JPS6331634B2 - - Google Patents

Info

Publication number
JPS6331634B2
JPS6331634B2 JP56160416A JP16041681A JPS6331634B2 JP S6331634 B2 JPS6331634 B2 JP S6331634B2 JP 56160416 A JP56160416 A JP 56160416A JP 16041681 A JP16041681 A JP 16041681A JP S6331634 B2 JPS6331634 B2 JP S6331634B2
Authority
JP
Japan
Prior art keywords
construction
outer tank
side wall
opening
tank side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP56160416A
Other languages
Japanese (ja)
Other versions
JPS5862253A (en
Inventor
Tsutomu Tomita
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kawasaki Heavy Industries Ltd
Original Assignee
Kawasaki Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Heavy Industries Ltd filed Critical Kawasaki Heavy Industries Ltd
Priority to JP16041681A priority Critical patent/JPS5862253A/en
Publication of JPS5862253A publication Critical patent/JPS5862253A/en
Publication of JPS6331634B2 publication Critical patent/JPS6331634B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Description

【発明の詳細な説明】 本発明は、PC外槽、詳しくは、プレストレス
トコンクリート(PC)で形成した外槽を有する
二重殻タンクの施工法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing a double shell tank having a PC outer tank, and more particularly, an outer tank formed of prestressed concrete (PC).

従来この種PC外槽を有する二重殻タンクの施
工法としては、第3〜5図に示すようなもので代
表される。即ち、第3図a,b,cで示す施工法
について説明すると、基礎1上に、PC外槽側壁
2を建設し、緊張工事をも行う。その後上記PC
外槽側壁2内で、底部保冷3の工事、内槽4の組
立溶接工事、検査を行う。この際、底部保冷工
事、内槽溶接工事、検査のための機材の搬入、搬
出及び作業人員の出入は、全て上記PC外槽側壁
の上部より行うことになる。
Conventional construction methods for double-shelled tanks with a PC outer tank of this type include those shown in Figures 3 to 5. That is, to explain the construction method shown in FIGS. 3a, b, and c, the PC outer tank side wall 2 is constructed on the foundation 1, and tension work is also performed. Then the above PC
Inside the outer tank side wall 2, construction of the bottom cold insulation 3, assembly and welding of the inner tank 4, and inspection are performed. At this time, the bottom cold insulation work, the inner tank welding work, the loading and unloading of equipment for inspection, and the entry and exit of workers will all be performed from the upper part of the side wall of the PC outer tank.

このような手段によると、(イ)、PC外槽側壁の
土木建設工事後、内槽組立溶接工事のメタル工事
を行うため、異質工事作業の切換えに伴う人員配
置の効率が悪く、工期が長くなる欠点がある。
(ロ)、内槽、底部保冷工事、検査のための機材の搬
出入を、全てPC外槽側壁越しに行われるため、
きわめて不便で、工期に影響を及ぼすばかりでな
く、作業者に対する危険性が伴う。
According to this method, (a) the metal work for assembling and welding the inner tank is performed after the civil engineering work for the side walls of the PC outer tank, resulting in poor staffing efficiency due to the changeover of different types of construction work, and a long construction period. There is a drawback.
(b) Because the inner tank, bottom cold insulation work, and equipment for inspection are all carried out through the side wall of the PC outer tank,
This is extremely inconvenient and not only affects the construction period but also poses a danger to workers.

次に第4図a,b,cで示す施工法について説
明すると、基礎1上に、先ず内槽底部保冷3工事
を行い、この上に内槽4を組立て溶接したのち、
これの外側にPC外槽側壁2の工事を行うとゝも
にこれの緊張工事をも行い、外槽屋根を完成さ
せ、所定検査のゝち、側部及び屋根保冷工事を行
う。
Next, to explain the construction method shown in Fig. 4 a, b, and c, first, the inner tank bottom cold insulation 3 construction is performed on the foundation 1, and after assembling and welding the inner tank 4 on top of this,
Work is carried out on the PC outer tank side wall 2 on the outside of this, and tension work is also carried out on this, the outer tank roof is completed, and as part of the prescribed inspection, cold insulation work on the sides and roof is performed.

このような手段によると、(イ)、内槽建設である
メタル工事を行つたのち、土木工事であるPC外
槽側壁の建設工事を行うために、異質工事作業の
切換えに伴う人員配置の効率が悪く、工期に長時
日を要する欠点がある。(ロ)、内槽工事終了後PC
土木工事を行う結果、コンクリート打設用型枠の
搬入、据付、搬出を始め、かなりの土木工事を
内、外槽の側壁間で行うことになり、必然的に、
内、外槽間の空間を広くせざるを得ない。
According to such a method, (a) the metal work for the inner tank construction is carried out, and then the civil engineering work for the PC outer tank side wall construction work is carried out, which reduces the efficiency of personnel allocation due to switching between different types of construction work. The disadvantage is that the construction period is long and the construction period is long. (b) PC after completion of inner tank construction
As a result of the civil engineering work, a considerable amount of civil engineering work was carried out between the inner and outer tank side walls, including the transport, installation, and removal of formwork for concrete pouring.
It is necessary to widen the space between the inner and outer tanks.

このことは、通常タンクで、1m前後のところ
を、1.5〜2.0mにする必要が生じ、保冷空間が必
要以上に大きく、保冷コストが増大するばかりで
なく、PC外槽の直径が大きくなり、土木コスト
が大巾に増大する。更に加えて、内、外槽間の保
冷空間体積が大きくなり、この空間内に充填する
窒素ガスの量が多く、また保冷空間内ガス圧力調
整用のブリージングタンクの容量が必要以上に大
きくなるなどきわめて不経済である。(ハ)、内槽工
事終了後、PC土木工事を行うものであるため、
外槽土木工事により内槽外面を損傷することがあ
り、好ましくない。
This means that the tank needs to be made 1.5 to 2.0 m from around 1 m in a normal tank, and the cold storage space is larger than necessary, which not only increases the cooling cost but also increases the diameter of the PC outer tank. Civil engineering costs will increase dramatically. In addition, the volume of the cold storage space between the inner and outer tanks becomes large, the amount of nitrogen gas filled in this space becomes large, and the capacity of the breathing tank for adjusting the gas pressure inside the cold storage space becomes larger than necessary. It is extremely uneconomical. (c) As the PC civil engineering work will be carried out after the inner tank construction is completed,
Civil engineering work on the outer tank may damage the outer surface of the inner tank, which is undesirable.

次に第5図a,b,c,dで示す施工法につい
て説明すると、基礎1上で、屋根5,6の組立溶
接を先行させ、その後、内槽側壁4a、PC外槽
側壁2を平行して組立て、両側壁2、4aが完成
後屋根5,6を所定位置に持ち上げて完成せし
め、所定の検査を行つてから、側部及び屋根部保
冷工事を行う。
Next, to explain the construction method shown in Fig. 5 a, b, c, and d, the roofs 5 and 6 are first assembled and welded on the foundation 1, and then the inner tank side wall 4a and the PC outer tank side wall 2 are welded in parallel. After the both side walls 2 and 4a are completed, the roofs 5 and 6 are lifted to a predetermined position and completed, and after predetermined inspections are performed, the side and roof insulation work is carried out.

このような手段によると、(イ)、屋根組立後内槽
側壁、PC側壁を平行して建設するため、内、外
槽の工事が錯綜し、工期が長くなる欠点がある。
(ロ)、安全管理上に危惧がある。即ち、工事の錯綜
に伴い、内槽の建設に必要な機材の搬入、搬出が
外槽壁を越えて行われるためである。(ハ)、両側壁
工事を適宜組合せて工事を進めるため、何れかの
工事を手空きが生じ、経済的でない。(ニ)、概し
て、内槽壁の建設が若干PC壁より先行する可能
性が高く、第3図の先行例同様に、内、外槽側壁
間隔を必要以上に大きくとる結果となり、上記同
様の欠点が伴う。(ホ)、土木工事のみについて考え
ると、基礎工事とPC外槽工事の間に長期間の屋
根工事(大型タンクで3〜4ケ月)が入ることに
なり、その間、土木工事が途切れる。従つて機材
の運用、人員の配置面で効率が悪い。
According to such a method, (a) the inner tank side wall and the PC side wall are constructed in parallel after the roof is assembled, so the construction of the inner and outer tanks becomes complicated and the construction period becomes longer.
(b) There are concerns regarding safety management. In other words, due to the complexity of the construction work, equipment necessary for constructing the inner tank must be brought in and taken out over the outer tank wall. (c) Since the construction work is carried out by appropriately combining both side wall works, it is not economical as there will be a shortage of hands for either of the works. (d) Generally speaking, there is a high possibility that the construction of the inner tank wall will take place slightly earlier than the PC wall, and as in the previous example shown in Figure 3, the gap between the inner and outer tank side walls will be larger than necessary, resulting in the same problem as above. It comes with drawbacks. (e) If we consider only the civil engineering work, there will be a long period of roof work (3 to 4 months for large tanks) between the foundation work and the PC outer tank work, and civil engineering work will be interrupted during that time. Therefore, it is inefficient in terms of equipment operation and personnel allocation.

本発明は、上述したような従来技術の問題点を
解消すべくなされたもので、きわめて合理的な施
工手段によつて従来の欠点を除去せしめ、PC外
槽の土木工事と両槽の屋根のメタル工事および底
部保冷、内槽底板、内槽側板の工事を伴行して行
つて完成させ、内外槽側壁工事の錯綜をなくし、
工期の短縮及び経済的効果の大きい施工法を提供
せんとするものである。
The present invention has been made to solve the problems of the prior art as described above, and eliminates the drawbacks of the conventional technology by using extremely rational construction methods. The metal work, bottom cold insulation, inner tank bottom plate, and inner tank side plate work were carried out and completed, eliminating the complication of work on the inner and outer tank side walls.
The aim is to provide a construction method that shortens the construction period and has a large economic effect.

第1図a,b,c,dについて本発明施工法の
実施例を説明すると次の通りである。bに示すよ
うに、基礎10上に外槽側壁11aを緊張するこ
となく組立てする過程で、これの下部に、第2図
に示すような工事用開口12を形成する。
Examples of the construction method of the present invention will be explained with reference to FIGS. 1a, b, c, and d as follows. As shown in FIG. 2B, in the process of assembling the outer tank side wall 11a on the foundation 10 without tension, a construction opening 12 as shown in FIG. 2 is formed in the lower part of the outer tank side wall 11a.

工事用開口12の両側のコンクリートからは、
周方向の緊張用のPC線17およびシース18を
一部突出させて、開口部閉鎖時のつなぎ込みに備
えておく。PC線17のつなぎ足しは困難である
ので、PC線17は予め所定の長さに設定して巻
いておくか、あるいは閉鎖時に所定長をシース1
8に一気に挿入すればよい。また、鉛直方向の緊
急のためのPC棒19およびシース20も一部を
開口12の上縁より突出させ、開口12の下部に
はシース20のみ埋めこんでおく。PC棒19は
カツプリングまたは溶接でつなぎ込む事は可能で
あり、後日の開口部12の閉鎖は支障なく行なえ
る。この工事用開口12より、屋根13,14の
建設に必要な機材を搬入し、基礎10上におい
て、外槽側壁11aの建設を継続しつゝ屋根1
3,14の地組立を行なう。
From the concrete on both sides of the construction opening 12,
The PC wire 17 and sheath 18 for circumferential tension are partially protruded in preparation for connection when the opening is closed. Since it is difficult to add the PC wire 17, it is necessary to set the PC wire 17 to a predetermined length and wind it, or to wrap the predetermined length into the sheath 1 when closing.
8 all at once. Further, a part of the PC rod 19 and the sheath 20 for emergencies in the vertical direction are made to protrude from the upper edge of the opening 12, and only the sheath 20 is buried in the lower part of the opening 12. The PC rods 19 can be connected by coupling or welding, and the opening 12 can be closed at a later date without any problem. The equipment necessary for constructing the roofs 13 and 14 is brought in through this opening 12 for construction, and while continuing the construction of the outer tank side wall 11a on the foundation 10, the roof 1
Perform the ground assembly of 3 and 14.

尚、PCコンクリート外槽の内面に、鋼製など
のライナーを張設する場合には、当然のことなが
ら底部ライナーの施工は先行させる必要があり、
また、第1図cに記述の如く、底部保冷の一部で
あるアニユラー部保冷21や、内槽アニユラープ
レート22および内槽側板の下段の一部施工を、
屋根13,14の地組立に先行させてもよい。
In addition, if a liner made of steel or the like is to be installed on the inner surface of the PC concrete outer tank, it is of course necessary to install the bottom liner first.
In addition, as shown in Fig. 1c, the annular part cold insulation 21, which is a part of the bottom cold insulation, the inner tank annular plate 22, and part of the lower part of the inner tank side plate were constructed.
This may be done prior to the erection of the roofs 13 and 14.

屋根13,14の完成後底部保冷および内槽底
板の組立を行なうが、施工によつては所要の機材
を予め搬入しておき、後日これらの組立を行うこ
ともできる。内槽側壁15aの建設に使用できる
機材を残し、他は上記工事用開口12から外槽外
部に搬出し、代りに、内槽側壁15aの建設に必
要な機材を工事用開口から搬入する。
After the roofs 13 and 14 are completed, the bottom cold storage and the inner tank bottom plate are assembled, but depending on the construction, the necessary equipment may be brought in in advance and assembled at a later date. The equipment that can be used for constructing the inner tank side wall 15a is left behind, the others are carried out of the outer tank through the construction opening 12, and instead, the equipment necessary for constructing the inner tank side wall 15a is brought in through the construction opening.

次いでcのように内槽側壁15aの建設を常法
の施工手順によつて行い、これを完成させる。使
用済の機材は、内槽側壁15aに設けた工事用開
口16、外槽側壁11aの工事用開口12から外
部に搬出し、次いで屋根13,14を持ち上げ、
一方の屋根14は内槽側壁15a上端に、他方の
屋根13は外槽側壁11a上端にとり合わせる。
Next, as shown in c, the inner tank side wall 15a is constructed using a conventional construction procedure, and is completed. The used equipment is carried outside through the construction opening 16 provided in the inner tank side wall 15a and the construction opening 12 in the outer tank side wall 11a, and then the roofs 13 and 14 are lifted.
One roof 14 is attached to the upper end of the inner tank side wall 15a, and the other roof 13 is attached to the upper end of the outer tank side wall 11a.

そして全ての機材を上記両工事用開口12,1
6から搬出したのち、この両開口12,16をd
のように閉鎖する。内槽の開口16の閉鎖は、常
法のごとく溶接により行なう。外槽の開口の閉鎖
は前述の如く、予めコンクリートから突出して設
けたシースに新たなシースをカツプリング、溶接
などでつなぎ込み、また予め突出させておいた
PC棒に新たなPC棒をカツプリング、溶接などで
つなぎこみこれらのPC棒、PC線をシース中に挿
入し、また前後して鉄筋をつなぎ込みその後に適
宜型枠を用いてコンクリート打設することにより
行なう。内面にライニングをした外槽において
は、ライニングを完成することは勿論である。そ
の後内槽15の耐圧試験、気密試験を行い、一方
外槽側壁11aにPC線、PC棒による緊張を与え
たのち、この外槽11の気密試験を行い、屋根1
3,14および側部保冷工事を行つて全ての工事
は終る。
Then, move all the equipment to both construction openings 12 and 1.
6, open both openings 12 and 16 by d.
Close like. The opening 16 of the inner tank is closed by welding in the usual manner. As mentioned above, the opening of the outer tank was closed by connecting a new sheath with a coupling or welding to the sheath that had been made to protrude from the concrete in advance, and also by making it protrude in advance.
Connect new PC rods to the PC rods by coupling, welding, etc., insert these PC rods and PC wires into the sheath, connect reinforcing bars back and forth, and then pour concrete using appropriate formwork. This is done by In the case of an outer tank whose inner surface is lined, the lining can of course be completed. Thereafter, a pressure test and an airtightness test were conducted on the inner tank 15, while tension was applied to the outer tank side wall 11a using PC wires and PC rods, and an airtightness test was conducted on the outer tank 11.
3, 14 and side cold insulation work, all construction work is completed.

尚外槽側壁11aに対する緊張は、気密試験、
屋根、側部保冷工事が終つたあとで行つてもよ
い。また外槽側壁11aの内面に、内槽より貯蔵
液が流出した場合の二次貯液性を与えるため、ラ
イナーを張つて液密性を高めてもよく、この場合
ライナーは、コンクリート打設の型枠の代りに使
用するか、あるいは、コンクリート打設後に張設
するものである。
The tension on the outer tank side wall 11a is determined by the airtight test,
This can be done after the roof and side cold insulation work is completed. In addition, a liner may be placed on the inner surface of the outer tank side wall 11a to provide secondary storage capacity in the event that the stored liquid flows out from the inner tank to improve liquid tightness. It is used in place of formwork or is placed after concrete is poured.

このように本発明は、PC外槽壁を建設しなが
ら、基礎上で屋根の建設を行い、屋根の地組立終
了後内槽側壁の建設を行うため、従来のように、
土木、メタル工事の錯綜が殆んどなく、工事の手
空きがなく、人員配置も合理的に行われることか
ら工期を大巾に短縮させることができる。また内
槽の建設工事は、PC壁の建設に併行して行なう
が、内槽壁の建設はPC壁の建設の終了後或はPC
壁の建設を追うようにして行なわれるため、この
PC壁との間に、内槽メタル工事ができる程度の
スペースがあればよく、従来のように、必要以上
に外槽径を大きくすることがなく、従つて保冷コ
スト、PC壁コスト、ブリージングタンク容量な
どの低減を計ることができるなど優れた特長を有
するものである。
In this way, the present invention constructs the roof on the foundation while constructing the PC outer tank wall, and constructs the inner tank side walls after the roof is assembled on the ground.
There is almost no complication between civil engineering and metal work, there is no construction work left unoccupied, and personnel allocation can be done rationally, making it possible to significantly shorten the construction period. In addition, the construction of the inner tank will be carried out concurrently with the construction of the PC wall, but the construction of the inner tank wall will be carried out after the construction of the PC wall is completed or after the construction of the PC wall.
This is done in a way that follows the construction of the wall.
There only needs to be enough space between the PC wall and the inner tank metal work, and unlike conventional methods, the outer tank diameter does not need to be increased more than necessary.This reduces cold storage costs, PC wall costs, and breathing tank costs. It has excellent features such as being able to reduce capacity.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図a,b,c,dは本発明施工法の流れ
図、第2図は同上要部の斜視図、第3図a,b,
c、第4図a,b,c、第5図a,b,c,dは
夫々従来施工例の流れ図である。
Figure 1 a, b, c, d is a flowchart of the construction method of the present invention, Figure 2 is a perspective view of the main parts of the same, Figure 3 a, b,
c, FIGS. 4a, b, and c, and FIGS. 5a, b, c, and d are flowcharts of conventional construction examples, respectively.

Claims (1)

【特許請求の範囲】[Claims] 1 外槽側壁を、プレストレスコンクリート
(PC)で形成した平底円筒二重殻タンクの施工に
際し、基礎上に、外槽側壁を緊張することなく組
立てる過程で、これの下部に工事用開口を形成
し、鉛直方向緊張用のPC棒及びシースを開口部
上下のコンクリートより一部突出せしめ、また、
周方向緊張用のPC線用のシースを開口の両側の
コンクリートより突出させておき、また、コンク
リートの配筋の一部を突出させておき、該工事用
開口より内槽など組立てに必要な機材を搬入せし
め、外槽側壁内部の基礎上で、内、外槽の屋根の
地組立て建設を遂行させるとともに、これと併行
してPC外槽側壁の組立工事を継続し、内外槽屋
根の地組立終了後、底部保冷および内槽底板の施
行を適宜行い、しかるのち、内槽側壁の建設工事
を行い、これを完成させ、搬入した機材類を上記
外槽側壁の工事用開口より外部に搬出したのち、
上記工事用開口に予めコンクリートより突出して
設けておいたシースに新たなシースをつなぎ込
み、新たにつなぎ足したPC棒及び予め所定長に
設定していたPC線を挿入して、更に、前後して
鉄筋をつなぎ込み、その後適宜型枠を用いてコン
クリート打設を行うことによつて開口部を閉鎖し
完成された外槽側壁に対し、PC線、PC棒などに
て所定の緊張を与えることを特徴とするPC外槽
を有する二重殻タンクの施工法。
1. When constructing a flat-bottom cylindrical double-shell tank whose outer tank side wall is made of prestressed concrete (PC), an opening for construction was created at the bottom of the outer tank side wall in the process of assembling it on the foundation without tension. Then, the PC rod and sheath for vertical tension were partially protruded from the concrete above and below the opening, and
The sheath for the PC wire for circumferential tension is made to protrude from the concrete on both sides of the opening, and a part of the concrete reinforcement is made to protrude, and equipment necessary for assembly, such as the inner tank, is placed through the construction opening. The construction of the inner and outer tank roofs was carried out on the foundation inside the outer tank side walls, and at the same time, the assembly work of the PC outer tank side walls was continued, and the ground assembly of the inner and outer tank roofs was carried out. After completion, the bottom was kept cool and the bottom plate of the inner tank was installed as appropriate, and then the inner tank side wall construction work was completed, and the equipment brought in was carried outside through the construction opening on the outer tank side wall. after,
Connect a new sheath to the sheath that was previously provided in the construction opening protruding from the concrete, insert the newly connected PC rod and the PC wire that had been set to a predetermined length, and then move it back and forth. Connect the reinforcing bars, then close the opening by pouring concrete using appropriate formwork, and apply a specified tension to the completed outer tank side wall using PC wires, PC rods, etc. A construction method for a double shell tank with a PC outer tank characterized by:
JP16041681A 1981-10-07 1981-10-07 Execution of double shell tank having pc outer tank Granted JPS5862253A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16041681A JPS5862253A (en) 1981-10-07 1981-10-07 Execution of double shell tank having pc outer tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16041681A JPS5862253A (en) 1981-10-07 1981-10-07 Execution of double shell tank having pc outer tank

Publications (2)

Publication Number Publication Date
JPS5862253A JPS5862253A (en) 1983-04-13
JPS6331634B2 true JPS6331634B2 (en) 1988-06-24

Family

ID=15714449

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16041681A Granted JPS5862253A (en) 1981-10-07 1981-10-07 Execution of double shell tank having pc outer tank

Country Status (1)

Country Link
JP (1) JPS5862253A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010275796A (en) * 2009-05-29 2010-12-09 Ihi Corp Method for manufacturing storage tank

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59210164A (en) * 1983-05-16 1984-11-28 甲陽建設工業株式会社 Construction of double shell tank
JPS6088297A (en) * 1983-10-18 1985-05-18 Taisei Corp Storage tank for low temperature fluid
JPH0814206B2 (en) * 1988-05-27 1996-02-14 株式会社東芝 Lining tank and lining tank construction method
US7736051B2 (en) 2004-03-30 2010-06-15 Yamatake Corporation Thermoelectric device and mirror surface state detection device
JP5672787B2 (en) * 2010-06-16 2015-02-18 株式会社Ihi Construction method of cylindrical tank

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4941049A (en) * 1972-08-26 1974-04-17
JPS5214917A (en) * 1975-07-25 1977-02-04 Kawasaki Heavy Ind Ltd Constructing method of double shell tank
JPS5214914A (en) * 1975-07-25 1977-02-04 Kawasaki Heavy Ind Ltd Constructing method of double shell tank with dome roofing
JPS5221726A (en) * 1975-08-12 1977-02-18 Nippon Telegr & Teleph Corp <Ntt> Color tv system
JPS5449609A (en) * 1977-09-28 1979-04-19 Nippon Kokan Kk <Nkk> Assembling method of double-walled tank
JPS5677474A (en) * 1979-11-28 1981-06-25 Ishikawajima Harima Heavy Ind Method of constructing multiple shell tank

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4941049A (en) * 1972-08-26 1974-04-17
JPS5214917A (en) * 1975-07-25 1977-02-04 Kawasaki Heavy Ind Ltd Constructing method of double shell tank
JPS5214914A (en) * 1975-07-25 1977-02-04 Kawasaki Heavy Ind Ltd Constructing method of double shell tank with dome roofing
JPS5221726A (en) * 1975-08-12 1977-02-18 Nippon Telegr & Teleph Corp <Ntt> Color tv system
JPS5449609A (en) * 1977-09-28 1979-04-19 Nippon Kokan Kk <Nkk> Assembling method of double-walled tank
JPS5677474A (en) * 1979-11-28 1981-06-25 Ishikawajima Harima Heavy Ind Method of constructing multiple shell tank

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010275796A (en) * 2009-05-29 2010-12-09 Ihi Corp Method for manufacturing storage tank

Also Published As

Publication number Publication date
JPS5862253A (en) 1983-04-13

Similar Documents

Publication Publication Date Title
RU2430295C2 (en) Reservoir for storage of cryogenic liquids
US2777295A (en) Concrete reservoir for liquefied gases
KR20120127541A (en) Cryogenic storage tank
US5131201A (en) Precast concrete panels and support pedestals constructed therefrom
JPS6331634B2 (en)
US5029426A (en) Precast concrete panels, support pedestals constructed therefrom and an associated method
US4044522A (en) Steel-concrete combination element for lining vessels such as storage tanks, prestressed concrete reactor pressure vessels, and the like
JPS60175668A (en) Construction of cylindrical tank
CN115354775A (en) Ultralow energy consumption building outer wall
JPS6354859B2 (en)
US4643872A (en) Process for the construction of a nuclear reactor with a reinforced concrete pressure vessel
JP3954894B2 (en) Construction port closing method and apparatus during roof air lasing of storage tank
JPH09287157A (en) Steel shell structure of composite immersed tunnel and construction method thereof
JPS6338594B2 (en)
JPH0351596Y2 (en)
JPH0862370A (en) Reactor container and reactor building
JPS5969597A (en) Tank having double wall and installation thereof
JPS6145745B2 (en)
TW202332827A (en) Triple-shell tank
JPH02257095A (en) Method for constructing body for nuclear installations
JP2887223B2 (en) Reactor structure
JP2909350B2 (en) Lining storage tank construction method
CN117536630A (en) End wall of station capable of being frozen and shield receiving system
JPH07128478A (en) Method for installing piping penetration part of concrete containment
JPS64549B2 (en)