JPS6130904A - Method of installing rotor unit in field - Google Patents

Method of installing rotor unit in field

Info

Publication number
JPS6130904A
JPS6130904A JP15073784A JP15073784A JPS6130904A JP S6130904 A JPS6130904 A JP S6130904A JP 15073784 A JP15073784 A JP 15073784A JP 15073784 A JP15073784 A JP 15073784A JP S6130904 A JPS6130904 A JP S6130904A
Authority
JP
Japan
Prior art keywords
rotating body
work
rotary body
cable
row
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15073784A
Other languages
Japanese (ja)
Inventor
本庄 正樹
薮田 均
憲正 吉田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Power Reactor and Nuclear Fuel Development Corp
Original Assignee
Toshiba Corp
Power Reactor and Nuclear Fuel Development Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp, Power Reactor and Nuclear Fuel Development Corp filed Critical Toshiba Corp
Priority to JP15073784A priority Critical patent/JPS6130904A/en
Publication of JPS6130904A publication Critical patent/JPS6130904A/en
Pending legal-status Critical Current

Links

Landscapes

  • Electric Cable Installation (AREA)
  • Manufacture Of Motors, Generators (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の技術的分野〕 本発明は回転体装置の現場据付工法に関わり、特に回転
体装置本体の据付および回転機駆動用電動機への給電ケ
ーブルの布設工法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to a method for on-site installation of a rotating body device, and particularly to a method for installing a body of a rotating body device and laying a power supply cable to a motor for driving a rotating machine.

〔発明の技術的背景およびその問題点〕第1図および第
2図は、回転体vit置を主体とする電動機プラントの
機器の基本的な配置を示す図であり、回転体装置A1〜
A8が基盤1上に複数列(図では2列)に据付けられて
いる。また、上記複数列の回転体装置A1−八8の両側
には基盤1上にケーブルトレイ2a、2bが設けられ、
そのケーブルトレイ2a、 2b内には、通常回転体装
置A1−八8の列の一端部に据付けられたiii源と回
転体装置1A1〜八8の各端子台3間に延びるケーブル
4(図には1本のみ示す)が敷設されている。
[Technical Background of the Invention and Problems Therewith] FIGS. 1 and 2 are diagrams showing the basic arrangement of equipment in an electric motor plant mainly consisting of rotating body devices A1 to A1.
A8s are installed on the base 1 in a plurality of rows (two rows in the figure). Further, cable trays 2a and 2b are provided on the base 1 on both sides of the plurality of rows of rotating body devices A1-88,
Inside the cable trays 2a and 2b, cables 4 (not shown in the figure) extend between the iii source installed at one end of the row of rotating body devices A1-88 and each terminal block 3 of the rotating body devices 1A1-88. (only one line is shown) has been installed.

一方、通常の電動機プラントでは回転体装置A1−八8
のみが単独で存在する場合は少なく、多くの場合回転体
装置A1−八8は相互にプロセス配管で接続どれている
。すなわち、回転体装置A1〜A4またはA5〜A8の
上部には、第2図に示すようにその列と平行に上部配管
5a、5bが配管サポート6a、6b上に取付けられて
おり、さらに回転体装置の各列の一側下部には下部配管
7a、7bが配設されている。
On the other hand, in a normal electric motor plant, the rotating body device A1-88
There are few cases in which only one rotor exists, and in many cases, the rotating body devices A1-88 are connected to each other by process piping. That is, as shown in FIG. 2, upper piping 5a, 5b is installed on piping supports 6a, 6b on the upper part of the rotating body apparatuses A1 to A4 or A5 to A8 in parallel with the row, and furthermore, the rotating body apparatus Lower pipes 7a and 7b are arranged at the lower part of one side of each row of devices.

このように、電動機プラントにおいては一般に各種の機
器、プロセス配管等が混在しており、かつ据付面積の縮
小の目的で各々がかなり稠密に配置・据付けられざるを
得ない。したがって、各々の機器据付けの現地工事の作
業性が悪い上、各現地工事の工期が錯綜しないような工
程調整が一般に困難である。
As described above, in an electric motor plant, various types of equipment, process piping, etc. are generally mixed, and in order to reduce the installation area, each of them must be arranged and installed quite densely. Therefore, the workability of the on-site construction work for installing each device is poor, and it is generally difficult to adjust the schedule so that the construction period of each on-site construction work is not complicated.

そこで、従来現地工事にあたっては、先づ回転体装置A
1−八8を搬入・据付【ブる。すなわち、第3図に示す
ように回転体装置を運搬用台車8に乗せて第1図に矢印
へで示す方向より奥側の回転体装置A1またはA5から
順に手前の方向の回転体装置を搬入し、順次所定位置に
据付ける。その後、各回転体装置に装着されている配管
サポート5a、5b上に上部配管5a、5bを取付ける
Therefore, conventionally, when performing on-site construction, first
1-88 was brought in and installed. That is, as shown in FIG. 3, the rotary body devices are placed on the transport trolley 8, and the rotary body devices A1 or A5 on the far side are carried in in order from the direction indicated by the arrow in FIG. and install them in the designated positions one after another. Thereafter, the upper pipes 5a, 5b are attached to the pipe supports 5a, 5b mounted on each rotating body device.

この場合、上述のようにすでに回転体装置1A1〜八8
が据付けであるので、上部配管5a、5bは、車輪部9
a、9bが回転体装置fAl等の両側を走行する配管運
搬台車9により適当な箇所に搬入された後、配管運搬台
車9より荷おろしされ、配管サポート6a、6b上に取
付けられる。この荷お−ろし、取付けの作業の際の作業
員10の足場は、上記配管運搬台車9が兼用される。
In this case, as described above, the rotating body devices 1A1 to 88
is installed, the upper pipes 5a and 5b are connected to the wheel part 9.
After the tubes a and 9b are carried to an appropriate location by the pipe carrier 9 running on both sides of the rotating body device fAl, etc., they are unloaded from the pipe carrier 9 and mounted on the pipe supports 6a and 6b. The pipe transport cart 9 is also used as a scaffold for the worker 10 during this unloading and installation work.

このようにして上部配管5a、5bが取付けられると、
その後上部配管5a、5bの漏洩試験を実施する。すな
わち、第4図に示すように漏洩試験の作業員10の乗る
足場118.11bを回転体装置A1の両側に立て、そ
の足場11a、11bに作業員10が乗って上部配管5
aをアクセスして漏洩試験を実施する。
When the upper pipes 5a and 5b are installed in this way,
Thereafter, a leakage test is performed on the upper pipes 5a and 5b. That is, as shown in FIG. 4, scaffolds 118 and 11b on which the leak test worker 10 stands are erected on both sides of the rotating body apparatus A1, and the worker 10 stands on the scaffolds 11a and 11b and connects the upper pipe 5.
Access a and perform a leak test.

このようにして回転体装置fA1〜八8の搬入・据付、
上部配管5a、5bの搬入・取付、および漏洩試験が修
了したら、次に下部配管7a、7bの取付作業を行ない
、その後ケーブルトレイ2a。
In this way, the transport and installation of the rotating body devices fA1 to fA88,
After carrying in and installing the upper pipes 5a and 5b and completing the leakage test, the lower pipes 7a and 7b are next installed, and then the cable tray 2a is installed.

2bの取付けと、ケーブル4の敷設、端子台3へのケー
ブル4の接続作業を実施する。この一連の作業修了後、
下部配管7a、7bの漏洩試験やケーブル4の電気的な
試験・検査を実施して全工事が完了する。
2b, laying the cable 4, and connecting the cable 4 to the terminal block 3. After completing this series of work,
Leak tests on the lower piping 7a and 7b and electrical tests and inspections on the cable 4 are carried out to complete the entire construction work.

上記一連の作業の工程を示したものが第5図である。た
だし、第5図は各作業の実施順序を示すものであり、各
作業の工期については想定したものであって、また下部
配管7a、7bの取付工事については第5図では省略し
た。
FIG. 5 shows the steps of the above-mentioned series of operations. However, FIG. 5 shows the order of implementation of each work, and the construction period of each work is assumed, and the installation work of the lower pipes 7a and 7b is omitted in FIG.

しかしながら、上記据付方法においては、第5図からも
明らかなように全ての工事がシリーズに実施されざるを
得ないので、総工期が長くなる等の問題がある。
However, in the above installation method, as is clear from FIG. 5, all the construction work has to be carried out in series, so there are problems such as a long total construction period.

すなわち、「上部配管の搬入・取付」工事は、配管サポ
ート6a、6bが回転体装置AI 、 A2・・・にそ
れぞれ設けられているため、[回転体装置の搬入・据付
」工事の修了後に実施せざるを得ない。また、[上部配
管の漏洩試験]も「上部配管の搬入・取付」俄に実施す
る必要がある。しかも、配管運搬台車の車輪部が通過し
たり、或は上部配管の漏洩試験の作業員が乗る足場が組
立てられる場所に、ケーブルトレイ2a、2bが設置さ
れる関係上、上記上部配管の漏洩試験が修了するまでは
ケーブルトレイ2a、2bの取付けや、ケーブル4の敷
設作業を実施することができず、電気工事やそれに続く
電気工事試験は、上部配管の漏洩試験の修了後に実施せ
ざるを得ない。このため回転体装置の搬入・組立等の工
事に加え、電気工事等が全てシリーズに実施されること
となり、全工期が長くなってしまい、各工事の工程調整
範囲もなく、現地工事工程が非常に厳しくなってしまう
等の問題がある。
In other words, since the piping supports 6a and 6b are installed on the rotating body devices AI, A2, etc., the “transporting and installing the upper piping” work will be carried out after the “transporting and installing the rotating body device” work is completed. I have no choice but to do it. In addition, a [leakage test for the upper piping] must be conducted before the upper piping is brought in and installed. Furthermore, since the cable trays 2a and 2b are installed in a place where the wheels of the pipe transport truck pass or where the scaffolding on which the worker for the leak test of the upper pipe is mounted is assembled, the above-mentioned leak test of the upper pipe is carried out. The installation of cable trays 2a and 2b and the laying of cables 4 cannot be carried out until the completion of the electrical work, and the electrical work and the subsequent electrical work test must be carried out only after the leakage test of the upper piping is completed. do not have. For this reason, in addition to the work such as transporting and assembling the rotating body equipment, all electrical work etc. will be carried out in series, resulting in a long overall construction period, and there is no scope for schedule adjustment for each work, making the on-site construction schedule extremely difficult. There are problems such as becoming stricter.

〔発明の目的〕[Purpose of the invention]

本発明はこのような点に鑑み、回転体B@の現地工事の
工期を短縮するとともに工程調整を容易にでき、工事黄
を低減させることができるようにした回転体装置の現場
据付工法を得ることを目的とする。
In view of these points, the present invention provides a method for on-site installation of a rotating body device that shortens the construction period for on-site construction of the rotating body B@, facilitates process adjustment, and reduces construction yellowing. The purpose is to

(発明の概要〕 本発明は、複数の回転機を共通架台上に取付けた回転体
装置を複数台2列平行に配置する回転体装置プラントに
おいて、一方の列の回転体装置群の該回転体装置または
該回転体装置の上部配管の搬入・取付は作業を実施する
のと同時期に、他方の列の回転体装置群の外側のビット
内に回転体装置に給電ケーブルを敷設する作業、または
該回転体装置への給電ケーブルの接続作業および電気工
事試験を行なうことを特徴とするものである。
(Summary of the Invention) The present invention provides a rotating body equipment plant in which a plurality of rotating body devices each having a plurality of rotating machines mounted on a common pedestal are arranged in two parallel rows. Carrying in and installing the equipment or the upper piping of the rotating body equipment is carried out at the same time as the work is being carried out, and the power supply cable to the rotating body equipment is laid in the outside bit of the rotating body equipment group in the other row, or The feature is that a power supply cable is connected to the rotating body device and an electrical work test is performed.

〔発明の実施例〕[Embodiments of the invention]

以下、第6図および第7図を参照して本発明の一実施例
について説明する。
An embodiment of the present invention will be described below with reference to FIGS. 6 and 7.

第6図は本発明の据付工法を適用する回転体装置プラン
トの回転体装置まわりの機器配置を示す図であって、回
転体装置A1の列およびA5の列の各外側にはビット1
2a、12bが設けられており、その両ビット12a、
12b内にケーブル敷設用台床13a、13bが取付け
られている。
FIG. 6 is a diagram showing the equipment arrangement around the rotary body device of a rotary body device plant to which the installation method of the present invention is applied.
2a, 12b are provided, both bits 12a,
Cable laying platforms 13a and 13b are installed in 12b.

このケーブル敷設用台床13a、13bは従来のケーブ
ルトレイと異なり、側面板がなく丁度ケーブルトレイの
底板に相当するものであって、このケーブル敷設用台床
13a、13bとビットさ 12a、12bの内壁とに囲まれたスペースにケーブル
4が敷設される。また、このビット12a。
These cable laying bases 13a, 13b differ from conventional cable trays in that they do not have side plates and correspond to the bottom plate of the cable tray, and the cable laying bases 13a, 13b and the bits 12a, 12b are similar to each other. A cable 4 is laid in a space surrounded by an inner wall. Also, this bit 12a.

12bには上蓋14a、14bが装着され、この上蓋1
4a、14bの適所に開けられた穴を通してケーブル4
が床上に引き出され、後は従来例同様に回転体装置AI
 、 A2 、・・・の各端子台3に接続されるように
しである。その他の点は従来のプラントと全く同一であ
る。
Upper lids 14a and 14b are attached to the upper lid 12b.
Pass the cable 4 through the holes drilled at the appropriate locations in 4a and 14b.
is pulled out onto the floor, and then the rotating body device AI
, A2, . . . are connected to each terminal block 3. Other points are exactly the same as the conventional plant.

しかして、回転体装置等の搬入・据付工事に際しては、
回転体装置の搬入・据付工事と平行して電気工事を実施
する。すなわち、合板りに回転体装置A1の列が搬入・
据付けられているときに、ビット12b内にケーブル敷
設用台床13bを装着し、そのケーブル敷設用台床13
b上にケーブル4を敷設する。次に、回転体装置A5の
列の搬入・据付は工事が行なわれているときに、ビット
12a内にケーブル敷設用台床13aを装着するととも
に、その上にケーブル4を敷設づる。このようにして、
[回転体装置の搬入・据付1とケーブル敷設等の「電気
工事」の対象を互いに逆の列にすることにより、上記2
工事の錯綜を完全に避けることができる。またこの時点
の電気工事においては、ビット128.12b内にケー
ブル4を敷設した後には上蓋14a、14bが装着され
、これにより後に続く工事のための足場を確保する。
However, when carrying in and installing rotating body equipment, etc.,
Electrical work will be carried out in parallel with the delivery and installation of the rotating body equipment. In other words, a row of rotating body devices A1 is carried in on a plywood board.
When installed, the cable-laying platform 13b is installed inside the bit 12b, and the cable-laying platform 13b is installed inside the bit 12b.
Lay the cable 4 on b. Next, when the row of rotary body devices A5 is carried in and installed, the cable laying platform 13a is installed in the bit 12a, and the cable 4 is laid on it. In this way,
[By arranging the objects of "carrying in and installing rotating body equipment 1" and "electrical work" such as cable laying in opposite rows, the above 2.
Construction complications can be completely avoided. Further, in the electrical work at this point, after the cable 4 is laid inside the bit 128, 12b, the upper covers 14a, 14b are attached, thereby securing a scaffold for the subsequent work.

以上の要領で「回転体装置の搬入・据付」と「電気工事
」が修了すると、次に[上部配管の搬入・取付]と[上
部配管の漏洩試験」を実施する。
Once the "transportation and installation of the rotating body equipment" and "electrical work" are completed in the manner described above, the next step is to carry out the "transportation and installation of the upper piping" and the "leakage test for the upper piping."

この2工事はその性質上シリーズに実施せざるを得ない
が、従来方式と異なり、この2工事と同時に「′N1気
工事」と「電気工事試験」を実施できる。
Due to their nature, these two works have to be carried out in series, but unlike the conventional method, the ``'N1 air work'' and the ``electrical work test'' can be carried out at the same time as these two works.

すなわち、「回転体装置の搬入・据付」と同時に実施し
た「電気工事」で残された分、つまりケーブル4の引き
出し作業と端子台3への接続作業と、電気工事試験を実
施する。その要領は、前記回転体装置の搬入・据付と電
気工事を並列展開させた時と全く同様で、互いに異なる
列の該当作業を実施すればよい。例えば上部配管5bの
搬入・取付時にビット12a内のケーブル4の引き出し
作業と端子台3への接続作業および電気工事試験を実施
する。
That is, what was left over from the "electrical work" carried out at the same time as the "carrying in and installation of the rotating body device", that is, the work of drawing out the cable 4, the work of connecting it to the terminal block 3, and the electrical work test are performed. The procedure is exactly the same as when carrying in and installing the rotary body device and the electrical work are performed in parallel, and the corresponding work can be carried out in different columns. For example, when the upper pipe 5b is carried in and installed, the cable 4 in the bit 12a is pulled out, the cable 4 is connected to the terminal block 3, and an electrical work test is performed.

このようにすることによって、「上部配管の搬入・取付
け」と該電気工事の残作業および「電気工事試験」との
両者を錯綜することもなくスムーズに行なうことができ
る。上記各工事工程を第7図に示す。
By doing this, it is possible to smoothly carry out both the "carrying in and installation of the upper piping", the remaining work of the electrical work, and the "electrical work test" without any complications. Figure 7 shows each of the above construction steps.

なお、上記実施例においては電気工事を回転体装置の搬
入・据付と並行に実施するようにしたものを示したが、
上記電気工事の実施時期はそれに限られることはなく、
回転体装置の搬入・据付に先んじて実施することもでき
る。すなわち、予めケーブル敷設用台床13a、13b
を装着し、その上にケーブル4を敷設し、その後上蓋1
4a。
In addition, in the above example, the electrical work was carried out in parallel with the delivery and installation of the rotating body device, but
The implementation timing of the above electrical work is not limited to that,
It can also be carried out prior to the delivery and installation of the rotating body device. In other words, the cable laying platforms 13a, 13b are installed in advance.
, lay the cable 4 on top of it, and then attach the top cover 1.
4a.

14bを装着しておき、その後回転体装置A1の列の回
転体装置の搬入・据付を行なう。その際ビット12aに
は上蓋14aが装着しであるため回転体装置A1の列の
搬入・据付の作業には何ら支障はない。そして、上記回
転体装置A1の列の搬入・据付が終り、回転体装置fA
5の列の搬入・据付作業が開始されると同時に予め敷設
されているビット12a内のケーブル4の引き出しと端
子台3への接続作業を開始する。そしてそれに引く続き
電気工事試験も実施する。その後、回転体装置A5の列
の回転体装置の搬入・据付と、回転体装置A1の列のケ
ーブル引き出しおよび接続と電気工事試験が修了した時
点で、次は回転体装置A1の列の上部配管の搬入・取付
作業と並行して1、回転体装置A5の列の残電気工事と
電気工事試験を実施1′る。
14b is installed, and then the rotary body devices in the row of rotary body devices A1 are carried in and installed. At this time, since the upper cover 14a is attached to the bit 12a, there is no problem in carrying in and installing the row of rotating body devices A1. Then, the transport and installation of the row of rotating body devices A1 is completed, and the rotating body device fA
At the same time as the carrying-in and installation work for row No. 5 is started, the work of pulling out the cable 4 in the bit 12a that has been laid out in advance and connecting it to the terminal block 3 starts. Following this, an electrical work test will also be conducted. After that, when the rotary body devices in the row of rotary body devices A5 are brought in and installed, the cables are pulled out and connected in the row of rotary body devices A1, and the electrical work test is completed, the next step is to move on to the upper piping of the row of rotary body devices A1. In parallel with the transport and installation work, the remaining electrical work and electrical work tests for the row of rotating body devices A5 will be carried out 1'.

このようにして、複数工事を順次同時展開して行なうこ
とが可能である。この例のように回転体装置の搬入・据
付前に電気工事を実施することは、第一実施例に比べ全
体の工程が長くなる欠点はあるが、作業員や工事資材の
割当の均一化、いわゆる現地工事仕事量の平準化を図る
ことができる。
In this way, it is possible to sequentially and simultaneously develop multiple construction projects. Performing electrical work before transporting and installing the rotary body equipment as in this example has the disadvantage that the overall process is longer than in the first example, but it also helps ensure uniform allocation of workers and construction materials. It is possible to level out the so-called on-site construction workload.

〔発明の効果〕〔Effect of the invention〕

以上説明したように、本発明は一方の列の回転体装置の
搬入・据付工事と同時に他方の列の電気工事等を行なう
ようにしたので、プラント全体の工程を大幅に短縮する
ことができ、また電気工事の実施時期を従来例に比べ冬
期に選定できるため、現地工事の仕事量の平準化や各仕
事の工程調整の幅を大きくすることができて、全工程に
添い各工事をスムーズに行なうことができる。さらに、
床上めケーブルトレイを排したことでその部分を歩行通
路として使用できることで敷地の有効利用が可能であり
、下部配管へのアクセスも容易となり、工事後の機器の
試験や保守の作業性を大幅に改善することができる等の
効果を奏する。
As explained above, according to the present invention, electrical work, etc., are carried out on the other row at the same time as the transport and installation of the rotary body devices on one row, so that the overall process of the plant can be significantly shortened. In addition, since electrical work can be carried out in the winter compared to conventional methods, it is possible to level out the workload of on-site construction and increase the range of schedule adjustment for each job, allowing each job to be carried out smoothly throughout the entire process. can be done. moreover,
By eliminating the above-the-floor cable tray, the area can be used as a walking path, allowing for effective use of the site. Access to the lower piping is also easier, which greatly improves the efficiency of equipment testing and maintenance after construction. It has effects such as being able to improve the situation.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来プラントにおける回転体装置と周辺機器の
配置図、第2図は第1図の矢視図、第3図は回転体装置
の搬入および上部配管の搬入・取付作業の説明図、第4
図は上部配管の漏洩試験の要領図、第5図は従来の工事
工程表、第6図は本発明における機器配置図、第7図は
本発明の一実施例における工事工程表である。 AI 、 A2〜A8 ・・・回転体装置、2a、2b
−・・ケーブルトレイ、3・・・端子台、4・・・ケー
ブル、5a、5b・・・上部配管、6a、6b・・・配
管サポート、7a、7b−・・下部配管、Ila、11
b、、、足場、12a、12b−=ビット、13a、1
3b・=ケーブル敷設用台床、14a、14b・・・上
蓋。 出願人代理人  猪  股     清第1閥 JP)2図 筋3園 第4− 第5園
Fig. 1 is a layout diagram of the rotating body device and peripheral equipment in a conventional plant, Fig. 2 is a view taken in the direction of the arrow in Fig. 1, and Fig. 3 is an explanatory diagram of carrying in the rotating body device and carrying in and installing the upper piping. Fourth
5 is a conventional construction schedule, FIG. 6 is an equipment layout diagram according to the present invention, and FIG. 7 is a construction schedule according to an embodiment of the present invention. AI, A2-A8...Rotating body device, 2a, 2b
-... Cable tray, 3... Terminal block, 4... Cable, 5a, 5b... Upper piping, 6a, 6b... Piping support, 7a, 7b-... Lower piping, Ila, 11
b, Scaffolding, 12a, 12b-=Bit, 13a, 1
3b = cable laying platform, 14a, 14b... upper cover. Applicant's agent Inomata Kiyoshi 1st branch JP) 2 Zusuji 3rd garden 4th - 5th garden

Claims (1)

【特許請求の範囲】[Claims] 回転体装置を複数台2列平行に配置する回転体装置プラ
ントにおいて、一方の列の回転体装置群の該回転体装置
または該回転体装置の上部配管の搬入・取付け作業を実
施するのと同時期に、他方の列の回転体装置群の外側の
ビット内に回転体装置への給電ケーブルを布設する作業
、または該回転体装置への給電ケーブルの接続作業およ
び電機工事試験を行なうことを特徴とする、回転体装置
の現場据付工法。
In a rotary body equipment plant where multiple rotary body units are arranged in two rows in parallel, this is the same as carrying in and installing the rotary body unit or the upper piping of the rotary body unit in one row of rotary body units. During this period, the work of laying the power supply cable to the rotary body device in the outside bit of the group of rotary body devices in the other row, the work of connecting the power supply cable to the rotary body device, and the electrical work test are carried out. An on-site installation method for rotating body equipment.
JP15073784A 1984-07-20 1984-07-20 Method of installing rotor unit in field Pending JPS6130904A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15073784A JPS6130904A (en) 1984-07-20 1984-07-20 Method of installing rotor unit in field

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15073784A JPS6130904A (en) 1984-07-20 1984-07-20 Method of installing rotor unit in field

Publications (1)

Publication Number Publication Date
JPS6130904A true JPS6130904A (en) 1986-02-13

Family

ID=15503308

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15073784A Pending JPS6130904A (en) 1984-07-20 1984-07-20 Method of installing rotor unit in field

Country Status (1)

Country Link
JP (1) JPS6130904A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62283132A (en) * 1987-05-15 1987-12-09 Kanegafuchi Chem Ind Co Ltd Production of laminate for electricity
JPS63124494A (en) * 1986-11-13 1988-05-27 昭和高分子株式会社 Electric circuit laminated board and manufacture of the same

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63124494A (en) * 1986-11-13 1988-05-27 昭和高分子株式会社 Electric circuit laminated board and manufacture of the same
JPS62283132A (en) * 1987-05-15 1987-12-09 Kanegafuchi Chem Ind Co Ltd Production of laminate for electricity

Similar Documents

Publication Publication Date Title
US9376828B2 (en) Modular processing facility
JPS6130904A (en) Method of installing rotor unit in field
US7569946B2 (en) Turbine-generator equipment and installation method thereof
JP5389547B2 (en) Data center building
SE528325C2 (en) Transformer station, method of making such and use
CN102733614A (en) Method for constructing room module of nuclear power plant
JPH05107381A (en) Method for constructing nuclear power plant reactor
JPS61162679A (en) Construction of nuclear reactor plant
KR102052680B1 (en) Construction method of standing module for building
JPH0718887A (en) Method for construction thermal power plant
JPH0644839A (en) Working device for wiring unit
TW202314099A (en) A data centre system and method of construction
CN110971147B (en) Construction method of static variable-frequency starting system of large-sized camera set
JP2003207588A (en) Construction method of nuclear reactor building
JPS62228975A (en) Method of construction of nuclear plant
JP2007247215A (en) Duct construction method
JPS61286462A (en) Integral suspension construction method of iron beam and pipings of atomic power plant building
JP3015229B2 (en) Construction method of vertical pipe of high-rise building
CN116073285A (en) Standardized offshore oil platform cable integrated installation method
CN107269928A (en) A kind of construction method of large-scale Pipe installing arranged side by side
CN116480157A (en) Hoisting method for large-span roof steel structure
JP2011225021A (en) Carrier for prefabricated frame for solar battery
JPH07184312A (en) Installation of field electric room and control room in power plant
CN111005564A (en) Construction method based on steel structure on waffle floor
CN107525989A (en) Battery management unit plug and pull out detector