JPS62288268A - Construction method for assembling reinforcing bar of support - Google Patents

Construction method for assembling reinforcing bar of support

Info

Publication number
JPS62288268A
JPS62288268A JP13036386A JP13036386A JPS62288268A JP S62288268 A JPS62288268 A JP S62288268A JP 13036386 A JP13036386 A JP 13036386A JP 13036386 A JP13036386 A JP 13036386A JP S62288268 A JPS62288268 A JP S62288268A
Authority
JP
Japan
Prior art keywords
hoist
stirrup
group
reinforcing bar
stirrups
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP13036386A
Other languages
Japanese (ja)
Other versions
JPH0516513B2 (en
Inventor
隆男 吉田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP13036386A priority Critical patent/JPS62288268A/en
Publication of JPS62288268A publication Critical patent/JPS62288268A/en
Publication of JPH0516513B2 publication Critical patent/JPH0516513B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 3、発明の、;T細な説明 〔産業上の利用分野〕 この発明は、鉄筋コンクリート建造物における支柱の中
核となる鉄筋、特に帯筋の組1γ[法に関するものであ
る。
[Detailed Description of the Invention] 3. Detailed Description of the Invention [Field of Industrial Application] This invention relates to reinforcing bars that are the core of supports in reinforced concrete buildings, particularly to the set 1γ of stirrup bars. be.

〔従来の技術〕[Conventional technology]

般に、鉄筋コンクリート建造物の支柱を建設置−る方法
としては、支柱の」、t、礎となる基盤トに、1、亥支
柱の横断面形状に対応してその外周面の内側に相当する
位置に所要の隣接間隔をもって立設されたL筋を、溶着
によって[一方へ延伸させ、各階をL′Y通して設け、
この一群の主筋外周を囲んで枠・へ!に形成された帯筋
(HOOP、まきたが)多数を 定のピッチをもって結
着し、その外方を型枠て取り囲ませた後、セメントを流
入して支柱を形成している。
In general, the method of constructing and installing columns for reinforced concrete buildings is to place the base of the column at a position corresponding to the cross-sectional shape of the column and the inside of its outer circumferential surface. Weld the L bars erected at the desired positions with the required spacing between each other and extend them in one direction, passing each floor through L'Y,
Surround the outer periphery of this group of main muscles and go to the frame! A large number of hoops (HOOP) are tied together at a certain pitch, and after surrounding the outside with formwork, cement is poured in to form the supports.

ところて従来、前記帯筋を支柱に組み付けるT法として
は、第7図に示すように、熟練作業者2〜3名か最ト一
層階からL層階へと各階ごとに、脚・I−に、あるいは
台などを利用して、rめ、チョーク分用い複数本のIE
筋1にピッチ印3を記した後、1.筋1群に外挿して床
1面に準備した所要数の枠型に形成した帯筋2・・・・
・・のうちから1個ずつ持ちトげ、l−階梁ドTまで順
々に前記ピッチ印3の位置に合わせて保持しつつ各主筋
1と帯筋2とを適当な箇所で結束線4により縛着して組
み立てていた。
However, conventionally, as shown in Fig. 7, the T method for assembling the tie bars to the pillars has been carried out by two to three skilled workers who have assembled the legs, I- Or use a stand or the like to store multiple IEs using chalk.
After marking pitch mark 3 on line 1, 1. Extrapolated to the first group of strips, the required number of tie bars 2 are prepared in a frame shape on one floor...
. . . Pick up one at a time and hold each main bar 1 and tie bar 2 at an appropriate point, holding them in sequence at the pitch mark 3 up to the L-story beam DoT. It was tied up and assembled.

(発明か解決しようとする問題点) 従来の鉄筋組)r、I法は、以トのような方法により行
っていたため、枠型の帯筋を作業者相互に調子を合わし
て高所に持ちFげるという危険が伴うばかりか、力(l
:’IGともなるのて作業者は疲労しや1−<、また、
ピッチ印に帯筋を保持しつつ縛着するには熟練を要し、
しかち脚1γにν1り降りしてピッチ印を付することも
数か多いため繁雑で時間もかかり、作業効率や安全性の
面に神々の問題点を有していた。
(Problem to be solved by the invention) The conventional reinforcing bar assembly) R, I method was carried out using the following method, so workers had to adjust the tension of the frame-shaped stirrups mutually and hold them at a high place. Not only is there a danger of being blown away, but the force (l)
:'IG also causes fatigue to the workers.1-<, also,
It takes skill to tie up the hoop while keeping it at the pitch mark,
However, it is complicated and time-consuming because it involves descending ν1 onto the leg 1γ and marking the pitch several times, which poses serious problems in terms of work efficiency and safety.

この発明は、叙トの1τ情に鑑みてなされたちので・、
作業者数も少く、そのうえ初心渚にb安全8鋳、かつ迅
速に実施1)−ることかてきるたけてなく疲労も少い組
I″L[法を提供してこれらの問題点を解決コ「ること
をI]的としだものである。
This invention was made in consideration of the 1st sentiment of the writer...
The number of workers is small, and moreover, it is safe for beginners, and it can be carried out quickly. It is the first thing to do.

〔問題点を解決するための手段〕[Means for solving problems]

この発明は、次の4一層階に(1′I″11“r:する
1、筋にホイストを設置し、該ホイストにより、L筋群
にeめ外挿して準備された所要数の帯筋を連結フックを
介し順々に吊りlxげてずだれ状に屯れFげた後、所要
の帯筋だけ1筋に縛着する組立T法である。
This invention installs a hoist on the following four first-story floors (1'I"11"r: 1), and uses the hoist to prepare the necessary number of stirrups prepared by extrapolating them to the L muscle group. This is the T-assembly method in which the required hoops are tied to one hoop after the hoops are hung one after the other via connecting hooks, and then the hoops are tied down to one hoop.

〔実施例〕〔Example〕

以F、この発明の一実施例を、四角柱1基を組みqてる
場合を例に採り、第1図ないし第6図に基づいて説明す
る。なお、従来例と同一・の部材等は同一の符号を用い
、その説明は省略する。
Hereinafter, one embodiment of the present invention will be described based on FIGS. 1 to 6, taking as an example a case in which one square prism is assembled. Note that the same members and the like as in the conventional example are denoted by the same reference numerals, and their explanations will be omitted.

第1図は、当階分所要数の帯筋2を角形に配置して〃設
したt筋lに沿って吊り上げ終わった状態を示す正面図
て、5は、所要の一対の主筋lに固定された吊りシャフ
ト、6は、該シャフト5のほぼ中心に吊下されたモータ
ブロック型のホイスト、7は、該ホイスト6の操作スイ
ッチ、8は、ホイスト6の吊トげ用チェーン、9は、該
チェーン8に係11−され、当階における最上部になる
帯筋2aを引っ掛ける吊りフック9fを有する複数の補
助チェーン、10は、次にF方に位置する帯筋2を吊り
1−げるとともに帯筋2相互の上下間隔を規−1する連
結フックである。なお、8fは、前記吊トげ用チェーン
8の先端に緩衝用のコイルスプリング8Sを介して取り
付けられ、+’+ff記補助チェーン9を係11−する
主フック8fである。(第6図参照) また、吊りシャフト5は、第2図に斜視図を示1−よう
に、棒状の本体5hの中央に、ホイスト6の釣f金」(
6にの移動を制御Fする。対のっば5tが固着されてお
り、かつ、本体5hの両端部に摺動可能に嵌挿された断
面U字形の取付金具5uが一対設けられている。該取付
金具5uの外側面には、T、筋1に挟持固着する取り付
きの主筋締付ねし5Nが、また、取付金34.、5 u
の中央には、本体5hを螺圧して該金具5uの位置決め
をする取手付きの本体締付ネジ5nがそれぞれ具備され
ている。
Figure 1 is a front view showing the state in which the required number of tie bars 2 for the current floor are arranged in a rectangular shape and hoisted along the T-bars L. 5 is fixed to the required pair of main bars L. 6 is a motor block type hoist suspended approximately at the center of the shaft 5; 7 is an operation switch for the hoist 6; 8 is a chain for hoisting the hoist 6; 9 is a A plurality of auxiliary chains 10 are connected to the chain 8 and have hanging hooks 9f for hooking the topmost strap 2a on the current floor, and then hang the strap 2 located in the F direction. Together with this, it is a connecting hook that regulates the vertical distance between the ties 2. Note that 8f is a main hook 8f that is attached to the tip of the hanging chain 8 via a buffering coil spring 8S and that engages the auxiliary chain 9 (11-). (See Fig. 6) In addition, as shown in the perspective view in Fig. 2, the hanging shaft 5 is attached to the hoist 6 at the center of the rod-shaped main body 5h.
Control F to move to 6. A pair of fittings 5t are fixedly attached to the main body 5h, and a pair of fittings 5u having a U-shaped cross section are slidably fitted to both ends of the main body 5h. On the outer surface of the mounting bracket 5u, there are attached main reinforcement tightening screws 5N that are clamped and fixed to the reinforcements 1 and 34. , 5 u
A body tightening screw 5n with a handle is provided at the center of each body for screwing the body 5h to position the metal fitting 5u.

そして、連結フック1oは、第3図に示すように、両端
に帯筋2を係止する 一対のフック10fを形成してお
り、該フック10fの中心間の距離1は、L筋1に設定
したときの帯筋2のピッチpに等しくなるようにしであ
る。
As shown in FIG. 3, the connecting hook 1o forms a pair of hooks 10f at both ends that lock the straps 2, and the distance 1 between the centers of the hooks 10f is set to the L-stripe 1. The pitch is set to be equal to the pitch p of the tie reinforcements 2 when

次に、鉄筋組)γ1法について述へる。Next, we will discuss the γ1 method (for reinforcing bars).

通常、T筋!は、第4図に示すように当階の床F5面に
f設すべき支社の横断面のq、形と相似形て、所要71
−法たけ小さい角形の頂点及び外辺に適当な間隔をもっ
て配置され、800−1300mmの商さに林\γして
設けられている。そこで、rめ枠型に形成された帯筋2
(13mmφ)を所要数(七階梁f丁までの高さ÷p 
) +’+;f述の林9−シた主筋1(25〜19mm
φ)の一群に外挿した後、該1:筋1それぞわに別の主
筋lを溶着により継ぎ足して1−階の梁F2面から所定
の高さに突出した■筋lのmmである鉄筋支柱11を構
成する。
Usually T muscles! As shown in Figure 4, the cross section of the branch office to be installed on F5 of the current floor is q, and the shape is similar to that of the required 71.
- They are arranged at appropriate intervals at the apex and outer edge of a fairly small square, and are arranged in a line with a width of 800-1300 mm. Therefore, the ties 2 formed in an r-frame shape
(13mmφ) to the required number (height to 7th floor beam f ÷ p
) +'+; Main reinforcement 1 (25 to 19 mm)
After extrapolating to a group of φ), 1: Another main reinforcement 1 is added to each of the reinforcements 1 by welding, and the diameter of the ■reinforcement 1 that protrudes from the 1st floor beam F2 surface to a predetermined height is mm. A reinforcing bar column 11 is configured.

次に、に1階の梁F2において、角形の中心に対し対称
の位置にある一対のL筋lを選定し、吊りシャフト5を
、その中央、すなわち 対のつば5tの中央が角形の中
心に位置するように、取付金J1.5 uをそれぞれ1
1f1°記1三筋lに取り付け、T筋締付わし5N及び
本体締付ねじ5nによって固定する。
Next, in the beam F2 on the first floor, select a pair of L beams l located symmetrically with respect to the center of the square, and place the hanging shaft 5 so that its center, that is, the center of the pair of ribs 5t, is at the center of the square. Attach the mounting brackets J1.5 u to 1 each so that
Attach to the 1st three bars l marked 1f1° and secure with the T bar tightening screw 5N and the body tightening screw 5n.

次に、ホイスト6を、釣下金具6kを一対のっぽ5を間
において吊りシャフト5の本体5hに掛11−.するこ
とにより吊り下げ、操作スイッチ7を操作して吊1げ用
チェーン8を屯下し補助チェーン9を降下させ、最上部
になる帯筋2aの所要箇所に吊りフック9f複数を下方
から引っ掛けた後、操作スイッチ7により吊−トげ用チ
ェーン8をわずかに巻き1げて補助チェーン9を釣合よ
く緊張させる。
Next, the hoist 6 is hung on the main body 5h of the hanging shaft 5 with the lower hanging bracket 6k and the pair of tails 5 in between 11-. By operating the operation switch 7, the suspension chain 8 was lowered and the auxiliary chain 9 was lowered, and a plurality of hanging hooks 9f were hooked from below to the required locations of the topmost strap 2a. After that, the operation switch 7 is used to slightly wind the hanging chain 8 and tension the auxiliary chain 9 in a balanced manner.

そして、静かに吊トげ用チェーン8を石きI−げると、
最1一部の帯筋2aは[−昇を始めるので、適当な高さ
において二番11の帯筋2bと最1一部の帯筋2aとを
複数の連結フック10により連結i−る。
Then, when you gently lift the hanging chain 8,
Since the first part of the straps 2a starts to rise, the second and eleventh ties 2b and the first part of the ties 2a are connected by a plurality of connecting hooks 10 at an appropriate height.

以上の動作を順次繰り返して三番1」の帯筋2C1四番
11の帯筋2d・・・・・・と連2n的に吊りl−げて
いけば、最1一部の帯筋2aかF階梁丁Tの高さに達し
たところで全部の帯筋2は、相互に所定の間隔U、すな
わち、所定のピッチpをもってずたれ状に鉄筋支社11
を取り囲んだ状態をI+−する。
By repeating the above operations in sequence and lifting the stirrups 2C, No. 3, No. 11, No. 4, No. 11, the stirrups 2d, etc., in a continuous manner, up to some of the stirrups 2a can be lifted. When the height of the F floor beam T is reached, all the stirrups 2 are staggered at a predetermined distance U, that is, a predetermined pitch p, and the reinforcing bar branches 11
The state surrounding is I+-.

そこで、に1階の梁F2、又は、脚qKを用いて最北部
の帯筋2aを適当の箇所、例えば角形の四隅、あるいは
各辺の中心に相当する主筋1に結束線4により縛着して
鉄筋支柱11の角形を整える。なお、要すれば、適当な
高さに位置した帯筋2を若F選定して主筋1に結束線4
による縛着を施す。
Therefore, using the first floor beam F2 or leg qK, tie the northernmost stirrup 2a to an appropriate location, for example, the four corners of the rectangle or the main reinforcement 1 corresponding to the center of each side, using binding wires 4. to adjust the rectangular shape of the reinforcing bar support 11. In addition, if necessary, select a young F from the tie bars 2 located at an appropriate height and connect the tie wires 4 to the main bars 1.
Apply restraints.

以上により、5階における支柱の鉄筋組立は終了するの
で、ホイスト6の一式と吊りシャフト5を撤去し、次の
上階へ移動して同様の鉄筋組立工法を続行する。
As described above, the reinforcing bar assembly for the columns on the fifth floor is completed, so the set of hoist 6 and the hanging shaft 5 are removed, and the next upper floor is moved to continue the same reinforcing bar assembly method.

なお、本実施例では、四角支柱を対象としたが、丸支柱
や多角支柱に適用することのできることはいうまでもな
い。
In addition, in this embodiment, although the square support was targeted, it goes without saying that it can be applied to a round support or a polygonal support.

また、実験結果によれば、−基の柱帯部組4炸業におい
て、25個の帯筋の場合、3生貝りの熟練作業′lS2
名で従来工法によれば60〜70分を要したに比べ、本
実施例の工法では未熟の作業者2名により30分で済み
、また、30個の帯筋の場合、従来工法の80〜90分
に対し、本実施例工法では40分を要したに過ぎなかっ
た。さらに施工金額を試算したところ2従来の場合、支
柱−基当り結束線代金を含めて5,000〜7,000
円であるに比べ、本実施例では連結フック代金を含めて
2,500〜3,000円(ホイスト一式の初度費は除
外)の実質T ’IF費となっている。
In addition, according to the experimental results, in the case of 25 straps in the 4-stirring work of the base column and belt section, the skilled work of 3 fresh shellfish 'lS2
Compared to the conventional construction method, which required 60 to 70 minutes, the construction method of this embodiment required only 30 minutes by two unskilled workers. Compared to 90 minutes, the construction method of this example required only 40 minutes. Furthermore, when we estimated the construction cost, it was 5,000 to 7,000 in the conventional case, including the cost of binding wires per post and base.
In this example, the actual T'IF cost is 2,500 to 3,000 yen (excluding the initial cost of a complete hoist), including the cost of the connecting hook.

なお、本実施例の工法によれば、未熟の作業者1名でも
1−分に組合−てマ1?ることが\γ1;正されている
In addition, according to the construction method of this embodiment, even one unskilled worker can assemble the machine in one minute. The fact that \γ1; has been corrected.

また、例えば吹抜けのホールなどに用いられる片しく高
い支柱の組Aγに際しては、第6図に示すように、5階
所要の帯筋2仝数を適当な複数群に分けて、各群ごとに
順次吊り上げて帯筋2を鉄筋支柱11に設定する方法も
ある。1j−なわち、第1の・11F筋群21を所定の
最l二位にホイスト6により吊りトげて設定した後、補
助チェーン9を第2群22における最1−位の帯筋22
aに着は替えて+Mf述のr、続きに従って第2の帯筋
群22をずたわ状に市れ下げて吊り1−げ、11j1記
最上位の帯筋22aか、第1の帯筋群21の最ド位の帯
筋21zに所定のピッチ2以内に近接したところていっ
たんホイスト6を停止1ユする。そして、複数本の連結
フックlOを+irf記両帯筋21z、22aの所要箇
所に取り付けた後、ホイスト6を111起動して補助チ
ェーン9を弛め、第2の帯筋群22を第1の帯筋群21
に所定のピッチpをもって連結し、第2の帯筋群22の
所要の帯筋2を1:筋1に結束線4をもって縛1「−4
−ることにより、該第2の帯筋群22を鉄筋支柱11に
設定する。
In addition, for the set Aγ of relatively high supports used in an open-air hall, for example, as shown in Figure 6, the number of tie bars required for the 5th floor is divided into several appropriate groups, and each group is There is also a method of setting the tie bars 2 to the reinforcing bar columns 11 by lifting them one by one. 1j-, that is, the first 11F muscle group 21 is hoisted and set at the predetermined lowest position by the hoist 6, and then the auxiliary chain 9 is attached to the highest position of the hoist 22 in the second group 22.
Switch to step a and proceed to +Mf as described above.Follow the continuation, lower the second stirrup group 22 in a zigzag shape and hang it up. Once the hoist 6 approaches the highest hoist 21z of the group 21 within a predetermined pitch of 2, the hoist 6 is stopped. Then, after attaching the plurality of connecting hooks 1O to the required locations of the +IRF band reinforcements 21z and 22a, the hoist 6 is activated 111 to loosen the auxiliary chain 9, and the second reinforcement group 22 is connected to the first Strap muscle group 21
with a predetermined pitch p, and tie the required straps 2 of the second strap group 22 to the 1:stripe 1 with the binding wire 4 1"-4
- By doing so, the second strap group 22 is set to the reinforcing bar column 11.

以1ニの動作をさらに次の帯筋群に繰返し行うことによ
り長尺の支柱の鉄筋組、′してをすることかできる。
By repeating the above steps 1 and 2 for the next group of reinforcing bars, it is possible to assemble the reinforcing bars for a long column.

したかって、本鉄筋組立工法は、その他煙突などのr1
状、あるいは、打状に類する高層建造物に通用すること
はいうまてもなく、対象物か高けわば高いほとその効果
は大となるものである。
Therefore, this reinforcing bar assembly method is suitable for r1 of other chimneys etc.
Needless to say, it is applicable to high-rise buildings similar to the shape or the shape of a hammer, and the higher the object, the greater the effect.

〔発明の効果〕〔Effect of the invention〕

以ト説明したように、本発明によりば、小ざなホイスト
を吊りシャフトを介して 対の1−筋に取り付け、林立
したIE筋からなる鉄筋支柱にrめ外挿された帯筋を順
次連結フックを介してずたれ状に吊り上げる鉄筋組1γ
工法を提供したため、−々チョークによる主筋へのピッ
チ印を付けることが不要となり、簡便な操作スイッチの
操作だけにより帯筋群をすだれ状に垂下することができ
るので高所作業も著しく誠少し、未熟作業者によっても
実施可能となり、作業人員の減少、作業時間や施工金額
 作業者の疲労などの半減となるばかりか安全性も極め
て向トするなと、数々の顕著な効果か11?られたもの
である。
As explained above, according to the present invention, a small hoist is attached to a pair of reinforcing bars via a hanging shaft, and hooks are used to sequentially connect tie bars extrapolated to reinforcing bars made of a forest of IE bars. Reinforcing bar set 1γ is lifted in a staggered manner through
By providing this construction method, it is no longer necessary to use chalk to mark the pitch of the main reinforcing bars, and the stirrup bars can be hung in the form of a blind just by operating a simple operation switch, making work at heights much easier. It can be carried out even by unskilled workers, and it has many remarkable effects such as reducing the number of workers, halving the work time, construction cost, and worker fatigue, as well as greatly improving safety. It is something that was given.

なお、各帯筋の設定間隔は、連結フックにより現;bl
lするため、見栄えもよい正確なピッチとなり、hI!
I’t j ?Ctの支柱各部の強度も均等化するとい
う利点も有している。
In addition, the setting interval of each stirrup is determined by the connecting hook;
1, resulting in an accurate pitch that looks good, and hI!
I't j? It also has the advantage of equalizing the strength of each part of the Ct support.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は、この発明の一実施例を適用して・117筋8
Tを所定の高さに吊りトげた状態を示すdE而面、第2
図は、吊りシャフトの斜視図、第3図は、連結フックの
側面図、第4図は、5階の床面にL筋か林3γした最初
の状態を示す斜視図、第5図は、鉄筋支柱を構成した状
態を示す正面図、第6図は、芹しく高い支柱の鉄筋支柱
に帯筋の第1群を吊りトげた状態をホイスト関係部材を
拡大して示した斜視図、第7図は、従来の支柱の鉄筋組
17王法による作業状況を示す説明図である。 !・・・・・・・・・主筋 2・・・・・・・・・帯筋 4・・・・・・・・・結束線 5・・・・・・−・・吊りシャフト 6・・・・・・・・・ホイスト 9・・・・・・・・・補助チェーン 10・・・・・・連結フック 11・・・・・・鉄筋支柱 21・・・・・・第1の帯筋群 第7図
FIG. 1 shows 117 lines 8 by applying one embodiment of the present invention.
dE surface showing the state in which T is suspended at a predetermined height, second
The figure is a perspective view of the hanging shaft, Fig. 3 is a side view of the connecting hook, Fig. 4 is a perspective view showing the initial state with L-shaped lines 3γ on the floor of the 5th floor, and Fig. 5 is Fig. 6 is a front view showing the reinforcing bar column in a state in which the reinforcing bar strut is constructed; The figure is an explanatory diagram showing the working situation according to the 17th method of reinforcing bars for conventional columns. !・・・・・・・・・Main reinforcement 2・・・・・・・・・Birth tie 4・・・・・・Binding wire 5・・・・・・−・Hanging shaft 6・・・...Hoist 9 ...Auxiliary chain 10 ...Connection hook 11 ...Reinforcement column 21 ...First band group Figure 7

Claims (1)

【特許請求の範囲】 林立した主筋からなる鉄筋支柱の下部に、予め外挿され
た所要数の枠型に形成した帯筋の少くとも1群以上に対
し、 (1)前記鉄筋支柱の上部に吊りシャフトを介してホイ
ストを取り付ける工程、 (2)該ホイストの補助チェーンを前記帯筋群の最上位
の帯筋に係止する工程、 (3)ホイストにより、前記最上位の帯筋を吊り上げつ
つ複数の連結フックを用い順々に次段の帯筋を連結して
すだれ状に形成しながら吊り上げる工程、 (4)最上位の帯筋が所定の高さに達したところでホイ
ストを停止し、最上位の帯筋及び要すれば所要段の帯筋
を所要の主筋に対して結束線により縛着する工程、 (5)要すれば、次の帯筋群を前述の第1の帯筋群につ
いて実施したと同様の手段によりすだれ状に吊り下げた
後、連結フック複数個をもって連結し、所要の縛着を施
して帯筋を組み付ける工程、(6)要すれば、上述手段
の繰返し実施により、順々に複数の帯筋群を連設する工
程、 (7)帯筋群の組付けが終了してホイスト関係部材■式
を撤去する工程、 以上の工程からなることを特徴とした支柱の鉄筋組立工
法。
[Scope of Claims] For at least one group of tie bars formed in a pre-extrapolated required number of frames at the bottom of a reinforcing bar column consisting of a forest of main bars, (1) at the top of the reinforcing bar column; a step of attaching a hoist via a suspension shaft; (2) a step of locking an auxiliary chain of the hoist to the topmost stirrup of the group of stirrups; (3) a step of lifting the topmost stirrup with the hoist; The process of hoisting by connecting the next level of stirrups one after another using multiple connecting hooks and forming a sash shape; (4) When the topmost stirrup reaches a predetermined height, the hoist is stopped and the hoist is lifted up. Step of tying the upper stirrups and, if necessary, the stirrups of the required steps to the required main reinforcements with binding wires; (5) If necessary, attaching the next stirrup group to the first stirrup group mentioned above; After suspending it in the form of a sash by the same means as carried out, connecting it with a plurality of connecting hooks, applying the required binding, and assembling the ties, (6) If necessary, by repeating the above-mentioned means, A process for sequentially installing a plurality of stirrup groups; (7) A process for removing hoist-related members after the assembly of the stirrup groups is completed. Assembly method.
JP13036386A 1986-06-06 1986-06-06 Construction method for assembling reinforcing bar of support Granted JPS62288268A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13036386A JPS62288268A (en) 1986-06-06 1986-06-06 Construction method for assembling reinforcing bar of support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13036386A JPS62288268A (en) 1986-06-06 1986-06-06 Construction method for assembling reinforcing bar of support

Publications (2)

Publication Number Publication Date
JPS62288268A true JPS62288268A (en) 1987-12-15
JPH0516513B2 JPH0516513B2 (en) 1993-03-04

Family

ID=15032584

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13036386A Granted JPS62288268A (en) 1986-06-06 1986-06-06 Construction method for assembling reinforcing bar of support

Country Status (1)

Country Link
JP (1) JPS62288268A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH077764U (en) * 1993-07-01 1995-02-03 広隆 末吉 Paint tank support device

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4899928A (en) * 1972-03-30 1973-12-17

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4899928A (en) * 1972-03-30 1973-12-17

Also Published As

Publication number Publication date
JPH0516513B2 (en) 1993-03-04

Similar Documents

Publication Publication Date Title
JP6017083B1 (en) Floor slab unit, floor slab construction method, and floor construction method
CN109680951A (en) A kind of assembled architecture Beam-Slab Construction method
JPS62288268A (en) Construction method for assembling reinforcing bar of support
NZ551496A (en) Lifting anchor support formed from two bent wires
CN112012387A (en) Construction process for beam slab joint of prefabricated concrete structure and portable stirrup bender
JPH0444568A (en) Hanging of reinforced steel rods and its device
CN211369560U (en) Novel cloth beam stirrup device
CN216076227U (en) Inverted V-shaped inserted hanging basket support system
JP3053847U (en) Rebar assembly equipment
CN109403548A (en) The method for assembling column tie-bar
JPS6022052Y2 (en) Rebar hanging equipment
CN210763896U (en) Inner ring opening string beam hoisting structure
CN109577632B (en) Suspended scaffold and construction method thereof
EP0874097A2 (en) Lifting chair and method of lifting
JP2507594Y2 (en) Lifting jig for pillar rebar unit
JP2000170376A (en) Temporary work method for work scaffolding for tower- shaped structure
JP3084325U (en) Concrete pole reinforcement
CN113846792A (en) Workshop steel structure roof, hoisting device and hoisting method thereof
AU2006241317B2 (en) Lifting anchor support
CN115627872A (en) Large antique algae well and construction method thereof
JP2023008193A (en) Method for constructing reinforcement unit for reinforcing concrete member
KR20200052783A (en) Rebar assembly
JP2599368Y2 (en) Column rebar lifting jig
JPH05171807A (en) Assembling method of underground-girder reinforcement
JPH0718841A (en) Method for assembling scaffold and assembling stand used therein