JPS6255305A - Method for withdrawing reinforced concrete floor panel of bridge - Google Patents

Method for withdrawing reinforced concrete floor panel of bridge

Info

Publication number
JPS6255305A
JPS6255305A JP19383685A JP19383685A JPS6255305A JP S6255305 A JPS6255305 A JP S6255305A JP 19383685 A JP19383685 A JP 19383685A JP 19383685 A JP19383685 A JP 19383685A JP S6255305 A JPS6255305 A JP S6255305A
Authority
JP
Japan
Prior art keywords
reinforced concrete
flange
bridge
slab
concrete floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP19383685A
Other languages
Japanese (ja)
Inventor
荒田 政次
戸次 和雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Engineering and Shipbuilding Co Ltd
Original Assignee
Mitsui Engineering and Shipbuilding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Engineering and Shipbuilding Co Ltd filed Critical Mitsui Engineering and Shipbuilding Co Ltd
Priority to JP19383685A priority Critical patent/JPS6255305A/en
Publication of JPS6255305A publication Critical patent/JPS6255305A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は橋梁鉄筋コンクリート床版の撒去工法に関する
ものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for removing reinforced concrete deck slabs for bridges.

〔従来技術〕[Prior art]

橋梁の主桁はI型ビームの断面形状をしているものが多
く、この主桁を構成する水平方向のフランジで鉄筋コン
クリート床版を支持している。
The main girders of bridges often have an I-beam cross-section, and the horizontal flanges that make up the main girders support the reinforced concrete slab.

ところで、この構造の橋梁において鉄筋コンクリート床
版に亀裂が生じる等により強度上危険となった場合は、
この鉄筋コンクリート床版を取替える必要がある。
By the way, if the reinforced concrete deck of a bridge with this structure becomes dangerous due to cracks, etc.,
This reinforced concrete slab needs to be replaced.

従来この場合、橋梁の支持部材を構成する主桁及びフラ
ンジを残して鉄筋コンクリート床版をエアーガウジング
又はコアブレーカ等により撒去することが行なわれてい
るが、この工法は騒音が激しく、橋梁が人家に近い場所
に設けられいてる場合が多いために騒音公害を来すばか
りでなく、その撒去作業には多大の時間と労力を必要と
していた。
Conventionally, in this case, the reinforced concrete slab was removed using air gouging or core breakers, leaving the main girders and flanges that make up the support members of the bridge, but this construction method was very noisy and caused the bridge to become inhabited. Because they are often installed near the ground, they not only cause noise pollution, but also require a great deal of time and effort to remove them.

前記工法の問題を解決するために、第6図に示すように
主桁1上に水平方向に設けられたフランジ2上において
、鉄筋コンクリート床版3を切断した際に前記主桁に支
持させるためにフランジ2の内側において垂直方向に切
断し、この切断された鉄筋コンクリート床版3をクレー
ン等で吊上げ撒去することが提案されている。
In order to solve the problem of the above construction method, as shown in Fig. 6, on the flange 2 provided horizontally on the main girder 1, when the reinforced concrete deck slab 3 is cut, it is supported by the main girder. It has been proposed to cut vertically inside the flange 2 and lift and scatter the cut reinforced concrete slab 3 using a crane or the like.

しかし、かかる方法においては、切断された鉄筋コンク
リート床版3の吊上げに時間がかかる・即ち・この鉄筋
コンクリート床版3の厚さWは、一般に30u程度あり
、ダイヤモンドカッター等による切断線4の間隔は30
0鰭程度となる。したがって、切断された鉄筋コンクリ
ート床版3を切断線4に沿って静かに吊上げなければフ
ランジ2に残された鉄筋コンクリート床版3′と当接し
、吊上げできないこととなる。加えて、フランジ2上に
おいて切断するため、カッターがフランジと接触し、こ
れの破損を生じる恐れがあった。
However, in this method, it takes time to lift the cut reinforced concrete slab 3. In other words, the thickness W of this reinforced concrete slab 3 is generally about 30 μ, and the intervals between cutting lines 4 made by a diamond cutter etc. are 30 mm.
Approximately 0 fins. Therefore, unless the cut reinforced concrete floor slab 3 is lifted gently along the cutting line 4, it will come into contact with the reinforced concrete floor slab 3' left on the flange 2 and cannot be lifted. In addition, since the cutter is cut on the flange 2, there is a risk that the cutter will come into contact with the flange and cause damage to the flange.

〔発明の目的〕[Purpose of the invention]

本発明は前記したような従来の問題点を解決するために
なされたものであって、その目的とするところは、騒音
公害が少な(、かつ作業性の良好な橋梁鉄筋コンクリー
ト床版の撒去工法を提供せんとするものである。
The present invention has been made in order to solve the conventional problems as described above, and its purpose is to provide a method for constructing bridge reinforced concrete deck slabs that causes less noise pollution (and has good workability). We aim to provide the following.

〔発明の概要〕[Summary of the invention]

本発明は前記目的を達成するために、主桁のフランジに
より鉄筋コンクリート床版を支持してなる橋梁において
、前記鉄筋コンクリート床版を切断線が上部から下部に
向って、フランジの幅方向外側に傾斜するように切断し
、この切断された鉄筋コンクリート床版を吊り上げ撒去
するようにした橋梁鉄筋コンクリート床版の撒去工法で
ある。
To achieve the above object, the present invention provides a bridge in which a reinforced concrete deck is supported by a flange of a main girder, in which a cutting line of the reinforced concrete deck is inclined outward in the width direction of the flange from the top to the bottom. This method involves cutting reinforced concrete deck slabs into bridges, then lifting and scattering the cut reinforced concrete deck slabs.

〔実施例〕〔Example〕

以下、第1図ないし第5図に基づき本発明による橋梁鉄
筋コンクリート床版の撒去工法の一実施例を説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the method for removing reinforced concrete slabs for bridges according to the present invention will be described below with reference to FIGS. 1 to 5.

第1図は鉄筋コンクリート床版11を撒去中の橋梁10
の一部斜視図、、第2図はその一部平面図、第3図は一
部断面図である。
Figure 1 shows a bridge 10 during which reinforced concrete slabs 11 are being removed.
FIG. 2 is a partial plan view, and FIG. 3 is a partial sectional view.

橋梁10は主桁12上にジベル13を有するフランジ1
4が水平方向に形成され、このフランジ14上に鉄筋コ
ンクリート床版11と舗装置5が積層されている。
The bridge 10 has a flange 1 having a dowel 13 on the main girder 12.
4 is formed in the horizontal direction, and a reinforced concrete floor slab 11 and a paving layer 5 are laminated on this flange 14.

本発明は、前記コンクリート床版をフランジ14の近傍
で切断する際の切断方法が従来の工法とは著しく異なっ
ている。
In the present invention, the method of cutting the concrete slab near the flange 14 is significantly different from conventional construction methods.

即ち、前記構成の鉄筋コンクリート床版11は第3図に
示すようにフランジ14に沿ってその切断線16が上部
から下部に向ってフランジ14の外側に角θとなるよう
傾斜するようにカッターにて切断される。
That is, the reinforced concrete floor slab 11 having the above structure is cut with a cutter along the flange 14 so that the cutting line 16 thereof is inclined from the top to the bottom at an angle θ to the outside of the flange 14, as shown in FIG. disconnected.

このように切断された鉄筋コンクリート床版11は長手
方向にクレーン17の吊上げ能力に合うようなブロック
22として第2図にしすめように切断線18で切断され
る。この切断線18は垂直であって差支えない。然る後
、鉄筋コンクリート床版11に吊具19を取付けてクレ
ーン17で吊上げてトラック20に搭載され、適宜輸送
される。
The thus cut reinforced concrete floor slab 11 is longitudinally cut along cutting lines 18 to form blocks 22 that match the lifting capacity of the crane 17 as shown in FIG. This cutting line 18 may be vertical. Thereafter, a lifting device 19 is attached to the reinforced concrete floor slab 11 and lifted by a crane 17, loaded onto a truck 20, and transported as appropriate.

前記のようにフランジ14の近傍においてフランジ14
の外側を向くようにコンクリート床版を上面から下面に
向けてカッターで切断し、この鉄筋コンクリート床版1
1を撒去すると、その一部が第4図に示すようにフラン
ジ14上に残るが、この鉄筋コンクリート床版11′に
は適当数の注入穴21が設けられ、この注入穴21に例
えば生石灰等の膨張材を注入し、これを静的に破砕し撒
去するのである。
As described above, in the vicinity of the flange 14, the flange 14
Cut the concrete slab from the top surface to the bottom surface with a cutter so that it faces outside of the reinforced concrete slab 1.
1, some of it remains on the flange 14 as shown in FIG. This involves injecting an inflatable material, statically crushing it, and then scattering it.

また、場合によっては通常のコンクリート破砕方法を併
用することができるが、この場合でもコンクリート床版
11′は少量であるので、従来のような大きな騒音を発
生することを防止できる。
Further, in some cases, a normal concrete crushing method may be used in combination, but even in this case, since the concrete slab 11' is a small amount, it is possible to prevent generation of large noises as in the conventional method.

第5図は箱桁橋の鉄筋コンクリート床版11を撒去する
場合の説明図であるが、第1実施例と同様の方法で撒去
するのである。
FIG. 5 is an explanatory diagram of the case where the reinforced concrete deck slab 11 of a box girder bridge is removed, and this is done in the same manner as in the first embodiment.

〔発明の効果〕〔Effect of the invention〕

以上の説明から明らかなように、本発明による橋梁鉄筋
コンクリート床版11の撒去工法は主桁12の上端に設
けられているフランジ14の近傍において、このフラン
ジ14の上方から斜め外側に向かってコンクリート床版
11を切断することに特徴がある。
As is clear from the above explanation, in the method of scattering the bridge reinforced concrete deck 11 according to the present invention, concrete is poured diagonally outward from above the flange 14 in the vicinity of the flange 14 provided at the upper end of the main girder 12. The feature is that the floor slab 11 is cut.

従って、本発明によれば騒音公害の発生も少なく、しか
もフランジ14に沿う切断線16を上部から下部に向っ
てフランジ14の外方に傾斜するようにしたため、切断
した後もコンクリート床版11はフランジ14上のコン
クリート床版11′に支持された状態となる。
Therefore, according to the present invention, there is less noise pollution, and since the cutting line 16 along the flange 14 is inclined outward from the flange 14 from the top to the bottom, the concrete slab 11 remains unchanged even after cutting. It is now supported by the concrete slab 11' on the flange 14.

また、切断線16が斜めになっているために、コンクリ
ート床版11をクレーンで上方へ吊り上げる際の作業が
容易である。
Moreover, since the cutting line 16 is oblique, the work when lifting the concrete slab 11 upward with a crane is easy.

更に、コンクリート床版11の切断作業中に従来の工法
のようにカッターがフランジ14に接触し、これを破損
することがな(なり作業性の良好な撒去が可能となるな
どの効果を有する。
Furthermore, during the cutting work of the concrete slab 11, the cutter does not come into contact with the flange 14 and damage it as in the conventional construction method (this has the effect of making it possible to remove the flange with good workability). .

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第5図は、本発明による橋梁鉄筋コンクリ
ート床版の撒去工法の実施例の説明図であって、第1図
は橋梁の一部斜視図、第2図は平面図、第3図は断面図
、第4図はフランジ14上の鉄筋コンクリート床版の撒
去説明図、第5図は他の構造の橋梁での適用例の説明図
である。第6図は従来の橋梁鉄筋コンクリート床版の撒
去工法の説明図である。 1.12・・・主桁、2,14・・・フランジ、3.1
1・・・鉄筋コンクリート床版、4.16.18・・・
切断線、10・・・橋梁、13・・・ジベル、15・・
・アスファルト、17・・・クレーン、19・・・吊具
、20・・・トランク、21・・・注入穴。
1 to 5 are explanatory diagrams of an embodiment of the bridge reinforced concrete deck scattering method according to the present invention, in which FIG. 1 is a partial perspective view of the bridge, FIG. 2 is a plan view, and FIG. The figure is a sectional view, FIG. 4 is an explanatory diagram of the removal of the reinforced concrete slab on the flange 14, and FIG. 5 is an explanatory diagram of an example of application to a bridge of another structure. FIG. 6 is an explanatory diagram of the conventional method for removing reinforced concrete slabs for bridges. 1.12...Main girder, 2,14...Flange, 3.1
1...Reinforced concrete floor slab, 4.16.18...
Cutting line, 10...Bridge, 13...Gibel, 15...
- Asphalt, 17... Crane, 19... Hanging tool, 20... Trunk, 21... Injection hole.

Claims (1)

【特許請求の範囲】[Claims] 主桁上に設けられたフランジにより鉄筋コンクリート床
版を支持してなる橋梁において、前記鉄筋コンクリート
床版を切断線が上部から下部に向って、フランジの幅方
向外側に傾斜するように切断し、該切断された鉄筋コン
クリート床版を吊り上げ撒去することを特徴とする橋梁
鉄筋コンクリート床版の撒去工法。
In a bridge in which a reinforced concrete deck is supported by a flange provided on a main girder, the reinforced concrete deck is cut so that the cutting line is inclined outward in the width direction of the flange from the top to the bottom; A method for removing reinforced concrete deck slabs for bridges, which is characterized by lifting up and removing the reinforced concrete deck slabs.
JP19383685A 1985-09-04 1985-09-04 Method for withdrawing reinforced concrete floor panel of bridge Pending JPS6255305A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19383685A JPS6255305A (en) 1985-09-04 1985-09-04 Method for withdrawing reinforced concrete floor panel of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19383685A JPS6255305A (en) 1985-09-04 1985-09-04 Method for withdrawing reinforced concrete floor panel of bridge

Publications (1)

Publication Number Publication Date
JPS6255305A true JPS6255305A (en) 1987-03-11

Family

ID=16314543

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19383685A Pending JPS6255305A (en) 1985-09-04 1985-09-04 Method for withdrawing reinforced concrete floor panel of bridge

Country Status (1)

Country Link
JP (1) JPS6255305A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007085037A (en) * 2005-09-20 2007-04-05 Kajima Corp Floor slab remodeling method using buried form

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007085037A (en) * 2005-09-20 2007-04-05 Kajima Corp Floor slab remodeling method using buried form

Similar Documents

Publication Publication Date Title
CN205875734U (en) Concrete placement splices template
US11473253B2 (en) Concrete deck demolition system and method
JPS6255306A (en) Method for withdrawing reinforced concrete floor panel of bridge
US4640648A (en) Industrial floor and construction method
JPS6255305A (en) Method for withdrawing reinforced concrete floor panel of bridge
US5743065A (en) Method for reducing stress cracks at re-entrant corners of a concrete slab
JPS6059209A (en) Replacing method of bridge reinforced concrete floor panel
JPH108429A (en) Structure of concrete protection fence and construction method therefor
JPS6245804A (en) Re-covering of bridge reinforced concrete
JP3120070B2 (en) How to build a thin concrete overlay
JPS5830988B2 (en) How to reinforce existing reinforced concrete floor slabs
JPS60126448A (en) Crack inducing structure of concrete structure
JPS6332058A (en) Method for lining floor with stone material
JPH0426483Y2 (en)
US5829213A (en) Concrete slab saver
JPS6085139A (en) Crack inducing structure in reinforced concrete structure
CN219599920U (en) Auxiliary component for precast concrete member hanging ring construction
CN209163445U (en) A kind of wafer board parting seam block structure
JP2642289B2 (en) Joint structure induced by concrete slab
JPH10152806A (en) Road surface lining board
JP3008040B2 (en) Large span composite slab erection method
JPH06248742A (en) Rc floor slab
JP2578606B2 (en) Brittle body surface shaping method
JP3131897B2 (en) Method of preventing defects due to concrete sedimentation
JPS6195142A (en) Construction of slab