JPS6258225B2 - - Google Patents
Info
- Publication number
- JPS6258225B2 JPS6258225B2 JP54164790A JP16479079A JPS6258225B2 JP S6258225 B2 JPS6258225 B2 JP S6258225B2 JP 54164790 A JP54164790 A JP 54164790A JP 16479079 A JP16479079 A JP 16479079A JP S6258225 B2 JPS6258225 B2 JP S6258225B2
- Authority
- JP
- Japan
- Prior art keywords
- load
- power
- failure
- contact
- accident
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000010586 diagram Methods 0.000 description 7
- 238000000034 method Methods 0.000 description 3
- 230000005284 excitation Effects 0.000 description 2
- 238000010008 shearing Methods 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 239000011159 matrix material Substances 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Description
【発明の詳細な説明】
この発明は受配電系統の負荷選択しや断装置に
関するもので、事故時にすみやかにかつ最適の負
荷をしや断するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a load selection and disconnection device for a power receiving and distribution system, which promptly and optimally disconnects a load in the event of an accident.
複数の負荷を接続した電源系統が多数個互いに
接続された第1図に示すような受配電系統におい
ては、受電系統の事故や発電機32の故障あるい
は事故が発生すると、電源容量の負荷バランスが
くずれ故障していない受電系統31や発電機32
が過負荷状態となるおそれがある。このような場
合、このまま放置すると次々にトリツプし全停電
状態に発展する。 In a power receiving and distributing system as shown in Fig. 1, in which a large number of power supply systems connecting multiple loads are connected to each other, if an accident in the power receiving system or a failure or accident in the generator 32 occurs, the load balance of the power supply capacity will be affected. Power receiving system 31 and generator 32 that have not collapsed or failed
may become overloaded. In such a case, if left untreated, the power will trip one after another and develop into a total power outage.
これをさける為、電源側の故障が発生した場合
には、故障して脱落した電源の供給量にみあう負
荷33をしや断し、脱落後の電源容量と負荷容量
のバランスを保つ負荷選択しや断を設けることが
ある。この負荷選択しや断装置は以下に述べるよ
うになつており、従来負荷選択しや断の方法とし
ては、ピンボードにて行なうものが広く使われて
いた。この方法は操作卓上に電源側のトリツプ原
因(以下故障原因と呼ぶ)と負荷系統をマトリツ
クス上に配置し、ピンボード上で指定するように
なつている。最近ではこれら人手で行なつていた
判断や指令を計算機で行なつことが多くなつてき
た。即ち事故発生時に計算機で事故側の電源容量
とこれにみあう必要なしや断量を求め、負荷のバ
ランスと負荷の優先順位を演算し選択指令を出す
ことが行なわれている。 In order to avoid this, when a failure occurs on the power supply side, the load 33 that matches the supply amount of the failed power supply is cut off, and a load selection is made to maintain a balance between the power supply capacity and the load capacity after the failure occurs. A break may be provided. This load selection and disconnection device is as described below, and in the past, as a method for load selection and disconnection, a pin board was widely used. In this method, trip causes on the power supply side (hereinafter referred to as failure causes) and load systems are arranged on a matrix on the operation desk, and specified on a pin board. Recently, many decisions and commands that used to be made manually are now being made by computers. That is, when an accident occurs, a computer is used to determine the power supply capacity on the accident side and the necessary or disconnected capacity to meet this capacity, calculate the load balance and load priority, and issue a selection command.
第2図は上記ピンボードの回路図である。
A1,A2,……Aoは電源側の故障原因により開閉
する接点で、第1図の電力系統31,もしくは発
電機32の故障が発生すると動作する。また
B1,B2,……Bnは実際の負荷系統に対応して設
けられた模擬負荷系統である。次にCij(i=1
〜n,j=1〜mただしn,mは正の整数)は電
源の故障原因によりどの負荷を選択しや断するか
決定する接点で、ピンボードにピンを挿入するこ
とによつて開閉する。一方1R,2R,mRは故障時
に該当負荷にしや断指令を与える為のリレーであ
る。このリレーの動作によりそれぞれD1,D2,
……Dnの接点を開閉し、しや断器CB1,CB2,…
…CBnをしや断する。第3図は計算機50を用い
た従来の負荷選択しや断の回路図である。E1,
E2,……Eoは計算機50が選択した負荷に対し
しや断指令を与える為のリレーである。 FIG. 2 is a circuit diagram of the pin board.
A 1 , A 2 , . . . A o are contacts that open and close depending on the cause of failure on the power supply side, and are activated when a failure occurs in the power system 31 or generator 32 shown in FIG. 1. Also
B 1 , B 2 , . . . B n are simulated load systems provided corresponding to the actual load systems. Next, Cij(i=1
~n, j = 1 ~ m (where n, m are positive integers) is a contact that determines which load is selected or disconnected depending on the cause of the failure of the power supply, and is opened or closed by inserting a pin into the pin board. . On the other hand, 1R, 2R, and mR are relays that give a shedding command to the relevant load in the event of a failure. Due to the operation of this relay, D 1 , D 2 ,
...opens and closes the contacts of D n , and the circuit breakers CB 1 , CB 2 ,...
...to cut off CB n . FIG. 3 is a circuit diagram of a conventional load selection and disconnection method using a computer 50. E1 ,
E 2 , . . . E o are relays for giving a shedding command to the load selected by the computer 50.
以上述べたような従来の負荷選択しや断装置で
はピンボードによる場合はピン選択が適切に行な
われていないと過しや断や不足しや断となるおそ
れがある。又計算機を用いた場合も、原理的に演
算時間や指令の出力には遅れが伴なうので、故障
発生後演算し負荷しや断指令を出しても間にあわ
ないおそれがある。 In the case of the conventional load selection and disconnection device as described above using a pin board, there is a risk of errors, disconnections, shortages, or disconnections if pin selection is not performed appropriately. Even when a computer is used, there is a delay in the calculation time and command output in principle, so there is a risk that it will not be in time even if the calculation is performed after a failure occurs and a load or disconnection command is issued.
本発明の目的は、故障発生前に常に最適しや断
状態を選択しておき、故障発生時にはすみやかに
最適負荷をしや断し、又故障が続発した場合にお
いても後発の故障に対しても最適しや断状態を選
択して、負荷をしや断し全停までいたらしめない
負荷しや断装置を得ることである。 The purpose of the present invention is to always select the optimum load-off state before a failure occurs, to quickly turn off the optimum load when a failure occurs, and to prevent subsequent failures even when failures occur one after another. The object of the present invention is to obtain a load shedding device which can select an optimum shearing state and shear the load without causing a complete stoppage.
以下本発明の実施例について第4図,第5図を
参照しながら説明する。第4図は本発明の回路図
を示す。接点F1…FoとG1…Goは電源の入力しや
断、あるいは発電機の過負荷、発電機トリツプ
等、電源供給側に発生した事故を検出する保護リ
レーあるいはシーケンスによつて組まれた事故信
号であつて、接点F1,F2,……Foは供給電源が
事故発生した時、瞬時に閉となる。この接点は第
1番目の事故発生後1回だけ動作し、続いて続発
する第2番目以後の事故時には動作しないように
なつている。接点G1,G2,……Goは供給電源が
事故発生しても即座には動作せず一定時間経過後
に閉となる。これらGi,Fiの接点は故障発生信
号に応動し、動作するようになつている。接点
Ci,j(i=1〜n,j=1〜m)は計算機が
故障原因と負荷バランス,負荷の優先順位をもと
に算出したしや断すべき負荷を選択する計算機の
出力Ei,j(i=1〜n,j=1〜m)により
開閉する。 Embodiments of the present invention will be described below with reference to FIGS. 4 and 5. FIG. 4 shows a circuit diagram of the invention. Contacts F 1 ...F o and G 1 ...G o are assembled by a protective relay or sequence that detects faults that occur on the power supply side, such as power input/output, generator overload, generator trip, etc. Contacts F 1 , F 2 , . . . , F o are instantaneously closed when an accident occurs in the power supply. This contact operates only once after the first accident occurs, and does not operate in the event of a second or subsequent accident. Contacts G 1 , G 2 , . . . G o do not operate immediately even if an accident occurs in the power supply, but close after a certain period of time has elapsed. These Gi and Fi contacts operate in response to a failure signal. contact
Ci,j (i = 1 to n, j = 1 to m) is the output Ei,j of the computer that selects the load that should be cut off, calculated by the computer based on the cause of failure, load balance, and load priority. (i=1 to n, j=1 to m).
G1…Goは事故フイーダのFが動作しても、内
部の負荷優先順位計算が終了するまで事故フイー
ダの選択をまたせるものである。しや断フイーダ
Cigは事故フイーダ1回線に対する選択である。
同時に2フイーダを選択しても2つの事故フイー
ダに共通したしや断フイーダCigがあるとこの分
だけしや断不足になる。第2事故に対してはあら
ためてしや断フイーダを選択しなおす必要があ
り、この時最大効率点を求めると最初の設定と異
なつたしや断フイーダが選択されるおそれがあ
る。G1…Goは第2事故に対し新たなしや断フイ
ーダを選択する時間を持たせるための限時要素を
持たせ、不足しや断あるいは過しや断を防ぐ役目
を持たせている。 G 1 ...G o is used to change the selection of the accident feeder until the internal load priority calculation is completed even if the accident feeder F operates. Shiyadan feeder
Cig is the choice for accident feeder 1 line.
Even if two feeders are selected at the same time, if there is a common feeder Cig for the two accidental feeders, the feeder will be short by this amount. In the case of the second accident, it is necessary to select the shingle cutting feeder again, and if the maximum efficiency point is determined at this time, there is a possibility that a shingle cutting feeder different from the initially set one will be selected. G 1 ...G o has a time limit element to allow time to select a new feeder or cut feeder in response to the second accident, and has the role of preventing shortages or cuts or errors or cuts.
F1…Fo,G1…Goの接点の動作では、第3事故
まで同時に発生すると、G1…Goの接点は第2,
第3事故に対し、G1…Goの刻当接点が同時に動
作するおそれはあるが、3つ以上の電源が同時に
事故となることは、本発明の装置が連鎖事故を防
いでいるかぎり非常にまれなケースであり、第2
事故まで防げれば充分に本装置の目的は充分に達
せられる。 In the operation of the contacts F 1 ...F o and G 1 ...G o , if up to the third accident occurs simultaneously, the contacts of G 1 ...G o will
Regarding the third accident, there is a possibility that the contact points of G 1 ... G o operate simultaneously, but as long as the device of the present invention prevents chain accidents, it is extremely unlikely that three or more power supplies will fail at the same time. This is a rare case, and the second
If accidents can be prevented, the purpose of this device can be fully achieved.
B1,B2,……Bnは負荷系統,A1,A2,……A
oは故障原因その他の記号は従来例に示すものと
同じである。計算機50の動作について第5図に
示す。計算機50は負荷系統の使用電力を取り入
れ別途指定する負荷の重要度,電源しや断等の条
件をもとに受電系統の容量,発電機の容量と負荷
のバランスを算出する。これに基づきしや断する
負荷の優先順位を決定する。 B 1 , B 2 , ...B n is the load system, A 1 , A 2 , ...A
o indicates the cause of failure and other symbols are the same as those shown in the conventional example. The operation of the computer 50 is shown in FIG. The computer 50 takes in the power used by the load system and calculates the balance between the capacity of the power receiving system, the capacity of the generator, and the load based on the importance of the load specified separately, conditions such as power interruption, etc. Based on this, the priority of the load to be shelved is determined.
計算機50は一定周期毎に各供給電力と負荷の
使用電力を読み、負荷バランスとしや断の優先順
位を演算し、故障原因A1,A2,……Aoの別毎に
どの負荷をしや断すべきか決定する。負荷しや断
パターンの算出は負荷フイーダの中から任意のフ
イーダを選らびしや断可能なフイーダの中から任
意に抽出し負荷容量を総計し、電源供給の不可能
な量にもつとも近いフイーダの組合せを見つけ出
す。又事故発生時には残された電源と負荷からし
や断の優先順位を再度演算し設定する。負荷フイ
ーダには優先順位を設け、負荷しや断をさけなけ
ればならないフイーダには高い優先順位を設定
し、最後まで負荷しや断されずに残るようにす
る。 The computer 50 reads each supplied power and the power used by each load at regular intervals, calculates load balance and shearing priority, and determines which load should be used for each failure cause A 1 , A 2 , . . . A o. Decide if it should be terminated. To calculate the load failure pattern, select any feeder from among the load feeders, select any feeder from among the feeders that can be disconnected, add up the load capacity, and calculate the load failure pattern of the feeder that is close to the amount of power that cannot be supplied. Find a combination. In addition, in the event of an accident, the priority order for shunting is calculated and set again from the remaining power source and load. A priority is set for the load feeders, and a high priority is set for the feeder that must be loaded or cut off, so that the feeder remains loaded and uncut until the end.
次に負荷選択しや断装置の動作について初めの
故障原因がA1次の故障がA2で起つた場合を例に
して説明する。電源系統に事故が発生した場合、
事故信号は接点F1,G1を閉にすると共に計算機
に入力される。接点F1は事故発生後瞬時に閉さ
れる為、あらかじめ計算機により最適負荷配分さ
れた設定すなわちC11,C12,……C1nに設定され
ている接点を通り、励磁コイルをオンする。この
励磁により負荷がしや断される。 Next, the operation of the load selection and disconnection device will be explained using an example in which the first failure cause is A and the primary failure occurs at A2 . If an accident occurs in the power system,
The fault signal closes contacts F 1 and G 1 and is input to the computer. Since the contact F 1 is closed instantly after the occurrence of an accident, the excitation coil is turned on through the contacts set to C 11 , C 12 , . This excitation causes the load to be quickly disconnected.
計算機50は事故発生信号を同時に受け、A系
統以外の残りの供給電力を残された負荷フイーダ
とから各電源が故障した場合の停止優先順位を決
定するとともに、C11,C12,……C1nを除く他の
Ci,j(i=2〜n,j=1〜m)の接点に演
算結果を設定する。この間に2度目の電源事故が
発生しても接点Ci,jが全て設定完了するまで
は、第1の故障によりF1が動作しているのでF2
は動作せず、かつ原因接点G2はデイレー中の
為、負荷しや断信号は出力されない。接点Ci,
jが全て設定完了したあと原因接点,G2はデイ
レーがとけ第2の原因による負荷がしや断され
る。本発明では従来のものが故障発生後に演算し
出力していたのに比べ常に最新の負荷バランスを
演算した結果が設定されているため故障発生と同
時に瞬時に対応することが可能である。この為演
算等の遅れに伴なう連鎖反応を防止できる。万一
故障,事故が続発しても次の故障,事故に対する
準備がすみやかに行なわれる為、それ以後への波
及を極力おさえることができる。 The computer 50 receives the accident occurrence signal at the same time, and determines the priority order for stopping the remaining power supplies other than the A system from the remaining load feeders in the event of a failure of each power source, and also determines the priority order of shutdown in the event of a failure of each power source, and also outputs the remaining power supplies other than the A system to the remaining load feeders. Other except 1n
The calculation result is set at the contact point of Ci,j (i=2 to n, j=1 to m). Even if a second power supply failure occurs during this time, F 1 will remain in operation due to the first failure, so F 2 will remain active until all contacts Ci and j have been set.
does not operate, and the cause contact G2 is on delay, so no load or disconnection signal is output. Contact point Ci,
After all settings of j are completed, the delay of the cause contact G2 is melted and the load due to the second cause is quickly cut off. In the present invention, the latest load balance calculation results are always set, unlike the conventional system which calculates and outputs the results after a failure occurs, so it is possible to respond instantly when a failure occurs. Therefore, chain reactions caused by delays in calculations, etc. can be prevented. Even if failures or accidents occur one after another, preparations for the next failure or accident can be made promptly, making it possible to minimize the impact on subsequent failures or accidents.
以上のように本発明の負荷選択しや断装置を使
用することにより、より信頼度の高い負荷選択し
や断装置とすることができる。 By using the load selection and disconnection device of the present invention as described above, it is possible to obtain a load selection and disconnection device with higher reliability.
第1図は受配電の系統図、第2図,第3図は従
来の負荷しや断装置の回路図、第4図は本発明の
負荷しや断器の回路図、第5図は本発明の動作を
示すフローチヤートである。
30…所内母線、31…受電系統、32…発電
機、33…負荷、A…事故信号、B…負荷系統、
CB…しや断器、F…瞬時接点、G…限時接点。
Figure 1 is a system diagram of power reception and distribution, Figures 2 and 3 are circuit diagrams of conventional load shield disconnectors, Figure 4 is a circuit diagram of the load shield disconnector of the present invention, and Figure 5 is a circuit diagram of the present invention. 3 is a flowchart showing the operation of the invention. 30...Internal busbar, 31...Power receiving system, 32...Generator, 33...Load, A...Fault signal, B...Load system,
CB...Shipping breaker, F...Momentary contact, G...Time-limited contact.
Claims (1)
力を、重要度の優先順位を設けた複数の負荷に供
給する受配電系統で、その系統の事故あるいは発
電機の故障時に前記複数の負荷にあらかじめ設定
してある優先順位に基づきその負荷をしや断する
装置において、故障信号に瞬時に応動する接点を
設け、この接点の動作によりその故障に対応する
負荷を選択しや断し、この選択しや断後の負荷お
よび電源に基き、この状態でさらに電源故障が起
こつた場合の選択しや断すべき負荷の選択を計算
機が演算する時間分だけ限時動作する限時接点を
設け、いずれかの前記瞬時接点が動作していると
きに系統故障が発生したときは前記限時接点の動
作により負荷選択しや断することを特徴とする負
荷選択しや断装置。1 A power receiving and distribution system that supplies electric power supplied from an electric power system and electric power from a generator to multiple loads with priority orders of importance, and in the event of an accident in the system or a failure of the generator, the multiple loads are In a device that cuts off the load based on a set priority, a contact is provided that instantly responds to a fault signal, and the operation of this contact selects and cuts off the load corresponding to the fault, and the selected load is cut off. Based on the load and power supply after the power failure, a time-limited contact is provided that operates for a time period during which a computer calculates the selection of the load to be selected in the event that a power failure occurs in this state. A load selection/disconnection device characterized in that when a system failure occurs while an instantaneous contact is operating, the load is selected or disconnected by operating the time-limited contact.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16479079A JPS5688628A (en) | 1979-12-20 | 1979-12-20 | Load selection breaker |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16479079A JPS5688628A (en) | 1979-12-20 | 1979-12-20 | Load selection breaker |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5688628A JPS5688628A (en) | 1981-07-18 |
JPS6258225B2 true JPS6258225B2 (en) | 1987-12-04 |
Family
ID=15799982
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP16479079A Granted JPS5688628A (en) | 1979-12-20 | 1979-12-20 | Load selection breaker |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5688628A (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5932326A (en) * | 1982-08-12 | 1984-02-21 | 株式会社明電舎 | Generator interlocking load selective breaker |
-
1979
- 1979-12-20 JP JP16479079A patent/JPS5688628A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS5688628A (en) | 1981-07-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7751166B2 (en) | Advanced feeder architecture with automated power restoration | |
EP1782517B1 (en) | Device for the safe isolation of a nuclear power plant from a supply mains during a mains failure | |
JPH08126210A (en) | Parallel off control device for commercial power supply linkage private generator | |
JPS6258225B2 (en) | ||
US6307723B1 (en) | Parallel-feeder directional overcurrent protection | |
CN113224734B (en) | Implementation method and terminal for auxiliary protection of line | |
JPH0429291B2 (en) | ||
JPH06335171A (en) | Load control method | |
JP2007159188A (en) | Power reception/distribution supervisory control system and its method | |
CN112771745B (en) | DC power distribution system | |
CN208904662U (en) | A kind of electric power system stability control device trip(ping) circuit | |
JPS6260896B2 (en) | ||
JP3433992B2 (en) | Protection system for different bus supply loop transmission line system | |
JPS6027258B2 (en) | Load selection and disconnection device | |
JP3313454B2 (en) | Load selection cut-off device | |
Kim et al. | A validation of IED for networked distribution system | |
JP3167166B2 (en) | Load selective cut-off device | |
JPH07107656A (en) | Protecting device for electric power system | |
Ghoudjebaklou et al. | System Protection Scheme for the DC link between Tasmania and the Mainland Australia | |
JPS6023576B2 (en) | Load shedding method in power system | |
JPH0591670A (en) | Operating system for transformer | |
JP2521159B2 (en) | Distribution system fault condition detector | |
JPS607888B2 (en) | Emergency control method for loop system | |
Bayer et al. | Control measures to ensure dynamic stability of the Cahora Bassa scheme and the parallel HVAC system | |
JP3228582B2 (en) | Step-out separation relay |