KR0148062B1 - Pile driving casing auger machine and foundation pile working method - Google Patents

Pile driving casing auger machine and foundation pile working method

Info

Publication number
KR0148062B1
KR0148062B1 KR1019950012143A KR19950012143A KR0148062B1 KR 0148062 B1 KR0148062 B1 KR 0148062B1 KR 1019950012143 A KR1019950012143 A KR 1019950012143A KR 19950012143 A KR19950012143 A KR 19950012143A KR 0148062 B1 KR0148062 B1 KR 0148062B1
Authority
KR
South Korea
Prior art keywords
casing
excavation
ready
auger
made pile
Prior art date
Application number
KR1019950012143A
Other languages
Korean (ko)
Other versions
KR960041555A (en
Inventor
박주민
Original Assignee
이내흔
현대건설주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이내흔, 현대건설주식회사 filed Critical 이내흔
Priority to KR1019950012143A priority Critical patent/KR0148062B1/en
Publication of KR960041555A publication Critical patent/KR960041555A/en
Application granted granted Critical
Publication of KR0148062B1 publication Critical patent/KR0148062B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/22Placing by screwing down
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/72Pile shoes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0038Production methods using an auger, i.e. continuous flight type

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

본 발명은 지중 굴착작업을 보다 효율적으로 수행하여서 기성말뚝의 매설 시공에 따른 작업능률 향상시켜주는 기성말뚝근입용 케이싱오거 및 그를 이용한 기성말뚝의 시공방법에 관한 것으로, 본 발명의 기술적 구성상의 특징은 내부에 기성말뚝(40)이 끼워질 수 있는 정도의 내경으로서 길게 형성된 끼움통로부(11)를 가지며 그 외측에 나선형의 토사배출띠(12)를 형성하여서 된 굴착케이싱(10)과, 상기 굴착케이싱(10)의 하단부에 착설되어지며 그 저하부에 굴착날(21)이 부착되는 굴착캡(20)과, 상기 굴착케이싱(10)의 상부에 착탈가능하게 끼워져서 조립되며 그 상단부 중앙에 돌출 형성되는 회동축(31)을 가지는 회동캡(30)으로 구성된 것에 있어서, 상기 굴착케이싱(10) 외주면 둘레에 형성되는 토사배출띠(12)는 그 굴착케이싱(10) 외주연의 상부로부터 하부까지 상호 일정간격을 유지하면서 나선형으로 감아지는 제 1, 제 2 나선띠판(12a)(12b)을 1개조로 하여 이루어지도록 하고, 상기 굴착케이싱(10) 최하부 끝단의 외주연 둘레에 등간격마다 소정의 각도로서 빗경사지게 굴착비트(13)들을 착설하여서 된 기성말뚝근입용 케이싱오거 및; 해당 작업위치의 지중에 케이싱오거(10)를 굴진시키면서 굴착작업을 수행하여서 굴착공(50)을 천공하고, 천공된 굴착공(50) 내에 위치한 케이싱오거(10) 상부를 개방하여 그 케이싱오거(10) 내부에 기성말뚝(40)을 근입하여, 케이싱오거(10)와 근입된 기성말뚝(40) 사이에 시멘트페이스트(80)를 주입하여서 충진하고, 주입된 시멘트페이스트(80)가 경화되기 이전에 굴착공(50)으로부터 케이싱오거(10)를 인발시켜서 굴착공(50) 내에서 경화된 시멘트페이스트(80)로서 기성말뚝(40)을 매립시키는 공정을 순차적으로 수행하여서 된 케이싱오거를 이용한 기성말뚝의 시공방법이다.The present invention relates to a ready-made pile inlet casing auger and a method of constructing a ready-made pile using the same, which performs underground excavation work more efficiently and improves work efficiency according to the construction of the ready-made pile. Excavation casing (10) and the excavation casing (10) formed by forming a spiral soil discharge band (12) on the outside having a fitting passage portion (11) formed long as an inner diameter to fit the ready-made pile 40 therein, the excavation The excavation cap 20 is installed in the lower end of the casing 10 and the excavation blade 21 is attached to the lower portion of the casing 10, and is detachably fitted to the upper portion of the excavation casing 10. In the configuration consisting of a rotating cap 30 having a rotating shaft 31 is formed, the earth and sand discharge strip 12 formed around the outer circumferential surface of the excavating casing 10 is lower from the top of the outer periphery of the excavating casing 10 The first and second spiral strips 12a and 12b wound in a spiral shape are kept in one piece while maintaining a constant distance therebetween, and predetermined at equal intervals around the outer periphery of the lowermost end of the excavating casing 10. And a built-in casing auger, which is made by laying excavation bits 13 at an angle of inclination; Drilling the excavation hole 50 by drilling the casing auger 10 in the ground of the work position, and open the upper casing auger 10 located in the drilled excavation hole 50 to open the casing auger ( 10) by filling the ready-made pile 40 therein, filling by filling the cement paste 80 between the casing auger 10 and the ready-made pile 40, before the injected cement paste 80 is hardened The casing auger 10 is drawn from the excavation hole 50 to sequentially fill the ready-made pile 40 as the cement paste 80 cured in the excavation hole 50. Construction method of pile.

Description

기성말뚝근입용 케이싱오거 및 그를 이용한 기성말뚝의 시공방법Casing auger for ready-made pile root and construction method of ready-made pile using the same

제 1 도의 (a),(b)는 종래 박육강관말뚝의 매설공법을 나타낸 예시도Figure 1 (a), (b) is an exemplary view showing a method of embedding a conventional thin steel pipe pile

제 2 도는 종래 박육강관말뚝을 나타낸 예시도2 is an exemplary view showing a conventional thin steel pipe pile

제 3 도는, 본발명 케이싱오거의 분해 사시도3 is an exploded perspective view of the casing auger of the present invention

제 4 도는, 본발명 케이싱오거의 조립 사시도4 is an assembled perspective view of the present invention casing auger

제 5 도는, 본발명 케이싱오거의 종단면도5 is a longitudinal sectional view of the present invention casing auger

제 6 도는, 본발명의 실시상태를 나타낸 예시도6 is an exemplary view showing an embodiment of the present invention.

제 7 도의 (a)(b)(c)(d)는, 본발명의 케이싱오거를 이용한 기성말뚝 시공방법에 따른 단계별 공정을 순차적으로 예시한 것임(A) (b) (c) (d) of FIG. 7 sequentially illustrate the step-by-step process according to the ready-made pile construction method using the casing auger of the present invention.

* 도면의 주요 부분에 대한 부호의 설명* Explanation of symbols for the main parts of the drawings

10 : 굴착 케이싱 11 : 끼움통로부10: excavation casing 11: fitting passage portion

12 : 토사배출띠 12a,12b : 제1, 제2 나선띠판12: earth and sand discharge band 12a, 12b: first, second spiral strip plate

13 : 굴착비트 14 : 삽입부13: drilling bit 14: insertion

15 : 끼움돌기 20 : 굴착캠15: fitting protrusion 20: excavation cam

21 : 굴착날 22 : 결합편21: excavation blade 22: coupling piece

30 : 회동홈 31 : 회동축30: rotating groove 31: rotating shaft

32 : 끼움홈 33 : 고정편32: fitting groove 33: fixing piece

본 발명은 건축물 자체의 하중을 지반층에 전달시켜서 지지하여 주는 기성말뚝을 지중에 매설하기 위한 것으로, 특히 지중 굴착작업을 보다 효율적으로 수행하여서 기성말뚝의 매설 시공에 따른 작업능률 향상시켜주는 기성말뚝근입용 케이싱오거 및 그를 이용한 기성말뚝의 시공방법에 관한 것이다.The present invention is to bury a ready-made pile in the ground to transfer the load of the building itself to the ground floor, and in particular, to perform the operation of underground excavation work more efficiently to improve the work efficiency according to the construction of the ready-made pile The present invention relates to a casing auger and a method for constructing a ready-made pile using the same.

현대의 건축물은 날로 고층화 및 대형화는 추세에 있으며, 이러한 고층의 건축물은 자중에 의한 수직하중이나 풍력을 크게 작용받게 되는 바, 이러한 건축물은 지층을 관통하여서 지반층에 받쳐지는 지지말뚝으로 지지되는 구조로서 시공되었다.Modern buildings are becoming increasingly tall and large in size, and these high-rise buildings are subject to large vertical loads or wind power caused by their own weight, and these structures are supported by supporting piles supported by the ground layers through the ground. It was constructed as.

이와 같이 고층의 건축물을 시공함에 있어 필수적으로 할 수 있는 말뚝공사는 항타기 등으로 타격하여 지중에 말뚝을 직접적으로 박아넣는 충격식과, 오거(Auger)를 회전시켜 굴착공을 천공한 후 그 굴착공 내에 말뚝을 근입하는 천공식으로서 대별된다. 충격식 말뚝공사는 주로 경암지반의 건축물 공사에 적용되는 반면에, 천공식 말뚝공사는 연약지반의 건축물 공사에 주로 적용되며 소음 발생을 방지할 수 있는 잇점을 가지는 것으로 알려져 있다.As such, the pile construction, which can be essential in the construction of high-rise buildings, is a shock type that directly hits the pile in the ground by hitting it with a driving machine, and drills the excavation hole by rotating an auger and then inside the excavation hole. It is roughly classified as a perforation ceremony based on the pile. Impact pile construction is mainly applied to construction of hard rock foundations, while perforated pile construction is mainly applied to construction of soft foundations and is known to have the advantage of preventing noise generation.

상기한 바와 같이 연약지반에 적용되는 천공식 말뚝공사는, 굴착장비에 장착된 오거로서 지중 굴착작업을 수행하여서 지지말뚝을 근입시킬 수 있도록 지반층까지 천공하고, 천공된 굴착공으로부터 오거를 인발한 후에 그 굴착공 내에 지지말뚝을 근입시켜서 설치하게 됨으로써, 기성말뚝 설치작업 중에 소음 발생을 방지할 수 있는 잇점을 가지게 되었다.As described above, perforated pile construction applied to the soft ground is drilled to the ground layer so that the support pile can be entered by performing underground excavation work as the auger mounted on the excavating equipment, and the auger is drawn from the drilled excavation hole. Later, by installing the support pile in the excavation hole, it has the advantage of preventing the occurrence of noise during the installation of the ready-made pile.

그러나, 이는 천공된 굴착공으로부터 오거를 인발할 때에 그 굴착공 내벽의 토사가 붕괴되어 굴착공 하부 바닥의 지반층을 두텁게 덮어서, 굴착공 내부에 근입되는 기성말뚝이 지반층과 맞닿아지지 못하였기 때문에, 기성말뚝에 가해지는 하중을 지반층에 직접 전달할 수 없어 기성말뚝을 통하여 지지되는 건축물이 구조적으로 취약한 문제점이 있었다.However, this is because when the auger is drawn from the drilled hole, the soil on the inner wall of the hole collapses and covers the ground layer of the bottom of the drill hole thickly so that the ready-made piles coming into the excavation hole cannot contact the ground layer. However, there is a problem that the structure supported by the ready-made pile is structurally weak because the load applied to the ready-made pile cannot be directly transferred to the ground layer.

상기한 바와 같은 문제점을 해결하기 위하여 제안된 것으로 일본 공개특허 특개평7-127055호에는 제 1 도에 도시된 바와 같이, 말뚝본체(1)의 하단에 바닥판(2)과 굴삭날(3, 3)을 설치하고, 이 하부 외주에 말뚝 본체외경의 2배전후의 외경을 가지는 나선날개(4)를 거의 한 번 감아 걸쳐 돌출 설치함과 동시에, 말뚝본체(1)의 헤드부 외주에 복수의 걸림턱(5.5)을 돌출 설치하여 이루어진 강관말뚝(A)의 헤드단부내에 천판(10)에 후육관(11)을 수직 설치하여 이루어지는 보강체(C)를 끼워 넣어 말뚝본체(1)에 외부로부터 삽입할 수 있는 몸통부(6)에 상기 걸림턱(5)과 착탈 자재로이 결합하는 결합홈(9, 9)을 설치한 회전캡(B)을 피감하고, 회전캡에 의하여 강관말뚝(A)을 지반에 틀어넣도록 압압하고, 나선날개(4)의 회전추진력에 의하여 매설하여 가는 박육강관말뚝의 매설공법 및;Japanese Patent Laid-Open Publication No. Hei 7-127055 has been proposed to solve the problems as described above, as shown in Figure 1, the bottom plate 2 and the excavation blade (3) at the bottom of the pile body (1) 3) is provided, and the spiral outer blade 4 having the outer diameter after the double distribution of the pile body outer diameter is almost wound once and projected on the lower outer periphery, and at the same time, a plurality of head portions of the head body 1 of the pile body 1 are provided. The reinforcement (C) formed by vertically installing the thick pipe (11) on the top plate (10) is inserted into the head end of the steel pipe pile (A) formed by protruding the locking jaw (5.5) from the outside to the pile body (1) Cover the rotating cap (B) provided with a coupling groove (9, 9) for coupling the engaging jaw (5) and the detachable material in the body portion (6) that can be inserted, the steel pipe pile (A) by the rotating cap Of thin steel pipe piles which are pressed so as to be inserted into the ground and embedded by the rotational driving force of the spiral blades 4. Process and;

제 2 도에 도시된 바와 같이, 말뚝본체(1)의 하단에 바닥판(2)과 굴삭날(3)을 설치하고, 이 하부 외주에 말뚝본체(1) 외경의 2배 전후의 외경을 가진 나선날개(4)를 거의 한 번 감아 걸쳐 돌출설치함과 동시에, 상기 말뚝본체(1)의 헤드부 외주에 복수의 걸림턱(5, 5)를 돌출 설치함과 동시에 말뚝본체(1) 헤드부의 걸림턱(5, 5)를 돌출 설치한 위치의 내부에 원형 또는 환상의 보강판(12)을 고착한 박육강관말뚝이 선출원 공개되어 있다.As shown in FIG. 2, the bottom plate 2 and the excavation blade 3 are installed at the lower end of the pile body 1, and the lower outer periphery has an outer diameter about twice as large as the outer diameter of the pile body 1. At the same time, the spiral blade 4 is wound around and provided to protrude, and at the same time, a plurality of locking jaws 5 and 5 are protruded to the outer periphery of the head portion of the pile body 1, and at the same time, the head portion of the pile body 1 is mounted. The thin-walled steel pipe pile which fixed the circular or annular reinforcement board 12 in the position which protruded and provided the latching jaws 5 and 5 is disclosed earlier.

이와 같은 박육강관말뚝의 매설공법은, 강관말뚝(A)의 헤드단부 외측에 피감된 회전캡(B)로서 강관말뚝(A)를 회전, 압압하여서 나선날개(4)의 회전추진력으로서 강관말뚝(A)를 지반에 매설할 때에, 회전력을 받는 강관말뚝(A)의 헤드부에 보강체(C)의 후육관(11)이 끼워져서 보강되도록 함으로써, 강관말뚝(A)의 헤드부가 작용되는 비틀림 회전력에 의하여 변형됨을 방지하여 주며,The method of embedding the thin steel pipe pile is a rotary cap (B) that is exposed to the outside of the head end of the steel pipe pile (A) to rotate and press the steel pipe pile (A) to serve as a rotary propulsion force of the spiral wing (4). When embedding A) in the ground, the torsion of the head of the steel pipe pile A is actuated by inserting the thick pipe 11 of the reinforcement C into the head portion of the steel pipe pile A subjected to the rotational force to be reinforced. Prevents deformation due to rotational force,

박육강관 말뚝은, 하단부에 바닥판(2)과 굴삭날(3, 3)과 대경의 나선날개(4)를 설치하여서 된 말뚝본체(1) 헤드부 내부에 보강판(12)를 고착하여, 굴착시 비틀림 회전력을 집중적으로 받게되는 강관말뚝(A)의 헤드부를 보강하여서, 강관말뚝(A)을 이루는 말뚝본체(1)의 단면을 얇게 형성할 수 있게 하였다.In the thin steel pipe pile, the reinforcing plate 12 is fixed to the inside of the head of the pile main body 1 by installing the bottom plate 2, the excavation blades 3 and 3, and the large spiral spiral blade 4 at the lower end thereof. By reinforcing the head portion of the steel pipe pile (A) to receive the torsional rotational force intensively during excavation, it was possible to form a thin section of the pile body (1) constituting the steel pipe pile (A).

즉, 이러한 박육강관말뚝의 매설방법 및 박육강관말뚝은, 기본적으로 강관말뚝(A) 자체를 회전, 압압하면서 지중에 박아넣어서 매설하게 됨으로써, 지반층에 강관말뚝(A)의 하단부가 맞닿아져서 접지되어 작용하는 하중이 직접 전달될 수 있도록 하는 장점을 가지는 동시에, 강관말뚝(A)을 이루는 말뚝본체(1)의 헤드부를 구조적으로 보강하여서 그 말뚝본체(1) 전체의 단면 두께를 최대한으로 얇게 형성시켜서 원가를 절감할 수 있는 장점을 가지는 것이 사실이다.That is, the method of embedding the thin steel pipe pile and the thin steel pipe pile is basically embedded in the ground while the steel pipe pile (A) itself is rotated and pressed, so that the lower end of the steel pipe pile (A) is in contact with the ground layer. While having the advantage of being able to directly transfer the load acting on the ground, structurally reinforcing the head portion of the pile body (1) forming the steel pipe pile (A) to make the cross-sectional thickness of the pile body (1) as thin as possible It is true that it has the advantage of reducing the cost by forming.

그러나, 이와 같은 종래의 박육강관말뚝의 매설공법 및 박육강관말뚝은, 강관말뚝 (A)을 이루는 말뚝본체(1)의 단면을 얇게 형성하여서 그 강관말뚝(A) 자체를 지중에 박아넣어서 매설하게 되는 바, 첫째 강관말뚝을 이루는 말뚝본체의 단면 두께를 얇게 형성함에 따라 굴착작업 중에 가해지는 무리한 회전력과 함께 압축력을 받게 되는 강관말뚝의 중간부가 뒤틀림이나 휨변형이 발생될 염려가 있었으며,However, such a conventional method for embedding thin steel pipe piles and thin steel pipe piles forms a thin section of the pile main body 1 constituting the steel pipe pile A and embeds the steel pipe pile A in the ground to be embedded. First, as the cross-sectional thickness of the pile body forming the steel pipe pile was thin, the middle part of the steel pipe pile subjected to the compressive force along with the excessive rotational force applied during the excavation work may be warped or bent.

둘째 강관말뚝(A)을 매설할 때마다 강관말뚝(A) 헤드부 내측에 별도의 보강체(C) 또는 보강판(12)를 설치하게 되고, 그 강관말뚝(A) 하부에는 나선날개(4)를 일일이 부착시키는 작업을 수행하게 됨으로써, 소요 부품수가 불필요하게 증가되어 경제성을 상실하게 되는 동시에 작업시에 노동력과 번거로움을 가중시켜서 작업능률이 저하되는 문제점이 있었으며,Whenever the second steel pipe pile (A) is embedded, a separate reinforcement (C) or reinforcing plate (12) is installed inside the head of the steel pipe pile (A), and the spiral wing (4) below the steel pipe pile (A) By attaching), the number of parts required is unnecessarily increased, resulting in the loss of economical efficiency, and at the same time, the labor efficiency and the hassle are increased.

셋째 회전되는 강관말뚝(A) 하부에 국한되게 설치된 나선날개(4)의 회전추진력에 의존하여 지중 굴착작업을 수행하게 됨으로써, 굴착작업 중에 굴토된 토사를 지상으로 원할하게 배출시키지 못함에 따라 실제적인 굴착능력이 저하되어서 강관말뚝(A) 매설시에 공사기간이 연장되는 문제점 등이 있었다.Third, the excavation work is carried out under the ground depending on the rotational propulsion force of the spiral wing 4 installed in the lower portion of the steel pipe pile (A) to be rotated, so that the excavated earth and sand during the excavation work cannot be discharged to the ground. There was a problem that the construction period was extended when the steel pipe pile (A) was laid due to the digging ability.

본 발명은 첫째 케이싱오거를 굴착수단으로 활용하여서 기성말뚝을 안정적이면서도 견고하게 지중에 매설시켜주어 기성말뚝 시공상의 신뢰성 향상을 도모하여, 둘째 케이싱오거 자체의 지중 굴착능력을 배가시켜서 기성말뚝 시공에 따른 공기단축을 실현시켜주며, 셋째 한 번 제작된 케이싱오거를 반복적으로 사용할 수 있도록 하여서 기성말뚝 시공에 따른 경제성을 제고하여 주는 케이싱오거 및 그를 이용한 기성말뚝의 시공방법을 제공하는데에 있다.The present invention utilizes the first casing auger as an excavation means to bury the ready-made pile in the ground stably and steadily to improve the reliability of the ready-made pile construction, and to double the underground excavation capacity of the casing auger itself according to the ready-made pile construction The present invention provides a casing auger and a method of constructing a ready-made pile using the same, which realizes a shortening of air and improves the economics of the ready-made pile by allowing the casing auger to be manufactured once and repeatedly.

본발명도, 내부에 기성말뚝(40)이 끼워질 수 있는 정도의 내경으로서 길게 형성된 끼움통로부(11)를 가지며 그 외측에 나선형의 토사배출띠(12)를 형성하여서 된 굴착케이싱(10)과, 상기 굴착케이싱(10)의 하단부에 착설되어지며 그 저하부에 굴착날(21)이 부착되는 굴착캡(20)과, 상기 굴착케이싱(10)의 상부에 착탈가능하게 끼워져서 조립되며 그 상단부 중앙에 돌출 형성되는 회동축(31)을 가지는 회동캡(30)으로 구성된 점에 있어서는 종래의 것과 기술적 개념을 같이 한다.The present invention also has an excavation casing (10) having a fitting passage portion (11) formed long as an inner diameter of the ready-made pile (40) to be fitted therein and forming a spiral soil discharge belt (12) on the outside thereof. And, the excavation cap 20 is installed on the lower end of the excavation casing 10 and the excavation blade 21 is attached to the lower portion, and is assembled by detachably fitted to the upper portion of the excavation casing 10 In terms of the rotating cap 30 having a rotating shaft 31 protruding from the center of the upper end, the technical concept is the same as the conventional one.

단, 본 발명의 기성말뚝근입용 케이싱오거(10)는 제 3 도 내지 제 6 도에 도시되는 바와 같이, 상기 굴착케이싱(10) 외주면 둘레에 형성되는 토사배출띠(12)는 그 굴착케이싱(10) 외주연의 상부로부터 하부까지 상호 일정간격을 유지하면서 나선형으로 감아지는 제 1, 제 2 나선띠판 (12a)(12b)을 1개조로하여 이루어지도록 하고, 상기 굴착케이싱(10) 최하부 끝단의 외주연 둘레에 등간격마다 소정의 각도로서 빗경사지게 굴착비트(13)들을 착설하여서 됨을 기술적 구성상의 특징으로 한다.However, as shown in FIGS. 3 to 6, the ready-made pile root inlet casing auger 10 of the present invention, the earth and sand discharge strip 12 formed around the outer peripheral surface of the excavation casing 10 is excavating casing ( 10) the first and second spiral strips 12a and 12b wound in a spiral shape while maintaining a constant distance from the top to the bottom of the outer periphery in one pair, and the bottom end of the excavation casing 10 The technical configuration is characterized in that the excavation bits 13 to be installed to be inclined at a predetermined angle at regular intervals around the outer periphery.

이와 같이 구성되는 본발명은, 첫째 케이싱오거(10)를 통하여 지중 굴착작업을 수행하여서 천공된 굴착공(50) 내에 기성말뚝(40)을 근입 설치할 수 있게 함으로써, 기성말뚝(40) 근입시에 변형이나 훼손됨이 없이 안정적으로 매설할 수 있게 됨은 물론이고, 둘째 케이싱오거(10) 외주면 전체에 걸쳐서 제 1, 제 2 나선띠판(12a)(12b)을 1개조로하여 착설된 토사배출띠(12)와 함께 굴착비트(13)로서 지중 굴착능력을 대폭적으로 향상시켜주며, 셋째 기성말뚝(40) 시공시 케이싱오거(10)를 반복적으로 계속해서 사용할 수 있도록 하여서 기성말뚝 공사를 보다 경제적으로 수행할 수 있도록 하는 장점을 가지게 되는 것이다.The present invention constituted as described above, by performing the underground excavation work through the first casing auger 10 to allow the installation of the ready-made pile 40 in the drilled drilling holes 50, when the ready-made pile 40 in Of course, it is possible to reliably bury without deformation or damage, and the earth and sand discharge bands (12) installed on the entire outer peripheral surface of the second casing auger (10) by one set of the first and second spiral strip plates (12a) (12b) ) And drastically improves the ground excavation capacity as an excavation bit (13), and by allowing the casing auger (10) to be used repeatedly during the construction of the third ready-made pile (40) to perform the ready-made pile construction more economically It will have the advantage of making it possible.

이하, 본발명의 구체적인 실시예를 통하여 각 구성부를 보다 상세히 설명하면 다음과 같다.Hereinafter, each component will be described in more detail with reference to specific embodiments of the present invention.

굴착케이싱(10)은 그 상부에 착설된 회동캡(30)에 의하여 회전하면서 굴진하게 되며, 그 굴착케이싱(10)을 통하여 기성말뚝(40)을 천공된 굴착공(50)내에 근입설치 할 수 있도록 하는 기능을 수행하는 구조부이다.Excavation casing 10 is to be excavated while rotating by the rotation cap 30 installed on the upper portion, through the excavation casing 10 can be installed in the perforated excavation hole 50 in the perforated excavation hole (50) This is the structure that performs the function.

이러한 굴착케이싱(10)은 원통형상의 강관파이프로 만들어져서 그 내부에 기성말뚝(40)이 끼워질 수 있도록 상하로 트여지는 끼움통로부(11)를 형성하고, 그 굴착케이싱(10) 외주면 둘레에는 토사배출띠(12)를 형성하여서 된다.The excavation casing 10 is made of a cylindrical steel pipe pipe to form a fitting passage portion 11 that is opened up and down so that the ready-made pile 40 can be fitted therein, and around the outer circumferential surface of the excavating casing 10. The soil discharge band 12 may be formed.

상기 토사배출띠(12)는 굴착케이싱(10) 외주면 둘레의 하부로부터 상부까지 제 1, 제 2 나선띠판(12a)(12b)을 1개조로 하여 상호 일정간격을 유지하면서 나선형으로 감아서 일체로 부착 고정된다.The earth and sand discharge strip 12 is integrally wound in a spiral while maintaining a constant interval with one set of the first and second spiral strip plates 12a and 12b from the bottom to the top of the outer circumference of the excavation casing 10. The attachment is fixed.

즉, 이러한 토사배출띠(12)는 제 1, 제 2 나선띠판(12a)(12b)을 1개조로 하여서 상기 굴착케이싱(10) 외주면 전체에 걸쳐서 형성되어, 지중 굴착시 뚫어진 굴착공(50) 내에 굴토된 토사를 지상으로 원할하게 배출시켜줌으로써, 지중 굴착작업 중에 굴착공(50) 내에 굴토된 토사에 의하여 굴착케이싱(10)에 작용되는 회전저항력을 감소시켜서 굴착공(50)을 신속하게 천공할 수 있는 동시에, 천공된 굴착공(50) 내에 기성말뚝(40)을 근입시킨 후에는 천공된 굴착공(50)으로부터 상기 굴착케이싱(10)을 용이하게 인발시킬 수 있는 잇점을 기대할 수 있게 되는 것이다.That is, the soil discharge strip 12 is formed over the entire outer circumferential surface of the excavation casing 10 by using one set of the first and second spiral strip plates 12a and 12b, and excavation hole 50 drilled during underground excavation By discharging the excavated soil in the ground smoothly, the drilling resistance 50 is quickly drilled by reducing the rotational resistance applied to the excavation casing 10 by the excavated soil in the excavation hole 50 during underground excavation work. At the same time, after incorporating the ready-made pile 40 into the drilled excavation hole 50, it is possible to expect an advantage of easily drawing the excavation casing 10 from the drilled excavation hole 50. will be.

그리고, 상기 굴착케이싱(10) 최하부 끝부분 외주면 둘레의 등간격마다 수개의 굴착비트(13)들을 소정의 각도로서 빗경사지게 착설하여서, 회전하면서 굴진되는 굴착케이싱(10)과 일체로 회전하면서 지중의 토사를 굴토하여서 굴착공(50)을 천공할 수 있도록 한다.Then, several drilling bits 13 are installed at a predetermined angle at regular intervals around the outer circumferential surface of the lowermost end of the excavation casing 10 at a predetermined angle, thereby rotating integrally with the excavating casing 10 which is excavated while rotating. By excavating the soil to be able to drill the excavation hole (50).

이때, 상기 굴착비트(13)들은 굴착케이싱(10) 외주면 전체에 걸쳐서 설치된 토사 배출띠(12)와 연계되도록 굴착케이싱(10) 하부에 배설하여서, 상기 굴착케이싱(10)이 회전하면서 굴진함에 따라 굴착비트(13)는 지중의 토사를 굴토하게 되고, 굴토된 토사는 상기 굴착케이싱(10) 외측의 토사배출띠(12)로서 지상으로 배출시키면서 굴착공(50)을 천공하게 됨으로써, 지중 굴착작업에 따른 굴착능력을 배가시켜주는 잇점을 가지게 되는 것이다.At this time, the excavation bits 13 are disposed below the excavation casing 10 so as to be connected to the earth and sand discharge strip 12 installed over the entire outer circumferential surface of the excavation casing 10, as the excavation casing 10 rotates and excavates. The excavation bit 13 is to excavate the earth and sand, the excavated soil is perforated the excavation hole 50 while discharging to the ground as the earth and sand discharge band 12 outside the excavation casing 10, underground excavation work It will have the advantage of double the excavation ability.

여기에서, 상기 굴착케이싱(10) 하단부 양측에 대향되는 한쌍의 삽입부(14)들을 절개 형성하여서 후술하는 굴착캡(20)이 조립될 수 있도록 하고, 그 굴착케이싱(10) 외측 상부 일정위치에 대향되는 한쌍의 끼움돌기(15)들을 형성하여서 후술하는 회동캡(30)이 조립될 수 있도록 한다.Here, the excavation casing (10) formed by cutting a pair of insertion portions (14) opposed to both sides of the lower end so that the excavation cap 20 to be described later to be assembled, the outer portion of the excavation casing (10) By forming a pair of opposing protrusions 15 to be assembled to the rotating cap 30 to be described later.

굴착캡(20)은 상기 굴착케이싱(10) 하단부 내측에 착탈가능하게 끼워져서 그 굴착케이싱(10) 최선단에서 토사를 굴착하는 동시에, 상기 굴착케이싱(10)을 인발할 때에는 그 굴착케이싱(10)으로부터 분리되어 기성말뚝(40)의 하단부를 받쳐주는 기능을 수행하는 구조부이다.The excavation cap 20 is detachably fitted inside the lower end of the excavation casing 10 to excavate the soil at the top end of the excavation casing 10 and at the same time when the excavation casing 10 is pulled out, the excavation casing 10 Separated from the) is a structural portion that performs the function of supporting the lower end of the ready-made pile 40.

이러한 굴착캡(20)의 저면에는 상호 일정간격을 두고 수직으로 돌출 형성되는 복수의 굴착날(21)들을 가지도록 하여, 상기 굴착케이싱(10) 하부의 최선단에서 토사 굴착작업을 수행할 수 있도록 한다.The bottom surface of the excavation cap 20 to have a plurality of excavation blades 21 protruding vertically at regular intervals to each other, so that the excavation work can be carried out at the bottom end of the excavation casing (10) do.

그리고, 상기 굴착캡(20)은 그 외주면의 대향되는 양측에, 상기 굴착 케이싱(10) 하단부에 수직으로 절개 형성된 한쌍의 삽입부(14)들과 대응하는 결합편(21)을 돌출 형성하고, 상기 굴착캡(20)의 결합편(21)을 상기 굴착케이싱(10)의 삽입부(14)에 끼워져서 굴착케이싱(10) 상부에 굴착캡(20)을 착탈가능하게 조립된다.In addition, the excavation cap 20 protrudes to form a pair of insertion portions 14 corresponding to a pair of insertion portions 14 cut vertically on the lower end of the excavation casing 10 on opposite sides of the outer peripheral surface thereof, The coupling piece 21 of the excavation cap 20 is inserted into the insertion portion 14 of the excavation casing 10 so that the excavation cap 20 is detachably assembled on the excavation casing 10.

이러한 굴착캡(20)은 그 외주면에 형성된 결합편(21)들이 상기 굴착케이싱(10)의 수직으로 절개된 삽입부(14)에 일직선으로 끼워져서 조립되기 때문에, 상기 굴착케이싱(10)이 회전하면서 굴진하는 중에는 그 굴착케이싱(10) 하부에 굴착캡(20)이 결합된 상태로서 일체로 회전하면서 굴착작업을 수행하게 된다. 또한 굴착공(50)을 천공한 굴착케이싱(10) 내부에 기성말뚝(40)을 근입시킨 상태에서 상기 굴착케이싱(10)을 인발하면, 상기 굴착케이싱(10) 하부의 굴착캡(20)이 기성말뚝(40) 하단부에 걸려서 자연스럽게 분리되면서, 상기 굴착캡(20)이 기성말뚝(40)의 하단부를 받쳐서 굴착공(50) 내의 지반층(70)에 접지시켜 주게 되는 것이다.Since the excavation cap 20 is assembled by fitting the coupling pieces 21 formed on the outer circumferential surface of the excavation casing 10 in a straight line, the excavation casing 10 rotates. While excavating while the excavation casing 10, the excavation cap 20 is coupled to the lower state while integrally rotating to perform excavation work. In addition, when the excavation casing 10 is pulled out in the state in which the ready-made pile 40 is mounted in the excavation casing 10 which drills the excavation hole 50, the excavation cap 20 under the excavation casing 10 is formed. While being naturally separated by being caught by the lower end of the ready-made pile 40, the excavation cap 20 supports the lower end of the ready-made pile 40 to be grounded to the ground layer 70 in the excavation hole 50.

회동캡(30)은 상기 굴착케이싱(10) 상부에 착탈가능하게 조립되어서 굴착장비(60)의 구동수단(61)에 의하여 회동되면서 상기 굴착케이싱(10)을 회전시켜서 굴진되게 하는 기능을 수행하는 구조부이다.Rotating cap 30 is detachably assembled on the top of the excavation casing 10 to rotate by the drive means 61 of the excavation equipment 60 to perform the function of rotating the excavation casing 10 to be excavated It is a structural department.

이러한 회동캡(30)은 그 하단부의 대향되는 양측에, 상기 굴착케이싱(10) 상부 외주면에 돌출 형성된 한쌍의 끼움돌기(15)들과 대응하는 끼움홈(32)들을 형성하고, 상기 굴착케이싱(10) 상단부 외측이 덮어지도록 회동캡(30)을 끼우고 그 회동캡(30)의 끼움홈(32)에 상기 굴착케이싱(10)의 끼움돌기(15)가 걸어물려져서 착탈가능하게 조립된다.The pivoting cap 30 forms fitting grooves 32 corresponding to the pair of fitting protrusions 15 protruding from the upper outer circumferential surface of the excavating casing 10 on both sides of the lower end thereof, and the excavating casing ( 10) Fit the rotation cap 30 so that the outer side of the upper end and the fitting protrusion 15 of the excavation casing 10 is engaged with the fitting groove 32 of the rotation cap 30 is detachably assembled.

따라서, 상기 회동캡(30)은 상기 굴착장비(60)의 구동수단(61)에 의하여 회동되면서 조립된 굴착케이싱(10)을 회전시켜서 지중 굴착작업을 수행할 수 있게 하면서도, 굴착작업이 종료된 후에는 굴착케이싱(10)으로부터 회동캡(30)을 분리하여서 천공된 굴착공(50) 내에 위치하여 상부가 개봉된 굴착케이싱(10) 내측에 기성말뚝(40)을 근입시킬 수 있게 하고, 기성말뚝(40)이 근입된 후에는 굴착공(10)로부터 굴착케이싱(10)을 인발할 수 있게 되는 것이다.Therefore, the pivoting cap 30 is rotated by the driving means 61 of the drilling equipment 60 while rotating the assembled casing 10 to perform underground excavation work, the excavation work is finished Afterwards, the rotating cap 30 is separated from the excavation casing 10 so as to be positioned in the perforated excavation hole 50 so that the top pile 40 can be mounted inside the excavating casing 10 with the upper portion opened, and After the pile 40 is entered, the excavation casing 10 can be drawn out from the excavation hole 10.

여기에서, 상기 회동캡(30)의 끼움홈(32)들은 각각 T형으로 형성하고, 그 끼움홈(32)들의 절개 자유단의 외측을 고정편(33)으로 연결하여서, 회전 굴착작업 중에 회동캡(30)의 끼움홈(32)에 가해지는 비틀림 회전력에 의한 변형을 방지하여 주도록 함이 바람직하다.Here, the fitting grooves 32 of the rotation cap 30 are each formed in a T-shape, by connecting the outer side of the incision free end of the fitting grooves 32 with the fixing piece 33, and rotates during the rotary excavation operation It is preferable to prevent deformation due to the torsional rotational force applied to the fitting groove 32 of the cap 30.

한편, 본 발명의 케이싱오거를 이용한 기성말뚝 시공방법을 첨부된 도면에 의하여 구체적으로 설명하면 다음과 같다.On the other hand, when the concrete pile construction method using the casing auger of the present invention will be described in detail by the accompanying drawings as follows.

제 7 도의 (a)는, 해당 작업위치의 지중에 케이싱오거(10)를 굴진시키면서 굴착작업을 수행하여서 굴착공(50)을 천공하는 단계의 공정을 나타낸 것이다.Figure 7 (a) shows the step of drilling the excavation hole 50 by performing the excavation work while drilling the casing auger 10 in the ground of the work position.

이와 같은 굴착공(50) 천공 작업은, 굴착케이싱(10) 상하단부에 회동캡(30)과 굴착캡(20)을 각각 조립하여서 케이싱오거(10)를 준비한 후에, 준비된 케이싱오거(10)를 굴착장비(60)의 구동수단(61)에 장착시키고, 굴착장비(60)의 구동수단(61)을 구동시켜서 케이싱오거(10)를 정회전시키면서 해당 작업위치의 지중 굴착작업을 수행하여서 굴착공(50)을 천공하게 되는 것이다.In this drilling hole 50 drilling operation, the casing auger 10 is prepared after assembling the pivoting cap 30 and the excavation cap 20 at the upper and lower ends of the excavation casing 10, respectively. Mounted in the drive means 61 of the excavation equipment 60, by driving the drive means 61 of the excavation equipment 60 to perform the underground excavation work of the work position while the forward rotation of the casing auger (10) 50 will be punched.

그리고, 굴착공(50)을 천공할 때에는 케이싱오거(10)의 하단부에 지반층(70)에 도달될 때까지 깊숙히 천공하여서, 이후에 상기 케이싱오거(10)의 굴착케이싱(10)을 통하여 천공된 굴착공(50) 내에 근입되는 기성말뚝(40)이 지반층(70)에 접지 고정될 수 있도록 한다.In addition, when drilling the drilling hole 50, it drills deeply until the bottom layer of the casing auger 10 reaches the ground layer 70, and then drills through the excavation casing 10 of the casing auger 10. The ready-made pile 40 in the excavation hole 50 to be ground-fixed to the ground layer 70.

제 7 도의 (b)는, 천공된 굴착공(50) 내에 위치한 케이싱오거(10) 상부를 개방하여 그 케이싱오거(10) 내부에 기성말뚝(40)을 근입하는 단계의 작업공정을 나타낸 것이다.FIG. 7 (b) shows the working process of opening the upper portion of the casing auger 10 located in the drilled excavation hole 50 and inserting the ready-made pile 40 into the casing auger 10. .

이와 같은 기성말뚝(40)의 근입작업은, 케이싱오거(10)로서 굴착공(50) 천공작업을 완료한 후에, 굴착장비(60)의 구동수단(61)으로부터 케이싱오거(10)를 분리시키고, 분리된 케이싱오거(10)의 회동캡(30)을 탈리하여 개방된 굴착케이싱(10) 내측의 끼움통로부(11) 상부를 통하여 콘크리트로서 성형 제조된 기성말뚝(40)을 근입시키게 되는 것이다.In this approach of the ready-made pile 40, after completing the drilling hole 50 drilling work as the casing auger 10, the casing auger 10 is separated from the drive means 61 of the excavating equipment 60 By detaching the rotating cap 30 of the separated casing auger 10, the ready-made pile 40 molded as concrete is introduced through the upper part of the fitting passage 11 inside the opened excavation casing 10. .

이때, 상기 케이싱 오거(10)을 이루는 굴착케이싱(10) 내부에 끼워진 기성말뚝(40)의 하부는 상기 굴착케이싱(10) 하단부에 조립된 굴착캡(20)과 맞닿아져서 지반층(70)에 접지되도록 근입하게 된다.At this time, the lower portion of the ready-made pile 40 fitted in the excavation casing 10 constituting the casing auger 10 is in contact with the excavation cap 20 assembled to the lower end of the excavation casing 10 to the ground layer 70. Will be grounded to ground.

제 7 도의 (c)는, 케이싱오거(10)와 근입된 기성말뚝(40) 사이에 시멘트페이스트(80)를 주입하여서 충진하는 단계의 작업공정을 나타낸 것이다.Figure 7 (c) shows the working process of the step of filling the cement paste 80 between the casing auger 10 and the ready-made pile 40 is filled.

즉, 이는 케이싱오거(10)의 굴착케이싱(10) 내부에 기성말뚝(40)이 근입된 상태에서, 상기 케이싱오거(10)의 개방된 굴착케이싱(10) 상단부에 시멘트주입구(미도시)를 통하여 그 케이싱오거(10)와 기성말뚝(40) 사이에 시멘트페이스트(80)를 주입하게 되는 것이다.That is, this is a cement inlet (not shown) at the upper end of the open casing 10 of the casing auger 10 in the state in which the ready-made pile 40 in the excavating casing 10 of the casing auger 10. The cement paste 80 is injected between the casing auger 10 and the ready-made pile 40.

제 7 도의 (d)는, 주입된 시멘트페이스트(80)가 경화되기 이전에 굴착공(50)으로부터 케이싱오거(10)를 인발시켜서 굴착공(50)내에서 경화된 시멘트페이스트(80)로서 기성말뚝(40)을 매립시켜서 시공을 완료하게 되는 것이다.FIG. 7D shows that the cement paste 80 hardened in the drilling hole 50 by drawing the casing auger 10 from the drilling hole 50 before the injected cement paste 80 is cured. The construction is completed by embedding the pile 40.

이와 같은 케이싱오거(10) 매립작업은, 굴착공(50) 내에 케이싱오거(10)와 기성말뚝(40) 사이에 혼입된 시멘트페이스트(80)가 완전히 경화되기 이전에 개방된 굴착케이싱(10) 상부에 혼입된 시멘트페이스트(80)가 완전히 경화되기 이전에 개방된 굴착케이싱(10) 상부에 회동캡(30)을 조립하고, 그 회동캡(30)을 통하여 굴착장비(60)의 구동수단(61)에 케이싱오거(10)를 장착한 후에, 굴착장비(60)의 구동수단(61)으로서 케이싱오거(10)를 역회전시키면서 굴착공(50)으로부터 인발하게 된다.The casing auger 10 is buried in the excavation hole 50 before the cement paste 80 mixed between the casing auger 10 and the ready-made pile 40 is completely hardened. Before the cement paste 80 incorporated in the upper portion is completely hardened, assembling the pivoting cap 30 on the upper opening of the excavation casing 10, the driving means of the drilling equipment 60 through the pivoting cap 30 ( After the casing auger 10 is mounted on the casing 61, the casing auger 10 is drawn out of the excavation hole 50 while the casing auger 10 is reversely rotated as the driving means 61 of the excavating equipment 60.

이때, 상기 케이싱오거(10)의 굴착케이싱(10) 하부에 위치한 굴착캡(20)은 기성말뚝(40)의 하단부를 받친 상태에서 굴착케이싱(10)으로부터 탈리되어, 기성말뚝(40) 외측의 굴착공(50) 내부에 채워지는 시멘트페이스트(80)에 의하여 기성말뚝(40)과 함께 매립되고, 케이싱오거(10)를 완전히 인발한 후에 일정시간이 경화되면서 시멘트페이스트(80)가 점차로 경화됨에 따라, 경화되는 시멘트페이스트(80)에 의하여 기성말뚝(40)이 천공된 굴착공(50) 내에 수직으로 세워져서 견고하게 매설되는 것이다.At this time, the excavation cap 20 located below the excavation casing 10 of the casing auger 10 is detached from the excavation casing 10 in a state supporting the lower end of the ready-made pile 40, the outside of the ready-made pile 40 Since the cement paste 80 filled in the excavation hole 50 is buried together with the ready-made pile 40, the cement paste 80 is gradually cured while being cured for a predetermined time after the casing auger 10 is completely drawn out. Accordingly, the ready-made pile 40 is vertically erected in the drilled drilling hole 50 by the cement paste 80 to be hardened, and is firmly embedded.

상기한 바와 같은 단계별 작업공정을 수행하는 본 발명의 케이싱오거를 이용한 기성말뚝의 시공방법은, 지중 굴착작업을 케이싱오거(10)로 수행하고, 케이싱오거(10)를 통하여 기성말뚝(40)을 천공된 굴착공(50)내에 무리하지 않게 근입시키면서도, 주입 경화된 시멘트 페이스트(80)로서 기성말뚝(40)을 지중에 견고하게 매설할 수 있도록 하는 장점을 가지고 있다.The construction method of the ready-made pile using the casing auger of the present invention performing a step-by-step work process as described above, the underground excavation operation to the casing auger (10), through the casing auger (10) the ready-made pile (40) It is possible to firmly embed the ready-made pile 40 in the ground as the injection-hardened cement paste 80 while unreasonably infiltrating into the drilled excavation hole 50.

이상에 살펴본 바와 같이 본 발명은 케이싱오거 자체의 굴착능력을 배가시켜서 기성말뚝 시공에 따른 설치작업을 효율적으로 수행하여서 공사기간을 단축시켜주는 동시에, 케이싱오거를 굴착수단으로 활용하여서 기성말뚝을 지중에 안정적이면서도 견고하게 설치할 수 있도록 하는 유용한 장점을 가지는 것이다.As described above, the present invention doubles the excavation capacity of the casing auger itself, thereby efficiently performing the installation work according to the construction of the ready-made pile, and shortens the construction period, and utilizes the casing auger as an excavating means, thus making the ready pile in the ground. It has the advantage of being stable and robust.

Claims (4)

내부에 기성말뚝(40)이 끼워질 수 있는 정도의 내경으로서 길게 형성된 끼움통로부(11)를 가지며 그 외측에 나선형의 토사배출띠(12)를 형성하여서 된 굴착케이싱(10)과, 상기 굴착케이싱(10)의 하단부에 착설되어지며 그 저하부에 굴착날(21)이 부착되는 굴착캡(20)과, 상기 굴착케이싱(10)의 상부에 착탈가능하게 끼워져서 조립되며 그 상단부 중앙에 돌출 형성되는 회동축(31)을 가지는 회동캡(30)으로 구성된 것에 있어서, 상기 굴착케이싱(10) 외주면 둘레에 형성되는 토사배출띠(12)는 그 굴착케이싱(10) 외주연의 상부로부터 하부까지 상호 일정간격을 유지하면서 나선형으로 감아지는 제 1, 제 2 나선띠판(12a)(12b)을 1개조로 하여 이루어지도록 하고, 상기 굴착케이싱(10) 최하부 끝단의 외주연 둘레에 등간격마다 소정의 각도로서 빗경사지게 굴착비트(13)들을 착설하여서 됨을 특징으로 하는 기성말뚝근입용 케이싱오거.Excavation casing (10) and the excavation casing (10) formed by forming a spiral soil discharge band (12) on the outside having a fitting passage portion (11) formed long as an inner diameter to fit the ready-made pile 40 therein, the excavation The excavation cap 20 is installed in the lower end of the casing 10 and the excavation blade 21 is attached to the lower portion of the casing 10, and is detachably fitted to the upper portion of the excavation casing 10. In the configuration consisting of a rotating cap 30 having a rotating shaft 31 is formed, the earth and sand discharge strip 12 formed around the outer circumferential surface of the excavating casing 10 from the upper to the lower portion of the outer periphery of the excavating casing 10 The first and second spiral strips 12a and 12b wound in a spiral shape are kept in one piece while maintaining a constant interval therebetween, and each predetermined interval is set around the outer periphery of the lowermost end of the excavating casing 10. Excavation bits 13 at an oblique angle as an angle Ready-made pile near ipyong as set hayeoseo casing characterized in that the auger. 제 1 항에 있어서, 상기 굴착캡(20)은 그 외주면의 대향되는 양측에, 상기 굴착케이싱(10) 하단부에 수직으로 절개 형성된 한쌍의 삽입부(14)들과 대응하는 결합편(21)을 돌출 형성하고, 상기 굴착캡(20)의 결합편(21)을 상기 굴착케이싱(10)의 삽입부(14)에 끼워져서 굴착케이싱(10) 상부에 굴착캡(20)을 착탈가능하게 조립됨을 특징으로 하는 기성말뚝근입용 케이싱오거.According to claim 1, wherein the excavation cap 20 is coupled to the opposite side of the outer peripheral surface, a pair of inserts (14) corresponding to the pair of inserts 14 formed in the vertical cut in the lower end of the excavation casing (10) Protruding form, the coupling piece 21 of the excavation cap 20 is fitted to the insertion portion 14 of the excavation casing 10 to be detachably assembled to the excavation cap 20 on the excavation casing 10 Casing Auger for ready-made pile roots characterized in that. 제 1 항에 있어서, 상기 회동캡(30)의 끼움홈(32)들은 각각 T형으로 형성하고, 그 끼움홈(32)들의 절개 자유단의 외측을 고정편(33)으로 연결하여서 됨을 특징으로 하는 기성말뚝근입용 케이싱오거.According to claim 1, wherein the fitting grooves 32 of the pivoting cap 30 are each formed in a T-shape, characterized in that by connecting the outside of the incision free end of the fitting grooves 32 to the fixing piece 33. Ready-made pile root casing auger. 해당 작업위치의 지중에 케이싱오거(10)를 굴진시키면서 굴착작업을 수행하여서 굴착공(50)을 천공하고, 천공된 굴착공(50) 내에 위치한 케이싱오거(10) 상부를 개방하여 그 케이싱오거(10) 내부에 기성말뚝(40)을 근입하여, 케이싱오거(10)와 근입된 기성말뚝(40) 사이에 시멘트페이스트(80)을 주입하여서 충진하고, 주입된 시멘트페이스트(80)가 경화되기 이전에 굴착공(50)으로부터 케이싱오거(10)를 인발시켜서 굴착공(50)내에서 경화된 시멘트페이스트(80)로서 기성말뚝(40)을 매립시키는 공정을 순차적으로 수행하여서 됨을 특징으로 하는 케이싱오거를 이용한 기성말뚝의 시공방법.Drilling the excavation hole 50 by drilling the casing auger 10 in the ground of the work position, and open the upper casing auger 10 located in the drilled excavation hole 50 to open the casing auger ( 10) by inserting the ready-made pile 40 inside, filling by filling the cement paste 80 between the casing auger 10 and the ready-made pile 40, before the injected cement paste 80 is hardened Casing auger characterized in that the step of drawing the casing auger (10) from the excavation hole 50 to bury the ready-made pile 40 as the cement paste 80 cured in the excavation hole (50) in sequence Construction method of ready-made pile using
KR1019950012143A 1995-05-16 1995-05-16 Pile driving casing auger machine and foundation pile working method KR0148062B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019950012143A KR0148062B1 (en) 1995-05-16 1995-05-16 Pile driving casing auger machine and foundation pile working method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019950012143A KR0148062B1 (en) 1995-05-16 1995-05-16 Pile driving casing auger machine and foundation pile working method

Publications (2)

Publication Number Publication Date
KR960041555A KR960041555A (en) 1996-12-19
KR0148062B1 true KR0148062B1 (en) 1998-09-15

Family

ID=19414625

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019950012143A KR0148062B1 (en) 1995-05-16 1995-05-16 Pile driving casing auger machine and foundation pile working method

Country Status (1)

Country Link
KR (1) KR0148062B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100491428B1 (en) * 2002-05-21 2005-05-25 (주)한맥기술 Reinforced in situ concrete pier on slope

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100687632B1 (en) * 2006-07-21 2007-02-27 주식회사 도화종합기술공사 Confined aquifer test method using double casing
KR100928083B1 (en) * 2007-05-10 2009-11-23 강상욱 Hollow steel pipe for rotation apparatus
KR102168528B1 (en) * 2020-06-16 2020-10-21 도원에프앤지(주) Underground continuous wall underpinning device capable of drawing casing and its method
KR102505449B1 (en) * 2022-07-28 2023-03-03 박태희 Casing for retaining wall construction and method for retaining wall construction using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100491428B1 (en) * 2002-05-21 2005-05-25 (주)한맥기술 Reinforced in situ concrete pier on slope

Also Published As

Publication number Publication date
KR960041555A (en) 1996-12-19

Similar Documents

Publication Publication Date Title
KR100820642B1 (en) Anchor-nail device for slope-reinforcement-construction and slope stabilization method
KR101243928B1 (en) Pile construction method using two excavating equipments and non welding type linked casing
JP3468724B2 (en) Method and device for placing concrete pile and enlarged head
JP3828731B2 (en) Construction method of structural column and Yatco and steel pipe pile used for this
JP4849580B1 (en) Non-debris crushed stone pile forming tool
KR0148062B1 (en) Pile driving casing auger machine and foundation pile working method
KR200384053Y1 (en) Casing structure of drilling equipment
KR102669178B1 (en) Connection apparatus of steel pipe to ring bit, reinforcement apparatus of direct boring and it's installation method
JP2874561B2 (en) Fore piling method with stiffening of the leading leg using a shaft
CN112982400A (en) Pile casing follow-up type drilling bored concrete pile drilling tool
EP1041240A2 (en) Auger drill
KR102464394B1 (en) Driving rod for forming reinforced part of piles
JP3909510B2 (en) Synthetic pile construction method
JP2001090067A (en) Rock bolt and rock-bolt execution method
KR101360614B1 (en) Front edge expanded bulb having internal excavation method used high strength steel pile
JPH07145616A (en) Cast-in-place concrete piling method
KR102171787B1 (en) Soil retaining wall using phc pile
KR20190137293A (en) Construction method for rotational penetration pile
JPS5827366B2 (en) Head reinforcement pile construction equipment
KR100932952B1 (en) Piles that have variable end
JP3851581B2 (en) Ground strength reinforcement structure of the ground
KR0134073B1 (en) Earth auger apparatus and concrete pile making method in the underground
KR20140008974A (en) Pile with non-closed channel shape of plural non-flat in the end of pile and method of construction of pile by using the same
JPH06287943A (en) Foot protection method for tip of foundation pile and cylindrical foundation pile
KR0176306B1 (en) Piling method using casing

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20070510

Year of fee payment: 10

LAPS Lapse due to unpaid annual fee