JPS63273067A - Watt-hour meter for air conditioner - Google Patents

Watt-hour meter for air conditioner

Info

Publication number
JPS63273067A
JPS63273067A JP62109325A JP10932587A JPS63273067A JP S63273067 A JPS63273067 A JP S63273067A JP 62109325 A JP62109325 A JP 62109325A JP 10932587 A JP10932587 A JP 10932587A JP S63273067 A JPS63273067 A JP S63273067A
Authority
JP
Japan
Prior art keywords
power
unit
air conditioner
power consumption
current transformer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP62109325A
Other languages
Japanese (ja)
Inventor
Hiroyuki Tsuji
弘之 辻
Michinobu Sakanaka
阪中 理展
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP62109325A priority Critical patent/JPS63273067A/en
Publication of JPS63273067A publication Critical patent/JPS63273067A/en
Pending legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

PURPOSE:To reduce a cost by detecting the input current of an air conditioner by a through type current transformer mounted to a power line and integrating a detected current value by time to determine the power consumption of the air conditioner. CONSTITUTION:A signal outputted from a through type current transformer 3 mounted to the power line 1 of the outdoor unit 2 of each air conditioner is inputted to a power integrating circuit 4 and, after converted 4a to a voltage value in the circuit 4, A/D-converted 4b and inputted to an arithmetic unit 4c. Electric energy outputted from the arithmetic unit 4c is transmitted to a centralized control unit 5 via an interface unit 4e. The output of a pulse output watt-hour meter 6 is inputted to the unit 5 and the power consumption of all the air conditioners is recorded in the unit 5. Thus, a cost can be reduced by constituting a power integrating instrument by the through type current transformer.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、空調機への取付けにおいて何ら特別な引出
端子を必要とせず、どの様なユニットも取付可能な電力
積算装置に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a power integration device that can be attached to any type of unit without requiring any special lead-out terminal when attached to an air conditioner.

(従来の技術”〕 一般に゛空調機の電力量を換算するには、空pI機の全
入力を電力計にて積算し管理する方法が取られているが
、電力計の設f1場所や電力計への配線の引まわし等が
必要であ夕、場所を大きくとる上に高”価なシステムと
なっていた。また、単純に運転時間のみを積算し、全使
用電力量を運転時間の□みで接分する方法や、これらを
改良して第3図のような電力換算器があった。図におい
て、(1)は電力線、(2)は室外機、(ト)は運転信
号出力端子、(4)は電力換算機、(4f〕は室外機よ
り出力された運転信号より空調機の運転時間を積算する
積算器、(4g)は対象ユニットの標準入力(、TIS
規格)を設定し電力換算器に出力する回路、(4a)は
運転時間の積算情報と標準人力より電力を算出する演算
器(cpu入(4d)はメモリー、’(4e )は得ら
れた電力量の信号の伝送を行うインターフェースユニッ
ト、(5)は端末より得られた電力消費情報を取入れ集
中管理を行う集中管理ユニット、(6)は全全j11機
の消費電力を検出するパルス出力端予行の電力量計で、
そのパルス出力は集中管理ユニット(5)に接続されて
いる0 次に動作について説明する0運転時間積算器は室外ユニ
ットからの運転信号を受は運転時間を積算し演算器(4
C)に出力する。入力設定回路(4g)には予めJ工S
規格によるユニットの標準入力が設定され演算器に出力
されている。従来の電力積算器は上記の運転時間の積算
値と標準入力の値を揖合せることにより消費電力を示す
演算値量を得ていた。こうして得られた各ユニットの消
費電力は集中管理ユニットに伝送される。集中管理ユニ
ットにおいては、パルス出力付電力量計の出力を、各ユ
ニットより伝送され九消費電力を示す演算値によ夕配分
することによって各ユニットを使用するテナント、店舗
Klt力料全料金求するものでめるO 〔発明が解決しようとする問題点〕 従来の電力積算装置は以上のように構成されているので
、空調機の取付けには運転gI号の引出端子が必要であ
り、専用接点取出し又は運転信号の引出端子が用意され
ていない空調機への取付けは圧縮機への電圧印加で判断
するため、AC200V 1[圧を電子機器へ取込むイ
ンターフェイスが必要でありシステムの適用に手数のか
かるものであった。
(Conventional technology) Generally speaking, in order to convert the power consumption of an air conditioner, a method is used in which all the inputs of the air conditioner are integrated and managed using a power meter. The system requires wiring to the meter, takes up a large amount of space, and is expensive.In addition, the system simply integrates only the operating hours and calculates the total amount of electricity used in the operating hours. There was a power converter as shown in Figure 3, which was developed by improving these methods.In the figure, (1) is the power line, (2) is the outdoor unit, and (g) is the operation signal output terminal. , (4) is a power converter, (4f) is an integrator that totals the operating time of the air conditioner from the operating signal output from the outdoor unit, and (4g) is the standard input of the target unit (, TIS
(4a) is an arithmetic unit that calculates electric power from cumulative operating time information and standard human power (CPU input (4d) is memory, '(4e) is the obtained electric power (5) is a central control unit that receives power consumption information obtained from terminals and performs centralized management; (6) is a pulse output end preliminary run that detects the power consumption of all J11 machines. With the electricity meter,
The pulse output is connected to the central control unit (5).The operation will be explained next.The operation time integrator receives the operation signal from the outdoor unit, integrates the operation time,
C). The input setting circuit (4g) is pre-installed with J-S.
The standard input of the unit according to the standard is set and output to the arithmetic unit. A conventional power integrator obtains a calculated value indicating power consumption by combining the above-mentioned integrated value of operating time and the standard input value. The power consumption of each unit thus obtained is transmitted to the central management unit. In the central control unit, the output of the electricity meter with pulse output is transmitted from each unit, and the total power charges are calculated for each tenant and store Klt that uses each unit by allocating it to a calculated value indicating the power consumption. [Problem to be solved by the invention] Since the conventional power integration device is configured as described above, a lead-out terminal of operation gI is required to install the air conditioner, and a dedicated contact is required. When installing to an air conditioner that does not have a terminal for extracting or operating signals, the judgment is made based on the voltage applied to the compressor, so an interface to take in AC200V 1 [pressure] to the electronic equipment is required, making it time-consuming to apply the system. This was the case.

更に、標準入力値が不明な空調機や空調機以外のビル付
帯設備が存在する場合も、入力値調査等に多大の時間を
必要とした。
Furthermore, when there is an air conditioner or building ancillary equipment other than the air conditioner for which the standard input value is unknown, a great deal of time is required to investigate the input value.

この発明は上記のような問題点を解消するためになされ
たもので、空調機への取付けに何も特別な処理や端子を
必要とせず、どのようなユニットにも取付可能な電力積
算装置を得ることを目的とする。
This invention was made to solve the above problems, and provides a power integration device that can be attached to any unit without requiring any special processing or terminals when attached to an air conditioner. The purpose is to obtain.

〔問題点を解決するための手段〕[Means for solving problems]

この発明に係る電力積算装置は空調機の入力電流を電力
線に取付けた貫通形電流変成器cTにより検出し、電流
値を時間によって積分することにより9111機の消費
電力を求めるようにしたものである。
The power integration device according to the present invention detects the input current of the air conditioner using a through-type current transformer cT attached to the power line, and calculates the power consumption of the 9111 aircraft by integrating the current value over time. .

〔作用〕[Effect]

との発明における電力積算装置は空調機の電力線をCT
IC貫通することにより空調機の電流値を得て、運転の
確認及び電流検知により消費電力を得るO 〔実施例〕 fs1図はこの発明による電力積算装置の一実施例を示
−したものであり、(1)は電力線、(2)社空調機の
室外機、(3)は電力#lK取付けられたCTであり、
(4)は電力積算回路、(5)は電力集中管理ユニット
、(6)は空調機電源の幹線部に取付けられ、全空調機
の消費電力をモニターするパルス出力付電力量計である
。電力線(1)に取付けられたC T (3)より出力
された信号は電力積算回路に入力され、内部で電圧値に
変換(4a)後A/D変換(4b)されcpu(4a)
に入力されている。cpu(4c)より出力された電力
量はインター7エースユニツト(以降工1i’U ) 
(4e)≦よシ集中管理ユニット(5)に伝送される。
The power integration device in the invention by CT CT
The current value of the air conditioner is obtained by passing through the IC, and the power consumption is obtained by checking the operation and detecting the current. , (1) is the power line, (2) the outdoor unit of the company's air conditioner, and (3) is the CT installed with power #lK,
(4) is a power integration circuit, (5) is a power central management unit, and (6) is a power meter with pulse output that is attached to the main power supply of the air conditioner and monitors the power consumption of all air conditioners. The signal output from the CT (3) attached to the power line (1) is input to the power integration circuit, internally converted to a voltage value (4a), then A/D converted (4b) and sent to the CPU (4a).
has been entered. The amount of electric power output from the CPU (4c) is
(4e)≦transmitted to the central management unit (5).

また、パルス出力電力量計(6)の出力は集中管理ユニ
ットに入力され集中管理ユニットにおいて全空調機の消
費電力が記録される。
Further, the output of the pulse output power meter (6) is input to a central control unit, and the power consumption of all air conditioners is recorded in the central control unit.

次に動作について説明する。第2図はcpu (4c)
の処理を示すフローチャートである。(6)〜(8)の
動作でt分毎に電流値工tを読み込み定飲工Wに加算し
ていくことで電流値の積分を行い、(9)において7時
間経過後もしくは集中管理ユニットからの電力送信要求
が生じた場合、(6)〜(8)の動作により積分された
電流値を相当する電力量に換算し、集中管理ユニットに
伝送すると共に工Wをリセットして勝る。この動作によ
り集中管理ユニットにはT時間毎、もしくは送信要求時
点での空調機の運転状態に応じた積算電力に応じた演算
値が各ユニットより人力される。
Next, the operation will be explained. Figure 2 shows CPU (4c)
3 is a flowchart showing the processing of FIG. In the operations of (6) to (8), the current value is integrated by reading the current value t every t minutes and adding it to the fixed value W, and in (9) after 7 hours have elapsed or the central control unit When a power transmission request occurs, the integrated current value is converted into the corresponding power amount by the operations (6) to (8), and transmitted to the central control unit, and the power W is reset. Through this operation, each unit manually inputs to the central management unit a calculated value corresponding to the integrated power according to the operating state of the air conditioner at the time of the transmission request or every T time.

こうして得られた各ユニットの演算値によυパルス出力
付電力計の出力より得た全消費電力を配分し、各テナン
ト、店舗に電力料金の請求を自動的に行っている。
The total power consumption obtained from the output of the υ pulse output wattmeter is distributed according to the calculated values of each unit, and each tenant and store is automatically billed for the power charges.

上記実施例では空調機の室外機の電力積算について説明
したが、室内機のヒータ通電の電力積算についても有効
である。
In the above embodiment, the power integration of the outdoor unit of the air conditioner has been described, but it is also effective for power integration of the heater energization of the indoor unit.

また1、ビル及び店舗に付帯される設備の共用電力量を
液分する場合の電力量も同様のシステムを適用すること
が可能である。
In addition, 1. A similar system can be applied to the amount of electricity when the amount of electricity shared by equipment attached to buildings and stores is divided into liquids.

なお、この実施例では、電流値を積分する演算で電力換
算している例を示したが、電流値と他の管理値の相関関
係を電力積算回路(4)K記憶させておき、電力計測対
象機器の特性を把握して、他の情報に使用することも可
能である。
In addition, in this embodiment, an example was shown in which power is converted by integrating the current value, but the correlation between the current value and other management values is stored in the power integration circuit (4) K, and the power measurement It is also possible to understand the characteristics of the target device and use it for other information.

〔発明の効果〕〔Effect of the invention〕

以上のように、この発明による電力積算装置はCTによ
り構成され安価である上に、電流検知により電力積算を
行う為、空調機への取付けは電力線をCTK通すだけで
よく、取付けに運転信号を取出す端子がなく、あらゆる
機種及び付帯設備に取付けが可能な電力積算装置が手軽
に得られる効果がある。
As described above, the power integration device according to the present invention is constructed of a CT and is inexpensive, and also integrates power by detecting current, so it can be installed in an air conditioner simply by passing the power line through the CTK, and an operation signal can be sent to the installation. There is no terminal to take out, and there is an effect that a power integration device that can be easily attached to any model and ancillary equipment can be obtained.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はこの発明の一実施例による電力積算装置のブロ
ック図、第2図はこの発明の一実施例によるフローチャ
ート、第3図は従来の電力積算装置のブロック図である
。(2)は空調機の室外二ニット、(3)は電流トラン
ス、(4)は電力積算装置、(5)は集中管理ユニツ)
、(6)はパルス出力付電力量計である。
FIG. 1 is a block diagram of a power integration device according to an embodiment of the present invention, FIG. 2 is a flowchart according to an embodiment of the invention, and FIG. 3 is a block diagram of a conventional power integration device. (2) is the outdoor unit of the air conditioner, (3) is the current transformer, (4) is the power integration device, and (5) is the central control unit)
, (6) is a power meter with pulse output.

Claims (2)

【特許請求の範囲】[Claims] (1)複数台の空気調和機を接続し、全ユニットの消費
電力を求めた上で、各ユニットの運転状態をモニターし
、各ユニットの消費電力に応じて電力料金を接分する電
力量料金管理システムにおいて、各ユニットの運転状況
をモニターする方法を各ユニットの入力線に取付けた貫
通式電流変成器(以降CTと略す)により得られる電流
信号によりモニターすることを特徴とする電力積算装置
(1) Electricity rate that connects multiple air conditioners, calculates the power consumption of all units, monitors the operating status of each unit, and divides the power fee according to the power consumption of each unit. A power integration device in a management system, characterized in that the operating status of each unit is monitored using a current signal obtained from a feedthrough current transformer (hereinafter abbreviated as CT) attached to an input line of each unit.
(2)複数台の空気調和機を接続する幹線部に発信装置
付電力量計を用いて上記電流信号をモニターした演算値
により、振分処理することを特徴とする電力積算装置。
(2) A power integration device that performs distribution processing based on a calculated value obtained by monitoring the current signal using a power meter with a transmitting device in a main line connecting a plurality of air conditioners.
JP62109325A 1987-04-30 1987-04-30 Watt-hour meter for air conditioner Pending JPS63273067A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62109325A JPS63273067A (en) 1987-04-30 1987-04-30 Watt-hour meter for air conditioner

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62109325A JPS63273067A (en) 1987-04-30 1987-04-30 Watt-hour meter for air conditioner

Publications (1)

Publication Number Publication Date
JPS63273067A true JPS63273067A (en) 1988-11-10

Family

ID=14507367

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62109325A Pending JPS63273067A (en) 1987-04-30 1987-04-30 Watt-hour meter for air conditioner

Country Status (1)

Country Link
JP (1) JPS63273067A (en)

Similar Documents

Publication Publication Date Title
US6708126B2 (en) Method and system for measuring current
US5315531A (en) Energy monitoring system for a plurality of local stations with snapshot polling from a central station
JP6115862B2 (en) Sensor unit, power measurement unit and power measurement system
US20130116952A1 (en) Power metering system and a method of displaying reading derived from the same
CN110646664B (en) Method and device for monitoring power consumption of multi-split system and multi-split system
CN110440422B (en) LORA communication-based central air-conditioning temperature controller cost control method and system
KR20160096350A (en) Performance measuring system and method for electric vehicle charger
JP3603876B2 (en) Weighing device
EP0528634B1 (en) Energy monitoring system for a plurality of local stations with snapshot polling from a central station
JPS63273067A (en) Watt-hour meter for air conditioner
JP2005352532A (en) Automatic meter reading system
JP3641443B2 (en) Electric equipment power management system
CN109239455B (en) Electric energy meter for substation gateway with function of monitoring secondary circuit fault
JPS63273752A (en) Integrating watt meter for airconditioner
TW202104910A (en) Expandable combination electric meter
CN211348421U (en) Electric energy power consumption monitoring system
JP3232303B2 (en) Terminal device
CN209728023U (en) A kind of guide tracked single-phase electric energy meter
JP3417279B2 (en) Metering / measuring control device for light / heat consumption and control method therefor
EP2492644A2 (en) Distributed computing with meters
JPH0221271A (en) Power charge management for air conditioning machine
JPS6172398A (en) Transducer
JPS58223774A (en) Radiation monitoring device
KR20010109229A (en) Image Based Meter reading system using image sensor and external integrator with intermittent power along by gas distribution pipe
JPH09212780A (en) Centralized metering system