KR100237194B1 - Method for constructing built-up upper plate of a bridge using epoxy in the connected part - Google Patents

Method for constructing built-up upper plate of a bridge using epoxy in the connected part Download PDF

Info

Publication number
KR100237194B1
KR100237194B1 KR1019970003276A KR19970003276A KR100237194B1 KR 100237194 B1 KR100237194 B1 KR 100237194B1 KR 1019970003276 A KR1019970003276 A KR 1019970003276A KR 19970003276 A KR19970003276 A KR 19970003276A KR 100237194 B1 KR100237194 B1 KR 100237194B1
Authority
KR
South Korea
Prior art keywords
top plate
upper plate
main
epoxy
bridge
Prior art date
Application number
KR1019970003276A
Other languages
Korean (ko)
Other versions
KR19980067313A (en
Inventor
이현달
Original Assignee
이도형
이현달
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이도형, 이현달 filed Critical 이도형
Priority to KR1019970003276A priority Critical patent/KR100237194B1/en
Publication of KR19980067313A publication Critical patent/KR19980067313A/en
Application granted granted Critical
Publication of KR100237194B1 publication Critical patent/KR100237194B1/en

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 에폭시를 연결부에 사용한 조립식 교량 상판 공법에 관한 것으로, 철근을 배근하고 콘크리트를 타설하여 판상으로 형성한 상판 본체의 전후, 좌우 벽면에 철근으로부터 연장 돌출되어 다수개의 연결고리를 형성한 상판을 이용하여 대부분의 차선에 차량을 통행시키면서 부분적으로 기존 상판을 철거하여 노출된 메인 거더에 상판 본체를 올려놓고 서로 결속 연결한 다음 상판 본체 사이의 간극과 상판 본체와 메인 거더사이의 간극에 에폭시 몰탈을 주입하여 결합하고, 그 위에 아스콘을 시공하는 것에 의하여 부분적인 상판 시공을 완료하고, 이 시공 완료된 상판에 대응하는 차선에 차량을 통행시키면서 이와 인접한 기존 상판의 일부에 대하여 상술한 방법으로 순차 시공하는 것에 의하여 접합강도가 높으면서도 공사비 및 공기를 줄일 수 있으며, 대부분의 자선에서 차량의 통행을 허용하면서도 간편하게 시공할 수 있게 되는 것이다. 또한 상판 본체 자체가 철판으로 된 보강테를 사용하지 않고 철근과 콘크리트로 된 프리캐스트형으로 함으로써 중량을 줄여 취급이 간편하게 되는 것이다.The present invention relates to a prefabricated bridge top plate method using epoxy as a connecting part. The top plate which protrudes from the reinforcement on the front, rear, left and right walls of the top plate body formed by reinforcing bars and placing concrete to form a plate form a plurality of connecting rings. While passing through the vehicle in most lanes, the existing top plate is partially dismantled, the top body is placed on the exposed main girder, and the tops are connected to each other, and epoxy mortar is applied to the gap between the top body and the gap between the top body and the main girder. By injecting and joining, and constructing ascon on it to complete the partial top plate construction, and sequentially constructing a portion of the existing top plate adjacent to this while passing the vehicle through the lane corresponding to the completed top plate. It can reduce construction cost and air while high bonding strength. It was, it is possible to simplify the construction while allowing the passage of vehicles in the most charitable. In addition, the upper body itself is made of precast type of reinforcing steel and concrete without using a reinforcing frame made of iron plate, thereby reducing the weight and simplifying handling.

Description

에폭시를 연결부에 사용한 조립식 교량 상판 공법Prefabricated bridge deck method using epoxy

본 발명은 에폭시를 연결부에 사용한 조립식 교량 상판 공법에 관한 것으로, 특히 접합강도가 높고 공사비 및 공기를 줄일 수 있으며 대부분의 차선에서 차량의 통행을 허용하면서도 간편하게 시공할 수 있음과 아울러 중량을 줄여 취급이 간편하게 되며, 프리캐스트형으로 구성되면서도 각 상판 접합부간의 체결력이 강고하여 차량의 통과에 따른 진동이나 충격하중에 의해 상판간의 접합상태가 쉽게 이완, 분리되는 일이 없으며 교량 상판 전체의 수평도가 균일하게 되고 각 상판의 주연부가 쉽게 손상되는 일이 없어 결과적으로 전체 교량의 사용수명을 연장시킬 수 있는 에폭시를 연결부에 사용한 조립식 교량 상판 공법에 관한 것이다.The present invention relates to a prefabricated bridge deck method using epoxy as a connecting part, and in particular, the bonding strength is high, the construction cost and the air can be reduced, and the construction can be easily carried out while allowing the vehicle to pass in most lanes, and the weight is reduced. It is simple, and even though it is composed of a precast type, the fastening force between each upper plate joint is strong, so that the joint state between the upper plates can not be easily relaxed and separated by vibration or impact load caused by the passage of the vehicle. The present invention relates to a prefabricated bridge deck method using epoxy at the connection part, which can not easily damage the periphery of each deck and consequently extend the service life of the entire bridge.

국내의 교량과 고가 차도등의 대부분은 그 상판 슬라브가 노후되어 크고 작은 붕괴 및 파손이 빈번하게 발생되고 있는 바, 이에 대한 근본적인 보수 대책이 시급한 실정이다.Most of the bridges and elevated roads in Korea are deteriorated and damaged frequently due to the deterioration of the slabs of the top plate, so fundamental repair measures are urgently needed.

이러한 교량 상판의 파손에 대한 보수 방법으로서는 그 일례로서 파손된 부분에 국한된 응급 복구공사 즉, 초속경화 시멘트를 사용하는 긴급 보수공사 위주로 시행되고 있다.As an example of the repair method for the damage of the bridge deck, the emergency repair work that is limited to the damaged part, that is, the emergency repair work using super-hardening cement, is carried out.

한편, 상기와 같은 제반 문제점을 감안하여 메인 거더(main girder)의 상부에 일정 규격을 가지는 프리캐스트(precast)상판을 조립식으로 설치하는 교량 상부 구조물의 시공방법이 알려진 바 있다.On the other hand, in view of the above problems, there has been known a construction method of the upper bridge structure to prefabricated to install a precast (precast) plate having a predetermined standard on the upper part of the main girder (main girder).

또한 본 출원인은 대한민국 실용신안등록 제96,795호와 같이 다수개의 접합돌부와 접합홈부가 교호로 형성된 콘크리트제 상판 본체와, 이 상판의 가장자리를 둘러싸는 보강테로 구성하여 보강테를 용접으로 접합하는 교량용 상판을 개발한 바 있다.In addition, the present applicant is a bridge for joining the reinforcement frame by welding by constructing a concrete upper plate body formed with alternating joining protrusions and joining grooves alternately, and a reinforcing frame surrounding the edge of the upper plate, as in Korean Utility Model Registration No. 96,795 He developed tops.

그러나 상술한 긴급 보수공사법에서는 초속경화 시멘트에 의해 시공된 보수 부위가 불과 수년(2∼3년)내에 파손됨에 따라 상판의 보수작업을 주기적으로 반복 재시행하여야 하는 문제점이 있을 뿐만 아니라 상기와 같은 보수작업에는 많은 공사비 및 공기가 소요되고 그 보수기간 동안 차량의 통행을 전면적으로 제한하지 않으면 안되는 등의 문제점이 있었다.However, in the above-mentioned emergency repair work method, as the repaired part constructed by the super-hardening cement is damaged within only a few years (2 to 3 years), the repair work of the top plate needs to be repeated periodically, as well as the repair as described above. The work required a lot of construction cost and air, and during the maintenance period, the traffic of the vehicle must be completely restricted.

또한 상술한 조립 상판을 이용하는 공법에서는 그 조립 상판이 철근과 같은 인장재가 내부에 배근된 장방형 판체상 프리캐스트 콘크리트 구조물로 제작되고, 이들 상판의 연결시에는 상호 접촉되는 각 상판의 길이방향 양단면벽 및 양측의 평면 접합부사이에 콘크리트 몰탈을 채움으로써 각 상판들을 종횡으로 연결 접합하게 되는 것으로, 각 상판 접합부간의 체결력이 취약하여 차량의 통과에 따른 진동이나 충격하중에 의해 상판간의 접합상태가 쉽게 이완, 분리되어 교량 상판 전체의 수평도가 불균일하게 되고 각 상판의 주연부가 쉽게 손상되어 결과적으로 전체 교량의 사용수명을 현저히 단축시키게 되는 문제점이 있었다.In addition, in the construction method using the above-described assembly top plate, the assembly top plate is made of a rectangular plate-shaped precast concrete structure in which a tension member such as reinforcing bar is disposed therein. Each floor plate is connected vertically and horizontally by filling concrete mortar between the planar joints on both sides. The fastening force between the top plate joints is weak so that the joining state between the top boards is easily relaxed and separated by vibration or impact load caused by the passage of the vehicle. As a result, the horizontality of the entire bridge deck becomes uneven and the periphery of each deck is easily damaged, resulting in a significant shortening of the service life of the entire bridge.

또한 상술한 교량용 상판을 사용하는 경우에는 접합강도가 높고 공사비를 줄일수 있으며 어느 정도 공기를 단축할 수 있고 차량의 통행을 전면적으로 통제하지 않고 대부분의 차선의 차량통행을 허용하면서 시공할 수 있다는 장점은 있으나 보강테를 일일이 용접으로 접합하여야 하므로 그 작업이 번거롭고 그에 소요되는 시간만큼 공기가 지연되며, 보강테를 구성하는 철판의 사용량만큼 중량이 무거워지므로 시공을 위한 취급이 어렵게 되는 문제점이 있었다.In addition, in the case of using the bridge deck as described above, the joint strength is high, the construction cost can be reduced, the air can be reduced to some extent, and the construction can be performed while permitting the traffic of most lanes without full control of the traffic passage. Although there is an advantage, the reinforcing frame has to be joined by welding, so the work is cumbersome and the air is delayed by the time required, and the weight of the steel plate constituting the reinforcing frame becomes heavy, making it difficult to handle for construction.

본 발명의 목적은 접합강도가 높고 공사비 및 공기를 줄일 수 있으며 대부분과 차선에서 차량의 통행을 허용하면서도 간편하게 시공할 수 있도록 한 에폭시를 연결부에 사용한 조립식 교량 상판 공법을 제공하려는 것이다.An object of the present invention is to provide a prefabricated bridge deck method using epoxy to the connection portion that can be high construction strength and construction cost and air can be easily installed while allowing the passage of the vehicle in the majority and lanes.

본 발명의 다른 목적은 철근과 콘크리트로 된 프리캐스트형으로 하여 중량을 줄여 취급이 간편하게 되도록 하려는 것이다.Another object of the present invention is to be made of precast type of reinforcing steel and concrete to reduce the weight and to simplify the handling.

본 발명의 또 다른 목적은 프리캐스트형으로 구성되면서도 각 상판 접합부간의 체결력이 강고하여 차량의 통과에 따른 진동이나 충격하중에 의해 상판간의 접합상태가 쉽게 이완, 분리되는 일이 없으며 교량 상판 전체의 수평도가 균일하게 되고 각 상판의 주연부가 쉽게 손상되는 일이 없어 결과적으로 전체 교량의 사용수명을 연장시킬 수 있도록 하려는 것이다.Another object of the present invention is a precast type, but the fastening force between the joints between the top plate is strong, so that the joint state between the top plate is not easily loosened, separated by vibration or impact load caused by the passage of the vehicle, the horizontal of the entire bridge top plate The aim is to ensure uniformity and not to easily damage the periphery of each deck, resulting in extending the service life of the entire bridge.

제1도는 본 발명에 의한 조립식 상판의 부분 절개 사시도.1 is a partial cutaway perspective view of a prefabricated top plate according to the present invention.

제2도는 본 발명에 의한 상판을 메인 거더 상이 얹어놓은 상태 사시도.2 is a perspective view of a state in which the main girder image is placed on the top plate according to the present invention.

제3도는 기존 상판의 일부를 철거하여 한쌍의 거더가 노출된 상태 평면도.3 is a plan view of a state where a pair of girders are exposed by removing a part of the existing top plate.

제4(a)도는 한쌍의 거더 사이에 본 발명의 상판 얹고 거더와 상판을 결합한 상태 평면도.4 (a) is a plan view of the top plate of the present invention between the pair of girders combined with the girder and the top plate.

제4(b)도는 프리캐스트 거더의 경우를 보인 제4(a)도의 A-A선 단면도.Fig. 4 (b) is a cross-sectional view taken along the line A-A of Fig. 4 (a) showing the case of a precast girder.

제4(c)도는 플랫 거더의 경우를 보인 제4(a)도의 A-A선 단면도.Fig. 4 (c) is a cross-sectional view taken along the line A-A of Fig. 4 (a) showing a flat girder.

제5(a)도는 상판을 연결철근으로 결속한 상태를 보인 사시도.Figure 5 (a) is a perspective view showing a state in which the top plate is bound with a connecting bar.

제5(b)도는 제5(a)도의 B부 확대도로서, 결속과정을 보인 사시도.Figure 5 (b) is an enlarged view of the portion B of Figure 5 (a), a perspective view showing the binding process.

제6(a)도는 상판 본체 사이에 에폭시 몰탈을 주입한 상태 평면도.6 (a) is a plan view in which epoxy mortar is injected between upper plate bodies.

제6(b)도는 제6(a)도의 C-C선 단면도.Fig. 6 (b) is a cross-sectional view taken along the line C-C in Fig. 6 (a).

제7도는 다음 번 거더에 대응하는 기존 상판을 철거하여 한쌍의 거더가 노출된 상태를 보인 평면도.7 is a plan view showing a state in which a pair of girders are exposed by removing the existing top plate corresponding to the next girder.

제8(a)도는 노출된 거더 사이에 본 발명의 상판 얹어 거더와 상판을 결합하고, 상판을 결속하여 수지를 주입한 상태 평면도.8 (a) is a plan view in which the top plate of the present invention is placed between the exposed girders, the girder and the top plate are bonded, and the top plate is bound to inject resin.

제8(b)도는 상판의 연결 구조를 보인 제8(a)도의 D부 확대평면도.FIG. 8 (b) is an enlarged plan view of part D of FIG. 8 (a) showing the connection structure of the upper plate.

제8(c)도는 프리캐스트 거더의 경우를 보인 제8(a)도의 E-E선 단면도.8 (c) is a cross-sectional view taken along the line E-E of FIG. 8 (a) showing a precast girder.

제8(d)도는 플랫 거더의 경우를 보인 제8(a)도의 E-E선 단면도.Fig. 8 (d) is a cross sectional view taken along the line E-E of Fig. 8 (a) showing a flat girder.

제9도는 상판 배열 상태를 보인 평면도.9 is a plan view showing a top plate arrangement state.

제10도는 제9도의 F-F선 단면도.10 is a sectional view taken along the line F-F in FIG.

제11도는 교량 전체에 대한 상판 배열을 상태를 보인 종단면도.FIG. 11 is a longitudinal sectional view showing the top plate arrangement of the entire bridge. FIG.

제12도는 난간부의 시공상태를 보인 종단면도.12 is a longitudinal sectional view showing a construction state of the handrail part.

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

10 : 상판 본체 11 : 측벽10: top plate body 11: side wall

12 : 난간부 21,22 : 철근12: handrail 21,22: rebar

23,24 : 연결고리 25 : 지지고리23,24: Hook 25: Hook

26 : 연결철근 31 : 앵커 철근26: connecting bar 31: anchor bar

32 : 앵커 볼트32: anchor bolt

이러한 본 발명의 목적을 달성하기 위하여 기존 교량의 상판 일부를 철거하여 적어도 2개의 메인 거더의 전부 또는 일부가 노출되게 하는 기존 상판 철거단계와: 노출된 메인 거더상에 다수개의 상판 본체를 올려놓는 상판 배열 단계와; 상판 본체의 전후, 좌우벽에 돌출 형성된 연결고리를 연결 철근에 의하여 결속 연결하는 연결 단계와; 상판 본체 사이의 간극과 상판 본체와 메인 거더 사이의 간극에 에폭시 몰탈을 주입하여 인접하는 상판 본체들과 상판 본체와 메인 거더를 접합하는 접합 단계와; 에폭시 몰탈이 응고된 후 상판 상에 아스콘을 시공하는 아스콘 시공 단계와; 먼저 번 시공된 상판과 인접하는 상판에 대하여 기존 상판 철거단계와 상판 배열 단계와 연결단계와 접합 단계와 아스콘 시공 단계를 순차 수행함을 특징으로 하는 에폭시를 연결부에 사용한 조립식 교량 상판 공법이 제공된다.In order to achieve the object of the present invention, to remove a portion of the upper plate of the existing bridge to remove at least two of the main girder to expose all or part of the top plate: a top plate to put a plurality of the top body on the exposed main girder An array step; A connecting step of connecting the connecting rings protruding from the front and rear and left and right walls of the upper plate body by connecting bars by connecting bars; Bonding step of injecting epoxy mortar into the gap between the upper plate main body and the gap between the upper plate main body and the main girder to join adjacent upper plate main bodies and the upper plate main body and the main girder; Ascon construction step of constructing ascon on the top plate after the epoxy mortar is solidified; First, the prefabricated bridge deck method using epoxy is used for connecting the first and the adjacent decks, and the decking step, the stacking step, the connecting step, the joining step, and the ascon construction step are sequentially provided.

이하, 본 발명에 의한 에폭시를 연결부에 사용한 조립식 교량 상판 공법을 첨부도면에 도시한 실시례에 따라서 상세히 설명한다.Hereinafter, the prefabricated bridge deck method using the epoxy according to the present invention in the connecting portion will be described in detail according to the embodiment shown in the accompanying drawings.

제1도는 본 발명에 의한 에폭시를 연결부에 사용한 조립식 교량 상판과 메인 거더의 결합상태를 보인 사시도이고, 제2도는 본 발명에 의한 조립식 교량 상판의 부분 절개 사시도로서, 이에 도시한 바와 같이, 상판 본체(10)의 내부에 배근되는 철근(21,22)을 상판 본체(10)의 전후, 좌우 벽면(11)에서 돌출시켜 대략 “ㄷ”자형으로 절곡된 연결고리(23,24)를 형성하도록 한 것이다.1 is a perspective view showing a state of coupling between the prefabricated bridge top plate and the main girder using the epoxy according to the present invention in the connecting portion, Figure 2 is a partial cutaway perspective view of the prefabricated bridge top plate according to the present invention, as shown therein, Reinforcing bars (21, 22) are arranged in the interior of the (10) protruding from the front and rear, left and right wall surface 11 of the upper plate body 10 to form a connecting ring (23, 24) bent in a substantially "c" shape will be.

상기 철근(21,22)을 배근함에 있어서는 철근을 지그재그로 꺾어서 배근하면서 상판 본체(10)의 전후, 좌우 벽면(11)측에서는 “ㄷ”자형으로 돌출되도록 함으로써 상기 연결고리(23,24)가 형성되도록 하는 것이다.In the reinforcement of the reinforcing bars 21 and 22, the connecting rings 23 and 24 are formed by protruding the reinforcing bars into a zigzag and protruding in front and rear and left and right wall surfaces 11 of the upper plate body 10 in a “c” shape. To make it possible.

또한 상기 철근(21,22)들은 제4(b)도 및 제4(c)도에 도시한 바와 같이 상판 본체(10)의 저면에서도 돌출되어 메인 거더와의 결합시 결합 강도를 보강하기 위한 지지고리(25)을 형성한다.In addition, the reinforcing bars (21, 22) as shown in Figure 4 (b) and 4 (c) also protrudes from the bottom surface of the upper body 10 to support for reinforcing the bonding strength when the coupling with the main girder To form a ring 25.

이하, 본 발명에 의한 에폭시를 사용한 조립식 교량 상판을 이용하여 교량을 시공하는 과정을 설명한다.Hereinafter, a process of constructing a bridge using a prefabricated bridge top plate using epoxy according to the present invention will be described.

[기존 상판 철거 단계][Existing roof demolition stage]

제3도에 도시한 바와 같이, 보수하고자 하는 상판의 일부, 즉 교량의 일측의 메인 거더(G1)과 (G2)사이에 설치된 상판을 철거하여 그 부분의 메인 거더(G1)는 완전히 노출되게 하고 메인 거더(G2)는 절반 정도만 노출되게 한다.As shown in FIG. 3, a part of the upper plate to be repaired, ie, the upper plate installed between the main girders G1 and G2 on one side of the bridge, is removed so that the main girders G1 of the portion are completely exposed. The main girder (G2) only exposes about half.

이때, 철거할 상판과 인접하는 메인 거더(G2)의 중앙선을 따라 아스콘과 사판 전체를 절취하여 메인 거더(G2)가 대략 절반만 노출되게 하는 것이다.At this time, the main girder G2 is exposed to about half by cutting the entire ascon and the swash plate along the center line of the main girder G2 adjacent to the upper plate to be removed.

제3도 및 제11도에서 40은 교각이다.40 are piers in FIGS. 3 and 11.

[상판 배열 단계][Tops Arrangement Step]

기존 상판 철거 단계에서 노출된 메인 거더(G1,G2)상에 제4(a)도에 도시한 바와 같이 상기 상판 본체(10)을 올려놓고 상판 본체(10)의 저면에서 돌출된 지지고리(25)를 메인 거더(G1,G2)에 타입되어 돌출된 앵커 철근(31)이나 앵커볼트(32)상에 걸리도록 한다.A support ring 25 protruding from the bottom surface of the top plate body 10 by placing the top body 10 on the main girders G1 and G2 exposed in the existing top plate removing step as shown in FIG. ) To the main girders (G1, G2) to be caught on the protruding anchor reinforcement 31 or anchor bolts (32).

여기서, 메인 거더(G1,G2)가 프리캐스트 거더(precast girder)인 경우에는 제4(b)도에 도시한 바와 같이 앵커 철근(31)을 타입 돌출되게 하며, 플랫 거더(flat girder)인 경우에는 제4(c)도에 도시한 바와 같이 앵커 볼트(32)를 타입 돌출되게 하는 것이 바람직하다.Here, in the case where the main girders G1 and G2 are precast girders, as shown in FIG. 4 (b), the anchor reinforcement 31 is protruded, and in the case of the flat girders. It is preferable to make the anchor bolt 32 protrude as shown in FIG. 4 (c).

[상판 연결 단계][Top Connection Step]

상판 본체(10)가 메인 거더(G1,G2)에 얹혀지면, 제5(a)도에 도시한 바와 같이 인접한 상판 본체(10)간의 연결고리(23,24)들을 연결 철근(26)으로 결속 연결한다.When the upper body 10 is mounted on the main girders (G1, G2), as shown in FIG. 5 (a), the connecting rings (23, 24) between the adjacent upper body 10 is bound to the connecting reinforcement (26) Connect.

연결고리(23,24)들을 연결 철근(26)으로 결속 연결함에 있어서는 제5(b)도에 도시한 바와 같이 한쌍의 암부(26a)가 연결부(26b)로 연결되어 대략 “ㄷ”자형으로 절곡형성된 연결 철근(26)을 그 연결부(26b)가 인업하는 상판 본체(10)의 연결고리(23,24)에 걸쳐지도록 한 다음 그 양측 암부(26a)를 180°절곡하는 것에 의하여 양측 연결고리(23,24)가 연결 철근(26)에 의하여 결속 연결되는 것이다.In the case of connecting the connecting rings 23 and 24 with the connecting bars 26, as shown in FIG. 5 (b), a pair of arm parts 26a are connected with the connecting parts 26b and bent in a roughly “c” shape. The connecting bar 26 is formed so that the connecting part 26b spans the connecting rings 23 and 24 of the upper plate main body 10 which is lifted up, and then the two arm parts 26a are bent by 180 °. 23 and 24 are bound by the connecting reinforcing bar 26.

[접합 단계][Join Step]

상판 본체(10)들의 연결고리(23,24)가 연결 완료되면, 제6(a)도 및 제6(b)도에 도시한 바와 같이 인접하는 상판 본체(10)사이에 형성된 간극(C1)부분에 에폭시 몰탈(E)을 주입하여 인접하는 상판 본체(10)사이의 간극(C1) 및 상기 메인 거더(G1,G2)와 상판 본체(10)사이의 간극(C2)에 에폭시 몰탈(E)이 채워지면서 상판 본체(10)와 상판 본체(10) 및 메인 거더(G1,G2)와 상판 본체(10)들이 에폭시 몰탈(E)에 의하여 결합되도록 한다.When the connecting rings 23 and 24 of the upper plate main bodies 10 are connected, the gap C1 formed between adjacent upper plate main bodies 10 as shown in FIGS. 6 (a) and 6 (b). Epoxy mortar (E) is injected into the part and the epoxy mortar (E) is inserted into the gap C1 between the adjacent upper body 10 and the gap C2 between the main girders G1 and G2 and the upper body 10. The filling is such that the upper plate body 10 and the upper plate body 10 and the main girders (G1, G2) and the upper plate body 10 are bonded by an epoxy mortar (E).

[아스콘 시공 단계][Ascon construction stage]

에폭시 몰탈(E)이 응고되어 상판과 상판, 상판과 메인 거더간의 결합이 완료되면, 상판 본체(10) 상면에 통상적인 방법으로 아스콘을 시공한다.When the epoxy mortar (E) is solidified and the bonding between the top plate and the top plate and the top plate and the main girder is completed, ascon is applied to the top surface of the top body 10 in a conventional manner.

[반복 시공 단계][Repeat construction stage]

이와 같이 먼저 번의 상판 시공이 완료되면, 제7도에 도시한 바와 같이 시공된 상판에 대응하는 차선에 차량을 통행시키면서 시공된 상판과 인접한 상판을 철거하여 메인 거더(G2,G3)의 일부(거더의 중앙선을 기준으로 절반 정도)가 노출되도록 한다.In this way, when the first top plate construction is completed, as shown in FIG. 7, the main plate G2 and G3 are removed by removing the top plate adjacent to the constructed top plate while passing the vehicle to the lane corresponding to the top plate constructed as shown in FIG. About half of the centerline of the lens is exposed.

노출된 메인 거더(G2,G3)사이에 상판 본체(10)를 올려놓는다. 이대, 제8(a)도와 같이 먼저 번 시공된 상판 본체(10)들과 이번 시공되는 상판 본체(10)들은 마치 별돌 쌓기와 절반씩 중첩되게 배치되도록 한다.The top body 10 is placed between the exposed main girders G2 and G3. This, as shown in the eighth (a) is the first top plate body 10 and the top plate body 10 to be constructed this time as if stacked so that overlapping with the dolseok.

다음 상술한 바와 같이 상판 본체(10)들을 메인 거더(G2,G3)에 타입된 앵커 철근(31)이나 앵커볼트(32)에 얹혀지게 하고, 제8(b)도와 같이 상판 본체(10)들을 연결철근(26)에 의하여 결속하고, 상판 본체(10)들 사이의 간극(C1)과 상판 본체(10)과 메인 거더(G2,G3)사이의 간극(C2)에 에폭시 몰탈(E)을 주입하여 상판 본체(10)들이 메인 거더(G2,G3)에 고정됨과 아울러 서로 결합되도록 한다.Next, as described above, the upper plate main bodies 10 are mounted on the anchor reinforcement 31 or anchor bolts 32 formed on the main girders G2 and G3, and the upper plate main bodies 10 as shown in FIG. 8 (b). Bonded by connecting reinforcing bars 26, epoxy mortar E is injected into the gap C1 between the upper plate main bodies 10 and the gap C2 between the upper plate main body 10 and the main girders G2 and G3. The upper main body 10 is fixed to the main girder (G2, G3) and to be coupled to each other.

제8(c)도는 메인 거더가 프리캐스트 거더인 경우 메인 거더(G2,G3)에 앵커 철근(31)을 타입하고 그 위에 상판 본체(10)의 저면에 돌출된 지지고리(25)를 얹혀지게 한 상태를 보인 것이고, 제8(d)도는 메인 거더가 플랫 거더인 경우 메인 거더(G2,G3)에 앵커볼트(32)를 타입하고 그 위에 상판 본체(10)의 저면에 돌출된 지지고리(25)를 얹혀지게 한 상태를 보인 것이다. 제8(c)도 및 제8(d)도에서 A는 아스콘이다.8 (c) shows that when the main girder is a precast girder, the anchor reinforcement 31 is typed on the main girders G2 and G3, and the support ring 25 protruding from the bottom of the upper plate body 10 is placed thereon. 8 (d) shows an anchor bolt 32 on the main girders G2 and G3 when the main girders are flat girders, and a support ring protruding from the bottom surface of the upper plate main body 10 thereon. 25) put it on. In FIGS. 8 (c) and 8 (d), A is ascone.

상판 본체(10)들을 결속함에 있어서는 제8(b)도와 같이 상기 상판 본체(10)들의 연결고리(23,24)를 연결철근(26)에 의하여 결속함과 아울러 먼저 번 시공된 상판의 연결고리(23,24)들과도 연결철근(26)으로 결속한다.In the binding of the upper plate main body 10, as shown in the eighth (b), the connecting ring 23, 24 of the upper plate main body 10 by the connecting reinforcing bar 26, and the first ring of the first construction (23, 24) also binds to the connecting bar (26).

이와 같은 방법으로 메인 거더(G4,G5,G6)등에 대응하는 상판에 대하여 순차적으로 시공하여 교량 상판 전체를 시공하게 되는 것이다.In this way, the top plate corresponding to the main girders G4, G5, G6, etc. are sequentially installed to construct the entire bridge top plate.

제9도는 교량 상판 전체에 대한 상판 본체(10) 배열의 일례를 보인 것으로, 하나의 경간에 대한 상판 본체(10)의 개수와 길이는 교량의 경간 길이에 따라 설정된다.9 shows an example of the arrangement of the upper plate main body 10 for the entire bridge upper plate, and the number and length of the upper plate main bodies 10 for one span are set according to the span length of the bridge.

도시례에서는 경간의 길이가 30m인 경우 15m짜리 상판 본체와 7.5m짜리 상판 본체를 교호로 배열하여 별돌 쌓기식으로 배열되게 하는 것이다.In the city example, when the length is 30m, the 15m top plate body and the 7.5m top plate body are alternately arranged so that they are arranged in a stacking manner.

제10도는 시공 완료된 상태에서 상판 본체(10)에 작용하는 응력을 보인 것으로, 상판 본체(10)간의 연결부위에서 상측에는 인장응력이, 하측에는 압축응력이 작용하며, 상판 본체(10)에서는 상측에는 압축응력이, 하측에는 인장응력이 작용함을 알 수 있다.Figure 10 shows the stress acting on the upper plate body 10 in the completed construction state, the tensile stress on the upper side, the compressive stress on the lower side in the connection between the upper plate body 10, the upper plate in the main body 10 It can be seen that the compressive stress, the tensile stress acts on the lower side.

제11도는 본 발명에 의하여 시공 완료된 상태를 보인 종단면도로서, 교각과 교각사이에 모든 상판이 시공된 결과를 볼 수 있다. 단, 상판 본체(10)위에 시공되는 아스콘은 생략되어 있다.Figure 11 is a longitudinal cross-sectional view showing a state in which construction is completed by the present invention, you can see the result of the construction of all the top plate between the bridge piers. However, the ascon which is constructed on the upper plate main body 10 is omitted.

한편, 교량의 난간부분을 시공함에 있어서는 제12도에 도시한 바와 같이 상술한 상판 본체(10)의 일측에 난간부(12)를 일체로 형성한 난간 상판 본체(10)를 사용하여 상술한 방법으로 시공하면 된다.On the other hand, in the construction of the handrail portion of the bridge, as shown in FIG. 12, the method described above using the handrail upper plate body 10 in which the handrail portion 12 is integrally formed on one side of the upper plate body 10 described above. It can be installed by.

즉, 상판 본체(10)의 내측에는 상술한 바와 같이 철근(21,22)로부터 연장 돌출된 연결고리(23,24)를 형성하고, 외측에는 상기 난간부(12)를 일체로 형성한 것을 사용하는 것이다.That is, the inner ring body (10) is formed inside the connecting ring (23, 24) protruding from the reinforcing bar (21, 22) as described above, the outer side of the handrail 12 is used integrally formed It is.

이상과 같이 본 발명에 의하면 철근과 콘크리트로 된 프리캐스트형으로 된 상판을 연결철근으로 결속, 연결하고, 그 사이의 간극에 에폭시 몰탈을 주입하는 것에 의하여 시공이 완료되는 것이므로 접합강도가 높으면서도 공사비 및 공기를 줄일 수 있으며, 대부분의 차선에서 차량의 통행을 허용하며서도 간편하게 시공할 수 있게 되는 것이다. 또한 상판 본체 자체가 철판으로 된 보강테를 사용하지 않고 철근과 콘크리트로된 프리캐스트형으로 함으로써 중량을 줄여 취급이 간편하게 되는 것이다.As described above, according to the present invention, since the construction is completed by binding and connecting the upper plate of the rebar and the concrete precast type with connecting bars and injecting epoxy mortar into the gap therebetween, And it can reduce the air, and in most lanes to allow the passage of the vehicle will be able to install easily. In addition, the upper body itself is made of a precast type of reinforcing steel and concrete without using a reinforcing frame made of iron plate, thereby reducing the weight and simplifying handling.

Claims (4)

기존 교량의 상판 일부를 철거하여 적어도 2개의 메인 거더의 전부 또는 일부가 노출되게 하는 기존 상판 철거단계와; 노출된 메인 거더상에 다수개의 상판 본체를 올려놓는 상판 배열 단계와; 상판 본체의 전후, 좌우벽에 돌출 형성된 연결고리를 연결 철근에 의하여 결속 연결하는 연결 단계와; 상판 본체 사이의 간극과 상판 본체와 메인 거더 사이의 간극에 에폭시 몰탈을 주입하여 인접하는 상판 본체들과 상판 본체와 메인 거더를 접합하는 접합 단계와; 에폭시 몰탈이 응고된 후 상판 상에 아스콘을 시공하는 아스콘 시공 단계와; 먼저 번 시공된 상판과 인접하는 상판에 대하여 기존 상판 철거단계와 상판 배열 단계와 연결단계와 접합 단계와 아스콘 시공 단계를 순차 수행함을 특징으로 하는 에폭시를 연결부에 사용한 조립식 교량 상판 공법.Removing the existing top plate of the existing bridge to expose all or part of at least two main girders; A top plate arrangement step of placing a plurality of top body bodies on the exposed main girders; A connecting step of connecting the connecting rings protruding from the front and rear and left and right walls of the upper plate body by connecting bars by connecting bars; Bonding step of injecting epoxy mortar into the gap between the upper plate main body and the gap between the upper plate main body and the main girder to join adjacent upper plate main bodies and the upper plate main body and the main girder; Ascon construction step of constructing ascon on the top plate after the epoxy mortar is solidified; A prefabricated bridge deck method using epoxy as a connecting part, characterized in that the first step of the top plate and the adjacent top plate is sequentially carried out the demolition step, the arrangement of the top plate, the connecting step, the bonding step and the ascon construction step. 제1항에 있어서, 상기 상판 배열 단계에서는 벽돌 쌓기식으로 교로로 배열되도록 함을 특징으로 하는 에폭시를 연결부에 사용한 조립식 교량 상판 공법.The method of claim 1, wherein in the arranging of the upper plate, an epoxy is used for the connecting part, the prefabricated bridge top method is characterized in that the stacking is arranged in a bridge. 제1항에 있어서, 상기 상판 배열 단계에서는 메인 거더에 앵커 철근을 타입하고, 상판 본체의 저면에 돌출 형성된 지지고리를 상기 앵커 철근에 지지되도록 하는 것을 특징으로 하는 에폭시를 연결부에 사용한 조립식 교량 상판 공법.The method of claim 1, wherein in the arrangement of the upper plate, an anchor reinforcing bar is formed on the main girder, and a support ring protruding from the bottom of the upper main body is supported on the anchor reinforcing bridge. . 제1항에 있어서, 상기 상판 배열 단계에서는 메인 거더에 앵커 볼트를 타입하고, 상판 본체의 저면에 돌출 형성된 지지고리를 상기 앵커 볼트에 지지되도록 하는 것을 특징으로 하는 에폭시를 연결부에 사용한 조립식 교량 상판 공법.The method of claim 1, wherein in the arrangement of the upper plate, an anchor bolt is formed on the main girder, and the supporting ring protruding from the bottom of the upper plate body is supported by the anchor bolt. .
KR1019970003276A 1997-02-03 1997-02-03 Method for constructing built-up upper plate of a bridge using epoxy in the connected part KR100237194B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019970003276A KR100237194B1 (en) 1997-02-03 1997-02-03 Method for constructing built-up upper plate of a bridge using epoxy in the connected part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019970003276A KR100237194B1 (en) 1997-02-03 1997-02-03 Method for constructing built-up upper plate of a bridge using epoxy in the connected part

Publications (2)

Publication Number Publication Date
KR19980067313A KR19980067313A (en) 1998-10-15
KR100237194B1 true KR100237194B1 (en) 2000-01-15

Family

ID=19496300

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019970003276A KR100237194B1 (en) 1997-02-03 1997-02-03 Method for constructing built-up upper plate of a bridge using epoxy in the connected part

Country Status (1)

Country Link
KR (1) KR100237194B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100778035B1 (en) * 2007-01-02 2007-11-21 김근택 Half precast concrets slab and coupling structure of bridges use the same

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100395590B1 (en) * 2001-05-31 2003-08-21 명보산공 주식회사 The Method of Lane Extension by Beam Support to Wayside and Structure Thereof
KR100436889B1 (en) * 2001-07-31 2004-06-25 벽연이앤지 주식회사 Polymer concrete precast deck panel for fabricated bridge and manufacturing method thereof, fabricated bridge deck panel installation method using polymer concrete precast deck panel and polymer concrete
KR100440621B1 (en) * 2001-08-10 2004-07-15 박재만 A construction method for reinforcing occurrence part of a bridge sub-moment and a structure thereof
CN110485256A (en) * 2019-08-21 2019-11-22 广州市第二市政工程有限公司 A kind of fabricated temporary bridge for construction and its construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5833501U (en) * 1981-08-28 1983-03-04 石川島建材工業株式会社 concrete floor slab
JPH06108420A (en) * 1992-09-22 1994-04-19 Ishikawajima Harima Heavy Ind Co Ltd Precast floor slab

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5833501U (en) * 1981-08-28 1983-03-04 石川島建材工業株式会社 concrete floor slab
JPH06108420A (en) * 1992-09-22 1994-04-19 Ishikawajima Harima Heavy Ind Co Ltd Precast floor slab

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100778035B1 (en) * 2007-01-02 2007-11-21 김근택 Half precast concrets slab and coupling structure of bridges use the same

Also Published As

Publication number Publication date
KR19980067313A (en) 1998-10-15

Similar Documents

Publication Publication Date Title
KR100935430B1 (en) Hybrid deep deck of constructing long span slim floor and structure using hybrid deep deck
KR101270733B1 (en) Prestressed Concrete Box Girder Integrated with Steel Deck and Constructing Method of Bridge using Such Girder
JP3880288B2 (en) Precast segment and bridge girder forming method using the same
JP7082522B2 (en) Precast synthetic deck joint structure
KR100237194B1 (en) Method for constructing built-up upper plate of a bridge using epoxy in the connected part
KR100923564B1 (en) Precast concrete panel, construction method and structure of precast concrete panel using steel plate
KR101735077B1 (en) Bridge deck using precast concrete panel
JPH04228710A (en) Road slab for bridge
KR101693266B1 (en) Hybrid girder
KR101067895B1 (en) Deck plate
CN212533705U (en) Wet seam connection structure of precast concrete bridge deck
CN210596967U (en) Set up prefabricated simple-supported box girder bridge of wet seam connecting piece of steel construction
JPH0338245Y2 (en)
JP2508677B2 (en) Reinforcement method of bridge reinforced concrete slab
JP4293696B2 (en) Construction method of composite floor slab bridge
KR200152482Y1 (en) Deck plate for the concrete slab
KR20200139572A (en) Bridge upper structure with rrecast slab
CN110886392A (en) Laminated arch shell structure and construction method thereof
KR20040043262A (en) Hollow Type I Beam Composite Deck having Longitudinal Joints and Constructing Method thereof
JPH09273117A (en) Joint construction of floor slab
CN218203878U (en) Replace reinforced concrete composite beam bridge mosaic structure that mound top falls back
JPH05239810A (en) Constructing method for reinforced concrete arch bridge
CN212000589U (en) Concrete cantilever plate
KR100424321B1 (en) Deck panel for the slab of architecture which equipped steel wire
KR20100009019A (en) Temporary bridge and method for constucting an temporary bridge

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20061002

Year of fee payment: 8

LAPS Lapse due to unpaid annual fee