JPS62160374A - Construction of iron plate concrete silo - Google Patents

Construction of iron plate concrete silo

Info

Publication number
JPS62160374A
JPS62160374A JP29799785A JP29799785A JPS62160374A JP S62160374 A JPS62160374 A JP S62160374A JP 29799785 A JP29799785 A JP 29799785A JP 29799785 A JP29799785 A JP 29799785A JP S62160374 A JPS62160374 A JP S62160374A
Authority
JP
Japan
Prior art keywords
steel plate
iron plate
concrete
construction
silo
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP29799785A
Other languages
Japanese (ja)
Other versions
JPH0665831B2 (en
Inventor
萩原 忠治
勝彦 斉藤
中山 昭郎
秀樹 野本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP60297997A priority Critical patent/JPH0665831B2/en
Publication of JPS62160374A publication Critical patent/JPS62160374A/en
Publication of JPH0665831B2 publication Critical patent/JPH0665831B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Storage Of Harvested Produce (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 産業上の利用分野 この発明は、鉄板筒体の外周にコンクリートを打設し被
覆して成り、輸入穀物類貯蔵用として好ましい構造であ
る鉄板コンクリートサイロを、改良した滑動型枠装置(
スライド装置)によりスライディングフオーム工法とし
て構築する工法に関する。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application The present invention is a steel plate concrete silo, which is made by pouring and covering the outer periphery of a steel plate cylindrical body and is a preferred structure for storing imported grains. Formwork equipment (
This invention relates to a construction method using a sliding form construction method (sliding device).

従来の技術 従来、鉄板コンクリートサイロの構築工法としては、 ■コンクリートの“吹付工法(特開昭57−17807
0号公報)。
Conventional technology Conventionally, the construction methods for steel plate concrete silos include: ■Concrete “spraying method” (Japanese Patent Application Laid-Open No. 57-17807
Publication No. 0).

■鉄板筒体にクライミングの反力をとって段階的にスラ
イドするセルフクライミング工法(特公昭52−197
02号、特公昭80−26!111号公報)。
■Self-climbing method in which a steel plate cylinder takes the reaction force of climbing and slides step by step (Special Publication No. 52-197)
No. 02, Special Publication No. 80-26!111).

■鉄板コンクリートサイロ合rk、Pc板を使用したプ
レハブ工法(特公昭!i?−50230号)などが公知
である。
■Prefabricated construction methods using iron plate concrete silo rk and PC boards (Special Publication Sho!i?-50230) are well known.

■また。いわゆるスライディングフオーム工法によるサ
オ石構築工法も公知に屈する(時分59−33746号
公報)。但し、これにより構築されたサイロには鉄板筒
体がない。
■Also. The so-called sliding form construction method for constructing stone is also known (Hibun No. 59-33746). However, the silo constructed using this method does not have an iron plate cylinder.

発明が解決しようとする問題点 従来の上記■〜■に記述した構築工法は、スライディン
グフオーム工法に比較してコンクリート打継面がコール
ドジヨイントとなり、気密性が悪いし、施工が非連続的
なので能率が悪い。
Problems to be Solved by the Invention Compared to the sliding form construction method, the conventional construction methods described in ■ to ■ above have cold joints on the concrete pouring surface, poor airtightness, and discontinuous construction. Poor efficiency.

また、鉄板筒体にクライミングの反力をとる構成のため
サイロ内側に内側ステージが不可欠であり、このため大
損りな施工装置になるという問題点があった。
In addition, since the iron plate cylinder is configured to absorb the reaction force of climbing, an inner stage is essential inside the silo, which poses the problem of resulting in a costly construction device.

また、上記■の場合は、ヨークが存在するため鉄板筒体
を建込むことは不可能で、鉄板コンクリートサイロの構
築はできないという問題点があった。
In addition, in the case of (2) above, there was a problem that it was impossible to erect a steel plate cylinder due to the presence of a yoke, and therefore a steel plate concrete silo could not be constructed.

問題点を解決するための手段 上記従来技術の問題点を解決するための手段として、こ
の発明に係る鉄板コンクリートサイロの構築工法は、図
面の第1図〜第9図に好適な実施例を示したとおり、 (イ) まず、工場等で製作されたモジュール鉄板(1
′)に基き現地の地上において鉄板筒体(1)を揚重可
能な大きさに地組みする。と同時に、この段階で該鉄板
筒体(1)の外周面の軸線方向にスライドガイド(2)
を取付け、またスタッドを取付ける。
Means for Solving the Problems As a means for solving the problems of the prior art described above, a method for constructing a steel plate concrete silo according to the present invention is shown in preferred embodiments in FIGS. 1 to 9 of the drawings. (a) First, the module iron plate (1
′), the steel plate cylinder (1) is assembled on the ground at the site to a size that allows it to be lifted. At the same time, at this stage, the slide guide (2) is moved in the axial direction of the outer peripheral surface of the iron plate cylinder (1).
and then install the studs.

(ロ) 次に、前記鉄板筒体(1)を揚重し建込んで鉄
板筒体構造物を構築する。
(b) Next, the iron plate cylindrical body (1) is lifted and erected to construct an iron plate cylindrical body structure.

(ハ) つづいて、鉄板筒体構造物(1)の外周に壁配
筋を設はし、また前記スライドガイド(2)に沿って昇
るスライド装M(3)を設置する。
(c) Next, wall reinforcement is installed around the outer periphery of the iron plate cylindrical structure (1), and a slide device M (3) that goes up along the slide guide (2) is installed.

(ニ) そして、前記スライド装置(3)を上昇させ、
該スライド装置(3)に支持されたせき板(4)と鉄板
筒体構造物(1)との間にコンクリート(10)を打設
すると共に、以下同様の工程をくり返して連続的に施工
することとした。
(d) Then, raise the slide device (3),
Concrete (10) is poured between the weir plate (4) supported by the slide device (3) and the steel plate cylindrical structure (1), and the same steps are repeated to continuously construct the concrete. I decided to do so.

作     用 スライド装と3は、所謂スライディングフオーム工法の
型枠滑動装置に相当するものであるが、スライドガイド
2につかまって外方への転倒に対する反力をとり上昇す
る構成であり、鉄板筒体1をその半径方向の内外方に横
切るヨークを持たない構造に改良されている。このため
、鉄板筒体1の建込みは何時でも自由に出来る。
The slide device 3 corresponds to the so-called formwork sliding device of the sliding form construction method, and is configured to hold onto the slide guide 2 and rise by absorbing the reaction force against falling outward. The structure has been improved so that it does not have a yoke that crosses 1 in the radial direction inside and out. Therefore, the steel plate cylinder 1 can be built freely at any time.

従って、前記スライド装置3でせき板4を連続的にせり
上げながらコンクリ−)10の打設をし、他方、鉄板筒
体1の建込み及び壁配筋等は予め必要な高さまで先行し
て行ない連続的施工に備える。
Therefore, the concrete 10 is poured while continuously raising the weir plate 4 with the slide device 3, and on the other hand, the erection of the steel plate cylinder 1 and wall reinforcement etc. are carried out in advance to the required height. Prepare for continuous construction.

よって、この発明の構築工法は1通常のスライディング
フオーム工法と全く同様にコンクリートの打継ぎ(コー
ルドジヨイント)は生じさせないで、気密性の良い高品
質のコンクリート打設が出来るし、その上連続的施工が
行なえるので能率が良いのである。
Therefore, the construction method of the present invention is capable of pouring high-quality concrete with good airtightness without creating cold joints in the same manner as the normal sliding form construction method; It is efficient because construction can be done easily.

実   施   例 次に、図示したこの発明の好適な実施例を説明する。Example Next, a preferred embodiment of the invention illustrated in the drawings will be described.

ま−? 、第1図Aは工場製作等されたモジュール鉄板
1′を示し、第1図B、Cは同モジュール鉄板1′を使
って現地の地上で地組みされた鉄板筒体1を示している
・ モジュール鉄板1′は、例えば%円弧のものとし、高さ
hは1.2m〜2.4m位に製作する。
Ma-? , Fig. 1A shows a module steel plate 1' manufactured in a factory, etc., and Fig. 1B and C show a steel plate cylindrical body 1 assembled on the ground at the site using the same module steel plate 1'. The module iron plate 1' is made, for example, in the shape of a circular arc, and has a height h of about 1.2 m to 2.4 m.

このモジュール鉄板1′を4個突合せ溶接して鉄板筒体
1が組立てられる。
The iron plate cylinder body 1 is assembled by butt welding four of the module iron plates 1'.

なお、第1図Cは、上述のようにして組立てた鉄板筒体
1を2個(但し、2個の限りではなく、クレーン等によ
る揚重可能な大きさ、重量であれば可)viみ重ねてそ
の突合せ部を円周溶接すると共に、外周面の軸方向にス
ライドガイド2・・・を取付けたユニットとして地組み
されたものを示している。鉄板とコンクリートとの一体
化を図るスタッド(図示省略)も、この段階までに鉄板
筒体1の外周面に突設される。
In addition, Fig. 1C shows two iron plate cylinders 1 assembled as described above (however, the number is not limited to two, and any size and weight that can be lifted by a crane etc. is acceptable). The abutting portions are overlapped and circumferentially welded, and a slide guide 2 is attached in the axial direction of the outer circumferential surface, and is assembled into a unit. Studs (not shown) for integrating the steel plate and concrete are also provided protruding from the outer peripheral surface of the steel plate cylinder 1 by this stage.

スライドガイド2は、第4図に示した如く横断面がH形
のレール材であり、これは1台のヨークにつき2木を一
組として軸線方向平行に取付けろれている、また、この
スライドガイド2は、1本当りの長さを50cm位のも
のとし、第4図と第5図に示した如く鉄板1の外周面に
ポルト13、ナツト14により着脱可能に取付けられて
いる。
The slide guide 2 is a rail material with an H-shaped cross section as shown in FIG. Each guide 2 has a length of about 50 cm, and is removably attached to the outer peripheral surface of the iron plate 1 with a port 13 and a nut 14, as shown in FIGS. 4 and 5.

ちなみに1木のサイロ(直径7m〜9m位のもの)につ
きスライド装置は円周を等分して12台ぐらい使用して
せき板4をスライドさせるので、スライドガイド2はこ
れに必要な組数だけ鉄板筒体1の外周に取付けられてい
る。
By the way, for one wooden silo (about 7m to 9m in diameter), about 12 slide devices are used to slide the weir plate 4 by dividing the circumference equally, so there are only as many sets of slide guides 2 as are necessary for this purpose. It is attached to the outer periphery of the iron plate cylindrical body 1.

第2図は、第1図Cの如くユニットとして地組みした鉄
板筒体1をクレーン等で吊り積み重ねて建込む段階を示
している。吊り込んだ鉄板筒体1は、積み正ね部を円周
方向に突き合せ溶接して一体化し順次鉄板筒体構造物と
して構築される。
FIG. 2 shows a stage in which the steel plate cylinders 1 assembled into the ground as a unit as shown in FIG. 1C are suspended and piled up using a crane or the like. The suspended iron plate cylindrical body 1 is integrated by butt-welding the stacked stacked portions in the circumferential direction, and is successively constructed as an iron plate cylindrical body structure.

ff13図Aは、上述の如くして所要の高さまで構築し
た鉄板筒体構造物1の外周に、スライドガイド2に沿っ
て昇るスライド装置3を設置し、これにせき板4を取付
けた段階を示している。
ff13 Figure A shows a stage in which a slide device 3 that ascends along a slide guide 2 is installed on the outer periphery of the iron plate cylindrical structure 1 constructed to the required height as described above, and a weir plate 4 is attached to this. It shows.

スライド装置3の構造詳細は、第4図と第5図に示した
とおり、内端部にスライドガイド2の溝に沿って転がる
ローラ5をもつヨーク6と、このヨーク6に取付は固定
したタライミシグジャッキ8とより成る。クライミング
ジヤツキ8は、予め立てられたロッド7を伝って所謂尺
取り虫のように登る構成である。ヨーク6の脚部下方の
内側に腹起し9を取付け、該腹起し9の内側にせき板4
が設置されている。せき板4の高さ寸法は通常100c
m位である。
As shown in FIGS. 4 and 5, the details of the structure of the slide device 3 include a yoke 6 having a roller 5 at its inner end that rolls along the groove of the slide guide 2, and a fixed tab attached to the yoke 6. Consists of Raimisig Jack 8. The climbing jack 8 is configured to climb like a so-called inchworm along a rod 7 erected in advance. A belly riser 9 is attached to the inside of the lower part of the leg of the yoke 6, and a weir plate 4 is attached to the inside of the belly riser 9.
is installed. The height of the weir plate 4 is usually 100c.
It is rank m.

第3図Bは、鉄板筒体構造物1とせき板4との間に壁鉄
筋(図示省略)を設置し、第1段階のコンクリート10
を打設した段階を示している。また、第3図C,Dはス
ライド装置3を例えば毎分当り20cm位の速度で上昇
させ、コンクリート打設が進められつつある段階を示し
ている。コンクリートの壁厚は200〜2501位であ
る。
FIG. 3B shows wall reinforcing bars (not shown) installed between the steel plate cylindrical structure 1 and the sheathing plate 4, and the concrete 10 in the first stage.
This shows the stage at which the concrete was poured. Further, FIGS. 3C and 3D show a stage in which the slide device 3 is raised at a speed of, for example, about 20 cm per minute, and concrete placement is progressing. The concrete wall thickness is about 200-2501.

第3図り中11は打設されたコンクリート壁表面の後仕
上げ用としてスライド装置3から吊下げた作業足場であ
る。また、第5図中12はスライド装置3のための作業
床である。
11 in the third diagram is a work scaffold suspended from the slide device 3 for finishing the surface of the poured concrete wall. Further, numeral 12 in FIG. 5 is a working floor for the slide device 3.

なお、スライド装置3が通過して無用となったスライド
ガイド2は、そのままコンクリート壁中に埋設しても良
いが、出来るだけポルト13、ナツト14をゆるめて取
外し、転用する。このために、スライドガイド2の1本
当りの長さは50cm位としているのである。
The slide guide 2, which has become useless after the slide device 3 has passed through it, may be buried in the concrete wall as it is, but it is removed by loosening the ports 13 and nuts 14 as much as possible and reusing it. For this reason, the length of each slide guide 2 is approximately 50 cm.

以下、スライド装置3の上昇を連続させてコンクリート
打設を一連的に行ない、他方、必要に応じて鉄板筒体l
の建込みと壁鉄筋を設置する工程をくり返して行ない、
所要高さの鉄板コンクリートサイロを完成するのである
Thereafter, the slide device 3 is raised continuously to perform concrete pouring, and the steel plate cylinder l is placed as needed.
The process of constructing the building and installing wall reinforcing bars was repeated.
A steel plate concrete silo of the required height was completed.

第6図はこの発明の構築方法で構築したサイロ群の平面
図を示している。出来れば全サイロの構築を同時に行な
うも良し、あるいはいくつかのグループに分割して施工
することもできる。なお、サイロ外部のサイロで囲まれ
た空間、所謂側ビン15を形成する隔壁16も、サイロ
筒体と合一に構築するのが許通であるが、別途の工事と
して施工しても良い。
FIG. 6 shows a plan view of a group of silos constructed by the construction method of the present invention. If possible, all silos can be constructed at the same time, or they can be divided into several groups. Note that the partition wall 16 forming the so-called side bin 15, which is a space surrounded by the silo outside the silo, is normally constructed integrally with the silo cylinder, but it may be constructed as a separate construction.

第2の実施例 第7図と第8図は、予め所定の高さに構築した鉄板筒体
構造物1の上端にジヤツキ受架台2oを設置し、このジ
ヤツキ受架台20に取付けたジヤツキ8によりロッド7
を介してスライド装置3を引張り上げる。所謂リフトア
ップ工法による施工図を示している。
7 and 8 show a second embodiment in which a jack holder 2o is installed at the upper end of a steel plate cylindrical structure 1 that has been constructed to a predetermined height, and a jack 8 attached to this jack holder 20 is used. rod 7
Pull up the slide device 3 via the . A construction drawing using the so-called lift-up construction method is shown.

本実施例を上記第1実施例のものと比較した場合、スラ
イド装置3がジヤツキを持たない点が異なるのみである
When this embodiment is compared with the first embodiment, the only difference is that the slide device 3 does not have a jerk.

ジヤツキ受架台20は、第9図に示したように、所要数
だけ等配して放射状配置に設置される。
As shown in FIG. 9, the jack receiving racks 20 are installed in a radial arrangement with the required number evenly spaced.

第8図Bは、当初構築した鉄板筒体構造物1の高さの限
度までコンクリート打設を行なった後、ジヤツキ受架台
20を撤去した段階を示している。
FIG. 8B shows a stage in which the jack pedestal 20 has been removed after concrete has been poured to the maximum height of the originally constructed steel plate cylindrical structure 1.

また、第8図Cは次段階の高さまで鉄板筒体構造物1の
構築を進めたところを示している。
Moreover, FIG. 8C shows the progress of construction of the iron plate cylindrical structure 1 to the next level of height.

さらに第8図りは、再び鉄板筒体構造物1の上端にジヤ
ツキ受架台20を設とし、スライド装置3の上昇を再開
してコンクリート打設を行なう段階を示している。以下
同様の工程をくり返して所要高さのサイロを構築するの
である。
Further, the eighth diagram shows a stage in which the jack holder 20 is again installed at the upper end of the steel plate cylindrical structure 1, and the raising of the slide device 3 is resumed to perform concrete pouring. The same process is then repeated to construct a silo of the required height.

発明が奏する効果 以上に実施例と併せて詳述したとおりであって、この発
明に係る鉄板コンクリートサイロの構築工法は、所謂ス
ライディングフオーム工法と全く同様に連続的な施工が
でき、それでいて鉄板筒体1の建込みには一切支障がな
いから、打継ぎがなく気密性の高い鉄板コンクリートの
サイロを極めた能率良く安価に構築できる。
The effects of the invention have been described in detail in conjunction with the examples, and the method of constructing a steel plate concrete silo according to the present invention allows for continuous construction just like the so-called sliding form method, and at the same time, it is possible to construct a steel plate concrete silo using a steel plate cylindrical body. Since there is no problem with the erection of 1, a highly airtight iron plate concrete silo with no pouring joints can be constructed extremely efficiently and at low cost.

また、コンクリート打込み高さは常に10〜20cmで
あるためスランプの少ない高品質のコンクリートを打設
ができるし、バイブレータによる締固め作業が容易であ
るため耐久性の高いコンクリート壁体が得られる。
Furthermore, since the height of concrete pouring is always 10 to 20 cm, high-quality concrete with little slump can be poured, and compaction work using a vibrator is easy, so a highly durable concrete wall can be obtained.

また、在来の大形型わく工法に比して大幅な工期の短縮
が図れるし、労務の平準化が図れるのである。
Additionally, compared to the conventional large frame construction method, the construction period can be significantly shortened and labor costs can be leveled out.

【図面の簡単な説明】[Brief explanation of drawings]

第1図A、B、Cはモジュール鉄板の斜視図とこれによ
り組立てた鉄板筒体の平面図及び斜視図である。第2図
は鉄板筒体の建込み状態を示す立面図、第3図A−Dは
この発明の工法の]二程図、t54図と第5図はスライ
ド装置の平面図と正面図、第6図は構築されたサイロの
平面図、第7図は第2実施例を説明するための立面図、
第8図は同工程図、第9図は鉄板筒体構造物の上端に設
置したジヤツキ受架台の平面図である。
FIGS. 1A, B, and C are a perspective view of a module steel plate, and a plan view and a perspective view of a steel plate cylindrical body assembled using the module steel plate. Fig. 2 is an elevational view showing the construction state of the iron plate cylinder, Fig. 3 A-D is a two-step drawing of the construction method of this invention, Fig. t54 and Fig. 5 are a plan view and a front view of the slide device, FIG. 6 is a plan view of the constructed silo, FIG. 7 is an elevation view for explaining the second embodiment,
FIG. 8 is a process diagram of the process, and FIG. 9 is a plan view of a jack holder installed at the upper end of the iron plate cylindrical structure.

Claims (1)

【特許請求の範囲】 [1](イ)地上にて鉄板筒体(1)を揚重可能な大き
さに地組みにすると共に、該鉄板筒体(1)の外周面の
軸線方向にスライドガイド(2)を組付ける段階と、 (ロ)前記鉄板筒体(1)を揚重し建込む段階と、 (ハ)前記スライドガイド(2)に沿って昇るスライド
装置(3)を設置する段階と、 (ニ)前記スライド装置(3)を上昇させ、該スライド
装置(3)に支持されたせき板(4)と鉄板筒体構造物
(1)との間にコンクリート(10)を打設する段階と
、 から成ることを特徴とする鉄板コンクリートサイロの構
築工法。
[Claims] [1] (a) The iron plate cylinder (1) is assembled on the ground to a size that can be lifted, and the iron plate cylinder (1) is slid in the axial direction of the outer peripheral surface of the iron plate cylinder (1). a step of assembling the guide (2); (b) a step of lifting and erecting the iron plate cylinder (1); and (c) installing a slide device (3) that ascends along the slide guide (2). (d) raising the slide device (3) and pouring concrete (10) between the weir plate (4) supported by the slide device (3) and the steel plate cylindrical structure (1); A method for constructing a steel plate concrete silo, characterized by comprising the steps of setting up a steel plate concrete silo.
JP60297997A 1985-12-30 1985-12-30 Construction method of iron plate concrete silo Expired - Fee Related JPH0665831B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60297997A JPH0665831B2 (en) 1985-12-30 1985-12-30 Construction method of iron plate concrete silo

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60297997A JPH0665831B2 (en) 1985-12-30 1985-12-30 Construction method of iron plate concrete silo

Publications (2)

Publication Number Publication Date
JPS62160374A true JPS62160374A (en) 1987-07-16
JPH0665831B2 JPH0665831B2 (en) 1994-08-24

Family

ID=17853789

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60297997A Expired - Fee Related JPH0665831B2 (en) 1985-12-30 1985-12-30 Construction method of iron plate concrete silo

Country Status (1)

Country Link
JP (1) JPH0665831B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016138368A (en) * 2015-01-26 2016-08-04 株式会社大林組 Slip form device and construction method for cylindrical wall body

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6055175A (en) * 1983-09-01 1985-03-30 日本鋼管株式会社 Construction of composite structural storage tank

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6055175A (en) * 1983-09-01 1985-03-30 日本鋼管株式会社 Construction of composite structural storage tank

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016138368A (en) * 2015-01-26 2016-08-04 株式会社大林組 Slip form device and construction method for cylindrical wall body

Also Published As

Publication number Publication date
JPH0665831B2 (en) 1994-08-24

Similar Documents

Publication Publication Date Title
JPS62160374A (en) Construction of iron plate concrete silo
CN107675876A (en) A kind of slding form operation method
US6082059A (en) Pour and set concrete construction system
JP3137448B2 (en) Construction method of concrete main tower
AU597836B2 (en) Wall casting system
JPH04161566A (en) Constructing apparatus for large space building
JPH01256636A (en) Construction method of building
JPH0681463A (en) Building method for stair
JPS6343333Y2 (en)
JP3192543B2 (en) Building demolition method
JP2684956B2 (en) Steel erection in a structure
US4272465A (en) Method for multi-storied concrete construction and apparatus therefor
JPH08218628A (en) Construction of roof for cylindrical structure
SU853031A1 (en) High-building construction method
SU1263793A1 (en) Method of erecting buildings with prefabricated solid skeleton
JPS62244941A (en) Push-up system construction method
RU2087650C1 (en) House-building combine
JP2591352B2 (en) How to build a building
JP2513376B2 (en) How to build a building
JPH0420471B2 (en)
NL9101940A (en) Method for constructing a multi-storey building, storey parts and accessories to be used in this method, and multi-storey building constructed in this way
JPS60258366A (en) Slide type mold frame apparatus using long leg yoke
JPH0128186Y2 (en)
JPH0571743B2 (en)
JPH03147984A (en) Construction of concrete side wall

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees