JPS6141370Y2 - - Google Patents

Info

Publication number
JPS6141370Y2
JPS6141370Y2 JP13618981U JP13618981U JPS6141370Y2 JP S6141370 Y2 JPS6141370 Y2 JP S6141370Y2 JP 13618981 U JP13618981 U JP 13618981U JP 13618981 U JP13618981 U JP 13618981U JP S6141370 Y2 JPS6141370 Y2 JP S6141370Y2
Authority
JP
Japan
Prior art keywords
arm
dragonfly
clamp
rope
wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP13618981U
Other languages
Japanese (ja)
Other versions
JPS5843107U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP13618981U priority Critical patent/JPS5843107U/en
Publication of JPS5843107U publication Critical patent/JPS5843107U/en
Application granted granted Critical
Publication of JPS6141370Y2 publication Critical patent/JPS6141370Y2/ja
Granted legal-status Critical Current

Links

Description

【考案の詳細な説明】 産業上の利用分野 この考案は、ホツト・ステイツクによる活線作
業時に、トンボ腕金を高圧腕金に取付ける場合に
使用するトンボ腕金吊上装置に関するものであ
る。
[Detailed Description of the Invention] Industrial Application Field This invention relates to a dragonfly arm lifting device used for attaching a dragonfly arm to a high-pressure arm during hot-stay live wire work.

従来技術 活線状態にある架空電線を支持している高圧腕
金に対し、トンボ腕金を取付ける場合、まずトン
ボ腕金を高圧腕金の所まで運び上げる必要があ
る。従来、トンボ腕金を運び上げる場合は、作業
員がトンボ腕金を背負つて高圧腕金の所まで登つ
ているが、活線状態にある架空電線に作業員が近
づくと危険であるので、架空電線を高圧腕金の上
方の安全圏に移設するという予備作業を行なう必
要があつた。
Prior Art When attaching a dragonfly arm to a high-voltage arm that supports live overhead power lines, it is first necessary to carry the dragonfly arm to the high-voltage arm. Conventionally, when lifting a dragonfly arm, a worker carries the dragonfly arm on his back and climbs up to the high-voltage arm, but it is dangerous for workers to approach live overhead power lines, so It was necessary to carry out preliminary work to relocate the power lines to a safe area above the high-voltage arms.

この予備作業を第1図および第2図によつて説
明すると、下記の手順で作業を行なつている。
This preliminary work will be explained with reference to FIGS. 1 and 2. The work is carried out in the following steps.

(1) 補助アーム6の高圧電線の間隔と同一間隔で
ワイヤー・ホルダー7を取付ける。
(1) Attach the wire holders 7 at the same spacing as the high-voltage wires on the auxiliary arm 6.

(2) 低圧線を電柱8から離隔する。(2) Separate the low-voltage line from utility pole 8.

(3) 電柱8に複数のワイヤー・トング・サドル9
およびロープ・ブロツク・サドル10を取付け
る。
(3) Multiple wire tongue saddles 9 on utility pole 8
and attach the rope block saddle 10.

(4) 垂直な主ワイヤー・トング11を電柱8の上
方側部に引き上げてワイヤー・トング・サドル
9に昇降自在に取付ける。
(4) The vertical main wire tong 11 is pulled up to the upper side of the utility pole 8 and attached to the wire tong saddle 9 so that it can be raised and lowered.

(5) 前記補助アーム6を電柱8の上部に引き上げ
て、その補助アーム6の中間部を主ワイヤー・
トング11の上端部に取付ける。
(5) Pull up the auxiliary arm 6 to the top of the utility pole 8, and attach the middle part of the auxiliary arm 6 to the main wire.
Attach to the upper end of the tongs 11.

(6) 補助ワイヤー・トング12を電柱8の上部に
引き上げて、その補助アーム・トング12の上
端部を補助ワイヤー・トング6の端部に連結す
る。
(6) Pull up the auxiliary wire tong 12 to the top of the utility pole 8 and connect the upper end of the auxiliary arm tong 12 to the end of the auxiliary wire tong 6.

(7) 補助ワイヤー・トング12の下端部を主ワイ
ヤー・トング11の下部に固定する。
(7) Fix the lower end of the auxiliary wire tongs 12 to the lower part of the main wire tongs 11.

(8) ロープ・ブロツク・サドル10に固定された
滑車13に巻掛けたロープ14の一端部を主ワ
イヤー・トング11の下端部に連結する。
(8) Connect one end of the rope 14 wound around the pulley 13 fixed to the rope block saddle 10 to the lower end of the main wire tong 11.

(9) 高圧碍子15のバインド線を解く。また必要
に応じ高圧碍子のボルトを外す。
(9) Untie the binding wire of high voltage insulator 15. Also, remove the high-voltage insulator bolts if necessary.

(10) ロープ14の他側部を引張つて、主ワイヤ
ー・トング11および補助アーム6等を上方に
引き上げ、その補助アーム6に取付けられてい
るワイヤー・ホルダー7により、活線状態にあ
る本線16を安全圏まで押上げたのち、主ワイ
ヤー・トング11を下降しないようにワイヤ
ー・トング・ホルダー9に固定する。
(10) By pulling the other side of the rope 14, pull up the main wire tongs 11 and the auxiliary arm 6, etc., and use the wire holder 7 attached to the auxiliary arm 6 to remove the main wire 16, which is in a live wire state. After pushing up the main wire tongs 11 to a safe range, the main wire tongs 11 are fixed to the wire tong holder 9 so as not to fall.

考案が解決しようとする問題点 しかるに、前記従来の場合は、作業員がトンボ
腕金を背負つて高圧腕金の所まで登らねばならな
いので、作業員に与える疲労が大きく、かつ作業
員が誤つて落下する恐れがあり、さらに煩雑な前
記予備作業を行なわねばならず、また高圧腕金の
上方の安全圏に移設された活線状態の架空電線が
地震時の振動その他の不測の原因により落下する
恐れがある。
Problems to be Solved by the Invention However, in the conventional case, the worker has to climb up to the high-pressure arm carrying the dragonfly arm on his back, which causes great fatigue to the worker, and also prevents the worker from making mistakes. There is a risk of falling, and the complicated preliminary work described above must be carried out, and the live overhead power lines, which have been relocated to a safe area above the high-voltage arms, may fall due to vibrations during an earthquake or other unforeseen causes. There is a fear.

考案の目的、構成 この考案は前述の問題を有利に解決できるトン
ボ腕金吊上装置を提供することを目的とするもの
であつて、この考案の要旨とするところは、仮設
アーム1の中間部に腕金クランプ2が取付けら
れ、前記仮設アーム1の両端部にはそれぞれ滑車
3が取付けられ、各滑車3に巻掛けられたロープ
4の一端部にそれぞれトンボ腕金クランプ5が連
結されていることを特徴とするトンボ腕金吊上装
置にある。
Purpose and structure of the invention The purpose of this invention is to provide a dragonfly arm lifting device that can advantageously solve the above-mentioned problems. An arm clamp 2 is attached to the temporary arm 1, pulleys 3 are attached to both ends of the temporary arm 1, and a dragonfly arm clamp 5 is connected to one end of a rope 4 wrapped around each pulley 3. A dragonfly arm lifting device is characterized by the following.

実施例 次にこの考案を図示の例によつて詳細に説明す
る。
Embodiments Next, this invention will be explained in detail using illustrated examples.

第3図ないし第5図はこの考案の一実施例に係
るトンボ腕金吊上装置を示すものであつて、電気
絶縁性材料からなる棒状の仮設アーム1の中間部
に、ほぼコ字状のクランプ本体18の下部腕がビ
ス等により固定され、その下部腕に固着された雌
ねじ部材19には、下端に係合孔20を有する垂
直なボルト21が螺合され、かつそのボルト21
の上端部には締付座金22が回動自在に取付けら
れ、前記クランプ本体18と雌ねじ部材19と締
付座金22および係合孔20を有するボルト21
とにより腕金クランプ2が構成されている。
Figures 3 to 5 show a dragonfly arm lifting device according to an embodiment of the invention, in which a roughly U-shaped rod is installed in the middle of a rod-shaped temporary arm 1 made of an electrically insulating material. A lower arm of the clamp body 18 is fixed with a screw or the like, and a vertical bolt 21 having an engagement hole 20 at the lower end is screwed into a female screw member 19 fixed to the lower arm.
A tightening washer 22 is rotatably attached to the upper end, and includes the clamp body 18, the female thread member 19, the tightening washer 22, and a bolt 21 having an engagement hole 20.
The cross arm clamp 2 is constituted by the above.

前記仮設アーム1の両端部にブラケツト23の
下端部が嵌合されてビス等により固定され、かつ
各ブラケツト23の上端部には、滑車3とロープ
外れ止め部材24とが取付けられ、各滑車3に巻
掛けられたロープ4の一端部にコ字状のクランプ
本体25の上部腕が連結され、さらにクランプ本
体25の下部腕に固着された雌ねじ部材26に
は、下部に係合孔27を有するボルト28が螺合
され、前記クランプ本体25とボルト28とによ
りトンボ腕金クランプ5が構成されている。また
各ロープ4の他端側部分は複胴型の巻取機29に
巻付けられている。
The lower ends of brackets 23 are fitted to both ends of the temporary arm 1 and fixed with screws, etc., and a pulley 3 and a rope stopper 24 are attached to the upper end of each bracket 23. An upper arm of a U-shaped clamp body 25 is connected to one end of the rope 4 wound around the clamp body 25, and a female screw member 26 fixed to the lower arm of the clamp body 25 has an engagement hole 27 at its lower part. A bolt 28 is screwed together, and the dragonfly arm clamp 5 is constituted by the clamp body 25 and the bolt 28. The other end portion of each rope 4 is wound around a double-barrel type winder 29.

前記実施例のトンボ腕金吊上装置を使用してト
ンボ腕金の取付作業を行なう場合は、まず地上に
おいて公知のグリツプ・クランプ・ステイツクに
より仮設アーム1を把持したのち持上げて、仮設
アーム1の中間部のクランプ本体18を高圧腕金
17に係合し、次いで地上においてステイツクに
よりボルト21を締付方向に回動して、腕金クラ
ンプ2により高圧腕金17を把持し、仮設アーム
1の中間部を高圧腕金17に固定する。
When installing a dragonfly arm using the dragonfly arm lifting device of the above embodiment, first grasp the temporary arm 1 on the ground using a known grip clamp stay, and then lift it up. The intermediate clamp main body 18 is engaged with the high-pressure arm 17, and then the bolt 21 is rotated in the tightening direction by the stake on the ground, the high-pressure arm 17 is gripped by the arm clamp 2, and the temporary arm 1 is The intermediate portion is fixed to the high-pressure armrest 17.

次に予め複数の碍子を取付けたトンボ腕金30
の両端部を、前記各ロープ4の一端部に連結され
ているトンボ腕金クランプ5により把持したの
ち、各ロープ4の他端側部分を地上において作業
員が手で引張るか、または複胴型の巻取機29に
より巻取ることにより、トンボ腕金30を高圧腕
金17の下面に接する位置まで吊上げ、次いでス
テイツクによりボルトおよびナツトを締付けて、
トンボ腕金30を高圧腕金17に固定する。
Next, a dragonfly arm 30 with multiple insulators attached in advance.
Both ends of the ropes 4 are gripped by dragonfly arm clamps 5 connected to one end of each rope 4, and then the other end of each rope 4 is manually pulled by a worker on the ground, or a double-barrel type By winding it up with the winder 29, the dragonfly arm 30 is lifted up to a position where it contacts the lower surface of the high-pressure arm 17, and then the bolts and nuts are tightened with the stay.
The dragonfly arm 30 is fixed to the high-pressure arm 17.

トンボ腕金30の取付作業を終了したのち、ス
テイツクによりトンボ腕金クランプ5のボルト2
8を回動して弛緩すると共に、トンボ腕金クラン
プ5をトンボ腕金30から外し、次いでステイツ
クにより腕金クランプ2のボルト21を回転して
弛緩し、次に、グリツプ・クランプ・ステイツク
により仮設アーム1を把持して地上に下ろす。
After completing the installation work of the registration arm arm 30, tighten the bolt 2 of the registration arm arm clamp 5 using the stay.
8 to loosen it, remove the registration arm arm clamp 5 from the registration arm arm 30, then rotate and loosen the bolt 21 of the arm arm clamp 2 using the stay, and then temporarily tighten the bolt 21 using the grip clamp stay. Grasp arm 1 and lower it to the ground.

この考案を実施する場合、第6図に示すよう
に、腕金クランプ2におけるクランプ本体18の
中間腕に、アタツチメント31をビスにより着脱
自在に設けておけば、そのアタツチメント18を
着脱することにより、異なる断面の高圧腕金17
A,17Bに対する取付けに兼用することができ
る。
When implementing this invention, as shown in FIG. 6, if an attachment 31 is detachably provided with a screw on the intermediate arm of the clamp body 18 of the arm clamp 2, by attaching and detaching the attachment 18, High pressure arms 17 with different cross sections
It can also be used for attachment to A and 17B.

考案の効果 この考案によれば、腕金クランプ2および滑車
3を備えている仮設アーム1を、地上でグリツ
プ・クランプ・ステイツク等により持上げて、腕
金クランプ2のクランプ本体18の高圧腕金17
に係合し、次いでステイツクにより腕金クランプ
2を締付けることにより、地上操作により仮設ア
ーム1を高圧腕金17に対し容易にかつ迅速に固
定することができ、さらに仮設アーム1の両端の
滑車3から垂下しているロープ4の一端部に連結
されたトンボ腕金クランプ5によりトンボ腕金3
0の両端部を把持したのち、地上で各ロープ4の
他端側部分を引張ることにより、トンボ腕金30
を高圧腕金17の下部の取付位置まで容易にかつ
迅速に吊上げることができ、そのため安全状態で
トンボ腕金を高圧腕金の位置まで吊上ることがで
きると共に、作業員に与える疲労を少なく、しか
も前記従来のように活線状態にある架空電線を安
全圏に移設するという煩雑な予備作業を必要とし
ない等の効果が得られる。
Effects of the invention According to this invention, the temporary arm 1 equipped with the arm clamp 2 and the pulley 3 is lifted on the ground by a grip clamp stay or the like, and the high-pressure arm 17 of the clamp body 18 of the arm clamp 2 is
The temporary arm 1 can be easily and quickly fixed to the high-pressure arm 17 by ground operation by engaging with the arm clamp 2 and then tightening the arm clamp 2 with the stay. The dragonfly arm clamp 5 is connected to one end of the rope 4 hanging from the dragonfly arm 3.
0, and then pull the other end of each rope 4 on the ground.
can be easily and quickly lifted to the lower mounting position of the high-pressure arm 17. Therefore, the dragonfly arm can be lifted to the position of the high-pressure arm in a safe state, and the fatigue caused to the worker can be reduced. Furthermore, there are advantages such as not requiring the complicated preliminary work of relocating live overhead wires to a safe area as in the prior art.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来の活性状態にある本線の押上装置
を示す正面図、第2図はその一部を示す側面図で
ある。第3図はこの考案の実施例に係るトンボ腕
金吊上装置を示す一部切欠正面図、第4図はその
縦断側面図、第5図は第3図のA−A線断面図で
ある。第6図は腕金クランプにアタツチメントを
取付けた状態を示す正面図である。 図において、1は仮設アーム、2は腕金クラン
プ、3は滑車、4はロープ、5はトンボ腕金クラ
ンプ、16は活線状態にある本線、18はクラン
プ本体、19は雌ねじ部材、20は係合孔、21
はボルト、22は締付座金、23はブラケツト、
24はロープ外れ止め部材、25はクランプ本
体、26は雌ねじ部材、27は係合孔、28はボ
ルト、29は巻取機、30はトンボ腕金である。
FIG. 1 is a front view showing a conventional main line lifting device in an activated state, and FIG. 2 is a side view showing a portion thereof. Fig. 3 is a partially cutaway front view showing a dragonfly arm lifting device according to an embodiment of this invention, Fig. 4 is a vertical side view thereof, and Fig. 5 is a sectional view taken along line A-A in Fig. 3. . FIG. 6 is a front view showing a state in which the attachment is attached to the arm clamp. In the figure, 1 is a temporary arm, 2 is a cross arm clamp, 3 is a pulley, 4 is a rope, 5 is a dragonfly arm clamp, 16 is a main wire in a live wire state, 18 is a clamp body, 19 is a female screw member, and 20 is a female screw member. Engagement hole, 21
is a bolt, 22 is a tightening washer, 23 is a bracket,
Reference numeral 24 indicates a rope retaining member, 25 a clamp body, 26 a female screw member, 27 an engagement hole, 28 a bolt, 29 a winder, and 30 a dragonfly arm.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 仮設アーム1の中間部に腕金クランプ2が取付
けられ、前記仮設アーム1の両端部にはそれぞれ
滑車3が取付けられ、各滑車3に巻掛けられたロ
ープ4の一端部にそれぞれトンボ腕金クランプ5
が連結されていることを特徴とするトンボ腕金吊
上装置。
An arm clamp 2 is attached to the middle part of the temporary arm 1, a pulley 3 is attached to each end of the temporary arm 1, and a dragonfly arm clamp is attached to one end of a rope 4 wrapped around each pulley 3. 5
A dragonfly arm lifting device characterized in that: are connected to each other.
JP13618981U 1981-09-16 1981-09-16 Dragonfly arm lifting device Granted JPS5843107U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13618981U JPS5843107U (en) 1981-09-16 1981-09-16 Dragonfly arm lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13618981U JPS5843107U (en) 1981-09-16 1981-09-16 Dragonfly arm lifting device

Publications (2)

Publication Number Publication Date
JPS5843107U JPS5843107U (en) 1983-03-23
JPS6141370Y2 true JPS6141370Y2 (en) 1986-11-25

Family

ID=29929524

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13618981U Granted JPS5843107U (en) 1981-09-16 1981-09-16 Dragonfly arm lifting device

Country Status (1)

Country Link
JP (1) JPS5843107U (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5306031B2 (en) * 2009-04-13 2013-10-02 中国電力株式会社 Indirect hot tool support
JP7112665B2 (en) * 2018-02-09 2022-08-04 中国電力株式会社 charging terminal

Also Published As

Publication number Publication date
JPS5843107U (en) 1983-03-23

Similar Documents

Publication Publication Date Title
CN104538887B (en) A kind of lightning conducter lifts converter
JPS6141370Y2 (en)
JP2006050855A (en) High-voltage pulling-down line supporting hardware and its attaching/detaching method to/from power distribution pole
JPS5843367Y2 (en) Angle adjustable grounded metal fitting
JPH07291000A (en) Tensile force temporary receiving device for stringing
CN219281402U (en) Wire drawing hardware fitting capable of preventing cable from loosening
CN216085962U (en) Insulator nut fastening device
SU1056279A1 (en) Method of mounting apparatus for lateral fixing of wire on neck of pin-type insulaator
CN112993862B (en) Wire tightening device for power construction
JPH07317305A (en) Scaffold for wire stretching and installation method thereof
JPS6032396Y2 (en) Power cable lifting device for liquid pump
JPH0321134Y2 (en)
JP2525987Y2 (en) Construction support bracket
JPS6345800Y2 (en)
KR200303401Y1 (en) Ground wire pulling tool
JPH01129708A (en) Cable suspender
JPH0514675Y2 (en)
CN2468670Y (en) Tail rope fastening device
JPH0440353Y2 (en)
JPH0297206A (en) Branch metal fixing tool for communication cable
JPS6338661Y2 (en)
JP5687079B2 (en) Suspension bracket with gold wheel and cable erection method
JP2782043B2 (en) Auxiliary equipment for overhead cable installation
JPH047634Y2 (en)
JPS6345803Y2 (en)