JPS62151684A - Method of installing piping - Google Patents

Method of installing piping

Info

Publication number
JPS62151684A
JPS62151684A JP60289382A JP28938285A JPS62151684A JP S62151684 A JPS62151684 A JP S62151684A JP 60289382 A JP60289382 A JP 60289382A JP 28938285 A JP28938285 A JP 28938285A JP S62151684 A JPS62151684 A JP S62151684A
Authority
JP
Japan
Prior art keywords
piping
unit
equipment
installation method
air
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP60289382A
Other languages
Japanese (ja)
Inventor
哲夫 山本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP60289382A priority Critical patent/JPS62151684A/en
Publication of JPS62151684A publication Critical patent/JPS62151684A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin

Landscapes

  • Jet Pumps And Other Pumps (AREA)
  • Pipeline Systems (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の技術分野] 本発明は、原子力発電所等の工業プラントでの配管据付
工事をブランj−建設現場で簡単に施工できる配管据付
方法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to a piping installation method that allows piping installation work in industrial plants such as nuclear power plants to be easily carried out at a construction site.

(発明の技術的前頭どその問題点) 従来より、工場プラント、Biに原子力発電プラン1−
の建設にJ3いて(よ配管裾付工事が工期、コストの両
面において大きなウエートを占めており、それは、現地
組工程の70%近くに達している。
(Problems with the technical front of the invention) Conventionally, nuclear power generation plan 1-
In the construction of J3, pipe hemming work accounts for a large portion of both construction time and cost, accounting for nearly 70% of the on-site assembly process.

このため、建設工期を短縮化するための対やとして早く
から検問されていた。
For this reason, it was inspected from an early stage as a means of shortening the construction period.

また、配管据付工事は、膨大な品であり、部品点数が多
いために現地での管理にも多くの労力が必要とされ、こ
れが、工期を短縮する上での大きなネックとなっている
In addition, piping installation work requires a large amount of work and a large number of parts, so a lot of effort is required for on-site management, which is a major bottleneck in shortening the construction period.

ここで、第5図を参照して従来の現地配管施工手順につ
いて説明する。
Here, a conventional on-site piping construction procedure will be explained with reference to FIG.

施工手順は、先ず、配管施工図、ナボート詳細図に基づ
いて配管・弁用サポート1が設置され、その後、弁2、
プロセス配管3が据付けられる。
In the construction procedure, first, the piping/valve support 1 is installed based on the piping construction drawing and Navoto detailed drawing, and then the valve 2,
Process piping 3 is installed.

次に、空気作動弁(AO弁)4を支持するための1−レ
イ用すボーh 5、計装用空気配管6の据付が施工され
、その施工後に、制御ケーブル用の後打アンカー7、コ
ンジット用ザボート8、電線管9が取付けられる。更に
、計装用導圧管、サンプリング配管が施工され、ポンプ
等の駆動機器、制ti+機器、計器に接続される。
Next, the installation of a 1-lay bow h 5 for supporting the air operated valve (AO valve) 4 and the instrumentation air piping 6 is carried out, and after installation, the post-driving anchor 7 for the control cable and the conduit are installed. The boat 8 and conduit 9 are installed. Furthermore, instrumentation impulse pipes and sampling pipes will be constructed and connected to drive equipment such as pumps, control equipment, and meters.

このような一連の配管据付工事において、プロセス配管
3.jf装用空気配管6、制ね11用ウーブル、計装用
導圧管、サンプリング配管は、それぞれ異なる作業者に
よって工事が行(2われでいる。そのため、作業者1r
Jに丁場の設置、撤去が実施されているのが現状で、ぞ
の結果、工期が非常に長くなり、また、足場の設置等の
小腹した作業ら数多く発生している。
In this series of piping installation work, process piping 3. The air piping 6 for the JF equipment, the Ouvre for the control 11, the instrumentation impulse pipe, and the sampling piping are each constructed by different workers (two workers are required.
The current situation is that the installation and removal of scaffolding is being carried out at J, and as a result, the construction period is extremely long, and there is a lot of tedious work such as setting up scaffolding.

一方、配管施工後では、弁類及び五12:類の単体試験
、溶接部の非破壊検査、更には官庁検査が実施される。
On the other hand, after piping construction, unit tests for valves and Class 512, non-destructive inspections of welded parts, and government inspections are conducted.

ところが、このような試験、検査を現地で実施するには
、作業環境が悪く、その後の品質管理にも余分な工数が
かかり、面倒であった。
However, carrying out such tests and inspections on-site requires an inconvenient work environment, and subsequent quality control requires additional man-hours and is troublesome.

また、前記の空気作動弁4の設置に際しては、それが数
多く設置されていて、しかも、それぞれに付属品が設け
られているので、大きなスペースが必要とされた。すな
わち、第6図に示ずように、空気作動弁4の1個あたり
には、ぞれぞれ、シ1装用空気10のフィルタ11、レ
ギュレータ(減圧器)12、Aイラー13が取付けられ
、制御ケーブル用の端子箱14、リミットスイッチ15
、電磁弁16も設置される。この空気作動弁4のメンテ
ナンススペースを考慮すると、250Aタイプの空気作
動弁4の場合には500a+X500s+程度の余裕寸
法を右するオーブンスペース17が必要となる。このオ
ーブンスペース17はメンテナンスのため必要であるか
ら縮小することはできず、建屋を小形にできない原因の
一つとなることであった。
Furthermore, when installing the air-operated valves 4, a large amount of space is required because a large number of them are installed, and each one is provided with an accessory. That is, as shown in FIG. 6, a filter 11, a regulator (pressure reducer) 12, and an A-filter 13 are attached to each air-operated valve 4, respectively. Terminal box 14 for control cable, limit switch 15
, a solenoid valve 16 is also installed. Considering the maintenance space for this air-operated valve 4, in the case of a 250A type air-operated valve 4, an oven space 17 with a margin of about 500a+X500s+ is required. Since this oven space 17 is necessary for maintenance, it cannot be reduced, and this is one of the reasons why the building cannot be made smaller.

(発明の目的〕 本発明は一ト記事情を考慮してなされたもので、現地で
の配管据付工事に際し必要されるn器類、n器類、配管
類、弁類を架台にユニット化して組込み、これを現地に
UQ人し、外部機器と接続させることで、現地配管工事
の平準化、工期短縮、品質の安定、現地各種試験、検査
の簡易化が可能な配管据付方法を提供することを目的と
する。
(Purpose of the Invention) The present invention has been made in consideration of one particular situation, and is a system for unitizing n devices, n appliances, piping, and valves required for on-site piping installation work on a frame. To provide a piping installation method that can standardize on-site piping work, shorten the construction period, stabilize quality, and simplify various on-site tests and inspections by incorporating it, sending it to the site by UQ personnel, and connecting it to external equipment. With the goal.

〔発明の概凹) 上述した目的達成するため、本発明は、工業プラン1〜
の配管据付方法において、所要の配管類、弁類、計器類
および機器類を架台とともにあらかじめ工場にて配管ユ
ニットとして組立て、この配管ユニットをプラント建設
現場で外部機器との接続を行なうことを特徴とする。
[General outline of the invention] In order to achieve the above-mentioned object, the present invention provides industrial plans 1 to 1.
This piping installation method is characterized by assembling the required piping, valves, instruments, and equipment together with the mount as a piping unit in advance at a factory, and connecting this piping unit to external equipment at the plant construction site. do.

(発明の実施例〕 以下、第1図ないし第4図を参照して本発明に係る配管
据付方法の一実施例を説明する。
(Embodiment of the Invention) Hereinafter, an embodiment of the piping installation method according to the present invention will be described with reference to FIGS. 1 to 4.

第1図、第2図においては、本発明方法での配管ユニッ
ト20、特に床設置タイプのそれにJ:って施工される
場合の例が示されている。
1 and 2, an example is shown in which a piping unit 20 is constructed using the method of the present invention, particularly a floor installation type piping unit 20.

この配管ユニット20は、原子力発電プラントにおいて
必要とされる各種のn器類、計器類、これらへの配管類
、弁類を、可搬可能な架台21とともにあらかじめ工場
にて組立てて得られる。りなわら、架台21には、ポン
プ22等の駆動は器、リミットスイッチ23のような制
御機器、PQFA伝送路24等の計器、各種機器からの
プロレス配管やユーティリティ配管の如き配管25、更
にはこの配管25中での多数の空気作動弁26、手動弁
27その他が既定のり一ポート詳細図、配管施工図をも
とに組込み、配設される。
This piping unit 20 is obtained by assembling various types of instruments, instruments, piping therefor, and valves required in a nuclear power plant together with a transportable pedestal 21 in advance at a factory. In addition, the pedestal 21 includes drive devices such as a pump 22, control devices such as a limit switch 23, meters such as a PQFA transmission line 24, piping 25 such as professional wrestling piping and utility piping from various devices, and furthermore, A large number of air-operated valves 26, manual valves 27, and others in the piping 25 are assembled and arranged based on the predetermined glue port detailed drawings and piping construction drawings.

また、空気作動弁26、各種機器への計装用空気(I△
)を供給づ“る81装川空気配管28、π1装用導圧管
29、サンプリングライン30も配管ユニット20に配
設される。それらの接続部は配管コニッ1−20自体の
端部に設()られた電磁弁ラック31に位置され、外部
の計装ラック32と取合可能にされている。
In addition, air-operated valve 26, instrumentation air (I△
), an 81-channel air pipe 28, a pi-1 pressure impulse pipe 29, and a sampling line 30 are also installed in the piping unit 20. Their connections are installed at the end of the piping unit 1-20 itself (). It is located in a solenoid valve rack 31 that is mounted on a wall, and is connectable to an external instrumentation rack 32.

更に、I’lff記した各種の機器、Jl器、弁への動
力用の電カケープル33、制御用の制御ケーブル34、
これらのケーブル33.34を収納配tlArt’る電
線管も、これらを支持するトレイ等を介して配管ユニッ
ト20に配線される。それらの接続部は配管ユニット2
0自他の端部に設けられた集中化した電力端子箱35、
制御端子箱36に位置され、外部電源、外部制御盤との
接続工事は、これらの端子t83536でのみ行なわれ
るようになっている。このように、ケーブル33.34
を端子箱35.36で外部と取合い、接続させることで
、現地作業が一層簡素化され、配管ユニット20内での
配線上の現地作業は不要となる。
In addition, various equipment listed in I'lff, Jl equipment, electric cable 33 for powering the valve, control cable 34 for control,
The conduits that house and distribute these cables 33 and 34 are also wired to the piping unit 20 via trays that support them. Their connections are connected to piping unit 2
0 centralized power terminal box 35 provided at the other end;
These terminals t83536 are located in the control terminal box 36, and connections with an external power source and an external control panel can be made only through these terminals t83536. In this way, cable 33.34
By connecting the terminal boxes 35 and 36 to the outside, on-site work is further simplified, and on-site work on wiring inside the piping unit 20 is no longer necessary.

前記架台21は、機器への配管25、計器への計装配管
28,29、サンプリングライン30のリポート、ケー
ブル33.34を支持するトレイのサポート、空気作動
弁26、手動弁27、ポンプ22等の機器のメンテナン
ス用架台を共用化させてある。共用化させることで、全
体構造の簡素化が図られ、スペースの有効活用、配管部
材の削減が可能であり、更には軽量化できることで、現
地への搬入容易性に寄与J−る。
The pedestal 21 includes piping 25 to the equipment, instrumentation piping 28, 29 to the instruments, a report of the sampling line 30, a tray support supporting cables 33, 34, an air-operated valve 26, a manual valve 27, a pump 22, etc. The maintenance stand for the equipment is shared. By sharing, the overall structure can be simplified, space can be used more effectively, piping components can be reduced, and the weight can be reduced, contributing to ease of transport to the site.

一方、前記空気作動弁26は、それに必要な電磁弁、フ
ィルター、レギュレータ、オイラー、制御ケーブル用端
子箱の付属品を前記電磁弁ラック31、制御l端子箱3
6に集中化させる。Ejなわち、配管ユニット20に設
けられる多数の空気作動弁26のそれらの1個毎に必要
な付属品を、配管ユニット20毎に集中化させてある。
On the other hand, the air-operated valve 26 is equipped with necessary accessories such as a solenoid valve, a filter, a regulator, an oiler, and a control cable terminal box in the solenoid valve rack 31 and the control l terminal box 3.
Concentrate on 6. Ej, that is, the accessories required for each of the many air-operated valves 26 provided in the piping unit 20 are centralized for each piping unit 20.

その結果、配管ユニット20内に設けられた各空気作動
弁26には、第3図に示すように、付属品が付設されず
、計装用空気配管28、制御端子箱36、電磁弁ラック
31に遠隔的に接続される。こうすることで、従来、各
空気作動弁26に必要とされた各別のメンテブンススペ
ースのff1u fQが不要となり、スペースを有効に
活用でき、付属品の部品点数ら削減可能で、全体の小形
化、省スペースに大きく役立つ。
As a result, each air-operated valve 26 provided in the piping unit 20 is not equipped with any accessories, as shown in FIG. connected remotely. By doing this, the separate maintenance space ff1u fQ that was conventionally required for each air-operated valve 26 is no longer necessary, the space can be used effectively, the number of accessory parts can be reduced, and the overall Greatly useful for downsizing and space saving.

以上のように構成された配管ユニット20が、現地に搬
入され、設置される。搬入に際しては、タワークレーン
あるいは大型クレーンが使用されることで、建築工事の
合理化、配管材、大型部品搬入用の後打ら壁の減少を図
ることができる。
The piping unit 20 configured as described above is carried to the site and installed. By using a tower crane or a large crane for transport, it is possible to streamline construction work and reduce the need for piping materials and walls to be constructed after transporting large parts.

更に、配管ユニツ1〜20の搬入時に、この配管ユニツ
1−20との接続配管及びナボー1〜をスプール化して
同時搬入することにより、11設工期を一層短縮化覆る
ことが可能となる。
Furthermore, when the piping units 1 to 20 are brought in, the connecting piping with the piping units 1 to 20 and the nabo 1 to 1 are spooled and brought in at the same time, thereby making it possible to further shorten the construction period.

配t2ユニツ1−20が搬入された現地では、外部別器
との接続が行なわれる。それは、第2図に示づように、
各i器37からは配管25に、MCC38からの動カケ
ープル39は電子端子箱35に、制υ11盤40からの
制御2(l信シうケーブル41は制御端子箱36にそれ
ぞれ接続される。
At the site where the distributed t2 units 1-20 are delivered, connections with external equipment are made. As shown in Figure 2,
Each I device 37 is connected to the piping 25, the dynamic cable 39 from the MCC 38 is connected to the electronic terminal box 35, and the control cable 41 from the control board 40 is connected to the control terminal box 36.

また、空気作動弁26、各種口器への泪装用空気は計装
用導圧管IPI42からの計装用空気母管43を通って
電磁弁ラック31に接続され、計装ラック32及びこれ
ら付設された差圧伝送路44からの計装用導圧管29は
配管ユニット20の端部で取り合わされる。
In addition, the air for supplying the air-operated valve 26 and various mouthpieces is connected to the solenoid valve rack 31 through the instrumentation air main pipe 43 from the instrumentation impulse pipe IPI42, and the instrumentation rack 32 and the attached differential The instrumentation pressure conduit 29 from the pressure transmission line 44 is joined at the end of the piping unit 20 .

このように外部機器と接続されると、各機器37からは
配管25にてポンプ22等の機器に接続される。M(,
038からは電力端子箱35、電カケープル33を介し
て、また、制…1盤40からはυ制御端子箱36、制御
ケーブル34を介して、計装用空気貯槽42からは電磁
弁ラック31を介してそれぞれ空気作動弁26、流量伝
送器24等の51器、ポンプ22等の機器にそれぞれ接
続される。
When connected to external devices in this way, each device 37 is connected to devices such as the pump 22 via piping 25. M(,
038 via the power terminal box 35 and the power cable 33, from the control panel 40 via the υ control terminal box 36 and the control cable 34, and from the instrumentation air storage tank 42 via the solenoid valve rack 31. 51, such as an air-operated valve 26, a flow rate transmitter 24, and equipment such as a pump 22, respectively.

更に、ffl装ラワラツク32は81装川導圧管29を
介して配管25、ル1器に接続される。
Further, the ffl loading raw rack 32 is connected to the piping 25 and the loop 1 unit via the 81 loading river pressure pipe 29.

また、第4図には、他の実施例にJ:る配管ユニッ(〜
20.ηなわら壁)卦tツタイブのそれが示されている
。この実施例においても、#3器、計器、これらへの配
管、弁を架台21とともに組立てられていること、外部
(大器への接続部位を端子箱35゜36.1ヒ磁ラツク
31に集中化Jること、これらの端子箱35.36、電
la弁ラック31の配管ユニッ1〜20喘部への設置等
は、先の実施例と異ならない。なJ3、この第4図にJ
′3いて、第1図乃至第3図に示した先の実施例とIn
1−のものには同一符号が付されている。また、図中4
5は架台吊りビーム、46はエアターミナルボックスで
ある。
FIG. 4 also shows a piping unit (~) in another embodiment.
20. η straw wall) that of the trigram is shown. In this embodiment as well, the #3 instrument, the meters, the piping for these, and the valves are assembled together with the pedestal 21, and the connection parts to the outside (larger instruments) are concentrated on the terminal box 35° 36.1 and the magnetic rack 31. In other words, the installation of these terminal boxes 35, 36 and the electric laver valve rack 31 in the piping units 1 to 20 parts is the same as in the previous embodiment.
'3, the previous embodiment shown in FIGS. 1 to 3 and In
Those with a 1- value are given the same reference numerals. Also, 4 in the figure
5 is a frame suspension beam, and 46 is an air terminal box.

(発明の効果) 本発明は以上のように実施され、各種の機器、計器、こ
れらの配管、弁を架台とともにあらかじめ組立て配管ユ
ニットとしてa3き、これを現地に搬入し、現地で外に
;機器との接続を行なうから、現地での配管据付工事が
大幅に減少し、据付工期を短縮できる。
(Effects of the Invention) The present invention is carried out as described above, and various devices, meters, their piping, and valves are preassembled together with a stand as a piping unit, and this is transported to the site and removed from the site; Since the connection is made with the pipes, on-site piping installation work can be significantly reduced and the installation period can be shortened.

また、配管ユニット内の機器、計器は、組立侵、工場内
で単体試験を実施可能であり、配管等の溶接部の試験、
検査を事6ηに工場内で実施できるから、現地での悪影
響下での作業が減少し、品質管理も容易になる。
In addition, the equipment and instruments in the piping unit can be assembled and tested in the factory, and welded parts of piping etc. can be tested.
Since inspections can be carried out within the factory within 6 hours, on-site work under adverse conditions is reduced and quality control becomes easier.

以上説明したにうに、本発明によれば、建設工Illの
大幅な短縮、現地作業の簡素化、及び工場製作による品
質管理の容易性が(!1られ、また、配管リポートの共
用化、スペースの有効利用により配管部材の削減が可能
である等の崎れた効果を秦する。
As explained above, according to the present invention, construction work is significantly shortened, on-site work is simplified, and quality control is facilitated by factory production (!1).In addition, piping reports can be shared, space is The effective use of water will result in significant benefits such as the reduction of piping components.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明方法の一実施例を説明するしのであり、
配管ユニツ1への斜視図、第2図は第1図で示す配管ユ
ニツ1−をプラント建設現場にJ3いてこの外部機器と
の接続を表わず斜視図、第3図は第1図で示す一実施例
でユニット化された空気作動弁の斜視図、第4図は配管
ユニツ1〜を壁掛【プ形に構成した本発明の他の実施例
における配管ユニットの斜視図であり、第5図及び第6
図は従来例を示し、第5図は配管施工後での斜視図、第
6図は空気作動弁の斜視図である。 1・・・配管・作用リーボート、2・・・弁、3・・・
プロセス配管、4・・・空気作動弁、5・・・トレイ川
1ナボート、6・・・計装用空気配管、7・・・後打ア
ンカー、8・・・コンジンす〜用リボ−1〜、9・・・
電線管、10・・・S1装川空気、11・・・フィルタ
、12・・・レギュレータ、13・・・オイラー、14
・・・端子箱、15・・・リミッ1〜スイッヂ、16・
・・電磁弁、17・・・A−プンスペース、20・・・
配管ユニツl−121・・・架台、22・・・ポンプ、
23・・・リミッ1〜スイッチ、24・・・流量伝送路
、25・・・配管、26・・・空気作動弁、27・・・
手動弁、28・・・計装用空気配管、29・・・計装用
導圧管、30・・・サンプリングライン、31・・・電
磁弁ラック、32・・・計装ラック、33・・・雷カケ
ープル、34・・・制御ケーブル、35・・・電力端子
箱、36・・・制611端子箱、37・・・各改器、3
8・・・MCC,39・・・動カケープル、40・・・
制り11盤、41・・・制御信号グープル、/12・・
・計装用空気貯(凸、43・・・b1装用空気母管、・
44・・・差圧伝送路、45・・・架台吊りビーム、/
16・・・エアターミナルボックス。 出願人代理人  波 多 野   久 寿 I 図
FIG. 1 illustrates an embodiment of the method of the present invention,
Fig. 2 is a perspective view of the piping unit 1 shown in Fig. 1 at the plant construction site and does not show connections with external equipment, and Fig. 3 is a perspective view of the piping unit 1 shown in Fig. 1. FIG. 4 is a perspective view of a unitized air-operated valve according to one embodiment, and FIG. and the sixth
The figures show a conventional example, FIG. 5 is a perspective view after piping construction, and FIG. 6 is a perspective view of an air-operated valve. 1...Piping/operating valve, 2...Valve, 3...
Process piping, 4...Air operated valve, 5...Tray river 1 boat, 6...Instrumentation air piping, 7...Post-throttle anchor, 8...Ribbo for conduit 1~, 9...
Electrical conduit, 10... S1 Sokawa air, 11... Filter, 12... Regulator, 13... Oiler, 14
...Terminal box, 15...Limit 1 to switch, 16.
...Solenoid valve, 17...A-Pun space, 20...
Piping unit l-121... Frame, 22... Pump,
23... Limit 1 to switch, 24... Flow rate transmission path, 25... Piping, 26... Air operated valve, 27...
Manual valve, 28... Instrumentation air piping, 29... Instrumentation impulse pipe, 30... Sampling line, 31... Solenoid valve rack, 32... Instrumentation rack, 33... Lightning cable , 34... Control cable, 35... Power terminal box, 36... System 611 terminal box, 37... Each change equipment, 3
8...MCC, 39...Moving capacity, 40...
Control 11 board, 41... Control signal group, /12...
・Instrumentation air storage (convex, 43...b1 air main pipe, ・
44... Differential pressure transmission line, 45... Frame suspension beam, /
16...Air terminal box. Applicant's agent Hisatoshi Hatano I Figure

Claims (1)

【特許請求の範囲】 1、工業プラントの配管据付方法において、所要の配管
類、弁類、計器類および機器類を架台とともにあらかじ
め工場にて配管ユニットとして組立て、この配管ユニッ
トをプラント建設現場で外部機器との接続を行なうこと
を特徴とする配管据付方法。 2、配管ユニットには、計装配管、計器への導圧管、サ
ンプリング配管、電線管、ケーブルを含めてある特許請
求の範囲第1項記載の配管据付方法。 3、配管ユニットの端部には、外部機器と接続させる配
管、ケーブルとの取合点をラック、端子箱で集中化して
ある特許請求の範囲第1項または第2項記載の配管据付
方法。 4、配管ユニットの架台は、機器へのプロセス配管、計
器への計装配管、サンプリング配管のサポート、ケーブ
ル用トレイのサポート、機器のメンテナンス架台を共用
化させてある特許請求の範囲第1項ないし第3項のいず
れか記載の配管据付方法。 5、配管ユニットの搬入時に、配管ユニットとの接続配
管およびサポートをスプール化して同時搬入する特許請
求の範囲第1項ないし第4項のいずれか記載の配管据付
方法。
[Claims] 1. In a piping installation method for an industrial plant, necessary piping, valves, instruments, and equipment are assembled together with a mount as a piping unit in advance at a factory, and this piping unit is installed externally at a plant construction site. A piping installation method characterized by connecting to equipment. 2. The piping installation method according to claim 1, wherein the piping unit includes an instrumentation piping, a pressure impulse pipe to a meter, a sampling piping, an electric conduit, and a cable. 3. The piping installation method as claimed in claim 1 or 2, wherein at the end of the piping unit, connection points for piping and cables connected to external equipment are centralized using racks and terminal boxes. 4. The mount of the piping unit is commonly used for process piping to equipment, instrumentation piping to instruments, support for sampling piping, support for cable trays, and equipment maintenance mount. Piping installation method described in any of paragraph 3. 5. The piping installation method according to any one of claims 1 to 4, wherein when the piping unit is brought in, the connecting piping and the support to the piping unit are spooled and brought in at the same time.
JP60289382A 1985-12-24 1985-12-24 Method of installing piping Pending JPS62151684A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60289382A JPS62151684A (en) 1985-12-24 1985-12-24 Method of installing piping

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60289382A JPS62151684A (en) 1985-12-24 1985-12-24 Method of installing piping

Publications (1)

Publication Number Publication Date
JPS62151684A true JPS62151684A (en) 1987-07-06

Family

ID=17742492

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60289382A Pending JPS62151684A (en) 1985-12-24 1985-12-24 Method of installing piping

Country Status (1)

Country Link
JP (1) JPS62151684A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016002064A1 (en) * 2014-07-04 2016-01-07 日本バルカー工業株式会社 Pipework workability evaluation and testing device

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5761884A (en) * 1980-09-30 1982-04-14 Ishikawajima Harima Heavy Ind Installing method of pipings or the like to trench of nuclear power generating plant
JPS5972097A (en) * 1982-10-18 1984-04-23 株式会社東芝 Plant constructing method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5761884A (en) * 1980-09-30 1982-04-14 Ishikawajima Harima Heavy Ind Installing method of pipings or the like to trench of nuclear power generating plant
JPS5972097A (en) * 1982-10-18 1984-04-23 株式会社東芝 Plant constructing method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016002064A1 (en) * 2014-07-04 2016-01-07 日本バルカー工業株式会社 Pipework workability evaluation and testing device

Similar Documents

Publication Publication Date Title
US20210278349A1 (en) Inspection system and method with variable-diameter traveling robot for inspection of natural gas pipeline
CN210958408U (en) Ship operation control system
US5808557A (en) Electronic sensor module
JPS62151684A (en) Method of installing piping
US20020177978A1 (en) Digital data acquisition system for manitoring and remote testing of gas and steam turbine performance parameters
CN203365115U (en) Hydraulic valve maintenance comparison test bench
CN211853527U (en) Portable sulfur hexafluoride gas pressure-stabilizing distribution device
CN209327819U (en) A kind of pulsed quantity signal input part daughter board
CN104517550A (en) Subway passenger information system construction method
CN217080632U (en) Gas turbine front fuel module
CN201060026Y (en) Intelligent bus liquid cabin liquid level nonitoring system
CN215987649U (en) Miniature pipeline SCADA system control simulation experiment device
JP2524631B2 (en) Inspection equipment for remote monitoring system
CN205187862U (en) Modular plate -type ozone generator
CN220291108U (en) Voltage type analog quantity redundant wiring terminal board
CN2211069Y (en) Disk-type sulfur dioxide automatic digital monitoring and testing instrument
CN211877904U (en) Bypass flue gas oxygen content measuring device
CN215639635U (en) Portable integrated flowmeter device for measuring air flow of airplane valve type component
CN216236021U (en) Control system for online monitoring and automatic oiling of motor
JPH0718887A (en) Method for construction thermal power plant
CN216081645U (en) Water meter control terminal
CN213513194U (en) Natural gas conveying pipeline flow adjusting device
CN210513203U (en) Automatic calibrating installation of power plant's thermal instrument
General PART 3: EXECUTION
Brandeis People and things