JPS61268589A - Transportation of plant unit - Google Patents

Transportation of plant unit

Info

Publication number
JPS61268589A
JPS61268589A JP10925185A JP10925185A JPS61268589A JP S61268589 A JPS61268589 A JP S61268589A JP 10925185 A JP10925185 A JP 10925185A JP 10925185 A JP10925185 A JP 10925185A JP S61268589 A JPS61268589 A JP S61268589A
Authority
JP
Japan
Prior art keywords
plant unit
transportation
plant
board
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10925185A
Other languages
Japanese (ja)
Inventor
Juichi Hisatomi
久富 寿一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Engineering and Shipbuilding Co Ltd
Original Assignee
Mitsui Engineering and Shipbuilding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Engineering and Shipbuilding Co Ltd filed Critical Mitsui Engineering and Shipbuilding Co Ltd
Priority to JP10925185A priority Critical patent/JPS61268589A/en
Publication of JPS61268589A publication Critical patent/JPS61268589A/en
Pending legal-status Critical Current

Links

Landscapes

  • Ship Loading And Unloading (AREA)

Abstract

PURPOSE:To assure safe and easy transportation to a carrying vessel or the like by using moving trucks having on the upper side lifting blocks on which a plant unit is placed. CONSTITUTION:In order to move a plant unit 1 put on fixed blocks 17, a plurality of moving trucks 4 having on the upper side lifting blocks 7 are moved in spaces l between the fixed blocks 17. The plant unit 1 is transferred onto the lifting blocks 7 of the moving trucks 4 and carried to a predetermined carrying vessel 18 or the like. Thus, transportion of the plant unit 1 can be performed safely and easily.

Description

【発明の詳細な説明】 〔発明の技術分野〕 本発明はプラントユニットの輸送方法、より詳しくは、
比較的低開発地にプラントを建設する場合に多く採用さ
れるプラントユニットの輸送方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to a method for transporting a plant unit, and more particularly, to a method for transporting a plant unit.
This invention relates to a method of transporting plant units, which is often adopted when constructing a plant in a relatively underdeveloped area.

〔従来の技術〕[Conventional technology]

一般に比較的低開発地に各種プラントを建設する場合、
現地工事を少なくするため、プラントに使用される機器
をあらかじめユニット化し、これを現地へ輸送し据付け
ることが行なわれている。そして、このユニットも海上
輸送する必要から一パージとして形成される。
Generally, when constructing various plants in relatively underdeveloped land,
In order to reduce the amount of on-site construction work, equipment used in plants is pre-assembled into units, which are then transported to the site and installed. This unit was also formed as a purge because it needed to be transported by sea.

更に詳しくは、第11図ないし第12図に示されるよう
に、プラントユニット1は陸上に配設された多数の盤木
2上で建造され(第11図)、進水後曳航もしくは第1
2図に示すように必要に応じて輸送用バージ3上に搭載
され据付現地まで輸送される。
More specifically, as shown in Figs. 11 and 12, the plant unit 1 is constructed on a number of boards 2 placed on land (Fig. 11), and after being launched, it is towed or the first
As shown in Figure 2, it is loaded onto a transportation barge 3 and transported to the installation site as required.

ところで、かかるプラントユニット1は通常大重量構造
物となるため、建造場所からの進水作業や輸送用バージ
3上への搭載、更には現地到着後の据付現場への輸送は
慎重を要するものであり、特に現地到着したプラントユ
ニット1を陸上に引揚げ輸送することは殆ど不可能であ
り、そのため、従来は一般に据付現地の海岸に湾状の池
を掘りここにプラントユニット1を引込んだ後、この池
を埋めもどして据付ける方法が採られている。しかし、
この方法によるとプランドユニット1への浸水の恐れが
あり、かつ地堀りゃ埋めもどし等に多大の時間と労力を
必要とし、その結果工期が長くかかり建造費が増大する
等の問題点があった。
By the way, such a plant unit 1 is usually a heavy structure, and therefore, careful work is required when launching it from the construction site, loading it onto the transportation barge 3, and furthermore, transporting it to the installation site after arriving at the site. In particular, it is almost impossible to lift up and transport the plant unit 1 to land after it has arrived at the site.Therefore, conventionally, a bay-shaped pond was generally dug on the coast of the installation site and the plant unit 1 was pulled into the pond and then transported. The method used is to refill the pond and install it. but,
According to this method, there is a risk of water intrusion into Planned Unit 1, and it requires a great deal of time and effort for digging and refilling the ground, resulting in longer construction times and higher construction costs. .

〔発明の目的〕[Purpose of the invention]

本発明は前記した問題点を解決するためになされたもの
であって、その目的は、特に大重量構造物を現地到着後
、陸上へ引揚げ輸送することによって据付工期の短縮等
を計って建造費を低減させることにある。
The present invention has been made in order to solve the above-mentioned problems, and its purpose is to shorten the installation period by hoisting and transporting large heavy structures to land after they arrive at the site. The goal is to reduce costs.

〔発明の概要〕[Summary of the invention]

前記目的を達成するための本発明は、車体の下部に多数
の車輪を配設し、その上部に上下動可能に盤木を設けた
受台を長手方向に複数個配置して移送台車を構成し、前
記移送台車を少なくとも2台以上平行に配置して台車群
となし、前記台車群によりプラントユニットを支持して
移送するようにしたことを特徴とするプラントユニット
の輸送方法である。
To achieve the above-mentioned object, the present invention comprises a transportation trolley in which a large number of wheels are disposed at the lower part of the vehicle body, and a plurality of pedestals each having a board mounted on the upper part thereof which can be moved up and down are arranged in the longitudinal direction. The method for transporting a plant unit is characterized in that at least two of the transport carts are arranged in parallel to form a group of carts, and the plant unit is supported and transferred by the group of carts.

〔実 施 例〕〔Example〕

以下第1図ないし第10図に基づき本発明によるプラン
トユニットの輸送方法の実施例を説明する。
An embodiment of the method for transporting a plant unit according to the present invention will be described below with reference to FIGS. 1 to 10.

第1図は本発明のプラントユニットの輸送方法に使用さ
れる移送台車4の側面図、第2図はその平面図である。
FIG. 1 is a side view of a transfer trolley 4 used in the plant unit transportation method of the present invention, and FIG. 2 is a plan view thereof.

移送台車4は車体5の下部に多数の車輪6が設けられ、
その上部の長手方向には受台7が複数個適当な間隔を置
いて配設されている。
The transfer trolley 4 is provided with a large number of wheels 6 at the bottom of a vehicle body 5,
A plurality of pedestals 7 are arranged at appropriate intervals in the longitudinal direction of the upper part.

この受台7は第3図及び第4図に示されるように架台8
と上下動可能な盤木9とにより構成されている。なお、
盤木9等によりプラントユニットを移送台車4上に支持
する高さが充分である場合には、架台8を省略すること
ができるものである。
This pedestal 7 is connected to a pedestal 8 as shown in FIGS. 3 and 4.
and a board 9 that can be moved up and down. In addition,
If the height for supporting the plant unit on the transfer carriage 4 by the board 9 or the like is sufficient, the pedestal 8 can be omitted.

詳述すれば盤木9は台形盤木10.山形盤木11゜楔形
盤木12及び矩形盤木13とよりなり、台形盤木10は
ボルト14により、また山形盤木11はボルト15によ
り組立てられており、このボルト14又はボルト15を
締付け、又は緩めることにより矩形盤木13の上面は上
下動するようになっている。
To be more specific, the board 9 is a trapezoidal board 10. It consists of a chevron board 11, a wedge-shaped board 12, and a rectangular board 13. The trapezoid board 10 is assembled with bolts 14, and the chevron board 11 is assembled with bolts 15. Tighten these bolts 14 or bolts 15, Or, by loosening it, the upper surface of the rectangular board 13 can move up and down.

このように構成された移送台車4は少なくとも2台が平
行になるような台車群16となってプラントユニット1
を支持するようになっている(第5図)。
The transfer carts 4 configured in this way form a group of carts 16 in which at least two of them are parallel to each other, and are transferred to the plant unit 1.
(Figure 5).

次に具体的な輸送方法について説明する。Next, a specific transportation method will be explained.

第6図に示すように、プラントユニット1は陸上に間隔
lを置いて複数列配置された受台17上で建造される。
As shown in FIG. 6, the plant unit 1 is constructed on pedestals 17 arranged in a plurality of rows on land at intervals l.

この受台17は前述した移送台車4上に設けられた受台
7と同様に構成される。
This pedestal 17 is constructed in the same manner as the pedestal 7 provided on the transfer carriage 4 described above.

そして受台17の間隔lは移送台車4の幅Wより大とな
るように配置されている。このようにして建造されたプ
ラントユニット1の下部に移送台車4,4°を移動させ
、受台17のボルトを緩めることによりプラントユニッ
ト1は移送台車4.4°上に設けられた受台7で支持す
ることとなる。
The pedestals 17 are arranged so that the interval 1 is larger than the width W of the transfer carriage 4. By moving the transfer cart 4.4° to the lower part of the plant unit 1 constructed in this way and loosening the bolts of the pedestal 17, the plant unit 1 is moved to the pedestal 7 provided 4.4° above the transfer cart. It will be supported by

前記状態で岸壁20までプラントユニット1を移送し、
輸送用バージ18に搭載される(第7図)。輸送用バー
ジ18にも同様の受台19を配設してプラントユニット
1をこの受台19で支持するようにしてもよいが、必要
に応じて移送台車4を輸送用バージ18に固定してもよ
い。
Transfer the plant unit 1 to the quay 20 in the above state,
It is loaded on the transportation barge 18 (FIG. 7). A similar pedestal 19 may be provided on the transportation barge 18 so that the plant unit 1 can be supported by this pedestal 19, but if necessary, the transportation cart 4 may be fixed to the transportation barge 18. Good too.

然る後、輸送用バージ18を現地まで移送し、前記した
搭載手順と逆の作業によりプラントユニット1を陸揚げ
し据付現場へ輸送する。即ち、現地へ移送された輸送用
バージ18はその甲板18゛と岸壁20aがほぼ同一高
さとなるようバラスト調整されるとともに受台19のボ
ルトを緩めてプラントユニット1を移送台車4a上に支
持する。
Thereafter, the transportation barge 18 is transported to the site, and the plant unit 1 is unloaded and transported to the installation site by performing the reverse operation of the loading procedure described above. That is, the transportation barge 18 transferred to the site is ballast-adjusted so that its deck 18' and the quay wall 20a are approximately at the same height, and the bolts of the cradle 19 are loosened to support the plant unit 1 on the transfer trolley 4a. .

そして、この移送台車4を図示しない巻取装置に巻層さ
れたワイヤ21により引張ることにより陸揚げされる(
第8図)。
Then, this transport trolley 4 is pulled ashore by a wire 21 wound around a winding device (not shown).
Figure 8).

このようにして陸揚げされたプラントユニット1は据付
現場まで移送され、あらかじめ設けられた基礎上に移送
台車4上の受台7のボルトをゆるめることにより据付け
るのである。
The plant unit 1 landed ashore in this manner is transported to the installation site, and is installed on a previously provided foundation by loosening the bolts of the pedestal 7 on the transport trolley 4.

なお、基礎の配設やプラントユニット1の据付方法につ
いては、従来の方法を採用して行うことができる。
Note that conventional methods can be used to arrange the foundation and install the plant unit 1.

第9図はプラントユニット1を輸送用バージ18に搭載
する方法の一例を示すものであって、輸送用バージ18
にバラスト水を張って吃水を深く保ち、その甲板18°
上にプラントユニット1を曳航位置させてからバラスト
水を排出するのである。もちろんプラントユニット1を
輸送用バージ18から降ろす場合はこの逆を行なえばよ
い。
FIG. 9 shows an example of a method for mounting the plant unit 1 on the transportation barge 18.
The deck is filled with ballast water to keep the water deep, and the deck is 18°
The ballast water is discharged after the plant unit 1 is towed to the top. Of course, if the plant unit 1 is to be unloaded from the transport barge 18, the reverse procedure may be performed.

更に第10図は、プラントユニット1を陸揚げする場合
の一実施を示すもので、岸壁22にはあらかじめ傾斜面
23が設けられており、移送台車4がこの傾斜面23上
を走行可能なようになっている。そしてプラントユニッ
ト1はあらかじめ配置された移送台車4上にセットされ
、ここから陸上に引揚げられるのである。
Furthermore, FIG. 10 shows one implementation when the plant unit 1 is unloaded, and a slope 23 is provided in advance on the quay 22, so that the transfer cart 4 can run on this slope 23. It has become. The plant unit 1 is then set on a transport trolley 4 that has been placed in advance, and is lifted onto land from there.

〔発明の効果〕〔Effect of the invention〕

以上説明したように本発明によるプラントユニットの輸
送方法によれば、大重量構造物として構成されるプラン
トユニットを容易に陸揚げし、据付現場に移送し据付け
ることができるので比較的低開発基でのプラントの建設
工事の工期短縮と工費の低減を計ることができるばかり
でなく、その据付現場を陸上に選定することができ、そ
の結果プラントユニット1への浸水の恐れもなくなる等
幾多の利点を有する。
As explained above, according to the method for transporting a plant unit according to the present invention, a plant unit configured as a heavy structure can be easily landed, transported to an installation site, and installed, so that the plant unit requires relatively little development. This system not only shortens the construction period and costs for plant construction, but also allows the installation site to be selected on land, which eliminates the risk of water intrusion into plant unit 1, among other advantages. have

【図面の簡単な説明】[Brief explanation of the drawing]

第1図ないし第10図は本発明によるプラントユニット
の輸送方法の実施を示すものであって、第1図は移送台
車の側面図、第2図はその平面図、第3図は第1図A部
の拡大図、第4図は第3図のA−A矢視図、第5図は台
車群の説明図、第6図ないし第10図はプラントユニッ
ト建造から据付までの方法を説明するものであって、第
6図は建造方法、第7図は輸送用パージへの搭載方法、
第8図は陸揚げ方法、第9図は輸送用パージへの例の搭
載方法、第10図は他の陸揚げ方法を示すものである。 第11図及び第12図は従来のプラントユニットの輸送
方法を示すものであって、第11図は建造方法、第12
図は輸送方法の説明図である。 1・・・プラントユニット、2.9・・・盤木、3゜1
8・・・輸送用パージ、4・・・移送台車、5・・・車
体、6・・・車輪、7.17.19・・・受台、8・・
・架台、lO・・・台形盤木、11・・・山形盤木、1
2・・・模形盤木、13・・・矩形盤木、14.15・
・・ボルト、16・・・台車群、20.20a22・・
・岸壁、21・・・ワイヤ、23・・・傾斜面。
1 to 10 show the implementation of the method for transporting plant units according to the present invention, in which FIG. 1 is a side view of the transport cart, FIG. 2 is a plan view thereof, and FIG. 3 is the same as that shown in FIG. 1. An enlarged view of part A, Figure 4 is a view from the A-A arrow in Figure 3, Figure 5 is an explanatory diagram of the group of bogies, and Figures 6 to 10 explain the method from construction to installation of the plant unit. Fig. 6 shows the construction method, Fig. 7 shows the method of loading it on the transport purge,
FIG. 8 shows a landing method, FIG. 9 shows an example loading method on a transportation purge, and FIG. 10 shows another landing method. 11 and 12 show a conventional method of transporting a plant unit, and FIG. 11 shows a construction method,
The figure is an explanatory diagram of the transportation method. 1... Plant unit, 2.9... Board, 3゜1
8... Transport purge, 4... Transfer trolley, 5... Vehicle body, 6... Wheels, 7.17.19... cradle, 8...
・Frame, lO... Trapezoid board, 11... Yamagata board, 1
2... Model board, 13... Rectangular board, 14.15.
...Bolt, 16...Bogie group, 20.20a22...
- Quay wall, 21...wire, 23...slope surface.

Claims (1)

【特許請求の範囲】[Claims] 車体の下部に多数の車輪を配設し、その上部に上下動可
能に盤木を設けた受台を長手方向に複数個配置して移送
台車を構成し、前記移送台車を少なくとも2台以上平行
に配置して台車群となし、前記台車群によりプラントユ
ニットを支持して移送するようにしたことを特徴とする
プラントユニットの輸送方法。
A transfer cart is constructed by disposing a plurality of wheels in the lower part of the car body, and a plurality of cradle having a board installed on the upper part thereof so as to be movable up and down in the longitudinal direction, and at least two or more said transfer carts are arranged in parallel. A method for transporting a plant unit, characterized in that the plant units are arranged to form a group of carts, and the plant unit is supported and transported by the group of carts.
JP10925185A 1985-05-23 1985-05-23 Transportation of plant unit Pending JPS61268589A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10925185A JPS61268589A (en) 1985-05-23 1985-05-23 Transportation of plant unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10925185A JPS61268589A (en) 1985-05-23 1985-05-23 Transportation of plant unit

Publications (1)

Publication Number Publication Date
JPS61268589A true JPS61268589A (en) 1986-11-28

Family

ID=14505440

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10925185A Pending JPS61268589A (en) 1985-05-23 1985-05-23 Transportation of plant unit

Country Status (1)

Country Link
JP (1) JPS61268589A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190111972A (en) * 2017-02-02 2019-10-02 테크니프 프랑스 에스.아.에스. How to assemble the device placed in the body of water

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190111972A (en) * 2017-02-02 2019-10-02 테크니프 프랑스 에스.아.에스. How to assemble the device placed in the body of water

Similar Documents

Publication Publication Date Title
US6802684B2 (en) Container tranfer terminal system and method
US6213319B1 (en) Powered lifting apparatus using multiple booms
EP0094434A1 (en) Work ship for installing large offshore structure
US4283890A (en) Transportable bed for industrial equipment
WO1994006677A1 (en) A method and a system for transporting vehicles
CN1126687C (en) Method and device for securing horizontally loaded cargo units to a vessel
JPS61268589A (en) Transportation of plant unit
US6601717B1 (en) Powered lifting apparatus using multiple booms
US4106638A (en) Ship and shore load handling system with an asymmetrical shaped pontoon for supporting carriage cables
JP2631366B2 (en) Relocated resort hotel
JP2676257B2 (en) Underwater concrete box shipping facility
JPS597630A (en) Floating unloader
US2619066A (en) Method and means for stowing cargo in vessels
CN112227214B (en) Splicing structure of steel members and mounting method thereof
JP2708498B2 (en) Boat storage facility
JPH09151462A (en) Slipway type caisson launching installation
JPS593318B2 (en) How to transport a large constructed structure from a dock to a floating body for waiting transportation
JP3268199B2 (en) Floating body launch equipment
SU1052613A1 (en) Pier
JPS5847393B2 (en) Construction and transport method of large structures
JPH09272690A (en) Installation method and temporary bearer for installation of crane and the like
JP2004238135A (en) Container terminal
JPH02225203A (en) Method for transporting heavy article
JPS61135891A (en) Ship for transporting structure on sea
JP3616072B2 (en) Structure assembly apparatus and manufacturing method