JPS644005B2 - - Google Patents

Info

Publication number
JPS644005B2
JPS644005B2 JP7079481A JP7079481A JPS644005B2 JP S644005 B2 JPS644005 B2 JP S644005B2 JP 7079481 A JP7079481 A JP 7079481A JP 7079481 A JP7079481 A JP 7079481A JP S644005 B2 JPS644005 B2 JP S644005B2
Authority
JP
Japan
Prior art keywords
reinforcing bar
joint
bars
reinforcing bars
underground wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP7079481A
Other languages
Japanese (ja)
Other versions
JPS57187418A (en
Inventor
Juichi Takeda
Kenichi Irisawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP7079481A priority Critical patent/JPS57187418A/en
Publication of JPS57187418A publication Critical patent/JPS57187418A/en
Publication of JPS644005B2 publication Critical patent/JPS644005B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 この発明は、地中深く掘削した溝内に鉄筋篭を
挿入した後コンクリートを打設すぬ連続地中壁の
施工において、その鉛直継手部にその剛性および
靭性に寄与するせん断補強筋を配置する方法に関
するものである。
[Detailed Description of the Invention] This invention contributes to the rigidity and toughness of vertical joints in the construction of continuous underground walls without pouring concrete after inserting reinforcing bar cages into trenches excavated deep underground. The present invention relates to a method for arranging shear reinforcing bars.

地中壁の継手部を剛接合とするため、通常、先
行地中壁部のコンクリートを打設した後、その端
部の鉛直継手部の函体を貫通してその内部に突出
した継手部横鉄筋(継手主筋)に後行地中壁鉄筋
篭の継手主筋を重ねて継手部コンクリートを打設
して一体化する。その際鉄筋篭は垂直に吊下ろさ
れる(第5図白ヌキ矢印参照)から、先行壁およ
び後行壁の継手主筋は互に平面上ずらせて重ね継
手とする。このため、従来は地中壁に直交する方
向の横鉄筋すなわちせん断補強筋は、継手主筋の
うち内寄りのもの(第3図の場合は2′a)に取
付けられた(図示せず)ので、外寄りの主筋(第
3図の2a)まで達しなかつた。このため、その
機能を十分発揮しないだけでなく鉛直継手部の強
度・変形能が劣るという欠点があつた。
In order to make the joint of the underground wall a rigid joint, after concrete is poured for the preceding underground wall, the side of the joint that penetrates the box of the vertical joint at the end and protrudes into the inside of the concrete is usually installed. Overlay the reinforcing bars (joint main bars) with the joint main bars of the trailing underground wall reinforcing bar basket, and pour concrete at the joint to integrate them. At this time, since the reinforcing bar cage is suspended vertically (see the open arrow in FIG. 5), the joint main bars of the leading wall and the trailing wall are shifted from each other on the plane to form a lap joint. For this reason, in the past, transverse reinforcing bars or shear reinforcing bars in the direction perpendicular to the underground wall were attached to the inner side of the joint main bars (2'a in the case of Figure 3) (not shown). , it did not reach the outer main reinforcement (2a in Figure 3). For this reason, it not only does not perform its function sufficiently, but also has the disadvantage that the strength and deformability of the vertical joint are inferior.

本発明は、上記欠点を解決するため、継手部の
外寄に配置される継手主筋まで及ぶせん断補強筋
を取付ける方法に関するものである。
In order to solve the above-mentioned drawbacks, the present invention relates to a method for attaching shear reinforcing bars that extend to the joint main bars located on the outer side of the joint.

第1図ないし第4図は、本発明の施工順序を示
す継手部を主とした平面図である。まず、掘削溝
1内に鉄筋篭2を挿入した後、コンクリート3を
打設するが、鉄筋篭端部には継手主筋2aを覆う
函体4が取付けられているため、この内部には、
この時点ではコンクリートは打設されない。こう
した点で従来と変わりないのであるが、本発明に
おいては、特に函体内に突出している継手主筋の
根元部に梯子の形状をした鉄筋枠5を遊嵌してお
くのである。この鉄筋枠は、第5図に示すよう
に、後に継手部の縦筋5aとなる2本の鉄筋を平
行に配置し、後に継手部のせん断補強筋5bとな
る多数の鉄筋を連結して梯子状の枠に形成したも
のである。これら縦筋およびせん断補強筋の長
さ、径および間隔は構造設計上決定される。
1 to 4 are plan views mainly showing the joint portion, showing the construction order of the present invention. First, after inserting the reinforcing bar cage 2 into the excavated groove 1, concrete 3 is poured.Since the box 4 that covers the joint main reinforcement 2a is attached to the end of the reinforcing bar cage, there are
No concrete will be placed at this point. Although this is no different from the conventional method, in the present invention, a ladder-shaped reinforcing bar frame 5 is loosely fitted, particularly at the root of the joint main bar protruding into the case. As shown in Fig. 5, this reinforcing bar frame is constructed by arranging two reinforcing bars in parallel that will later become the vertical reinforcements 5a of the joint, and connecting a large number of reinforcing bars that will later become the shear reinforcing bars 5b of the joint. It is formed into a shaped frame. The length, diameter, and spacing of these longitudinal bars and shear reinforcing bars are determined based on structural design.

つぎに後行地中壁部を掘削した後、函体4の
引抜板4aを抜取り函体内と後行壁掘削溝1′と
を連通、一体化し(第2図)、函体内の先行壁継
手主筋2aにガイド9をはさんで平行配置される
べき継手主筋2′aを有する後行壁鉄筋篭2′を挿
入する(第3図)。
Next, after excavating the trailing underground wall, the pull-out plate 4a of the box 4 is extracted, and the box and the trailing wall excavated groove 1' are communicated and integrated (Fig. 2), and the leading wall joint inside the box is connected. A trailing wall reinforcing bar cage 2' having a joint main reinforcement 2'a to be arranged parallel to the main reinforcement 2a with a guide 9 in between is inserted (FIG. 3).

つぎにガイド9を抜き取り、前記鉄筋枠を所定
位置まで移動させる(第4図)。
Next, the guide 9 is removed and the reinforcing bar frame is moved to a predetermined position (FIG. 4).

この移動は水中ジヤツキ(図示せず)によつて
も良いが、第6図に示すように鉄筋枠に緊結した
ワイヤー7を横に引き継手主筋に取付けた滑車6
に巻き方向変換して地上に延長し、これを牽引す
る方法が好ましい。なお、滑車の代りにスリーブ
6′を遊嵌した鉄筋を最下部継手主筋先端部に取
付けたものを用いても良い(第5図)。
This movement may be carried out by an underwater jack (not shown), but as shown in Fig. 6, a pulley 6 is attached to the main reinforcing bar next to the wire 7 tied to the reinforcing bar frame.
It is preferable to change the winding direction, extend it to the ground, and tow it. Note that instead of the pulley, a reinforcing bar with a sleeve 6' loosely fitted therein may be used, which is attached to the tip of the main bar of the lowermost joint (FIG. 5).

また、隣接する各鉄筋枠を一定長のワイヤー等
の可撓線材8で相互に緊結すれば、最も外側(後
行壁側)の一つの鉄筋枠を移動するだけで全て
の鉄筋枠を所定位置に配置できる。
In addition, if each adjacent reinforcing bar frame is tied together with a flexible wire material 8 such as a wire of a certain length, all the reinforcing bar frames can be moved to the predetermined position by simply moving one of the outermost reinforcing bars (tracing wall side). It can be placed in

なお、本実施例では、継手主筋を重ね継手にし
たとき、先行地中壁の鉄筋篭2の継手主筋2aが
外寄になるよう設計されたのでこれに梯子状鉄筋
枠5をあらかじめ遊嵌したが、逆の場合には、後
行地中壁の継手主筋2′aに遊嵌する。
In addition, in this example, when the joint main reinforcement is made into a lap joint, the joint main reinforcement 2a of the reinforcing bar cage 2 of the preceding underground wall is designed to be on the outside, so the ladder-shaped reinforcing bar frame 5 is loosely fitted in advance to this. However, in the opposite case, it loosely fits into the joint main reinforcement 2'a of the trailing underground wall.

さて、第4図に示すように鉄筋枠を所定の位置
に移動させた後、継手部函体内および後行壁部分
にコンクリートを打設して先行壁と一体化させ
(図示せず)一行程を終えるのである。
Now, as shown in Figure 4, after moving the reinforcing bar frame to a predetermined position, concrete is poured into the joint part box and the trailing wall part to integrate it with the leading wall (not shown). This is the end of the process.

その結果、外寄継手主筋に達するせん断補強筋
5bが組み込まれ、継手部の構造的性能が向上
し、特に破壊時の外寄継手主筋の剥離の防止によ
り変形能力が良好となる。
As a result, the shear reinforcing bars 5b reaching the outer joint main reinforcing bars are incorporated, improving the structural performance of the joint, and in particular, improving the deformability by preventing the outer joint main reinforcing bars from peeling off at the time of fracture.

なお、本実施例では、継手部と後行壁部のコン
クリートが一体打ちである場合を示したが、継手
部独自の鉄筋篭(図示せず)を使用して、後打ち
する場合にも適用できる。
In addition, although this example shows the case where the concrete of the joint part and the trailing wall part is cast as one piece, this method can also be applied to the case where the joint part's own reinforcing bar basket (not shown) is used and the concrete is cast afterwards. can.

以上、本発明は、鉄筋枠を継手主筋に遊嵌して
おき、後に移動するだけで構造上有利なせん断補
強筋の設置を容易とするのみならず、鉄筋枠を構
成する部材は、すべてせん断補強筋または縦筋と
して、構造部材として使用されるから資材の無駄
がない。
As described above, the present invention not only facilitates the installation of structurally advantageous shear reinforcing bars by simply loosely fitting the reinforcing bar frame into the joint main reinforcement and moving it later, but also makes it possible to easily install shear reinforcing bars that are structurally advantageous. There is no wastage of materials because it is used as a reinforcing bar or longitudinal bar and as a structural member.

また、隣接する鉄筋枠相互を一定長の可撓線材
で随所に緊結しておけば、外側の一つの鉄筋枠を
移動させるだけですべての鉄筋枠を所定位置に配
置することができ、作業が合理化される。
In addition, if adjacent reinforcing bars are tied together with flexible wires of a certain length, all reinforcing bars can be placed in the specified position by simply moving one outer reinforcing bar frame, making the work easier. Streamlined.

さらに、鉄筋枠の移動に際し、ロープを取付
け、滑車等により方向変換して地上で牽引する方
法によれば、油圧ジヤツキを使用するものに比べ
軽微で経済的である。
Furthermore, when moving the reinforcing bar frame, a method of attaching a rope, changing direction using a pulley, etc., and towing it on the ground is lighter and more economical than using a hydraulic jack.

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第4図は本発明の実施例を施工順
に示す地中壁平面断面図である。第5図および第
6図は、第2図および第4図の施工段階をそれぞ
れ示す切欠き斜視図である。なお点線は公知部分
であることを示す。 1,1′:掘削溝、2,2′:鉄筋篭、2a,
2′a:継手部横鉄筋(継手主筋)、3,3′:コ
ンクリート、4:(継手部の)函体、4a:引抜
板、5:(梯子状の)鉄筋枠、5a:(鉄筋枠の)
縦鉄筋、5b:せん断補強筋、6:滑車、6′:
スリーブ、7:ロープ、8:可撓線材、9:ガイ
ド。
1 to 4 are plan sectional views of underground walls showing embodiments of the present invention in the order of construction. 5 and 6 are cutaway perspective views showing the construction stages of FIGS. 2 and 4, respectively. Note that dotted lines indicate known parts. 1, 1': Excavation groove, 2, 2': Rebar cage, 2a,
2'a: Joint horizontal reinforcing bar (joint main reinforcement), 3, 3': Concrete, 4: Case (of the joint), 4a: Drawn plate, 5: (ladder-shaped) reinforcing bar frame, 5a: (reinforcing bar frame) of)
Vertical reinforcement, 5b: Shear reinforcement, 6: Pulley, 6':
Sleeve, 7: rope, 8: flexible wire, 9: guide.

Claims (1)

【特許請求の範囲】 1 先行地中壁および後行地中壁の鉄筋篭
2,2′の端部の継手部横鉄筋2a,2′aを互い
に重ね継手とする鉛直継手部Jの施工において、
前記継手部横鉄筋のうち重ね継手としたときに外
寄に位置する継手部横鉄筋に、あらかじめ縦筋と
せん断補強筋とからなる梯子形状の鉄筋枠5を遊
嵌しておき、前記鉄筋篭を所定位置に設置した
後、前記鉄筋枠を所定位置に移動させることを特
徴とする地中壁鉛直継手部のせん断補強筋の配筋
方法。 2 複数個の梯子状鉄筋枠5がそれぞれ相対応す
る部分において、一定長の可撓線材8で相互に緊
結されたものである特許請求の範囲第1項に記載
の地中壁鉛直継手部せん断補強筋の配筋方法。 3 鉄筋篭2の継手部横鉄筋2aの根元部に遊嵌
された梯子状の鉄筋枠5に一端を緊結されたロー
プ7を横に引き、前記継手部横鉄筋の先端に取付
けた滑車6またはスリーブ6′により方向を変換
して地上に延長し、これを牽引することを特徴と
する地中壁鉛直継手部梯子状鉄筋枠の移動方法。
[Scope of Claims] 1. In the construction of a vertical joint J in which the joint horizontal reinforcing bars 2a, 2'a at the ends of the reinforcing bar baskets 2, 2' of the leading underground wall and the trailing underground wall are overlapped with each other. ,
A ladder-shaped reinforcing bar frame 5 made up of longitudinal bars and shear reinforcing bars is loosely fitted in advance to the horizontal reinforcing bars of the joint part located on the outer side when a lap joint is made of the horizontal reinforcing bars of the joint part, and 1. A method for arranging shear reinforcing bars in a vertical joint of an underground wall, the method comprising: installing a reinforcing bar in a predetermined position, and then moving the reinforcing bar frame to a predetermined position. 2. The underground wall vertical joint section shear according to claim 1, wherein a plurality of ladder-like reinforcing bars 5 are connected to each other by a fixed length of flexible wire 8 at corresponding portions. Reinforcement reinforcement method. 3. A rope 7, one end of which is tied to a ladder-like reinforcing bar frame 5 that is loosely fitted to the base of the horizontal reinforcing bar 2a at the joint portion of the reinforcing bar cage 2, is pulled sideways, and a pulley 6 or A method for moving a ladder-like reinforcing bar frame at a vertical joint of an underground wall, which comprises changing the direction using a sleeve 6', extending it above ground, and towing it.
JP7079481A 1981-05-13 1981-05-13 Arrangement of shearing reinforcing iron bars for vertical coupler of underground wall Granted JPS57187418A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7079481A JPS57187418A (en) 1981-05-13 1981-05-13 Arrangement of shearing reinforcing iron bars for vertical coupler of underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7079481A JPS57187418A (en) 1981-05-13 1981-05-13 Arrangement of shearing reinforcing iron bars for vertical coupler of underground wall

Publications (2)

Publication Number Publication Date
JPS57187418A JPS57187418A (en) 1982-11-18
JPS644005B2 true JPS644005B2 (en) 1989-01-24

Family

ID=13441795

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7079481A Granted JPS57187418A (en) 1981-05-13 1981-05-13 Arrangement of shearing reinforcing iron bars for vertical coupler of underground wall

Country Status (1)

Country Link
JP (1) JPS57187418A (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59145825A (en) * 1983-02-10 1984-08-21 Ohbayashigumi Ltd Reinforcement of vertical joint of underground continuous wall
DE3401834A1 (en) * 1984-01-20 1985-07-25 Basf Ag, 6700 Ludwigshafen FLAME RETARDED THERMOPLASTIC MOLDING
US4763987A (en) * 1985-11-20 1988-08-16 Minolta Camera Kabushiki Kaisha Lens barrel
JPS6355213A (en) * 1986-03-31 1988-03-09 Tekken Kensetsu Co Ltd Coupling work in underground continuous wall

Also Published As

Publication number Publication date
JPS57187418A (en) 1982-11-18

Similar Documents

Publication Publication Date Title
WO1996018001A1 (en) Pile head treating tool for cast-in-place pile, pile head treating method, and cast-in-place piling method
JPS644005B2 (en)
JPS641610B2 (en)
JP6353775B2 (en) Construction method of leading element of underground continuous wall, construction method of underground continuous wall, and construction device of leading element of underground continuous wall
JPH0237480B2 (en)
JP2979115B2 (en) Construction method of cast-in-place concrete pile
JP2618850B2 (en) Construction method of high strength pile
JP2694715B2 (en) Joint structure of underground wall
JPH0468407B2 (en)
JP4069059B2 (en) Method for reinforcing concrete power pole and reinforcing structure for concrete power pole
JP2561967B2 (en) Reinforcing bar cage for underground wall construction with variable cross section
JPH11324565A (en) Construction method of shaft
JPH07268867A (en) Cast-in-place concrete pile and method for fabricating the same
JPH0343520A (en) Method of setting bottom die frame in reverse winding process
JPH10220162A (en) Immersion body having projecting body on outer peripheral surface and division ring which constitutes the sam immersion body
JP2605941B2 (en) Construction method for underground structures
US1839304A (en) Concrete pile
JP6401964B2 (en) System and method for installing a built-in member directly under a ground obstacle
JP3072248B2 (en) How to install heater tube
JP2000130070A (en) Construction method for vertical shaft for shield
JPS5919232B2 (en) Construction method of tower-like structure using unbonded PC steel wire
JPH07107268B2 (en) Joint structure of underground continuous wall
JPS6132450B2 (en)
JP6354277B2 (en) Ground improvement column
JPS61257529A (en) Underground continuous wall construction work