JPS6131521A - Joining method for underground continuous wall - Google Patents

Joining method for underground continuous wall

Info

Publication number
JPS6131521A
JPS6131521A JP15260984A JP15260984A JPS6131521A JP S6131521 A JPS6131521 A JP S6131521A JP 15260984 A JP15260984 A JP 15260984A JP 15260984 A JP15260984 A JP 15260984A JP S6131521 A JPS6131521 A JP S6131521A
Authority
JP
Japan
Prior art keywords
partition
space
plate
plates
slime
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP15260984A
Other languages
Japanese (ja)
Other versions
JPS642728B2 (en
Inventor
Takeo Morita
森田 建男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TEKKEN KENSETSU CO Ltd
Tekken Corp
Original Assignee
TEKKEN KENSETSU CO Ltd
Tekken Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TEKKEN KENSETSU CO Ltd, Tekken Corp filed Critical TEKKEN KENSETSU CO Ltd
Priority to JP15260984A priority Critical patent/JPS6131521A/en
Publication of JPS6131521A publication Critical patent/JPS6131521A/en
Publication of JPS642728B2 publication Critical patent/JPS642728B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Abstract

PURPOSE:To completely clean a partitioning mesh panel, by a method wherein water is injected from an injection pipe against a partitioning mesh panel mounted between the internal plates of a partition member to disperse slime adhered thereto toward the side opposite to the injection pipe, and the slime is sucked through a suction pipe for removal. CONSTITUTION:A partitioning mesh plate 8, bent in zigzag by support levers 6 to form projections and recesses, is located between internal plates 4 of a partition member 2 of an underground continuous wall. Prior to concreting, water is injected from an injection pipe 19 gradually lowered, slime adhered to the partitioning mesh plate 8 is dispersed toward the side opposite to the pipe, and the slime is sucked through a suction pipe 20 for removal. This enables complete cleaning of the partitioning mesh plate 8, and enables unit wall bodies to be engaged with each other after concrete is placed to reliably form the wall bodies integrally with each other.

Description

【発明の詳細な説明】 この発明は地中連続壁接合工法に関する。[Detailed description of the invention] The present invention relates to an underground continuous wall joining method.

地中連続壁は種々の地盤条件、施工条件等によシ壁体の
長さが限定され、そのため壁体を複数の単位壁体から構
成しなければならず、互いに隣接する各単位壁体間には
接合部が生じる。
The length of an underground continuous wall is limited due to various ground conditions, construction conditions, etc. Therefore, the wall must be composed of multiple unit walls, and the distance between each adjacent unit wall is limited. A joint occurs in the

従来、単位壁体間の接合工法としては、接合部に仕切板
を設置し、この仕切板の両側に先行および後行単位壁体
を構築するのが一般的であり、その特殊な例として仕切
板に連続した凹凸部を形成し、先行および後行単位壁体
が接合部において噛み合うようにした工法がある。この
工法は前記のような噛み合いにより、単位壁体間の応力
伝達の向上を意図したものであるが、仕切板の凹所に溜
まった泥水によるスライムを除去するのが困難であり、
そのためスライムが残置し、結果として単位壁体どうし
の一体化が確実になさ耗ないという欠点があった。
Conventionally, the common method for joining unit walls is to install a partition plate at the joint and construct leading and trailing unit walls on both sides of this partition plate. There is a construction method in which continuous uneven parts are formed on the board so that the leading and trailing unit walls interlock at the joints. This construction method is intended to improve stress transmission between unit walls through the interlocking described above, but it is difficult to remove slime caused by muddy water that has accumulated in the recesses of the partition plates.
As a result, slime remains behind, resulting in the disadvantage that unit walls cannot be reliably integrated with each other and will not wear out.

この発明は上記のような従来工法の欠点を排除し、仕切
板に付着したスライムの除去を完全に行うことができる
地中連続壁接合工法を提供することを目的とする。すな
わちこの発明は、同一垂直面上に間隔を置いて配置され
、かつ外側端縁間の間隔が溝孔の巾とほぼ等しくなって
いる1対の外方板と、両外方板の内側端縁に直交するよ
うに対向して固着され、両側端部に係合部が形成された
1対の内方板とを有する仕切部材を具え、前記内方板間
に多数の支持杆を縦方向に亘ってじぐざぐに配列して固
着し、これらの支持杆に骨材を通さない程度の多数の網
目を有する仕切網目板を順次捲回して連続した凹凸部を
形成し、前記仕切部材に鉄筋篭と継手部材とをそれぞれ
横向きに固着し、前記鉄筋篭を前記外方板の1側面側に
位置させ、前記継手部材の継手部分を外方板の他側面側
に位置させてなる組立体をあらかじめ形成し1、掘削し
た先行溝孔に前記組立体を挿入設置し、それにより先行
溝孔を前記鉄筋篭が配置された第1空間と、前記継手部
分が配置された第2空間とに区画し、次いで両側端部に
係合部が形成された1対の第1、第2仮仕切板をその係
合部と前記内方板の係合部とを係合させてこの内方板間
に挿入設置するとともに、前記第2空間に支持材を設置
し、次いで前記第1空間における第1仮仕切板と前記仕
切網目板との間に高圧水の噴出部材を挿入するとともに
、第2空間における第2仮仕切板と前記仕切網目板との
間に吸入部材を挿入し、前記噴出部材から前記仕切網目
板に向けて隅圧水を噴射し、それ咳より仕切網目板に付
着したスライム全前記吸入部材側に飛散させ、この吸入
部材により前記スライムを吸入除去しした後、前記噴出
部材を撤去し、次いで前記第1仮仕切板を撤去するとと
もに第1空間にコンクリートを打設硬化させて先行単位
壁体を構築し、次いで前記第2空間を含む後行溝孔を掘
削した後、この後行溝孔内に前記と同様の組立体を挿入
設置し、前記第2仮仕切板を撤去するとともに、後行溝
孔の第1空間にコンクIJ −ト’r打設硬化させて後
行単位壁体を構築することを特徴とする地中連続壁の接
合工法にある。
An object of the present invention is to provide an underground continuous wall joining method that eliminates the drawbacks of the conventional method as described above and can completely remove slime adhering to partition plates. That is, the present invention includes a pair of outer plates arranged at intervals on the same vertical plane and having a distance between outer edges that is approximately equal to the width of the slot, and inner edges of both outer plates. A partition member having a pair of inner plates fixed to face each other perpendicularly to the edge and having engaging portions formed at both ends thereof, and a plurality of support rods arranged longitudinally between the inner plates. Partition mesh plates are arranged and fixed in a diagonal pattern over the support rods and have a large number of meshes that do not allow the aggregate to pass through, and are sequentially wound to form a continuous uneven part, and reinforcing bars are attached to the partition members. A cage and a joint member are each fixed horizontally, the reinforcing bar cage is located on one side of the outer plate, and the joint part of the joint member is located on the other side of the outer plate. The assembly is inserted into and installed in a pre-formed and excavated pre-slot hole, thereby dividing the pre-slot hole into a first space where the reinforcing bar cage is placed and a second space where the joint portion is placed. Then, a pair of first and second temporary partition plates each having an engaging portion formed at both end portions are engaged with the engaging portion of the inner plate to separate the inner plates. At the same time, a support member is installed in the second space, and then a high-pressure water spouting member is inserted between the first temporary partition plate and the partition mesh plate in the first space, and a support member is installed in the second space. A suction member is inserted between the second temporary partition plate and the partition mesh plate, and corner pressure water is injected from the jetting member toward the partition mesh plate to remove all the slime that has adhered to the partition mesh plate. After scattering the slime to the suction member side and inhaling and removing the slime with the suction member, the spouting member is removed, and then the first temporary partition plate is removed and concrete is poured and hardened in the first space. After constructing the leading unit wall and then excavating a trailing groove containing the second space, inserting and installing the same assembly as described above into the trailing groove, and removing the second temporary partition plate. In addition, there is provided a method for joining an underground continuous wall, characterized in that a trailing unit wall is constructed by pouring and hardening concrete in the first space of a trailing trench.

以下図面に示す一実施例について説明する。An embodiment shown in the drawings will be described below.

第1,2図に示すように、この発明工法に使用する組立
体1は仕切部材2を具え、この仕切部材2−同一垂直面
上に間隔を置いて配置された1対の外方板3,3の内側
端縁に、直交するようVこ1対の内方板4,4を対向し
て固着してなり、外方板3の外側端縁間の間隔は溝孔の
巾とほぼ等しく、また内方板4,4はその両側端部が折
曲され、それにより凸状の係合部5が形成されている。
As shown in FIGS. 1 and 2, an assembly 1 used in the invention method comprises a partition member 2 - a pair of outer plates 3 spaced apart from each other on the same vertical plane. , 3, a pair of V-shaped inner plates 4, 4 are fixed to face each other perpendicularly to the inner edges of the outer plates 3, and the distance between the outer edges of the outer plates 3 is approximately equal to the width of the slot. Furthermore, both end portions of the inner plates 4, 4 are bent, thereby forming a convex engaging portion 5.

内方板4,4間には多数の支持杆6が縦方向に亘って千
鳥状に配列され、これらの支持杆6は両端部に雄ねじ部
を形成して、ナツト7により内方板4,4に固着されて
いる。支持杆6には骨材を通さない程度の大きさの多数
の網目を有する仕切網目板8が順次捲回して固定され、
それによシ仕切網目板8には連続した凹凸部9が形成さ
れている。図示の例では凹凸部9の先端は尖っているが
、支持杆6を階段状に配列し、凹凸部9の先端を平坦と
してもよい。
A large number of support rods 6 are arranged in a staggered manner in the vertical direction between the inner plates 4, 4, and these support rods 6 have male threads formed at both ends, and are connected to the inner plates 4, 4 by nuts 7. It is fixed to 4. A partition mesh plate 8 having a large number of meshes of a size that does not allow the aggregate to pass through is sequentially wound and fixed to the support rod 6.
In addition, continuous uneven portions 9 are formed on the partition mesh plate 8. In the illustrated example, the tips of the uneven portions 9 are sharp, but the support rods 6 may be arranged in a stepped manner, and the tips of the uneven portions 9 may be flat.

内方板4には多数の縦向鉄筋10と横向鉄筋11とを固
着してなる鉄筋篭12および継手鉄筋13がそれぞれ横
向きに固着され、鉄筋篭12は外方板3の一側面側に位
置し、継手鉄筋13の継手部分13aは他側面側に位置
している。
A reinforcing bar cage 12 and a joint reinforcing bar 13, which are made up of a large number of longitudinal reinforcing bars 10 and horizontal reinforcing bars 11 fixed to each other, are fixed to the inner plate 4 in a horizontal direction, and the reinforcing bar cage 12 is located on one side of the outer plate 3. However, the joint portion 13a of the joint reinforcing bar 13 is located on the other side.

次に上記のような組立体を使用しての地中連続壁接合工
法について説明する。
Next, a method for joining underground continuous walls using the above-mentioned assembly will be explained.

まず第1,2図(示すように地盤Eに掘削機によシ先行
溝孔14を掘削し、その際溝孔14には従来と同様に泥
水を満たしながら掘削を行い、壁面の崩壊を防ぐ。
First, as shown in Figures 1 and 2, a preliminary trench 14 is excavated in the ground E using an excavator, and at this time, the trench 14 is filled with muddy water in the same way as before to prevent the wall from collapsing. .

次に溝孔14に組立体1を挿入設置し、それにより溝孔
14を鉄筋篭12が配置された第1空間S1  と継手
鉄筋13の継手部分13aが配置された第2空間S2 
とに区画する。そして内方板4,4間に1対の第1.第
2仮仕切板18a、18bを挿入設置し、内方板4,4
および第1.第2仮仕切板18a、18bによって区画
されたゼックス状の空間を形成する。第1、第2仮仕切
板18a、18bの両側端部には凹状の係合部17が形
成され、その挿入の際は係合部17と内方板4の係合部
5とを係合させる。また第2空間S2には防護柵15f
、設置して継手部分13a’i覆い、さらにロッキング
パイプ16を設置して組立体1を支持する。
Next, the assembly 1 is inserted and installed in the slot 14, thereby dividing the slot 14 into the first space S1 where the reinforcing bar cage 12 is arranged and the second space S2 where the joint portion 13a of the joint reinforcing bar 13 is arranged.
It is divided into two parts. And between the inner plates 4, 4, a pair of first. Insert and install the second temporary partition plates 18a and 18b, and
and 1st. A box-shaped space is formed divided by the second temporary partition plates 18a and 18b. Concave engaging portions 17 are formed at both ends of the first and second temporary partition plates 18a and 18b, and when inserted, the engaging portions 17 and the engaging portions 5 of the inner plate 4 are engaged. let In addition, there is a protective fence 15f in the second space S2.
, to cover the joint portion 13a'i, and further install the locking pipe 16 to support the assembly 1.

次に第1仮仕切板18aと仕切網目板8との間に高圧水
の噴出管19、第2仮仕切板18bと仕切網目板8との
間に吸入管2of:それぞれ挿入し、噴出管19を上下
に移動させながらまた先端を回転させながら該先端から
仕切網目板8に向けて高圧水を噴射し、それにより仕切
網目板8に付着した泥水によるスライムを吸入管20側
に飛散させ、この吸入管2oによりスライムを吸入して
除去する。高圧水としては清水を使用し、吸入管20か
ら清水が出てくるのを確認したらその作業を終了する。
Next, a high-pressure water ejection pipe 19 is inserted between the first temporary partition plate 18a and the partition mesh plate 8, and a suction pipe 2of: is inserted between the second temporary partition plate 18b and the partition mesh plate 8. While moving up and down, and rotating the tip, high-pressure water is injected from the tip toward the partition mesh plate 8, thereby scattering the slime due to muddy water adhering to the partition mesh plate 8 to the suction pipe 20 side. The slime is sucked in and removed through the suction pipe 2o. Clean water is used as the high-pressure water, and once it is confirmed that clean water is coming out of the suction pipe 20, the work is finished.

またこのような仕切網目板8の清掃作業と併行して内外
方板3.4等の清掃作業も行う。
Further, in parallel with the cleaning work of the partition mesh plate 8, cleaning work of the inner and outer plates 3, 4, etc. is also performed.

次いで第3図に示すように、噴出管19f:撤去し、第
1空間S1 にコンクリートを打設して硬化させ、先行
単位壁体21を“構築する。コンクリート打設の際は第
1仮仕切板18aの下端が、上昇するコンクリートヘッ
ドよりも常時下方に位置するようにしながら、仮住切板
18aを徐々に上昇させて撤去し、それによりコンクリ
ート打設によるスライムの巻込みを防止する。
Next, as shown in FIG. 3, the ejection pipe 19f is removed, and concrete is poured into the first space S1 and hardened to construct the preceding unit wall 21. When concrete is poured, the first temporary partition is The temporary housing cutting board 18a is gradually raised and removed while the lower end of the board 18a is always located below the rising concrete head, thereby preventing slime from being drawn in by concrete pouring.

上記のようにして先行単位壁体21を構築したら、ロッ
キングパイプ16を撤去し、第2空間S2を含む後行溝
孔22を掘削し、掘削終了後防脆柵15を撤去してこの
後行溝孔22に前記と同様の組立体(その鉄筋篭12の
み示す)を挿入設置する。そして第2仮仕切板18bと
仕切網目板8との間に噴出管19および吸入管20の双
方を挿入し、噴出管19からの高圧水により仕切網目板
8に付着したスライムを飛散させ、このスライムおよび
先行単位壁体21のコンクリート打設の際に仕切網目板
8を通過したセメントペース)を吸入管20により吸入
して除去する。この時のスライム量およびセメントペー
スト量は極く微少であり、このような清掃作業は必ずし
も行わなくともよい。
After constructing the preceding unit wall 21 as described above, the locking pipe 16 is removed, the trailing groove hole 22 including the second space S2 is excavated, and after the excavation is completed, the anti-brittle fence 15 is removed and the trailing groove hole 22 is excavated. An assembly similar to the above (only the reinforcing bar cage 12 is shown) is inserted into the slot 22 and installed. Then, both the ejection pipe 19 and the suction pipe 20 are inserted between the second temporary partition plate 18b and the partition mesh plate 8, and the slime adhering to the partition mesh plate 8 is scattered by high pressure water from the ejection pipe 19. The slime and the cement paste that passed through the partition mesh plate 8 during concrete placement of the preceding unit wall 21 are sucked into the suction pipe 20 and removed. The amount of slime and cement paste at this time is extremely small, so such cleaning work does not necessarily have to be performed.

次いで第4,5図に示すように噴出管19および吸入管
20′lt−撤去し、後行溝孔22の第1空間S1 に
コンクリートを打設して硬化させ、後行単位壁体23を
構築する。コンクリート打設の際は、第2仮仕切板18
bi第1仮仕切板18のときと同様に徐々に上昇させて
撤去する。
Next, as shown in FIGS. 4 and 5, the ejection pipe 19 and the suction pipe 20'lt are removed, and concrete is poured into the first space S1 of the trailing slot 22 and hardened to form the trailing unit wall 23. To construct. When pouring concrete, use the second temporary partition plate 18.
2) Gradually raise and remove as in the case of the first temporary partition plate 18.

以上のように単位壁体を順次構築して接合し、接合部に
おいて単位壁体どうしが噛み合った地中連続壁を形成す
るものである。
As described above, the unit walls are constructed and joined one after another, and the unit walls are interlocked with each other at the joints to form an underground continuous wall.

この発明は上記のようであって、仕切部材の内方板間に
連続した凹凸部を形成した仕切網目板を設け、コンクリ
ートの打設前に前記仕切網目板に高圧水を噴射して付着
したスライムを反対側に飛散させ、このスライムを吸入
管によシ吸入して除去するので、仕切網目板の清掃が完
全になされ、とくにその凹部にスライムが残置すること
がなく、単位壁体が互いに噛み合って確実に一体化され
、したがって止水性に優れ、また応力伝達性に優れた地
中連続壁を構築できる。
This invention is as described above, in which a partition mesh plate having continuous uneven parts is provided between the inner plates of the partition member, and high-pressure water is sprayed onto the partition mesh plate to adhere the concrete before concrete is poured. Since the slime is scattered to the opposite side and removed by suction into the suction pipe, the partition mesh plate is completely cleaned, and no slime is left in the recesses, and the unit walls are mutually separated. They interlock and are reliably integrated, making it possible to construct an underground continuous wall with excellent water-stopping properties and stress transmission properties.

【図面の簡単な説明】[Brief explanation of the drawing]

図面はこの発明工法の施工手順を示し、第1図は組立体
を先行溝孔に建込んだ状態を示す横断面図、第2図は同
上の縦断面図、第3図は先行単位壁体を構築した状態を
示す横断面図、第4図は後行単位壁体を構築した状態を
示す横断面図、第5図は同上の縦断面図。
The drawings show the construction procedure of this invention construction method, Fig. 1 is a cross-sectional view showing the assembly installed in the preceding groove, Fig. 2 is a longitudinal sectional view of the same, and Fig. 3 is the preceding unit wall. FIG. 4 is a cross-sectional view showing the construction of the trailing unit wall, and FIG. 5 is a vertical cross-sectional view of the same.

Claims (1)

【特許請求の範囲】[Claims] 1、同一垂直面上に間隔を置いて配置され、かつ外側端
縁間の間隔が溝孔の巾とほぼ等しくなつている1対の外
方板と、両外方板の内側端縁に直交するように対向して
固着され、両側端部に係合部が形成された1対の内方板
とを有する仕切部材を具え、前記内方板間に多数の支持
杆を縦方向に亘つてじぐざぐに配列して固着し、これら
の支持杆に骨材を通さない程度の多数の網目を有する仕
切網目板を順次捲回して連続した凹凸部を形成し、前記
仕切部材に鉄筋篭と継手部材とをそれぞれ横向きに固着
し、前記鉄筋篭を前記外方板の1側面側に位置させ、前
記継手部材の継手部分を外方板の他側面側に位置させて
なる組立体をあらかじめ形成し、掘削した先行溝孔に前
記組立体を挿入設置し、それにより先行溝孔を前記鉄筋
篭が配置された第1空間と、前記継手部分が配置された
第2空間とに区画し、次いで両側端部に係合部が形成さ
れた1対の第1、第2仮仕切板をその係合部と前記内方
板の係合部とを係合させてこの内方板間に挿入設置する
とともに、前記第2空間に支持材を設置し、次いで前記
第1空間における第1仮仕切板と前記仕切網目板との間
に高圧水の噴出部材を挿入するとともに、第2空間にお
ける第2仮仕切板と前記仕切網目板との間に吸入部材を
挿入し、前記噴出部材から前記仕切網目板に向けて高圧
水を噴射し、それにより仕切網目板に付着したスライム
を前記吸入部材側に飛散させ、この吸入部材により前記
スライムを吸入除去しした後、前記噴出部材を撤去し、
次いで前記第1仮仕切板を撤去するとともに第1空間に
コンクリートを打設硬化させて先行単位壁体を構築し、
次いで前記第2空間を含む後行溝孔を掘削した後、この
後行溝孔内に前記と同様の組立体を挿入設置し、前記第
2仮仕切板を撤去するとともに、後行溝孔の第1空間に
コンクリートを打設硬化させて後行単位壁体を構築する
ことを特徴とする地中連続壁の接合工法。
1. A pair of outer plates spaced apart on the same vertical plane, with the spacing between their outer edges being approximately equal to the width of the slot, and perpendicular to the inner edges of both outer plates. a partition member having a pair of inner plates fixed to face each other so as to face each other and having engaging parts formed at both ends thereof, and a large number of support rods extending longitudinally between the inner plates. Partition mesh plates are fixed in a zigzag arrangement and have a large number of meshes that do not allow aggregate to pass through these support rods, and are sequentially wound to form continuous uneven parts, and the partition members are fitted with reinforcing bar baskets and joints. An assembly is formed in advance, in which the reinforcing bar cage is positioned on one side of the outer plate, and the joint portion of the joint member is positioned on the other side of the outer plate. , the assembly is inserted and installed in the excavated preceding groove, thereby dividing the preceding groove into a first space where the reinforcing bar basket is placed and a second space where the joint portion is placed, and then both sides are separated. A pair of first and second temporary partition plates having engaging portions formed at their ends are inserted and installed between the inner plates by engaging the engaging portions with the engaging portions of the inner plates. At the same time, a support member is installed in the second space, and then a high-pressure water jetting member is inserted between the first temporary partition plate and the partition mesh plate in the first space, and a support member is installed in the second space. A suction member is inserted between the partition plate and the partition mesh plate, and high-pressure water is injected from the jetting member toward the partition mesh plate, thereby scattering the slime attached to the partition mesh plate toward the suction member side. After the slime is suctioned and removed by the suction member, the ejection member is removed;
Next, the first temporary partition plate is removed and concrete is cast and hardened in the first space to construct a preceding unit wall,
Next, after excavating a trailing groove containing the second space, an assembly similar to that described above is inserted and installed in the trailing groove, the second temporary partition plate is removed, and the trailing groove is opened. A method for joining an underground continuous wall, characterized by constructing a trailing unit wall by pouring and hardening concrete in a first space.
JP15260984A 1984-07-23 1984-07-23 Joining method for underground continuous wall Granted JPS6131521A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15260984A JPS6131521A (en) 1984-07-23 1984-07-23 Joining method for underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15260984A JPS6131521A (en) 1984-07-23 1984-07-23 Joining method for underground continuous wall

Publications (2)

Publication Number Publication Date
JPS6131521A true JPS6131521A (en) 1986-02-14
JPS642728B2 JPS642728B2 (en) 1989-01-18

Family

ID=15544137

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15260984A Granted JPS6131521A (en) 1984-07-23 1984-07-23 Joining method for underground continuous wall

Country Status (1)

Country Link
JP (1) JPS6131521A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020204222A (en) * 2019-06-19 2020-12-24 ケミカルグラウト株式会社 Earth retaining wall construction method

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0547060Y2 (en) * 1987-07-06 1993-12-10
JPH0547061Y2 (en) * 1987-09-24 1993-12-10
JPH02108827U (en) * 1989-02-18 1990-08-29
JPH02141331U (en) * 1989-05-01 1990-11-28

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020204222A (en) * 2019-06-19 2020-12-24 ケミカルグラウト株式会社 Earth retaining wall construction method

Also Published As

Publication number Publication date
JPS642728B2 (en) 1989-01-18

Similar Documents

Publication Publication Date Title
JPS6131521A (en) Joining method for underground continuous wall
JP3681314B2 (en) Water stop device used for small-scale continuous wall construction
KR100812845B1 (en) Device for facilitating the removal of formwork
JPH08246443A (en) Joint construction of great depth continuous underground wall reinforced cage
JP7012504B2 (en) How to build a jig for soil removal and a retaining wall
JP2007170145A (en) Stacked block
JPS63125721A (en) Construction of underground continuous wall and element coupler therefor
JPH0527542Y2 (en)
JPS6358976B2 (en)
JP7248558B2 (en) How to build a diaphragm wall
JPH09228365A (en) Washing method of steel material for underground continuous wall, and washing device
AT367130B (en) METHOD FOR PRODUCING A SLOT WALL IN THE GROUND FLOOR, FIRST POST-LIKE PRECAST CONCRETE PART, MOLDING BOX AND SECOND PLATE-SHAPED PRECAST CONCRETE PART FOR IMPLEMENTING THE METHOD
JPH0551727B2 (en)
JP2613541B2 (en) Underground diaphragm wall joint cleaning machine
JPH0516275Y2 (en)
JP2778318B2 (en) Slime removal method for excavation trench for underground wall construction
JP2987662B2 (en) How to build a continuous underground wall
JPH0517326B2 (en)
JPS63251518A (en) Construction of continuous underground wall
JPH05179804A (en) Concrete placing joint method in reverse depositing
JPH07173830A (en) Partition member of continuous underground wall
JPS61290114A (en) Coupler for underground continuous wall and its manufacture
JPH07113215B2 (en) Construction method of underground continuous wall joint
JPS6360325A (en) Caisson with coupler and its settlement
JPH06346445A (en) Joint cleaner of underground continuous wall