JPS62215743A - Method for constructing housing - Google Patents

Method for constructing housing

Info

Publication number
JPS62215743A
JPS62215743A JP5756486A JP5756486A JPS62215743A JP S62215743 A JPS62215743 A JP S62215743A JP 5756486 A JP5756486 A JP 5756486A JP 5756486 A JP5756486 A JP 5756486A JP S62215743 A JPS62215743 A JP S62215743A
Authority
JP
Japan
Prior art keywords
frame
scaffold
assembly
constructing
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5756486A
Other languages
Japanese (ja)
Inventor
信之 黒柳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
National House Industrial Co Ltd
Original Assignee
National House Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by National House Industrial Co Ltd filed Critical National House Industrial Co Ltd
Priority to JP5756486A priority Critical patent/JPS62215743A/en
Publication of JPS62215743A publication Critical patent/JPS62215743A/en
Pending legal-status Critical Current

Links

Landscapes

  • Cable Accessories (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔技術分野〕 この発明は、住宅やその他の建物の骨組みとなる架構体
を構築する架構体構築方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Technical Field] The present invention relates to a method for constructing a frame that serves as the frame of a house or other building.

〔背景技術〕[Background technology]

従来、架構体は、下から上へ組上げて行(方法が謀られ
ている。
Conventionally, frames are assembled from the bottom to the top.

しかし、その場合、架構体の全周に足場を必要とし、狭
小地では足場を組めないことがある。また、間口の狭い
場所では必要位置への材料の搬入に手間がかかり、施工
能率が悪い。
However, in this case, scaffolding is required all around the frame, and it may not be possible to set up scaffolding in narrow spaces. In addition, in spaces with narrow openings, it takes time and effort to carry materials to the required locations, resulting in poor construction efficiency.

〔発明の目的〕[Purpose of the invention]

この発明は、間口等の狭い狭小地でも能率良く構築が行
なえる架構体構築方法を提供することを目的とする。
An object of the present invention is to provide a method for constructing a frame structure that can be constructed efficiently even in a narrow space such as a narrow frontage.

〔発明の開示〕[Disclosure of the invention]

この発明の架構体構築方法は、架構体構築場所に基礎を
構築する工程と、前記架構体構築場所の一端に足場を構
築する工程と、wti体の前記足場から離れた部分とな
る架構体部分組立体を前記足場の近傍で組立てる工程と
、この組立てた架構体部分組立体を据付位置まで前記基
礎上で移動させる工程と、この移動させた架構体部分組
立体を前記基礎に据付ける工程と、前記架構体部分組立
体の組立て、移動、および据付けを繰り返す工程とを含
む方法である。
The method for constructing a frame according to the present invention includes a step of constructing a foundation at a frame construction site, a step of constructing a scaffold at one end of the frame construction site, and a portion of the frame remote from the scaffold of the wti body. a step of assembling the assembly near the scaffold; a step of moving the assembled frame subassembly to an installation position on the foundation; and a step of installing the moved frame subassembly on the foundation. , repeating the steps of assembling, moving, and installing the frame subassembly.

この発明の方法によると、架構体構築場所の一端に足場
を構築し、この足場で架構体部分組立体を順次組立てて
据付位置へ移動させるので、足場を架構体構築場所の全
体に設ける必要がなく、狭小地であっても施工が行なえ
る。また、間口部分で架構体部分組立体を構築し、この
際に足場を利用して構築できるので、クレーン等の大が
かりな設備を架構体構築場所の奥部に配置しなくても施
工できる。したがって間口の狭い場所でも施工できる。
According to the method of this invention, a scaffold is constructed at one end of the frame construction site, and the frame subassemblies are sequentially assembled using this scaffold and moved to the installation position, so there is no need to provide scaffolding throughout the frame construction site. Therefore, construction can be carried out even in narrow spaces. In addition, since the frame partial assembly can be constructed at the frontage area and scaffolding can be used at this time, construction can be performed without placing large-scale equipment such as a crane in the inner part of the frame construction site. Therefore, it can be installed even in narrow spaces.

さらに、同じ足場を利用して各架構体部分組立体を組立
てるので、能率良く組立てが行“なえ、施工性が向上す
る。
Furthermore, since each frame subassembly is assembled using the same scaffolding, assembly can be performed efficiently and construction efficiency is improved.

実施例 この発明の一実施例を第1図および第2図に基づいて説
明する。この架構体構築方法は、架構体構築場所lに基
EjI2を構築する工程と、架構体構築場所lの一端に
足場3を構築する工程と、架構体4の足場3から離れた
部分となる架構体部分組立体4aを足場3の近傍で組立
てる工程と、この組立てた架構体部分組立体4a’l据
付位置まで基PJ2上で移動させる工程と、この移動さ
せた架構体部分組立体4aを基礎2に据付ける工程と、
架構体部分組立体4bの組立て、移動、および据付けを
繰り返す工程とを含む方法である。架構体4は、例えば
2階建以上の住宅の骨組み等となるものである。
Embodiment An embodiment of the present invention will be explained based on FIGS. 1 and 2. This method of constructing a frame consists of a step of constructing a base EjI2 at a frame construction location l, a step of constructing a scaffold 3 at one end of the frame construction location l, and a step of constructing a scaffold 3 at one end of the frame construction location l, and a step of constructing a scaffold 3 at a part of the frame construction 4 that is remote from the scaffold 3. A step of assembling the body part assembly 4a near the scaffold 3, a step of moving the assembled frame part assembly 4a'l on the base PJ2 to the installation position, and a step of moving the moved frame part assembly 4a to the base PJ2. 2. The process of installing the
This method includes the steps of repeatedly assembling, moving, and installing the frame partial assembly 4b. The frame body 4 is, for example, the frame of a two-story or higher house.

足場3は、基礎2の外側を囲んで平面形状コ字形に構築
してあり、垂直材と水平材と斜材とで骨組みを組立て、
足場板を掛は渡す0足場3には組立てに必要な工具やウ
ィンチ等の設備を備えておく。
The scaffolding 3 is constructed in a U-shape in plan surrounding the outside of the foundation 2, and the frame is assembled with vertical members, horizontal members, and diagonal members.
Scaffolding board 3 is equipped with tools and winches necessary for assembly.

構築方法をさらに詳細に説明する。まず、架構体4の最
も奥側の外壁となる架構体部分組立体4aを、足場3の
位置で組立てる(第2図(A) )。
The construction method will be explained in more detail. First, the frame partial assembly 4a, which will be the innermost outer wall of the frame 4, is assembled at the position of the scaffold 3 (FIG. 2(A)).

架構体部分組立体4aは柱と梁を組立てたものであり、
最上階の部分まで組立てる。この場合に、基礎2上で移
動させるための運搬治具5−ヒで組立てる。運搬治具5
は、台車として構成したものであり、かつ架構体部分組
立体4aの柱を直立状態で着脱自在に保持する保持手段
を備えている。架構体部分組立体4aの組立てが完了す
ると、第2図(B)のように基礎2上を運搬治具5で移
動させる。据付位置に達すると、架構体部分組立体4a
の柱の下端を基礎2のアンカーボルト等に据付ける。こ
の場合、接合金具等を予じめアンカーボルトに取付けて
おき、この接合金具に柱を据付けてもよい。この接合が
完了すると、架構体部分組立体4aから運搬治具5を取
外す。
The frame partial assembly 4a is an assembly of columns and beams,
Assemble up to the top floor. In this case, it is assembled using a transportation jig 5-H for moving on the foundation 2. Transport jig 5
is constructed as a truck, and is provided with holding means for detachably holding the columns of the frame partial assembly 4a in an upright state. When the assembly of the frame partial assembly 4a is completed, it is moved on the foundation 2 using the transportation jig 5 as shown in FIG. 2(B). When the installation position is reached, the frame subassembly 4a
Install the lower end of the column to the anchor bolt etc. of foundation 2. In this case, a joining fitting or the like may be attached to the anchor bolt in advance, and the pillar may be installed on this joining fitting. When this joining is completed, the transport jig 5 is removed from the frame partial assembly 4a.

つぎに、隣りの架構体部分組立体4bを、第2図(C)
のように足場3で前記と同様に組立てる。
Next, remove the adjacent frame partial assembly 4b as shown in FIG. 2(C).
Assemble in the same manner as above using scaffolding 3.

この架構体部分組立体4bは、架構体4の奥行方向の梁
を有するものである6組立完了後、前記と同様に架構体
部分組立体4bを基礎2上で運搬治具5により据付位置
までi!liする。そして、この運搬した架構体部分組
立体4bを、先に掬付けた架構体部分組立体4aに接合
し、かつ基ii!2に据付け、据付けの完了後に運搬治
具5を取外す、この工程を繰り返して順次奥側から架構
体4を構築する。
This frame subassembly 4b has a beam extending in the depth direction of the frame 4.6 After assembly is completed, the frame subassembly 4b is moved onto the foundation 2 by the transport jig 5 to the installation position in the same manner as described above. i! Lie. Then, this transported frame partial assembly 4b is joined to the previously scooped frame partial assembly 4a, and base ii! 2, and after the installation is completed, the transport jig 5 is removed.This process is repeated to construct the frame body 4 sequentially from the back side.

このようにして構築を行なうが、この方法によると、架
構体構築場所1の一端に足場3を構築し、この足場3で
架構体部分組立体4a、4bを順次組立てて据付位置へ
移動させるので、足場3を架構体構築場所1の全体に設
ける必要がなく、狭小地であっても施工が行なえる。ま
た、間口部分で架構体部分組立体4a、4bを構築し、
この際に足場を利用して構築できるので、クレーン等の
大がかかりな設備を架構体構築場所の奥部に配置しなく
ても施工でき、したがって間口の狭い場所でも施工でき
る。さらに、同じ足場を利用して各架構体部分組立体4
a、4bを組立てるので、集約的な作業が行なえて能率
良く組立てが行なえ、施工性が向上する。
Construction is carried out in this manner. According to this method, a scaffold 3 is constructed at one end of the frame construction site 1, and the frame subassemblies 4a and 4b are sequentially assembled using this scaffold 3 and moved to the installation position. There is no need to provide scaffolding 3 throughout the frame construction site 1, and construction can be carried out even in narrow spaces. In addition, frame partial assemblies 4a and 4b are constructed at the frontage part,
Since the structure can be constructed using scaffolding, the structure can be constructed without placing large-scale equipment such as a crane deep inside the frame construction site, and therefore construction can be carried out even in narrow spaces. Furthermore, each frame subassembly 4 was assembled using the same scaffolding.
Since parts a and 4b are assembled, intensive work can be performed and assembly can be carried out efficiently, improving workability.

なお、前記実施例では架構体部分組立体4a。In addition, in the above embodiment, the frame partial assembly 4a.

4bの相互の接合を、据付位置への移動の都度行ったが
、全ての架構体部分組立体4a、4bの移動完了後に相
互の接合を行ってもよい。
4b are joined to each other each time they are moved to the installation position, but they may be joined to each other after all frame subassemblies 4a, 4b have been moved.

〔発明の効果〕〔Effect of the invention〕

この発明の架構体構築方法は、架構体構築場所の一端に
足場を構築し、この足場で架構体部分組立体を順次組立
てて据付位置へ移動させるので、足場を架構体構築場所
の全体に設ける必要がなく、狭小地であっても施工が行
なえる。また、間口部分で架構体部分組立体を構築し、
この際に足場を利用して構築できるので、クレーン等の
大がかりな設備を架構体構築場所の奥部に配置しなくて
も施工できる。したがって間口の狭い場所でも施工でき
る。さらに、同じ足場を利用して各架構体部分組立体を
組立てるので、能率良く組立てが行なえ、施工性が向上
するという効果がある。
In the frame construction method of the present invention, a scaffold is constructed at one end of the frame construction site, and the frame subassemblies are sequentially assembled on this scaffold and moved to the installation position, so the scaffold is provided throughout the frame construction site. There is no need for it, and construction can be carried out even in narrow spaces. In addition, a frame partial assembly is constructed in the frontage area,
At this time, the structure can be constructed using scaffolding, so construction can be performed without placing large-scale equipment such as a crane deep inside the frame construction site. Therefore, it can be installed even in narrow spaces. Furthermore, since each frame subassembly is assembled using the same scaffolding, assembly can be carried out efficiently and construction efficiency is improved.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の一実施例の斜視図、第2図はその工
程説明図である。 l・・・架構体構築場所、2・・・基礎、3・・・足場
、4・・・架構体、4a、4b・・・架構体部分組立体
、5・・・運搬治具 第1図
FIG. 1 is a perspective view of an embodiment of the present invention, and FIG. 2 is an explanatory diagram of its process. l... Frame construction location, 2... Foundation, 3... Scaffolding, 4... Frame, 4a, 4b... Frame partial assembly, 5... Transportation jig Fig. 1

Claims (1)

【特許請求の範囲】[Claims] 架構体構築場所に基礎を構築する工程と、前記架構体構
築場所の一端に足場を構築する工程と、架構体の前記足
場から離れた部分となる架構体部分組立体を前記足場の
近傍で組立てる工程と、この組立てた架構体部分組立体
を据付位置まで前記基礎上で移動させる工程と、この移
動させた架構体部分組立体を前記基礎に据付ける工程と
、前記架構体部分組立体の組立て、移動、および据付け
を繰り返す工程とを含む架構体構築方法。
a step of constructing a foundation at the frame construction site; a step of constructing a scaffold at one end of the frame construction site; and a step of assembling a frame subassembly that is a part of the frame away from the scaffold near the scaffold. a step of moving the assembled frame subassembly to an installation position on the foundation; a step of installing the moved frame subassembly on the foundation; and assembling the frame subassembly. , movement, and installation.
JP5756486A 1986-03-14 1986-03-14 Method for constructing housing Pending JPS62215743A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5756486A JPS62215743A (en) 1986-03-14 1986-03-14 Method for constructing housing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5756486A JPS62215743A (en) 1986-03-14 1986-03-14 Method for constructing housing

Publications (1)

Publication Number Publication Date
JPS62215743A true JPS62215743A (en) 1987-09-22

Family

ID=13059328

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5756486A Pending JPS62215743A (en) 1986-03-14 1986-03-14 Method for constructing housing

Country Status (1)

Country Link
JP (1) JPS62215743A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5676724B1 (en) * 2013-11-15 2015-02-25 株式会社 秀光ビルド Construction method and building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5676724B1 (en) * 2013-11-15 2015-02-25 株式会社 秀光ビルド Construction method and building

Similar Documents

Publication Publication Date Title
JPS62215743A (en) Method for constructing housing
JP3360843B2 (en) Soundproof panel assembling method using pillars for assembling soundproof panels in prefabricated soundproof building
JP2003269010A (en) Column-beam joint part fitted with base isolation device
JP2618567B2 (en) Construction method of unit building
JPH0238996Y2 (en)
JP2607710B2 (en) Unit house
JPS62215744A (en) Method for constructing housing
JPH05163773A (en) Execution method of building
JP3046779B2 (en) How to build a house
FR2719616A1 (en) Standardised metal frame for houses and other buildings up to two storeys high
JP2515467Y2 (en) Roof unit assembly and transportation jig
JPH0334534B2 (en)
JPH028027Y2 (en)
JP2878006B2 (en) Exterior wall construction method
JPS61126244A (en) Production of house unit
JP3877422B2 (en) Manufacturing method of auxiliary unit for building
JPH05148904A (en) Structure of multi-storied building
JP2000144921A (en) Connecting structure and connecting method of building unit
JPS5924040A (en) Building structure
JPH06346517A (en) Unit type building
JPH0642058A (en) Building unit
JPH03286056A (en) Executing method for unit house
JPH0791070A (en) Fitting structure of fasteneer for vertical furring strips
JPS6259766A (en) Method for disassembling building
JPH06257228A (en) Building unit