KR0162033B1 KR1019950029621A KR19950029621A KR0162033B1 KR 0162033 B1 KR0162033 B1 KR 0162033B1 KR 1019950029621 A KR1019950029621 A KR 1019950029621A KR 19950029621 A KR19950029621 A KR 19950029621A KR 0162033 B1 KR0162033 B1 KR 0162033B1
Authority
KR
South Korea
Prior art keywords
pedestal
support
spiral
connecting pipe
height
Prior art date
Application number
KR1019950029621A
Other languages
Korean (ko)
Other versions
KR970015980A (en
Inventor
김재연
Original Assignee
김재연
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김재연 filed Critical 김재연
Priority to KR1019950029621A priority Critical patent/KR0162033B1/en
Publication of KR970015980A publication Critical patent/KR970015980A/en
Application granted granted Critical
Publication of KR0162033B1 publication Critical patent/KR0162033B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/04Shores or struts; Chocks telescopic
    • E04G25/06Shores or struts; Chocks telescopic with parts held together by positive means
    • E04G25/065Shores or struts; Chocks telescopic with parts held together by positive means by a threaded nut
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/18Scaffolds primarily resting on the ground adjustable in height

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

본 발명은 패널과 지지장치(동바리)를 분해와 조립이 가능한 형태로 구성하는 한편, 받침대 중간에는 보강수단을 설치하여 견고히 판넬 지지하는 건축용 슬라브 폼(Form) 지지장치에 관한 것으로, 철재 또는 알루미늄으로 구성된 상부 프레임의 중심부에 연결 파이프를 용접 설치하고, 상기 연결 파이프를 받침대를 삽입한 후 연결캡으로 고정체결한 상부조립 수단과, 상기 받침대 중간에는 다수의 지지축이 형성된 승강부를 설치하여 프레임의 가로지지대와 세로지지대가 교차하는 각 모서리부분을 상기 지지축 끝단의 지지대로 받치는 보강수단과, 상기 보강수단의 승강부 하측에는 높이 조절대로 높이를 조절하는 높이 조절수단으로 이루어진 것이다.The present invention relates to a structural slab form support device for firmly supporting a panel by installing a reinforcing means in the middle of the pedestal while constructing a panel and a support device (dongbari) in a form that can be disassembled and assembled. The connecting pipe is welded and installed in the center of the configured upper frame, and the upper assembly means is fixed by fastening the connecting pipe with a connecting cap, and a lifting part having a plurality of support shafts is installed in the middle of the pedestal. Reinforcing means for supporting each corner portion that the support and the vertical support crosses with the support of the end of the support shaft, and the height adjusting means for adjusting the height in the lower side of the lifting portion of the reinforcing means.

Description

건축용 슬라브 폼 지지장치Building Slab Foam Support

제1도는 본 발명의 설치 상태를 나타낸 분해 사시도.1 is an exploded perspective view showing an installation state of the present invention.

제2도는 본 발명의 설치 상태를 나타낸 전단면도.2 is a front sectional view showing an installation state of the present invention.

제3도는 제2도의 A부 상태 확대도.3 is an enlarged view of a state of part A of FIG.

제4도는 제2도의 B부 상세 확대도.4 is a detailed enlarged view of part B of FIG.

제5도는 종래의 예를 설명 하기 위한 사시도.5 is a perspective view for explaining a conventional example.

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

2 : 프레임 4 : 합판2: frame 4: plywood

6 : 가로지지대 8 : 세로지지대6: horizontal support 8: vertical support

10 : 상부조립수단 12 : 연결파이프10: upper assembly means 12: connection pipe

14 : 고정돌기 16 : 받침대14: fixing projections 16: pedestal

18 : 단턱 19 : 나선18: step 19: spiral

20 : 연결캡 22 : 연결핀20: connecting cap 22: connecting pin

30 : 보강수단 34 : 승강부30: reinforcing means 34: lifting unit

35 : 격판 38 : 지지축35: plate 38: support shaft

42 : 지지대 43 : 격벽42: support 43: bulkhead

44 : 상부턱 46 : 하부턱44: upper jaw 46: lower jaw

47 : 중간대 48 : 힌지47: Middle 48: Hinge

60 : 높이조절수단 62 : 높이조절대60: height adjustment means 62: height adjustment

64 : 부싱 68 : 록킹부64: bushing 68: locking part

70 : 힌지 72 : 나선70: hinge 72: spiral

74 : 걸림손잡이74: jam handle

본 발명은 건축용 슬라브 폼(Form) 지지장치에 관한 것으로, 특히 패널과 지지장치(동바리)를 분해와 조립이 가능한 형태로 구성하는 한편, 받침대 중간에는 보강수단을 설치하여 견고히 패널을 지지하는 건축용 슬라브 폼(Form) 지지장치에 관한 것이다.The present invention relates to a building slab form support device, and in particular, the panel and the support device (circle) in a form that can be disassembled and assembled, while in the middle of the pedestal building slabs for firmly supporting the panel by installing reinforcement It relates to a form support device.

일반적으로 폼(Form) 또는 거푸집은 콘크리트 타설시에 건축물의 벽면이나 바닥판을 형성하기 위하여 일정한 형태를 갖는 것으로서, 특히 바닥 또는 보의 밑부분을 형성하기 위한 종래의 슬라브 폼(Form)은 동바리를 세운후 그 위에 멍에를 걸치고, 멍에 위에 장선을 올려놓은 다음 합판을 깔아서 완성하는 것이다.In general, a form or formwork has a certain shape to form a wall or floor plate of a building when concrete is laid. In particular, a conventional slab form for forming the bottom of a floor or beam is a copper bar. Yoke it up, put it on the yoke, put the joist on the yoke and lay the plywood to complete it.

이러한 종래의 것은 폭이 좁은 목재위로 걸어 다니면서 폼(Form)을 설치하는 것으로 각종 안전사고가 많이 발생할 뿐만 아니라 폼(Form)의 구성요소인 동바리, 멍에, 장선등이 각각 구성되어 있으므로 자재의 손실과 공사기간이 길어지기 때문에 공사비가 많이 투입되는 등의 문제점이 있다.Such a conventional method is to install a form while walking on a narrow wood, and not only a lot of safety accidents occur, but also a component of a form, such as a copper bar, a yoke, and a joist, respectively, causes loss of materials and Since the construction period is long, there are problems such as a lot of construction costs.

이러한 종래의 문제점을 해소하기 위하여 도면 제5도에 도시한 바와 같이 패널(51)의 하단에 철제로 된 비임(52)을 설치하고 드롭헤드(Drop Head)(53)가 결합되어 있는 받침대(54)에 의하여 지지되고 있는 폼(Form)이 제한된 바 있으나, 이것 역시 각 구성요소들이 각각 별개로 구성되어 있을 뿐만 아니라 대부분이 무거운 철재로 구성되어 있으므로 조립 및 분해작업이 곤란한 등의 문제점이 있는 것이다.In order to solve such a conventional problem, as shown in FIG. 5, an iron beam 52 is installed at the lower end of the panel 51 and a pedestal 54 having a drop head 53 coupled thereto. The form is supported by the () has been limited, but this also has a problem, such as difficult to assemble and disassembly because each component is composed of each, as well as most of the heavy steel.

따라서, 본 발명은 이러한 문제점을 해소하기 위하여 발생된 것으로, 조립 및 분해가 용이하여 폼(Form)의 설치작업을 안전하고 신속하게 할 수 있으며, 균일한 품질의 콘크리트 슬라브층을 형성할 수 있는 건축용 슬라브 폼(Form)을 제공하는데 그 목적이 있다.Accordingly, the present invention has been made to solve such a problem, it is easy to assemble and disassemble, so that the installation work of the form (Form) can be safely and quickly, the building material that can form a concrete slab layer of uniform quality The purpose is to provide a slab form.

상기한 바와 같은 목적을 달성하기 위한 본 발명은 철재 또는 알루미늄으로 구성된 상부 프레임의 중심부에 연결 파이프를 용접 설치하고, 상기 연결 파이프를 받침대를 삽입한 후 연결캡으로 고정체결한 상부조립 수단과, 상기 받침대 중간에는 다수의 지지축이 형성된 승강부를 설치하여 프레임의 가로지지대와 세로지지대가 교차하는 각 모서리부분을 상기 지지축 끝단의 지지대로 받치는 보강수단과, 상기 보강수단의 승강부 하측에는 높이 조절대로 높이를 조절하는 높이 조절수단으로 이루어진 것이다.The present invention for achieving the object as described above is installed by welding the connecting pipe in the center of the upper frame made of steel or aluminum, and inserting the pedestal of the connecting pipe and the upper assembly means fixed by the connecting cap, and In the middle of the pedestal is provided with a lifting portion formed with a plurality of support shafts to support each corner portion of the cross and the vertical support of the frame as a support of the end of the support shaft end, and the lower side of the lifting portion of the reinforcement means It consists of height adjustment means for adjusting the height.

이하, 본 발명을 첨부된 도면에 의거 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

제1도 및 제2도는 본 발명의 설치 상태를 도시한 것으로, 합판(4)이 재치되는 프레임(2)은 가로지지대(6)와 세로지지대(8)가 구획되게 구성되어 있으며, 상기 가로지지대(6)와 세로지지대(8)의 교차하는 지점에는 연결파이프(12)를 용접 설치하고, 그 내측에는 받침대(16)의 상측을 삽입고정할 수 있는 상부조립수단(10)과; 상기 받침대(16) 중간에는 승강이 가능한 승강부(34)를 설치하되, 프레임(2)의 가로지지대(6)와 세로지지대(8)가 교차하는 각 모서리 부분에는 상기 승강부(34)와 연결된 지지축(38)의 끝단에 설치된 지지대(42)를 고정 지지하며, 상기 지지축(38) 사이에는 상기 받침대(16)과 연결된 중간대(46)를 설치한 보강수단(30)과; 상기 보강수단(30)의 승강부(34)의 높이를 조절할 수 있도록 받침대(16) 중간에는 나선(19)을 설치하고, 상기 나선(19) 형성부에는 높이를 조절하는 높이 조절대(62)가 설치된 높이 조절수단(60)으로 이루어진 구성을 나타낸다.1 and 2 illustrate the installation state of the present invention, the frame 2 on which the plywood 4 is mounted is configured such that the horizontal support 6 and the vertical support 8 are partitioned. An upper assembly means (10) capable of welding and installing a connecting pipe (12) at an intersection point of the (6) and the vertical support (8), and inserting and fixing the upper side of the pedestal (16) therein; In the middle of the pedestal 16 is provided a lifting portion 34 which can be lifted, the support portion connected to the lifting portion 34 at each corner portion of the horizontal support 6 and the vertical support 8 of the frame 2 intersect. Reinforcing means (30) fixedly supporting a support (42) installed at an end of the shaft (38), and an intermediate bar (46) connected to the pedestal (16) between the support shafts (38); A height adjuster 62 is installed in the middle of the pedestal 16 to adjust the height of the lifting portion 34 of the reinforcing means 30, and the height is adjusted to the spiral 19 forming portion. Represents a configuration consisting of the height adjustment means 60 is installed.

제3도는 본 발명의 상부 조립수단(10)을 나타낸 확대도로서, 상기 프레임(2)의 중앙의 연결파이프(12) 내부에는 받침대(16)의 내경을 고정하는 고정돌기(14)와 그 외경에는 나선을 형성하며, 상기 연결파이프(12) 내경에는 상단과 일정거리를 두고 단턱(18)이 형성된 받침대(16)를 삽입하고, 상기 연결파이프(12)에는 연결캡(20)을 받침대(16)의 상측에 형성된 단턱(18)을 사이에 두고 상기 연결파이프(12) 하측에 형성된 나선(19)과 연결 고정하는 한편, 상기 받침대(16)의 상측과 상기 연결파이프(12)를 서로 관통하는 연결관(22)을 삽입고정한 구성을 보여준다.Figure 3 is an enlarged view showing the upper assembly means 10 of the present invention, the fixing projection 14 and the outer diameter of the fixing pipe 14 for fixing the inner diameter of the pedestal 16 in the connection pipe 12 in the center of the frame (2) A spiral is formed in the connection pipe 12, and a pedestal 16 having a step 18 formed at a predetermined distance from the upper end is inserted into the connection pipe 12, and the connection cap 20 is provided with the pedestal 16 at the connection pipe 12. While fixing the connection with the spiral (19) formed on the lower side of the connecting pipe 12 with the step (18) formed in the upper side of the (), while passing through the upper side of the pedestal 16 and the connecting pipe 12 to each other The configuration in which the connector 22 is fixed is shown.

제2도 및 제4도는 본 발명의 보강수단(30) 및 높이 조절수단(60)을 나타낸 것이다.2 and 4 show the reinforcement means 30 and the height adjustment means 60 of the present invention.

먼저, 보강수단(30)은 상기 받침대(16) 중간에 형성된 나선 상단에 위치되는 것으로, 상기 나선 상단에는 다수의 격판(35)을 일체로 형성한 승강부(34)를 설치하고, 승강부(34)의 격판(35)에는 다수의 지지축(38)을 회전가능하게 되도록 힌지(36) 결합하며, 지지축(38)의 끝단에는 상기 프레임(2)의 가로지지대(6)과 세로지지대(8)의 교차부분인 각 모서리 부분에 좌, 우 지지용 격판(42) 및 처짐 방지용 상, 하부턱(44)(46)으로 구성된 지지대(42)룰 고정하는 한편, 상기 다수 지지축(38) 중간과 상기 승강부(34) 상측의 받침대(16) 사이에는 중간대(46)를 힌지(48) 결합한 것이다.First, the reinforcing means 30 is located at the upper end of the spiral formed in the middle of the pedestal 16, the upper end of the spiral is provided with a lifting unit 34 formed integrally with a plurality of diaphragm 35, the lifting unit ( The hinge 35 is coupled to the diaphragm 35 of the 34 to allow the support shaft 38 to be rotatable, and the horizontal support 6 and the longitudinal support (6) of the frame 2 are connected to the end of the support shaft 38. Fixing the support 42 consisting of the left and right support diaphragm 42 and the sagging prevention upper and lower jaw 44 and 46 to each corner portion that is the intersection of 8), while the multiple support shaft 38 Between the middle and the pedestal 16 above the elevating portion 34 is a hinge 48 is coupled to the middle.

또한, 높이조절수단(60)은 상기 받침대(16) 중간의 나선(19)에 위치되어 높이를 조절하는 것으로, 일측이 개방되고 내부 일측에 상기 보강대(16)의 외경과 동일한 내경의 부싱(64)의 고정된 높이 조절대(62)를 설치하여 상기 높이 조절대(62)의 개방부에는 내측에 나선(72)이, 그 일측에는 걸림손잡이(74)를 형성한 록킹부(68)가 힌지(70) 결합된 구성을 나타낸다.In addition, the height adjusting means 60 is located in the spiral 19 in the middle of the pedestal 16 to adjust the height, one side is open and the bushing 64 of the inner diameter equal to the outer diameter of the reinforcing table 16 on one inner side The fixed height adjuster 62 is installed, the opening of the height adjuster 62 is hinged by a locking portion 68 formed with a spiral 72 on the inside and a locking handle 74 on one side thereof. 70 shows a combined configuration.

상기와 같이 구성된 본 발명의 작용효과를 설명하면 다음과 같다.Referring to the effects of the present invention configured as described above are as follows.

조립시 상기 상부조립수단(10)을 먼저 고정하고, 프레임의 가로지지대(6)와 세로지지대(8)의 교차부분인 각 모서리부에 보강수단(30)을 설치하고, 이와 동시에 상기 보강수단(30)의 높이를 조절하는 높이 조절수단(60)을 장착하여 조립을 완성하는 것이다.When assembling, the upper assembly means 10 is first fixed, and reinforcement means 30 is installed at each corner that is an intersection of the horizontal support 6 and the vertical support 8 of the frame, and at the same time the reinforcement means ( 30 is to complete the assembly by mounting the height adjusting means (60) to adjust the height.

이를 상세히 설명하면, 먼저, 상부 조립수단(10)의 조립을 프레임(2)의 가로지지대(6)와 세로지지대(10)가 교차하는 중심부에 용접설치된 연결파이프(12)의 내부의 고정돌기(14)에 받침대(16)의 끝단내경을 억지끼워 맞춤으로 고정하여 흔들림을 방지하는 한편, 통상의 받침대(16) 중간에 설치되는 잭(jack; 도시되지 않음)을 조절하여 프레임(2)의 높이를 바닦면과 맞춘다. 그후, 상기 연결파이프(12)와 받침대(16) 상단을 견고히 조립하기 위하여 받침대(16)의 단턱(18)을 받치고 연결파이프(12)와 연결되는 연결캡(20)을 회전시켜 고정하므로서, 콘크리트 타설시 받침대(16)의 흔들림을 최소화 하고, 연결파이프(12)와 받침대(16)을 관통하는 연결핀(22)을 삽입하여 받침대(16)가 기울어지는 것을 방지한다.In detail, first, assembling of the upper assembly means 10, the fixing projections inside the connection pipe 12 welded to the center of the horizontal support 6 and the vertical support 10 of the frame 2 intersects ( 14) by pressing the inner diameter of the end of the pedestal 16 to fit to prevent shaking, while adjusting the jack (not shown) installed in the middle of the ordinary pedestal 16 to adjust the height of the frame (2) To the bottom. Then, in order to firmly assemble the connection pipe 12 and the upper end of the pedestal 16, by supporting the step 18 of the pedestal 16 and rotating by fixing the connection cap 20 connected to the connection pipe 12, concrete Minimize the shaking of the pedestal 16 during pouring, inserting the connecting pipe 12 and the connecting pin 22 penetrating the pedestal 16 to prevent the pedestal 16 is inclined.

그후, 콘크리트의 타설시 하중에 의한 프레임(2)의 모서리 부분의 처짐을 방지하기 위하여 가로지지대(6)와 세로지지대(8)가 이루는 각 모서리부에 승강부(34)를 상승시켜 지지축(38)의 끝단에 설치된 지지대(42)가 각 모서리 부분에 안착시킴과 동시에 높이조절대(62)의 록킹부(68)의 걸림손잡이(74)를 잠그면 록킹부(68) 내면의 나선(72)이 받침대(16)의 나선(19)에 걸려 고정되므로서 승강부(34)는 아래로 처지지 안하게 되어 모서리 부분을 지지하는 것이다.After that, in order to prevent sagging of the corner portion of the frame 2 due to the load during the concrete pouring, the lifting portions 34 are raised to the corner portions formed by the horizontal support 6 and the vertical support 8 to support the shaft ( The support 42, which is installed at the end of the end 38, is seated at each corner and at the same time the locking handle 74 of the locking portion 68 of the height adjustment 62 is locked, and the spiral 72 of the inner surface of the locking portion 68 is locked. The lifting portion 34 is supported by the edge 19 of the pedestal 16 while being fixed to the spiral 19 so as not to sag down.

또한, 콘크리트의 타설이 끝난후 지지장치의 해체는 상기 조립의 역순으로 이루어지는 것이다.In addition, the disassembly of the support device after finishing the concrete is done in the reverse order of the assembly.

이와 같은 본 발명은 종래의 철골, 콘크리트 구조물의 슬라브용 폼(Form)은 그 구성요소가 동바리, 멍에, 장선등으로 각각 구성되어 있으므로, 조립 및 분해시에 자재의 손실이 많은 뿐만 아니라 공사기간이 길어지는 문제점이 있는 것인데 반하여, 슬라브용 폼(Form) 각 구성요소를 분해 및 조립이 용이하도록 일체화 한 것이므로 슬라브용 폼(Form)의 설치작업을 안전하고 신속하게 할 수 있을 뿐만 아니라 재생이 가능하여 공사비를 절감할 수 있으며, 본 발명의 슬라브 폼(Form)은 수명이 맞지 아니하면 조립이 되지 아니하므로 균일한 품질과 양질의 건축물을 형성할 수 있는 효과가 있다.In the present invention as described above, the slab form (form) of the conventional steel frame, concrete structure is composed of each of the components, such as clubb, yoke, joist, etc., as well as a lot of material loss during assembly and disassembly as well as construction period On the contrary, the components of the slab form are integrated to facilitate disassembly and assembly. Therefore, the installation work of the slab form can be safely and quickly performed, as well as recyclable. Construction cost can be reduced, the slab form of the present invention (Form) is not assembled if the life does not fit, there is an effect that can form a uniform quality and high-quality buildings.

Claims (4)

프레임(2)의 중심부에는 연결파이프(12)를 형성하여 받침대(16)을 삽입한후, 연결파이프(12)와 받침대(16)를 연결캡(20)으로 고정 체결한 상부조립수단(10)과; 상기 받침대(16) 중간에는 승강부(34)를 설치하여 프레임의 각 모서리 부분에 상기 승강대와 연결된 지지축(38)을 고정한 보강수단(30)과; 상기 보강수단(30)의 승강부(34)의 높이를 조절할 수 있도록 받침대(16) 중간부의 나선(19)에 높이조절대(62)가 설치된 높이조절수단(60)으로 이루어진 것을 특징으로 하는 건축용 슬라브 폼(Form) 지지장치.After forming the connecting pipe 12 in the center of the frame (2) to insert the pedestal 16, the upper assembly means 10 for fastening the connection pipe 12 and the pedestal 16 fixed with the connecting cap 20 and; Reinforcing means 30 is installed in the middle of the pedestal 16 to secure the support shaft 38 connected to the platform in each corner portion of the frame; Building construction, characterized in that the height adjusting means 60 is installed in the helix 19 of the middle portion of the pedestal 16 to adjust the height of the lifting portion 34 of the reinforcement means 30 is installed. Slab form support. 제1항에 있어서, 상기 상부조립수단(10)은 프레임(2)의 중앙의 연결파이프(12) 내부에는 받침대(16)의 내경을 고정하는 고정돌기(14)와 그 외경에는 나선을 형성하며, 상기 연결파이프(12) 내경에는 상단과 일정거리를 두고 단턱(18)이 형성된 받침대(16)을 삽입하고, 상기 연결 파이프(12)에는 연결캡(20)을 받침대(16)의 상측에 형성된 단턱(18)을 사이에 두고 상기 연결파이프(12) 하측에 형성된 나선(19)과 연결고정하는 한편, 상기 받침대(16)의 상측과 상기 연결파이프(12)를 서로 관통하는 연결핀(22)을 삽입고정한 것을 특징으로 하는 건축용 슬라브 폼(Form) 지지장치.According to claim 1, wherein the upper assembly means 10 is formed inside the connecting pipe 12 of the center of the frame 2 to the fixing projections 14 for fixing the inner diameter of the pedestal 16 and the outer diameter of the spiral In the inner diameter of the connecting pipe 12, a pedestal 16 having a step 18 formed therein is inserted at a predetermined distance from the top, and the connecting pipe 12 has a connecting cap 20 formed on the upper side of the pedestal 16. The connecting pin 22 penetrating the upper side of the pedestal 16 and the connecting pipe 12 while fixing the connection with the spiral 19 formed on the lower side of the connecting pipe 12 with the step 18 therebetween. Building slab form (Form) support device, characterized in that the fixing. 제1항에 있어서, 상기 보강수단(30)은 받침대(16) 중간에 형성된 나선 상단에 위치되는 것으로, 상기 나선 상단에는 다수의 격판(35)에는 다수의 지지축(38)을 회전가능하게 하도록 힌지(26) 결합하며, 지지축(38)의 끝단에는 상기 프레임(2)의 가로지지대(6)와 세로지지대(8)의 교차부분인 각 모서리 부분에 좌, 우 지지용 격판(42) 및 처짐 방지용 상, 하부턱(44)(46)으로 구성된 지지대(42)를 고정하는 한편, 상기 다수 지지축(38) 중간과 상기 승강부(34) 상측의 받침대(16) 사이에는 중간대(46)을 힌지(48) 결합한 것을 특징으로 하는 건축용 슬라브 폼(Form) 지지장치.According to claim 1, wherein the reinforcing means 30 is located at the top of the spiral formed in the middle of the base 16, the top of the spiral so that the plurality of support shafts (38) on the plurality of diaphragm (35) rotatable Hinge 26 is coupled to the end of the support shaft 38, the left and right support diaphragm 42 and each corner portion that is the intersection of the horizontal support 6 and the vertical support (8) of the frame (2) and The support 42 which consists of upper and lower jaw 44 and 46 for sag prevention is fixed, and the intermediate | middle stand 46 is between the middle of the said multiple support shaft 38, and the pedestal 16 above the lifting-up part 34. The hinge slab 48, characterized in that the building slab form (Form) support device. 제1항에 있어서, 상기 높이조절수단(60)은 받침대(16) 중간의 나선(19)에 위치되어 높이를 조절하는 것으로, 일측이 개방되고 내부 일측에 상기 보강대(16)의 외경과 동일한 내경의 부싱(64)이 고정된 높이 조절대(62)를 설치하여 상기 높이 조절대(62)의 개방부에는 내측에 나선(72)이 그 일측에는 걸림손잡이(74)를 형성하는 록킹부(68)가 힌지(70) 결합된 구성을 특징으로 하는 건축용 슬라브 폼(Form) 지지장치.According to claim 1, wherein the height adjustment means 60 is located in the spiral 19 in the middle of the pedestal 16 to adjust the height, one side is open and the inner diameter of the same as the outer diameter of the reinforcing table 16 on the inner side The locking portion 68 is provided with a height adjuster 62 to which the bushing 64 is fixed to form an engaging handle 74 on one side thereof with a spiral 72 inside the opening of the height adjuster 62. Construction slab form support device characterized in that the hinge (70) combined configuration.
KR1019950029621A 1995-09-12 1995-09-12 Strut for slabforms KR0162033B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019950029621A KR0162033B1 (en) 1995-09-12 1995-09-12 Strut for slabforms

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019950029621A KR0162033B1 (en) 1995-09-12 1995-09-12 Strut for slabforms

Publications (2)

Publication Number Publication Date
KR970015980A KR970015980A (en) 1997-04-28
KR0162033B1 true KR0162033B1 (en) 1998-12-15

Family

ID=19426468

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019950029621A KR0162033B1 (en) 1995-09-12 1995-09-12 Strut for slabforms

Country Status (1)

Country Link
KR (1) KR0162033B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100738410B1 (en) * 2005-11-14 2007-07-11 깨뱉시스템주식회사 Support system for Flying form and Concreate slab construction method using the same
KR100855120B1 (en) 2007-03-06 2008-08-28 삼성중공업 주식회사 Supporter for block support of ship
KR20200099754A (en) * 2019-02-15 2020-08-25 가톨릭관동대학교산학협력단 Expandable supporting post with a wide work space
KR102404978B1 (en) * 2021-09-29 2022-06-08 장익식 the deck support structure for seismic resistance
KR20230067846A (en) * 2021-11-10 2023-05-17 주식회사 비에스티산업 Waffle form system capable of removing with supporting
KR20230146406A (en) * 2022-04-12 2023-10-19 한국삭도플렛폼 주식회사 Plank road

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114046062A (en) * 2021-12-15 2022-02-15 华济建设工程集团有限公司 Novel independent braced system of post-cast strip

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100738410B1 (en) * 2005-11-14 2007-07-11 깨뱉시스템주식회사 Support system for Flying form and Concreate slab construction method using the same
KR100855120B1 (en) 2007-03-06 2008-08-28 삼성중공업 주식회사 Supporter for block support of ship
KR20200099754A (en) * 2019-02-15 2020-08-25 가톨릭관동대학교산학협력단 Expandable supporting post with a wide work space
KR102404978B1 (en) * 2021-09-29 2022-06-08 장익식 the deck support structure for seismic resistance
KR20230067846A (en) * 2021-11-10 2023-05-17 주식회사 비에스티산업 Waffle form system capable of removing with supporting
KR20230146406A (en) * 2022-04-12 2023-10-19 한국삭도플렛폼 주식회사 Plank road

Also Published As

Publication number Publication date
KR970015980A (en) 1997-04-28

Similar Documents

Publication Publication Date Title
KR0162033B1 (en) Strut for slabforms
KR100860064B1 (en) A slab panel structure of joint type mold
KR20220022256A (en) Non-welding prefabricated deck stairs
KR200201589Y1 (en) Spring support for slab
JP2623200B2 (en) Formwork equipment
CN112095875B (en) Rapid supporting system of building composite floor slab with steel bar structure and construction process thereof
KR200298117Y1 (en) framable set mold for construction
KR0152385B1 (en) Slab form panel
JP3423162B2 (en) Handrail wall panel mounting structure
JPH0874361A (en) Fixture for mounting external wall material and method of laminating high-and-medium-rise building by using the same
KR100408483B1 (en) Construction method for apartment's ceiling slab
JP2642891B2 (en) Non-bearing wall construction pedestal and method of constructing non-bearing wall using the pedestal
KR102691830B1 (en) System for tableform with capable of installation and dismantlement
CN112277152B (en) Steel plate fixed precast concrete beam and manufacturing method thereof
JPH10311113A (en) Mounting structure for alc wall panel
JP3449394B2 (en) Handrail wall panel mounting bracket
KR200232411Y1 (en) Construction for apartment's ceiling slab
KR200246102Y1 (en) A mold supporter for a sleeve forming of building
KR200365824Y1 (en) Formwork for Concrete Buildings
KR200362880Y1 (en) A Support Structure of Mould for Concrete Buildings
KR20000043527A (en) Mold for constructing wall/slab
US5799447A (en) Apparatus for moving a wall form assembly
JP2745238B2 (en) Temporary support for slab half PCa board erection
JP2981123B2 (en) Jig for rebar assembly
JPH0512546U (en) Nemaki hardware for pillar formwork

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant