KR100257658B1 - Method for constructing and dismantling concrete forms safely - Google Patents

Method for constructing and dismantling concrete forms safely Download PDF

Info

Publication number
KR100257658B1
KR100257658B1 KR1019970027147A KR19970027147A KR100257658B1 KR 100257658 B1 KR100257658 B1 KR 100257658B1 KR 1019970027147 A KR1019970027147 A KR 1019970027147A KR 19970027147 A KR19970027147 A KR 19970027147A KR 100257658 B1 KR100257658 B1 KR 100257658B1
Authority
KR
South Korea
Prior art keywords
yoke
slab
panel
support
frame panel
Prior art date
Application number
KR1019970027147A
Other languages
Korean (ko)
Other versions
KR19990003302A (en
Inventor
박선근
Original Assignee
박양근
주식회사우림엔지니어링건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박양근, 주식회사우림엔지니어링건축사사무소 filed Critical 박양근
Priority to KR1019970027147A priority Critical patent/KR100257658B1/en
Publication of KR19990003302A publication Critical patent/KR19990003302A/en
Application granted granted Critical
Publication of KR100257658B1 publication Critical patent/KR100257658B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/22Stiff scaffolding clamps for connecting scaffold members of common shape for scaffold members in end-to-side relation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/18Scaffolds primarily resting on the ground adjustable in height
    • E04G1/20Scaffolds comprising upright members and provision for supporting cross-members or platforms at different positions therealong

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PURPOSE: A frame panel and a pillar installing method is provided to safely install or release the frame panel while forming a pillar, a beam and a slab by establishing concrete. CONSTITUTION: A pillar(1) supports a frame panel and engages a control nut(6) with a stopping nut(7) by forming a screw thread(3) on an upper outer circumference of an outer pipe(2) having a supporter(8). A long hole(4) penetrates on a portion forming the screw thread. A head protrusion(11) is mounted on upper side of a through hole(10) combining a fixing bar(5) with a specific interval on both sides of an inner pipe(9) inserted to inside of the outer pipe. A recessed groove rotating at 360 degrees by connecting to the head protrusion is mounted an extended piece(13) composing a sleeper back(12) of U-shape. Thereby, the frame panel forms the sleeper back of U-shape on an upper portion of the pillar to safely construct by preventing the sleeper from releasing on the pillar.

Description

건축용 지주대와 형틀판넬을 안전하게 설치 및 해체하는 방법How to safely install and dismantle building struts and form panels

제1도는 본 발명의 지주대를 나타내는 사시도.1 is a perspective view showing the holding post of the present invention.

제2도는 본 발명 지주대의 멍에받침 종단면도.Figure 2 is a longitudinal cross-sectional view of the yoke support of the present invention.

제3도는 건축의 기둥과 보를 설치하는 상태의 일예를 나타내는 상태의 평면도.3 is a plan view of a state showing an example of a state of installing the pillars and beams of construction.

제4도는 건축상태에 따라 가로강관과 세로강관으로 지주대를 사방으로 일정한 간격을 두어 고정시키는 상태의 평면 예시도.4 is a plan view showing a state in which the holding posts are fixed at regular intervals in all directions by the horizontal steel pipe and the vertical steel pipe according to the construction state.

제5도를 보를 지지하는 지주대를 설치하는 상태를 나타내는 평면 예시도.Fig. 5 is a planar exemplified diagram showing a state in which a support stand supporting the beam is installed in Fig. 5.

제6도는 본 발명 지주대의 멍에받침에 멍에를 삽입설치한 상태를 나타내는 평면 예시도.Figure 6 is a plan view showing a state in which the yoke is inserted into the yoke support of the holding post of the present invention.

제7도는 지주대 멍에받침에 설치고정한 멍에의 상부로 장선과 각각의 패널을 설치하는 상태를 나타내는 평면 예시도.7 is a plan view showing the state of mounting the joist and each panel to the upper portion of the yoke fixed to the support stand yoke support.

제8도는 지주대와 강관비계 및 각각의 판널을 설치완료한 상태의 정면예시도.8 is a front view of the holding post, steel pipe scaffolding and each panel is installed.

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

1 : 지주대 2 : 외측관1: holding post 2: outer tube

6 : 조절너트 7 : 멈춤너트6: Adjustment nut 7: Stop nut

9 : 내측관 11 : 헤드돌기9: inner tube 11 head projection

12 : 멍에받침 13 : 연장편12: yoke support 13: extension

14 : 요홈 19,22 : 가로강관비계14: groove 19,22: horizontal steel pipe scaffolding

20,21 : 세로강관비계 23,24 : 멍에20,21: longitudinal steel scaffolding 23,24: yoke

25,26,27 : 장선 28 : 보측면형틀판넬25, 26, 27: joist 28: beam side frame panel

29 : 기둥형틀판넬 30,30a,30b,30c : 슬라브 형틀판넬29: pillar frame panel 30, 30a, 30b, 30c: slab frame panel

31,31a : 보바닥형틀판넬31,31a: Bottom frame panel

본 발명은 단층이나 고층으로 형성을 하는 최근 콘크리트 건물에 있어서 기둥과 슬라브를 받쳐주는 보 및 슬라브를 콘크리트로 형성을 함에 콘크리트 양생용 형틀을 안전하고 손쉽게 설치 및 해체를 할 수 있도록 하기 위한 건축용 형틀판넬을 안전하게 설치 및 해체하는 방법에 관한 것이다.The present invention is a formwork panel for building and dismantling the concrete curing mold safely and easily in forming concrete beams and slabs supporting pillars and slabs in a concrete building recently formed in a single or high-rise To safely install and dismantle it.

일반적으로 철근과 콘크리트 및 벽돌을 사용하여 건축을 함에 있어 기둥과 보 및 슬라브를 콘크리트로 형성하기 위해서는 목제와 합판으로 제작하는 판널을 지주대로 지지하도록 함으로서 건물의 외각 형태를 형성시키고 이에 콘크리트를 타설시켜서 양생을 시킨 다음 다시 위층을 상기와 같은 방법으로 형성을 하고 있는 실정이었다.In general, in the construction of reinforcement, concrete, and brick, in order to form pillars, beams, and slabs into concrete, it is necessary to support panels made of wood and plywood as supporters to form the exterior shape of the building and cast concrete on it. After curing, the upper layer was formed in the same manner as described above.

이러한 철근과 콘크리트로 건축을 형성함에 있어 설치하고자 하는 기둥의 위치를 설정후 기둥형상에 맞도록 형성한 기둥형틀판넬을 설치하고, 기둥과 기둥의 사이를 연결하는 보의 형틀중 보바닥형틀판넬을 바닥에서 제작을 한 다음 보가 형성되는 높이로 올려서 설치고정함과 동시에 지주대로서 보바닥형틀을 지지하며, 보바닥형틀판넬의 설치가 완료되면 보측면형틀판넬을 보바닥형틀판넬의 상부양측으로 설치고정한다.In the construction of reinforcing steel and concrete, after setting the position of the column to be installed, install the pillar frame panel formed to fit the column shape and install the beam floor frame panel among the frame of the beam connecting the pillar and the pillar. After making from the floor, it is fixed to the height where the beam is formed and fixed at the same time, supporting the bottom frame as a support stand.When the installation of the bottom frame panel is completed, the side frame panel is fixed to the upper sides of the bottom frame panel. do.

그리고 슬라브를 지지하는 멍에와 장선을 지주대로 일정한 간격과 높이가 유지되도록 설치를 하고, 그 위에 슬라브 형틀판넬을 설치함으로 기둥과 보 및 슬라브의 형틀설치가 완료된다.And the yoke and the joist for supporting the slab are installed to maintain a certain distance and height as a holding post, and the installation of the pillar, beam and slab is completed by installing the slab form panel thereon.

그러나 이와 같이 형틀판넬 중 보바닥형틀판넬을 일정한 높이로 설치함에 있어 기둥과 기둥간의 거리가 천차만별이나 가정집의 경우에는 보통 12자의 거리가 보통이고, 상가의 건물에는 23자의 거리가 보통이며, 보바닥형틀판넬을 형성하는 보의 넓이는 일정하지 않으므로 보바닥형틀판넬의 넓이는 보의 넓이에 1자의 넓이를 더한 넓이로 형성을 하며, 보바닥형틀판넬을 형성하기 위해서는 형틀판넬의 하부에 45×90싸이즈를 갖는 각재의 목재를 설치고정을 시킴으로 보바닥판넬을 형성시 M2당 40~50k형틀판넬이 됨으로 가정집을 형성하기 위해서는 2.5자(보의 넓이를 1.5자로 할시)×12자이면 보바닥형틀의 무게는 110~135k형틀판넬이고 보측면형틀판넬까지 조립을 하면 270~330k형틀판넬이 됨을 알수 있고, 상가건물을 형성하기 위해서는 2.5자(보의 넓이를 1.5자로 할시×23자이면 210~260k형틀판넬이 되며 보측면형틀판넬까지 조립을 하면 510~630k형틀판넬이 됨으로서 이를 일정한 높이로 올려서 기둥형틀판넬에 양측을 고정시키기 위해서는 인부가 5~7명의 인원을 필요로 하고 있으며, 이를 적은 인원의 인부를 사용하기 위해서는 크레인으로 들어서 설치를 하고 있는 실정이었다.However, in installing the bottom frame panels among the frame panels at the same height, the distance between the pillars and the pillars varies widely, but in the case of homes, the distance is usually 12 characters, and the distance between the pillars is 23 characters. Since the width of the beam forming the mold panel is not constant, the width of the beam bottom mold panel is formed by adding the width of one beam to the width of the beam.In order to form the bottom mold panel, 45 × 90 at the bottom of the mold panel in order to make the timber of a timber having a customer specification sikimeuro the installation fixed in forming the beam bottom panel doemeuro is 40 ~ 50k formwork panels per M 2 form a private home is 2.5 chair (Halsey a beam width of 1.5 character) × 12 characters beams bottom flask The weight of the panel is 110 ~ 135k type panel, and if it is assembled to the beam side frame panel, it can be seen that it becomes 270 ~ 330k type panel panel. To form the mall building, it is 2.5 characters (the width of the beam is 1.5 characters. If it is x23 characters, it becomes 210 ~ 260k type panel and if it is assembled to the beam side frame panel, it becomes 510 ~ 630k type panel. To raise it to a certain height and fix both sides to the column type panel, the worker has 5 ~ 7 people. In order to use a small number of laborers, the situation was installed by lifting a crane.

이와 같이 많은 인원이 들어가거나 특수장비인 크레인을 사용하여 보를 형성하여도 기둥형틀판넬이 견고히 고정이 되어 있지를 않아서 기둥형틀판넬과 보형틀판넬이 불안정하게 설치되어 있음으로 기둥형틀판넬과 보형틀판넬의 상부에서 일을 하는 인부들이 떨어져 부상을 입게되는 등의 문제점이 있었다.Thus, even if a large number of people enter or use a special equipment crane to form a beam, the column frame panel and the frame frame panel are unstable, so the column frame panel and the frame frame panel are unstable. Workers who work at the upper part of the fall and were injured.

또한 각각의 형틀판넬을 설치하여 콘크리트를 타설하고 타설된 콘크리트가 완전히 양생이 되면 형틀판넬을 지지하고 있던 지주대를 제거하고 각각의 형틀판넬을 제거하게 되는데 이는 각각의 형틀판넬이 천정인 상부측에 설치가 되어 있어 지주대를 제거하면 일시에 형틀판넬이 떨어지게 됨으로 아래에서 형틀판넬을 제거하는 인부를 보호하는 안정장치가 없음으로 인부가 불안한 상태에서 작업을 하여야만 하였었고, 이같이 인부가 안전장치도 없이 형틀판넬의 해체작업을 하는 도중에 형틀판넬이 일시에 떨어지면서 작업을 하던 인부를 덮쳐서 대형사고가 빈번하게 발생하였으며, 형틀판넬이 천정부분에서 바닥으로 일시에 떨어지면서 형틀판넬간이 서로 부딪쳐서 형틀판넬이 손상됨으로 재 사용이 불가능하게 되는 등의 문제점이 있었다.In addition, when each mold panel is installed and concrete is completely cured, the caster supporting the mold panel is removed, and each mold panel is removed. When the holding stand is removed, the mold panel falls off at once, so there is no stabilizer to protect the worker from removing the mold panel from below. Therefore, the worker had to work in an unstable state. During the dismantling of the mold panel, a large accident occurred frequently because the mold panel fell temporarily and struck the laborer, and the mold panel fell to each other from the ceiling to the floor. There was a problem such that it is impossible to reuse because of damage.

이와 같은 제반문제점을 감안하여 안출되었던 고안이 공개번호 제96-17822호인 건축용 받침지주가 있으나, 이는 패널을 지지하는 보를 받쳐주도록 하는 지주로서 보가 안전하게 받침지주의 상부에 안착이 되어 있도록 상부받침구를“

Figure kpo00001
”형상의 클립을 형성함으로 보가 안전하게 상부받침구에 위치하여 안전사고를 예방할 수는 있는 실정이었다.In view of the above problems, there is a construction support column, which is designed to be published No. 96-17822, but it is a support to support the beam supporting the panel, so that the upper support is securely seated on the upper support column. “
Figure kpo00001
“By forming a clip, the beam can be safely placed on the upper support, preventing a safety accident.

그러나 건축용 받침지주가 터언버클(Turnbuckle)의 형상으로 이루어져 상,하부받침구가 고정이 된 상태에서 핸들로서 지주를 돌려 상,하부받침구가 인출되거나 인입이 되도록 함으로 받침지주의 길이를 조절하도록 되어 있음으로 이는 보의 상부에 판널을 설치한 상태에서 판널의 상부에서 작업인부가 작업을 하면 받침지주에 무게가 가중이 됨이 연속적으로 반복이 됨으로 받침지주의 길이조절기능상 나사형식으로 이루어져 있어 지주가 회전이 됨으로서 받침지주가 짤아지게 되어 받침지주의 역할을 제대로 하지를 못하였으며, 받침지주의 길이를 설정한 상태에서 상부받침구에 보를 안착시키기 위하여 클립을 보의 길이부분으로 회전시키면 상부받침구와 지주간이 나사산으로 결합되어 있어 받침지주의 길이가 변하게 되어 다시 받침지주의 길이를 조절하여야 함으로 건축의 작업을 하는데에 많은 어려움이 있었다.However, the supporting base is made of the shape of the turnbuckle, and the upper and lower supporters are turned to handle the upper and lower supporters to be pulled out or pulled in order to adjust the length of the support base. This is because the weight is added to the supporting column continuously when the worker works on the upper part of the panel while the panel is installed on the upper part of the beam. As the supporting base was squeezed due to the rotation, it could not function properly as the supporting base. When the length of the supporting base is set, the clip is rotated to the length of the beam to seat the beam on the upper supporting port. The daytime is threaded, so the length of the supporting column changes, By section shall there were a lot of difficulties in the operation of the building.

그리고 공개번호 제97-2024호인 건축용 받침지지대는 지지대의 하부에 나사산을 형성하는 나사축을 설치함으로 조절판으로서 받침지지대의 길이를 조절하고, 조절판의 하부에 잠금판을 형성하여 조절판이 외부의 충격에 의해 회전되는 것을 방지하여 받침지지대의 길이의 변화가 없도록 하고는 있으나, 보와 접하는 상부분이 평면상태로 이루어져 있어 보가 안정되게 안착이 잘되지를 않고 받침지지대가 지면과 상부의 보의 하부에 접하여져 있음으로 받침지지대가 넘어질수 있는 사항이 비일비재하여 안전하고의 위험이 빈번한등의 문제점이 있었다.And the support base for the construction of the Publication No. 97-2024 is to adjust the length of the support base as a throttle by installing a screw shaft forming a screw thread in the lower portion of the support, forming a locking plate on the lower side of the throttle to prevent the throttle Although it prevents rotation, there is no change in the length of the support, but the upper part in contact with the beam is made in a flat state so that the beam is not settled stably, and the support is in contact with the lower part of the ground and the upper beam. There was a problem that the support braces could fall and the safety and risks were frequent.

본 발명은 건축을 함에 있어 형틀판넬을 설치시에 형틀판넬을 지지하는 지주대의 상부에“

Figure kpo00002
”자 형상의 멍에받침을 형성하여 멍에가 지주대에서 이탈이 되지 않도록하여 안전하게 형틀판넬의 시공을 할 수 있도록 하고, 지주대를 설치고정한 상태에서 지주대의 상부에 멍에와 장선 및 각각의 형틀판넬을 순차적으로 설치 및 조립을 할 수 있도록 하여 적은 인원으로도 형틀판넬의 시공을 할 수 있도록 하며, 해체시에 설치하였던 형틀판넬이 일시에 떨어지지 않도록 일측부터 차례로 해체작업을 하여 작업인부의 부상을 방지하고 판널의 손상을 방지하여 형틀판넬의 재사용이 가능하도록 하는데 주목적이 있는 것으로 이를 첨부한 도면에 의거하여 보다 상세히 설명하면 다음과 같다.According to the present invention, in the construction, the upper part of the holding post supporting the mold panel at the time of installing the mold panel “
Figure kpo00002
”The yoke-shaped yoke support is formed so that the yoke does not escape from the support stand so that the construction of the form panel can be done safely. The yoke, joist, and each form panel are placed on the upper part of the support stand with the support stand fixed. It can be installed and assembled sequentially so that the mold panel can be constructed with a small number of people.In order to prevent the falling of the mold panel installed at the time of disassembly, it is necessary to dismantle from one side in order to prevent injuries of workers. The main purpose is to prevent the damage of the panel to enable the reuse of the mold panel as described in more detail based on the accompanying drawings as follows.

제1도 내지 제2도에 도시한 바와 같이 각각의 형틀판넬을 지지하는 지주대(1)를 형성함에 있어 하부에 받침대(8)를 갖는 외측관(2)의 상부외주연에 나사산(3)을 형성하여 조절너트(6)와 멈춤너트(7)를 결합하고, 나사산(3)이 형성된 부분에 양측으로 관통하는 장공(4)을 형성하여 이루어지며, 상기 외측관(2)의 내측으로 삽입될 수 있는 내측관(9)의 양측으로 상부에서 하부로 일정한 간격을 두고 고정봉(5)이 결합할 수 있는 통공(10)을 형성한 상부측으로 헤드돌기(11)를 형성하고, 헤드돌기(11)가 결합하여 360°회전을 할 수 있는 요홈(14)을 갖는 연장편(13)이 하주측에 형성하는“

Figure kpo00003
”형상의 멍에받침(12)으로 구성한다.As shown in FIGS. 1 to 2, in forming the support base 1 for supporting each mold panel, a screw thread 3 is formed on the upper outer periphery of the outer tube 2 having a pedestal 8 at the bottom thereof. It is formed by combining the adjustment nut (6) and the stop nut (7), and forms a long hole (4) penetrating to both sides in the portion formed with the thread (3), and inserted into the inner tube (2) On both sides of the inner tube (9) that can be formed at the top side to the top side to form a head projection (11) to the upper side to form a through hole 10 to which the fixed rod (5) can be coupled at regular intervals, and the head projection ( 11 is formed on the lower circumferential side of the extension piece 13 having a groove 14 that can be rotated 360 °
Figure kpo00003
”Consists of a shaped yoke support (12).

이와 같이 형성하는 지주대(1)를 사용하여 건축용 형틀판넬을 안전하게 설치 및 해체하는 방법에 대하여 설명하고자 한다.It will be described how to safely install and dismantle the building mold panel using the holding post (1) formed in this way.

[설치방법][How to install]

형틀판넬의 넓이는 3×6자로 이루어진 합판을 사용하는 것을 일예로 들어서 설명하고자 한다.The width of the mold panel will be described using an example of using 3 × 6 plywood.

[제1공정][Step 1]

제3도에 도시한 바와 같이 먼저 기둥(15,15a,15b,15c,16,16a,16b,16c)과 큰보(17,17a,17b,17c) 및 작은보(18,18a,18b)가 설치되는 위치인 바닥에 먹줄을 긋는다.As shown in FIG. 3, columns 15, 15a, 15b, 15c, 16, 16a, 16b and 16c, beams 17, 17a, 17b and 17c and small beams 18, 18a and 18b are first installed. Draw a line on the floor where it will be.

[제2공정][Step 2]

바닥에 먹줄을 그은 상태에서 지주대(1)를 설정된 가로와 세로간에 일정한 거리의 위치를 설정하여 세워서 설치를 하되 건축자재인 강관비계로서 가로강관비계(19)와 세로강관비계(20)로서 지주대(1) 외측관(2)의 나사산(3) 하부측인 상,하부측에 고정시키고 이때에 지주대(1)의 상부에 설치되는 가로 강관비계(19)와 세로강관비계(20)의 위치높이는 슬라브형틀판넬(30,30a,30b,30c)간과의 거리가 1500mm(5자)이상을 넘지 않도록 설치하며, 가로강관비계(19)와 세로강관비계(20)가 맞나는 위치에 지주대(1)가 고정설치됨으로 지주대(1)와 가로강관비계(19) 및 세로강관비계(20)가 슬라브를 지지 및 발판역활을 하도록 제4도에 도시한 바와 같이 설치한다.In the state of drawing on the floor, the holding post 1 is set up and set up at a predetermined distance between the set horizontal and vertical, but is installed as a building material steel pipe scaffolding as horizontal steel pipe scaffolding 19 and vertical steel pipe scaffolding 20 1 of the horizontal steel pipe scaffold 19 and the vertical steel pipe scaffold 20 which are fixed to the upper and lower sides of the lower end of the thread 3 of the outer tube 2 and are installed at the upper part of the support base 1 at this time. Position height shall be installed so that the distance between slab frame panels (30, 30a, 30b, 30c) does not exceed 1500mm (5 characters) or more, and the holding post is located at the position where the horizontal steel scaffolding (19) and the vertical steel scaffolding (20) are fitted. (1) is fixedly installed, as shown in FIG. 4 so that the holding post 1, the horizontal steel pipe scaffold 19, and the vertical steel pipe scaffold 20 support the slab and serve as scaffolding.

[제3공정][Step 3]

지주대(1)를 가로와 세로로 일정한 거리를 두어 세워설치하고 가로강관비계(19)와 세로강관비계(20)로서 지주대(1)를 고정시키고 난 후 기둥(15,15a,15b,15c,16,16a,16b,16c)간의 사이와 슬라브의 하부에 설치하는 작은보(18,18b) 위치의 하부에 가로강관비계(22)와 세로강관비계(21)를 사용하여 보를 지지하는 지주대(1a)를 제5도에 도시한 바와 같이 일정한 간격으로 설치고정한다.The pillars (15, 15a, 15b, 15c) are installed at fixed distances vertically and horizontally from the struts (1), and then fixed to the struts (1) as horizontal steel scaffolds (19) and longitudinal steel scaffolds (20). Props for supporting beams using transverse steel scaffolding 22 and longitudinal steel scaffolding 21 in the lower part of small beams 18 and 18b installed between the sections 16, 16a, 16b, and 16c and at the bottom of slab. Installation (1a) is fixed at regular intervals as shown in FIG.

[제4공정][Step 4]

가로강관비계(19,22)와 세로강관비계(20,21)로서 세워고정시킨 지주대(1,1a)의 멍에받침(12)의 높이를 도면상 높이에서 형틀판넬과 멍에 및 장선의 두께를 뺀 상태의 높이에 맞게 높이를 조절한다.The height of the yoke support (12) of the props (1,1a) set up and fixed as the horizontal steel scaffolding (19,22) and the vertical steel scaffolding (20,21) is the thickness of the form panel, the yoke and the joist at the drawing height. Adjust the height to match the height of the subtraction.

이때에 많은 양으로 올리거나 내릴때에는 통공(10)과 고정봉(5)을 결합 또는 분리하여 조절하고, 작은 거리를 조절할때에는 조절너트를 죠이거나 풀어서 조절을 한 상태에서 멈춤너트(7)로서 조절너트(6)와 견고히 접하도록 죠여 놓으면 상부에서 작업을 하더라도 충격에 의한 조절너트(6)가 풀려져서 슬라브 및 보의 높이를 변형시키지 않게 된다.At this time, when raising or lowering a large amount, the through hole 10 and the fixed rod 5 are combined or separated to adjust, and when adjusting a small distance, the adjusting nut is tightened or released to adjust as a stop nut (7). Tightening so as to contact the nut (6) firmly, even if the work from the top to loosen the adjustment nut (6) by the impact does not deform the height of the slab and beam.

[제5공정][Step 5]

가로강관비계(19,22)와 세로강관비계(20,21)를 사용하여 세워고정시킨 지주대(1,1a)의 상부에 형성되어 있는 멍에받침(12)을 회전시켜서 큰보(17,17a,17b,17c)와 작은보(18,18a,18b)측은 보와의 직각이 되도록 하여 멍에받침(12)에 90×90mm 싸이즈인 목재의 멍에(24)를 삽입설치하고, 슬라브에 지지하는 지주대(1)의 멍에받침(12)을 회전시켜 일정한 일방향으로 향하도록 한 상태에서 멍에받침(12)에 90×90mm 싸이즈인 목재의 멍에(23)를 제6도에 도시한 바와 같이 설치고정한다.Rotating the yoke support 12 formed on the upper part of the props 1 and 1a fixed using the horizontal steel pipe scaffolding 19 and 22 and the vertical steel pipe scaffolding 20 and 21, the large beams 17, 17a, 17b, 17c) and small beams (18, 18a, 18b) are to be perpendicular to the beam so that yoke support (12) is fitted with a wooden yoke (24) of 90 × 90 mm size and is supported on the slab. In the state where the yoke support 12 of (1) is rotated to face in one direction, the yoke support 23 of wood having a size of 90 × 90 mm is fixed to the yoke support 12 as shown in FIG.

[제6공정][Step 6]

지주대(1,1a)의 멍에받침(12)에 멍에(23,24)를 설치고정한 상태에서 멍에(23,24)의 상부에 45×45mm 싸이즈와 45×90mm 싸이즈인 장선(25,26,27)을 설치고정하되 슬라브 부분은 합판의 넓이인 1.5자 간격으로 설치고정하고, 보부분은 보의 넓이에 1자를 더한 넓이 내측에 설치고정함을 제7도의 우측하단부에 도시한 바와 같다.The yoke (23, 24) is fixed to the yoke support (12) of the support stand (1, 1a), and the joist (25, 26, sized 45 × 45 mm and 45 × 90 mm is placed on the upper part of the yoke (23, 24). 27), but the slab part is fixed at the interval of 1.5 characters, which is the width of the plywood, and the beam part is fixed at the inner side of the width of the beam plus 1 character, as shown in the lower right part of FIG.

[제7공정][Step 7]

멍에(23,24)의 상부에 장선(25,26,27)을 설치고정한 상태에서 기둥(15,15a,15b,15c,16,16a,16b,16c)의 위치에 제작된 기둥형틀판넬(29)을 제7도의 좌측하부에 도시한 바와 같이 설치고정한다.Column frame panel 29 manufactured at the positions of pillars 15, 15a, 15b, 15c, 16, 16a, 16b, and 16c with the joists 25, 26 and 27 installed on the yoke 23 and 24. ) Is fixed as shown in the lower left of FIG.

[제8공정][Step 8]

멍에(23,24)의 상부에 장선(25,26,27)을 각각 설치고정한 상태에서 보가 설치되는 부분에는 보의 넓이 +1자×6자×9T(또는 12T)의 보바닥형틀판넬(31)과 양측의 쪽으로 이루어진 보바닥형특판넬(31a)을 설치고정하고, 슬라브측에는 3자×6자×9T(또는 12T)의 슬라브형틀판넬(30)을 사방양측이 일정한 간격이 유지되도록 장선(25,26,27)의 상부에 제7도의 좌측하부에 도시한 바와 같이 설치고정한다.In the part where the beams are installed while the joists (25, 26, 27) are fixed to the upper part of the yoke (23, 24), the bottom frame panel (31) of the width of the beam + 1 letter × 6 letters × 9T (or 12T) ) And the bottom floor special panel 31a formed on both sides, and on the slab side, the slab frame panel 30 of 3 × 6 × 9T (or 12T) is placed on the slab so that the sides are kept at regular intervals. , 26, 27, and fix it as shown in the lower left of FIG.

[제9공정][Step 9]

보바닥형틀판넬(31,31a)의 상부에 큰보(17,17a,7b,17c)와 작은보(18,18a,18b)의 설치위치에 맞게 먹줄을 긋고, 기둥형틀판넬(29)의 보설치 위치와 먹줄간을 일치시켜 기둥형틀판넬(29)과 보바닥형틀판넬(31a)을 고정설치한다.The beams of the columnar panel 29 are drawn by drawing a line in the upper part of the bottom frame panels 31 and 31a in accordance with the installation positions of the large beams 17, 17a, 7b and 17c and the small beams 18, 18a and 18b. Align the position with the ink line and fix the columnar frame panel 29 and the bottom frame panel (31a).

[제10공정][Step 10]

보바닥형틀판넬(31,31a)과 슬라브형틀판넬(30)을 설치고정한 상태에서 외측은 슬라브의 두께인 바닥의 높이에 맞고 내부측은 슬라브하부에 맞는 보측면형틀판넬(28,28a)을 큰보(17,17a,7b,17c)와 작은보(18,18a,18b)의 넓이에 맞게 제7도의 우측상부에 도시한 바와 같이 보바닥형틀판넬(31)의 상부에 설치고정한다.With the bottom floor frame panels 31 and 31a and the slab frame panel 30 installed and fixed, the outer side fits the height of the floor, which is the thickness of the slab, and the inside side beam side frame panels 28 and 28a fit the bottom of the slab. As shown in the upper right side of FIG. 7, the mounting fixture is fixed to the upper part of the bottom frame panel 31 according to the width of 17, 17a, 7b, 17c and the small beams 18, 18a, 18b.

[제11공정][Step 11]

슬라브형틀판넬(30)이 설치고정된 사방으로 슬라브형틀판넬을 설치하지 않은 부분에 내측으로 형성하는 보측면형틀판넬(28a)의 상부에 얹쳐지도록 하는 넓이로 제단한 슬라브형틀판넬(30a,30b,30c)을 제7도의 좌측상부에 도시한 바와 같이 설치고정함으로서 형틀판넬의 설치공정이 완전히 완료된다.Slab type frame panels 30a and 30b cut to an area so that the slab type panel 30 is mounted on the upper part of the beam side frame panel 28a which is formed inward in a portion where the slab frame panel is not installed. As shown in the upper left of Fig. 7, the installation process of the mold panel is completely completed.

또한 기둥형틀판넬(29)을 설치함에 있어 제1공정인 바닥에 먹줄을 그은후 제2공정으로 시행을 하면은 기둥형틀판넬(29)을 설치하기가 편리하게 이루어짐으로 기둥형틀판넬(29)의 설치를 제2공정으로 하여도 무방하다.In addition, in the installation of the columnar panel 29, the first step is to draw a line in the bottom, and if the second step is carried out in the installation of the columnar panel 29 is conveniently made of the columnar panel 29 The installation may be the second step.

이와 같이 건축용 형틀판넬을 설치함에 있어 지주대(1,1a)를 가로강관비계(19,22)와 세로강관비계(20,21)를 사용하여 세워서 고정을 시킴으로 설치한 강관비계(19,20,21,22)의 상부에 발판을 설치하여 멍에와 장선 및 각각의 형틀판넬의 설치를 눈높이 아래에서 작업을 할 수 있고, 각각의 멍에(23,24)와 장선(25,26,27) 및 보바닥형틀판넬(31,31a), 슬라브형틀판넬(30,30a,30b,30c), 보측면형틀판넬(28,28a)에 사용되는 자재를 원자재로 운반하여 설치하고자하는 장소부근에서 가공하여 설치고정을 할 수 있음으로 안전하고 편리하게 형틀판넬을 설치할 수 있게 된다.In this way, in installing the building frame panel for construction, the holding posts (1,1a) are installed by using the horizontal steel pipe scaffolding (19,22) and the vertical steel pipe scaffolding (20,21) to fix the steel pipe scaffolding (19,20, 21, 22) can be installed at the upper part of the yoke and joist and the installation of each mold panel at eye level, yoke (23, 24) and joist (25, 26, 27) and beam respectively The material used for the floor frame panels (31, 31a), slab frame panels (30, 30a, 30b, 30c), and the beam side frame panels (28, 28a) is transported as raw materials and fixed in the place where it is intended to be installed. It is possible to install the mold panel safely and conveniently.

그리고 설치된 형틀판넬에 콘크리트를 타설하고, 타설된 콘크리트가 완전히 양생이 되면 설치고정되어 있는 각각의 형틀판넬을 안전하게 해체함에 있어 이를 아래와 같이 상세하게 설명하고자 한다.And when the concrete is cast on the installed mold panel, when the cast concrete is completely cured, in the dismantling of each of the fixed mold panels fixed installation will be described in detail as follows.

[해체방법][Disassembly method]

[제1공정][Step 1]

기둥형틀판넬(29)을 분리제거하고 난 후 큰보(17,17a,17b,17c) 작은보(18,18a,18b)를 지지하고 있는 지주대(1a)의 멈춤너트(7)와 조절너트(6)를 풀어서 멍에(24)가 멍에받침(12)에서 빠질수 있을 정도만 멍에받침(12)을 하부로 이동을 시킨다.After removing and removing the columnar panel 29, the stop nut 7 and the adjusting nut (7) of the support base 1a supporting the beams 17, 17a, 17b, and 17c and the beams 18, 18a, and 18b are removed. 6) Loosen the yoke support (12) by moving the yoke support (12) to the bottom only enough to be out of the yoke support (12).

[제2공정][Step 2]

멍에받침(12)을 하부로 이동을 시킨 상태에서 멍에(24)와 보바닥형틀판넬(31,31a)의 사이에 설치고정되어 있는 장선(27)을 제거하면 멍에받침(12)에서 분리되어 있던 멍에(24)가 멍에받침(12)내로 떨어지면서 재 결합한다.In the state where the yoke support (12) is moved downward, the joist (27) fixed between the yoke (24) and the bottom frame panel (31, 31a) is removed and the yoke support (12) is separated from the yoke support (12). The yoke (24) falls into the yoke support (12) and rejoins.

[제3공정][Step 3]

장선(27)을 제거한 상태에서 보바닥형틀판넬(31,31a)을 보(17,17a,17b,17c,18,18a,18b)에서 제거를 한다.With the joist 27 removed, the bottom frame panels 31 and 31a are removed from the beams 17, 17a, 17b, 17c, 18, 18a and 18b.

[제4공정][Step 4]

보바닥형틀판넬(31,31a)을 제거한 상태에서 멍에받침(12)을 상부로 올려서 멍에(24)가 보(17,17a,17b,17c,18,18a,18b)의 하부에 견고히 받쳐주도록 조절너트(6)를 죠여서 콘크리트가 완전히 양생이 될 때까지 고정시킨다.The yoke support 12 is raised to the upper part by removing the bottom frame panels 31 and 31a so that the yoke 24 firmly supports the lower part of the beams 17, 17a, 17b, 17c, 18, 18a and 18b. Tighten the nut (6) until the concrete is completely cured.

[제5공정][Step 5]

큰보(17,17a,17b,17c)와 작은보(18,18a,18b)의 형틀판넬인 보바닥형틀판넬(28,28a) 및 장선(27)을 제거한후 큰보(17,17a,17b,17c)와 작은보(18,18a,18b)의 사이에 설치되어 있는 슬라브를 지지하고 있는 지주대(1)의 조절너트(6)와 멈춤너트(7)를 풀어서 멍에받침(12)을 멍에(23)와 떨어지도록 풀은 상태에서 멍에(23)와 슬라브형틀판넬(30,30a,30b,30c)의 사이에 고정설치되어 있는 장선(25,26)을 분리제거하면 멍에받침(12)과 분리되어 있던 멍에(23)는 멍에받침(12)내로 떨어지면서 멍에(23)가 멍에받침(12)과 재결합하게 되고, 장선(25,26)을 제거한 상태에서 슬라브형틀판넬(30,30a,30b,30c)을 슬라브에서 제거를 하며, 슬라브형틀판넬(30,30a,30b,30c)을 제거한 상태에서 멍에(23)를 제거한다.The beams 17, 17a, 17b, 17c and the beams 17, 17a, 17b, 17c after removing the bottom frame panels 28, 28a and the joist 27, which are the mold panels of the small beams 17, 17a, 17b, 17c and the small beams 18, 18a, 18b. ) And yoke support (12) to yoke (23) by unscrewing the adjusting nut (6) and the stop nut (7) of the support base (1) supporting the slab installed between the small beam (18, 18a, 18b). Loosen to be separated from the yoke support (12) by separating and removing the joist (25, 26) fixed between the yoke (23) and the slab-type panel (30, 30a, 30b, 30c) in the state separated from The yoke (23) was dropped into the yoke support (12), the yoke (23) is recombined with the yoke support (12), slab-shaped panel (30, 30a, 30b, 30c with the joists (25, 26) removed ) Is removed from the slab, and the yoke (23) is removed while removing the slab frame panels (30, 30a, 30b, 30c).

[제6공정][Step 6]

제5공정에서와 같은 방법으로 순차적으로 슬라브형틀판넬(30,30a,30b,30c)과 장선(25,26) 및 멍에(23)를 제거한다.The slab frame panels 30, 30a, 30b, 30c, the joists 25, 26 and the yoke 23 are sequentially removed in the same manner as in the fifth process.

[제7공정][Step 7]

슬라브를 지지하던 슬라브형틀판넬(30,30a,30b,30c)과 장선(25,26) 및 멍에(23)를 완전히 제거한 상태에서 지주대(1)와 가로강관비계(19,22)와 세로강관비계(20,21)를 제거하면 해체작업이 완전히 끝나게 되는 것이다.Slab-shaped panel (30, 30a, 30b, 30c), joist (25, 26) and yoke (23) that supported the slab were completely removed from the holding table (1), transverse steel scaffold (19, 22) and longitudinal steel pipe. If you remove the scaffold (20, 21) is complete dismantling work.

이와 같이 각각의 형틀판넬을 해체작업함에 있어 각각의 형틀판넬과 장선 및 멍에를 해체작업하는 도중인 지주대의 멍에받침을 낮추거나 장선을 제거할시에 설치되어 있는 각각의 형틀판넬이 떨어지더라도 멍에의 상부에 떨어지게 됨으로 작업인부에게는 영향을 미치지 않게 되어 작업인부가 안전하게 작업을 할 수 있고, 장선 또한 멍에의 상부에 있음으로 안전하게 해체작업을 할 수 있는 매우 우수한 발명인 것이다.Thus, in dismantling each mold panel, even if each mold panel installed during lowering of yoke support or removal of the joist is removed while each mold panel, joist and yoke are dismantled, Falling on the upper part does not affect the workman can workman can work safely, the joist is also a very excellent invention that can be safely dismantled because the upper part of the yoke.

Claims (3)

기둥과 큰보 및 작은보를 형성하고자 하는 위치에 먹줄을 긋고 난 후 먹줄을 그은 상태에서 지주대를 설정된 가로와 세로간의 일정한 거리의 위치에 설치를 하되 건축자재인 강관비계를 사용하여 가로강관비계와 세로강관비계로서 지주대 외측관의 나사산 하부측인 상,하부분에 고정설치하고, 상부에 설치되는 가로강관비계와 세로강관비계간의 높이는 슬라브형틀판넬간과의 거리가 1,500mm이상을 넘지 않도록 설치를 하며, 기둥간의 사이와 슬라브의 하부에 일정한 간격으로 설치하는 큰보와 작은보의 위치에 가로강관비계와 세로강관비계로서 지주대를 설치고정하고 난 후 설계도면의 높이에 비해 멍에와 장선 및 패널의 높이를 뺀 높이에 맞게 지주대의 상부에 형성되어 있는 멍에받침의 높이를 조절고정하고, 보를 지지하는 지주대에 결합하는 멍에는 보에 대하여 직각이 되도록 하고 슬라브를 지지하는 멍에는 일정한 방향인 일방향으로 멍에를 설치고정하고 난 후 멍에의 상부에 각각의 장선을 설치고정하며, 기둥의 위치에 제작된 기둥형틀판넬을 설치고정하고 난 후 보를 지지하는 장선과 슬라브를 지지하는 장선의 상부중앙으로부터 보바닥형틀판넬과 슬라브형틀판넬을 설치고정하고, 보바닥형틀판넬의 상부에 보가 설정되는 위치에 먹줄을 긋고 기둥형틀판넬의 보가 설치되는 위치와 보바닥형틀판넬에 그은 먹줄의 위치가 상호 일치되도록하여 기둥형틀판넬과 보형틀판넬을 상호 고정설치하며, 보바닥형틀판넬의 상부에 그은 먹줄에 따라 보측면형틀판넬을 설치고정하고 난 후 슬라브형틀판넬을 설치고정한 사방주연으로 슬라브형틀판넬을 설치하지 않은 부분을 내측으로 설치고정한 보측면형틀판넬의 상부에 얻쳐지도록 재단한 슬라브형틀판넬을 설치고정함을 특징으로 하는 건축용 형틀판넬을 안전하게 설치하는 방법.After drawing the line at the place where you want to form the pillar, the big beam and the small beam, install the holding post at a certain distance between the set width and length in the state of drawing the food line, but use the steel pipe scaffold which is the building material. As a steel pipe scaffold, it is fixedly installed on the upper and lower parts of the lower side of the thread of the outer side of the column, and the height between the horizontal steel scaffold and the vertical steel scaffold is installed so that the distance between the slab frame panels does not exceed 1,500mm. The height of the yoke, joist and panel compared to the height of the design drawing after fixing the struts as horizontal steel scaffolding and vertical steel scaffolding at the positions of large beams and small beams that are installed at regular intervals between the columns and at the bottom of the slab. Adjust and fix the height of the yoke support formed on the upper part of the support to fit the height except the yoke and join the yoke to support the support The yoke supporting the slab is perpendicular to the beam, and the yoke is fixed in one direction in one direction, and then the respective joists are mounted on the upper part of the yoke, and the column frame panel manufactured at the position of the column is fixed. After installing the bottom frame panel and the slab frame panel from the upper center of the joist supporting the beam and the slab supporting the slab, fix the bottom frame panel and the slab frame panel. The column frame panel and the frame frame panel are fixed to each other so that the installed position and the position of the food line drawn on the bottom frame panel are mutually fixed, and the side frame panel is fixed to the top of the bottom frame panel according to the drawn line. After the slab frame panel is fixed, the four sides of the slab frame panel are fixed. If seolchigo a foundation so eotchyeo on top of the formwork panel slab formwork panel installing securely construction formwork panels characterized by tenderness. 기둥형틀판넬을 제거하고 난 후 큰보와 작은보를 지지하는 지주대의 조절너트와 멈춤너트를 풀어서 멍에와 멍에받침을 분리하고, 멍에와 보바닥형틀판넬의 사이에 설치고정되어 있는 장선을 분리제거하고 난 후 보바닥형틀판넬과 보측면형틀판넬을 분리 제거하며, 조절너트를 죠여서 멍에가 하부에 견고히 닫도록 지주대로 보를 지지하도록 멍에받침을 상승시킨후 보간의 사이에 설치되어 있는 슬라브를 지지하는 지주대 중 일측에 있는 지주대의 조절너트와 멈춤너트를 풀어서 멍에받침과 멍에가 분리되도록 한 후 멍에와 슬라브형틀판넬의 사이에 설치고정되어 있는 장선을 제거하고, 슬라브형틀판넬을 슬라브에서 제거를 한 후 멍에받침에 설치되어 있게 되는 멍에를 멍에받침에서 분리를 하며, 나머지 슬라브를 지지하고 있는 멍에와 장선 및 슬라브형틀판넬을 상기 슬라브의 멍에와 장선 및 슬라브형틀판넬을 해체하는 작업 순서 방법으로 하여 순차적으로 분리 해체를 한 후 가로강관비계와 세로강관비계 및 지주대를 분리해체하여 이루어짐을 특징으로 하는 건축용 형틀판넬을 안전하게 해체하는 방법.After removing the column frame panel, loosen the yoke and yoke support by releasing the adjusting nut and the stop nut of the support base supporting the large beam and the small beam, and separating the joist that is fixed between the yoke and the bottom frame panel. After separating and removing the bottom frame panel and the side frame panel, tighten the adjustment nut to raise the yoke base to support the beam with the support so that the yoke closes firmly to the lower part, and then support the slab installed between the interpolation. Loosen the yoke base and yoke by loosening the adjustment nut and the stop nut of the support stand on one side of the mass, remove the joist that is installed between the yoke and the slab frame panel, and remove the slab frame panel from the slab. The yoke, which is installed on the yoke support, is separated from the yoke support and the yoke, joist, and slab that supports the remaining slabs Building frame, characterized in that the slab yoke and joist and slab frame panel of the slab as a work order method of dismantling and then dismantled sequentially by separating the horizontal steel scaffolding and longitudinal steel scaffolding and the holding post How to dismantle the panel safely. 형틀판넬을 지지하고, 하부에 받침대를 갖고 상부측으로 양측에 장공을 갖는 외주연에 나사산을 형성하여 조절너트를 결합하는 외측관을 형성하며, 상기 외측관의 내측으로 삽입되고 양측으로 상부에서 하부로 일정한 간격을 두고 고정봉이 결합할 수 있는 통공을 형성한 상부측으로 멍에받침을 형성하여 내측관으로 구성하는 건축용 받침지주대에 있어서, 상기 내측관(9)의 상부에 환형의 헤드돌기(11)를 형성하고, 헤드돌기(11)가 결합하여 360°회전을 할 수 있는 요홈(14)을 갖는 연장편(13)이 하부측에 형성하는“
Figure kpo00004
”자 형상의 멍에받침(12)로 이루어지는 내측관(9)으로 구성함을 특징으로 하는 건축용 지주대.
Supports the form panel, forms a thread on the outer periphery having a pedestal at the bottom and a long hole on both sides to form an outer tube for joining the adjustment nut, is inserted into the outer tube and from both sides from the top to the bottom In the support base for construction consisting of the inner tube by forming a yoke support to the upper side to form a through-hole that can be coupled to the fixed rod at regular intervals, the annular head projection 11 in the upper portion of the inner tube (9) Formed on the lower side of the extension piece 13 having a groove 14 capable of engaging the head protrusion 11 to rotate 360 °.
Figure kpo00004
Construction post characterized in that it consists of an inner tube (9) consisting of a yoke support (12) of the shape.
KR1019970027147A 1997-06-25 1997-06-25 Method for constructing and dismantling concrete forms safely KR100257658B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019970027147A KR100257658B1 (en) 1997-06-25 1997-06-25 Method for constructing and dismantling concrete forms safely

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019970027147A KR100257658B1 (en) 1997-06-25 1997-06-25 Method for constructing and dismantling concrete forms safely

Publications (2)

Publication Number Publication Date
KR19990003302A KR19990003302A (en) 1999-01-15
KR100257658B1 true KR100257658B1 (en) 2000-06-01

Family

ID=19511118

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019970027147A KR100257658B1 (en) 1997-06-25 1997-06-25 Method for constructing and dismantling concrete forms safely

Country Status (1)

Country Link
KR (1) KR100257658B1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110017141A (en) * 2019-04-22 2019-07-16 中建三局基础设施建设投资有限公司 A kind of ultra-deep shaft concrete ring grid beam quick template supporting system and its construction method
KR102452857B1 (en) * 2021-05-24 2022-11-10 주식회사 디섹 Scaffolding structure for liquefied gas storage tank and installation method thereof
CN114855628B (en) * 2022-05-23 2024-02-23 南京东部路桥工程有限公司 Suspension device for bridge deck pouring combined steel box girder and pouring construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR970002024U (en) * 1995-06-14 1997-01-24 최희송 Construction Support

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR970002024U (en) * 1995-06-14 1997-01-24 최희송 Construction Support

Also Published As

Publication number Publication date
KR19990003302A (en) 1999-01-15

Similar Documents

Publication Publication Date Title
US9556630B2 (en) Panel support bracket
US4470574A (en) Support structure for building forms
CN113513160B (en) Construction method of basement high and large formwork support system
US3807681A (en) Forming system for concrete floor and roof decks
EP0123264A2 (en) Building system and components thereof
KR102097909B1 (en) Space expansion self-assembly temporary working stand
JP3106335B2 (en) System formwork
US2916245A (en) Adjustable scaffold bracket
KR100257658B1 (en) Method for constructing and dismantling concrete forms safely
US10533330B2 (en) Concrete formwork and a formwork support bracket for forming a suspended floor slab
KR200294830Y1 (en) Supporting structure of scaffold for mold
KR100296744B1 (en) Mold installation of cement concrete building using horizontal mold rest and execution method
KR100247608B1 (en) Concrete form with a scaffolding
JP2584052Y2 (en) Level adjustment jig for perforated panel of driving formwork
RU204002U1 (en) Supporting building structure
JP2862656B2 (en) Permanent form plate assembly unit
JPH0115799Y2 (en)
KR102198600B1 (en) Slab mold support device
KR101854159B1 (en) External scaffold joint structure
JP3014107U (en) Roof scaffolding equipment
JPS6322269Y2 (en)
JP2960572B2 (en) Handrail tipping method for overhanging parts such as balconies
KR20240042939A (en) Supports for work deck of system scaffolding or system support
CN116427679A (en) Construction method of safe and stable cantilever incremental structure high formwork system
CN117513740A (en) Cast-in-situ stair formwork system and construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20080109

Year of fee payment: 9

LAPS Lapse due to unpaid annual fee