can run without falling into the soft ground.

이렇게 주행하여 작업위치로 이동하는 과정에서 개펄 등의 연약지반에 모래를 포설하고자 할 경우에는 콘베어(20)를 선회시키기 위한 구동모터(21)를 구동시키면, 상기 구동모터(21)의 구동력에 의해 콘베어(20)가 회전이동하게 된다.In the process of moving to the working position in this way to install sand on the soft ground such as gaepul driving the drive motor 21 for turning the conveyor 20, by the drive force of the drive motor 21 The conveyor 20 is rotated.

상기와 같이 콘베어(20)가 회전이동함에 따라 콘베어(20)의 상측에 적재되어 있던 모래가 모래포설기의 전방으로 낙하하면서 연약지반에 균일하게 포설되며, 이렇게 모래가 균일하게 포설됨에 따라 연약지반이 균일한 강도로 단단해져 연약지반을 개량하기 위한 별도의 차기투입장비도 원활하고 안전하게 투입할 수 있게 되는 것이며, 이후 원활한 수평배수층의 역할도 가능하게 되는 것이다.As the conveyor 20 rotates as described above, the sand loaded on the upper side of the conveyor 20 falls in front of the sand spreader and is uniformly installed on the soft ground. As the sand is uniformly laid, the soft ground This uniform strength is hardened, so that additional next injection equipment for improving the soft ground can be smoothly and safely inputted, and then a smooth horizontal drainage layer is also possible.

또한, 상기 콘베어(20)의 회전과 모래포설기의 진행장치인 구동롤러(14)의 회전속도를 조절하여 균일한 두께로 모래를 포설할 수 있는 바, 콘베어(20)의 회전을 느리게하고 구동롤러(14)의 회전을 빠르게 하면 얇은 두께로 균일하게 포설할 수 있고, 반대로 콘베어(20)의 회전을 빠르게 하고 구동롤러(14)의 회전을 느리게 하면 두꺼운 두께로 균일하게 포설할 수 있는 것이다.In addition, by adjusting the rotational speed of the drive roller (14), the rotation of the conveyor 20 and the sand spreader, the sand can be laid with a uniform thickness, and the rotation of the conveyor (20) is slow and driven. The faster the rotation of the roller 14 can be uniformly laid in a thin thickness. On the contrary, the faster the rotation of the conveyor 20 and the slower the rotation of the drive roller 14 can be laid in a thicker thickness.

다음은 본 발명의 이실시예를 도 4 및 도 5를 토대로 살펴보기로 한다.Next, this embodiment of the present invention will be described with reference to FIGS. 4 and 5.

이실시예에 의한 모래포설기를 이용하여 초연약지반이나 물과 뻘이 혼재된 지역 등의 습지에 모래를 포설하고자 할 경우에는 콘베어(20)가 동작되지 않게 정지시킨 상태에서 모래적재함(22)에 모래를 채워넣으면, 호퍼부(23)하측의 개구부를 통하여 모래가 새어 나와 호퍼부(23)의 하측과 인접하게 설치되어 있는 콘베어(20)의 모래수수부에 쌓이게 된다.In the case of using sand sander according to this embodiment to install sand in wet ground, such as ultra soft ground or water and water mixed area, the conveyor 20 is stopped in the sand storage 22 in the stopped state. When the sand is filled, the sand leaks out through the opening portion under the hopper portion 23 and accumulates in the sand receiving portion of the conveyor 20 provided adjacent to the lower side of the hopper portion 23.

이렇게 모래수수부에 쌓이는 모래는 호퍼부(23) 하측과 콘베어(20)의 모래수수부와는 소정의 간견을 두고 있어서 일정량만 모래수수부에 쌓이고 나머지는 모래적재함(22)의 내측에 채워지게 되는 것이다.The sand accumulated in the sand sintered part has a predetermined distance from the bottom of the hopper 23 and the sand stalk part of the conveyor 20 so that only a predetermined amount is accumulated in the sand sintered part and the rest is filled in the sand carrier 22. Will be.

상기와 같이 모래적재함(22)에 모래가 적재된 상태에서 모래를 포설할 연약지반으로 모래포설기가 주행을 하면, 위에서 살펴본 바와 같이 모래포설기의 양측하방에 설치된 캐터필러폰툰(11)이 부력이 작용하도록 밀폐된 통체형태로 형성되어서 초연약지반이나 물과 뻘이 혼재된 지역 등의 습지에서도 모래포설기가 빠지지 않고 주행할 수 있게 된다.As described above, when the sand spreader travels on the soft ground to install sand in the sand loading state 22 as described above, the caterpillar pontoon 11 installed on both sides of the sand spreader is buoyant as described above. It is formed in a closed cylindrical shape so that sand spreaders can travel in wetlands such as ultra soft ground or areas where water and water are mixed.

상기와 같이 모래포설기가 주행하는 과정에서 연약지반에 모래를 포설하고자 할 경우에는 콘베어구동용 구동모터(21)를 구동시켜서 콘베어(20)가 선회이동되면, 초기에 모래수수부에 쌓인 모래가 콘베어(20)의 모래포설부측으로 이동하게 되고, 호퍼부(23)의 하측 개구부에서는 모래가 계속적으로 새어나와 콘베어(20)의 상측에 동일한 두께로 분포되면서 적재된다.When sand is to be laid on the soft ground in the process of sand sander running as described above, when the conveyor 20 is pivoted by driving the drive motor 21 for driving the conveyor, the sand accumulated in the sand mill is initially conveyed to the conveyor. The sand 20 is moved to the sand spreading portion side, and sand is continuously leaked from the lower opening of the hopper portion 23 and is loaded while being distributed with the same thickness on the upper side of the conveyor 20.

이렇게 콘베어(20)의 상부에 균일한 두께로 모래가 실리면서 콘베어(20)는 계속 전방측으로 선회이동함에 따라 콘베어(20)에 적재되어 있는 모래는 모래포설부에서 모래를 포설할 연약지반으로 흘러내리면서 균일한 두께로 포설된다.As the sand is loaded on the upper portion of the conveyor 20 with a uniform thickness, the conveyor 20 continues to move forward and the sand loaded on the conveyor 20 flows from the sand laying part to the soft ground to install sand. As it is lowered, it is laid in a uniform thickness.

상기와 같이 모래포설기가 주행하는 전방에 모래가 균일한 두께로 포설됨에 따라 연약지반이 균일한 강도로 단단해져 연약지반을 개량할 차기장비투입도 원활하고 안전하게 투입할 수 있게 되는 것이며, 이후 원활한 수평배수층의 역할도 가능하게 되는 것이다.As sand is laid in a uniform thickness in front of the sand spreader as described above, the soft ground becomes hard with uniform strength, so that the next equipment input to improve the soft ground can be smoothly and safely injected, and then the smooth horizontal drainage layer. The role of is also possible.

한편, 본 발명의 모래포설기는 모래적재함(22)에 다량의 모래가 적재되면서 모래적재함(22)의 폭이 넓어서 모래적재함(22)의 하측이 휠 염려가 있는데, 모래적재함(22)의 하측에는 받침지지구(16)가 상향으로 받치고 있어서 모래적재함(22)의 하부가 휠 염려가 없게 되며, 상기와 같이 모래적재함(22)의 하부가 휠 염려가 없으므로 호퍼부(23)의 개구부와 콘베어(20)의 모래수수부와의 간격을 일정하게 유지하여 콘베어(20)의 상부에 일정한 두께로 모래가 적재된다.On the other hand, the sand spreader of the present invention is a large amount of sand is loaded on the sand carrier 22, the width of the sand carrier 22 is wide, there is a concern that the lower side of the sand carrier (22), the lower side of the sand carrier (22) Since the support base 16 is supported upward, the lower portion of the sand carrier 22 is not concerned with wheels, and the lower part of the sand carrier 22 is not concerned with wheels as described above. The sand is loaded with a constant thickness on the upper portion of the conveyor 20 by maintaining a constant distance from the sand mill of 20).

또한, 상기 콘베어(20)의 회전과 모래포설기의 진행장치인 구동롤러(14)의 회전속도를 조절하여 균일한 두께로 모래를 포설할 수 있는 바, 콘베어(20)의 회전을 느리게하고 구동롤러(14)의 회전을 빠르게 하면 얇은 두께로 균일하게 포설할 수 있고, 반대로 콘베어(20)의 회전을 빠르게 하고 구동롤러(14)의 회전을 느리게 하면 두꺼운 두께로 균일하게 포설할 수 있는 것이다.In addition, by adjusting the rotational speed of the drive roller (14), the rotation of the conveyor 20 and the sand spreader, the sand can be laid with a uniform thickness, and the rotation of the conveyor (20) is slow and driven. The faster the rotation of the roller 14 can be uniformly laid in a thin thickness. On the contrary, the faster the rotation of the conveyor 20 and the slower the rotation of the drive roller 14 can be laid in a thicker thickness.

이상에서 살펴본 바와 같은 본 발명에 따른 습지주행용 모래포설기는, 모래포설기의 하체 특히 캐터필러폰툰이 소정의 부력이 작용할 수 있는 통체형태로 형성되어 초연약지반 및 물과 뻘이 혼재된 지역에서도 빠지지 않으면서 원활하고 안전하게 주행이 가능한 장점을 지니고 있고, 상기와 같이 모래포설기가 습지에 빠지지 않으면서 모래포설기가 진행하는 전방에 콘베어의 회전속도와 구동롤러의 회전속도를 적절하게 조절하여 일정한 두께로 모래를 포설할 수 있기에 연약지반을 균일한 강도로 개량할 수 있고, 균일하게 포설된 모래는 원활한 수평배수층의 역할을 하게 되는 것이다.Wet sand sander according to the present invention as described above, the lower body of the sand sander in particular, caterpillar pontoons are formed in a tubular shape in which a predetermined buoyancy can act to fall in the ultra soft ground and water and water mixed area It has the advantage that it can run smoothly and safely without having to, and as mentioned above, sand sander has a certain thickness by appropriately adjusting the rotation speed of the conveyor and the driving roller in front of the sand spreader without the sand spreader falling into the wetland. Since it is possible to install the soft ground can be improved to a uniform strength, evenly laid sand is to act as a smooth horizontal drainage layer.

또한, 본 발명의 모래포설기가 진행하는 전방에 일정한 두께로 모래를 포설할 수 있으므로 해서 모래포설거리가 먼 경우에도 안전하게 모래를 포설할 수 있고, 이로 인하여 면적이 넓은 연약지반을 효과적으로 개량할 수 있는 등의 매우 특출한 효과가 있는 것이다.In addition, sand can be laid in a predetermined thickness in front of the sand spreader of the present invention, so that sand can be laid safely even when the sand spreading distance is long, thereby effectively improving the soft ground having a large area. There is a very outstanding effect.

Claims (2)

습지 등의 연약지반에 모래를 포설하여 연약지반을 단단하게 하는 습지주행용 모래포설기에 있어서,In the sand spreading machine for wetland driving, where sand is laid on the soft ground such as a wetland to harden the soft ground, 프레임(15)의 양측에는 속이 비어 부력이 작용하는 캐터필러폰툰(11)이 고정설치되고, 상기 캐터필러폰툰(11)의 외주연에는 다수개의 트랙슈(12)가 링크식으로 연결된 캐터필러(13)가 구동롤러(14)에 의해 선회토록 권회설치되어 하체(10)를 구성하며,Caterpillar pontoon 11 is fixed to the both sides of the frame 15 is hollow buoyancy acting, the caterpillar 13 is connected to a plurality of track shoes 12 in the outer periphery of the caterpillar pontoon (11) It is wound by the drive roller 14 so as to turn and constitutes the lower body 10, 상기 하체(10)의 상측에는 모래가 적재되어 연약지반에 모래를 살포하는 콘베어(20)가 구동모터(21)에 의해 선회토록 설치되고, 상기 콘베어(20)의 양측에는 모래유실커버(25)가 설치된 것을 특징으로 하는 습지주행용 모래포설기.On the upper side of the lower body 10, the sand is loaded and the conveyor 20 for spraying the sand on the soft ground is installed to be swiveled by the drive motor 21, and the sand loss cover 25 is provided on both sides of the conveyor 20. Wet running sand spreader characterized in that the installation. 제 1항에 있어서, 상기 하체(10)의 상측에는 하측이 개구된 호퍼부(23)를 구비한 모래적재함(22)이 지지대(24)에 의해 설치된 것을 특징으로 하는 습지주행용 모래포설기.The wet sander according to claim 1, wherein a sand storage box (22) having a hopper portion (23) having an open lower side is installed by a support (24) on an upper side of the lower body (10).
KR1019980009152A 1998-03-11 1998-03-11 Wet sanders KR100280694B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019980009152A KR100280694B1 (en) 1998-03-11 1998-03-11 Wet sanders

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019980009152A KR100280694B1 (en) 1998-03-11 1998-03-11 Wet sanders

Publications (2)

Publication Number Publication Date
KR19980019437A KR19980019437A (en) 1998-06-05
KR100280694B1 true KR100280694B1 (en) 2001-02-01

Family

ID=65909133

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019980009152A KR100280694B1 (en) 1998-03-11 1998-03-11 Wet sanders

Country Status (1)

Country Link
KR (1) KR100280694B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101037956B1 (en) * 2008-05-22 2011-05-31 이재주 The driving machine for the damp gro und by using gyrosensor

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100458381B1 (en) * 2001-10-30 2004-12-03 삼성중공업 주식회사 Construction method of sand-mat for reinforcing ground of weakness
KR20040045589A (en) * 2002-11-25 2004-06-02 (주)하나공사 Equipment and method for placing of drainage material on soft ground improvement

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101037956B1 (en) * 2008-05-22 2011-05-31 이재주 The driving machine for the damp gro und by using gyrosensor

Also Published As

Publication number Publication date
KR19980019437A (en) 1998-06-05

Similar Documents

Publication Publication Date Title
CN111749088B (en) Road construction is with shakeout device
CN106759603A (en) One kind automation city river irrigation canals and ditches sludge removal equipment
CN106759604A (en) A kind of municipal channel cleanout harnessing project silt cleaning machinery
KR100280694B1 (en) Wet sanders
CN106315118A (en) Single chain type earthwork vertical lifting device
CN212573725U (en) Organic covering laying device
KR100750342B1 (en) A traveling type of soil transportation apparatus using expansible and contractible conveyer and backfilling method using the soil transportation apparatus
US5282694A (en) Method of reclaiming abandoned settling ponds
KR100467174B1 (en) Apparatus for spreading materials for reinforcing the ground for approach of equipments to the soft ground
US4462747A (en) Material conveyor for use with a backhoe
KR200427979Y1 (en) A Traveling Type of Soil Transportation Apparatus Using Expansible and Contractible Conveyer
KR100672815B1 (en) Sand spreader apparatus and method on water
US3587825A (en) Jackknife type conveyor for reclaiming material
KR100898806B1 (en) The construction method and apparatus for spreading materials for reinforcing theground for approach of equipments to the soft ground
KR200398546Y1 (en) equipment for sand distribution works
KR100517388B1 (en) A Motional Sprayer,A Belt Conveyor System with the Motional Sprayer and Backfilling Method using the Belt Conveyor System
JP2004060261A (en) Construction method and construction device for slope seepage control work and apparatus carrying device
KR200337858Y1 (en) A Motional Sprayer and A Belt Conveyor System with the Motional Sprayer
KR100458381B1 (en) Construction method of sand-mat for reinforcing ground of weakness
CN212505739U (en) Mechanical paving device for horizontal subsurface flow constructed wetland filler
KR20100062412A (en) Soil scattering apparatus using conveyer
KR100550674B1 (en) An apparatus and a spreading method by moving belt sprayer
KR20070078525A (en) Improvement method for soft ground
CN220035081U (en) Wet spraying road mixing type surface soft foundation rapid treatment equipment
KR200296438Y1 (en) Apparatus for spreading materials for reinforcing the ground for approach of equipments to the soft ground

Legal Events

Date Code Title Description
A201 Request for examination
G15R Request for early opening
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20071109

Year of fee payment: 8

LAPS Lapse due to unpaid annual fee